Anda di halaman 1dari 49

BACK UP DATA

NO. URAIAN PEKERJAAN PERHITUNGAN VOLUME

RUMAH TINGGAL TYPE 45 M2


1 PEMBUATAN BARAK KERJA Panjang = 4 m
Lebar = 3 m

VOLUME = 4 x 3 = 12 m2

2 PEMBERSIHAN DAN PERATAAN Panjang = 6 m


Lebar = 7.5 m
Luas bangunan = 6 x 7.5 = 45 m2
Panjang = 10 m
Lebar = 15 m
Luas Lapangan = 10 x 15 = 150 m2

VOLUME TOTAL = 45 + 150 = 195 m2

3 PENGUKURAN DAN PEMASANGAN Panjang = 9.5 + 9.5 + 8 + 8


BOWPLANK = 35 M

4 GALIAN TANAH PONDASI Pondasi Menerus


Panjang Pondasi =
Datar = 6.15 + 6.15 + 6.15 + 1.6 + 2.23
= 22.28 m

Vertikal = 6.3 + 2.8 + 3.9 + 1.43 + 0.95


+ 6.3
= 21.68 m
Dikurangin pertemuan
Jumlah pertemuan = 15 bh
Lebar rata rata Pondasi = 80 cm
Panjang pertemuan = 18 x 0.8 = 14.4 m

Panjang Total = 22.28 + 21.68 - 14.4 = 29.56 m


Lebar = 0.8 m
Dalam = 0.6 m
Volume = 14.189 m3

5 URUGAN TANAH KEMBALI 1/3 Galian Pondasi = 14.19 / 3 = 4.73 m3

6 URUGAN PASIR DI BAWAH Pondasi Menerus


PONDASI Panjang = 29.56 m
Lebar = 80 cm
Tebal = 5 cm
Volume = 29.56 x 0.8 x 0.05 = 1.1824 m3

7 URUGAN PASIR DI BAWAH Tebal = 5 cm


LANTAI Luas 1 = 2.85 x 5.85 = 16.67 m2
Luas 2 = 2.85 x 2.6 = 7.41 m2
Luas 3 = 2.15 x 1.43 = 3.07 m2
Luas 4 = 3 x 1.1 = 3.30 m2
Luas 5 = 2.85 x 1.85 = 5.27 m2
Jumlah Luas Lantai = 35.7 m2

Volume = 0.05 x 35.73 = 1.7865 m3

8 URUGAN TANAH PENINGGIAN LANTAI


Tinggi Timbunan = 0.4 m
Luas 1 = 2.85 x 5.85 = 16.67 m2
Luas 2 = 2.85 x 2.6 = 7.41 m2
Luas 3 = 2.15 x 1.43 = 3.07 m2
Luas 4 = 3 x 1.1 = 3.30 m2
Luas 5 = 2.85 x 1.85 = 5.27 m2
Jumlah Luas Lantai = 35.7 m2

Volume = 0.4 x 35.73 = 14.292 m3

9 COR BETON LANTAI RUMAH Tebal = 5 cm


Tebal = 5 cm Luas 1 = 2.85 x 5.85 = 16.67 m2
Luas 2 = 2.85 x 2.6 = 7.41 m2
Luas 3 = 2.15 x 1.43 = 3.07 m2
Luas 4 = 3 x 1.1 = 3.30 m2
Luas 5 = 2.85 x 1.85 = 5.27 m2
Jumlah Luas Lantai = 35.7 m2

Volume = 0.05 x 35.73 = 1.7865 m3

10 PONDASI MENERUS Pondasi Menerus


Panjang Pondasi =
Datar = 6.15 + 6.15 + 6.15 + 1.6 + 2.23
= 22.28 m

Vertikal = 6.3 + 2.8 + 3.9 + 1.43 + 0.95


+ 6.3
= 21.68 m
= 21.68 m

Dikurangin pertemuan
Jumlah pertemuan = 15 bh
Lebar rata rata Pondasi = 50 cm
Panjang pertemuan = 18 x 0.5 = 9 m

Panjang Total = 22.28 + 21.68 - 9 = 34.96 m

Lebar atas = 30 cm Rata2 = 30 + 70 / 2


Lebar Bawah = 70 cm = 50 cm
Dalam = 70 cm
Volume = 34.96 x 0.5 x 0.7 = 12.236 m3

11 SLOOF 15 x 20 - Beton Panjang Sloof =


Datar = 6.15 + 6.15 + 1.6 + 3.15 + 3.15
= 20.2 m

Vertikal = 6.15 + 6.15 + 7.58 + 1.4 + 1.58


= 22.86 m

Dikurangin pertemuan
Pertemuan T
Jumlah pertemuan = 11 bh
Lebar rata rata Pondasi = 17.5 cm
Panjang pertemuan = 11 x 0.175 / 2 = 0.9625 m

Panjang Total = 20.2 + 22.86 - 0.175 - 0.9625


= 41.923 m
Tinggi = 20 cm
Lebar = 15 bh

Volume = 41.923 x 0.2 x 0.15 = 1.2577 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 82.815 Kg/m3 Volume Total= 104.15 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 31.258 Kg/m3 Volume Total= 39.312 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 16.769 m2


12 KOLOM 15 X 15
- Beton Tinggi Kolom = 375 cm
Panjg = 15 cm
Lebar = 15 cm
Jumlah = 8 bh
Volume = 3.75 x 0.15 x 0.15 x 8 = 0.675 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 110.37 Kg/m3 Volume Total= 74.5 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 35.165 Kg/m3 Volume Total= 23.736 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 9 m2

KOLOM 15 X 15
- Beton Tinggi Kolom = 300 cm
Panjg = 15 cm
Lebar = 15 cm
Jumlah = 6 bh
Volume = 3 x 0.15 x 0.15 x 6 = 0.405 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 110.37 Kg/m3 Volume Total= 44.7 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 35.165 Kg/m3 Volume Total= 14.242 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 5.4 m2

13 KOLOM 15 X 30
- Beton Tinggi Kolom = 315 cm
Panjg = 15 cm
Lebar = 30 cm
Jumlah = 3 bh
Volume = 3.15 x 0.15 x 0.3 x 3 = 0.4253 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 82.89 Kg/m3 Volume Total= 35.249 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 27.35 Kg/m3 Volume Total= 11.631 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 5.67 m2

14 RINGBALK 15 x 15 - Beton Panjang Ringbalk =


Datar = 3.15 + 3.15 + 3.15
= 9.45 m

Vertikal = 6.15 + 6.15 +


= 12.3 m
Dikurangin pertemuan
Pertemuan +
Jumlah pertemuan = 0 bh
Lebar rata rata Pondasi = 15 cm
Panjang pertemuan = 0 x 0.15 = 0 m
Pertemuan T
Jumlah pertemuan = 2 bh
Lebar rata rata Pondasi = 15 cm
Panjang pertemuan = 2 x 0.15 / 2 = 0.15 m

Panjang Total = 9.45 + 12.3 - 0 - 0.15


= 21.6 m
Tinggi = 15 cm
Lebar = 15 bh

Volume = 21.6 x 0.15 x 0.15 = 0.486 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 110.37 Kg/m3 Volume Total= 53.64 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 35.165 Kg/m3 Volume Total= 17.09 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 6.48 m2

RINGBALK 15 x 15 - Beton Panjang Ringbalk =


Datar = 3.15 + 3.15 + 3.15
= 9.45 m

Vertikal = 6.15 + 6.15 + 1.4 + 1.5 + 6


= 21.2 m
Dikurangin pertemuan
Pertemuan +
Jumlah pertemuan = 1 bh
Lebar rata rata Pondasi = 15 cm
Panjang pertemuan = 1 x 0.15 = 0.15 m
Pertemuan T
Jumlah pertemuan = 6 bh
Lebar rata rata Pondasi = 15 cm
Panjang pertemuan = 6 x 0.15 / 2 = 0.45 m

Panjang Total = 9.45 + 21.2 - 0.15 - 0.45


= 30.05 m
Tinggi = 15 cm
Lebar = 15 bh

Volume = 30.05 x 0.15 x 0.15 = 0.6761 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 0 Kg/m3 Volume Total= 0 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 0 Kg/m3 Volume Total= 0 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 9.015 m2

15 BALOK DAK 15 x 20 - Beton Panjang Ringbalk =


Datar = 4.16
= 4.16

Vertikal = 2.86
= 2.86 m
Pertemuan T
Jumlah pertemuan = 3 bh
Lebar rata rata Pondasi = 15 cm
Panjang pertemuan = 3 x 0.15 / 2 = 0.225 m

Panjang Total = 4.16 + 2.86 - 0.225


= 6.795 m
Tinggi = 15 cm
Lebar = 15 bh

Volume = 6.795 x 0.15 x 0.15 = 0.1529 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 110.37 Kg/m3 Volume Total= 16.874 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 35.165 Kg/m3 Volume Total= 5.3763 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 2.0385 m2

16 RING BALK MANUMATA


- Beton Panjang Balok =
Datar = 6.15 + 3.39 + 3.39 + 3.55 + 2.98

= 19.46 m

Panjang Total = 19.46 + 0


= 19.46 m
Tinggi = 15 cm
Lebar = 15 bh

Volume = 19.46 x 0.15 x 0.15 = 0.4379 m3

- Besi Tulangan dia. 10mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 110.37 Kg/m3 Volume Total= 48.326 m3

- Besi Tulangan dia. 6mm Berat besi dia. 6 mm = 0.22 kg/m'


Volume = 35.165 Kg/m3 Volume Total= 15.397 m3

- Begesting Volume = 13.333 m2/m3 Volume Tota 5.838 m2

17 DAK BETON TEBAL 10 CM


- Beton Tebal = 10 cm
Luas 1 = 1.73 x 2.45 = 4.2385 m2
Jumlah = 4.2385 m2

Volume = 4.2385 x 0.1 = 0.4239 m3

- Besi Tulangan dia. 10 mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 124 Kg/m3 Volume Total= 52.557 Kg

- Begesting Volume = 10 m2/m3 Volume Tota 4.2385 m2

18 PLAT MEJA BETON


- Beton Tebal = 10 cm
Luas 1 = 2.85 x 0.5 = 1.425 m2
Volume = 0.1 x 1.425 = 0.1425 m3

- Besi Tulangan dia. 10 mm Berat besi dia. 10 mm = 0.62 kg/m'


Volume = 93 Kg/m3 = 13.253 Kg

- Begesting Volume = 10 m2/m3 = 1.425 m2

- Dudukan Pas. Bata Tinggi = 75 cm


Lebar = 60 cm
Tebal = 10 cm
Jumlah = 2 Bh
Volume = 0.75 x 0.6 x 0.1 x 2
= 0.09 m3
19 PAS. BATA RINGAN DINDING Tinggi Dinding = 3.6 m
Panjang Dinding = = 19.75 m
Dikurangi
- Kolom 15/15 = 8 x 0.15 = 1.2 m
= 18.55 m
Luas Bruto = 3.6 x 18.55 = 66.78 m2

Dikurangi :
Pintu PJ1 1 x 2.1 x 1.45 = 3.045 m2
Pintu P3 2 x 0.8 x 2.1 = 3.36 m2
Ventilasi V1 6 x 0.25 x 0.25 = 0.375 m2
Jumlah = 6.78 m2

TOTAL Volume Dinding = 66.78 - 6.78 = 60 m2

PAS. BATA RINGAN DINDING Tinggi Dinding = 2.85 m


Panjang Dinding = = 20.15 m
Dikurangi
- Kolom 15/15 = 10 x 0.15 = 1.5 m
= 18.65 m
Luas Bruto = 2.85 x 18.65 = 53.153 m2

Dikurangi :
p1 2 x 0.9 x 2.1 = 3.78 m2
Pintu P2 1 x 0.8 x 2.1 = 1.68 m2
Jendel J1 2 x 1.1 x 1.6 = 3.52 m2
Ventilasi V1 3 x 0.25 x 0.25 = 0.1875 m2
Jumlah = 9.1675 m2

TOTAL Volume Dinding = 53.153 - 9.1675 = 43.985 m2

20 PAS. BATA RINGAN MANUMATA Panjg = 6.15 m


Tinggi = 0.52 cm
Volume = 3.075 x 0.0052 = 0.016 m2

4.3973
Volume total = 4.4132 m2

21 PLESTERAN DINDING Volume Total = ### M2

21 Pintu Jendela PJ1 Jumlah = 1 Unit

22 Pintu P2 Jumlah = 2 Unit

23 Pintu P3 Jumlah = 1 Unit

24 Jendela J1 Jumlah = 2 Unit

25 Jendela J2 Jumlah = 2 Unit

26 Ventilasi V1 Jumlah = 9 Unit

27 Pas. Kusen Pintu Dan Jendela 5/10


Luasan Pintu (PJ1) = (0.8 + 2.1 + 2.1 + 1 + 1 + 1.6 + 1.6 + 0.2 + 0.2 = 12.2 M
Luasan Pintu (P2) = (0.8 + 2.1 + 2.1 + 0.25 + 0.25 +0.8 + 0.8) x 2 = 14.2 M
Luasan Pintu ( P3) = (0.7 + 2.1 + 2.1 ) x 1 = 6.8 M
Luasan Jendela 2 ( P4) = (0.6+ 1.6 + 1.6 ) x 1 = 4.9 M
Luasan Jendela ( J1) = (0.5 + 0.5+ 1.6 + 1.6 + 0.25 + 0.25 + 0.5 + 0.5) = 11.4 M
Luasan Ventilasi ( V1) = (0.3 + 0.3 + 0.15 + 0.15 ) x 9 = 8.1 M
Luasan Jendelai Atas Dak = (0.35 + 0.35 + 0.35 + 0.35 + 1.45 + 1.45 + 1.45 = 5.75 M
Total = 63.35 M
Dibagi 4 = 15.838 Btg
Volume = 0.3168 M3
28 Pasang Kuda-kuda dan ikatan angin ky kls II, 5/10
- Kuda - kuda Kuda - kuda , Ukuran 5/10 cm
Kaki Kuda-Kuda 4 x 2 = 8 m
Balok Gapit= 6.81 x 2 = 13.62 m
Balok Skor= 2.1 x 2 = 4.2 m
Balok Sokong= 1.21 x 2 = 2.42 m
Tiang Raja= = 1.65 m
Panjang Total = 29.89 m
dibagi 4 7.4725dibulatkan 8 Btg
Jumlah Kuda-kuda= 2
Jumlah Total Kayu= 16 Btg
Balok angin= 4 Btg
Total Kebutuhan Kayu= 20 Btg
1 kubik kayu 5/10 cm
1/0.05/0.10/4 = 50 Btg
0.4 dibulatk 0.4 m3

Pasang Kuda-kuda dan ikatan angin ky kls II, 5/10


- Kuda - kuda Kuda - kuda , Ukuran 5/10 cm
Kaki Kuda-Kuda 3.86 x 2 = 7.72 m
Balok Gapit= 6.56 x 2 = 13.12 m
Balok Skor= 2.1 x 2 = 4.2 m
Balok Sokong= 1.21 x 2 = 2.42 m
Tiang Raja= = 1.91 m
Panjang Total = 29.37 m
dibagi 4 7.3425dibulatkan 8 Btg
Jumlah Kuda-kuda= 2
Jumlah Total Kayu= 16 Btg
Balok angin= 4 Btg
Total Kebutuhan Kayu= 20 Btg
1 kubik kayu 5/10 cm
1/0.05/0.10/4 = 50 Btg
0.4 dibulatk 0.4 m3

29 Pasang Gording ky kls II, 4/8


Gording Kuda - Kuda , kayu 5/10 cm
Panjang = 3.5 m
Overlap = 0.25 x 2 = 0.5 m
Total panjang = 3.5 + 0.5 = 4m
Jumlah gording = 24 batang
Panjang Total 96 m dibagi 4 24 dibulatk 24 Btg
1 kubik Kayu 4/8 78.125 btg
Volume Gording = 0.3072 m3

30 Pasang Lisplank kayu klas I, 2/20 Panjang = 3.5 + 3.5 + 3.65 + 3.65 + 3.76
+ 3.76 + 3.76 + 3.76
= 29.34 m
papan 1/2 14.67 m
Total panjang= 44.01 m
31 Pasang Nok lapis seng plat Panjang = 3.53 + 3.53
= 7.06 m

32 Pasang atap BJLS 0.20 Atap 1


Panjang = 3.5 m
Lebar = 4.05 m
Jml bidang = 2 bidang
Luas = 3.5 x 4.05 x 2 = 28.35 m2

Atap 2
Panjang = 4.19 m
Lebar = 3.5 m
Jml bidang = 2 bidang
Luas = 4.19 x 3.5 x 2 = 29.33 m2

TOTAL Volume = 28.35 + 29.33 = 57.68 m2


33 KERAMIK 60 X 60 cm
Luas 1 = 2.85 x 5.85 = 16.67 m2
Luas 2 = 2.85 x 2.6 = 7.41 m2
Luas 3 = 2.15 x 1.43 = 3.07 m2
Luas 4 = 3 x 1.1 = 3.30 m2
Luas 4 = 2.85 x 1.85 5.27 m3
Jumlah Luas Lantai = 35.7 m2

34 KERAMIK KM/WC 25 x 25 cm
Luas 1 = 1.25 x 1.75 = 2.19 m2
Jumlah Luas Lantai = 2.19 m2

35 KERAMIK MEJA BETON 30 x 30 cm


Luas 1 = 2 x 0.5 = 1 m2
Jumlah = 2 x 0.6 = 1 m2

36 KERAMIK DINDING KM/WC 25 x 25


Luas 1 = 1.25 + 1.25 x 2.00 x 1.75 = 8.75 m2
Jumlah Luas Dinding bruto = 8.8 m2
Dikurangi
Luas P3 = 0.8 x 1.5 x 1 = 1.20 m2
TOTAL Jumlah = 7.55 m2
37 PLAFOND TRIPLEKS 5 MM
Luas 1 = 2.85 x 5.85 = 16.67 m2
Luas 2 = 2.85 x 2.6 = 7.41 m2
Luas 3 = 2.15 x 1.43 = 3.07 m2
Luas 4 = 3 x 1.1 = 3.30 m2
Luas 7 = 1.35 x 1.35 = 1.82 m2
Luas 8 = 2.85 x 0.5 = 1.43 m2
Luas 9 = 2.85 x 0.5 = 1.43 m2
Luas 10 = 3.15 x 0.5 = 1.58 m2
Luas 11 = 3.15 x 0.5 = 1.58 m2
Luas 12 = 4.02 x 0.5 = 2.01 m2
Luas 13 = 4.02 x 0.5 = 2.01 m2
Luas 14 = 4.02 x 0.5 = 2.01 m2
Luas 15 = 4.02 x 0.5 = 2.01 m2
Jumlah Luas Lantai = 46.3 m2

38 Pas. RANGKA PLAFOND Volume 46.3 m2

39 Pas. Lampu LED 24 Watt = 5 Titik

40 Pas. Lampu LED 14 Watt = 1 Titik

41 Pas. Stop Kontak = 5 Titik

42 Pas. Saklar Ganda = 4 Titik

43 Pas. Saklar Tunggal = 1 Titik

44 Pasang MCB Box = 1 Unit

45 Pasangan kloset duduk porselin = 1 Bh

46 Pasangan wastafel = 1 Bh

47 Pasangan instalasi air bersih, pipa PVC 3/4"- AW dgn Acc = 8 M'

48 Pasangan instalasi air kotor dan air hujan, pipa PVC 2"- = 5 M'

49 Pasangan instalasi air kotor ke septicktank, pipa PVC 4"- = 3 M'

50 Pasangan kran air 3/4" = 2 Bh


51 Pengadaan dan pemasangan pompa = 1 Bh

52 Bak Mandi = 1 Bh

53 Septictank = 1 Unit

54 Pasang Floor drain = 1 Bh

55 CAT TEMBOK Volume Mengikuti Volume Plesteran= 128.83 m2

56 CAT WATER PROOF Luas Dak Beton = 4.2385 m2

57 CAT PLAFOND Luas Plafond Plafond = 46.3 m2

58 CAT MENY KAYU


Ukuran Sisi Kayu 5/10 = 0.05 + 0.05 + 0.1 = 0.2 M
Volume Listplank = 44.0 M
Volume PJ1 = 12.2 M
Volume P2 = 14.2 M
Volume P3 = 6.8 M
Volume P4 = 4.9 M
Volume J1 = 11.4 M
Volume V1 = 8.1 M
Volume Ventilasi atas dak = 5.8 M
Volume total = 107.4 M
Total volume yg dicat = 21.5 M2

59 CAT KILAP KAYU Volume cat kilap mengikuti cat meny = 21.5 M2

60 Pek. FINISHING DAN PEMBERSIHAN AKHIR = 1 Ls

Kepi, De
Mengetahui, Diperiksa oleh, Di Hit
PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontrakto
( PPTK ) CV. JASA KONSULTAN PT. KALI K

dr. GIOVANNY TANUDJAJA Ir. ARIFIN KURNIAWAN AGNES A


NIP. 19780825 200801 1 024 Direktur

Mengetahui/Menyetujui,
PEJABAT PEMBUAT KOMITMEN (PPK)
DINAS KESEHATAN KABUPATEN MAPPI

SILFESTER SIKTEUBUN, SIP


NIP. 19640506 198603 1 020
ACK UP DATA
VOLUME SAT.

12.00 M2

195.00 M2

35.00 M

14.19 M3

4.73 M3

1.18 M3

1.79 M3
14.29 M3

1.79 M3

12.24 M3

1.26 M3

104.15 Kg

39.31 Kg

16.77 M2
0.68 M3

74.50 Kg

23.74 Kg

9.00 M2

0.41 M3

44.70 Kg

14.24 Kg

5.40 M2

0.43 M3

35.25 Kg

11.63 Kg

5.67 M2
0.49 M3

53.64 Kg

17.09 Kg

6.48 M2

0.68 M3

- Kg

- Kg

9.02 M2
0.15 M3

16.87 Kg

5.38 Kg

2.04 M2

0.88 M3

96.65 Kg

30.79 Kg

11.68 M2

0.42 M3

52.56 Kg

4.24 M2

0.14 M3

13.25 Kg

1.43 M2

0.09 M3
60.00 M2

43.99 M2

8.83 M2

128.83 M2

1.00 Unit

2.00 Unit

1.00 Unit

1.00 Unit

2.00 Unit

9.00 Unit

0.32 M3
0.4 M3

0.4 M3

0.3072 M3

44.01 M

7.06 M
57.68 M2

35.73 M2

2.19 M2

1.00 M2

7.55 M2

46.32 M2

46.32 M2

5.00 Titik

1.00 Titik

5.00 Titik

4.00 Titik

1.00 Titik

1.00 Unit

1.00 Bh

1.00 Bh

8.00 M'

5.00 M'

3.00 M'

2.00 Bh
1.00 Bh

1.00 Bh

1.00 Unit

1.00 Bh

128.83 M2

4.24 M2

46.32 M2

21.47 M2

21.47 M2

1.00 Ls

Kepi, Desember 2020


Di Hitung oleh,
Kontraktor Pelaksana
PT. KALI KORA INDAH

AGNES ANASTASIA
Direktris

engetahui/Menyetujui,
PEMBUAT KOMITMEN (PPK)
EHATAN KABUPATEN MAPPI

STER SIKTEUBUN, SIP


19640506 198603 1 020
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL TYPE 45 M2


LOKASI PEKERJAAN : Gg. SEHATI KALIWEDA 2
KABUPATEN : MERAUKE
TAHUN : 2022

HARGA
No. URAIAN / JENIS PEKERJAAN SAT. VOL. JUMLAH HARGA
SATUAN

I PEKERJAAN PENDAHULUAN
1 Pembuatan Camp Darurat Konstruksi Kayu M2 12.000 1,068,219.00 12,818,628.00
2 Pembersihan Lokasi Dan Pertaan M2 195.000 20,309.00 3,960,255.00
3 Pengukuran dan Pemasangan Bouwplank M' 35.000 111,402.00 3,899,070.00
Sub Jumlah 20,677,953.00

II PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi M3 14.189 182,781.00 2,593,443.05
2 Urugan Tanah Kembali M3 4.730 70,066.00 331,384.15
3 Urugan Pasir Bawah Lantai, t=5 cm M3 1.786 1,111,856.00 1,986,302.95
4 Urugan Tanah Peninggian Lantai M3 14.292 474,301.00 6,778,615.03
Sub Jumlah 11,689,745.19

III PEKERJAAN PONDASI DAN STRUKTUR BETON


1 Cor Beton Lantai Rumah T : 5 cm M3 1.786 3,863,492.00 6,902,031.87
2 Pasangan Pondasi Menerus Bata, 1 Pc : 5 Ps M3 12.236 2,965,241.00 36,282,688.88
3 Sloof Beton Bertulang 15/20 cm ###
- Beton mutu f'c=21,7 Mpa (K 250) M3 1.258 3,058,615.00 3,846,743.62
- Besi beton tulangan polos Ø10 mm Kg 104.155 20,946.00 2,181,629.42
- Besi beton tulangan polos Ø6 mm Kg 39.312 21,760.00
- Bekesting Kayu Kelas III M2 16.769 334,039.00 5,601,499.99
4 Kolom Beton Bertulang 15/15 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.675 3,058,615.00 2,064,565.13
- Besi beton tulangan polos Ø10 mm Kg 74.500 20,946.00 1,560,486.22
- Besi beton tulangan polos Ø6 mm Kg 23.736 21,760.00 516,500.58
- Bekesting Kayu Kelas III M2 9.000 672,273.00 6,050,457.00
5 Kolom Beton Bertulang 15/30 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.425 3,058,615.00 1,300,676.03
- Besi beton tulangan polos Ø10 mm Kg 35.249 20,946.00 738,323.79
- Besi beton tulangan polos Ø6 mm Kg 11.631 21,760.00 253,085.29
- Bekesting Kayu Kelas III M2 5.670 672,273.00 3,811,787.91
6 Ring Balk Beton Bertulang 15/15 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.486 3,058,615.00 1,486,486.89
- Besi beton tulangan polos Ø10 mm Kg 53.640 20,946.00 1,123,550.08
- Besi beton tulangan polos Ø6 mm Kg 17.090 21,760.00 371,880.42
- Bekesting Kayu Kelas III M2 6.480 686,742.00 4,450,088.16
7 Ring Balk Manumata Beton Bertulang 15/15 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.876 3,058,615.00 2,678,429.16
- Besi beton tulangan polos Ø10 mm Kg 96.652 20,946.00 2,024,470.78
- Besi beton tulangan polos Ø6 mm Kg 30.794 21,760.00 670,073.42
- Bekesting Kayu Kelas III M2 11.676 686,742.00 8,018,399.59
8 Balok Dak Beton Bertulang 15/15 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.153 3,058,615.00 467,624.00
- Besi beton tulangan polos Ø10 mm Kg 16.874 20,946.00 353,450.13
- Besi beton tulangan polos Ø6 mm Kg 5.376 21,760.00 116,987.38
- Bekesting Kayu Kelas III M2 2.039 686,742.00 1,399,923.57
9 Cor Dak Beton Bertulang T : 7 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.424 3,058,615.00 1,296,393.97
- Besi beton tulangan polos Ø10 mm Kg 52.557 20,946.00 1,100,867.30
- Bekesting Kayu Kelas III M2 4.239 752,267.00 3,188,483.68
10 Cor Plat Meja Beton Bertulang T : 7 cm
- Beton mutu f'c=21,7 Mpa (K 250) M3 0.143 3,058,615.00 435,852.64
HARGA
No. URAIAN / JENIS PEKERJAAN SAT. VOL. JUMLAH HARGA
SATUAN
- Besi beton tulangan polos Ø10 mm Kg 13.253 20,946.00 277,586.87
- Bekesting Kayu Kelas III M2 1.425 752,267.00 1,071,980.48
- Dudukan Pas. Bata M3 0.090 665,016.00 59,851.44
Sub Jumlah 101,702,855.65
###
IV PEKERJAAN PASANG BATU DAN PLESTERAN
1 Pasang Bata Ringan Dinding Dan Manumata M2 68.826 665,016.00 45,770,710.42
2 Plesteran Dinding , 1Pc : 3Ps (Pasir lokal) M2 128.826 182,434.00 23,502,330.05
Sub Jumlah 69,273,040.48
V PEKERJAAN KUSEN & PINTU JENDELA
1 Pek. Kusen Pintu/Jendela/Ventilasi Kayu Kelas II 5/10 M3 0.317 11,949,273.00 3,784,932.22
2 Pas. Pintu Panel 80 x 210 cm Bh 3.000 1,700,000.00 5,100,000.00
3 Pas. Pintu Panel 70 x 210 cm Bh 2.000 1,600,000.00 3,200,000.00
5 Pas. Jendela 50 x 160 cm Bh 2.000 750,000.00 1,500,000.00
6 Pas. Kaca Riben Jendela Atas Dak 5 mm M2 0.270 215,630.00 58,220.10
Sub Jumlah 13,643,152.32
VI PEKERJAAN ATAP ###
1 Pasang Kuda-Kuda Kayu Kelas III 5/10 M3 0.400 8,131,189.00 3,252,475.60
2 Pasang Atap Seng BJLS 0,20 M2 57.680 91,010.00 5,249,456.80
3 Pasang Gording Kayu Kelas III 4/8 M3 0.307 6,452,945.00 1,982,344.70
4 Pasang Listplank Papan M' 44.010 70,835.00 3,117,448.35
5 Pasang Nok lapis Seng Plat M' 7.060 128,901.00 910,041.06
Sub Jumlah 14,511,766.51
VII PEKERJAAN KUNCI DAN PENGGANTUNG ###
1 Pas. Kunci Tanam Pintu Alumunium 2x Putar Bh 5.000 371,749.00 1,858,745.00
2 Pas. Engsel Pintu Bh 15.000 68,191.00 1,022,865.00
3 Pas. Engsel Jendela Bh 8.000 52,348.00 418,784.00
4 Pas. Kait Angin Bh 8.000 41,901.00 335,208.00
5 Pas. Grendel Bh 8.000 128,248.00 1,025,984.00
Sub Jumlah 4,661,586.00
VIII PEKERJAAN KERAMIK DAN PLAFOND ###
1 Keramik 60 x 60 cm utk lantai dalam dan teras M2 35.730 408,919.00 14,610,471.41
2 Keramik Meja Beton 30 x 30 cm M2 1.000 255,114.00 255,114.00
3 Keramik Anti slip utk Lantai KM/WC, 25 x 25 cm M2 2.188 256,740.00 561,618.75
4 Keramik Dinding KM/WC 25 x 25 Cm, t=150 cm M2 7.550 439,688.00 3,319,644.40
5 Pas. Rangka Plafond 60 x 120 cm M3 46.320 172,687.00 7,998,775.50
6 Pasang Plafond Tripleks T : 5 mm M2 46.320 82,915.00 3,840,581.34
Sub Jumlah 30,586,205.40

IX PEKERJAAN INSTALASI LISTRIK


1 Pas. Instalasi Lampu LED 24 Watt Titik 6.000 267,003.00 1,602,018.00
2 Pas. Instalasi Lampu LED 14 Watt Titik 1.000 253,394.00 253,394.00
3 Pas. Instalasi Stop Kontak Titik 4.000 178,354.00 713,416.00
4 Pas. Instalasi Saklar Ganda Titik 2.000 410,209.00 820,418.00
5 Pas. Instalasi Saklar Tunggal Titik 3.000 405,264.00 1,215,792.00
6 Pasang MCB Group Bh 1.000 442,852.00 442,852.00
Sub Jumlah 5,047,890.00
X PEKERJAAN SANITAIR DAN PLUMBING
1 Bak Mandi Fiberglass Bh 1.000 1,778,917.00 1,778,917.00
2 Pasangan Kloset Duduk Porselin Bh 1.000 4,239,658.00 4,239,658.00
3 Pasangan kitchen zink 1 lubang Bh 1.000 608,300.00 608,300.00
4 Pasangan instalasi air bersih, pipa PVC 3/4"- AW dgn Acc M' 8.000 39,567.00 316,536.00
5 Pasangan instalasi air kotor dan air hujan, pipa PVC 2"- AW dgn Acc M' 5.000 139,604.08 698,020.39
6 Pasangan instalasi air kotor ke septicktank, pipa PVC 4"- AW dgn Acc M' 3.000 174,057.00 522,171.00
7 Pasangan kran air 3/4" Bh 2.000 57,733.00 115,466.00
8 Septictank Unit 1.000 8,468,760.00 8,468,760.00
9 Pompa Air Sanyo Unit 1.000 1,126,388.00 1,126,388.00
10 Pasang Floor drain Bh 1.000 85,000.00 85,000.00
Sub Jumlah 17,959,216.39

XI PEKERJAAN CAT
1 Cat Tembok setara Dulux M2 128.826 80,841.00 10,414,461.47
2 Cat Pelapis Waterproof Plat Atap Dak M2 4.239 111,709.00 473,478.60
HARGA
No. URAIAN / JENIS PEKERJAAN SAT. VOL. JUMLAH HARGA
SATUAN
3 Cat Plafond M2 46.320 80,841.00 3,744,514.70
4 Cat Meny Kayu M2 21.472 27,784.00 596,578.05
5 Cat Kilap Kayu M2 21.472 174,949.00 3,756,504.93
Sub Jumlah 18,985,537.74

XII PEKERJAAN FINISHING DAN PEMBERSIHAN


1 Pek. Finishing Dan Pembersihan Akhir Ls 1.000 2,000,000.00 2,000,000.00
Sub Jumlah 2,000,000.00

PEMBANGUNAN RUMAH TINGGAL TYPE 45 M2

REKAPITULASI :

I PEKERJAAN PENDAHULUAN ………………………………………………..Rp,- 20,677,953.00

II PEKERJAAN TANAH DAN PASIR ………………………………………………..Rp,- 11,689,745.19

III PEKERJAAN PONDASI DAN STRUKTUR BETON ………………………………………………..Rp,- 101,702,855.65

IV PEKERJAAN PASANG BATU DAN PLESTERAN ………………………………………………..Rp,- 69,273,040.48

V PEKERJAAN KUSEN & PINTU JENDELA ………………………………………………..Rp,- 14,511,766.51

VI PEKERJAAN ATAP ………………………………………………..Rp,- 14,511,766.51

VII PEKERJAAN KUNCI DAN PENGGANTUNG ………………………………………………..Rp,- 4,661,586.00

VIII PEKERJAAN KERAMIK DAN PLAFOND ………………………………………………..Rp,- 30,586,205.40

IX PEKERJAAN INSTALASI LISTRIK ………………………………………………..Rp,- 5,047,890.00

X PEKERJAAN SANITAIR DAN PLUMBING ………………………………………………..Rp,- 17,959,216.39

XI PEKERJAAN CAT ………………………………………………..Rp,- 18,985,537.74

XII PEKERJAAN FINISHING DAN PEMBERSIHAN ………………………………………………..Rp,- 2,000,000.00

Jumlah Harga Pekerjaan ………………………………………………..Rp,- 311,607,562.87

TERBILANG : (TIGA RATUS SEBELAS JUTA ENAM RATUS TUJUH RIBU LIMA RATUS ENAM PULUH TIGA RUPIAH)
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN: PEMBANGUNAN RUMAH TINGGAL TYPE 45 M2
LOKASI PEK: Gg. SEHATI KALIWEDA 2
KABUPATEN: MERAUKE
TAHUN : 2022
PERIODE : JULI - DESEMBER 2021

NO. ITEM PEKERJAAN KODE SATUAN KOEF.


HARGA SATUAN
JUMLAH HARGA

1 PEKERJAAN PERSIPAAN

1 M2 Membersihkan Lapangan dan Perataan PU-CK.A8


RSNI T-12-2002
Tenaga
Pekerja L-4 OH 0.1000 Rp 165,000.00 Rp 16,500.00
Mandor Bangunan L-1 OH 0.0050 Rp 232,000.00 Rp 1,160.00

Jumlah (1) Rp 17,660.00


Bahan
- - - - -
- - - - -

Jumlah (2) Rp -
Peralatan
- - - - -
- - - - -

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 17,660.00


Overhead 15% Rp 2,649.00
Jumlah Total Rp 20,309.00

1 M2 Camp Darurat Kontsruksi Kayu PU-CK.A10


RSNI T-12-2002
Tenaga
Pekerja L-4 OH 1.0000 Rp 165,000.00 Rp 165,000.00
Tukang kayu L-3 OH 2.0000 Rp 211,000.00 Rp 422,000.00
Kepala Tukang L-2 OH 0.2000 Rp 223,000.00 Rp 44,600.00
Mandor L-1 OH 0.0500 Rp 232,000.00 Rp 11,600.00
Jumlah (1) Rp 643,200.00
Bahan
Kayu bus gergajian MC.32 Batang 0.0500 Rp 2,918,110.00 Rp 145,905.50
Paku campuran MC.1 M3 0.5000 Rp 21,901.00 Rp 10,950.50
Paku seng MD.16 KG 0.1500 Rp 35,094.00 Rp 5,264.10
Seng Bjls 0.20 ( SNI ) MB.10 KG 2.0000 Rp 61,783.00 Rp 123,566.00
Jumlah (2) Rp 285,686.10
Peralatan

Jumlah (3) -

Jumlah (1+2+3) Rp 928,886.10


Overhead 15% Rp 139,332.92
Jumlah Total Rp 1,068,219.00

1 M' Pengukuran dan Pasangan Bouwplank PU-CK.A4


RSNI T-12-2002
Tenaga
Pekerja kayu L-4 OH 0.1000 Rp 165,000.00 Rp 16,500.00
Tukang kayu L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala Tukang Kayu L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Mandor L-1 OH 0.0050 Rp 232,000.00 Rp 1,160.00
Jumlah (1) Rp 40,990.00
Bahan
Balok Kayu Bus MC.1 M3 0.0120 Rp 2,918,110.00 Rp 35,017.32
Kayu Papan Bus MC.5 M3 0.0070 Rp 2,918,110.00 Rp 20,426.77
Paku Biasa Campur 2" - 5" MD.16 KG 0.0200 Rp 21,901.00 Rp 438.02
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Jumlah (2) Rp 55,882.11


Peralatan

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 96,872.11


Overhead 15% Rp 14,530.82
Jumlah Total Rp 111,402.00

2 PEKERJAAN TANAH DAN PASIR

1 M3 Galian Tanah Biasa Sedalam 1 - 2 M PU-CK.B.3


SNI 2835:2008
Tenaga
Pekerja L-4 OH 0.9000 Rp 165,000.00 Rp 148,500.00
Mandor L-1 OH 0.0450 Rp 232,000.00 Rp 10,440.00
Jumlah (1) Rp 158,940.00
Bahan

Jumlah (2) Rp -
Peralatan

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 158,940.00


Overhead 15% Rp 23,841.00
Jumlah Total Rp 182,781.00

1 M3 Urug Kembali Tanah Biasa Sedalam 1 - 2 PU-CK.B.4


SNI 2835:2008
Tenaga
1/3PU-CK.B.3
Dihitung 1/3 kali Galian Tanah Biasa Sedalam 1 - 2 M M3 0.3333 Rp 182,781.00 Rp 60,927.00
Jumlah (1) Rp 60,927.00
Bahan

Jumlah (2) Rp -

Peralatan

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 60,927.00


Overhead 15% Rp 9,139.05
Jumlah Total Rp 70,066.00

1 M3 Urugan Tanah Urug (material didatangkanPU-CK.B.14


SNI 2835:2008
Tenaga
Pekerja L-4 OH 0.5000 Rp 165,000.00 Rp 82,500.00
Mandor L-1 OH 0.0500 Rp 232,000.00 Rp 11,600.00
Jumlah (1) Rp 94,100.00
Bahan
Tanah timbun biasa/urug MB.3 M3 1.2000 Rp 265,280.00 Rp 318,336.00
Jumlah (2) Rp 318,336.00
Peralatan

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 412,436.00


Overhead 15% Rp 61,865.40
Jumlah Total Rp 474,301.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

1 M3 PU-CK.B.16
Urugan Pasir Bawah Pondasi/Lantai/Konst
SNI 2835:2008
Tenaga
Pekerja L-4 OH 0.3000 Rp 165,000.00 Rp 49,500.00
Mandor L-1 OH 0.0100 Rp 232,000.00 Rp 2,320.00
Jumlah (1) Rp 51,820.00
Bahan
Pasir semen (lokal) MB.2 M3 1.2000 Rp 762,510.00 Rp 915,012.00
Jumlah (2) Rp 915,012.00
Peralatan

Jumlah (3) Rp -

Jumlah (1+2+3) Rp 966,832.00


Overhead 15% Rp 145,024.80
Jumlah Total Rp 1,111,856.00

3 PEKERJAAN PONDASI DAN BETON

1 M3 Pasangan Bata, Camp. 1PC : 3PS - Pasir PU-CK.C.5


HPS.PU- 2021
TENAGA
Pekerja pasir/batu L-4 OH 2.8571 Rp 165,000.00 Rp 471,428.57
Tukang pasir/batu L-3 OH 1.2857 Rp 211,000.00 Rp 271,285.71
Kepala tukang pasir/batu L-2 OH 0.4286 Rp 223,000.00 Rp 95,571.43
Mandor pasir/batu L-1 OH 0.1429 Rp 232,000.00 Rp 33,142.86
Jumlah (1) Rp 871,428.57
BAHAN
Batu bata MB.7 Buah 649.0000 Rp 1,380.00 Rp 895,620.00
Semen Portland (PC) @ 50 Kg MB.10 Zak 4.3731 Rp 103,850.00 Rp 454,148.77
Pasir semen (lokal) MB.1 M3 0.4685 Rp 762,510.00 Rp 357,273.18
Jumlah (2) Rp 1,707,041.95

Jumlah (1+2) Rp 2,578,470.52


Overhead 15% Rp 386,770.58
Jumlah Total Rp 2,965,241.00

1 M3 Campuran Beton 1PC : 3PS Pasir Lokal - PU-CK.D.7


HPS.PU- 2021
Tenaga
Pekerja pasir/batu L-4 OH 6.0000 Rp 165,000.00 Rp 990,000.00
Tukang pasir/batu L-3 OH 1.0000 Rp 211,000.00 Rp 211,000.00
Kepala tukang pasir/batu L-2 OH 0.1000 Rp 223,000.00 Rp 22,300.00
Mandor pasir/batu L-1 OH 0.3000 Rp 232,000.00 Rp 69,600.00
Jumlah (1) Rp 1,292,900.00
Bahan
Semen Portland (PC) @ 50 Kg MB.10 Zak 11.4750 Rp 103,850.00 Rp 1,191,678.75
Pasir semen (lokal) MB.1 M3 1.1475 Rp 762,510.00 Rp 874,980.23
Jumlah (2) Rp 2,066,658.98

Jumlah (1+2) Rp 3,359,558.98


Overhead 15% Rp 503,933.85
Jumlah Total Rp 3,863,492.00

1 M3 Beton mutu f’'c = 21,7 MPa (K 250), slumPU-CK.D.34


SNI 7394:2008
Tenaga
Pekerja pasir/batu L-4 OH 1.6500 Rp 165,000.00 Rp 272,250.00
Tukang pasir/batu L-3 OH 0.2750 Rp 211,000.00 Rp 58,025.00
Kepala tukang pasir/batu L-2 OH 0.0275 Rp 223,000.00 Rp 6,132.50
Mandor pasir/batu L-1 OH 0.0825 Rp 232,000.00 Rp 19,140.00
Jumlah (1) Rp 355,547.50
Bahan
Semen Portland (PC) @ 50 Kg MB.10 KG 384.0000 Rp 2,077.00 Rp 797,568.00
Pasir semen (import) MB.1 M3 0.4943 Rp 1,161,410.00 Rp 574,068.37
Kerikil/batu pecah (import) MB.5 M3 0.7696 Rp 1,197,630.00 Rp 921,731.53
Air MN.13 Liter 215.0000 Rp 50.00 Rp 10,750.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Jumlah (2) Rp 2,304,117.90

Jumlah (1+2) Rp 2,659,665.40


Overhead 15% Rp 398,949.81
Jumlah Total Rp 3,058,615.00

1 KG Pembesian Besi polos/ulir Ø. 6 mm SNI PU-CK.D.52


SNI 7394:2008
Tenaga
Pekerja L-4 OH 0.0070 Rp 165,000.00 Rp 1,155.00
Tukang besi L-3 OH 0.0070 Rp 211,000.00 Rp 1,477.00
Kepala tukang L-2 OH 0.0007 Rp 223,000.00 Rp 156.10
Mandor L-1 OH 0.0004 Rp 232,000.00 Rp 92.80
Jumlah (1) Rp 2,880.90
Bahan
Besi Beton Dia.6 SNI (P=12 m) MD.2 KG 1.0500 Rp 14,919.00 Rp 15,664.95
Kawat beton MD.9 KG 0.0150 Rp 25,090.00 Rp 376.35
Jumlah (2) Rp 16,041.30

Jumlah (1+2) Rp 18,922.20


Overhead 15% Rp 2,838.33
Jumlah Total Rp 21,760.00

1 KG Pembesian Besi polos/ulir Ø. 10 mm SNIPU-CK.D.51


SNI 7394:2008
Tenaga
Pekerja L-4 OH 0.0070 Rp 165,000.00 Rp 1,155.00
Tukang besi L-3 OH 0.0070 Rp 211,000.00 Rp 1,477.00
Kepala tukang L-2 OH 0.0007 Rp 223,000.00 Rp 156.10
Mandor L-1 OH 0.0004 Rp 232,000.00 Rp 92.80
Jumlah (1) Rp 2,880.90
Bahan
Besi Beton Dia.10 SNI (P=12 m) MD.3 KG 1.0500 Rp 14,245.00 Rp 14,957.25
Kawat beton MD.9 KG 0.0150 Rp 25,090.00 Rp 376.35
Jumlah (2) Rp 15,333.60

Jumlah (1+2) Rp 18,214.50


Overhead 15% Rp 2,732.18
Jumlah Total Rp 20,946.00

1 M2 Bekisting untuk Sloof PU-CK.D.60


SNI 7394:2008
Tenaga
Pekerja Kayu L-4 OH 0.5200 Rp 165,000.00 Rp 85,800.00
Tukang Kayu L-3 OH 0.2600 Rp 211,000.00 Rp 54,860.00
Kepala Tukang Kayu L-2 OH 0.0260 Rp 223,000.00 Rp 5,798.00
Mandor L-1 OH 0.0260 Rp 232,000.00 Rp 6,032.00
Jumlah (1) Rp 152,490.00
Bahan
Kayu Bekisting Kelas 3 MC.5 M3 0.0450 Rp 2,918,110.00 Rp 131,314.95
Paku Campur Biasa 5 cm - 10 cm MD.16 KG 0.3000 Rp 21,901.00 Rp 6,570.30
Minyak Bekisting/oli bekas MA.5 Liter 0.1000 Rp 940.00 Rp 94.00
Jumlah (2) Rp 137,979.25

Jumlah (1+2) Rp 290,469.25


Overhead 15% Rp 43,570.39
Jumlah Total Rp 334,039.00

1 M2 Bekisting untuk Kolom PU-CK.D.61


SNI 7394:2008
Tenaga
Pekerja Kayu L-4 OH 0.6600 Rp 165,000.00 Rp 108,900.00
Tukang Kayu L-3 OH 0.3300 Rp 211,000.00 Rp 69,630.00
Kepala Tukang Kayu L-2 OH 0.0330 Rp 223,000.00 Rp 7,359.00
Mandor L-1 OH 0.0330 Rp 232,000.00 Rp 7,656.00
Jumlah (1) Rp 193,545.00
Bahan
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Kayu Bekisting Kelas 3 MC.5 M3 0.0400 Rp 2,918,110.00 Rp 116,724.40


Paku Campur Biasa 5 cm - 10 cm MD.16 KG 0.4000 Rp 21,901.00 Rp 8,760.40
Minyak Bekisting/oli bekas MA.5 Liter 0.2000 Rp 940.00 Rp 188.00
Balok Kayu Kelas 2 MC.2 M3 0.0150 Rp 4,193,980.00 Rp 62,909.70
Plywood 9 mm MC.21 Lembar 0.3500 Rp 479,080.00 Rp 167,678.00
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 MC.32 Batang 2.0000 Rp 17,390.00 Rp 34,780.00
Jumlah (2) Rp 391,040.50

Jumlah (1+2) Rp 584,585.50


Overhead 15% Rp 87,687.83
Jumlah Total Rp 672,273.00

1 M2 Bekisting untuk Balok PU-CK.D.62


SNI 7394:2008
Tenaga
Pekerja Kayu L-4 OH 0.6600 Rp 165,000.00 Rp 108,900.00
Tukang Kayu L-3 OH 0.3300 Rp 211,000.00 Rp 69,630.00
Kepala Tukang Kayu L-2 OH 0.0330 Rp 223,000.00 Rp 7,359.00
Mandor L-1 OH 0.0330 Rp 232,000.00 Rp 7,656.00
Jumlah (1) Rp 193,545.00
Bahan
Kayu Bekisting Kelas 3 MC.5 M3 0.0400 Rp 2,918,110.00 Rp 116,724.40
Paku Campur Biasa 5 cm - 10 cm MD.16 KG 0.4000 Rp 21,901.00 Rp 8,760.40
Minyak Bekisting/oli bekas MA.5 Liter 0.2000 Rp 940.00 Rp 188.00
Balok Kayu Kelas 2 MC.2 M3 0.0180 Rp 4,193,980.00 Rp 75,491.64
Plywood 9 mm MC.21 Lembar 0.3500 Rp 479,080.00 Rp 167,678.00
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 MC.32 Batang 2.0000 Rp 17,390.00 Rp 34,780.00
Jumlah (2) Rp 403,622.44

Jumlah (1+2) Rp 597,167.44


Overhead 15% Rp 89,575.12
Jumlah Total Rp 686,742.00

1 M2 Bekisting Untuk Dak PU-CK.D.63


SNI 7394:2008
Tenaga
Pekerja Kayu L-4 OH 0.6600 Rp 165,000.00 Rp 108,900.00
Tukang Kayu L-3 OH 0.3300 Rp 211,000.00 Rp 69,630.00
Kepala Tukang Kayu L-2 OH 0.0330 Rp 223,000.00 Rp 7,359.00
Mandor L-1 OH 0.0330 Rp 232,000.00 Rp 7,656.00
Jumlah (1) Rp 193,545.00
Bahan
Kayu Bekisting Kelas 3 MC.5 M3 0.0400 Rp 2,918,110.00 Rp 116,724.40
Paku Campur Biasa 5 cm - 10 cm MD.16 KG 0.4000 Rp 21,901.00 Rp 8,760.40
Minyak Bekisting/oli bekas MA.5 Liter 0.2000 Rp 940.00 Rp 188.00
Balok Kayu Kelas 2 MC.2 M3 0.0150 Rp 4,193,980.00 Rp 62,909.70
Plywood 9 mm MC.21 Lembar 0.3500 Rp 479,080.00 Rp 167,678.00
Kayu dolken Ø 8-10, Panjang 400 cm - Kayu Kelas 3 MC.32 Batang 6.0000 Rp 17,390.00 Rp 104,340.00
Jumlah (2) Rp 460,600.50

Jumlah (1+2) Rp 654,145.50


Overhead 15% Rp 98,121.83
Jumlah Total Rp 752,267.00
4 PEKERJAAN PASANGAN DAN PLESTERAN

1 M2 Bata ringan (10 x 20 x 60) cm


SNI 6897:2008
TENAGA
Pekerja pasir/batu L-4 OH 0.3000 Rp 165,000.00 Rp 49,500.00
Tukang pasir/batu L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala tukang pasir/batu L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Mandor pasir/batu L-1 OH 0.0100 Rp 232,000.00 Rp 2,320.00
Jumlah (1) Rp 75,150.00
BAHAN
Bata Ringan MB.7 M3 8.7500 Rp 55,000.00 Rp 481,250.00
Prime Mortar MU-380 MB.10 KG 2.5000 Rp 8,750.00 Rp 21,875.00
Jumlah (2) Rp 503,125.00

Jumlah (1+2) Rp 578,275.00


NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Overhead 15% Rp 86,741.25


Jumlah Total Rp 665,016.00

1 M2 Plesteran 1PC : 3PS, Tebal 25 mm - PasirPU-CK.F.28


SNI 2837:2008
TENAGA
Pekerja pasir/batu L-4 OH 0.3000 Rp 165,000.00 Rp 49,500.00
Tukang pasir/batu L-3 OH 0.2000 Rp 211,000.00 Rp 42,200.00
Kepala tukang pasir/batu L-2 OH 0.0200 Rp 223,000.00 Rp 4,460.00
Mandor pasir/batu L-1 OH 0.0130 Rp 232,000.00 Rp 3,016.00
Jumlah (1) Rp 99,176.00
BAHAN
Semen Portland (PC) @ 50 Kg MB.10 KG 6.2400 Rp 6,260.00 Rp 39,062.40
Pasir semen (lokal) MB.2 M3 0.0240 Rp 850,000.00 Rp 20,400.00
Jumlah (2) Rp 59,462.40

Jumlah (1+2) Rp 158,638.40


Overhead 15% Rp 23,795.76
Jumlah Total Rp 182,434.00

5 PEKERJAAN LANTAI DAN DINDING

1 M2 Lantai Ubin Teralux Marmer Ukuran 60 xPU-CK.I.13


SNI 7395-2008
TENAGA
Pekerja L-4 OH 0.2400 Rp 165,000.00 Rp 39,600.00
Tukang batu L-3 OH 0.1200 Rp 211,000.00 Rp 25,320.00
Kepala tukang L-2 OH 0.0120 Rp 223,000.00 Rp 2,676.00
Mandor L-1 OH 0.0120 Rp 232,000.00 Rp 2,784.00
Jumlah (1) Rp 70,380.00
BAHAN
Ubin Teralux Marmer Ukuran 60 x 60 cm MF.15 Buah 3.1000 Rp 73,366.00 Rp 227,434.60
Semen Portland (PC) @ 50 Kg MB.10 KG 9.6000 Rp 2,077.00 Rp 19,939.20
Pasir Semen (lokal) MB.2 M3 0.0450 Rp 762,510.00 Rp 34,312.95
Semen Warna MB.11 KG 1.5000 Rp 2,343.66 Rp 3,515.49
Jumlah (2) Rp 285,202.24

Jumlah (1+2) Rp 355,582.24


Overhead 15% Rp 53,337.34
Jumlah Total Rp 408,919.00

1 M2 Lantai Ubin PC Warna Ukuran 30 x 30 c PU-CK.I.5


SNI 7395-2008
TENAGA
Pekerja L-4 OH 0.2600 Rp 165,000.00 Rp 42,900.00
Tukang batu L-3 OH 0.1300 Rp 211,000.00 Rp 27,430.00
Kepala tukang L-2 OH 0.0130 Rp 223,000.00 Rp 2,899.00
Mandor L-1 OH 0.0130 Rp 232,000.00 Rp 3,016.00
Jumlah (1) Rp 76,245.00
BAHAN
Ubin Warna Ukuran 30 x 30 MF.5 Buah 11.8700 Rp 7,329.00 Rp 86,995.23
Semen Portland (PC) @ 50 Kg MB.10 KG 10.0000 Rp 2,077.00 Rp 20,770.00
Pasir Semen (lokal) MB.2 M3 0.0450 Rp 762,510.00 Rp 34,312.95
Semen Warna MB.11 KG 1.5000 Rp 2,343.66 Rp 3,515.49
Jumlah (2) Rp 145,593.67

Jumlah (1+2) Rp 221,838.67


Overhead 15% Rp 33,275.80
Jumlah Total Rp 255,114.00

1 M2 Lantai Ubin PC Warna Ukuran 20 x 20 c PU-CK.I.4


SNI 7395-2008
TENAGA
Pekerja L-4 OH 0.2700 Rp 165,000.00 Rp 44,550.00
Tukang batu L-3 OH 0.1350 Rp 211,000.00 Rp 28,485.00
Kepala tukang L-2 OH 0.0140 Rp 223,000.00 Rp 3,122.00
Mandor L-1 OH 0.0140 Rp 232,000.00 Rp 3,248.00
Jumlah (1) Rp 79,405.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

BAHAN
Ubin Warna Ukuran 20 x 20 MF.4 Buah 26.5000 Rp 3,175.00 Rp 84,137.50
Semen Portland (PC) @ 50 Kg MB.10 KG 10.4000 Rp 2,077.00 Rp 21,600.80
Pasir Semen (lokal) MB.2 M3 0.0450 Rp 762,510.00 Rp 34,312.95
Semen Warna MB.11 KG 1.6200 Rp 2,343.66 Rp 3,796.73
Jumlah (2) Rp 143,847.98

Jumlah (1+2) Rp 223,252.98


Overhead 15% Rp 33,487.95
Jumlah Total Rp 256,740.00

1 M2 Dinding Porselin Ukuran 20 x 20 cm PU-CK.I.49


SNI 7395-2008
TENAGA
Pekerja L-4 OH 0.9000 Rp 165,000.00 Rp 148,500.00
Tukang batu L-3 OH 0.4500 Rp 211,000.00 Rp 94,950.00
Kepala tukang L-2 OH 0.0450 Rp 223,000.00 Rp 10,035.00
Mandor L-1 OH 0.0450 Rp 232,000.00 Rp 10,440.00
Jumlah (1) Rp 263,925.00
BAHAN
Porselin Ukuran 20 x 20 cm MF.30 Buah 26.5000 Rp 3,050.00 Rp 80,825.00
Semen Portland (PC) @ 50 Kg MB.10 KG 9.3000 Rp 2,077.00 Rp 19,316.10
Pasir Semen (lokal) MB.2 M3 0.0180 Rp 762,510.00 Rp 13,725.18
Semen Warna MB.11 KG 1.9400 Rp 2,343.66 Rp 4,546.70
Jumlah (2) Rp 118,412.98

Jumlah (1+2) Rp 382,337.98


Overhead 15% Rp 57,350.70
Jumlah Total Rp 439,688.00

6 PEKERJAAN ATAP

1 M3 PU-CK.G.21
Konstruksi Kuda-Kuda Konvensional, Kay
SNI 3434:2008
TENAGA
Pekerja Kayu L-4 OH 4.0000 Rp 165,000.00 Rp 660,000.00
Tukang Kayu L-3 OH 12.0000 Rp 211,000.00 Rp 2,532,000.00
Kepala Tukang L-2 OH 1.2000 Rp 223,000.00 Rp 267,600.00
Mandor L-1 OH 0.2000 Rp 232,000.00 Rp 46,400.00
Jumlah (1) Rp 3,506,000.00
BAHAN
Balok Kayu Kelas III (Kayu Bus) MC.1 M3 1.1000 Rp 2,918,110.00 Rp 3,209,921.00
Besi Strip Tebal 5 cm MD.51 KG 15.0000 Rp 15,468.89 Rp 232,033.33
Paku Campuran MD.16 KG 5.6000 Rp 21,901.00 Rp 122,645.60
Jumlah (2) Rp 3,564,599.93

Jumlah (1+2) Rp 7,070,599.93


Overhead 15% Rp 1,060,589.99
Jumlah Total Rp 8,131,189.00
1 M3 Konstruksi Gordeng - Kayu Kelas III
SNI 3434:2008
TENAGA
Pekerja Kayu L-4 OH 2.4000 Rp 165,000.00 Rp 396,000.00
Tukang Kayu L-3 OH 7.2000 Rp 211,000.00 Rp 1,519,200.00
Kepala Tukang L-2 OH 0.7200 Rp 223,000.00 Rp 160,560.00
Mandor L-1 OH 0.1200 Rp 232,000.00 Rp 27,840.00
Jumlah (1) Rp 2,103,600.00
BAHAN
Balok Kayu Kelas III (Kayu Bus) MC.1 M3 1.1000 Rp 2,918,110.00 Rp 3,209,921.00
Besi Strip Tebal 5 cm MD.51 KG 15.0000 Rp 15,468.89 Rp 232,033.33
Paku Campuran MD.16 KG 3.0000 Rp 21,901.00 Rp 65,703.00
Jumlah (2) Rp 3,507,657.33

Jumlah (1+2) Rp 5,611,257.33


Overhead 15% Rp 841,688.60
Jumlah Total Rp 6,452,945.00

1 M' Lisplank Ukuran (2 x 20) cm, Kayu KelasPU-CK.G.41


HPS.PU-2021
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

TENAGA
Pekerja Kayu L-4 OH 0.1000 Rp 165,000.00 Rp 16,500.00
Tukang Kayu L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala Tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Mandor L-1 OH 0.0050 Rp 232,000.00 Rp 1,160.00
Jumlah (1) Rp 40,990.00
BAHAN
Papan Kayu Kelas II (Kayu Rahay) tebal = 2 Cm MC.6 M3 0.0046 Rp 4,193,980.00 Rp 19,292.31
Paku Campuran MD.16 KG 0.0600 Rp 21,901.00 Rp 1,314.06
Jumlah (2) Rp 20,606.37

Jumlah (1+2) Rp 61,596.37


Overhead 15% Rp 9,239.46
Jumlah Total Rp 70,835.00

1 M2 Penutup Atap Seng Gelombang BJLS 0,2 PU-CK.H.3


SNI 03-3436-2002
TENAGA
Pekerja L-4 OH 0.1200 Rp 165,000.00 Rp 19,800.00
Tukang Kayu L-3 OH 0.0600 Rp 211,000.00 Rp 12,660.00
Kepala Tukang L-2 OH 0.0060 Rp 223,000.00 Rp 1,338.00
Mandor L-1 OH 0.0060 Rp 232,000.00 Rp 1,392.00
Jumlah (1) Rp 35,190.00
BAHAN
Seng Gelombang BJLS 0,20 ME.3 Lembar 0.7000 Rp 61,783.00 Rp 43,248.10
Paku Seng MD.17 KG 0.0200 Rp 35,094.00 Rp 701.88
Jumlah (2) Rp 43,949.98

Jumlah (1+2) Rp 79,139.98


Overhead 15% Rp 11,871.00
Jumlah Total Rp 91,010.00

1 M' Bubungan/Nok Atap Seng Gelombang BJ PU-CK.H.5


SNI 03-3436-2002
TENAGA
Pekerja L-4 OH 0.1250 Rp 165,000.00 Rp 20,625.00
Tukang Kayu L-3 OH 0.2500 Rp 211,000.00 Rp 52,750.00
Kepala Tukang L-2 OH 0.0250 Rp 223,000.00 Rp 5,575.00
Mandor L-1 OH 0.0060 Rp 232,000.00 Rp 1,392.00
Jumlah (1) Rp 80,342.00
BAHAN
Seng Plat BJLS 0,20 ME.7 Lembar 0.4000 Rp 46,900.00 Rp 18,760.00
Paku Campuran MD.16 KG 0.0600 Rp 21,901.00 Rp 1,314.06
Papan Kayu Kelas III (Kayu Bus) t = 2 - 5 cm MC.5 M3 0.0040 Rp 2,918,110.00 Rp 11,672.44
Jumlah (2) Rp 31,746.50

Jumlah (1+2) Rp 112,088.50


Overhead 15% Rp 16,813.28
Jumlah Total Rp 128,901.00

7 PEKERJAAN PLAFOND

1 M2 Rangka Plafond (60 x 120), Kayu Kelas IIPU-CK.G.34


HPS.PU-2021
TENAGA
Pekerja Kayu L-4 OH 0.1700 Rp 165,000.00 Rp 28,050.00
Tukang Kayu L-3 OH 0.2700 Rp 211,000.00 Rp 56,970.00
Kepala Tukang L-2 OH 0.0270 Rp 223,000.00 Rp 6,021.00
Mandor L-1 OH 0.0085 Rp 232,000.00 Rp 1,972.00
Jumlah (1) Rp 93,013.00
BAHAN
Balok Kayu Kelas II (Kayu Rahay) MC.2 M3 0.0130 Rp 4,193,980.00 Rp 54,521.74
Paku Campuran MD.16 KG 0.1200 Rp 21,901.00 Rp 2,628.12
Jumlah (2) Rp 57,149.86

Jumlah (1+2) Rp 150,162.86


Overhead 15% Rp 22,524.43
Jumlah Total Rp 172,687.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

1 M2 Langit-langit Triplek Ukuran (120 x 240) tebal 4 mm


SNI 2839:2008
TENAGA
Pekerja Kayu L-4 OH 0.1000 Rp 165,000.00 Rp 16,500.00
Tukang Kayu L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala Tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Mandor L-1 OH 0.0050 Rp 232,000.00 Rp 1,160.00
Jumlah (1) Rp 40,990.00
BAHAN
Triplek ukuran (120 x 240) cm tebal 4 mm MC.12 Lembar 0.3750 Rp 81,210.00 Rp 30,453.75
Paku Triplek MD.16 KG 0.0300 Rp 21,901.00 Rp 657.03
Jumlah (2) Rp 31,110.78

Jumlah (1+2) Rp 72,100.78


Overhead 15% Rp 10,815.12
Jumlah Total Rp 82,915.00
1 M' Pasang list plafond gypsum profil PU-CK.K.6
SNI 2839:2008
TENAGA
Pekerja L-4 OH 0.0600 Rp 165,000.00 Rp 9,900.00
Tukang L-3 OH 0.0600 Rp 211,000.00 Rp 12,660.00
Kepala Tukang L-2 OH 0.0060 Rp 223,000.00 Rp 1,338.00
Mandor L-1 OH 0.0030 Rp 232,000.00 Rp 696.00
Jumlah (1) Rp 24,594.00
BAHAN
List profil Gypsum Lebar Sampai 5 cm MC.28 M' 1.0500 Rp 35,352.50 Rp 37,120.13
Tepung gypsum MB.12 KG 0.1500 Rp 4,947.25 Rp 742.09
Jumlah (2) Rp 37,862.21

Jumlah (1+2) Rp 62,456.21


Overhead 15% Rp 9,368.43
Jumlah Total Rp 71,824.00

8 PEKERJAAN KUSEN PINTU DAN JENDELA

1 M3 Kusen Pintu dan Jendela Kayu Kelas II PU-CK.G.2


SNI 3434:2008
TENAGA
Pekerja Kayu L-4 OH 6.0000 Rp 165,000.00 Rp 990,000.00
Tukang Kayu L-3 OH 18.0000 Rp 211,000.00 Rp 3,798,000.00
Kepala Tukang L-2 OH 1.8000 Rp 223,000.00 Rp 401,400.00
Mandor L-1 OH 0.3000 Rp 232,000.00 Rp 69,600.00
Jumlah (1) Rp 5,259,000.00
BAHAN
Balok Kayu Kelas II (Kayu Rahay) MC.2 M3 1.2000 Rp 4,193,980.00 Rp 5,032,776.00
Paku Campuran MD.16 KG 1.2500 Rp 21,901.00 Rp 27,376.25
Lem Kayu MN.1 KG 1.0000 Rp 71,520.00 Rp 71,520.00
Jumlah (2) Rp 5,131,672.25

Jumlah (1+2) Rp 10,390,672.25


Overhead 15% Rp 1,558,600.84
Jumlah Total Rp 11,949,273.00

1 Buah Kunci Pintu Tanam Antik PU-CK.L.1


Pt T-30-2000-C
TENAGA
Tukang L-3 OH 0.6000 Rp 211,000.00 Rp 126,600.00
Kepala tukang L-2 OH 0.0600 Rp 223,000.00 Rp 13,380.00
Jumlah (1) Rp 139,980.00
BAHAN
Kunci Tanam Antik MH.2 Buah 1.0000 Rp 183,280.00 Rp 183,280.00
Jumlah (2) Rp 183,280.00

Jumlah (1+2) Rp 323,260.00


Overhead 15% Rp 48,489.00
Jumlah Total Rp 371,749.00

1 Buah Engsel Pintu PU-CK.L.4


Pt T-30-2000-C
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

TENAGA
Tukang L-3 OH 0.1250 Rp 211,000.00 Rp 26,375.00
Kepala tukang L-2 OH 0.0130 Rp 223,000.00 Rp 2,899.00
Jumlah (1) Rp 29,274.00
BAHAN
Engsel Pintu MH.6 Buah 1.0000 Rp 30,023.00 Rp 30,023.00
Jumlah (2) Rp 30,023.00

Jumlah (1+2) Rp 59,297.00


Overhead 15% Rp 8,894.55
Jumlah Total Rp 68,191.00

1 Buah Engsel Jendela PU-CK.L.6


Pt T-30-2000-C
TENAGA
Tukang L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Jumlah (1) Rp 23,330.00

BAHAN
Engsel Jendela MH.7 Buah 1.0000 Rp 22,190.00 Rp 22,190.00
Jumlah (2) Rp 22,190.00

Jumlah (1+2) Rp 45,520.00


Overhead 15% Rp 6,828.00
Jumlah Total Rp 52,348.00

1 Buah Kait Angin PU-CK.L.7


Pt T-30-2000-C
TENAGA
Tukang L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Jumlah (1) Rp 23,330.00
BAHAN
Kait Angin MH.11 Buah 1.0000 Rp 13,106.00 Rp 13,106.00
Jumlah (2) Rp 13,106.00

Jumlah (1+2) Rp 36,436.00


Overhead 15% Rp 5,465.40
Jumlah Total Rp 41,901.00

1 Buah Grendel PU-CK.L.8


Pt T-30-2000-C
TENAGA
Tukang L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.00
Kepala tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.00
Jumlah (1) Rp 23,330.00
BAHAN
Grendel MH.13 Buah 1.0000 Rp 88,190.00 Rp 88,190.00
Jumlah (2) Rp 88,190.00

Jumlah (1+2) Rp 111,520.00


Overhead 15% Rp 16,728.00
Jumlah Total Rp 128,248.00

1 M2 Kaca raiben tebal 5 mm PU-CK.L.11


Pt T-30-2000-C
TENAGA
Pekerja kayu L-4 OH 0.1600 Rp 165,000.00 Rp 26,400.00
Tukang kayu L-3 OH 0.1600 Rp 211,000.00 Rp 33,760.00
Kepala tukang L-2 OH 0.0160 Rp 223,000.00 Rp 3,568.00
Mandor kayu L-1 OH 0.0080 Rp 232,000.00 Rp 1,856.00
Jumlah (1) Rp 5,424.00
BAHAN
Kaca raiben tebal 5 mm MG.10 M2 1.1000 Rp 215,630.00 Rp 237,193.00
Kayu Lat MC.10 Batang 0.0000 Rp 25,400.00 Rp -
Paku Campur MD.16 KG 0.0000 Rp 21,901.00 Rp -
Jumlah (2) Rp 237,193.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Jumlah (1+2) Rp 242,617.00


Overhead 15% Rp 36,392.55
Jumlah Total Rp 279,009.00

9 PEKERJAAN PENGECATAN

1 M2 Pelapisan Bidang Kayu Dengan Meny PU-CK.N.9


Pt.T-38-2000-C
TENAGA
Pekerja cat L-4 OH 0.0750 Rp 165,000.00 Rp 12,375.00
Mandor cat L-1 OH 0.0040 Rp 232,000.00 Rp 928.00
Jumlah (1) Rp 13,303.00
BAHAN
Cat meny kayu MI.4 KG 0.1700 Rp 36,993.00 Rp 6,288.81
Minyak Cat MI.9 Liter 0.1000 Rp 40,943.00 Rp 4,094.30
Kuas MN.11 Buah 0.0150 Rp 31,600.00 Rp 474.00
Jumlah (2) Rp 10,857.11

Jumlah (1+2) Rp 24,160.11


Overhead 15% Rp 3,624.02
Jumlah Total Rp 27,784.00

1 M2 Cat Plafond 2 Lapis dgn cat tembok (setara Dulux Weathershield), kuas roll
HPS.PU-2021
TENAGA
Pekerja cat L-4 OH 0.0600 Rp 165,000.00 Rp 9,900.00
Tukang cat L-3 OH 0.0400 Rp 211,000.00 Rp 8,440.00
Kepala tukang cat L-2 OH 0.0040 Rp 223,000.00 Rp 892.00
Mandor cat L-1 OH 0.0030 Rp 232,000.00 Rp 696.00
Jumlah (1) Rp 19,928.00
BAHAN
Plamur MI.11 KG 0.1000 Rp 7,186.50 Rp 718.65
Cat Tembok (Setara Dulux Weathershield) MI.10 KG 0.4700 Rp 97,426.00 Rp 45,790.22
Kertas amplas (kayu) MI.1 Lembar 0.5000 Rp 6,435.00 Rp 3,217.50
Kuas roll MN.12 Buah 0.0100 Rp 34,225.00 Rp 342.25
Kapek Buah 0.0500 Rp 6,000.00 Rp 300.00
Jumlah (2) Rp 50,368.62

Jumlah (1+2) Rp 70,296.62


Overhead 15% Rp 10,544.49
Jumlah Total Rp 80,841.00

1 M2 Mengecat Penutup 2 Lapis Pada Kayu PU-CK.N.11


Pt.T-38-2000-C
TENAGA
Pekerja cat L-4 OH 0.1500 Rp 165,000.00 Rp 24,750.00
Tukang cat L-3 OH 0.1500 Rp 211,000.00 Rp 31,650.00
Kepala tukang cat L-2 OH 0.0150 Rp 223,000.00 Rp 3,345.00
Mandor cat L-1 OH 0.0080 Rp 232,000.00 Rp 1,856.00
Jumlah (1) Rp 61,601.00
BAHAN
Cat tutup/cat kayu MI.6 KG 0.3000 Rp 67,026.00 Rp 20,107.80
Minyak Cat MH.2 Liter 0.2000 Rp 40,943.00 Rp 8,188.60
Kuas MN.11 Buah 0.0200 Rp 31,600.00 Rp 632.00
Jumlah (2) Rp 90,529.40

Jumlah (1+2) Rp 152,130.40


Overhead 15% Rp 22,819.56
Jumlah Total Rp 174,949.00

1 M2 Cat tembok khusus (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
HPS.PU-2021
TENAGA
Pekerja cat L-4 OH 0.0600 Rp 165,000.00 Rp 9,900.00
Tukang cat L-3 OH 0.0600 Rp 211,000.00 Rp 12,660.00
Kepala tukang cat L-2 OH 0.0060 Rp 223,000.00 Rp 1,338.00
Mandor cat L-1 OH 0.0030 Rp 232,000.00 Rp 696.00
Jumlah (1) Rp 24,594.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

BAHAN
Plamur MI.11 KG 0.1000 Rp 7,186.50 Rp 718.65
Cat Dasar (Setara Dulux Weathershield) MI.10 KG 0.2350 Rp 97,426.00 Rp 22,895.11
Cat Penutup (Setara Dulux Weathershield) MI.10 KG 0.4700 Rp 97,426.00 Rp 45,790.22
Kertas amplas (kayu) MI.1 Lembar 0.5000 Rp 6,435.00 Rp 3,217.50
Kuas roll Buah 0.0100 Rp 34,225.00 Rp 342.25
Kapek Buah 0.0500 Rp 6,000.00 Rp 300.00
Jumlah (2) Rp 72,545.08

Jumlah (1+2) Rp 97,139.08


Overhead 15% Rp 14,570.86
Jumlah Total Rp 111,709.00

10 PEKERJAAN INTALASI LISTRIK

1 Titik Instalasi Lampu SL 18 - 23 VA+ Pitting +PU-CK.O.1


HPS.PU-2021
TENAGA
Upah Memasang LS 1.0000 Rp 60,000.00 Rp 60,000.00
Jumlah (1) Rp 60,000.00
BAHAN
Vetting lampu MJ.14 Buah 1.0000 Rp 16,693.00 Rp 16,693.00
Kabel NYA 2x1,5 mm MJ.2 M 7.0000 Rp 10,095.63 Rp 70,669.41
Saklar MJ.4 Buah 1.0000 Rp 24,180.00 Rp 24,180.00
Lampu SL 23 VA MJ.17 Buah 1.0000 Rp 54,110.00 Rp 54,110.00
Klem Kabel MJ.20 Dos 0.2000 Rp 25,190.00 Rp 5,038.00
Isolasi MJ.21 Buah 0.1000 Rp 10,856.00 Rp 1,085.60
Sekrup MJ.22 Dos 0.1000 Rp 4,006.00 Rp 400.60
Jumlah (2) Rp 172,176.61

Jumlah (1+2) Rp 232,176.61


Overhead 15% Rp 34,826.49
Jumlah Total Rp 267,003.00

1 Titik Instalasi Lampu SL 8 - 14 VA+ Pitting + PU-CK.O.2


HPS.PU-2021
TENAGA
Upah Memasang LS 1.0000 Rp 60,000.00 Rp 60,000.00
Jumlah (1) Rp 60,000.00

BAHAN
Vetting lampu MJ.14 Buah 1.0000 Rp 16,693.00 Rp 16,693.00
Kabel NYA 2x1,5 mm MJ.2 M 7.0000 Rp 10,095.63 Rp 70,669.41
Saklar MJ.4 Buah 1.0000 Rp 24,180.00 Rp 24,180.00
Lampu SL 14 VA MJ.18 Buah 1.0000 Rp 42,276.00 Rp 42,276.00
Klem Kabel MJ.20 Dos 0.2000 Rp 25,190.00 Rp 5,038.00
Isolasi MJ.21 Buah 0.1000 Rp 10,856.00 Rp 1,085.60
Sekrup MJ.22 Dos 0.1000 Rp 4,006.00 Rp 400.60
Jumlah (2) Rp 160,342.61

Jumlah (1+2) Rp 220,342.61


Overhead 15% Rp 33,051.39
Jumlah Total Rp 253,394.00

1 Titik Instalasi Stop Kontak PU-CK.O.3


HPS.PU-2021
TENAGA
Upah Memasang LS 1.0000 Rp 60,000.00 Rp 60,000.00
Jumlah (1) Rp 60,000.00
BAHAN
Stop Kontak MJ.6 Buah 1.0000 Rp 38,330.00 Rp 38,330.00
Kabel NYA 3x2.5 mm MJ.1 M 3.0000 Rp 16,745.63 Rp 50,236.89
Klem Kabel MJ.20 Dos 0.2000 Rp 25,190.00 Rp 5,038.00
Isolasi MJ.21 Buah 0.1000 Rp 10,856.00 Rp 1,085.60
Sekrup MJ.22 Dos 0.1000 Rp 4,006.00 Rp 400.60
Jumlah (2) Rp 95,091.09

Jumlah (1+2) Rp 155,091.09


Overhead 15% Rp 23,263.66
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Jumlah Total Rp 178,354.00

1 Unit MCB PU-CK.O.4


HPS.PU-2021
TENAGA
Upah Memasang LS 1.0000 Rp 60,000.00 Rp 60,000.00
Jumlah (1) Rp 60,000.00
BAHAN
MCB Buah 1.0000 Rp 50,000.00 Rp 50,000.00
Box Buah 1.0000 Rp 8,000.00 Rp 8,000.00
Kabel NYA 3x2.5 mm MJ.1 M 15.0000 Rp 16,745.63 Rp 251,184.45
Klem Kabel MJ.20 Dos 0.4000 Rp 25,190.00 Rp 10,076.00
Isolasi MJ.21 Buah 0.5000 Rp 10,856.00 Rp 5,428.00
Sekrup MJ.22 Dos 0.1000 Rp 4,006.00 Rp 400.60
Jumlah (2) Rp 325,089.05

Jumlah (1+2) Rp 385,089.05


Overhead 15% Rp 57,763.36
Jumlah Total Rp 442,852.00

1 Titik Saklar Ganda PU-CK.O.5


HPS.PU-2021
TENAGA
Upah Memasang 2xL-4 OH 1.0000 Rp 330,000.00 Rp 330,000.00
Jumlah (1) Rp 330,000.00
BAHAN
Saklar Ganda MJ.4 Buah 1.0000 Rp 24,180.00 Rp 24,180.00
Jumlah (2) Rp 24,180.00
PERALATAN
Alat Bantu + Aksesoris LS 1.0000 Rp 2,524.00 Rp 2,524.00
Jumlah (3) Rp 2,524.00

Jumlah (1+2+3) Rp 356,704.00


Overhead 15% Rp 53,505.60
Jumlah Total Rp 410,209.00

1 Titik Saklar Tunggal PU-CK.O.6


HPS.PU-2021
TENAGA
Upah Memasang 2xL-4 OH 1.0000 Rp 330,000.00 Rp 330,000.00
Jumlah (1) Rp 330,000.00
BAHAN
Saklar Tunggal MJ.5 Buah 1.0000 Rp 19,880.00 Rp 19,880.00
Jumlah (2) Rp 19,880.00
PERALATAN
Alat Bantu + Aksesoris LS 1.0000 Rp 2,524.00 Rp 2,524.00
Jumlah (3) Rp 2,524.00

Jumlah (1+2+3) Rp 352,404.00


Overhead 15% Rp 52,860.60
Jumlah Total Rp 405,264.00

1 M' Kabel NYA 2.5 mm PU-CK.O.8


HPS.PU-2021
TENAGA
Upah Memasang 0,1 x L - 4 OH 1.0000 Rp 16,500.00 Rp 16,500.00
Jumlah (1) Rp 16,500.00
BAHAN
Kabel NYA 2.5 mm MJ.2 M 1.1000 Rp 10,095.63 Rp 11,105.19
Pipa Listrik dia, 5/8 MJ.3 M' 1.0500 Rp 10,890.00 Rp 11,434.50
Jumlah (2) Rp 22,539.69
PERALATAN
Alat Bantu + Aksesoris LS 1.0000 Rp 432.10 Rp 432.10
Jumlah (3) Rp 432.10

Jumlah (1+2+3) Rp 39,471.79


Overhead 15% Rp 5,920.77
Jumlah Total Rp 45,392.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

11 PEKERJAAN SANITASI

1 Buah Bak Mandi Fiberglass 0,3 M3 PU-CK.M.6


RSNI T-15-2002
TENAGA
Pekerja pasir/batu L-4 OH 1.8000 Rp 165,000.00 Rp 297,000.00
Tukang pasir/batu L-3 OH 2.7000 Rp 211,000.00 Rp 569,700.00
Kepala tukang pasir/batu L-2 OH 0.5400 Rp 223,000.00 Rp 120,420.00
Mandor pasir/batu L-1 OH 0.1100 Rp 232,000.00 Rp 25,520.00
Jumlah (1) Rp 1,012,640.00
BAHAN
Bak Mandi Fiberglass 0,3 M3 MK.30 Buah 1.0000 Rp 452,750.00 Rp 452,750.00
Jumlah (2) Rp 452,750.00

PERALATAN
Perlengkapan 18%xMK.30 Set 1.0000 Rp 81,495.00 Rp 81,495.00
Jumlah (3) Rp 81,495.00

Jumlah (1+2+3) Rp 1,546,885.00


Overhead 15% Rp 232,032.75
Jumlah Total Rp 1,778,917.00

1 BH Closet duduk / monoblok PU-CK.M.1


RSNI T-15-2002
TENAGA
Pekerja pasir/batu L-4 OH 3.3000 Rp 165,000.00 Rp 544,500.00
Tukang pasir/batu L-3 OH 1.1000 Rp 211,000.00 Rp 232,100.00
Kepala tukang pasir/batu L-2 OH 0.0010 Rp 223,000.00 Rp 223.00
Mandor pasir/batu L-1 OH 0.1600 Rp 232,000.00 Rp 37,120.00
Jumlah (1) Rp 813,943.00
BAHAN
Closet duduk / monoblok MK.22 Buah 1.0000 Rp 2,710,110.00 Rp 2,710,110.00
Jumlah (2) Rp 2,710,110.00

PERALATAN
Perlengkapan 6%xMK.22 Set 1.0000 Rp 162,606.60 Rp 162,606.60
Jumlah (3) Rp 162,606.60

Jumlah (1+2+3) Rp 3,686,659.60


Overhead 15% Rp 552,998.94
Jumlah Total Rp 4,239,658.00

1M Memasang Pipa PVC Tipe AW Dia. 3/4"PU-CK.M.20


RSNI T-15-2002
TENAGA
Pekerja L-4 OH 0.0360 Rp 165,000.00 Rp 5,940.00
Tukang pipa L-3 OH 0.0600 Rp 211,000.00 Rp 12,660.00
Kepala tukang L-2 OH 0.0060 Rp 223,000.00 Rp 1,338.00
Mandor L-1 OH 0.0018 Rp 232,000.00 Rp 417.60
Jumlah (1) Rp 20,355.60
BAHAN
Pipa PVC Tipe AW Dia. 3/4" MK.16 M 1.2000 Rp 9,065.00 Rp 10,878.00
Jumlah (2) Rp 10,878.00

PERALATAN
Perlengkapan 35%xMK.16 Set 1.0000 Rp 3,172.75 Rp 3,172.75
Jumlah (3) Rp 3,172.75

Jumlah (1+2+3) Rp 34,406.35


Overhead 15% Rp 5,160.95
Jumlah Total Rp 39,567.00

1M Memasang Pipa PVC Tipe AW Dia. 2" PU-CK.M.23


RSNI T-15-2002
TENAGA
Pekerja L-4 OH 0.0540 Rp 165,000.00 Rp 8,910.00
Tukang pipa L-3 OH 0.0900 Rp 211,000.00 Rp 18,990.00
Kepala tukang L-2 OH 0.0090 Rp 223,000.00 Rp 2,007.00
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

Mandor L-1 OH 0.0027 Rp 232,000.00 Rp 626.40


Jumlah (1) Rp 30,533.40
BAHAN
Pipa PVC Tipe AW Dia. 2" MK.16 M 1.2000 Rp 70,866.00 Rp 85,039.20
Jumlah (2) Rp 85,039.20

PERALATAN
Perlengkapan 35%xMK.16 Set 1.0000 Rp 5,822.25 Rp 5,822.25
Jumlah (3) Rp 5,822.25

Jumlah (1+2+3) Rp 121,394.85


Overhead 15% Rp 18,209.23
Jumlah Total Rp 139,604.08

1M Memasang Pipa PVC Tipe AW Dia. 4" PU-CK.M.25


RSNI T-15-2002
TENAGA
Pekerja L-4 OH 0.0810 Rp 165,000.00 Rp 13,365.00
Tukang pipa L-3 OH 0.1350 Rp 211,000.00 Rp 28,485.00
Kepala tukang L-2 OH 0.1350 Rp 223,000.00 Rp 30,105.00
Mandor L-1 OH 0.0041 Rp 232,000.00 Rp 951.20
Jumlah (1) Rp 72,906.20
BAHAN
Pipa PVC Tipe AW Dia. 4" MK.11 M 1.2000 Rp 50,611.50 Rp 60,733.80
Jumlah (2) Rp 60,733.80

PERALATAN
Perlengkapan 35%xMK.11 Set 1.0000 Rp 17,714.03 Rp 17,714.03
Jumlah (3) Rp 17,714.03

Jumlah (1+2+3) Rp 151,354.03


Overhead 15% Rp 22,703.10
Jumlah Total Rp 174,057.00

1 BH Kran air Dia. 3/4" atau 1/2" PU-CK.M.26


RSNI T-15-2002
TENAGA
Pekerja L-4 OH -
Tukang pipa L-3 OH 0.1000 Rp 211,000.00 Rp 21,100.0000
Kepala tukang L-2 OH 0.0100 Rp 223,000.00 Rp 2,230.0000
Mandor L-1 OH -
Jumlah (1) Rp 23,330.00
BAHAN
Kran air Dia. 3/4" atau 1/2" MK.32 Buah 1.2000 Rp 22,290.00 Rp 26,748.00
Seal Tape Buah 0.0250 Rp 5,000.00 Rp 125.00
Jumlah (2) Rp 26,873.00

Jumlah (1+2) Rp 50,203.00


Overhead 15% Rp 7,530.45
Jumlah Total Rp 57,733.00

1 Unit Septictank 2 x (1 x 1) dalam 1,5 M + ResPU-CK.M.31


HPS.PU-2021
TENAGA
Pekerja O/H 5.0000 Rp 165,000.00 Rp 825,000.00
Tukang batu O/H 0.5000 Rp 211,000.00 Rp 105,500.00
Kepala Tukang O/H 0.5000 Rp 223,000.00 Rp 111,500.00
Mandor Bangunan O/H 0.2500 Rp 232,000.00 Rp 58,000.00
Jumlah (1) Rp 1,100,000.00
0
0
Bahan
Galian Tanah Biasa Sedalam 1 - 2 M M3 3.6000 Rp 146,385.00 Rp 526,986.00
Semen Portland (PC) @ 50 Kg Zak 5.5000 Rp 103,170.00 Rp 567,435.00
Pasir semen (lokal) M3 2.5000 Rp 745,150.00 Rp 1,862,875.00
Batu bata Buah ### Rp 1,350.00 Rp 1,641,600.00
Besi beton dia 10 mm KG 112.4000 Rp 11,890.00 Rp 1,336,436.00
Kawat ikat beton KG 0.5000 Rp 25,250.00 Rp 12,625.00
M3 0.0880 Rp 2,095,260.00 Rp 184,382.88
NO. ITEM PEKERJAAN KODE SATUAN KOEF.
HARGA SATUAN
JUMLAH HARGA

M 2.0000 Rp 65,900.00 Rp 131,800.00


Jumlah (2) Rp 6,264,139.88

Jumlah (1+2) Rp 7,364,139.88


Overhead 15% Rp 1,104,620.98
Jumlah Total Rp 8,468,760.00

1 Unit Pompa dragon/pompa tangan PU-CK.M.36


HPS.PU-2021
TENAGA

BAHAN
Pompa Dragon Buah 1.0000 Rp 650,000.00 Rp 650,000.00
Shock ulir Buah 1.0000 Rp 25,000.00 Rp 25,000.00
L Bough 2" Buah 2.0000 Rp 6,000.00 Rp 12,000.00
Pipa PVC dia 1" ( D ) Batang 2.0000 Rp 12,500.00 Rp 25,000.00
Lem PVC Buah 0.1000 Rp 10,000.00 Rp 1,000.00
Campuran 1PC : 3PS - import ( 0,4 x 0,4 x 0,4 ) Upah PU-CK.D.2 M3 0.0640 Rp 3,772,937.88 Rp 241,468.02
Jumlah (1) Rp 954,468.02
PERALATAN
Alat bantu LS 1.0000 Rp 25,000.00 Rp 25,000.00
Jumlah (2) Rp 25,000.00

Jumlah (1+2) Rp 979,468.02


Overhead 15% Rp 146,920.20
Jumlah Total Rp 1,126,388.00
DAFTAR HARGA SATUAN UPAH

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL TYPE 45 M2


LOKASI PEKERJAAN : Gg. SEHATI KALIWEDA 2
KABUPATEN : MERAUKE
TAHUN : 2022
PERIODE : JULI - DESEMBER 2021

HARGA DASAR TENAGA


NO. URAIAN TENAGA KODE
(Per Hari ) ( per jam )
1 Mandor Bangunan / Lapangan L-1 Rp 232,000.00 Rp 33,143.00
2 Kepala Tukang (Batu, Pasir, Kayu, dsb) L-2 Rp 223,000.00 Rp 31,858.00
3 Tukang (Batu, Pasir, Kayu, dsb) L-3 Rp 211,000.00 Rp 30,143.00
4 Pekerja L-4 Rp 165,000.00 Rp 23,572.00
5 Mandor Alat Berat (F. Equipment) (*) L-5 Rp 239,000.00 Rp 34,143.00
6 Operator Alat Berat (*) L-6 Rp 211,000.00 Rp 30,143.00
7 Pembantu Operator (*) L-7 Rp 165,000.00 Rp 23,572.00
8 Sopir / Driver (*) L-8 Rp 211,000.00 Rp 30,143.00
9 Pembantu Sopir / Driver (*) L-9 Rp 165,000.00 Rp 23,572.00
10 Mekanik (*) L - 10 Rp 211,000.00 Rp 30,143.00
11 Pembantu Mekanik (*) L - 11 Rp 165,000.00 Rp 23,572.00
12 Surveyor L - 12 Rp 211,000.00 Rp 30,143.00
13 Pembantu Surveyor L - 13 Rp 165,000.00 Rp 23,572.00
DAFTAR HARGA SATUAN BAHAN

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL TYPE 45 M2


LOKASI PEKERJ : Gg. SEHATI KALIWEDA 2
KABUPATEN : MERAUKE
TAHUN : 2022
PERIODE : JULI - DESEMBER 2021

Harga Dasar + Inflasi +


No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
A. BAHAN BAKAR DAN PENCAMPUR
1 Premium (Non Subsidi) - Pertalite MA.1 Liter Rp 14,687.00
2 Solar (Non Subsidi) - Dexlite MA.2 Liter Rp 15,217.00
3 Minyak Tanah (Non Subsidi) - Kerosene MA.3 Liter Rp 14,552.00
4 Minyak Pelumas / Olie MA.4 Liter Rp 42,940.00
5 Minyak Bekisting / Oli Bekas MA.5 Liter Rp 940.00
6 Polimer MA.6 Liter Rp 20,613.00
7 Aspal MA.7 Kg Rp 15,947.00
8 Residu MA.8 Liter Rp 23,979.00

B. BAHAN PASIR, BATU DAN SEMEN


1 Pasir Semen (Import) MB.1 M3 Rp 1,161,410.00
2 Pasir Pasang Lokal (kualitas baik) MB.2 M3 Rp 762,510.00
3 Tanah Timbun biasa MB.3 M3 Rp 265,280.00
4 Tanah Pilihan (Selmat) MB.4 M3 Rp 265,280.00
5 Batu Kerikil/Koral beton (Import) MB.5 M3 Rp 1,197,630.00
6 Batu Kali/Gunung (Import) MB.6 M3 Rp 1,259,630.00
7 Batu Bata Merah MB.7 Buah Rp 1,380.00
8 Batu Cetak 10 x 20 x 30 Cm MB.8 Buah Rp 2,800.00
9 Paving Blok MB.9 Buah Rp 6,750.00
10 Semen Portland (PC) @ 50 Kg MB.10 Zak Rp 103,850.00
11 Semen PC Warna MB.11 Zak Rp 117,183.00
12 Tepung Gypsum MB.12 Zak Rp 98,945.00

C. BAHAN KAYU, TRIPLEKS DLL


1 Balok Kayu Kelas III (Kayu Bus) MC.1 M3 Rp 2,918,110.00
2 Balok Kayu Kelas II (Kayu Rahay) MC.2 M3 Rp 4,193,980.00
3 Balok Kayu Kelas I (Kayu Besi) MC.3 M3 Rp 6,219,840.00
4 Balok Kayu Kelas IV (Kayu Campur) MC.4 M3 Rp 2,629,320.00
5 Papan Kayu Kelas III (Kayu Bus) t : 2-5 cm MC.5 M3 Rp 2,918,110.00
6 Papan Kayu Kelas II (Kayu Rahay) t : 2 cm MC.6 M3 Rp 4,193,980.00
7 Papan Kayu Kelas II (Kayu Rahay) t : 3 cm MC.7 M3 Rp 4,193,980.00
8 Papan Kayu Kelas I (Kayu Besi) t : 2-3 cm MC.8 M3 Rp 6,219,840.00
9 Papan Kayu Kelas IV (tebal = 2-5 cm) MC.9 M3 Rp 2,629,320.00
10 Kayu Lat/Reng/List, Kayu Kelas II MC.10 Batang Rp 25,400.00
11 Tripleks (1,22 x 2,44) cm - tebal 3 mm MC.11 Lembar Rp 65,374.00
12 Tripleks (1,22 x 2,44) cm - tebal 4 mm MC.12 Lembar Rp 81,210.00
13 Tripleks (1,22 x 2,44) cm - tebal 6 mm MC.13 Lembar Rp 106,403.00
14 Tripleks (1,22 x 2,44) cm - tebal 9 mm MC.14 Lembar Rp 161,646.00
15 Tripleks (1,22 x 2,44) cm - tebal 12 mm MC.15 Lembar Rp 208,068.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
16 Tripleks (1,22 x 2,44) cm - tebal 15 mm MC.16 Lembar Rp 286,800.00
17 Tripleks (1,22 x 2,44) cm - tebal 18 mm MC.17 Lembar Rp 307,938.00
18 Tripleks (1,22 x 2,44) cm - tebal 22 mm MC.18 Lembar Rp 312,170.00
19 Teak - Wood (1.22 x 2.44 Cm) - 3 mm MC.19 Lembar Rp 161,160.00
20 Teak - Wood (0.92 x 2.44 Cm) - 4 mm MC.20 Lembar Rp 112,210.00
21 Plywood - Multiplex (9 mm) MC.21 Lembar Rp 479,080.00
22 Melamin MC.22 Lembar Rp 144,862.00
23 Formika Polos (122 x 244) Cm MC.23 Lembar Rp 303,320.00
24 Pelat Asbes Tebal 6 mm MC.24 Lembar Rp 130,450.00
25 Pelat Asbes Tebal 5 mm MC.25 Lembar Rp 67,880.00
26 Pelat Asbes Tebal 4 mm MC.26 Lembar Rp 8,400.00
27 Gypsum Board tebal 9 mm MC.27 Lembar Rp 88,141.00
28 List profil Gypsum Lebar Sampai 5 cm MC.28 M' Rp 35,352.50
29 Hard Board MC.29 Lembar Rp 85,410.00
30 Tiang Kayu Bulat (Dia 20 cm, L=4-6 m) MC.30 Batang Rp 151,410.00
31 Tiang Kayu Bulat (Dia 25-30 cm, L=4-6 m) MC.31 Batang Rp 249,880.00
32 Kayu dolken Ø 8-10, L=4 M MC.32 Batang Rp 17,390.00
33 Patok kayu (Dia = 3 cm, L= 1 m) MC.33 Batang Rp 3,000.00
34 Patok kayu (Dia = 5 cm, L= 5 m) MC.34 Batang Rp 5,000.00
35 Kayu Bakar (Campuran) MC.35 M3 Rp 400,000.00

D. BAHAN BESI, PAKU, ALUMUNIUM DAN KAWAT


1 Besi Beton Dia.6 mm (SNI) MD.1 Kg Rp 14,919.00
2 Besi Beton Dia.8 mm (SNI) MD.2 Kg Rp 14,228.00
3 Besi Beton Dia.10 mm (SNI) MD.3 Kg Rp 14,245.00
4 Besi Beton Dia.12 mm (SNI) MD.4 Kg Rp 14,449.00
5 Besi Beton Dia.14 mm (SNI) MD.5 KG Rp 14,941.00
6 Besi Beton Dia.16 mm (SNI) MD.6 KG Rp 15,272.00
7 Besi Beton Dia.19 mm (SNI) MD.7 KG Rp 16,307.00
8 Besi Beton Dia.22 mm (SNI) MD.8 KG Rp 13,033.00
9 Kawat Beton MD.9 KG Rp 25,090.00
10 Kawat beton / bindrat 4 mm MD.10 KG Rp 25,840.00
11 Paku 1" (2,5 - 3 cm) MD.11 KG Rp 23,044.00
12 Paku 2" (5 cm) MD.12 KG Rp 22,044.00
13 Paku 3" (7 cm) MD.13 KG Rp 21,901.00
14 Paku 4" (10 cm) MD.14 KG Rp 21,758.00
15 Paku 5" (12 - 15 cm) MD.15 KG Rp 22,758.00
16 Paku Campur MD.16 KG Rp 21,901.00
17 Paku Seng MD.17 KG Rp 35,094.00
18 Paku Ardex Ulir MD.18 KG Rp 34,840.00
19 Paku Sirap MD.19 Buah Rp 15,340.00
20 Paku Ondoline MD.20 KG Rp 20,340.00
21 Paku Tembok / Kecil 2/3 MD.21 Buah Rp 366.33
22 Paku/Skrup 5 cm MD.22 KG Rp 27,777.00
23 Kawat Nyamuk (Plastik / Nylon) MD.23 M Rp 22,834.00
24 Kawat Has / Bankhas dia 12 mm MD.24 M2 Rp 24,338.00
25 Kawat Harmonika Has 40x40 mm MD.25 M Rp 72,743.00
26 Kawat burung MN.26 M² Rp 26,077.00
27 Kawat Duri Baja 20 M MD.27 KG Rp 36,310.00
28 Kawat Las 26 MD.28 Dos Rp 164,923.00
29 Timah Solder MD.29 KG Rp 106,776.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
30 Baut Jembatan Dia. <14 mm MD.30 KG Rp 15,340.00
31 Baut Dia, 3/8" - 17.5 + Mur - Ring MD.31 Buah Rp 7,440.00
32 Baut Dia, 3/8" - 12.0/15.0 + Mur - Ring MD.32 Buah Rp 6,740.00
33 Baut Dia, 3/8" - 20.0 + Mur - Ring MD.33 Buah Rp 9,740.00
34 Baut Dia, 3/8" - 35.0 + Mur - Ring MD.34 Buah Rp 6,340.00
35 Besi angkur dia. 8 mm MN.35 Buah Rp 47,840.00
36 Kasa (Ram Ayam) Dia, 10 mm MD.36 M Rp 23,653.00
37 Besi Siku 30 . 30 . 3 - L = 6 Meter MD.37 Batang Rp 89,630.00
38 Besi Siku 50 . 50 . 5 - L = 6 Meter MD.38 Batang Rp 268,073.00
39 Besi Siku 50 . 50 . 6 - L = 6 Meter MD.39 Batang Rp 293,150.00
40 Besi Siku 40 . 40 . 4 - L = 6 Meter MD.40 Batang Rp 234,100.00
41 Besi Siku 40 . 40 . 5 - L = 6 Meter MD.41 Batang Rp 170,153.00
42 Besi Siku 20 . 20 . 3 - L = 6 Meter MD.42 Batang Rp 71,920.00
43 Besi Plat 1.0 mm - 120 x 240 Cm MD.43 Lembar Rp 526,150.00
44 Besi Plat 1.2 mm - 120 x 240 Cm MD.44 Lembar Rp 618,550.00
45 Besi Plat 2.0 mm - 120 x 240 Cm MD.45 Lembar Rp 990,650.00
46 Besi Plat 3.0 mm - 120 x 240 Cm MD.46 Lembar Rp 1,446,790.00
47 Besi Plat 12 mm -120 x 240 cm MD.47 Lembar Rp 1,504,170.00
48 Besi Strip 2 x 4mm MD.48 Batang Rp 45,910.00
49 Besi Strip 3 x 4mm MD.49 Batang Rp 58,700.00
50 Besi Strip 4 x 4mm MD.50 Batang Rp 94,715.00
51 Besi Strip 5 x 4mm MD.51 Batang Rp 139,220.00
52 Waltermur Dia 16 mm MD.52 Buah Rp 24,710.00
53 Gording lips chanel 150.65.20.2,3 ( 6 N ) MD.53 Batang Rp 729,710.00
54 Baja profil IWF MD.54 KG Rp 21,280.00
55 Besi gording canal MD.55 KG Rp 22,829.00
56 Water mur MD.56 KG Rp 15,280.00
57 Sealent MD.57 Tube Rp 44,446.00

E. BAHAN PENUTUP ATAP


1 Seng Gelombang BJLS 0,30 ME.1 Lembar Rp 90,703.00
2 Seng Gelombang BJLS 0,22 ME.2 Lembar Rp 69,300.00
3 Seng Gelombang BJLS 0,20 ME.3 Lembar Rp 61,783.00
4 Atap Seng Plastik Gelombang Kecil ME.4 Lembar Rp 67,755.00
5 Atap Seng Gelombang Besar Fiber Glass ME.5 Lembar Rp 99,500.00
6 Seng Plat BJLS 0.30 ME.6 Lembar Rp 48,036.00
7 Seng Plat BJLS 0.20 ME.7 Lembar Rp 46,900.00
8 Genteng Metal - Multiroof ME.8 Lembar Rp 66,955.00
9 Nok Genteng Metal - Multiroof ME.9 Bh Rp 47,955.00
10 Atap Allumunium Gelombang ME.10 M2 Rp 71,580.00

F. BAHAN KERAMIK
1 Ubin Abu-Abu 20 x 20 Cm MF.1 Buah Rp 3,350.00
2 Ubin Abu-Abu 30 x 30 Cm MF.2 Buah Rp 7,522.00
3 Ubin Abu-Abu 40 x 40 Cm MF.3 Buah Rp 15,273.00
4 Ubin Warna 20 x 20 Cm MF.4 Buah Rp 3,175.00
5 Ubin Warna 30 x 30 Cm MF.5 Buah Rp 7,329.00
6 Ubin Warna 40 x 40 Cm MF.6 Buah Rp 14,106.00
7 Ubin Teraso Ukuran 30 x 30 cm MF.7 Buah Rp 6,840.00
8 Ubin Teraso Ukuran 40 x 40 cm MF.8 Buah Rp 14,606.00
9 Ubin Granito Ukuran 30 x 30 cm MF.9 Buah Rp 6,568.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
10 Ubin Granito Ukuran 40 x 40 cm MF.10 Buah Rp 12,606.00
11 Ubin Teralux Kerang Ukuran 30 x 30 cm MF.11 Buah Rp 7,522.00
12 Ubin Teralux Kerang Ukuran 40 x 40 cm MF.12 Buah Rp 14,690.00
13 Ubin Teralux Marmer Ukuran 30 x 30 cm MF.13 Buah Rp 11,613.00
14 Ubin Teralux Marmer Ukuran 40 x 40 cm MF.14 Buah Rp 22,523.00
15 Ubin Teralux Marmer Ukuran 60 x 60 cm MF.15 Buah Rp 73,366.00
16 Keramik Artistik 10x20; 15x15 cm MF.16 Buah Rp 1,370.00
17 Keramik Artistik 10x10 atau 5x20 cm MF.17 Buah Rp 750.00
18 Keramik Lantai 20 x 20 cm MF.18 Buah Rp 3,223.00
19 Keramik Lantai 20 x 30 cm MF.19 Buah Rp 4,887.00
20 Keramik Lantai 30 x 30 cm MF.20 Buah Rp 6,009.00
21 Keramik Lantai 30 x 30 berglasir MF.21 Buah Rp 7,159.00
22 Keramik Lantai 30 x 30 berglasir (Mozaik) MF.22 Buah Rp 7,068.00
23 Keramik Lantai 40 x 40 cm MF.23 Buah Rp 13,290.00
24 Keramik Lantai 50 x 50 cm MF.24 Buah Rp 24,185.00
25 Keramik Lantai 60 x 60 cm MF.25 Buah Rp 90,500.00
26 Keramik Dinding 10 x 20 cm MF.26 Buah Rp 1,520.00
27 Keramik Dinding 20x20 atau 20x25 cm MF.27 Buah Rp 3,306.00
28 Ubin Dinding Porselin 11 x 11 MF.28 Buah Rp 770.00
29 Ubin Dinding Porselin 10 x 20 cm MF.29 Buah Rp 1,156.00
30 Ubin Dinding Porselin 20 x 20 MF.30 Buah Rp 3,050.00
31 Plint Ubin Abu-Abu 15 x 20 cm MF.31 Buah Rp 12,690.00
32 Plint Ubin Abu-Abu 10 x 30 cm MF.32 Buah Rp 10,200.00
33 Plint Ubin Abu-Abu 10 x 40 cm MF.33 Buah Rp 12,440.00
34 Plint Ubin Warna 10 x 20 cm MF.34 Buah Rp 4,620.00
35 Plint Ubin Warna 10 x 30 cm MF.35 Buah Rp 10,200.00
36 Plint Ubin Warna 10 x 40 cm MF.36 Buah Rp 11,690.00
37 Plint Ubin Teraso 10 x 30 cm MF.37 Buah Rp 10,200.00
38 Plint Ubin Teraso 10 x 40 cm MF.38 Buah Rp 12,690.00
39 Plint Ubin Granito 10 x 40 cm MF.39 Buah Rp 12,690.00
40 Plint Ubin Granito 10 x 30 cm MF.40 Buah Rp 8,200.00
41 Plint Ubin Teralux Kerang 10 x 40 cm MF.41 Buah Rp 8,190.00
42 Plint Ubin Teralux Kerang 10 x 30 cm MF.42 Buah Rp 8,200.00
43 Plint Ubin Teralux Marmer 10 x 60 cm MF.43 Buah Rp 33,710.00
44 Plint Ubin Teralux Marmer 10 x 40 cm MF.44 Buah Rp 10,190.00
45 Plint Ubin Teralux Marmer 10 x 30 cm MF.45 Buah Rp 7,700.00
46 Plint Keramik Artistik 10 x 20 cm MF.46 Buah Rp 5,120.00
47 Plint Keramik Artistik 10 x 10 cm MF.47 Buah Rp 4,600.00
48 Plint Keramik Artistik 5 x 20 cm MF.48 Buah Rp 5,600.00
49 Plint Keramik Artistik 10 x 30 cm MF.49 Buah Rp 10,200.00
50 Marmer Ukuran 100 x 100 cm MF.50 Buah Rp 359,430.00
51 Wall paper (Lebar 50 cm) MF.51 M2 Rp 310,404.00
52 Batu Paras MF.52 Buah Rp 22,977.00
53 Batu Tempel Hitam MF.53 Buah Rp 28,431.00

G. BAHAN KACA
1 Kaca Polos 3 mm MG.1 M2 Rp 147,331.00
2 Kaca Polos 5 mm MG.2 M2 Rp 194,667.00
3 Kaca Buram 3 mm MG.3 M2 Rp 109,938.00
4 Kaca Buram 4 mm MG.4 M2 Rp 110,378.00
5 Kaca Buram 5 mm MG.5 M2 Rp 199,029.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
6 Kaca Naco / Louver - 7 Clips (polos) MG.6 Buah Rp 149,100.00
7 Kaca Naco / Louver - 8 Clips (polos) MG.7 Buah Rp 162,830.00
8 Kaca Naco / Louver - 9 Clips (polos) MG.8 Buah Rp 182,760.00
9 Kaca Naco / Louver - 10 Clips (polos) MG.9 Buah Rp 194,533.00
10 Kaca Rayban 25 % - tebal 5 mm MG.10 M2 Rp 215,630.00
11 Kaca Acrylic (Kaca Plastik) - 5 mm MG.11 Lembar Rp 1,464,560.00

H. BAHAN/ALAT PENGGANTUNG
1 Kunci Tanam (Setara Cap Kuda Terbang) MH.1 Set Rp 112,713.00
2 Kunci Tanam - 2 Slaagh MH.2 Set Rp 183,280.00
3 Kunci Tanam - 1 Slaagh MH.3 Set Rp 157,713.00
4 Kunci Tanam (Setara Cap Anchor / Yale) MH.4 Set Rp 198,880.00
5 Kunci Gembok MH.5 Set Rp 30,940.00
6 Engsel 4" (Untuk Pintu) MH.6 Pasang Rp 30,023.00
7 Engsel 3" (Untuk Jendela) MH.7 Pasang Rp 22,190.00
8 Engsel Kupu-Kupu T MH.8 Pasang Rp 26,190.00
9 Engsel Nylon Kuningan 4" MH.9 Pasang Rp 17,690.00
10 Engsel Biasa 3" (Untuk Jendela) MH.10 Pasang Rp 14,773.00
11 Hak Angin / Kait Angin MH.11 Buah Rp 13,106.00
12 Espagnolet MH.12 Set Rp 10,190.00
13 Grendel Tanam (Pintu) MH.13 Buah Rp 88,190.00
14 Grendel Besar / Kecil MH.14 Buah Rp 42,773.00
15 Tarikan Pintu MH.15 Buah Rp 98,773.00
16 Tarikan Jendela MH.16 Buah Rp 11,023.00

I. BAHAN CAT
1 Amplas Kertas (Amplas Kayu) MI.1 Lembar Rp 6,435.00
2 Amplas Besi MI.2 Lembar Rp 5,719.00
3 Dempul Kayu MI.3 Kg Rp 36,193.00
4 Cat Meny Kayu MI.4 Kg Rp 36,993.00
5 Cat Meny Besi MI.5 Kg Rp 44,110.00
6 Cat Kayu MI.6 Kg Rp 67,026.00
7 Cat Besi MI.7 Kg Rp 71,360.00
8 Cat Kilat LN MI.8 Kg Rp 71,860.00
9 Minyak Cat / Thinner MI.9 Kg Rp 40,943.00
10 Cat Tembok (Setara Dulux Weathershield) MI.10 Kg Rp 97,426.00
11 Plamur Tembok MI.11 Zak Rp 143,730.00
12 Cat Tembok Biasa (1 Klg @ 5 Kg) MI.12 Kaleng Rp 84,110.00
13 Cat Besi Crom MI.13 Kg Rp 57,276.00
14 Cat Besi (Setara Nippon Paint) MI.14 Kg Rp 77,610.00
15 Politur Kaleng (Setara Apache) MI.15 Kg Rp 68,235.00
16 Floor Hardener MI.16 KG Rp 66,110.00

J. BAHAN LISTRIK DAN ELEKTRONIKA


1 Kabel Listrik NYM/NYA 3x2.5 mm MJ.1 Roll Rp 1,674,563.00
2 Kabel Listrik NYM/NYA 2x1.5 mm MJ.2 Roll Rp 1,009,563.00
3 Pipa Listrik dia, 5/8 MJ.3 Batang Rp 10,890.00
4 Saklar Double - Tempel MJ.4 Buah Rp 24,180.00
5 Saklar Tunggal / Engkel - Tempel MJ.5 Buah Rp 19,880.00
6 Stop Kontak 500 Watt - Tempel MJ.6 Buah Rp 38,330.00
7 Stop Kontak 1000 Watt - Tempel MJ.7 Buah Rp 53,830.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
8 Home Saklar 1 Fase Komplit MJ.8 Buah Rp 829,273.00
9 Lampu TL 1 x 40 Watt Komplit MJ.9 Buah Rp 141,360.00
10 Lampu TL 1 x 20 Watt Komplit MJ.10 Buah Rp 89,610.00
11 Lampu Pijar 40 Watt Komplit MJ.11 Buah Rp 20,710.00
12 Lampu Pijar 60 Watt Komplit MJ.12 Buah Rp 21,110.00
13 Lampu Pijar 100 Watt Komplit MJ.13 Buah Rp 22,610.00
14 Vitting Lampu MJ.14 Buah Rp 16,693.00
15 Lampu XL 40 Watt MJ.15 Set Rp 81,110.00
16 Lampu XL 20 Watt MJ.16 Set Rp 61,610.00
17 Lampu SL 23 Watt MJ.17 Set Rp 54,110.00
18 Lampu SL 14 Watt MJ.18 Set Rp 42,276.00
19 Sekring Kas 1 Group (Biasa) MJ.19 Buah Rp 550,350.00
20 Klem Kabel MJ.20 Dus Rp 25,190.00
21 Isolasi Listrik MJ.21 Buah Rp 10,856.00
22 Sekrup MJ.22 Dus Rp 4,006.00
23 Panil Distribusi MJ.23 Buah Rp 12,500,940.00

K. BAHAN PIPA DAN SANITAIR


1 Pipa GIP (Leideng) Dia. 1/2" - 6 Meter MK.1 Batang Rp 163,390.00
2 Pipa GIP (Leideng) Dia. 3/4" - 6 Meter MK.2 Batang Rp 215,233.00
3 Pipa GIP (Leideng) Dia. 1" - 6 Meter MK.3 Batang Rp 300,730.00
4 Pipa GIP (Leideng) Dia. 1.25" - 6 Meter MK.4 Batang Rp 365,103.00
5 Pipa GIP (Leideng) Dia. 1.5" - 6 Meter MK.5 Batang Rp 423,300.00
6 Pipa GIP (Leideng) Dia. 2" - 6 Meter MK.6 Batang Rp 588,803.00
7 Pipa GIP (Leideng) Dia. 3" - 6 Meter MK.7 Batang Rp 999,573.00
8 Pipa GIP (Leideng) Dia. 4" - 6 Meter MK.8 Batang Rp 1,387,920.00
9 Pipa PVC Dia. 5" - 4 Meter (AW) MK.9 Batang Rp 803,210.00
10 Pipa PVC Dia. 4" - 4 Meter (AW) MK.10 Batang Rp 291,196.00
11 Pipa PVC Dia. 4" - 4 Meter (D) MK.11 Batang Rp 202,446.00
12 Pipa PVC Dia. 3" - 4 Meter (D) MK.12 Batang Rp 132,366.00
13 Pipa PVC Dia. 2" - 4 Meter (D) MK.13 Batang Rp 70,866.00
14 Pipa PVC Dia. 1" - 4 Meter (D) MK.14 Batang Rp 49,016.00
15 Pipa PVC Dia. 1/2" - 4 M MK.15 Batang Rp 29,836.00
16 Pipa PVC Dia. 3/4" - 4 M MK.16 Batang Rp 36,260.00
17 Pipa PVC Dia. 2,5" - 4 M MK.17 Batang Rp 104,846.00
18 Talang PVC Oval 6" - 4 Meter MK.18 Batang Rp 92,060.00
19 Talang PVC Oval 8" - 4 Meter MK.19 Batang Rp 126,540.00
20 Talang PVC Kotak 4" - 4 Meter MK.20 Batang Rp 157,863.00
21 Talang PVC Kotak 8" - 4 Meter MK.21 Batang Rp 569,140.00
22 Closed Duduk Porselin Komplit MK.22 Buah Rp 2,710,110.00
23 Closet duduk (siram) MK.23 Buah Rp 1,236,070.00
24 Closed Jongkok Porselin (Standar) MK.24 Buah Rp 487,630.00
25 Closed Jongkok Fiber Glass / Plastik MK.25 Buah Rp 122,405.00
26 Urinoir MK.26 Buah Rp 1,650,800.00
27 Wastafel Porselin MK.27 Buah Rp 608,300.00
28 Bak Air / Fiber Glass 1 M3 MK.28 Buah Rp 444,130.00
29 Bak Air / Fiber Glass 1/2 M3 MK.29 Buah Rp 398,300.00
30 Bak Air / Fiber Glass 1/4 M3 MK.30 Buah Rp 452,750.00
31 Tangki Air / Fiber Glass 1 M3 MK.31 Buah Rp 1,954,926.00
32 Kran Air 3/4" MK.32 Buah Rp 22,290.00
33 Kran Air 1/2" MK.33 Buah Rp 20,090.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
34 Kran Air 1" MK.34 Buah Rp 27,356.00
35 Stop Kran 1/2" MK.35 Buah Rp 20,440.00
36 Doble Neple GIP 1/2" MK.36 Buah Rp 15,440.00
37 Soccet 1/2" MK.37 Buah Rp 14,190.00
38 Elbow GIP 90º x 1/2" ( PE ) MK.38 Buah Rp 16,565.00
39 Tee 1/2" x 1/2" MK.39 Buah Rp 12,065.00
40 Hand Kran 1/2" Besi MK.40 Buah Rp 72,065.00
41 Dop GIP 1/2" MK.41 Buah Rp 17,440.00
42 Water Meter 1/2" MK.42 Buah Rp 291,370.00
43 Clamp Sadle 2" mm x 1/2" ( PE ) MK.43 Buah Rp 66,370.00
44 Pengaman Box Meter MK.44 Buah Rp 251,370.00
45 Pipa HDPE Ø 150 mm MK.45 M Rp 400,400.00
46 Pipa HDPE Ø 100 mm MK.46 M Rp 196,920.00
47 Pipa HDPE Ø 75 mm MK.47 M Rp 103,930.00
48 Pipa HDPE Ø 50-63 mm MK.48 M Rp 70,170.00
49 Tee All Flange Ø 50 x 50 mm (HDPE) MK.49 Buah Rp 456,370.00
50 Tee All Flange Ø 75 x 50 mm (HDPE) MK.50 Buah Rp 481,480.00
51 Tee All Flange Ø 75 x 75 mm (HDPE) MK.51 Buah Rp 506,580.00
52 Tee All Flange Ø 100 x 75 mm (HDPE) MK.52 Buah Rp 656,690.00
53 Bend 90 All Flange Ø 50 mm (HDPE) MK.53 Buah Rp 211,740.00
54 Bend 90 All Flange Ø 75 mm (HDPE) MK.54 Buah Rp 340,750.00
55 Bend 90 All Flange Ø 100 mm (HDPE) MK.55 Buah Rp 55,920.00
56 Gate Valve Flange Ø 50 mm MK.56 Buah Rp 1,864,950.00
57 Gate Valve Flange Ø 75 mm MK.57 Buah Rp 2,365,730.00
58 Gate Valve Flange Ø 1/2" MK.58 Buah Rp 200,200.00
59 Stub Flange Ø 50 mm MK.59 Buah Rp 201,240.00
60 Stub Flange Ø 75 mm MK.60 Buah Rp 602,400.00
61 Stub Flange Ø 100 mm MK.61 Buah Rp 842,980.00
62 End Cap (Dop) Ø 50 mm (HDPE) MK.62 Buah Rp 37,319.00
63 End Cap (Dop) Ø 75 mm (HDPE) MK.63 Buah Rp 88,113.00
64 Stop Cock (PIT Kran) 1/2" MK.64 Buah Rp 950,450.00
65 Reducer Ø 75 x 75 mm (HDPE) MK.65 Buah Rp 529,440.00
66 Reducer Ø 75 x 50 mm (HDPE) MK.66 Buah Rp 504,380.00
67 Quil Elbow HDPE (adaptor) Ø15 (1/2") MK.67 Buah Rp 49,740.00
68 Pipa Input HDPE Ø 1/2" MK.68 Buah Rp 40,140.00

M. BETON PRACETAK
1 Dwiker Sumur/Gorong2 Ø 1 m, H 60 cm MM.1 Buah Rp 949,550.00
2 Dwiker Sumur/Gorong2 Ø 0,8 m, H 60 cm MM.2 Buah Rp 811,330.00
3 Dwiker/Gorong2 Ø 0,6 m, H 80 cm MM.3 Buah Rp 743,610.00
4 Dwiker/Gorong2 Ø 0,45 m, H 80 cm MM.4 Buah Rp 713,210.00

N. BAHAN BANGUNAN LAIN


1 Lem Aica Aibon MN.1 KG Rp 71,520.00
2 Lem Fox MN.2 KG Rp 50,735.00
3 Lem Vinyl MN.3 KG Rp 20,360.00
4 Ijuk MN.4 KG Rp 27,200.00
5 Pipa Plastik dia, 3" (AW) MN.5 Batang Rp 234,006.00
6 Galvanies / Lysplank MN.6 Lembar Rp 288,400.00
7 Mata bor MN.7 Buah Rp 88,403.00
8 Mata gurinda MN.8 Buah Rp 14,100.00
Harga Dasar + Inflasi +
No. Nama Barang Kode Barang Satuan
Ongkos angkut

1 2 3 4 5
9 Gas elpiji MN.9 KG Rp 20,610.00
10 Oksigen (@50 kg/btl) MN.10 KG Rp 186,990.00
11 Kuas Cat Minyak MN.11 Buah Rp 31,600.00
12 Kuas Roll (Cat Tembok) MN.12 Buah Rp 34,225.00
DAFTAR ANALISA
ONGKOS ANGKUT PER 200 KM

ANALISA ONGKOS ANGKUT RADIUS 200 KM

DATA UMUM LOKASI PEKERJAAN

Jarak Angkut Rata-Rata Material Ke Loksi Pekerjaan = - Km


Kapasitas Maksimum Dump. Truck 3 - 4 M3 = 6.00 Ton
Kecepatan Rata-Rata Muatan = 45.00 Km / Jam
Kecepatan Rata-Rata Kosong = 60.00 Km / Jam

ONGKOS PENGGUNAAN / SEWA DUMP TRUCK 3 - 4 M3

1 Unit Dump Truck 3 - 4 M3 Rp. - / 1 Jam = - / Jam

WAKTU YANG DIPERLUKAN

Waktu muat = 10.00 Menit


Waktu bongkar = 5.00 Menit
Lain-Lain = 3.00 Menit
Perjalanan PP 2x - Km x 60 Menit = - Menit
45.00 Km / Jam
Jumlah = 18.00 Menit

Ongkos angkut 1 Ret = 6 Ton Kap. 3 -4 M3 0.30 x - = -


Ongkos Angkut Untuk 1 Ret -

ANALISA BONGKAR MUAT RADIUS 200 KM

1 Semen PC @ 50 KG ( BJ. 2.7 T/M3 ) 1 Ton = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 60 Zak @ 50 Kg 1 Zak = Rp. -

2 Solar, Bensin, Minyak Tanah, Pelumas dll @ 200 Ltr ( BJ. 0.83 T/M3 ) 1 Drum = Rp. -
Untuk 1 Ret Kapasitas Maks 6 Ton ==== 15 Drum 1 Ltr = Rp. -

3 Aspal Bitumen 1 Drum Kap. 155 Ltr (Bj. 1.1 T/M3) 1 Drum = Rp. -
Untuk 1 Ret Kapasitas Maks 6 Ton ==== 18 Drum 1 Ltr = Rp. -

4 Baja Tulangan 1 Ton = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton 1 Kg = Rp. -

5 Pasir Pasang / Beton ( BJ. 1.6 T/M3 ) 1 Ret = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 2.5 M3 1 M3 = Rp. -

6 Kerikil / Batu Pecah ( BJ. 1.55 T/M3 ) 1 Ret = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 2.58 M3 1 M3 = Rp. -
DAFTAR ANALISA
ONGKOS ANGKUT PER 5 KM

ANALISA ONGKOS ANGKUT RADIUS 5 KM

DATA UMUM LOKASI PEKERJAAN

Jarak Angkut Rata-Rata Material Ke Lokasi Pekerjaan = 5.00 Km


Kapasitas Maksimum Dump. Truck 3 - 4 M3 = 6.00 Ton
Kecepatan Rata-Rata Muatan = 45.00 Km / Jam
Kecepatan Rata-Rata Kosong = 60.00 Km / Jam

ONGKOS PENGGUNAAN / SEWA DUMP TRUCK 3 - 4 M3

1 Unit Dump Truck 3 - 4 M3 Rp. - / 1 Jam = - / Jam

WAKTU YANG DIPERLUKAN

Waktu muat = 10.00 Menit


Waktu bongkar = 5.00 Menit
Lain-Lain = 2.00 Menit
Perjalanan PP 2x 5.00 Km x 60 Menit = 13.33 Menit
45.00 Km / Jam
Jumlah = 30.33 Menit

Ongkos angkut 1 Ret = 6 Ton Kap. 3 -4 M3 0.51 x - = -


Ongkos Angkut Untuk 1 Ret -

ANALISA BONGKAR MUAT RADIUS 5 KM

1 Semen PC @ 50 KG ( BJ. 2.7 T/M3 ) 1 Ton = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 60 Zak @ 50 Kg 1 Zak = Rp. -

2 Solar, Bensin, Minyak Tanah, Pelumas dll @ 200 Ltr ( BJ. 0.83 T/M3 ) 1 Drum = Rp. -
Untuk 1 Ret Kapasitas Maks 6 Ton ==== 15 Drum 1 Ltr = Rp. -

3 Aspal Bitumen 1 Drum Kap. 155 Ltr (Bj. 1.1 T/M3) 1 Drum = Rp. -
Untuk 1 Ret Kapasitas Maks 6 Ton ==== 18 Drum 1 Ltr = Rp. -

4 Baja Tulangan 1 Ton = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton 1 Kg = Rp. -

5 Pasir Pasang / Beton ( BJ. 1.6 T/M3 ) 1 Ret = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 2.5 M3 1 M3 = Rp. -

6 Kerikil / Batu Pecah ( BJ. 1.55 T/M3 ) 1 Ret = Rp. -


Untuk 1 Ret Kapasitas Maks 6 Ton ==== 2.58 M3 1 M3 = Rp. -
D. PEMBANGUNAN AIR BERSIH (SUMUR BOR DAN MENARA AIR)
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN VOL SAT.
(Rp) (Rp)

I. PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.000 Ls 200,000.00 200,000.00
2 Pengukuran dan Pematokan 1.000 Ls 200,000.00 200,000.00
Sub Jumlah 400,000.00

II. PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi 1.290 M³ #REF! #REF!
2 Urugan Tanah Kembali 0.430 M³ #REF! #REF!
3 Urugan Pasir Bawah Pondasi 0.080 M³ #REF! #REF!
Sub Jumlah #REF!

III. PEKERJAAN BETON/LANTAI/ PASANGAN


1 Pondasi Cor Bertulang 1pc : 3ps Uk.20/50/50
- Cor beton 1pc : 3ps 0.390 M3 #REF! #REF!
- Bekesting Pondasi 4.200 M2 #NAME? #NAME?
2 Kolom Cor Bertulang 1pc : 3Ps Uk.20/20
- Cor Beton 1pc : 3 ps 0.480 M3 #REF! #REF!
- Besi Tulangan Utama 4@ 12 mm 53.280 Kg #NAME? #NAME?
- Besi Tulangan Begel @ 8 mm - 15 cm 25.140 Kg #NAME? #NAME?
- Bekesting Kolom 4.800 M2 21,760.00 104,448.00
3 Ringbalk Cor Bertulang 1 pc : 3ps Uk. 15/20
- Cor Beton 1pc : 3ps 0.280 M3 #REF! #REF!
- Besi Tulangan Utama 4@ 12 mm 37.300 Kg #NAME? #NAME?
- Besi Tulangan Begel @ 8 mm - 15 cm 15.930 Kg #NAME? #NAME?
- Bekesting Balok 4.140 M2 #NAME? #NAME?
4 Plat Lantai Cor Bertulang 1pc : 3 ps, Tebal=10 cm
- Cor Beton 1 pc : 3ps 0.482 M3 #REF! #REF!
- Besi Tulangan Utamam @ 12 mm - 15 cm 298.936 Kg #NAME? #NAME?
- Bekesting Lantai 8.416 M2 #NAME? #NAME?
Sub Jumlah #REF!

IV. PEKERJAAN JARINGAN PIPA


1 Pembuatan sumur bor, komplit 1.000 Unit 35,000,000.00 35,000,000.00
2 Pengadaan dan pemasangan Pompa 1.000 Unit 3,500,000.00 3,500,000.00
3 Pengadaan dan pemasangan Profiltank 2200 ltr 2.000 Unit 8,280,000.00 16,560,000.00
4 Pemasangan Pipa Outlet/Inlet Pipa PVC Dia. 1" 25.000 M' #REF! #REF!
5 Pemasangan Pipa Outlet/Inlet Pipa PVC Dia. 3/4" 200.000 M' #REF! #REF!
6 Pengadaan Dan Pemasangan asesoris jaringan pipa 1.000 Ls 2,000,000.00 2,000,000.00
7 Pengadaan dan Pemasangan mainhole plat besi 2 mm 1.000 Ls 2,000,000.00 2,000,000.00
Sub Jumlah #REF!

REKAPITULASI :
I. PEKERJAAN PERSIAPAN …………………………………………..Rp,- 400,000.00

II. PEKERJAAN TANAH DAN PASIR …………………………………………..Rp,- #REF!

III. PEKERJAAN BETON/LANTAI/PASANGAN …………………………………………..Rp,- #REF!

IV. PEKERJAAN JARINGAN PIPA …………………………………………..Rp,- #REF!

Jumlah Harga Pekerjaan …………………………………………..Rp,- #REF!

Anda mungkin juga menyukai