Anda di halaman 1dari 199

BACK UP DATA PERHITUNGAN KANTOR LANTAI 2 ( PERMANEN )

I PEKERJAAN PERSIAPAN

1 Pembersihan Lokasi

Panjang = 10 m'
Lebar = 12 m'
Rumus =
= 288 m2

2 Pengukuran dan Pemasangan Bouwplank

Panjang = 10 m'
Lebar = 12 m'
Rumus =
= 195 m2

II PEKERJAAN TANAH DAN PASIR

1 Galian Tanah Pondasi


a. Galian Tanah Pondasi Menerus
Lebar pondasi bawah = 0.9
Tinggi galian tanah = 0.8
Panjang pondasi = 77.5
Rumus = LB x TP x P.P.keliling
Volume = 55.80 m3

b. Galian Tanah Pondasi Poerplat


Lebar pondasi bawah = 1.4
Tinggi galian pondasi poerplat = 1.52
Banyaknya pondasi poerplat yang digali = 20
Rumus = LB x TP xJumlah Pondasi
= 42.56
Volume total galian pondasi = a+b
= 98.36 m3

2 Urugan Tanah Kembali


Volume galian pondasi x 1/3 = 32.79

3 Urugan Tanah Peninggian Lantai


Luas bangunan lantai 1 = 111
Luas Teras = 6.39
Peninggian Lantai 0.49
Rumus = = ( Luas Bangunan Lt 1 + Luas teras) x Peninggian Lantai
Volume = 57.52

4 Urugan Pasir Bawah Pondasi


Panjang Urugan Pasir dibawah Pondasi = 77.5
Tebal Urugan Pasir = 0.07
Lebar Urugan Pasir Bawah Pondasi = 0.9
Rumus = Panjang U P x Tebal U P x Lebar U
Volume = 4.88

5 Urugan Pasir Bawah Lantai


Luas bangunan lantai 1 (3,5 x 9) + (3 x 7) + (9 x 6,5) = 111
Luas teras 3 x 2.13 = 6.39
Tebal Urugan Pasir = 0.07
Rumus = ( Luas Bangunan Lt 1 + Luas teras) x Tebal U Pasir = 8.22

III PEKERJAAN PONDASI BETON DAN PASANGAN

1 Lantai Kerja Tebal 7 cm


Panjang Lantai Kerja = 1.4
Lebar lantai Kerja = 1.4
Tebal Lantai Kerja = 0.07
Banyaknya Lantai Kerja = 20
Volume = 2.74

2 Pondasi Poer B. Bertulang


Tinggi P.Poerplat = 1.2
Panjang P.Poerplat = 0.35
Lebar P.Poerplat = 0.35
Banyaknya P.Poerplat = 20
Panjang Plat P.Poerplat = 1.2
Lebar Plat bawah P.Poerplat = 1.2
Tebal P.Poerplat = 0.45
Rumus = (( Tinggi PP x Panjang PP x Lebar PP) + ( P PP x L PP x T PP )) x Banyak PP
Volume = 15.9

3 Pas. Pondasi Menerus 1 Pc : 3 Ps


Panjang Pondasi Keliling = 77.5
Lebar atas Pondasi = 0.3
Lebar Bawah Pondasi = 0.8
Tinggi Pondasi = 0.9
Rumus = P.pondasi x L.atas pondasi x L.bawah pondasi x T.pondasi
Volume = 16.74

4 Sloof Beton Bertulang 25 x 40 cm


Tinggi Sloof = 0.4
Lebar Sloof = 0.25
Panjang Sloof Keliling = 77.5
Rumus =
Volume = 7.75

IV PEKERJAAN BESI DAN ALUMUNIUM

1 1 KG Pasangan Besi Profil


A WF 300.300.10.15 (Kolom)
Jumlah Kolom Lt.1 = 20
Tinggi Kolom Lt.1 = 4
Berat Besi Per 1 Kg = 94.05
Rumus = (Jumlah Kolom x Tinggi Kolom) x Berat Besi Per 1 Kg
Volume = 7524

B WF 300.300.10.15 (Kolom)
Jumlah Kolom Lt.2 = 20
Tinggi Kolom Lt.2 = 3.5
Berat Besi Per 1 Kg = 94.05
Rumus = (Jumlah Kolom x Tinggi Kolom) x Berat Besi Per 1 Kg
Volume = 6583.5
Total A + B = 14107.5

2 1 KG Pasangan Besi Profil


WF 400.200.8.13 (Balok Utama)
Panjang Balok Keliling = 91.5
Berat Besi Per 1 Kg = 66
Rumus = Panjang Balok Keliling x Berat Besi Per 1 Kg
Volume = 6039

3 Plat Bondek Tebal 0,75 mm


Berat Tebal Plat Bondek Per 1 m2 = 6.95
Luasan Plat Bondek = 91.5
Luasan Total = Berat x Luasan
= 635.93
4 WF 400.200.8.13 (Ringbalk)
Panjang Balok Keliling = 43
Berat Besi Per 1 Kg = 66
Rumus = Panjang Balok Keliling x Berat Besi Per 1 Kg
Volume = 2838
5 1 KG Pasangan Kuda-Kuda Baja IWF
a WF 250.125.6.9 (Kontruksi Kuda-Kuda)
Kuda-kuda type 1
Kemiringan Kuda - kuda = 6.24 x 2= 12.48
Jumlah kuda - kuda = 3
Berat Per 1 Kg = 37.44
= 1401.75
b WF 250.125.6.9 (Kontruksi Kuda-Kuda)
Kuda - kuda type 2
Kemiringan Kuda - kuda = 4.62
Jumlah kuda - kuda = 3
Berat Per 1 Kg = 13.86
= 192.0996
Berat Total Kuda - kuda (a+b) = 1593.85

6 1 KG Gording Baja
CNP 100.50.5.7,5
Berat Gording Per KG = 9.36
Gording Type A
Panjang gording = 6
Jumlah gording 1 sisi = 7
Total Panjang Gording 2 sisi = 84

Gording Type B
Panjang gording = 10.51
Jumlah gording 1 sisi = 7
Total Panjang Gording = 73.57

Rumus Berat Total Gording = (Gording Type A + Gording Type B) x Berat Gording Per KG
= 1474.86

7 100 KG Perakitan Besi Baja


A Berat Total Kolom Baja = 14107.5
B Berat Total Balok Lantai 1 = 6039
C Berat Total Balok Lantai 2 = 2838
D Berat Total Plat Bondek = 635.93
E Berat Total Kuda-Kuda Baja = 1593.85
F Berat Total Gording Baja = 1474.86
Berat Total = 26689.1334
Rumus = Berat Total : 100
= 266.89
V PEKERJAAN COR
1 1 M3 Cor Kolom
Banyak Kolom Lantai 1 = 20
Panjang Kolom = 0.35
Lebar Kolom = 0.35
Tinggi Kolom = 7.5
Rumus = (( Panjang Kolom x Lebar Kolom ) x tinggi x banyaknya kolom ) x 2 sisi
= 36.75

2 Kolom Praktis 15 x 15 cm, Beton Bertulang


A Kolom Lantai 1
Panjang Kolom = 0.15
Lebar Kolom = 0.15
Tinggi Kolom Lt.1 = 4
Banyaknya Kolom Lt.1 = 8
Rumus = Panjang Kolom x Lebar Kolom x ( Tinggi Kolom x Banyak Kolom )
= 0.72

B Kolom Lantai 2
Panjang Kolom = 0.15
Lebar Kolom = 0.15
Tinggi Kolom Lt.1 = 3.5
Banyaknya Kolom Lt.1 = 5
Rumus = Panjang Kolom x Lebar Kolom x ( Tinggi Kolom x Banyak Kolom )
= 0.39
Volume Total ( A + B ) = 1.11

3 Cor Plat Lantai Tebal 10 cm


Luas bangunan Lt. 2 = 75
Tebal Cor Plat Lantai = 0.1
Banyaknya Kolom = 20
Luas Kolom 35 x 35 = 0.12
Luas Total Kolom = 2.45
Rumus = (T.Coran Lantai x Luas Bangunan Lt.2) - Luasan Total Kolom
Volume = 5.05

4 Pas. Dinding 1/2 Bata


Panjang dinding Lt. 1
H = 18+12+ = 30
V =10.5 +10.5+7+2.5 = 30.5
Panjang Total Dinding Lt.1 = 60.5

Panjang dinding Lt. 2


H = 7.5+7.5+4+1.5 = 20.5
V = 25+3+2 = 30
Panjang Total Dinding Lt.2 = 50.5
Panjang Dinding Lt.1 + Panjang Dinding Lt.2 = 111
Lebar Batu Bata = 0.1
Tinggi Bangunan = 7.5
Luasan Pintu dan Jendela
Luasan Pintu (P1) = 2,1 x 1,2 x 2 = 5.04
Luasan Pintu (P2) = 2,1 x 0,8 x 5 = 8.4
Luasan Pintu (P3) = 2,1 x 0,7 x 3 = 4.41
Luasan Jendela (J1) = 1,68 x 1,1 x 5 = 9.24
Luasan Jendela (J2) = 1,2 x 1,6 x 2 = 3.84
Luasan Pintu Los = 1,35 x 2,5 x 1 = 3.38
Luasan Ventilasi (V1) = 0,5 x 0,6 x 3 = 0.9
Luasan Ventilasi (V2) = 0,3 x 0,45 x 31 = 4.19
Luasan Glassblock = 0,2 x 0,2 x 12 = 0.48
Volume Total = 39.87
(Panjang Dinding x Tinggi Dinding)-V.Total = 792.63
Luas Panjang Dinding x 0,1 = 79.263

5 Plesteran Tebal 15 mm 1 PC : 4 PS
Rumus = Pas. Dinding 1/2 Bata x 2
= 1585.26

6 Cor Lantai t = 8 cm
Luas Bangunan Lt.1 = 111
Tebal Cor Lantai = 0.08
Rumus = Luas Bangunan Lt.1 x Tebal Cor Lantai
Volume = 8.88

7 Cor Tangga B. Bertulang


Volume Anak Tangga
Tinggi Anak Tangga = 0.26
Lebar Anak Tangga = 0.3
Lebar Tangga = 1.3
Rumus =
Volume = 0.051
Banyak Anak Tangga = 16
Volume x Banyak Anak Tangga = 0.81
Volume Plat Tangga
Tebal = 0.14
lebar tangga = 1.3
Panjang Total Tangga = 6.95
Rumus =
Volume = 1.265
V.anak tangga + V.plat tangga = 2.08
8 1 M3 Cor Atap Dak
Panjang Dak = 8
Lebar Dak = 5
Tebal Cor Dak = 0.2
Volume = 8
VI PEKERJAAN PASANGAN ATAP
1 1 M2 Penutup Atap
Type A
Panjang atap = 6
Lebar atap = 6
kemiringan kuda - kuda = 6.24
Rumus =
Luasan atap Type A = 74.88

Type B
Panjang atap = 10.5
Lebar atap = 4.43
kemiringan kuda - kuda = 4.62
Rumus =
Luasan atap Type B = 68.98

Luasan Total Type A + Type B = 143.86

2 1 M' Nok Stuk Plat BJLS 0.20 mm


Panjang Seng Plat = 16.5
Lebar Seng Plat = 0.4
Rumus = P. Seng Plat x L. Seng Plat = 6.6

3 Pas. Rangka Plafond Kayu 5/5 cm


Hitung Luas m2 Rangka Plafond
Luas Bangunan Lt.1 = 111
Luas Bangunan Lt.2 = 75
Luas B. Lt 1 + B. Lt 2 = 186

4 Pas. Plafond Tripleks t : 3 mm


Luas B. Lt 1 + B. Lt 2 = 186

VII PEKERJAAN SANITASI DAN AIR

1 Bak Air = 3
2 Pas. Closet Jongkok Porselin = 3
3 Septictank uk. Pas. 1/2 Bata = 1
4 Pipa PVC Tipe AW Dia. 3/4" = 18
5 Pipa PVC Tipe AW Dia. 4" = 18
6 Kran Air Dia. 3/4" atau 1/2" = 4
7 Mesin Pompa = 1

VIII PEKERJAAN INSTALASI LISTRIK

1 Lampu tanam LED TS = 4


2 Lampu 14 watt = 13
3 Saklar Ganda = 4
4 Saklar Tunggal = 5
5 Stop Kontak = 8
6 Sekring Case = 1

IX PEKERJAAN LANTAI

1 Pas. Lantai Keramik 60 x 60 cm

Luas Bangunan Lt.1 = 111


Luas Bangunan Lt.2 = 75
Luas Bangunan Total = 186
Km/wc 1,5 x 2 = 3
Banyak Km/Wc = 3
V.Total Km/Wc = 9
Luas Tangga 2,6 x 2.4 = 6.24
Rumus =
Luasan Total Pas. Keramik = 188.76
2 Pas. Lantai Keramik 30 x 30 cm

Luas Teras = 6.6


Luas Balkon = 5.25
Luas Bangunan Total = 11.85

3 Pas. Lantai Keramik 25 x 25 cm

A Pasangan Keramik Tangga


Tangga Ruas 1
Luas Tangga (P x L) = 4.16
Tinggi Anak Tangga = 0.26
Banyak Anak Tangga = 8
Rumus = L.tangga x B.anak tangga x T.anak tangga
Luas = 8.65

Tangga Ruas 2
Luas Tangga (P x L) = 3.77
Tinggi Anak Tangga = 0.26
Banyak Anak Tangga = 8
Rumus = L.tangga x B.anak tangga x T.anak tangga
Luas = 7.84

Panjang Bordrest = 2.85


Lebar Bordrest = 0.85
Luas Bordrest = 2.423

Luasan Total = 18.92

B Pasangan Keramik KM/WC

Luas Km/Wc (1,5 x 2) = 3


Banyak Km/Wc = 3
Luas Total = 9

4 Pas. Keramik Dinding 20 x 25 cm t = 1,5 m

Luas Total Pas. Keramik Km/Wc = 15.18


Banyaknya Km/Wc = 3
Tinggi Dinding = 1.5
Rumus =Luas Total x Tinggi dinding
= 68.31

X PEKERJAAN PASANGAN KUSEN

1 Pas. Pintu Double 1,2 x 2,10 (P1) = 2


2 Pas. Pintu Panel Kayu 80 x 210 (P2) = 5
3 Pas. Pintu 70 x 210 (P3) = 3
4 Pas. Jendela Ungkit 168 x 110 (J1) = 5
5 Pas. Jendela Ungkkit 120 x 160 (J2) = 2
6 Pasangan Ventilasi 50 x 60 (V1) = 0.9 M2
7 Pasangan Ventilasi 30 x 45 (V2) = 4.185 M2

IX PEKERJAAN PENGECATAN

1 Cat Meny Kayu Dihitung Ikut Volume Meny Kayu


Ukuran Kayu
0,06 + 0,12 + 0,1
a Luasan Pintu (P1) = 2,1 x 1,2 x 2 = 5.04
b Luasan Pintu (P2) = 2,1 x 0,8 x 5 = 8.4
c Luasan Pintu (P3) = 2,1 x 0,7 x 3 = 4.41
d Luasan Jendela (J1) = 1,68 x 1,1 x 5 = 9.24
e Luasan Jendela (J2) = 1,2 x 1,6 x 2 = 3.84
f Luasan Ventilasi (V1) = 0,5 x 0,6 x 3 = 0.9
g Luasan Ventilasi (V2) = 0,3 x 0,45 x 31 = 4.19
Luas Total = 36.02
Rumus = Luas Total x Lebar kayu
= 10.08
2 Cat Kilap Kayu
Cat Kilap Kayu Dihitung Ikut Volume Meny Kayu = 10.08

3 Cat Tembok Untuk Dinding


Cat Tembok Untuk Dinding Ikut Volume Plesteran = 1585.26

4 Cat Plafond
Luas Bangunan Lt.1 = 111
Luas Bangunan Lt.2 = 75
Luasan Total = 186
DAFTAR HARGA SATUAN UPAH
LOKASI KEGIATAN : KOTA MERAUKE - DISTRIK MERAUKE

KEGIATAN : PENYUSUNAN NORMA, STANDAR, PEDOMAN DAN MANUAL (NSP


PEKERJAAN : PERHITUNGAN HARGA SATUAN BAHAN, UPAH, PEKERJAAN DAN
LOKASI : KOTA MERAUKE - DISTRIK MERAUKE
KABUPATEN / PROPINSI : MERAUKE - PAPUA
TAHUN ANGGARAN : 2019
SUMBER DANA : ---

PERIODE : JULI - DESEMBER 2019

Harga Dasar
No. Uraian Tenaga Kode Tenaga
(per hari)
1 2 3 4

1 Mandor Bangunan / Lapangan L-1 196,000.00


2 Kepala Tukang (Batu, Pasir, Kayu, dsb) L-2 186,000.00
3 Tukang (Batu, Pasir, Kayu, dsb) L-3 178,000.00
4 Pekerja L-4 140,000.00
5 Mandor Alat Berat (F. Equipment) (*) L-5 214,000.00
6 Operator Alat Berat (*) L-6 178,000.00
7 Pembantu Operator (*) L-7 140,000.00
8 Sopir / Driver (*) L-8 178,000.00
9 Pembantu Sopir / Driver (*) L-9 140,000.00
10 Mekanik (*) L - 10 178,000.00
11 Pembantu Mekanik (*) L - 11 140,000.00
12 Surveyor L - 12 186,000.00
13 Pembantu Surveyor L - 13 140,000.00

Jam kerja efektif per hari = 7.00 Jam

Jumlah hari per bulan = 25.00 Hari

Overhead + profit = 15.00%


UPAH
IK MERAUKE

OMAN DAN MANUAL (NSPM)


N, UPAH, PEKERJAAN DAN KEGIATAN

Harga Dasar
Tenaga Keterangan
(per jam)
5 8

28,000.00
26,572.00
25,429.00
20,000.00
30,572.00
25,429.00
20,000.00
25,429.00
20,000.00
25,429.00
20,000.00
26,572.00
20,000.00
DAFTAR HARGA SATUAN BAHA
LOKASI KEGIATAN : KOTA MERAUKE - DISTRIK
KEGIATAN : PENYUSUNAN NORMA, STANDAR, PEDOMAN DAN MANUAL (NSP
PEKERJAAN : PERHITUNGAN HARGA SATUAN BAHAN, UPAH, PEKERJAAN DAN
LOKASI : KOTA MERAUKE - DISTRIK MERAUKE
KABUPATEN / PROPINSI : MERAUKE - PAPUA
TAHUN ANGGARAN : 2019
SUMBER DANA : ---

PERIODE : JULI - DESEMBER 2019


Kode
No. Nama Bahan/Barang Barang Satuan

1 2 3 4

A. BAHAN BAKAR DAN PENCAMPUR


1 Bensin (Non Subsidi) MA.1 Liter
2 Solar (Non Subsidi) MA.2 Liter
3 Minyak Tanah (Non Subsidi) MA.3 Liter
4 Minyak Pelumas / Olie MA.4 Liter
5 Minyak Bekisting / Oli Bekas MA.5 Liter
6 Polimer MA.6 Liter
7 Aspal MA.7 Kg
8 Residu MA.8 Liter

B. BAHAN PASIR, BATU DAN SEMEN


1 Pasir Semen (Import) MB.1 M3
2 Pasir Pasang Lokal (kualitas baik) MB.2 M3
3 Tanah Timbun biasa MB.3 M3
4 Tanah Pilihan (Selmat) MB.4 M3
5 Batu Kerikil/Koral beton (Import) MB.5 M3
6 Batu Kali/Gunung (Import) MB.6 M3
7 Batu Bata Merah MB.7 Buah
8 Batu Cetak 10 x 20 x 30 Cm MB.8 Buah
9 Paving Blok MB.9 Buah
10 Semen Portland (PC) @ 50 Kg MB.10 Zak
11 Semen PC Warna MB.11 Zak
12 Tepung Gypsum MB.12 Zak

C. BAHAN KAYU, TRIPLEKS DLL


1 Balok Kayu Kelas III (Kayu Bus) MC.1 M3
2 Balok Kayu Kelas II (Kayu Rahay) MC.2 M3
3 Balok Kayu Kelas I (Kayu Besi) MC.3 M3
4 Balok Kayu Kelas IV (Kayu Campur) MC.4 M3
5 Papan Kayu Kelas III (Kayu Bus) t : 2-5 cm MC.5 M3
6 Papan Kayu Kelas II (Kayu Rahay) t : 2 cm MC.6 M3
7 Papan Kayu Kelas II (Kayu Rahay) t : 3 cm MC.7 M3
8 Papan Kayu Kelas I (Kayu Besi) t : 2-3 cm MC.8 M3
9 Papan Kayu Kelas IV (tebal = 2-5 cm) MC.9 M3
10 Kayu Lat/Reng/List, Kayu Kelas II MC.10 Batang
11 Tripleks (1,22 x 2,44) cm - tebal 3 mm MC.11 Lembar
12 Tripleks (1,22 x 2,44) cm - tebal 4 mm MC.12 Lembar
13 Tripleks (1,22 x 2,44) cm - tebal 6 mm MC.13 Lembar
14 Tripleks (1,22 x 2,44) cm - tebal 9 mm MC.14 Lembar
15 Tripleks (1,22 x 2,44) cm - tebal 12 mm MC.15 Lembar
16 Tripleks (1,22 x 2,44) cm - tebal 15 mm MC.16 Lembar
17 Tripleks (1,22 x 2,44) cm - tebal 18 mm MC.17 Lembar
18 Tripleks (1,22 x 2,44) cm - tebal 22 mm MC.18 Lembar
19 Teak - Wood (1.22 x 2.44 Cm) - 3 mm MC.19 Lembar
20 Teak - Wood (0.92 x 2.44 Cm) - 4 mm MC.20 Lembar
21 Plywood - Multiplex (9 mm) MC.21 Lembar
22 Melamin MC.22 Lembar
23 Formika Polos (122 x 244) Cm MC.23 Lembar
24 Pelat Asbes Tebal 6 mm MC.24 Lembar
25 Pelat Asbes Tebal 5 mm MC.25 Lembar
26 Pelat Asbes Tebal 4 mm MC.26 Lembar
27 Gypsum Board tebal 9 mm MC.27 Lembar
28 List profil Gypsum Lebar Sampai 5 cm MC.28 M'
29 Hard Board MC.29 Lembar
30 Tiang Kayu Bulat (Dia 20 cm, L=4-6 m) MC.30 Batang
31 Tiang Kayu Bulat (Dia 25-30 cm, L=4-6 m) MC.31 Batang
32 Kayu dolken Ø 8-10, L=4 M MC.32 Batang
33 Patok kayu (Dia = 3 cm, L= 1 m) MC.33 Batang
34 Patok kayu (Dia = 5 cm, L= 5 m) MC.34 Batang
35 Kayu Bakar (Campuran) MC.35 M3

D. BAHAN BESI, PAKU DAN KAWAT


1 Besi Beton Dia.6 mm (SNI) MD.1 Kg
2 Besi Beton Dia.8 mm (SNI) MD.2 Kg
3 Besi Beton Dia.10 mm (SNI) MD.3 Kg
4 Besi Beton Dia.12 mm (SNI) MD.4 Kg
5 Besi Beton Dia.14 mm (SNI) MD.5 KG
6 Besi Beton Dia.16 mm (SNI) MD.6 KG
7 Besi Beton Dia.19 mm (SNI) MD.7 KG
8 Besi Beton Dia.22 mm (SNI) MD.8 KG
9 Kawat Beton MD.9 KG
10 Kawat beton / bindrat 4 mm MD.10 KG
11 Paku 1" (2,5 - 3 cm) MD.11 KG
12 Paku 2" (5 cm) MD.12 KG
13 Paku 3" (7 cm) MD.13 KG
14 Paku 4" (10 cm) MD.14 KG
15 Paku 5" (12 - 15 cm) MD.15 KG
16 Paku Campur MD.16 KG
17 Paku Seng MD.17 KG
18 Paku Ardex Ulir MD.18 KG
19 Paku Sirap MD.19 Buah
20 Paku Ondoline MD.20 KG
21 Paku Tembok / Kecil 2/3 MD.21 Buah
22 Paku/Skrup 5 cm MD.22 KG
23 Kawat Nyamuk (Plastik / Nylon) MD.23 M
24 Kawat Has / Bankhas dia 12 mm MD.24 M2
25 Kawat Harmonika Has 40x40 mm MD.25 M
26 Kawat burung MN.26 M²
27 Kawat Duri Baja 20 M MD.27 KG
28 Kawat Las 0.26 MD.28 Dos
29 Timah Solder MD.29 KG
30 Baut Jembatan Dia. <14 mm MD.30 KG
31 Baut Dia, 3/8" - 17.5 + Mur - Ring MD.31 Buah
32 Baut Dia, 3/8" - 12.0/15.0 + Mur - Ring MD.32 Buah
33 Baut Dia, 3/8" - 20.0 + Mur - Ring MD.33 Buah
34 Baut Dia, 3/8" - 35.0 + Mur - Ring MD.34 Buah
35 Besi angkur dia. 8 mm MN.35 Buah
36 Kasa (Ram Ayam) Dia, 10 mm MD.36 M
37 Besi Siku 30 . 30 . 3 - L = 6 Meter MD.37 Batang
38 Besi Siku 50 . 50 . 5 - L = 6 Meter MD.38 Batang
39 Besi Siku 50 . 50 . 6 - L = 6 Meter MD.39 Batang
40 Besi Siku 40 . 40 . 4 - L = 6 Meter MD.40 Batang
41 Besi Siku 40 . 40 . 5 - L = 6 Meter MD.41 Batang
42 Besi Siku 20 . 20 . 3 - L = 6 Meter MD.42 Batang
43 Besi Plat 1.0 mm - 120 x 240 Cm MD.43 Lembar
44 Besi Plat 1.2 mm - 120 x 240 Cm MD.44 Lembar
45 Besi Plat 2.0 mm - 120 x 240 Cm MD.45 Lembar
46 Besi Plat 3.0 mm - 120 x 240 Cm MD.46 Lembar
47 Besi Plat 12 mm -120 x 240 cm MD.47 Lembar
48 Besi Strip 20.2 MD.48 Batang
49 Besi Strip 30.3 MD.49 Batang
50 Besi Strip 40.4 MD.50 Batang
51 Besi Strip 50.5 MD.51 Batang
52 Waltermur Dia 16 mm MD.52 Buah
53 Gording lips chanel 150.65.20.2,3 ( 6 N ) MD.53 Batang
54 Baja profil IWF MD.54 KG
55 Besi gording canal MD.55 KG
56 Water mur MD.56 KG
57 Sealent MD.57 Tube

E. BAHAN PENUTUP ATAP


1 Seng Gelombang BJLS 0,30 ME.1 Lembar
2 Seng Gelombang BJLS 0,22 ME.2 Lembar
3 Seng Gelombang BJLS 0,20 ME.3 Lembar
4 Atap Seng Plastik Gelombang Kecil ME.4 Lembar
5 Atap Seng Gelombang Besar Fiber Glass ME.5 Lembar
6 Seng Plat BJLS 0.30 ME.6 Lembar
7 Seng Plat BJLS 0.20 ME.7 Lembar
8 Genteng Metal - Multiroof ME.8 Lembar
9 Nok Genteng Metal - Multiroof ME.9 Bh
10 Atap Allumunium Gelombang ME.10 M2
11 Nok Atap Allumunium ME.11 M
12 Karet Talang ME.12 M1

F. BAHAN KERAMIK
1 Ubin Abu-Abu 20 x 20 Cm MF.1 Buah
2 Ubin Abu-Abu 30 x 30 Cm MF.2 Buah
3 Ubin Abu-Abu 40 x 40 Cm MF.3 Buah
4 Ubin Warna 20 x 20 Cm MF.4 Buah
5 Ubin Warna 30 x 30 Cm MF.5 Buah
6 Ubin Warna 40 x 40 Cm MF.6 Buah
7 Ubin Teraso Ukuran 30 x 30 cm MF.7 Buah
8 Ubin Teraso Ukuran 40 x 40 cm MF.8 Buah
9 Ubin Granito Ukuran 30 x 30 cm MF.9 Buah
10 Ubin Granito Ukuran 40 x 40 cm MF.10 Buah
11 Ubin Teralux Kerang Ukuran 30 x 30 cm MF.11 Buah
12 Ubin Teralux Kerang Ukuran 40 x 40 cm MF.12 Buah
13 Ubin Teralux Marmer Ukuran 30 x 30 cm MF.13 Buah
14 Ubin Teralux Marmer Ukuran 40 x 40 cm MF.14 Buah
15 Ubin Teralux Marmer Ukuran 60 x 60 cm MF.15 Buah
16 Keramik Artistik 10x20; 15x15 cm MF.16 Buah
17 Keramik Artistik 10x10 atau 5x20 cm MF.17 Buah
18 Keramik Lantai 20 x 20 cm MF.18 Buah
19 Keramik Lantai 20 x 30 cm MF.19 Buah
20 Keramik Lantai 30 x 30 cm MF.20 Buah
21 Keramik Lantai 30 x 30 berglasir MF.21 Buah
22 Keramik Lantai 30 x 30 berglasir (Mozaik) MF.22 Buah
23 Keramik Lantai 40 x 40 cm MF.23 Buah
24 Keramik Lantai 50 x 50 cm MF.24 Buah
25 Keramik Lantai 60 x 60 cm MF.25 Buah
26 Keramik Dinding 10 x 20 cm MF.26 Buah
27 Keramik Dinding 20x20 atau 20x25 cm MF.27 Buah
28 Ubin Dinding Porselin 11 x 11 MF.28 Buah
29 Ubin Dinding Porselin 10 x 20 cm MF.29 Buah
30 Ubin Dinding Porselin 20 x 20 MF.30 Buah
31 Plint Ubin Abu-Abu 15 x 20 cm MF.31 Buah
32 Plint Ubin Abu-Abu 10 x 30 cm MF.32 Buah
33 Plint Ubin Abu-Abu 10 x 40 cm MF.33 Buah
34 Plint Ubin Warna 10 x 20 cm MF.34 Buah
35 Plint Ubin Warna 10 x 30 cm MF.35 Buah
36 Plint Ubin Warna 10 x 40 cm MF.36 Buah
37 Plint Ubin Teraso 10 x 30 cm MF.37 Buah
38 Plint Ubin Teraso 10 x 40 cm MF.38 Buah
39 Plint Ubin Granito 10 x 40 cm MF.39 Buah
40 Plint Ubin Granito 10 x 30 cm MF.40 Buah
41 Plint Ubin Teralux Kerang 10 x 40 cm MF.41 Buah
42 Plint Ubin Teralux Kerang 10 x 30 cm MF.42 Buah
43 Plint Ubin Teralux Marmer 10 x 60 cm MF.43 Buah
44 Plint Ubin Teralux Marmer 10 x 40 cm MF.44 Buah
45 Plint Ubin Teralux Marmer 10 x 30 cm MF.45 Buah
46 Plint Keramik Artistik 10 x 20 cm MF.46 Buah
47 Plint Keramik Artistik 10 x 10 cm MF.47 Buah
48 Plint Keramik Artistik 5 x 20 cm MF.48 Buah
49 Plint Keramik Artistik 10 x 30 cm MF.49 Buah
50 Marmer Ukuran 100 x 100 cm MF.50 Buah
51 Wall paper (Lebar 50 cm) MF.51 M2
52 Batu Paras MF.52 Buah
53 Batu Tempel Hitam MF.53 Buah

G. BAHAN KACA
1 Kaca Polos 3 mm MG.1 M2
2 Kaca Polos 5 mm MG.2 M2
3 Kaca Buram 3 mm MG.3 M2
4 Kaca Buram 4 mm MG.4 M2
5 Kaca Buram 5 mm MG.5 M2
6 Kaca Naco / Louver - 7 Clips (polos) MG.6 Buah
7 Kaca Naco / Louver - 8 Clips (polos) MG.7 Buah
8 Kaca Naco / Louver - 9 Clips (polos) MG.8 Buah
9 Kaca Naco / Louver - 10 Clips (polos) MG.9 Buah
10 Kaca Rayban 25 % - tebal 5 mm MG.10 M2
11 Kaca Acrylic (Kaca Plastik) - 5 mm MG.11 Lembar

H. BAHAN/ALAT PENGGANTUNG
1 Kunci Tanam (Setara Cap Kuda Terbang) MH.1 Set
2 Kunci Tanam - 2 Slaagh MH.2 Set
3 Kunci Tanam - 1 Slaagh MH.3 Set
4 Kunci Tanam (Setara Cap Anchor / Yale) MH.4 Set
5 Kunci Gembok 1" MH.5 Set
6 Engsel 4" (Untuk Pintu) MH.6 Pasang
7 Engsel 3" (Untuk Jendela) MH.7 Pasang
8 Engsel Kupu-Kupu T MH.8 Pasang
9 Engsel Nylon Kuningan 4" MH.9 Pasang
10 Engsel Biasa 3" (Untuk Jendela) MH.10 Pasang
11 Hak Angin / Kait Angin MH.11 Buah
12 Espagnolet MH.12 Set
13 Grendel Tanam (Pintu) MH.13 Buah
14 Grendel Besar / Kecil MH.14 Buah
15 Tarikan Pintu MH.15 Buah
16 Tarikan Jendela MH.16 Buah

I. BAHAN CAT
1 Amplas Kertas (Amplas Kayu) MI.1 Lembar
2 Amplas Besi MI.2 Lembar
3 Dempul Kayu MI.3 Kg
4 Cat Meny Kayu MI.4 Kg
5 Cat Meny Besi MI.5 Kg
6 Cat Kayu MI.6 Kg
7 Cat Besi MI.7 Kg
8 Cat Kilat LN MI.8 Kg
9 Minyak Cat / Thinner MI.9 Kg
10 Cat Tembok (Setara Dulux Weathershield) MI.10 Kg
11 Plamur Tembok MI.11 Zak
12 Cat Tembok Biasa (1 Klg @ 5 Kg) MI.12 Kaleng
13 Cat Besi Crom MI.13 Kg
14 Cat Besi (Setara Nippon Paint) MI.14 Kg
15 Politur Kaleng (Setara Apache) MI.15 Kg
16 Floor Hardener MI.16 KG

J. BAHAN LISTRIK DAN ELEKTRONIKA


1 Kabel Listrik NYM/NYA 3x2.5 mm MJ.1 Roll
2 Kabel Listrik NYM/NYA 2x1.5 mm MJ.2 Roll
3 Pipa Listrik dia, 5/8 MJ.3 Batang
4 Saklar Double - Tempel MJ.4 Buah
5 Saklar Tunggal / Engkel - Tempel MJ.5 Buah
6 Stop Kontak 500 Watt - Tempel MJ.6 Buah
7 Stop Kontak 1000 Watt - Tempel MJ.7 Buah
8 Home Saklar 1 Fase Komplit MJ.8 Buah
9 Lampu TL 1 x 40 Watt Komplit MJ.9 Buah
10 Lampu TL 1 x 20 Watt Komplit MJ.10 Buah
11 Lampu Pijar 40 Watt Komplit MJ.11 Buah
12 Lampu Pijar 60 Watt Komplit MJ.12 Buah
13 Lampu Pijar 100 Watt Komplit MJ.13 Buah
14 Vitting Lampu MJ.14 Buah
15 Lampu XL 40 Watt MJ.15 Set
16 Lampu XL 20 Watt MJ.16 Set
17 Lampu SL 23 Watt MJ.17 Set
18 Lampu SL 14 Watt MJ.18 Set
19 Sekring Kas 1 Group (Biasa) MJ.19 Buah
20 Klem Kabel MJ.20 Dus
21 Isolasi Listrik MJ.21 Buah
22 Sekrup MJ.22 Dus
23 Panil Distribusi MJ.23 Buah

K. BAHAN PIPA DAN SANITAIR


1 Pipa GIP (Leideng) Dia. 1/2" - 6 Meter MK.1 Batang
2 Pipa GIP (Leideng) Dia. 3/4" - 6 Meter MK.2 Batang
3 Pipa GIP (Leideng) Dia. 1" - 6 Meter MK.3 Batang
4 Pipa GIP (Leideng) Dia. 1.25" - 6 Meter MK.4 Batang
5 Pipa GIP (Leideng) Dia. 1.5" - 6 Meter MK.5 Batang
6 Pipa GIP (Leideng) Dia. 2" - 6 Meter MK.6 Batang
7 Pipa GIP (Leideng) Dia. 3" - 6 Meter MK.7 Batang
8 Pipa GIP (Leideng) Dia. 4" - 6 Meter MK.8 Batang
9 Pipa PVC Dia. 5" - 4 Meter (AW) MK.9 Batang
10 Pipa PVC Dia. 4" - 4 Meter (AW) MK.10 Batang
11 Pipa PVC Dia. 4" - 4 Meter (D) MK.11 Batang
12 Pipa PVC Dia. 3" - 4 Meter (D) MK.12 Batang
13 Pipa PVC Dia. 2" - 4 Meter (D) MK.13 Batang
14 Pipa PVC Dia. 1" - 4 Meter (D) MK.14 Batang
15 Pipa PVC Dia. 1/2" - 4 M MK.15 Batang
16 Pipa PVC Dia. 3/4" - 4 M MK.16 Batang
17 Pipa PVC Dia. 2,5" - 4 M MK.17 Batang
18 Talang PVC Oval 6" - 4 Meter MK.18 Batang
19 Talang PVC Oval 8" - 4 Meter MK.19 Batang
20 Talang PVC Kotak 4" - 4 Meter MK.20 Batang
21 Talang PVC Kotak 8" - 4 Meter MK.21 Batang
22 Closed Duduk Porselin Komplit MK.22 Buah
23 Closet duduk (siram) MK.23 Buah
24 Closed Jongkok Porselin (Standar) MK.24 Buah
25 Closed Jongkok Fiber Glass / Plastik MK.25 Buah
26 Urinoir MK.26 Buah
27 Wastafel Porselin MK.27 Buah
28 Bak Air / Fiber Glass 1 M3 MK.28 Buah
29 Bak Air / Fiber Glass 1/2 M3 MK.29 Buah
30 Bak Air / Fiber Glass 1/4 M3 MK.30 Buah
31 Tangki Air / Fiber Glass 1 M3 MK.31 Buah
32 Kran Air 3/4" MK.32 Buah
33 Kran Air 1/2" MK.33 Buah
34 Kran Air 1" MK.34 Buah
35 Stop Kran 1/2" MK.35 Buah
36 Doble Neple GIP 1/2" MK.36 Buah
37 Soccet 1/2" MK.37 Buah
38 Elbow GIP 90º x 1/2" ( PE ) MK.38 Buah
39 Tee 1/2" x 1/2" MK.39 Buah
40 Hand Kran 1/2" Besi MK.40 Buah
41 Dop GIP 1/2" MK.41 Buah
42 Water Meter 1/2" MK.42 Buah
43 Clamp Sadle 2" mm x 1/2" ( PE ) MK.43 Buah
44 Pengaman Box Meter MK.44 Buah
45 Pipa HDPE Ø 150 mm MK.45 M
46 Pipa HDPE Ø 100 mm MK.46 M
47 Pipa HDPE Ø 75 mm MK.47 M
48 Pipa HDPE Ø 50-63 mm MK.48 M
49 Tee All Flange Ø 50 x 50 mm (HDPE) MK.49 Buah
50 Tee All Flange Ø 75 x 50 mm (HDPE) MK.50 Buah
51 Tee All Flange Ø 75 x 75 mm (HDPE) MK.51 Buah
52 Tee All Flange Ø 100 x 75 mm (HDPE) MK.52 Buah
53 Bend 90 All Flange Ø 50 mm (HDPE) MK.53 Buah
54 Bend 90 All Flange Ø 75 mm (HDPE) MK.54 Buah
55 Bend 90 All Flange Ø 100 mm (HDPE) MK.55 Buah
56 Gate Valve Flange Ø 50 mm MK.56 Buah
57 Gate Valve Flange Ø 75 mm MK.57 Buah
58 Gate Valve Flange Ø 1/2" MK.58 Buah
59 Stub Flange Ø 50 mm MK.59 Buah
60 Stub Flange Ø 75 mm MK.60 Buah
61 Stub Flange Ø 100 mm MK.61 Buah
62 End Cap (Dop) Ø 50 mm (HDPE) MK.62 Buah
63 End Cap (Dop) Ø 75 mm (HDPE) MK.63 Buah
64 Stop Cock (PIT Kran) 1/2" MK.64 Buah
65 Reducer Ø 75 x 75 mm (HDPE) MK.65 Buah
66 Reducer Ø 75 x 50 mm (HDPE) MK.66 Buah
67 Quil Elbow HDPE (adaptor) Ø15 (1/2") MK.67 Buah
68 Pipa Input HDPE Ø 1/2" MK.68 Buah

M. BETON PRACETAK
1 Dwiker Sumur/Gorong2 Ø 1 m, H 60 cm MM.1 Buah
2 Dwiker Sumur/Gorong2 Ø 0,8 m, H 60 cm MM.2 Buah
3 Dwiker/Gorong2 Ø 0,6 m, H 80 cm MM.3 Buah
4 Dwiker/Gorong2 Ø 0,45 m, H 80 cm MM.4 Buah

N. BAHAN BANGUNAN LAIN


1 Lem Aica Aibon MN.1 KG
2 Lem Fox MN.2 KG
3 Lem Vinyl MN.3 KG
4 Ijuk MN.4 KG
5 Pipa Plastik dia, 3" (AW) MN.5 Batang
7 Mata bor MN.7 Buah
8 Mata gurinda MN.8 Buah
9 Gas elpiji MN.9 KG
10 Oksigen (@50 kg/btl) MN.10 KG
11 Kuas Cat Minyak MN.11 Buah
12 Kuas Roll (Cat Tembok) MN.12 Buah
13 Air Bersih MN.13 Liter

NB - Pemilihan Harga Satuan disesuaikan dengan Format Standar Analisa Harga Satuan Pekerjaan Ma
- Harga Sewaktu-waktu dapat berubah, penentuan nilai barang/material dalam penyusunan HPS di
ARGA SATUAN BAHAN
KOTA MERAUKE - DISTRIK MERAUKE
R, PEDOMAN DAN MANUAL (NSPM)
BAHAN, UPAH, PEKERJAAN DAN KEGIATAN

Harga Dasar Tingkat Sumber Ongkos Harga Dasar +


(Distributor) Inflasi Bahan Angkut Inflasi +
( Rp. ) ( %. ) (Rp) Ongkos angkut
5 6 7 8

11,367.00 0% Merauke 401.00 11,768.00


13,723.00 0% Merauke 401.00 14,124.00
11,802.00 0% Merauke 401.00 12,203.00
35,000.00 0% Merauke 407.00 35,407.00
500.00 0% Merauke 407.00 907.00
18,000.00 0% Merauke 568.00 18,568.00
15,483.00 0% Merauke 426.00 15,909.00
24,900.00 0% Merauke 852.00 25,752.00

1,125,000.00 0% Merauke 33,994.00 1,158,994.00


500,000.00 0%
Pantai Urumb 247,550.00 747,550.00
150,000.00 0% Quarry 110,010.00 260,010.00
150,000.00 0% Quarry 110,010.00 260,010.00
1,125,000.00 0% Merauke 37,930.00 1,162,930.00
1,218,000.00 0% Merauke 37,930.00 1,255,930.00
1,000.00 0% Buper 340.00 1,340.00
2,000.00 0% Buper 720.00 2,720.00
6,500.00 0% Merauke 230.00 6,730.00
90,000.00 0% Merauke 8,030.00 98,030.00
127,500.00 0% Merauke 8,030.00 135,530.00
99,000.00 0% Merauke 11,080.00 110,080.00

2,750,000.00 0% Merauke 153,800.00 2,903,800.00


4,000,000.00 0% Merauke 177,460.00 4,177,460.00
6,000,000.00 0% Merauke 201,120.00 6,201,120.00
2,500,000.00 0% Merauke 118,300.00 2,618,300.00
2,750,000.00 0% Merauke 153,800.00 2,903,800.00
4,000,000.00 0% Merauke 177,460.00 4,177,460.00
4,000,000.00 0% Merauke 177,460.00 4,177,460.00
6,000,000.00 0% Merauke 201,120.00 6,201,120.00
2,500,000.00 0% Merauke 118,300.00 2,618,300.00
25,000.00 0% Merauke 360.00 25,360.00
64,375.00 0% Merauke 1,520.00 65,895.00
79,500.00 0% Merauke 2,030.00 81,530.00
102,000.00 0% Merauke 3,040.00 105,040.00
145,000.00 0% Merauke 4,570.00 149,570.00
201,500.00 0% Merauke 6,090.00 207,590.00
259,625.00 0% Merauke 7,620.00 267,245.00
292,750.00 0% Merauke 9,650.00 302,400.00
300,000.00 0% Merauke 11,170.00 311,170.00
127,500.00 0% Merauke 1,520.00 129,020.00
120,000.00 0% Merauke 2,030.00 122,030.00
450,000.00 0% Merauke 3,750.00 453,750.00
126,500.00 0% Merauke 2,500.00 129,000.00
300,000.00 0% Merauke 3,040.00 303,040.00
127,000.00 0% Merauke 3,170.00 130,170.00
65,000.00 0% Merauke 2,640.00 67,640.00
61,000.00 0% Merauke 2,110.00 63,110.00
90,625.00 0% Merauke 5,110.00 95,735.00
35,000.00 0% Merauke 322.50 35,322.50
75,500.00 0% Merauke 9,100.00 84,600.00
125,000.00 0% Sumber 24,090.00 149,090.00
150,000.00 0% Sumber 91,100.00 241,100.00
12,500.00 0% Sumber 4,490.00 16,990.00
3,000.00 0% Sumber - 3,000.00
5,000.00 0% Sumber - 5,000.00
400,000.00 0% Sumber - 400,000.00

14,264.00 0% Merauke 260.00 14,524.00


13,697.00 0% Merauke 290.00 13,987.00
13,635.00 0% Merauke 310.00 13,945.00
13,698.00 0% Merauke 430.00 14,128.00
13,636.00 0% Merauke 370.00 14,006.00
13,660.00 0% Merauke 560.00 14,220.00
14,312.00 0% Merauke 450.00 14,762.00
11,884.00 0% Merauke 410.00 12,294.00
25,666.00 0% Merauke 310.00 25,976.00
27,500.00 0% Merauke 310.00 27,810.00
24,833.00 0% Merauke 300.00 25,133.00
20,750.00 0% Merauke 300.00 21,050.00
20,750.00 0% Merauke 300.00 21,050.00
20,750.00 0% Merauke 300.00 21,050.00
21,000.00 0% Merauke 300.00 21,300.00
20,750.00 0% Merauke 300.00 21,050.00
41,750.00 0% Merauke 340.00 42,090.00
85,000.00 0% Merauke 310.00 85,310.00
15,000.00 0% Merauke 310.00 15,310.00
20,000.00 0% Merauke 310.00 20,310.00
268.00 0% Merauke 10.33 278.33
705.00 0% Merauke 310.00 1,015.00
25,500.00 0% Merauke 173.00 25,673.00
29,500.00 0% Merauke 192.00 29,692.00
80,500.00 0% Merauke 974.00 81,474.00
25,000.00 0% Merauke 974.00 25,974.00
20,500.00 0% Merauke 280.00 20,780.00
152,375.00 0% Merauke 310.00 152,685.00
35,333.00 0% Merauke 100.00 35,433.00
15,000.00 0% Merauke 310.00 15,310.00
4,200.00 0% Merauke 310.00 4,510.00
3,250.00 0% Merauke 310.00 3,560.00
5,550.00 0% Merauke 310.00 5,860.00
6,000.00 0% Merauke 310.00 6,310.00
10,000.00 0% Merauke 310.00 10,310.00
25,250.00 0% Merauke 415.00 25,665.00
78,500.00 0% Merauke 2,870.00 81,370.00
247,000.00 0% Merauke 8,480.00 255,480.00
240,000.00 0% Merauke 8,860.00 248,860.00
170,000.00 0% Merauke 4,500.00 174,500.00
145,000.00 0% Merauke 8,100.00 153,100.00
110,000.00 0% Merauke 1,760.00 111,760.00
406,000.00 0% Merauke 8,400.00 414,400.00
492,000.00 0% Merauke 8,760.00 500,760.00
781,000.00 0% Merauke 13,290.00 794,290.00
1,157,000.00 0% Merauke 15,460.00 1,172,460.00
1,450,000.00 0% Merauke 48,890.00 1,498,890.00
39,250.00 0% Merauke 470.00 39,720.00
57,000.00 0% Merauke 1,100.00 58,100.00
76,250.00 0% Merauke 2,150.00 78,400.00
92,000.00 0% Merauke 2,960.00 94,960.00
20,000.00 0% Merauke 4,320.00 24,320.00
725,000.00 0% Merauke 4,320.00 729,320.00
21,000.00 0% Merauke 260.00 21,260.00
22,549.00 0% Merauke 260.00 22,809.00
15,000.00 0% Merauke 260.00 15,260.00
31,333.00 0% Merauke 260.00 31,593.00

78,750.00 0% Merauke 790.00 79,540.00


65,000.00 0% Merauke 720.00 65,720.00
54,250.00 0% Merauke 630.00 54,880.00
68,250.00 0% Merauke 340.00 68,590.00
83,000.00 0% Merauke 1,450.00 84,450.00
78,500.00 0% Merauke 790.00 79,290.00
55,666.00 0% Merauke 630.00 56,296.00
74,500.00 0% Merauke 1,430.00 75,930.00
31,250.00 0% Merauke 1,430.00 32,680.00
65,000.00 0% Merauke 1,430.00 66,430.00
21,000.00 0% Merauke 1,430.00 22,430.00
10,500.00 0% Merauke 320.00 10,820.00

3,000.00 0% Merauke 140.00 3,140.00


6,818.00 0% Merauke 230.00 7,048.00
14,166.00 0% Merauke 400.00 14,566.00
2,780.00 0% Merauke 140.00 2,920.00
6,227.00 0% Merauke 230.00 6,457.00
10,833.00 0% Merauke 400.00 11,233.00
6,590.00 0% Merauke 230.00 6,820.00
14,083.00 0% Merauke 400.00 14,483.00
6,318.00 0% Merauke 230.00 6,548.00
12,166.00 0% Merauke 400.00 12,566.00
7,272.00 0% Merauke 230.00 7,502.00
14,250.00 0% Merauke 400.00 14,650.00
11,363.00 0% Merauke 230.00 11,593.00
22,083.00 0% Merauke 400.00 22,483.00
71,666.00 0% Merauke 1,560.00 73,226.00
1,250.00 0% Merauke 110.00 1,360.00
650.00 0% Merauke 90.00 740.00
2,953.00 0% Merauke 140.00 3,093.00
4,062.00 0% Merauke 180.00 4,242.00
6,250.00 0% Merauke 230.00 6,480.00
7,272.00 0% Merauke 230.00 7,502.00
7,272.00 0% Merauke 230.00 7,502.00
13,875.00 0% Merauke 400.00 14,275.00
24,041.00 0% Merauke 790.00 24,831.00
98,888.00 0% Merauke 1,560.00 100,448.00
1,400.00 0% Merauke 110.00 1,510.00
3,010.00 0% Merauke 140.00 3,150.00
670.00 0% Merauke 90.00 760.00
1,036.00 0% Merauke 110.00 1,146.00
2,900.00 0% Merauke 140.00 3,040.00
12,500.00 0% Merauke 180.00 12,680.00
10,000.00 0% Merauke 180.00 10,180.00
12,250.00 0% Merauke 180.00 12,430.00
4,500.00 0% Merauke 110.00 4,610.00
10,000.00 0% Merauke 180.00 10,180.00
12,000.00 0% Merauke 180.00 12,180.00
10,000.00 0% Merauke 180.00 10,180.00
12,500.00 0% Merauke 180.00 12,680.00
12,500.00 0% Merauke 180.00 12,680.00
8,000.00 0% Merauke 180.00 8,180.00
8,000.00 0% Merauke 180.00 8,180.00
8,000.00 0% Merauke 180.00 8,180.00
33,500.00 0% Merauke 190.00 33,690.00
10,000.00 0% Merauke 180.00 10,180.00
7,500.00 0% Merauke 180.00 7,680.00
5,000.00 0% Merauke 110.00 5,110.00
4,500.00 0% Merauke 90.00 4,590.00
4,000.00 0% Merauke 90.00 4,090.00
7,500.00 0% Merauke 180.00 7,680.00
350,000.00 0% Merauke 8,650.00 358,650.00
250,000.00 0% Merauke 366.00 250,366.00
22,727.00 0% Merauke 230.00 22,957.00
28,181.00 0% Merauke 230.00 28,411.00

115,182.00 0% Merauke 2,030.00 117,212.00


169,895.00 0% Merauke 2,840.00 172,735.00
107,698.00 0% Merauke 2,030.00 109,728.00
107,698.00 0% Merauke 2,430.00 110,128.00
107,698.00 0% Merauke 2,840.00 110,538.00
165,166.00 0% Merauke 3,080.00 168,246.00
195,666.00 0% Merauke 3,470.00 199,136.00
218,250.00 0% Merauke 3,860.00 222,110.00
245,000.00 0% Merauke 4,260.00 249,260.00
215,000.00 0% Merauke 2,840.00 217,840.00
1,400,000.00 0% Merauke 2,780.00 1,402,780.00

94,333.00 0% Merauke 350.00 94,683.00


123,500.00 0% Merauke 350.00 123,850.00
110,000.00 0% Merauke 350.00 110,350.00
117,000.00 0% Merauke 350.00 117,350.00
85,000.00 0% Merauke 170.00 85,170.00
22,833.00 0% Merauke 170.00 23,003.00
16,666.00 0% Merauke 170.00 16,836.00
30,000.00 0% Merauke 170.00 30,170.00
20,000.00 0% Merauke 170.00 20,170.00
17,000.00 0% Merauke 170.00 17,170.00
16,500.00 0% Merauke 170.00 16,670.00
65,000.00 0% Merauke 170.00 65,170.00
127,500.00 0% Merauke 170.00 127,670.00
34,666.00 0% Merauke 170.00 34,836.00
165,000.00 0% Merauke 170.00 165,170.00
14,000.00 0% Merauke 170.00 14,170.00

5,166.00 0% Merauke 18.00 5,184.00


4,666.00 0% Merauke 18.00 4,684.00
34,666.00 0% Merauke 330.00 34,996.00
36,166.00 0% Merauke 330.00 36,496.00
36,166.00 0% Merauke 330.00 36,496.00
63,750.00 0% Merauke 330.00 64,080.00
71,500.00 0% Merauke 330.00 71,830.00
62,000.00 0% Merauke 330.00 62,330.00
30,750.00 0% Merauke 330.00 31,080.00
26,250.00 0% Merauke 330.00 26,580.00
134,250.00 0% Merauke 9,000.00 143,250.00
105,000.00 0% Merauke 1,850.00 106,850.00
64,000.00 0% Merauke 330.00 64,330.00
84,250.00 0% Merauke 330.00 84,580.00
63,250.00 0% Merauke 330.00 63,580.00
19,000.00 0% Merauke 330.00 19,330.00

1,451,000.00 0% Merauke 24,990.00 1,475,990.00


835,000.00 0% Merauke 24,990.00 859,990.00
7,600.00 0% Merauke 120.00 7,720.00
21,750.00 0% Merauke 540.00 22,290.00
15,875.00 0% Merauke 540.00 16,415.00
15,250.00 0% Merauke 540.00 15,790.00
23,250.00 0% Merauke 540.00 23,790.00
553,333.00 0% Merauke 860.00 554,193.00
183,750.00 0% Merauke 100.00 183,850.00
129,750.00 0% Merauke 100.00 129,850.00
11,000.00 0% Merauke 100.00 11,100.00
11,125.00 0% Merauke 100.00 11,225.00
10,166.00 0% Merauke 100.00 10,266.00
12,500.00 0% Merauke 100.00 12,600.00
140,000.00 0% Merauke 100.00 140,100.00
41,250.00 0% Merauke 100.00 41,350.00
47,000.00 0% Merauke 100.00 47,100.00
39,500.00 0% Merauke 100.00 39,600.00
0.00 0% Merauke 320.00 320.00
33,625.00 0% Merauke 170.00 33,795.00
8,700.00 0% Merauke 170.00 8,870.00
15,500.00 0% Merauke 170.00 15,670.00
12,500,000.00 0% Merauke 860.00 12,500,860.00

116,500.00 0% Merauke 1,270.00 117,770.00


154,500.00 0% Merauke 1,740.00 156,240.00
195,666.00 0% Merauke 2,510.00 198,176.00
249,333.00 0% Merauke 3,920.00 253,253.00
281,000.00 0% Merauke 4,870.00 285,870.00
313,000.00 0% Merauke 6,860.00 319,860.00
598,333.00 0% Merauke 20,410.00 618,743.00
742,000.00 0% Merauke 23,790.00 765,790.00
550,000.00 0% Merauke 2,950.00 552,950.00
329,833.00 0% Merauke 1,860.00 331,693.00 82923.25
236,875.00 0% Merauke 1,860.00 238,735.00
147,375.00 0% Merauke 1,100.00 148,475.00
77,125.00 0% Merauke 640.00 77,765.00
43,625.00 0% Merauke 320.00 43,945.00
26,166.00 0% Merauke 150.00 26,316.00
34,625.00 0% Merauke 240.00 34,865.00 8716.25
106,666.00 0% Merauke 860.00 107,526.00
80,000.00 0% Merauke 1,610.00 81,610.00
99,666.00 0% Merauke 2,150.00 101,816.00
135,250.00 0% Merauke 2,550.00 137,800.00
395,000.00 0% Merauke 3,110.00 398,110.00
2,311,000.00 0% Merauke 4,690.00 2,315,690.00
580,000.00 0% Merauke 3,740.00 583,740.00
205,000.00 0% Merauke 3,790.00 208,790.00
87,000.00 0% Merauke 1,870.00 88,870.00
1,495,000.00 0% Merauke 3,030.00 1,498,030.00
517,500.00 0% Merauke 3,030.00 520,530.00
427,500.00 0% Merauke 3,790.00 431,290.00
340,000.00 0% Merauke 3,030.00 343,030.00
295,000.00 0% Merauke 2,520.00 297,520.00
1,970,000.00 0% Merauke 7,580.00 1,977,580.00
29,125.00 0% Merauke 170.00 29,295.00
22,875.00 0% Merauke 170.00 23,045.00
30,000.00 0% Merauke 170.00 30,170.00
15,500.00 0% Merauke 170.00 15,670.00
15,000.00 0% Merauke 170.00 15,170.00
2,000.00 0% Merauke 170.00 2,170.00
50,000.00 0% Merauke 170.00 50,170.00
2,250.00 0% Merauke 170.00 2,420.00
30,000.00 0% Merauke 170.00 30,170.00
6,500.00 0% Merauke 170.00 6,670.00
450,000.00 0% Merauke 1,260.00 451,260.00
80,000.00 0% Merauke 1,260.00 81,260.00
250,000.00 0% Merauke 1,260.00 251,260.00
398,000.00 0% Merauke 2,200.00 400,200.00
196,000.00 0% Merauke 840.00 196,840.00
107,000.00 0% Merauke 390.00 107,390.00
60,000.00 0% Merauke 150.00 60,150.00
450,000.00 0% Merauke 5,850.00 455,850.00
475,000.00 0% Merauke 5,950.00 480,950.00
500,000.00 0% Merauke 6,040.00 506,040.00
650,000.00 0% Merauke 6,140.00 656,140.00
210,000.00 0% Merauke 1,600.00 211,600.00
335,000.00 0% Merauke 5,270.00 340,270.00
50,000.00 0% Merauke 5,430.00 55,430.00
1,850,000.00 0% Merauke 13,730.00 1,863,730.00
2,350,000.00 0% Merauke 14,440.00 2,364,440.00
200,000.00 0% Merauke 180.00 200,180.00
200,000.00 0% Merauke 1,130.00 201,130.00
600,000.00 0% Merauke 2,200.00 602,200.00
840,000.00 0% Merauke 2,740.00 842,740.00
37,009.00 0% Merauke 280.00 37,289.00
86,873.00 0% Merauke 1,130.00 88,003.00
950,000.00 0% Merauke 410.00 950,410.00
525,000.00 0% Merauke 4,070.00 529,070.00
500,000.00 0% Merauke 4,020.00 504,020.00
48,000.00 0% Merauke 1,600.00 49,600.00
38,400.00 0% Merauke 1,600.00 40,000.00

430,000.00 0% Merauke 45,660.00 475,660.00


380,000.00 0% Merauke 38,080.00 418,080.00
340,000.00 0% Merauke 40,190.00 380,190.00
340,000.00 0% Merauke 30,600.00 370,600.00

49,500.00 0% Merauke 330.00 49,830.00


31,250.00 0% Merauke 330.00 31,580.00
20,000.00 0% Merauke 330.00 20,330.00
45,000.00 0% Merauke 410.00 45,410.00
151,000.00 0% Merauke 310.00 151,310.00
18,000.00 0% Merauke 60.00 18,060.00
23,750.00 0% Merauke 90.00 23,840.00
250,000.00 0% Merauke 560.00 250,560.00
350,000.00 0% Merauke 680.00 350,680.00
22,000.00 0% Merauke 90.00 22,090.00
33,500.00 0% Merauke 90.00 33,590.00
50.00 0% Merauke - 50

ar Analisa Harga Satuan Pekerjaan Masing-masing Bidang Pekerjaan Konstruksi


ng/material dalam penyusunan HPS disesuaikan dengan hasil survei dilapangan kembali.
7126.866

7127
A. PEKERJAAN PERSIAPAN

Pekerjaan : 1 M2 Pagar Sementara (Seng Gelombang 2 M)


Referensi : RSNI T-12-2002
Kode Analisa : PU-CK.A2
PERKIR
NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala Tukang Kayu OH
Mandor OH

B BAHAN
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 Batang
Semen Portland (PC) @ 50 Kg KG
Seng Gelombang BJLS 0,20 Lembar
Pasir Semen (import) M3
Kerikil/batu pecah (import) M3
Balok Kayu Bus M3
Paku Biasa Campur 2" - 5" KG
Meni Besi KG

C Jumlah Harga Tenaga Kerja dan Bahan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Membersihkan Lapangan dan Perataan


Referensi : RSNI T-12-2002
Kode Analisa : PU-CK.A8

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH

B Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


C Overhead + Profit
D Harga Satuan Pekerjaan(B+C)
E Jumlah harga dibulatkan

Pekerjaan : 1 M' Pengukuran dan Pasangan Bouwplank


Referensi : RSNI T-12-2002
Kode Analisa : PU-CK.A4

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala Tukang Kayu OH
Mandor OH

B BAHAN
Balok Kayu Bus M3
Kayu Papan Bus M3
Paku Biasa Campur 2" - 5" KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B)


D Overhead + Profit
E Harga Satuan Pekerjaan(D+E)
F Jumlah harga dibulatkan

B. PEKERJAAN TANAH DAN PASIR

Pekerjaan : 1 M3 Galian Tanah Biasa Sedalam 1 - 2 M


Referensi : SNI 2835:2008
Kode Analisa : PU-CK.B.3

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH

B Jumlah Harga Tenaga Kerja


C Overhead + Profit
D Harga Satuan Pekerjaan(D+E)
E Jumlah harga dibulatkan

Pekerjaan : 1 M3 Urug Kembali Tanah Biasa Sedalam 1 - 2 M


Referensi : SNI 2835:2008
Kode Analisa : PU-CK.B.4

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Dihitung 1/3 kali M3

D Jumlah Harga Tenaga Kerja

Pekerjaan : 1 M3 Memadatkan Tanah Per 20 cm


Referensi : SNI 2835:2008
Kode Analisa : PU-CK.B.13

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M3 Urugan Tanah Urug (material didatangkan)


Referensi : SNI 2835:2008
Kode Analisa : PU-CK.B.14
Untuk pemadatan per 20 cm

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH
B BAHAN
Tanah timbun biasa/urug M3

C Jumlah Harga Tenaga Kerja, dan Bahan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Urugan Pasir Bawah Pondasi


Referensi : SNI 2835:2008
Kode Analisa : : PU-CK.B.16

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH

B BAHAN
Pasir semen (lokal) M3

C Jumlah Harga Tenaga Kerja, dan Bahan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Urugan Pasir Bawah Lantai


Referensi : SNI 2835:2008
Kode Analisa : : PU-CK.B.16

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Mandor OH

B BAHAN
Pasir semen (lokal) M3
C Jumlah Harga Tenaga Kerja, dan Bahan
D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

C. PEKERJAAN PONDASI DAN PASANGAN

Pekerjaan : 1 M3 Pasangan Bata, Camp. 1PC : 3PS - Pasir Import (Manual)


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.C.2

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Batu bata Buah
Semen Portland (PC) @ 50 Kg Zak
Pasir semen (import) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87
Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.30

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3
Air Liter

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Pondasi beton bertulang (150 kg besi + bekisting)


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.60

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Batu OH
Tukang Kayu OH
Tukang Besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Kayu Bekisting Kelas 3 M3
Paku Campur Biasa KG
Minyak Bekisting Liter
Besi tulangan beton dia. 10 mm KG
Kawat ikat besi beton KG
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Sloof beton bertulang (200 kg besi + bekisting)


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.61
NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Batu OH
Tukang Kayu OH
Tukang Besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Kayu Bekisting Kelas 3 M3
Paku Campur Biasa KG
Minyak Bekisting Liter
Besi tulangan beton dia. 10 mm KG
Kawat ikat besi beton KG
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

D. PEKERJAAN BESI DAN ALUMUNIUM

Pekerjaan : 1 KG Pasang Besi Profil (KOLOM)


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi profil KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pasang Besi Profil (BALOK UTAMA)


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi profil KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pasang Besi Profil (RING BALK)


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH
B BAHAN
Besi profil KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pasang Besi Profil PLAT BONDEK)


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi profil KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pasang Kuda - Kuda Baja IWF


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.2

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH
B BAHAN
Besi profil KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pasangan Gording Canal


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.3

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang las OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi gording canal KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 100 KG Perakitan Besi Baja


Referensi : SNI 7393-2008
Kode Analisa : PU-CK.J.4

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Solar Liter
Minyak Pelumas Liter
Sewa Alat Kerja Perakitan Jam

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga per 1 KG
G Jumlah harga dibulatkan

Pekerjaan : 1 KG Pembesian Besi polos/ulir Ø. 8 mm SNI


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.40

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang besi OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi Beton Dia.8 SNI (P=12 m) KG
Kawat beton KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pembesian Besi polos/ulir Ø. 10 mm SNI


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.41

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang besi OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi Beton Dia.10 SNI (P=12 m) KG
Kawat beton KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 KG Pembesian Besi polos/ulir Ø. 12 mm SNI


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.42

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang besi OH
Kepala tukang OH
Mandor OH

B BAHAN
Besi Beton Dia.12 SNI (P=12 m) KG
Kawat beton KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

E. PEKERJAAN COR BETON

Pekerjaan : 1 M3 Campuran Beton 1PC : 2PS - Pasir Import (mekanis) Coran Kolom
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.D.11
NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Jam
Tukang pasir/batu Jam
Kepala tukang Jam
Mandor Jam

B BAHAN
Semen Portland (PC) @ 50 Kg Zak
Pasir semen (import) M3

C PERALATAN
Concrete Mixer Jam
Truck tanki air Jam
Water Pump Jam
Alat bantu Set

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M3 Campuran Beton 1PC : 3PS - Pasir Import (mekanis)


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.D.12

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Jam
Tukang pasir/batu Jam
Kepala tukang Jam
Mandor Jam

B BAHAN
Semen Portland (PC) @ 50 Kg Zak
Pasir semen (import) M3

C PERALATAN
Concrete Mixer Jam
Truck tanki air Jam
Water Pump Jam
Alat bantu Set

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M' Kolom 15 x 15 (1PC : 3PS) - Pasir Import


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.D.70
Analisa per 1 M3 Kolom

NO KOMPONEN SATUAN

1 2 4
A TENAGA

B BAHAN
Begisting beton (kolom) LS
Tulangan Sengkang (polos) Dia. 8 mm KG
Tulangan Utama (polos) Dia. 10 mm KG
Campuran Beton 1PC : 3PS (import) M3

C PERALATAN

Pekerjaan : 1 M3 Plat beton bertulang (150 kg besi + bekisting)


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.64

NO KOMPONEN SATUAN
1 2 4
A TENAGA
Pekerja OH
Tukang Batu OH
Tukang Kayu OH
Tukang Besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Kayu Bekisting Kelas 3 M3
Paku Campur Biasa KG
Minyak Bekisting Liter
Besi tulangan beton dia. 10 mm KG
Kawat ikat besi beton KG
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3
Balok Kayu Kelas 2 M3
Plywood 9 mm Lembar
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 Batang

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Bata merah (5 x 10 x 20) cm Tebal 1/2 Bata, 1PC : 3PS - Pasir Import
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.E.13

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Bata merah (5 x 10 x 20) cm Buah
Semen Portland (PC) @ 50 Kg Zak
Pasir semen (import) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Plesteran 1PC : 4PS, Tebal 15 mm - Pasir Import


Referensi : SNI 2837:2008
Kode Analisa : PU-CK.F.4

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Campuran Beton 1PC : 3PS - Pasir Import (mekanis) Coran Lantai
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.D.12

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Jam
Tukang pasir/batu Jam
Kepala tukang Jam
Mandor Jam

B BAHAN
Semen Portland (PC) @ 50 Kg Zak
Pasir semen (import) M3

C PERALATAN
Concrete Mixer Jam
Truck tanki air Jam
Water Pump Jam
Alat bantu Set

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M3 Tangga beton bertulang (150 kg besi + bekisting)


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.D.67

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Batu OH
Tukang Kayu OH
Tukang Besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Kayu Bekisting Kelas 3 M3
Paku Campur Biasa KG
Minyak Bekisting Liter
Besi tulangan beton dia. 10 mm KG
Kawat ikat besi beton KG
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3
Balok Kayu Kelas 2 M3
Plywood 9 mm Lembar
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 Batang

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M3 Plat beton bertulang (150 kg besi + bekisting)


Referensi : SNI 7394:2008
Kode Analisa : PU-CK.D.64

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Batu OH
Tukang Kayu OH
Tukang Besi OH
Kepala Tukang OH
Mandor OH

B BAHAN
Kayu Bekisting Kelas 3 M3
Paku Campur Biasa KG
Minyak Bekisting Liter
Besi tulangan beton dia. 10 mm KG
Kawat ikat besi beton KG
Semen Portland (PC) @ 50 Kg KG
Pasir semen (import) M3
Kerikil/batu pecah (import) M3
Balok Kayu Kelas 2 M3
Plywood 9 mm Lembar
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 Batang

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

F. PEKERJAAN ATAP

Pekerjaan : 1 M2 Penutup Atap Alumunium Gelombang


Referensi : SNI 03-3436-2002
Kode Analisa : PU-CK.H.10
NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Atap Allumunium Gelombang M2
Angker / Baut Buah

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M' Bubungan/Nok Atap Seng Gelombang BJLS 0,30


Referensi : SNI 03-3436-2002
Kode Analisa : PU-CK.H.4

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Seng Plat BJLS 0,30 Lembar
Paku Campuran KG
Papan Kayu Kelas III (Kayu Bus) t = 2 - 5 cm M3

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M2 Rangka Plafond (60 x 120), Kayu Kelas II


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.G.34

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Kayu OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Balok Kayu Kelas II (Kayu Rahay) M3
Paku Campuran KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit

Pekerjaan : 1 M2 Langit-langit Triplek Ukuran (120 x 240) tebal 3 mm


Referensi : SNI 2839:2008
Kode Analisa : PU-CK.K.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Kayu OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Triplek ukuran (120 x 240) cm tebal 3 mm Lembar
Paku Triplek KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M' Lisplank Ukuran (2 x 20) cm, Kayu Kelas II


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.G.41

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Kayu OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Papan Kayu Kelas II (Kayu Rahay) tebal = 2 Cm M3
Paku Campuran KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

G. PEKERJAAN SANITASI

Pekerjaan : 1 Buah Bak Air Fiberglass 1 M3


Referensi : RSNI T-15-2002
Kode Analisa : PU-CK.M.7

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Bak Air Fiberglass 1 M3 Buah

C PERALATAN
Perlengkapan Set
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 BH Closet jongkok porselin


Referensi : RSNI T-15-2002
Kode Analisa : PU-CK.M.2

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja pasir/batu OH
Tukang pasir/batu OH
Kepala tukang pasir/batu OH
Mandor pasir/batu OH

B BAHAN
Closet jongkok porselin Buah
Semen Portland (PC) @ 50 Kg KG
Pasir semen (lokal) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Unit Septictank 1 x (1 x 1) dalam 1,5 M + Resapan


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.M.32

NO KOMPONEN SATUAN

1 2 4
A TENAGA

B BAHAN
Pengukuran dan pasangan bowplank M1
Galian tanah septic tank M3
Urugan tanah galian kembali M3
Urugan pasir bawah bak M3
Lantai Septictank pasangan batu bata 1PC : 3PS (Pasir import) M3
Bekisting untuk kolom LS
Pembesian Beton 4D10 Kolom KG
Pembesian Beton D8-150 Kolom KG
Beton Campuran 1PC : 3PS (Pasir Import) Kolom - Manual M3
Pasangan Dinding 1/2 Batu Bata 1Pc:3Ps (Pasir Import) M2
Cor Lantai Bak Septictank Beton Camp. 1PC:3PS (Lokal-Manual) M3
Plesteran Dinding Bak 1PC : 3PS, tebal 15 mm M2
Acian dinding Bak M2
Bekisting untuk plat dak LS
Pembesian Beton D.10-20 Penutup Plat Dak KG
Beton Campuran 1PC : 3PS (Pasir Import) Plat Dak - Manual M3
Pemasangan Pipa Inlet PVC Ø 4" dari WC M
Pemasangan Pipa Outlet ke Bak Resapan - PVC Ø 2" M
Ventilasi Udara dari Pipa GIP Ø 1,5" M
Urugan Batu Pecah M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Jumlah harga dibulatkan

Pekerjaan : 1 M Memasang Pipa PVC Tipe AW Dia. 3/4"


Referensi : RSNI T-15-2002
Kode Analisa : PU-CK.M.20

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang pipa OH
Kepala tukang OH
Mandor OH

B BAHAN
Pipa PVC Tipe AW Dia. 3/4" M

C PERALATAN
Perlengkapan Set
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 M Memasang Pipa PVC Tipe D Dia. 4"


Referensi : RSNI T-15-2002
Kode Analisa : PU-CK.M.25

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang pipa OH
Kepala tukang OH
Mandor OH

B BAHAN
Pipa PVC Tipe D Dia. 4" M

C PERALATAN
Perlengkapan Set

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 BH Kran air Dia. 3/4" atau 1/2"


Referensi : RSNI T-15-2002
Kode Analisa : PU-CK.M.26

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang pipa OH
Kepala tukang OH
Mandor OH

B BAHAN
Kran air Dia. 3/4" atau 1/2" Buah
Seal Tape Buah

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Unit Pompa dragon/pompa tangan


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.M.36

NO KOMPONEN SATUAN

1 2 4
A TENAGA

B BAHAN
Pompa Dragon Buah
Shock ulir Buah
L Bough 2" Buah
Pipa PVC dia 1" ( D ) Batang
Lem PVC Buah
Campuran 1PC : 3PS - import ( 0,4 x 0,4 x 0,4 ) Upah kerja M3

C PERALATAN
Alat bantu LS

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan
H. PEKERJAAN INSTALASI LISTRIK

Pekerjaan : 1 Titik Instalasi Lampu TL Double 2 x 36 Watt


Referensi :
Kode Analisa :

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Upah Memasang LS

B BAHAN
Kabel NYA 2x1,5 mm M
Saklar Buah
Lampu TL double 2 x 36 Watt Buah
Klem Kabel Dos
Isolasi Buah
Sekrup Dos

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Titik Instalasi Lampu SL 18 - 23 VA+ Pitting + Saklar


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.O.1

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Upah Memasang LS

B BAHAN
Vetting lampu Buah
Kabel NYA 2x1,5 mm M
Saklar Buah
Lampu SL 23 VA Buah
Klem Kabel Dos
Isolasi Buah
Sekrup Dos

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Titik Instalasi Stop Kontak


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.O.3

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Upah Memasang LS

B BAHAN
Stop Kontak Buah
Kabel NYA 3x2.5 mm M
Klem Kabel Dos
Isolasi Buah
Sekrup Dos

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Titik Saklar Ganda


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.O.5

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Upah Memasang OH

B BAHAN
Saklar Ganda Buah

C PERALATAN
Alat Bantu + Aksesoris LS

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 Titik Saklar Tunggal


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.O.6

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Upah Memasang OH

B BAHAN
Saklar Tunggal Buah

C PERALATAN
Alat Bantu + Aksesoris LS

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

Pekerjaan : 1 Unit Panel Box


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.O.7

NO KOMPONEN SATUAN
1 2 4
A TENAGA
Upah Memasang OH

B BAHAN
Panel Box Buah

C PERALATAN
Alat Bantu + Aksesoris LS

D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


E Overhead + Profit
F Harga Satuan Pekerjaan(D+E)
G Jumlah harga dibulatkan

I. PEKERJAAN LANTAI

Pekerjaan : 1 M2 Lantai Ubin Teralux Marmer Ukuran 60 x 60 cm


Referensi : SNI 7395-2008
Kode Analisa : PU-CK.I.13

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang batu OH
Kepala tukang OH
Mandor OH

B BAHAN
Ubin Teralux Marmer Ukuran 60 x 60 cm Buah
Semen Portland (PC) @ 50 Kg KG
Pasir Semen (lokal) M3
Semen Warna KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Lantai Ubin PC Abu-abu Ukuran 30 x 30 cm


Referensi : SNI 7395-2008
Kode Analisa : PU-CK.I.2

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang batu OH
Kepala tukang OH
Mandor OH

B BAHAN
Ubin Abu-abu Ukuran 30 x 30 Buah
Semen Portland (PC) @ 50 Kg KG
Pasir Semen (lokal) M3

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Lantai Keramik Ukuran 20 x 25 cm


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.I.23

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang batu OH
Kepala tukang OH
Mandor OH

B BAHAN
Ubin Keramik Ukuran 20 x 25 Buah
Semen Portland (PC) @ 50 Kg KG
Pasir Semen (lokal) M3
Semen Warna KG
C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Dinding Keramik Ukuran 20 x 25 cm


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.I.54

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja OH
Tukang batu OH
Kepala tukang OH
Mandor OH

B BAHAN
Keramik Ukuran 20 x 25 cm Buah
Semen Portland (PC) @ 50 Kg KG
Pasir Semen (lokal) M3
Semen Warna KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

J. PEKERJAAN PASANGAN KUSEN

Pekerjaan : 1 Unit Pintu double tripleks 70 x 210 cm, bingkai kayu 3,5 x 9 cm
Referensi : HPS.PU- 2019
Kode Analisa : : PU-CK.L.20

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala tukang kayu OH
Mandor kayu OH

B BAHAN
Balok kayu Rahay (Bingkai 3 x 8 cm + les) M3
Papan kayu Rahay Lembar
Engsel 4" Kuningan (untuk pintu) Buah
Kait angin 8" Buah
Kunci tanam 2 slangh Buah
Grendel besar Buah
Paku Campur KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 Unit Pintu Panel 80 x 210 cm


Referensi : HPS.PU- 2019
Kode Analisa : : PU-CK.L.17

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala tukang kayu OH
Mandor kayu OH

B BAHAN
Papan kayu Rahay M3
Engsel 4" Kuningan (untuk pintu) Buah
Kait angin Buah
Kunci tanam (setara kuda terbang) Buah
Grendel besar Buah
Paku Campur KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan
Pekerjaan : 1 Unit Pintu double tripleks 70x210 cm, bingkai kayu 3,5x9 cm lapis seng plat
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.L.21

NO KOMPONEN SATUAN

1 2 4
A BAHAN
Pintu double tripleks 70 x 210 cm, bingkai kayu 3,5 x 9 cm Buah
Seng Plat BJLS 0.30 Lembar
Paku Campur KG

B Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


C Overhead + Profit
D Harga Satuan Pekerjaan(C+B)
E Jumlah harga dibulatkan

Pekerjaan : 1 Unit Jendela 75 x 120 cm


Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.L.16

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala tukang kayu OH
Mandor kayu OH

B BAHAN
Balok kayu Rahay (Bingkai 3 x 8 cm + les) M3
Engsel jendela 3" Buah
Kait angin Buah
Grendel jendela Buah
Paku Campur KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan
Pekerjaan : 1 Unit Jendela Ungkit (75 x 115 cm), bingkai 3x8 cm, kaca polos 5 mm
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.L.14

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja kayu OH
Tukang kayu OH
Kepala tukang kayu OH
Mandor kayu OH

B BAHAN
Balok kayu Rahay (Bingkai 3 x 8 cm + les) M3
Kaca polos tebal 5 mm M2
Tarikan jendela aluminium Buah
Kait angin 6" Buah
Grendel jendela Buah
Paku Campur KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Jalusi Kusen, Kayu Kelas II


Referensi : SNI 3434:2008
Kode Analisa : PU-CK.G.16

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja Kayu OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

B BAHAN
Papan Kayu Kelas II (Kayu Rahay) tebal = 2 Cm M3
Paku Campuran KG
C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Pelapisan Bidang Kayu Dengan Meny


Referensi : Pt.T-38-2000-C
Kode Analisa :

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja cat OH
Mandor cat OH

B BAHAN
Cat meny kayu KG
Minyak Cat Liter
Kuas Buah

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Mengecat Penutup 2 Lapis Pada Kayu


Referensi : Pt.T-38-2000-C
Kode Analisa : : PU-CK.N.11

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja cat OH
Tukang cat OH
Kepala tukang cat OH
Mandor cat OH

B BAHAN
Cat tutup/cat kayu KG
Minyak Cat Liter
Kuas Buah
C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan
D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Cat tembok biasa (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Referensi : HPS.PU- 2019
Kode Analisa : PU-CK.N.15

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja cat OH
Tukang cat OH
Kepala tukang cat OH
Mandor cat OH

B BAHAN
Plamur KG
Cat dasar KG
Cat penutup 2 kali KG

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan

Pekerjaan : 1 M2 Cat Plafond 2 Lapis dgn cat tembok (setara Dulux Weathershield), kuas roll
Referensi : HPS.PU- 2019
Kode Analisa : : PU-CK.N.7

NO KOMPONEN SATUAN

1 2 4
A TENAGA
Pekerja cat OH
Tukang cat OH
Kepala tukang cat OH
Mandor cat OH

B BAHAN
Plamur KG
Cat Tembok (Setara Dulux Weathershield) KG
Kertas amplas (kayu) Lembar
Kuas roll Buah
Kapek Buah

C Jumlah Harga Tenaga Kerja, Bahan dan Peralatan


D Overhead + Profit
E Harga Satuan Pekerjaan(C+D)
F Jumlah harga dibulatkan
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.2000 L-4 140,000.00 28,000.00


0.4000 L-3 178,000.00 71,200.00
0.0200 L-2 186,000.00 3,720.00
0.0200 L-1 196,000.00 3,920.00
JUMLAH HARGA TENAGA 106,840.00

1.2500 MC.32 16,990.00 21,237.50


2.5000 MB.10 1,961.00 4,902.50
1.2000 ME.3 54,880.00 65,856.00
0.0050 MB.1 1,158,994.00 5,794.97
0.0090 MB.5 1,162,930.00 10,466.37
0.0720 MC.1 2,903,800.00 209,073.60
0.0600 MD.16 21,050.00 1,263.00
0.4500 MI.5 36,496.00 16,423.20
JUMLAH HARGA BAHAN 335,017.14
441,857.14
15% 66,278.57
508,135.71
508,135.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1000 L-4 140,000.00 14,000.00


0.0050 L-1 196,000.00 980.00
JUMLAH HARGA TENAGA 14,980.00
14,980.00
15% 2,247.00
17,227.00
17,227.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1000 L-4 140,000.00 14,000.00


0.1000 L-3 178,000.00 17,800.00
0.0100 L-2 186,000.00 1,860.00
0.0050 L-1 196,000.00 980.00
JUMLAH HARGA TENAGA 34,640.00

0.0120 MC.1 2,903,800.00 34,845.60


0.0070 MC.5 2,903,800.00 20,326.60
0.0200 MD.16 21,050.00 421.00
JUMLAH HARGA BAHAN 55,593.20
90,233.20
15% 13,534.98
103,768.18
103,760.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.9000 L-4 140,000.00 126,000.00


0.0450 L-1 196,000.00 8,820.00
JUMLAH HARGA TENAGA 134,820.00
134,820.00
15% 20,223.00
155,043.00
155,040.00

Referensi

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.3333 1/3 155,040.00 51,680.00


JUMLAH HARGA TENAGA 51,680.00
51,680.00

Pekerjaan

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.5000 L-4 140,000.00 70,000.00


0.0500 L-1 196,000.00 9,800.00
JUMLAH HARGA TENAGA 79,800.00
79,800.00
15% 11,970.00
91,770.00
91,770.00

n per 20 cm
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.5000 L-4 140,000.00 70,000.00


0.0500 L-1 196,000.00 9,800.00
JUMLAH HARGA TENAGA 79,800.00
1.2000 MB.3 260,010.00 312,012.00
JUMLAH HARGA BAHAN 312,012.00
391,812.00
15% 58,771.80
450,583.80
450,580.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.3000 L-4 140,000.00 42,000.00


0.0100 L-1 196,000.00 1,960.00
JUMLAH HARGA TENAGA 43,960.00

1.2000 MB.2 747,550.00 897,060.00


JUMLAH HARGA BAHAN 897,060.00
941,020.00
15% 141,153.00
1,082,173.00
1,082,170.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.3000 L-4 140,000.00 42,000.00


0.0100 L-1 196,000.00 1,960.00
JUMLAH HARGA TENAGA 43,960.00

1.2000 MB.2 747,550.00 897,060.00


941,020.00
15% 141,153.00
1,082,173.00
1,082,170.00
H

al) D

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

2.8571 L-4 140,000.00 400,000.00


1.2857 L-3 178,000.00 228,857.14
0.4286 L-2 186,000.00 79,714.29
0.1429 L-1 196,000.00 28,000.00
JUMLAH HARGA TENAGA 736,571.43

649.0000 MB.7 1,340.00 869,660.00


4.3302 MB.10 98,030.00 424,494.28
0.4640 MB.1 1,158,994.00 537,721.32
JUMLAH HARGA BAHAN 1,831,875.60
2,568,447.03
-
2,568,447.03
2,568,447.00

3-6) cm w/c = 0,87

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.2000 L-4 140,000.00 168,000.00


0.2000 L-3 178,000.00 35,600.00
0.0200 L-2 186,000.00 3,720.00
0.0600 L-1 196,000.00 11,760.00
JUMLAH HARGA TENAGA 219,080.00

230.0000 MB.10 1,961.00 451,030.00


0.6379 MB.1 1,158,994.00 739,272.60
0.7607 MB.5 1,162,930.00 884,688.23
200.0000 MN.13 50.00 10,000.00
JUMLAH HARGA BAHAN 2,084,990.83
2,304,070.83
15% 345,610.62
2,649,681.46
2,649,681.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

5.3000 L-4 140,000.00 742,000.00


0.2750 L-3 178,000.00 48,950.00
1.3000 L-3 178,000.00 231,400.00
1.0500 L-3 178,000.00 186,900.00
0.2620 L-2 186,000.00 48,732.00
0.2650 L-1 196,000.00 51,940.00
JUMLAH HARGA TENAGA 1,309,922.00

0.2000 MC.5 2,903,800.00 580,760.00


1.5000 MD.16 21,050.00 31,575.00
0.4000 MA.5 907.00 362.80
157.0000 MD.3 13,945.00 2,189,365.00
2.2500 MD.9 25,976.00 58,446.00
336.0000 MB.10 1,961.00 658,896.00
0.5400 MB.1 1,158,994.00 625,856.76
0.8100 MB.5 1,162,930.00 941,973.30
JUMLAH HARGA BAHAN 5,087,234.86
6,397,156.86
15% 959,573.53
7,356,730.39
7,356,730.00

Referensi

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

5.6500 L-4 140,000.00 791,000.00


0.2750 L-3 178,000.00 48,950.00
1.5600 L-3 178,000.00 277,680.00
1.4000 L-3 178,000.00 249,200.00
0.3230 L-2 186,000.00 60,078.00
0.2830 L-1 196,000.00 55,468.00
JUMLAH HARGA TENAGA 1,482,376.00

0.2700 MC.5 2,903,800.00 784,026.00


2.0000 MD.16 21,050.00 42,100.00
0.6000 MA.5 907.00 544.20
210.0000 MD.3 13,945.00 2,928,450.00
3.0000 MD.9 25,976.00 77,928.00
336.0000 MB.10 1,961.00 658,896.00
0.5400 MB.1 1,158,994.00 625,856.76
0.8100 MB.5 1,162,930.00 941,973.30
JUMLAH HARGA BAHAN 6,059,774.26
7,542,150.26
-
7,542,150.26
7,542,150.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00
1.1500 MD.54 21,260.00 24,449.00

JUMLAH HARGA BAHAN 24,449.00


45,233.00
15% 6,784.95
52,017.95
52,017.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00

1.1500 MD.54 21,260.00 24,449.00

JUMLAH HARGA BAHAN 24,449.00


45,233.00
0% -
45,233.00
45,233.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00
1.1500 MD.54 21,260.00 24,449.00

JUMLAH HARGA BAHAN 24,449.00


45,233.00
0% -
45,233.00
45,233.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00

1.1500 MD.54 21,260.00 24,449.00

JUMLAH HARGA BAHAN 24,449.00


6,784.95
0% -
6,784.95
6,784.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00

1.1500 MD.54 21,260.00 24,449.00

JUMLAH HARGA BAHAN 24,449.00


45,233.00
0% -
45,233.00
45,233.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 20,784.00

1.1500 MD. 55 22,809.00 26,230.35

JUMLAH HARGA BAHAN 26,230.35


47,014.35
0% -
47,014.35
47,014.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1000 L-4 140,000.00 14,000.00


0.1000 L-3 178,000.00 17,800.00
0.0010 L-2 186,000.00 186.00
0.0050 L-1 196,000.00 980.00
JUMLAH HARGA TENAGA 32,966.00

1.0000 MA.2 14,124.00 14,124.00


0.1000 MA.4 35,407.00 3,540.70
0.8000 750,000.00 600,000.00
JUMLAH HARGA BAHAN 617,664.70
650,630.70
0% -
650,630.70
6,506.31
6,506.00

Referensi

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0070 L-4 140,000.00 980.00


0.0070 L-3 178,000.00 1,246.00
0.0007 L-2 186,000.00 130.20
0.0004 L-1 196,000.00 78.40
JUMLAH HARGA TENAGA 2,434.60

1.0500 MD.2 13,987.00 14,686.35


0.0150 MD.9 25,976.00 389.64
JUMLAH HARGA BAHAN 15,075.99
17,510.59
0% -
17,510.59
17,510.00

Referensi

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7
0.0070 L-4 140,000.00 980.00
0.0070 L-3 178,000.00 1,246.00
0.0007 L-2 186,000.00 130.20
0.0004 L-1 196,000.00 78.40
JUMLAH HARGA TENAGA 2,434.60

1.0500 MD.3 13,945.00 14,642.25


0.0150 MD.9 25,976.00 389.64
JUMLAH HARGA BAHAN 15,031.89
17,466.49
0% -
17,466.49
17,466.00

Referensi

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0070 L-4 140,000.00 980.00


0.0070 L-3 178,000.00 1,246.00
0.0007 L-2 186,000.00 130.20
0.0004 L-1 196,000.00 78.40
JUMLAH HARGA TENAGA 2,434.60

1.0500 MD.4 14,128.00 14,834.40


0.0150 MD.9 25,976.00 389.64
JUMLAH HARGA BAHAN 15,224.04
17,658.64
0% -
17,658.64
17,658.00

oran Kolom

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

16.0000 L-4 20,000.00 320,000.00


4.8000 L-3 25,429.00 122,059.20
1.6000 L-2 26,572.00 42,515.20
1.6000 L-1 28,000.00 44,800.00
JUMLAH HARGA TENAGA 529,374.40

15.1500 MB.10 98,030.00 1,485,154.50


1.0821 MB.1 1,158,994.00 1,254,197.08
JUMLAH HARGA BAHAN 2,739,351.58

1.6000 E-8 70,997.00 113,595.20


0.1734 E - 10 385,142.00 66,785.01
1.6000 E-9 61,851.00 98,961.60
1.0000 1,000.00 1,000.00
JUMLAH HARGA PERALATAN 280,341.81
3,549,067.79
0% -
3,549,067.79
3,549,067.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

16.0000 L-4 20,000.00 320,000.00


4.8000 L-3 25,429.00 122,059.20
1.6000 L-2 26,572.00 42,515.20
1.6000 L-1 28,000.00 44,800.00
JUMLAH HARGA TENAGA 529,374.40

11.3625 MB.10 98,030.00 1,113,865.88


1.2174 MB.1 1,158,994.00 1,410,971.71
JUMLAH HARGA BAHAN 2,524,837.59

1.6000 E-8 70,997.00 113,595.20


0.1301 E - 10 385,142.00 50,088.76
1.6000 E-9 61,851.00 98,961.60
1.0000 1,000.00 1,000.00
JUMLAH HARGA PERALATAN 263,645.56
3,317,857.55
0% -
3,317,857.55
3,317,857.00

Pekerjaan

M3 Kolom
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

-
-
JUMLAH HARGA TENAGA -

1.0000 2,000,000.00 2,000,000.00


65.9935 PU-CK.D.40 17,510.00 1,155,545.39
109.9349 PU-CK.D.41 17,466.00 1,920,122.98
1.1000 PU-CK.D.12 3,317,857.00 3,649,642.70
JUMLAH HARGA BAHAN 8,725,311.07

- -
- -
JUMLAH HARGA PERALATAN -

Jumlah harga pekerjaan per 1 M3 8,725,311.07


Volume Kolom per 1 M' 0.02
Jumlah harga kolom per 1 M' 196,319.50
Jumlah harga dibulatkan 196,319.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

5.3000 L-4 140,000.00 742,000.00


0.2750 L-3 178,000.00 48,950.00
1.3000 L-3 178,000.00 231,400.00
1.0500 L-3 178,000.00 186,900.00
0.2650 L-2 186,000.00 49,290.00
0.2650 L-1 196,000.00 51,940.00
JUMLAH HARGA TENAGA 1,310,480.00

0.3200 MC.5 2,903,800.00 929,216.00


3.2000 MD.16 21,050.00 67,360.00
1.6000 MA.5 907.00 1,451.20
157.5000 MD.3 13,945.00 2,196,337.50
2.2500 MD.9 25,976.00 58,446.00
336.0000 MB.10 1,961 658,761.60
0.5400 MB.1 1,158,994.00 625,856.76
0.8100 MB.5 1,162,930.00 941,973.30
0.1200 MC.2 4,177,460.00 501,295.20
2.8000 MC.21 453,750.00 1,270,500.00
32.0000 MC.32 16,990.00 543,680.00
JUMLAH HARGA BAHAN 7,794,877.56
9,105,357.56
0% -
9,105,357.56
9,105,357.00

Pasir Import

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0143 L-4 140,000.00 2,000.00


0.0429 L-3 178,000.00 7,628.57
0.1286 L-2 186,000.00 23,914.29
0.2857 L-1 196,000.00 56,000.00
JUMLAH HARGA TENAGA 89,542.86

70.0000 MB.7 1,340.00 93,800.00


0.4625 MB.10 98,030.00 45,334.34
0.0495 MB.1 1,158,994.00 57,426.55
JUMLAH HARGA BAHAN 196,560.89
286,103.75
0% -
286,103.75
286,103.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.3000 L-4 140,000.00 42,000.00


0.1500 L-3 178,000.00 26,700.00
0.0150 L-2 186,000.00 2,790.00
0.0150 L-1 196,000.00 2,940.00
JUMLAH HARGA TENAGA 74,430.00

6.2400 MB.10 1,961 12,234.14


0.0240 MB.1 1,158,994.00 27,815.86
JUMLAH HARGA BAHAN 40,050.00
114,480.00
0% -
114,480.00
114,480.00

oran Lantai 1

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

16.0000 L-4 140,000.00 2,240,000.00


4.8000 L-3 178,000.00 854,400.00
1.6000 L-2 186,000.00 297,600.00
1.6000 L-1 196,000.00 313,600.00
JUMLAH HARGA TENAGA 3,705,600.00
11.3625 MB.10 98,030.00 1,113,865.88
1.2174 MB.1 1,158,994.00 1,410,971.71
JUMLAH HARGA BAHAN 2,524,837.59

1.6000 E-8 70,997.00 113,595.20


0.1301 E - 10 385,142.00 50,088.76
1.6000 E-9 61,851.00 98,961.60
1.0000 1,000.00 1,000.00
JUMLAH HARGA PERALATAN 263,645.56
6,494,083.15
0% -
6,494,083.15
6,494,083.00

NO

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

5.6000 L-4 140,000.00 784,000.00


0.3500 L-3 178,000.00 62,300.00
2.3000 L-3 178,000.00 409,400.00
1.4000 L-3 178,000.00 249,200.00
0.4050 L-2 186,000.00 75,330.00
0.2020 L-1 196,000.00 39,592.00
JUMLAH HARGA TENAGA 1,619,822.00

0.2500 MC.5 2,903,800.00 725,950.00


3.0000 MD.16 21,050.00 63,150.00
1.2000 MA.5 907.00 1,088.40
200.0000 MD.3 13,945.00 2,789,000.00
3.0000 MD.9 25,976.00 77,928.00
323.0000 MB.10 1,961.00 633,403.00
0.5200 MB.1 1,158,994.00 602,676.88
0.7800 MB.5 1,162,930.00 907,085.40
0.1050 MC.2 4,177,460.00 438,633.30
2.5000 MC.21 453,750.00 1,134,375.00
14.0000 MC.32 16,990.00 237,860.00
JUMLAH HARGA BAHAN 7,611,149.98
9,230,971.98
0% -
9,230,971.98
9,230,971.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

5.3000 L-4 140,000.00 742,000.00


0.2750 L-3 178,000.00 48,950.00
1.3000 L-3 178,000.00 231,400.00
1.0500 L-3 178,000.00 186,900.00
0.2650 L-2 186,000.00 49,290.00
0.2650 L-1 196,000.00 51,940.00
JUMLAH HARGA TENAGA 1,310,480.00

0.3200 MC.5 2,903,800.00 929,216.00


3.2000 MD.16 21,050.00 67,360.00
1.6000 MA.5 907.00 1,451.20
157.5000 MD.3 13,945.00 2,196,337.50
2.2500 MD.9 25,976.00 58,446.00
336.0000 MB.10 1,961 658,761.60
0.5400 MB.1 1,158,994.00 625,856.76
0.8100 MB.5 1,162,930.00 941,973.30
0.1200 MC.2 4,177,460.00 501,295.20
2.8000 MC.21 453,750.00 1,270,500.00
32.0000 MC.32 16,990.00 543,680.00
JUMLAH HARGA BAHAN 7,794,877.56
9,105,357.56
0% -
9,105,357.56
9,105,357.00
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1200 L-4 140,000.00 16,800.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0060 L-1 196,000.00 1,176.00
JUMLAH HARGA TENAGA 29,772.00

1.1000 ME.10 66,430.00 73,073.00


2.0000 MD.33 5,860.00 11,720.00
JUMLAH HARGA BAHAN 84,793.00
114,565.00
0% -
114,565.00
114,565.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1250 L-4 140,000.00 17,500.00


0.2500 L-3 178,000.00 44,500.00
0.0250 L-2 186,000.00 4,650.00
0.0060 L-1 196,000.00 1,176.00
JUMLAH HARGA TENAGA 67,826.00

0.4000 ME.6 - -
0.0600 MD.16 21,030.00 1,261.80
0.0040 MC.5 2,893,040.00 11,572.16
JUMLAH HARGA BAHAN 12,833.96
80,659.96
0% -
80,659.96
80,659.00
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1700 L-4 140,000.00 23,800.00


0.2700 L-3 178,000.00 48,060.00
0.0270 L-2 186,000.00 5,022.00
0.0085 L-1 196,000.00 1,666.00
JUMLAH HARGA TENAGA 78,548.00

0.0130 MC.2 4,177,460.00 54,306.98


0.1200 MD.16 21,050.00 2,526.00
JUMLAH HARGA BAHAN 56,832.98
135,380.98
0% -

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1000 L-4 140,000.00 14,000.00


0.1000 L-3 178,000.00 17,800.00
0.0100 L-2 186,000.00 1,860.00
0.0050 L-1 196,000.00 980.00
JUMLAH HARGA TENAGA 34,640.00

0.3750 MC.11 65,895.00 24,710.63


0.0300 MD.16 21,050.00 631.50
JUMLAH HARGA BAHAN 25,342.13
59,982.00
0% -
59,982.00
59,982.00
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1000 L-4 140,000.00 14,000.00


0.1000 L-3 178,000.00 17,800.00
0.0100 L-2 186,000.00 1,860.00
0.0050 L-1 196,000.00 980.00
JUMLAH HARGA TENAGA 34,640.00

0.0046 MC.6 4,177,460.00 19,216.32


0.0600 MD.16 21,050.00 1,263.00
JUMLAH HARGA BAHAN 20,479.32
55,119.32
0% -
55,119.32
55,119.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

3.0000 L-4 140,000.00 420,000.00


4.5000 L-3 178,000.00 801,000.00
0.9000 L-2 186,000.00 167,400.00
0.9000 L-1 196,000.00 176,400.00
JUMLAH HARGA TENAGA 1,564,800.00

1.0000 MK.28 431,290.00 431,290.00

JUMLAH HARGA BAHAN 431,290.00

1.0000 12%xMK.28 51,754.80 51,754.80


JUMLAH HARGA PERALATAN 51,754.80

2,047,844.80
0% -
2,047,844.80
2,047,844.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 L-4 140,000.00 140,000.00


1.5000 L-3 178,000.00 267,000.00
0.1500 L-2 186,000.00 27,900.00
0.1600 L-1 196,000.00 31,360.00
JUMLAH HARGA TENAGA 466,260.00

1.0000 MK.23 208,790.00 208,790.00


6.0000 MB.10 1,961 11,763.60
0.0100 MB.2 747,550.00 7,475.50
JUMLAH HARGA BAHAN 228,029.10
694,289.10
0% -
694,289.10
694,289.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

JUMLAH HARGA TENAGA -

8.3000 PU-CK.A4 90,233.20 748,935.56


4.8175 PU-CK.B.3 155,040.00 746,905.20
2.6050 PU-CK.B.4 51,680.00 134,626.40
0.09 PU-CK.B.16 1,082,170.00 94,689.88
0.1640 PU-CK.C.2 2,568,447.00 421,225.31
1.0000 100,000.00 100,000.00
12.3455 PU-CK.D.41 17,466.00 215,625.71
5.6945 PU-CK.D.40 17,510.00 99,711.49
0.0719 PU-CK.D.2 4,163,273.00 299,235.25
7.6000 PU-CK.E.13 286,103.00 2,174,382.80
0.0675 PU-CK.D.7 3,539,824.00 238,938.12
10.0800 PU-CK.F.3 133,785.00 1,348,552.80
10.0800 PU-CK.F.47 64,392.00 649,071.36
1.0000 500,000.00 500,000.00
36.6413 PU-CK.D.41 17,466.00 639,977.10
0.1056 PU-CK.D.2 4,163,273.00 439,641.63
3.0000 PU-CK.M.25 176,862.00 530,586.00
3.0000 PU-CK.M.23 64,306.00 192,918.00
2.0000 PU-CK.M.16 144,228.00 288,456.00
0.2700 PU-CK.B.17 1,650,720.00 445,694.40
JUMLAH HARGA BAHAN 10,309,173.00
10,309,173.00
10,309,173.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0360 L-4 140,000.00 5,040.00


0.0600 L-3 178,000.00 10,680.00
0.0060 L-2 186,000.00 1,116.00
0.0018 L-1 196,000.00 352.80
JUMLAH HARGA TENAGA 17,188.80

1.2000 MK.16 8,716.25 10,459.50

JUMLAH HARGA BAHAN 10,459.50

1.0000 35%xMK.16 3,050.69 3,050.69


JUMLAH HARGA PERALATAN 3,050.69

30,698.99
0% -
30,698.99
30,698.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0810 L-4 140,000.00 11,340.00


0.1350 L-3 178,000.00 24,030.00
0.1350 L-2 186,000.00 25,110.00
0.0041 L-1 196,000.00 803.60
JUMLAH HARGA TENAGA 61,283.60

1.2000 MK.11 59,684 71,620.50

JUMLAH HARGA BAHAN 71,620.50

1.0000 35%xMK.11 20,889.31 20,889.31

JUMLAH HARGA PERALATAN 20,889.31

153,793.41
0% -
153,793.41
153,793.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

- L-4 140,000.00 -
0.1000 L-3 178,000.00 17,800.00
0.0100 L-2 186,000.00 1,860.00
- L-1 196,000.00 -
JUMLAH HARGA TENAGA 19,660.00

1.2000 MK.32 29,295.00 35,154.00


0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 35,279.00
54,939.00
0% -
54,939.00
54,939.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

JUMLAH HARGA TENAGA -

1.0000 650,000.00 650,000.00


1.0000 25,000.00 25,000.00
2.0000 6,000.00 12,000.00
2.0000 12,500.00 25,000.00
0.1000 10,000.00 1,000.00
0.0640 PU-CK.D.2 3,620,237.59 231,695.21
JUMLAH HARGA BAHAN 944,695.21

1.0000 25,000.00 25,000.00

JUMLAH HARGA PERALATAN 25,000.00

969,695.21
0% -
969,695.21
969,695.00
PERKIRAAN HARGA JUMLAH
KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 60,000.00 60,000.00


-
JUMLAH HARGA TENAGA 60,000.00

7.0000 MJ.2 8,600 60,199.30


1.0000 MJ.4 22,290.00 22,290.00
1.0000 270,000.20 270,000.20
0.2000 MJ.20 33,795.00 6,759.00
0.1000 MJ.21 8,870.00 887.00
0.1000 MJ.22 15,670.00 1,567.00
JUMLAH HARGA BAHAN 361,702.50
421,702.50
0% -
421,702.50
421,702.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 60,000.00 60,000.00


-
JUMLAH HARGA TENAGA 60,000.00

1.0000 MJ.14 12,600.00 12,600.00


7.0000 MJ.2 8,600 60,199.30
1.0000 MJ.4 22,290.00 22,290.00
1.0000 MJ.17 47,100.00 47,100.00
0.2000 MJ.20 33,795.00 6,759.00
0.1000 MJ.21 8,870.00 887.00
0.1000 MJ.22 15,670.00 1,567.00
JUMLAH HARGA BAHAN 151,402.30
211,402.30
0% -
211,402.30
211,402.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 60,000.00 60,000.00


-
JUMLAH HARGA TENAGA 60,000.00

1.0000 MJ.6 15,790.00 15,790.00


3.0000 MJ.1 14,760 44,279.70
0.2000 MJ.20 33,795.00 6,759.00
0.1000 MJ.21 8,870.00 887.00
0.1000 MJ.22 15,670.00 1,567.00
JUMLAH HARGA BAHAN 69,282.70
129,282.70
0% -
129,282.70
129,282.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 2xL-4 280,000.00 280,000.00


-
JUMLAH HARGA TENAGA 280,000.00
1.0000 MJ.4 22,290.00 22,290.00

JUMLAH HARGA BAHAN 22,290.00

1.0000 2,229.00 2,229.00

JUMLAH HARGA PERALATAN 2,229.00

304,519.00
0% -
304,519.00
304,519.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 2xL-4 280,000.00 280,000.00


-
JUMLAH HARGA TENAGA 280,000.00

1.0000 MJ.5 16,415.00 16,415.00

JUMLAH HARGA BAHAN 16,415.00

1.0000 1,641.50 1,641.50

JUMLAH HARGA PERALATAN 1,641.50


298,056.50
0% -
298,056.50
298,056.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 2,5 x L - 4 350,000.00 350,000.00


-
JUMLAH HARGA TENAGA 350,000.00

1.0000 MJ.23 12,500,860.00 12,500,860.00

JUMLAH HARGA BAHAN 12,500,860.00

1.0000 6,250,430.00 6,250,430.00

JUMLAH HARGA PERALATAN 6,250,430.00


19,101,290.00
0% -
19,101,290.00
19,101,290.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.2400 L-4 140,000.00 33,600.00


0.1200 L-3 178,000.00 21,360.00
0.0120 L-2 186,000.00 2,232.00
0.0120 L-1 196,000.00 2,352.00
JUMLAH HARGA TENAGA 59,544.00

3.1000 MF.15 73,226.00 227,000.60


9.6000 MB.10 1,961 18,821.76
0.0450 MB.2 747,550.00 33,639.75
1.5000 MB.11 2,711 4,065.90
JUMLAH HARGA BAHAN 283,528.01
343,072.01
0% -
343,072.01
343,072.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.2600 L-4 140,000.00 36,400.00


0.1300 L-3 178,000.00 23,140.00
0.0130 L-2 186,000.00 2,418.00
0.0130 L-1 196,000.00 2,548.00
JUMLAH HARGA TENAGA 64,506.00

11.8700 MF.2 7,048.00 83,659.76


10.0000 MB.10 1,961.00 19,610.00
0.0450 MB.2 747,550.00 33,639.75
JUMLAH HARGA BAHAN 136,909.51
201,415.51
0% -
201,415.51
201,415.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.7000 L-4 140,000.00 98,000.00


0.3500 L-3 178,000.00 62,300.00
0.0350 L-2 186,000.00 6,510.00
0.0350 L-1 196,000.00 6,860.00
JUMLAH HARGA TENAGA 173,670.00

20.0000 MF.19 4,242.00 84,840.00


8.1900 MB.10 1,961 16,057.31
0.0450 MB.2 747,550.00 33,639.75
3.2000 MB.11 2,711 8,673.92
JUMLAH HARGA BAHAN 143,210.98
143,210.98
0% -
143,210.98
143,210.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.9000 L-4 140,000.00 126,000.00


0.4500 L-3 178,000.00 80,100.00
0.0450 L-2 186,000.00 8,370.00
0.0450 L-1 196,000.00 8,820.00
JUMLAH HARGA TENAGA 223,290.00

20.0000 MF.27 3,150.00 63,000.00


9.3000 MB.10 1,960.60 18,233.58
0.0180 MB.2 747,550.00 13,455.90
1.9400 MB.11 2,710.60 5,258.56
JUMLAH HARGA BAHAN 99,948.04
323,238.04
0% -
323,238.04
323,238.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.8500 L-4 140,000.00 119,000.00


2.6000 L-3 178,000.00 462,800.00
0.2600 L-2 186,000.00 48,360.00
0.0425 L-1 196,000.00 8,330.00
JUMLAH HARGA TENAGA 638,490.00

0.0570 MC.2 4,177,460.00 238,115.22


0.0750 MC.11 65,895.00 4,942.13
1.5000 MH.6 23,003.00 34,504.50
1.0000 MH.11 16,670.00 16,670.00
1.0000 MH.2 123,850.00 123,850.00
1.0000 MH.14 34,836.00 34,836.00
0.2000 MD.16 21,050.00 4,210.00
JUMLAH HARGA BAHAN 457,127.85
1,095,617.85
0% -
1,095,617.85
1,095,617.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

2.2659 L-4 140,000.00 317,226.00


6.9720 L-3 178,000.00 1,241,016.00
0.6972 L-2 186,000.00 129,679.20
0.1133 L-1 196,000.00 22,206.80
JUMLAH HARGA TENAGA 1,710,128.00

0.0750 MC.7 4,177,460.00 313,309.50


1.5000 MH.6 23,003.00 34,504.50
1.0000 MH.11 16,670.00 16,670.00
1.0000 MH.1 94,683.00 94,683.00
1.0000 MH.14 34,836.00 34,836.00
0.2200 MD.16 21,050.00 4,631.00
JUMLAH HARGA BAHAN 498,634.00
2,208,762.00
0% -
2,208,762.00
2,208,762.00
lapis seng plat

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 PU-CK.L.17 1,095,617.00 1,095,617.00


1.2000 ME.6 79,290.00 95,148.00
0.1000 MD.16 21,050.00 2,105.00
JUMLAH HARGA BAHAN 1,192,870.00
1,192,870.00
0% -
1,192,870.00
1,192,870.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

1.0000 L-4 140,000.00 140,000.00


2.0000 L-3 178,000.00 356,000.00
1.0000 L-2 186,000.00 186,000.00
0.5000 L-1 196,000.00 98,000.00
JUMLAH HARGA TENAGA 780,000.00

0.0600 MC.2 4,177,460.00 250,647.60


2.0000 MH.10 16,836.00 33,672.00
1.0000 MH.11 16,670.00 16,670.00
1.0000 MH.14 34,836.00 34,836.00
0.8500 MD.16 21,050.00 17,892.50
JUMLAH HARGA BAHAN 353,718.10
1,133,718.10
0% -
1,133,718.10
1,133,718.00
s 5 mm

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.3000 L-4 140,000.00 42,000.00


1.5000 L-3 178,000.00 267,000.00
0.1500 L-2 186,000.00 27,900.00
0.1500 L-1 196,000.00 29,400.00
JUMLAH HARGA TENAGA 366,300.00

0.0300 MC.2 4,177,460.00 125,323.80


0.6200 MG.2 172,735.00 107,095.70
2.0000 MH.16 14,170.00 28,340.00
2.0000 MH.11 16,670.00 33,340.00
2.0000 MH.14 34,836.00 69,672.00
0.0650 MD.16 21,050.00 1,368.25
JUMLAH HARGA BAHAN 365,139.75
731,439.75
0% -
731,439.75
731,439.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.6700 L-4 140,000.00 93,800.00


2.0000 L-3 178,000.00 356,000.00
0.2000 L-2 186,000.00 37,200.00
0.3350 L-1 196,000.00 65,660.00
JUMLAH HARGA TENAGA 552,660.00

0.0600 MC.6 4,177,460.00 250,647.60


0.1500 MD.16 21,050.00 3,157.50
JUMLAH HARGA BAHAN 253,805.10
806,465.10
0% -
806,465.10
806,465.00

Kode Analisa :

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0750 L-4 140,000.00 10,500.00


0.0040 L-1 196,000.00 784.00
JUMLAH HARGA TENAGA 11,284.00

0.1700 MI.4 36,496.00 6,204.32


0.1000 MI.9 31,080.00 3,108.00
0.0150 MN.11 22,090.00 331.35
JUMLAH HARGA BAHAN 9,643.67
20,927.67
0% -
20,927.67
20,927.00

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.1500 L-4 140,000.00 21,000.00


0.1500 L-3 178,000.00 26,700.00
0.0150 L-2 186,000.00 2,790.00
0.0080 L-1 196,000.00 1,568.00
JUMLAH HARGA TENAGA 52,058.00

0.3000 MI.6 64,080.00 19,224.00


0.2000 MH.2 31,080.00 6,216.00
0.0200 MN.11 22,090.00 441.80
JUMLAH HARGA BAHAN 25,881.80
77,939.80
0% -
77,939.80
77,939.00

up)

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0200 L-4 140,000.00 2,800.00


0.0630 L-3 178,000.00 11,214.00
0.0063 L-2 186,000.00 1,171.80
0.0025 L-1 196,000.00 490.00
JUMLAH HARGA TENAGA 15,675.80

0.1000 MI.11 7,127 712.69


0.1000 MI.12 21,370.00 2,137.00
0.2600 MI.12 21,370.00 5,556.20
JUMLAH HARGA BAHAN 8,405.89
24,081.69
0% -
24,081.69
24,081.00

kuas roll

PERKIRAAN HARGA JUMLAH


KUANTITAS KODE SATUAN HARGA
(Rp.) (Rp.)
5 3 6 7

0.0600 L-4 140,000.00 8,400.00


0.0400 L-3 178,000.00 7,120.00
0.0040 L-2 186,000.00 744.00
0.0030 L-1 196,000.00 588.00
JUMLAH HARGA TENAGA 16,852.00
0.1000 MI.11 7,126.87 712.69
0.4700 MI.10 26,580.00 12,492.60
0.5000 MI.1 5,184.00 2,592.00
0.0100 MN.12 33,590.00 335.90
0.0500 5,000.00 250.00
JUMLAH HARGA BAHAN 16,383.19
33,235.19
0% -
33,235.19
33,235.00
DAFTAR HARGA SATUAN ALA
LOKASI KEGIATAN : KOTA MERAUKE - DISTRIK M

KEGIATAN : PENYUSUNAN NORMA, STANDAR, PEDOMAN DAN MANUAL (NSP


PEKERJAAN : PERHITUNGAN HARGA SATUAN BAHAN, UPAH, PEKERJAAN DAN
LOKASI : KOTA MERAUKE - DISTRIK MERAUKE
KABUPATEN / PROPINSI : MERAUKE - PAPUA
TAHUN ANGGARAN : 2019
SUMBER DANA : ---

PERIODE : JULI - DESEMBER 2019

Harga
No. Uraian Alat Kode Alat Baru
(Rupiah)
1 2 3 4

1 DUMP TRUCK E-1 415,000,000.00


2 EXCAVATOR 100-140 HP E-2 1,751,530,000.00
3 BULLDOZER 100-150 HP E-3 3,315,180,000.00
4 MOTOR GRADER >100 HP E-4 2,381,500,000.00
5 VIBRATOR ROLLER 5-8 T. E-5 1,240,000,000.00
6 PNEUMATIC T. ROLLER 8-15 T. E-6 1,423,300,000.00
7 TANDEM ROLER 6-8 T E-7 1,315,000,000.00
8 CONCRETE MIXER 0.3-0.6 M3 E-8 18,000,000.00
9 WATER PUMP 70-100 mm E-9 7,500,000.00
10 WATER TANKER 3000-4500 L. E - 10 395,000,000.00
11 CHAIN SAW (MESIN POTONG KAYU) E - 11 5,500,000.00
12 COMPRESSOR 4000-6500 L\M E - 12 50,000,000.00
13 ASPHALT SPRAYER E - 13 45,000,000.00
14 FARM TRACTOR (ROTARI) M 5000 E - 14 295,000,000.00
15 STAMPER E - 15 32,500,000.00
16 WHELL LOADER E - 16 1,696,580,000.00
17 ASPHALT FINIZHER E - 17 1,977,960,000.00
18 GENERATOR ZET E - 18 35,000,000.00
19 ASPHAL MIXING PLANT (AMP) E - 19 3,220,525,000.00
20 EXCAVATOR MINI + BLADE E - 20 554,400,000.00
21 FULVI MIXER E - 21 800,000,000.00
22 MILLING MACHINE E - 22 6,500,000,000.00
23 CEMENT SPREADER E - 23 2,500,000,000.00
24 ADDITIVE SPREADER E - 24 1,260,000,000.00
Catatan :
- Harga satuan belum termasuk pajak PPN dan PPH
- Harga - harga hanya sebagai pedoman / pendukung, dalam perhitungan konstruksi ( tidak mengik
- Undang -undang no. 13 tahun 2003 tentang Ketenagakerjaan (Bab X Pasal 77)
Jika dalam 1 hari bekerja selama 8 jam (5 hari kerja/ senin s/d jumat) maka dalam 1 bulan bekerja
Jika dalam 1 hari bekerja selama 7 jam (6 hari kerja/ senin s/d sabtu) maka dalam 1 bulan bekerja
SATUAN ALAT
AUKE - DISTRIK MERAUKE

N DAN MANUAL (NSPM)


AH, PEKERJAAN DAN KEGIATAN

Kapasitas Alat Berat Biaya Alat


HP Jumlah Satuan Tanpa Over Head Keterangan
(Rupiah/Jam)
5 6 7 8 9

115 3.5 Ton 381,488.00


135 0.9 M3 757,096.00
155 - - 1,179,369.00
135 - - 910,144.00
100 8 Ton 558,637.00
129 8 Ton 664,637.00
83 8 Ton 540,826.00
10 500 Liter 70,997.00
8 30 M3/hari 61,851.00
115 5000 Liter 385,142.00
10 - - 65,349.00
80 - - 200,545.00
15 800 Liter 90,888.00
50 2 Ton 240,993.00
5 0.2 Ton 64,423.00
95 1.5 M3 762,008.00
144 - - 951,316.00
50 - - 162,036.00
150 30 Ton/Jam 4,803,160.00
50 - - 403,948.00
345 - - 971,036.00
428 - - 2,926,534.00
155 - - 1,133,165.00
95 - - 629,426.00
konstruksi ( tidak mengikat ).

ka dalam 1 bulan bekerja selama 21 hari


ka dalam 1 bulan bekerja selama 25 hari
RENCANA ANGGARAN BIAYA ( RAB )
TUGAS BESAR : MENEJEMEN KONTRUKSI DAN ESTIMASI BIAYA
DIBUAT OLEH : ADRIAN RIADI PUTRA
NPM : 2016-22-201-002
JURUSAN : TEKNIK SIPIL
DIPERIKSA OLEH : HERMANSYAH
DISETUJUI OLEH : YANCE KAKERISSA, ST.,M.T

No. URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN


1 2 3 4 5

I. PEKERJAAN PERSIAPAN
1 Pagar Sementara 288.00 M2 Rp.
2 Pembersihan Lokasi 288.00 M 2
Rp.
3 Pengukuran dan Pemasangan Bouwplank 195.00 M1 Rp.
4 Papan Nama Proyek 1.00 Ls Rp.
JUMLAH I

II. PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi 98.36 M3 Rp.
2 Urugan Tanah Kembali 32.79 M3 Rp.
3 Urugan Tanah Peninggian Lantai 57.52 M3 Rp.
4 Urugan Pasir Bawah Pondasi 4.88 M3 Rp.
5 Urugan Pasir Bawah Lantai ` 8.22 M 3
Rp.
JUMLAH II

III. PEKERJAAN PONDASI BETON DAN PASANGAN


1 Lantai Kerja Tebal 7 cm 2.74 M3 Rp.
2 Pondasi Poer B. Bertulang 15.90 M 3
Rp.
3 Pas. Pondasi Menerus 1 Pc : 3 Ps 16.74 M3 Rp.
4 Sloof B.Bertulang 25 x 40 cm 7.75 M3 Rp.
JUMLAH II

IV. PEKERJAAN BESI DAN ALUMMUNIUM


1 WF 300.300.10.15 (Kolom) 14,107.50 Kg Rp.
2 WF 400.200.8.13 (Balok Utama) 6,039.00 Kg Rp.
3 Plat Bondek Tebal 0,75 mm 635.93 Kg Rp.
4 WF 400.200.8.13 (Ringbalk) 2,838.00 Kg Rp.
5 WF 250.125.6.9 (Kontruksi Kuda-Kuda) 1,593.85 Kg Rp.
6 CNP 100.50.5.7,5 (Gording) 1,474.86 Kg Rp.
7 Perakitan Besi Baja 266.89 Kg Rp.
JUMLAH II
V. PEKERJAAN COR
1 Cor Kolom Utama 36.75 M3 Rp.
2 Kolom Praktis 15 x 15 cm, B. Bertulang 1.11 M3 Rp.
3 Cor Plat Lantai Tebal 10 cm 5.05 M 3
Rp.
4 Pas. Dinding 1/2 Bata 79.26 M3 Rp.
5 Plesteran Tebal 15 mm 1585.26 M2 Rp.
6 Cor Lantai Tebal 8 cm 8.88 M3 Rp.
7 Cor Tangga Beton B. Bertulang 2.08 M3 Rp.
8 Cor Plat Dak 8.00 M3 Rp.
JUMLAH III

VI. PEKERJAAN PASANGAN ATAP


1 Penutup Atap Alumunium Gelombang 143.86 M2 Rp.
2 Nok Stuk Plat BJLS 0.20 mm 6.60 M1 Rp.
3 Pas. Rangka Plafond Kayu 5/5 cm 186.00 M2 Rp.
4 Pas. Plafond Tripleks t : 3 mm 186.00 M 2
Rp.
JUMLAH III
VII. PEKERJAAN SANITASI DAN AIR
1 Bak Air 3.00 Ls Rp.
2 Pas. Closet Jongkok Porselin 3.00 Ls Rp.
3 Septictank uk. Pas. 1/2 Bata 1.00 Ls Rp.
4 Pipa PVC Tipe AW Dia. 3/4" 18.00 M1 Rp.
5 Pipa PVC Tipe AW Dia. 4" 18.00 M1 Rp.
6 Kran Air Dia. 3/4" atau 1/2" 4.00 Ls Rp.
7 Mesin Pompa 1.00 Ls Rp.
JUMLAH IV
VIII. PEKERJAAN INSTALASI LISTRIK
1 Lampu tanam LED TS 4.00 Titik Rp.
2 Lampu XL 14 Watt 13.00 Titik Rp.
3 Saklar Ganda 4.00 Titik Rp.
4 Saklar Tunggal 5.00 Titik Rp.
5 Stop Kontak 8.00 Titik Rp.
6 Sekring Case 1.00 Titik Rp.
7 Biaya Penyambungan Listrik 1.00 Ls Rp.
JUMLAH VI
No. URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN
1 2 3 4 5

IX. PEKERJAAN LANTAI


1 Pas. Lantai Keramik 60 x 60 cm 188.76 M2 Rp.
2 Pas. Lantai Keramik 30 x 30 cm 11.85 M 2
Rp.
3 Pas. Lantai Keramik Uk. 25 x 25 cm 37.83 M2 Rp.
JUMLAH VII
X. PEKERJAAN PASANGAN KUSEN
1 Pas. Pintu Double 1,2 x 2,10 (P1) 2.00 Bh Rp.
2 Pas. Pintu Panel Kayu 80 x 210 (P2) 5.00 Bh Rp.
3 Pas. Pintu 70 x 210 (P3) 3.00 Bh Rp.
4 Pas. Jendela Ungkit 168 x 110 (J1) 5.00 Bh Rp.
5 Pas. Jendela Ungkkit 120 x 160 (J2) 2.00 Bh Rp.
6 Pasangan Ventilasi 50 x 60 (V1) 0.90 M2 Rp.
7 Pasangan Ventilasi 30 x 45 (V2) 4.19 M2 Rp.
JUMLAH VII
XI. PENGERJAAN PENGECATAN
1 Cat Meny Kayu 10.08 M1 Rp.
2 Cat Kilap Kayu 10.08 M1 Rp.
3 Cat Tembok Untuk Dinding 1,585.26 M2 Rp.
4 Cat Plafond 186.00 M 2
Rp.
JUMLAH VII
XII. PEKEKERJAAN FINISHING
1 Pembersihan Akhir 1.00 Ls Rp.
JUMLAH VII

REKAPITULASI :
I. PEKERJAAN PERSIAPAN ………………….…………………………………
II. PEKERJAAN TANAH DAN PASIR ………………….…………………………………
III. PEKERJAAN PONDASI BETON DAN PASANGAN ………………….…………………………………
IV. PEKERJAAN BESI DAN ALUMMUNIUM ………………….…………………………………
V. PEKERJAAN COR ………………….…………………………………
VI. PEKERJAAN PASANGAN ATAP ………………….…………………………………
VII. PEKERJAAN SANITASI DAN AIR ………………….…………………………………
VIII. PEKERJAAN INSTALASI LISTRIK ………………….…………………………………
IX. PEKERJAAN LANTAI ………………….…………………………………
X. PEKERJAAN PASANGAN KUSEN ………………….…………………………………
XI. PENGERJAAN PENGECATAN ………………….…………………………………
XII. PEKEKERJAAN FINISHING ………………….…………………………………

JUMLAH ………………….…………………………………
DIBULATKAN ………………….…………………………………

BIAYA FISIK ………………….…………………………………

BIAYA PERENCANAAN ………………….…………………………………

BIAYA PENGAWASAN ………………….…………………………………

BIAYA PENGELOLAAN ………………….…………………………………

JUMLAH ………………….…………………………………
PPN 10% ………………….…………………………………
TOTAL BIAYA

DIBULATKAN ………………….…………………………………

Terbilang : #NAME?

Diperiksa Oleh

Hermansyah
ASISTEN DOSEN
AYA ( RAB )

HARGA SATUAN JUMLAH HARGA


5 6 = (3) x (5)

508,135.00 Rp. 146,342,880.00


17,227.00 Rp. 4,961,376.00
103,760.00 Rp. 20,233,200.00
500,000.00 Rp. 500,000.00
JUMLAH I Rp. 172,037,456.00

155,040.00 Rp. 15,249,734.40


51,680.00 Rp. 1,694,414.93
450,580.00 Rp. 25,917,857.24
1,082,170.00 Rp. 5,283,695.03
1,082,170.00 Rp. 8,892,515.54
UMLAH II Rp. 57,038,217.14

2,649,681.00 Rp. 7,270,724.66


7,356,730.00 Rp. 116,972,007.00
2,568,447.00 Rp. 42,995,802.78
7,542,150.00 Rp. 58,451,662.50
UMLAH II Rp. 225,690,196.94

52,017.00 Rp. 733,829,827.50 Rp 508,788,680


45,233.00 Rp. 273,162,087.00
6,784.00 Rp. 4,314,115.20
45,233.00 Rp. 128,371,254.00
45,233.00 Rp. 72,094,761.80
47,014.00 Rp. 69,338,842.37
6,506.00 Rp. 1,736,395.02
UMLAH II Rp. 1,282,847,282.89

3,549,067.00 Rp. 130,428,212.25


196,319.00 Rp. 218,650.29
3,317,857.00 Rp. 16,755,177.85
286,103.00 Rp. 22,677,382.09
114,480.00 Rp. 181,480,564.80
6,494,083.00 Rp. 57,667,457.04
9,230,971.00 Rp. 19,164,418.89
9,105,357.00 Rp. 72,842,856.00
UMLAH III Rp. 501,234,719.21

114,565.00 Rp. 16,480,931.38


80,659.00 Rp. 532,349.40
135,380.98 Rp. 25,180,862.28
59,982.00 Rp. 11,156,652.00
UMLAH III Rp. 53,350,795.06

2,047,844.00 Rp. 6,143,532.00


694,289.00 Rp. 2,082,867.00
10,309,173.00 Rp. 10,309,173.00
30,698.00 Rp. 552,564.00
153,793.00 Rp. 2,768,274.00
54,939.00 Rp. 219,756.00
969,695.00 Rp. 969,695.00
UMLAH IV Rp. 23,045,861.00

421,702.00 Rp. 1,686,808.00


211,402.00 Rp. 2,748,226.00
304,519.00 Rp. 1,218,076.00
298,056.00 Rp. 1,490,280.00
129,282.00 Rp. 1,034,256.00
19,101,290.00 Rp. 19,101,290.00
5,000,000.00 Rp. 5,000,000.00
UMLAH VI Rp. 30,592,128.00
HARGA SATUAN JUMLAH HARGA
5 6 = (3) x (5)

343,072.00 Rp. 64,758,270.72


201,415.00 Rp. 2,386,767.75
143,210.00 Rp. 5,418,178.50
UMLAH VII Rp. 72,563,216.97

1,095,617.00 Rp. 2,191,234.00


2,208,762.00 Rp. 11,043,810.00
1,192,870.00 Rp. 3,578,610.00
1,133,718.00 Rp. 5,668,590.00
731,439.00 Rp. 1,462,878.00
806,465.00 Rp. 725,818.50
806,465.00 Rp. 3,375,056.03
UMLAH VII Rp. 28,045,996.53

20,927.00 Rp. 211,032.05


77,939.00 Rp. 785,952.46
24,081.00 Rp. 38,174,646.06
33,235.00 Rp. 6,181,710.00
UMLAH VII Rp. 45,353,340.58

1,000,000.00 Rp. 1,000,000.00


UMLAH VII Rp. 1,000,000.00

………………………………… Rp. 172,037,456.00


………………………………… Rp. 57,038,217.14
………………………………… Rp. 225,690,196.94
………………………………… Rp. 1,282,847,282.89
………………………………… Rp. 501,234,719.21
………………………………… Rp. 53,350,795.06
………………………………… Rp. 23,045,861.00
………………………………… Rp. 30,592,128.00
………………………………… Rp. 72,563,216.97
………………………………… Rp. 28,045,996.53
………………………………… Rp. 45,353,340.58
………………………………… Rp. 1,000,000.00

………………………………… Rp. 2,492,799,210.31


………………………………… Rp. 2,492,790,000.00

………………………………… Rp. 2,492,790,000.00

………………………………… Rp. 249,279,000.00

………………………………… Rp. 12,463,950.00

………………………………… Rp. 99,711,600.00

………………………………… Rp. 2,854,244,550.00 Rp2,304,000,000


………………………………… Rp. 285,424,455.00
Rp. 3,139,669,005.00

………………………………… Rp. 3,139,660,000.00

E?

Merauke, DESEMBER 2019


Dibuat Oleh
ESTIMATOR

Adrian Riadi Putra


2016-22-201-002
ANALISA HARGA SATUAN

No. Komponen

1 2
I. PEKERJAAN PERSIAPAN
1 1 M2 Membersihkan Lapangan dan Perataan
2 1 M' Pengukuran dan Bouwplank
RSNI T-12-2002
Balok Kayu Bus
Kayu Papan Bus
Paku Biasa Campur 2" - 5"

II. PEKERJAAN TANAH DAN PASIR


1 1 M3 Galian Tanah Biasa Sedalam 1-2 M

2 1 M3 Urug Kembali Tanah Biasa Sedalam 1-2 M


SNI 2835:2008

3 1 M3 Urugan Tanah Urug (material didatangkan)


SNI 2835:2008
Tanah timbun biasa/urug

4 1 M3 Urugan Pasir Bawah Pondasi


SNI 2835:2008
Pasir semen (lokal)

5 1 M3 Urugan Pasir Bawah Lantai


SNI 2835:2008
Pasir semen (lokal)

III. PEKERJAAN PONDASI BETON DAN PASANGAN


1 1 M3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87
SNI 7394:2008
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)
Air

2 1 M3 Pondasi beton bertulang (150 kg besi + bekisting)


SNI 7394:2008
Kayu Bekisting Kelas 3
Paku Campur Biasa
Minyak Bekisting
Besi tulangan beton dia. 10 mm
Kawat ikat besi beton
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)

3 1 M3 Pasangan Bata, Camp. 1PC : 3PS - Pasir Import (Manual)


HPS.PU- 2018
Batu Bata Merah
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

4 1 M3 Sloof beton bertulang (200 kg besi + bekisting)


SNI 7394:2008
Kayu Bekisting Kelas 3
Paku Campur Biasa
Minyak Bekisting
Besi tulangan beton dia. 10 mm
Kawat ikat besi beton
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)
IV. PEKERJAAN BESI DAN ALUMMUNIUM
1 1 KG Pasang Besi Profil ( Kolom )
SNI 7393-2008
Besi profil

2 1 KG Pasang Besi Profil ( Balok Utama)


SNI 7393-2008
Besi profil

3 1 KG Pasang Besi Profil ( Plat Bondek)


SNI 7393-2008
Besi profil

4 1 KG Pasang Besi Profil ( Ringbalk)


SNI 7393-2008
Besi profil

5 1 KG Pasang Kuda-Kuda Baja IWF


SNI 7393-2008
Baja profil IWF

No. Komponen

1 2
6 1 KG Gording Baja
SNI 7393-2008
Besi gording canal

7 100 KG Perakitan Besi Baja


SNI 7393-2008
Solar
Minyak Pelumas
V. PEKERJAAN COR
1 1 M3 Campuran Beton 1PC : 2PS - Pasir Import (mekanis) Coran Kolom
HPS.PU- 2018
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

2 1 M' Kolom 15 x 15 (1PC : 3PS) - Pasir Import


HPS.PU- 2018
Begisting beton (kolom)
Kayu Bekisting Kelas 3
Paku Campur Biasa 5 cm - 10 cm
Minyak Bekisting/oli bekas
Balok Kayu Kelas 2
Plywood 9 mm
Kayu dolken Ø 8-10, P. 400 cm - Kayu Kelas 3
Tulangan Sengkang (polos) Dia. 8 mm
Tulangan Utama (polos) Dia. 10 mm
Campuran Beton 1PC : 3PS (import)
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

3 1 M3 Plat beton bertulang (150 kg besi + bekisting)


SNI 7394:2008
Kayu Bekisting Kelas 3
Paku Campur Biasa
Minyak Bekisting
Besi tulangan beton dia. 10 mm
Kawat ikat besi beton
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)
Balok Kayu Kelas 2
Plywood 9 mm
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3

4 1 M2 Bata merah (5 x 10 x 20) cm Tebal 1/2 Bata, 1PC : 3PS - Pasir Import
HPS.PU- 2019
Bata merah (5 x 10 x 20) cm
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

5 1 M2 Plesteran 1PC : 2PS, Tebal 15 mm - Pasir Import


SNI 2837:2008
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

6 1 M3 Campuran Beton 1PC : 3PS - Pasir Import (mekanis) Coran Lantai


HPS.PU- 2018
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

7 1 M3 Tangga beton bertulang (150 kg besi + bekisting)


HPS.PU- 2018
Kayu Bekisting Kelas 3
Paku Campur Biasa
Minyak Bekisting
Besi tulangan beton dia. 10 mm
Kawat ikat besi beton
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)
Balok Kayu Kelas 2
Plywood 9 mm
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3

8 1 M3 Campuran Beton 1PC : 3PS Pasir Import - Manual


HPS.PU- 2018
Semen Portland (PC) @ 50 Kg
Pasir semen (import)

9 1 M3 Plat beton bertulang (150 kg besi + bekisting)


SNI 7394:2008
Kayu Bekisting Kelas 3
Paku Campur Biasa
Minyak Bekisting
Besi tulangan beton dia. 10 mm
Kawat ikat besi beton
Semen Portland (PC) @ 50 Kg
Pasir semen (import)
Kerikil/batu pecah (import)
Balok Kayu Kelas 2
Plywood 9 mm
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3
No. Komponen

1 2
VI. PEKERJAAN PASANGAN ATAP
1 1 M2 Penutup Atap Alumunium Gelombang
SNI 03-3436-2002
Atap Allumunium Gelombang
Angker / Baut

2 1 M' Nok Stuk Plat BJLS 0.20 mm


SNI 7393-2008
Seng Plat BJLS 0,30
Paku Campuran
Papan Kayu Kelas III (Kayu Bus) t = 2 - 5 cm

3 1 M2 Rangka Plafond (60 x 120), Kayu Kelas II


HPS.PU- 2018
Balok Kayu Kelas II (Kayu Rahay)
Paku Campuran

4 1 M2 Langit-langit Triplek Ukuran (120 x 240) tebal 3 mm


SNI 2839:2008
Triplek ukuran (120 x 240) cm tebal 3 mm
Paku Triplek
VII. PEKERJAAN SANITASI DAN AIR
1 1 Unit 1 Buah
HPS.PU- 2018
Bak Air Fiberglass 1 M3

2 1 BH Closet jongkok porselin


RSNI T-15-2002
Closet jongkok porselin
Semen Portland (PC) @ 50 Kg
Pasir semen (lokal)

3 1 Unit Septictank 2 x (1 x 1) dalam 1,5 M + Resapan


HPS.PU- 2018
Pengukuran dan pasangan bowplank
Galian tanah septic tank
Urugan tanah galian kembali
Urugan pasir bawah bak
Lantai Septictank pasangan batu bata 1PC : 3PS (Pasir import)
Bekisting untuk kolom
Pembesian Beton 4D10 Kolom
Pembesian Beton D8-150 Kolom
Beton Campuran 1PC : 3PS (Pasir Import) Kolom - Manual
Pasangan Dinding 1/2 Batu Bata 1Pc:3Ps (Pasir Import)
Cor Lantai Bak Septictank Beton Camp. 1PC:3PS (Lokal-Manual)
Plesteran Dinding Bak 1PC : 3PS, tebal 15 mm
Acian dinding Bak
Bekisting untuk plat dak
Pembesian Beton D.10-20 Penutup Plat Dak
Beton Campuran 1PC : 3PS (Pasir Import) Plat Dak - Manual
Pemasangan Pipa Inlet PVC Ø 4" dari WC
Pemasangan Pipa Outlet ke Bak Resapan - PVC Ø 2"
Ventilasi Udara dari Pipa GIP Ø 1,5"
Urugan Batu Pecah

4 1M Memasang Pipa PVC Tipe AW Dia. 3/4"


RSNI T-15-2002
Pipa PVC Tipe AW Dia. 3/4"

5 1M Memasang Pipa PVC Tipe AW Dia. 4"


RSNI T-15-2002
Pipa PVC Tipe AW Dia. 4"

6 1 BH Kran air Dia. 3/4" atau 1/2"


RSNI T-15-2002
Kran air Dia. 3/4" atau 1/2"
Seal Tape

7 1 Unit Pompa dragon/pompa tangan


HPS.PU- 2018
Pompa Dragon
Shock ulir
L Bough 2"
Pipa PVC dia 1" ( D )
Lem PVC
Campuran 1PC : 3PS - import ( 0,4 x 0,4 x 0,4 ) Upah kerja
VIII. PEKERJAAN INSTALASI LISTRIK
1 1 Titik Instalasi Lampu TL Double 2 x 36 Watt
HPS.PU- 2018
Kabel NYA 2x1,5 mm
Saklar
Lampu TL double 2 x 36 Watt
Klem Kabel
Isolasi
Sekrup

No. Komponen

1 2
2 1 Titik Instalasi Lampu SL14 Watt+ Pitting + Saklar
HPS.PU- 2018
Vetting lampu
Kabel NYA 2x1,5 mm
Saklar
Lampu SL 14 VA
Klem Kabel
Isolasi
Sekrup

3 1 Titik Saklar Ganda


HPS.PU- 2018
Saklar Ganda

4 1 Titik Saklar Tunggal


HPS.PU- 2018
Saklar Tunggal
5 1 Titik Instalasi Stop Kontak
HPS.PU- 2018
Stop Kontak
Kabel NYA 3x2.5 mm
Klem Kabel
Isolasi

6 1 Unit Panel Box


HPS.PU- 2018
Panel Box
IX. PEKERJAAN LA
1 1 M2 Pas. Lantai Keramik 60 x 60 cm
HPS.PU- 2018
Ubin Teralux Marmer Ukuran 60 x 60 cm
Semen Portland (PC) @ 50 Kg
Pasir Semen (lokal)
Semen Warna

2 1 M2 Pas. Lantai Keramik 30 x 30 cm


HPS.PU- 2018
Ubin Abu-abu Ukuran 30 x 30
Semen Portland (PC) @ 50 Kg
Pasir Semen (lokal)

3 1 M2 Lantai Keramik Ukuran 25 x 25 cm


HPS.PU- 2018
Ubin Keramik Ukuran 25 x 25
Semen Portland (PC) @ 50 Kg
Pasir Semen (lokal)
Semen Warna
X. PEKERJAAN PASANGAN KUSEN
1 1 Unit Pintu Double Panel cm
HPS.PU- 2018
Balok kayu Rahay (Bingkai 3 x 8 cm + les)
Papan kayu Rahay
Engsel 4" Kuningan (untuk pintu)
Kait angin 8"
Kunci tanam 2 slangh
Grendel besar
Paku Campur

2 1 Unit Pintu Panel 80 x 210 cm


HPS.PU- 2018
Papan kayu Rahay
Engsel 4" Kuningan (untuk pintu)
Kait angin
Kunci tanam (setara kuda terbang)
Grendel besar
Paku Campur

3 1 Unit Pintu double tripleks 70 x 210 cm, bingkai kayu 3,5 x 9 cm


HPS.PU- 2018
Balok kayu Rahay (Bingkai 3 x 8 cm + les)
Tripleks (1,22 x 2,44) cm - tebal 3 mm
Engsel 4" Kuningan (untuk pintu)
Kait angin
Kunci tanam 2 slangh
Grendel besar
Paku Campur

4 1 Unit Jendela 75 x 120 cm


HPS.PU- 2018
Balok kayu Rahay (Bingkai 3 x 8 cm + les)
Engsel jendela 3"
Kait angin
Grendel jendela
Paku Campur

No. Komponen

1 2

5 1 Unit Jendela Ungkit (75 x 115 cm), bingkai 3x8 cm, kaca polos 5 mm
HPS.PU- 2018
Balok kayu Rahay (Bingkai 3 x 8 cm + les)
Kaca polos tebal 5 mm
Tarikan jendela aluminium
Kait angin 6"
Grendel jendela
Paku Campur

6 1 M2 Jalusi Kusen, Kayu Kelas II


HPS.PU- 2018
Papan Kayu Kelas II (Kayu Rahay) tebal = 2 Cm
Paku Campuran

7 1 M2 Jalusi Kusen, Kayu Kelas II


HPS.PU- 2018
Papan Kayu Kelas II (Kayu Rahay) tebal = 2 Cm
Paku Campuran

XI. PEKERJAAN PENGECETAN


1 1 M2 Pelapisan Bidang Kayu Dengan Meny
Pt.T-38-2000-C
Cat meny kayu
Minyak Cat
Kuas

2 1 M2 Mengecat Penutup 2 Lapis Pada Kayu


Pt.T-38-2000-C
Cat tutup/cat kayu
Minyak Cat
Kuas

3 1 M2 Cat tembok biasa (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
HPS.PU- 2018
Plamur
Cat dasar
Cat penutup 2 kali

4 1 M2 Cat Plafond 2 Lapis dgn cat tembok menggunakan roll


Pt.T-38-2000-C
Plamur
Cat tembok
Kertas amplas (kayu)
Kuas roll
Kapek
SATUAN

Perkiraan
Volume Satuan Kuantitas Volume Satuan

3 4 5 3x5 7

- -

195.00 M3
M3 0.0120 2.34 M3
M3 0.0070 1.37 M3
KG 0.0200 3.90 KG

98.36 M3

32.79 M3

57.52 M3
M3 1.2000 69.03 M3

4.88 M3
M3 1.2000 5.86 M3

8.22 M3
M3 1.2000 9.86 M3

2.74 M3
KG 230.0000 631.12 KG
M3 0.6379 1.75 M3
M3 0.7607 2.09 M3
Liter 200.0000 548.80 Liter

15.90 M3
M3 0.2000 3.18 M3
KG 1.5000 23.85 KG
Liter 0.4000 6.36 Liter
KG 157.0000 2,496.30 KG
KG 2.2500 35.78 KG
KG 336.0000 5,342.40 KG
M3 0.5400 8.59 M3
M 3
0.8100 12.88 M3

16.74 M3
Buah 649.0000 10,864.26 Buah
Zak 4.3302 72.49 Zak
M3 0.4640 7.77 M3

7.75 M3
M3 0.2700 2.09 M3
KG 2.0000 15.50 KG
Liter 0.6000 4.65 Liter
KG 210.0000 1,627.50 KG
KG 3.0000 23.25 KG
KG 336.0000 2,604.00 KG
M3 0.5400 4.19 M3
M 3
0.8100 6.28 M3

14,107.50 KG
KG 1.1500 16,223.63 KG

6,039.00 KG
KG 1.1500 6,944.85 KG

635.93 KG
KG 1.1500 731.31 KG

2,838.00 KG
KG 1.1500 3,263.70 KG

1,593.85 KG
KG 1.1500 1,832.93 KG

Perkiraan
Volume Satuan Kuantitas Volume Satuan

3 4 5 3x5 7

1,474.86 KG
KG 1.1500 1,696.08 KG

266.89 0.47
Liter 1.0000 266.89 Liter
Liter 0.1000 26.69 Liter

5.05 M3
Zak 15.1500 76.51 Zak
M3 1.0821 5.46 M3
1.11 M'

M3 0.04 0.02 M3
M3 0.40 0.19 KG
Liter 0.20 0.09 Liter
M3 0.02 0.01 M3
Lbr 0.35 0.17 Lbr
Btg 2.00 0.95 Btg
KG 65.99 31.18 KG
KG 109.93 51.94 KG

Zak 11.36 5.37 Zak


M3 1.22 0.58 M3

5.05 M3
M3 0.3200 1.62 M3
KG 3.2000 16.16 KG
Liter 1.6000 8.08 Liter
KG 157.5000 795.38 KG
KG 2.2500 11.36 KG
KG 336.0000 1,696.80 KG
M3 0.5400 2.73 M3
M 3
0.8100 4.09 M3
M3 0.1200 0.61 M3
Lembar 2.8000 14.14 Lembar
Batang 32.0000 161.60 Batang

79.26 M2
Buah 70.0000 5,548.41 Buah
Zak 0.6166 48.87 Zak
M3 0.0440 3.49 M3

1,585.26 M2
KG 6.2400 9,892.02 KG
M3 0.0240 38.05 M3
8.88 M3
Zak 11.3625 100.90 Zak
M3 1.2174 10.81 M3

2.08 M3
M3 0.2500 0.52 M3
KG 3.0000 6.23 KG
Liter 1.2000 2.49 Liter
KG 200.0000 415.22 KG
KG 3.0000 6.23 KG
KG 323.0000 670.58 KG
M3 0.5200 1.08 M3
M 3
0.7800 1.62 M3
M3 0.1050 0.22 M3
Lembar 2.5000 5.19 Lembar
Batang 14.0000 29.07 Batang

- M3
Zak 11.3625 #VALUE! Zak
M3 1.2174 #VALUE! M3

8.00 M3
M3 0.3200 2.56 M3
KG 3.2000 25.60 KG
Liter 1.6000 12.80 Liter
KG 157.5000 1,260.00 KG
KG 2.2500 18.00 KG
KG 336.0000 2,688.00 KG
M3 0.5400 4.32 M3
M 3
0.8100 6.48 M3
M3 0.1200 0.96 M3
Lembar 2.8000 22.40 Lembar
Batang 32.0000 256.00 Batang
Perkiraan
Volume Satuan Kuantitas Volume Satuan

3 4 5 3x5 7

143.86 M2
Lembar 0.7000 100.70 Lembar
KG 0.0200 2.88 KG

6.60 M'
Lembar 0.4000 2.64 Lembar
KG 0.0600 0.40 KG
M3 0.0040 0.03 M3

186.00 M2
M3 0.0130 2.42 M3
KG 0.1200 22.32 KG

186.00 M2
Lembar 0.3750 69.75 Lembar
KG 0.0300 5.58 KG

3.00 Bh
Bh 1.0000 3.00 Zak

3.00 Bh
Buah 1.0000 3.00 Buah
KG 6.0000 18.00 KG
M3 0.0100 0.03 M3
1.00 Bh
M1 8.30 8.30
M 3
4.82 4.82
M3 2.61 2.61
M 3
0.09 0.09
M 3
0.16 0.16
LS 1.00 1.00
KG 12.35 12.35
KG 5.69 5.69
M3 0.07 0.07
M2 7.60 7.60
M3 0.07 0.07
M 2
10.08 10.08
M 2
10.08 10.08
LS 1.00 1.00
KG 36.64 36.64
M3 0.11 0.11
M 3.00 3.00
M 3.00 3.00
M 2.00 2.00
M3 0.27 0.27

18.00 M
M 1.2000 21.60 M

18.00 M
M 1.2000 21.60 M

4.00 Bh
Buah 1.2000 4.80 Buah
Buah 0.0250 0.10 Buah

1.00 Bh
Buah 1.0000 1.00 Buah
Buah 1.0000 1.00 Buah
Buah 2.0000 2.00 Buah
Batang 2.0000 2.00 Batang
Buah 0.1000 0.10 Buah
M3 0.0640 0.06 M3

4.00 Bh
M 7.0000 28.00 M
Buah 1.0000 4.00 Buah
Buah 1.0000 4.00 Buah
Dos 0.2000 0.80 Dos
Buah 0.1000 0.40 Buah
Dos 0.1000 0.40 Dos

Perkiraan
Volume Satuan Kuantitas Volume Satuan

3 4 5 3x5 7

13.00 Bh
Buah 1.0000 13.00 Buah
M 7.0000 91.00 M
Buah 1.0000 13.00 Buah
Buah 1.0000 13.00 Buah
Dos 0.2000 2.60 Dos
Buah 0.1000 1.30 Buah
Dos 0.1000 1.30 Dos

4.00 Bh
Buah 1.0000 4.00 Buah

5.00 Bh
Buah 1.0000 5.00 Buah
8.00 Bh
Buah 1.0000 8.00 Buah
M 3.0000 24.00 M
Dos 0.2000 1.60 Dos
Buah 0.1000 0.80 Buah

1.00 Bh
Buah 1.0000 1.00 Buah

188.76 M2
Buah 3.1000 585.16 Buah
KG 9.6000 1,812.10 KG
M3 0.0450 8.49 M3
KG 1.5000 283.14 KG

11.85 M2
Buah 11.8700 140.66 Buah
KG 10.0000 118.50 KG
M3 0.0450 0.53 M3

27.92 M2
Buah 20.0000 558.34 Buah
KG 8.1900 228.64 KG
M3 0.0450 1.26 M3
KG 3.2000 89.33 KG

2.00 Bh
M3 0.0570 0.11 M3
M3 0.0750 0.15 Buah
Buah 1.5000 3.00 Buah
Buah 1.0000 2.00 Buah
Buah 1.0000 2.00 Buah
Buah 1.0000 2.00 Buah
KG 0.2000 0.40 KG

5.00 Bh
M3 0.0750 0.38 M3
Buah 1.5000 7.50 Buah
Buah 1.0000 5.00 Buah
Buah 1.0000 5.00 Buah
Buah 1.0000 5.00 Buah
KG 0.2200 1.10 KG

3.00 Bh
M3 0.0640 0.19 M3
Lembar 1.8000 5.40 Lembar
Buah 1.5000 4.50 Buah
Buah 1.0000 3.00 Buah
Buah 1.0000 3.00 Buah
Buah 1.0000 3.00 Buah
KG 0.2000 0.60 KG

5.00 Bh
M3 0.0600 0.30 M3
Buah 2.0000 10.00 Buah
Buah 1.0000 5.00 Buah
Buah 1.0000 5.00 Buah
KG 0.8500 4.25 KG

Perkiraan
Volume Satuan Kuantitas Volume Satuan

3 4 5 3x5 7

2.00 Bh
M3 0.0300 0.06 M3
M 3
0.6200 1.24 M2
Buah 2.0000 4.00 Buah
Buah 2.0000 4.00 Buah
Buah 2.0000 4.00 Buah
KG 0.0650 0.13 KG

0.90 M2
M3 0.0600 0.05 M3
KG 0.1500 0.14 KG

4.19 M3
M3 0.0600 0.25 M3
KG 0.1500 0.63 KG

10.08 M2
KG 0.1700 1.71 KG
Liter 0.1000 1.01 Liter
Buah 0.0150 0.15 Buah

10.08 M3
KG 0.3000 3.03 KG
Liter 0.2000 2.02 Liter
Buah 0.0200 0.20 Buah

1,585.26 M2
KG 0.1000 158.53 KG
KG 0.1000 158.53 KG
KG 0.2600 412.17 KG

186.00 M2
KG 0.1000 18.60 KG
KG 0.4700 87.42 KG
Lembar 0.5000 93.00 Lembar
Buah 0.0100 1.86 Buah
Buah 0.0500 9.30 Buah
TOTAL KEBUTUHAN BAHAN
TUGAS BESAR : MENEJEMEN KONTRUKSI DAN ESTIMASI BIAYA
DIBUAT OLEH : ADRIAN RIADI PUTRA
NPM : 2016-22-201-002
JURUSAN : TEKNIK SIPIL
DIPERIKSA OLEH : HERMANSYAH
DISETUJUI OLEH : YANCE KAKERISSA, ST.,M.T

NO NAMA BAHAN / UPAH SAT Total bahan Harga Bahan Total (Rp)

a b c d e dxe
A BAHAN BAKAR DAN PENCAMPUR
1 Minyak Bekisting / Oli Bekas Liter 34.48 Rp. 907.00 Rp.
2 Solar Liter 266.89 Rp. 14,124.00 Rp.
3 Minyak Pelumas Liter 26.69 Rp. 35,407.00 Rp.
Rp.
B BAHAN PASIR, BATU & SEMEN
1 Pasir semen (lokal) M3 24.36 Rp. 747,550.00 Rp.
2 Pasir semen (import) M3 88.80 Rp. 1,158,994.00 Rp.
3 Tanah timbun biasa/urug M 3
71.63 Rp. 260,010.00 Rp.
4 Kerikil/batu pecah (import) M3 33.43 Rp. 1,162,930.00 Rp.
5 Batu Bata Merah Buah 16412.67 Rp. 1,340.00 Rp.
6 Semen Portland (PC) @ 50 Kg Zak 620.34 Rp. 98,030.00 Rp.
7 Semen Warna Zak 7.45 Rp. 110,080.00 Rp.
Rp.
C BAHAN KAYU,TRIPLEKS DLL
1 Balok Kayu Kelas II (Kayu Rahay) M3 3.084 Rp. 4,177,460.00 Rp.
2 Balok Kayu Kelas III (Kayu Bus) M3 2.34 Rp. 2,903,800.00 Rp.
3 Papan Kayu Kelas II (Kayu Rahay) t : 2 cm M 3
0.83 Rp. 4,177,460.00 Rp.
4 Papan Kayu Kelas III (Kayu Bus) t : 2-5 cm M3 11.38 Rp. 2,903,800.00 Rp.
5 Tripleks (1,22 x 2,44) cm - tebal 3 mm Lembar 75.15 Rp. 65,895.00 Rp.
6 Plywood - Multiplex (9 mm) Lembar 41.90 Rp. 453,750.00 Rp.
7 Kayu dolken Ø 8-10, L=4 M Btng 300.15 Rp. 16,990.00 Rp.
Rp.
D BAHAN BESI, PAKU DAN KAWAT
1 Besi Beton Dia.8 mm (SNI) Kg Rp. 13,987.00 Rp.
2 Besi Beton Dia.10 mm (SNI) Kg Rp. 13,945.00 Rp.
3 Kawat Beton Kg Rp. 25,976.00 Rp.
4 Paku Campur Kg Rp. 21,050.00 Rp.
5 Paku Triplek Kg Rp. 25,133.00 Rp.
6 Angker / Baut Kg Rp. 10,310.00 Rp.
Rp.
E BAHAN PENUTUP ATAP
1 Atap Allumunium Gelombang Lembar Rp. Rp.
2 Seng Plat BJLS 0,30 Lembar Rp. Rp.
Rp.
F BAHAN KERAMIK
1 Ubin Teralux Marmer Ukuran 60 x 60 cm Bh Rp. Rp.
2 Ubin Abu-abu Ukuran 30 x 30 Bh Rp. Rp.
3 Ubin Keramik Ukuran 25 x 25 Bh Rp. Rp.
Rp.
G BAHAN KACA
1 Kaca polos tebal 5 mm Rp. Rp.
Rp.
H BAHAN / ALAT PENGGANTUNG
1 Kunci Tanam (Setara Cap Kuda Terbang) Bh Rp. Rp.
2 Kunci Tanam - 2 Slaagh Bh Rp. Rp.
3 Engsel 4" Kuningan (untuk pintu) Bh Rp. Rp.
4 Engsel Biasa 3" (Untuk Jendela) Bh Rp. Rp.
5 Hak Angin / Kait Angin Bh Rp. Rp.
6 Grendel Besar / Kecil Bh Rp. Rp.
Rp.
I BAHAN ALUMUNIUM
1 WF 300.300.10.15 (Kolom) Kg Rp. Rp.
2 WF 400.200.8.13 (Balok Utama) Kg Rp. Rp.
3 WF 400.200.8.13 (Ringbalk) Kg Rp. Rp.
4 Plat Bondek Tebal 0,75 mm Rp. Rp.
5 WF 250.125.6.9 (Kontruksi Kuda-Kuda) Kg Rp. Rp.
6 CNP 100.50.5.7,5 Kg Rp. Rp.
Rp.

NO NAMA BAHAN / UPAH SAT Total bahan Harga Bahan Total (Rp)

a b c d e dxe
J BAHAN CAT
1 Amplas Kertas (Amplas Kayu) Lembar Rp. Rp.
2 Cat Meny Kayu Kg Rp. Rp.
3 Cat Kayu Kg Rp. Rp.
4 Minyak Cat / Thinner Kg Rp. Rp.
5 Cat Tembok Biasa (1 Klg @ 5 Kg) Kg Rp. Rp.
6 Plamur Tembok Zak Rp. Rp.
Rp.
K BAHAN LISTRIK DAN ELEKTRONIKA
1 Kabel Listrik NYM/NYA 3x2.5 mm Rol Rp. Rp.
2 Kabel Listrik NYM/NYA 2x1.5 mm Rol Rp. Rp.
3 Saklar Double - Tempel Bh Rp. Rp.
4 Saklar Tunggal / Engkel - Tempel Bh Rp. Rp.
5 Stop Kontak 1000 Watt - Tempel Bh Rp. Rp.
6 Vitting Lampu Bh Rp. Rp.
7 Lampu SL 23 VA Set Rp. Rp.
8 Lampu TL double 2 x 36 Watt Set Rp. Rp.
9 Klem Kabel Dos Rp. Rp.
10 Isolasi Listrik Bh Rp. Rp.
11 Sekrup Dus Rp. Rp.
12 Panil Distribusi Bh Rp. Rp.
Rp.
L BAHAN PIPA DAN SANITAIR
1 Closed Duduk Porselin Komplit Bh Rp. Rp.
2 Pipa PVC Dia. 3/4" - 4 M M Rp. Rp.
3 Pipa PVC Dia. 4" - 4 Meter (AW) M Rp. Rp.
4 Kran air Dia. 3/4" atau 1/2" Bh Rp. Rp.
5 Seal Tape Bh Rp. Rp.
6 Pompa Dragon Bh Rp. Rp.
7 Shock ulir Bh Rp. Rp.
8 L Bough 2" Bh Rp. Rp.
9 Pipa PVC dia 1" ( D ) Btg Rp. Rp.
10 Lem PVC Bh Rp. Rp.
Rp.
Total (Rp)

dxe

31,270
3,769,573.20
944,982
4,745,825

18,210,326
102,921,396
18,624,600
38,881,204.61
21,992,977.80
60,811,961.73
820,038.93
262,262,505

12,883,287
6,794,892
3,467,710
33,038,928
4,952,009
19,010,140
5,099,555
85,246,521

-
-
-
-
-
-
-
-
-

-
-
-
-

-
-

-
-
-
-
-
-
-

-
-
-
-
-
-
-

Total (Rp)

dxe

-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
Koef. Tg Kerja
No. URAIAN PEKERJAAN Per Satuan
Pekerjaan
I. PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi
Pekerja 0.1
Mandor 0.005
2 Pagar Sementara
Pekerja kayu 0.2
Tukang kayu 0.4
Kepala Tukang Kayu 0.02
Mandor 0.02
3 Pengukuran dan Pemasangan Bouwplank
Pekerja kayu 0.1
Tukang kayu 0.1
Kepala Tukang Kayu 0.01
Mandor 0.005
4 Papan Nama Proyek

II. PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi
Pekerja 0.9
Mandor 0.045
2 Urugan Tanah Kembali
Pekerja
Mandor
3 Urugan Tanah Peninggian Lantai
Pekerja 0.5
Mandor 0.05
4 Urugan Pasir Bawah Pondasi
Pekerja 0.3
Mandor 0.01
5 Urugan Pasir Bawah Lantai
Pekerja 0.3
Mandor 0.01

III. PEKERJAAN PONDASI BETON DAN PASANGAN


1 Lantai Kerja Tebal 7 cm
Pekerja pasir/batu 1.2
Tukang pasir/batu 0.2
Kepala tukang pasir/batu 0.02
Mandor pasir/batu 0.06
2 Pondasi Poer B. Bertulang
Pekerja 5.3
Tukang Batu 0.275
Tukang Kayu 1.3
Tukang Besi 1.05
Kepala Tukang 0.262
Mandor 0.265
3 Pas. Pondasi Menerus 1 Pc : 3 Ps
Pekerja pasir/batu 2.857
Tukang pasir/batu 1.286
Kepala tukang pasir/batu 0.429
Mandor pasir/batu 0.143
4 Sloof B.Bertulang 25 x 40 cm
Pekerja 5.65
Tukang Batu 0.275
Tukang Kayu 1.56
Tukang Besi 1.4
Kepala Tukang 0.323
Mandor 0.283

IV. PEKERJAAN BESI DAN ALUMMUNIUM


1 WF 300.300.10.15 (Kolom)
Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

2 WF 400.200.8.13 (Balok Utama)


Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

3 Plat Bondek Tebal 0,75 mm


Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

4 WF 400.200.8.13 (Ringbalk)
Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

5 WF 250.125.6.9 (Kontruksi Kuda-Kuda)


Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

6 CNP 100.50.5.7,5 (Gording)


Pekerja 0.06
Tukang besi 0.06
Kepala Tukang 0.006
Mandor 0.003

7 Perakitan Besi Baja


Pekerja 0.1
Tukang besi 0.1
Kepala Tukang 0.001
Mandor 0.005

V. PEKERJAAN COR
1 Cor Kolom Utama
Pekerja 16
Tukang pasir/batu 4.8
Kepala tukang 1.6
Mandor 1.6
2 Kolom Praktis 15 x 15 cm, B. Bertulang
3 Cor Plat Lantai Tebal 10 cm
Pekerja 5.3
Tukang Batu 0.275
Tukang Kayu 1.3
Tukang Besi 1.05
Kepala Tukang 0.265
Mandor 0.265
4 Pas. Dinding 1/2 Bata
Pekerja pasir/batu 0.014
Tukang pasir/batu 0.043
Kepala tukang pasir/batu 0.129
Mandor pasir/batu 0.286
5 Plesteran Tebal 15 mm
Pekerja pasir/batu 0.3
Tukang pasir/batu 0.15
Kepala tukang pasir/batu 0.015
Mandor pasir/batu 0.015
6 Cor Lantai Tebal 8 cm
Pekerja 16
Tukang pasir/batu 4.8
Kepala tukang 1.6
Mandor 1.6
7 Cor Tangga Beton B. Bertulang
Pekerja 5.6
Tukang Batu 0.35
Tukang Kayu 2.3
Tukang Besi 1.4
Kepala Tukang 0.405
Mandor 0.202
8 Cor Plat Dak
Pekerja 5.3
Tukang Batu 0.275
Tukang Kayu 1.3
Tukang Besi 1.05
Kepala Tukang 0.265
Mandor 0.265

VI. PEKERJAAN PASANGAN ATAP


1 Penutup Atap Alumunium Gelombang
Pekerja 0.12
Tukang Kayu 0.06
Kepala Tukang 0.006
Mandor 0.006
2 Nok Stuk Plat BJLS 0.20 mm
Pekerja 0.125
Tukang Kayu 0.25
Kepala Tukang 0.025
Mandor 0.006
3 Pas. Rangka Plafond Kayu 5/5 cm
Pekerja Kayu 0.17
Tukang Kayu 0.27
Kepala Tukang 0.027
Mandor 0.0085
4 Pas. Plafond Tripleks t : 3 mm
Pekerja Kayu 0.1
Tukang Kayu 0.1
Kepala Tukang 0.01
Mandor 0.005
VII. PEKERJAAN SANITASI DAN AIR
1 Bak Air
Pekerja pasir/batu 3
Tukang pasir/batu 4.5
Kepala tukang pasir/batu 0.9
Mandor pasir/batu 0.9
2 Pas. Closet Jongkok Porselin
Pekerja pasir/batu 1
Tukang pasir/batu 1.5
Kepala tukang pasir/batu 0.15
Mandor pasir/batu 0.16
3 Septictank uk. Pas. 1/2 Bata
4 Pipa PVC Tipe AW Dia. 3/4"
Pekerja 0.036
Tukang pipa 0.06
Kepala tukang 0.006
Mandor 0.0018
5 Pipa PVC Tipe AW Dia. 4"
Pekerja 0.081
Tukang pipa 0.135
Kepala tukang 0.135
Mandor 0.0041
6 Kran Air Dia. 3/4" atau 1/2"
Tukang pipa 0.1
Kepala tukang 0.01
7 Mesin Pompa

VIII. PEKERJAAN INSTALASI LISTRIK

IX. PEKERJAAN LANTAI


1 Pas. Lantai Keramik 60 x 60 cm
Pekerja 0.24
Tukang batu 0.12
Kepala tukang 0.012
Mandor 0.012
2 Pas. Lantai Keramik 30 x 30 cm
Pekerja 0.26
Tukang batu 0.13
Kepala tukang 0.013
Mandor 0.013
3 Pas. Lantai Keramik Uk. 25 x 25 cm
Pekerja 0.7
Tukang batu 0.35
Kepala tukang 0.035
Mandor 0.035

X. PEKERJAAN PASANGAN KUSEN


1 Pas. Pintu Double 1,2 x 2,10 (P1)
Pekerja kayu 0.85
Tukang kayu 2.6
Kepala tukang kayu 0.26
Mandor kayu 0.0425
2 Pas. Pintu Panel Kayu 80 x 210 (P2)
Pekerja kayu 2.2659
Tukang kayu 6.972
Kepala tukang kayu 0.6972
Mandor kayu 0.1133
3 Pas. Pintu 70 x 210 (P3)
Pekerja kayu 0.85
Tukang kayu 2.6
Kepala tukang kayu 0.26
Mandor kayu 0.0425
4 Pas. Jendela Ungkit 168 x 110 (J1)
Pekerja kayu 1
Tukang kayu 2
Kepala tukang kayu 1
Mandor kayu 0.5
5 Pas. Jendela Ungkkit 120 x 160 (J2)
Pekerja kayu 0.3
Tukang kayu 1.5
Kepala tukang kayu 0.15
Mandor kayu 0.15
6 Pasangan Ventilasi 50 x 60 (V1)
Pekerja Kayu 0.67
Tukang Kayu 2
Kepala Tukang 0.2
Mandor 0.335
7 Pasangan Ventilasi 30 x 45 (V2)
Pekerja Kayu 0.67
Tukang Kayu 2
Kepala Tukang 0.2
Mandor 0.335

XI. PENGERJAAN PENGECATAN


1 Cat Meny Kayu
Pekerja cat 0.075
Mandor cat 0.004
2 Cat Kilap Kayu
Pekerja cat 0.15
Tukang cat 0.15
Kepala tukang cat 0.015
Mandor cat 0.008
3 Cat Tembok Untuk Dinding
Pekerja cat 0.02
Tukang cat 0.063
Kepala tukang cat 0.0063
Mandor cat 0.0025
4 Cat Plafond
Pekerja cat 0.06
Tukang cat 0.04
Kepala tukang cat 0.004
Mandor cat 0.003

XII. PEKEKERJAAN FINISHING


Volume Kemam. Pekerjaan Jmlh Hari Utk Rencana Jmlh Orang
Pekerjaan Menyelesaikan Pek Menye Kes Hari Yang
Dalam 1 Hari Vol Pek(1 Org) Kerja Dibutuhkan

288.00
10 28.8 3 9.6
200 1.44 3 0.48
288.00
5 57.6
2.5 115.2
50 5.76
50 5.76
195.00
10 19.5 11 1.772727
10 19.5 11 1.772727
100 1.95 11 0.177273
200 0.975 11 0.088636

98.36
1.111 88.524 5 17.7048
22.222 4.4262 5 0.88524
0.333

57.52
2 28.761 2 14.38028
20 2.876 2 1.438028
4.88
3.333 1.465 4 0.366188
100 0.049 4 0.012206
8.22
3.333 2.465 2 1.232595
100 0.082 2 0.041087

2.74
0.833 3.293 2 1.6464
5 0.549 2 0.2744
50 0.055 2 0.02744
16.667 0.165 2 0.08232
15.90
0.189 84.270 15 5.618
3.636 4.373 15 0.2915
0.769 20.670 15 1.378
0.952 16.695 15 1.113
3.817 4.166 15 0.27772
3.774 4.214 15 0.2809
16.74
0.35 47.829 5 9.565714
0.778 21.523 5 4.304571
2.333 7.174 5 1.434857
7 2.391 5 0.478286
7.75
0.177 43.788 5 8.7575
3.636 2.131 5 0.42625
0.641 12.090 5 2.418
0.714 10.850 5 2.17
3.096 2.503 5 0.50065
3.534 2.193 5 0.43865

14,107.50
16.667 846.450 18 47.025
16.667 846.450 18 47.025
166.667 84.645 18 4.7025
333.333 42.323 18 2.35125

6,039.00
16.667 362.340 12 30.195
16.667 362.340 12 30.195
166.667 36.234 12 3.0195
333.333 18.117 12 1.50975

635.93
16.667 38.156 2 19.07775
16.667 38.156 2 19.07775
166.667 3.816 2 1.907775
333.333 1.908 2 0.953888

2,838.00
16.667 170.280 9 18.92
16.667 170.280 9 18.92
166.667 17.028 9 1.892
333.333 8.514 9 0.946

1,593.85
16.667 95.631 5 19.12624
16.667 95.631 5 19.12624
166.667 9.563 5 1.912624
333.333 4.782 5 0.956312

1,474.86
16.667 88.491 5 17.69826
16.667 88.491 5 17.69826
166.667 8.849 5 1.769826
333.333 4.425 5 0.884913

266.89
10 26.689 1 26.68913
10 26.689 1 26.68913
1000 0.267 1 0.266891
200 1.334 1 1.334457

36.75
0.0625 588.000 7 84
0.208 176.400 7 25.2
0.625 58.800 7 8.4
0.625 58.800 7 8.4

5.05
0.189 26.765 3 8.921667
3.636 1.389 3 0.462917
0.769 6.565 3 2.188333
0.952 5.303 3 1.7675
3.774 1.338 3 0.446083
3.774 1.338 3 0.446083
79.26
70 1.132 5 0.226466
23.33 3.397 5 0.679397
7.78 10.191 5 2.038191
3.5 22.647 5 4.529314
1585.26
3.333 475.578 9 52.842
6.667 237.789 9 26.421
66.667 23.779 9 2.6421
66.667 23.779 9 2.6421
8.88
0.0625 142.080 4 35.52
0.208 42.624 4 10.656
0.625 14.208 4 3.552
0.625 14.208 4 3.552
2.08
0.179 11.626 2 5.81308
2.857 0.727 2 0.363318
0.435 4.775 2 2.387515
0.714 2.907 2 1.45327
2.469 0.841 2 0.42041
4.950 0.419 2 0.209686
8.00
0.189 42.400 4 10.6
3.636 2.200 4 0.55
0.769 10.400 4 2.6
0.952 8.400 4 2.1
3.774 2.120 4 0.53
3.774 2.120 4 0.53

143.86
8.333 17.263 2 8.631396
16.667 8.631 2 4.315698
166.667 0.863 2 0.43157
166.667 0.863 2 0.43157
6.60
8.000 0.825 1 0.825
4.000 1.650 1 1.65
40.000 0.165 1 0.165
166.667 0.040 1 0.0396
186.00
5.882 31.620 4 7.905
3.704 50.220 4 12.555
37.037 5.022 4 1.2555
117.647 1.581 4 0.39525
186.00
10 18.600 2 9.3
10 18.600 2 9.3
100 1.860 2 0.93
200 0.930 2 0.465
#DIV/0!
#DIV/0!
3.00 #DIV/0!
0.333 9.000 1 9
0.222 13.500 1 13.5
1.111 2.700 1 2.7
1.111 2.700 1 2.7
3.00 #DIV/0!
1 3.000 1 3
1 4.500 1 4.5
7 0.450 1 0.45
6 0.480 1 0.48
#DIV/0!
18.00 #DIV/0!
28 0.648 3 0.216
17 1.080 3 0.36
167 0.108 3 0.036
556 0.032 3 0.0108
18.00 #DIV/0!
12 1.458 1 1.458
7 2.430 1 2.43
7 2.430 1 2.43
244 0.074 1 0.0738
4.00
10 0.400 1 0.4
100 0.040 1 0.04

188.76
4 45.302 6 7.5504
8 22.651 6 3.7752
83 2.265 6 0.37752
83 2.265 6 0.37752
11.85
4 3.081 1 3.081
8 1.541 1 1.5405
77 0.154 1 0.15405
77 0.154 1 0.15405
37.8338
1 26.484 2 13.24183
3 13.242 2 6.620915
29 1.324 2 0.662092
29 1.324 2 0.662092

2.00
1 1.700 1 1.7
0.38 5.200 1 5.2
4 0.520 1 0.52
24 0.085 1 0.085
5.00
0.44 11.330 4 2.832375
0.14 34.860 4 8.715
1 3.486 4 0.8715
9 0.567 4 0.141625
3.00
1 2.550 1 2.55
0.38 7.800 1 7.8
4 0.780 1 0.78
24 0.128 1 0.1275
5.00
1 5.000 2 2.5
1 10.000 2 5
1 5.000 2 2.5
2 2.500 2 1.25
2.00
3 0.600 1 0.6
1 3.000 1 3
7 0.300 1 0.3
7 0.300 1 0.3
0.90 #DIV/0!
1 0.603 1 0.603
1 1.800 1 1.8
5 0.180 1 0.18
3 0.302 1 0.3015
4.19 #DIV/0!
1 2.804 1 2.80395
1 8.370 1 8.37
5 0.837 1 0.837
3 1.402 1 1.401975
#DIV/0!
#DIV/0!
10.08 #DIV/0!
13 0.756 #DIV/0!
250 0.040 #DIV/0!
10.08 #DIV/0!
7 1.513 #DIV/0!
7 1.513 #DIV/0!
67 0.151 #DIV/0!
125 0.081 #DIV/0!
1,585.26 #DIV/0!
50 31.705 #DIV/0!
16 99.871 #DIV/0!
159 9.987 #DIV/0!
400 3.963 #DIV/0!
186.00 #DIV/0!
17 11.160 #DIV/0!
25 7.440 #DIV/0!
250 0.744 #DIV/0!
333 0.558 #DIV/0!
Jmlh Orang
Yang
Dibutuhkan

10
1

2
2
1
1
F
NO JENIS PEKERJAAN

I. PEKERJAAN PERSIAPAN

II. PEKERJAAN TANAH DAN PASIR

III. PEKERJAAN PONDASI BETON DAN PASANGAN

IV. PEKERJAAN BESI DAN ALUMMUNIUM

V. PEKERJAAN COR

VI. PEKERJAAN PASANGAN ATAP

VII. PEKERJAAN SANITASI DAN AIR

VIII. PEKERJAAN INSTALASI LISTRIK

IX PEKERJAAN LANTAI

X PEKERJAAN PASANGAN KUSEN

XI PENGERJAAN PENGECATAN

XII. PEKEKERJAAN FINISHING


Total
Rencana Fisik per Minggu
Rencana Fisik Komulatif

DiPERIKSA

HERMANSYAH
ASISTEN DOSEN
TIME SCHEDULE " KURVA S "
JUMLAH BULAN KE 1 BULAN KE 2
BOBOT
HARGA MINGGU KE MINGGU KE
(%)
( Rp ) 1 2 3 4 1 2
172,037,456.00 6.901 2.300 2.300 2.300

57,038,217.14 2.288 0.763 0.763 0.763

225690196.944 9.054 1.51 1.51

1,282,847,282.89 51.462 7.35

501,234,719.21 20.107

53350795.059 2.140

23,045,861.00 0.924

30,592,128.00 1.227

72,563,216.97 2.911

28,045,996.53 1.125

45,353,340.58 1.819

1,000,000.00 0.040
2,492,799,210.31 100
2.300 2.300 2.300 0.763 2.272 9.623
2.300 4.601 6.901 7.664 9.936 19.559
Chart Title
AS"
BULAN KE 2 BULAN KE 3 BULAN KE 4
MINGGU KE MINGGU KE MINGGU KE
3 4 1 2 3 4 1 2 3 4

1.51 1.51 1.51 1.51

7.35 7.35 7.35 7.35 7.35 7.35

5.03 5.03 5.03 5.03

0.713 0.713 0.713

0.308 0.308 0.308

0.409 0.409 0.409

0.582 0.582 0.582 0.582 0.582

0.563 0.563

0.455 0.455 0.455 0.455

0.040

9.443 9.443 9.443 14.470 14.545 14.827 6.912 0.864 0.455 0.040
29.002 38.445 47.888 62.357 76.902 91.729 98.641 99.505 99.960 100

Merauke, DESEMBER 2019


Dibuat Oleh

ADRIAN RIADI PUTRA


2016-22-201-002
Chart Title
KETERANGAN

100%

50%

0%

MBER 2019
120

BOBOT
NO URAIAN PEKERJAAN Bulan I
(%)
1 2 3
I. PEKERJAAN PERSIAPAN
1 Pagar Sementara 5.87 0.5337
2 Pembersihan Lokasi 0.20 0.10 0.10
100
3 Pengukuran dan Pemasangan Bouwplank 0.81
4 Papan Nama Proyek 0.02
II. PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi 0.61
2 Urugan Tanah Kembali 0.07
3 Urugan Tanah Peninggian Lantai 1.04
4 Urugan Pasir Bawah Pondasi 0.21
5 Urugan Pasir Bawah Lantai 0.36
III. PEKERJAAN PONDASI BETON DAN PASANGAN
1 Lantai Kerja Tebal 7 cm 0.29
2 Pondasi Poer B. Bertulang 4.69
3 Pas. Pondasi Menerus 1 Pc : 3 Ps 1.72

80
4 Sloof B.Bertulang 25 x 40 cm 2.34
IV. PEKERJAAN BESI DAN ALUMMUNIUM 80
1 WF 300.300.10.15 (Kolom) 29.44
2 WF 400.200.8.13 (Balok Utama) 10.96
3 Plat Bondek Tebal 0,75 mm 0.17
4 WF 400.200.8.13 (Ringbalk) 5.15
5 WF 250.125.6.9 (Kontruksi Kuda-Kuda) 2.89
6 CNP 100.50.5.7,5 (Gording) 2.78
7 Perakitan Besi Baja 0.07
V. PEKERJAAN COR
1 Cor Kolom Utama 5.23
2 Kolom Praktis 15 x 15 cm, B. Bertulang 0.01
3 Cor Plat Lantai Tebal 10 cm 0.67
4 Pas. Dinding 1/2 Bata 0.91
5 Plesteran Tebal 15 mm 7.28
6 Cor Lantai Tebal 8 cm 2.31 60
7 Cor Tangga Beton B. Bertulang 0.77
8 Cor Plat Dak 2.92
VI. PEKERJAAN PASANGAN ATAP
1 Penutup Atap Alumunium Gelombang 0.66
2 Nok Stuk Plat BJLS 0.20 mm 0.02
3 Pas. Rangka Plafond Kayu 5/5 cm 1.01
4 Pas. Plafond Tripleks t : 3 mm 0.45
VII. PEKERJAAN SANITASI DAN AIR
1 Bak Air 0.25
2 Pas. Closet Jongkok Porselin 0.08
3 Septictank uk. Pas. 1/2 Bata 0.41
4 Pipa PVC Tipe AW Dia. 3/4" 0.02
5 Pipa PVC Tipe AW Dia. 4" 0.11
40
6 Kran Air Dia. 3/4" atau 1/2" 0.01
7 Mesin Pompa 0.04
VIII. PEKERJAAN INSTALASI LISTRIK
1 Lampu tanam LED TS 0.07
2 Lampu XL 14 Watt 0.11
3 Saklar Ganda 0.05
4 Saklar Tunggal 0.06
5 Stop Kontak 0.04
6 Sekring Case 0.77
7 Biaya Penyambungan Listrik 0.20
IX. PEKERJAAN LANTAI
1 Pas. Lantai Keramik 60 x 60 cm 2.60
2 Pas. Lantai Keramik 30 x 30 cm 0.10
3 Pas. Lantai Keramik Uk. 25 x 25 cm 0.22 20
20
X. PEKERJAAN PASANGAN KUSEN
1 Pas. Pintu Double 1,2 x 2,10 (P1) 0.09
2 Pas. Pintu Panel Kayu 80 x 210 (P2) 0.44
3 Pas. Pintu 70 x 210 (P3) 0.14
4 Pas. Jendela Ungkit 168 x 110 (J1) 0.23
5 Pas. Jendela Ungkkit 120 x 160 (J2) 0.06
6 Pasangan Ventilasi 50 x 60 (V1) 0.03
7 Pasangan Ventilasi 30 x 45 (V2) 0.14
XI. PENGERJAAN PENGECATAN
1 Cat Meny Kayu 0.01
2 Cat Kilap Kayu 0.03
3 Cat Tembok Untuk Dinding 1.53
4 Cat Plafond 0.25
XII. PEKEKERJAAN FINISHING 0
1 2 3
1 Pembersihan Akhir 0.04
0.0995 0.0995 0.5337
0.0995 0.199 0.7327
4 5 6 7 8 9 10 11 12 13 14 15 16

0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337

0.1353 0.1353 0.1353


0.0201
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0.5337 0.5337 0.5538 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.5337 0.1353 0.1353 0.1353
1.2664 1.8001 2.3539 2.8876 3.4212 3.9549 4.4886 5.0223 5.556 6.0897 6.225 6.3603 6.4955
17 18 19 20 21 22 23 24 25 26 27 28 29

0.1353 0.1353 0.1353

0.1224 0.1224 0.1224 0.1224 0.1224

0.05 0.05 0.05 0.05

0.1458 0.1458
0.3128 0.3128
4 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

0.1353 0.1353 0.1353 0.1224 0.1224 0.1224 0.1224 0.1224 0.053 0.1988 0.1988 0.3658 0.3128
6.6308 6.7661 6.9014 7.0237 7.1461 7.2684 7.3908 7.5131 7.5661 7.7649 7.9638 8.3296 8.6424
30 31 32 33 34 35 36 37 38 39 40 41 42

0.034

0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128
7 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43

0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3128 0.3468 0.3128 0.3128 0.3128 0.3128
8.9552 9.2681 9.5809 9.8937 10.207 10.519 10.832 11.145 11.492 11.805 12.117 12.43 12.743
43 44 45 46 47 48 49 50 51 52 53 54 55

0.034
0.52 0.52

0.1784 0.1784

0.345 0.345 0.345 0.345 0.345


0.469 0.469 0.469 0.469 0.469

1.6354 1.6354 1.6354


41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

0.345 0.345 0.345 0.3789 0.345 0.469 0.469 0.469 0.9888 0.9888 1.8138 1.8138 1.6354
13.088 13.433 13.778 14.157 14.502 14.971 15.44 15.909 16.898 17.886 19.7 21.514 23.15
WAKTU PELAKSANA (HARI)

56 57 58 59 60 61 62 63 64 65 66 67 68
1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354
0.9132 0.9132 0.9132 0.9132
54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69

1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 1.6354 2.5486 2.5486 2.5486 2.5486
24.785 26.42 28.056 29.691 31.327 32.962 34.598 36.233 37.869 40.417 42.966 45.514 48.063
69 70 71 72 73 74 75 76 77 78 79 80 81
1.6354 1.6354
0.9132 0.9132 0.9132 0.9132 0.9132 0.9132 0.9132 0.9132
0.0865 0.0865
0.5722 0.5722 0.5722 0.5722 0.5722 0.5722
0.5784

0.7475 0.7475 0.7475 0.7475 0.7475 0.7475 0.7475


0.0088
67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 8

2.5486 2.5486 0.9132 0.9132 0.9132 0.9132 1.7472 2.3193 1.3196 1.3196 1.3196 1.3196 1.9068
50.612 53.16 54.073 54.987 55.9 56.813 58.56 60.879 62.199 63.519 64.838 66.158 68.065
82 83 84 85 86 87 88 89 90 91 92 93 94
0.5722 0.5722 0.5722
0.5784 0.5784 0.5784 0.5784
0.5563 0.5563 0.5563 0.5563 0.5563
0.07

0.224 0.224 0.224


0.1819 0.1819 0.1819 0.1819 0.1819
0.8089 0.8089 0.8089 0.8089 0.8089

0.07
0.11
0.05
0.06
0.04
0.26 0.26 0.26
0.20

0.433 0.433 0.433


0.09

80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96

1.3747 1.3747 1.3747 1.3167 0.7383 0.7383 0.8059 0.9182 0.959 1.0643 1.4973 1.4973 1.5304
69.439 70.814 72.189 73.505 74.244 74.982 75.788 76.706 77.665 78.729 80.227 81.724 83.254
95 96 97 98 99 100 101 102 103 104 105 106 107
0.8089 0.8089 0.8089 0.8089
0.5783 0.5783 0.5783 0.5783
0.3844 0.3844
0.7305 0.7305 0.7305 0.7305

0.3306 0.3306
0.0214
0.2525 0.2525 0.2525 0.2525
0.2238 0.2238

0.25
0.08
0.14 0.14

0.433 0.433 0.433


0.10
0.1087 0.1087
0.11 0.11 0.11 0.11
0.14
0.11 0.11
0.06
0.03
0.14

93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109

1.3526 1.3526 1.3526 1.5938 1.1611 1.1313 1.6965 1.0418 1.0122 1.5029 0.8546 0.4452 0.1379
84.607 85.96 87.312 88.906 90 91 92.696 93.738 94.75 96.253 97.108 97.553 97.691
108 109 110 111 112 113 114 115 116 117 118 119 120
0.14
0.02
0.11
0.01
0.04
0.01
0.03
0.1914 0.1914 0.1914 0.1914 0.1914 0.1914 0.1914 0.1914
0.124 0.124

106 107 108 109 110 111 112 113 114 115 116 117 118 119 120
0.02 0.02
0.2 0.3025 0.2391 0.1914 0.1914 0.1914 0.1914 0.1914 0.1914 0.124 0.124 0.0201 0.0201
97.8 98.102 98.342 98.533 98.724 98.916 99.2 99.5 99.6 99.724 99.848 99.868 100
Minggu VII
119 120
Minggu VIII

Anda mungkin juga menyukai