1. GALIAN TANAH
A. GALIAN TANAH FOOTPLAT
Panjang x Lebar x dalam Jml titik Volume
FP1= 0.7 x 0.7 x 1.5 x 8 = 5.88 M3
44.2 m1
0.20 M3
PEMBESIAN
Telapak
Panjang x Jumlah x Besi ø 10
X 2 x 6 x 0.617 = 7.40 Kg
Y 2 x 6 x 0.617 = 7.40 Kg
14.81 x 8 = 118.464
Peudestail
Panjang x Jumlah x Besi ø 12
2 x 4 x 0.888 = 7.11 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 14 x 0.39488 = 3.96 Kg
= 11.07 Kg
PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 10
2.5 x 4 x 0.617 = 6.17 Kg
Beugel
Panjang x Jumlah x Besi ø 8
6.00 x 1 x 0.39488 = 2.37 Kg
= 8.54 Kg
1 STR Jumlah STR
8.54 x 0 = 0.00 Kg
Volume Pembesian 0.000 Kg
BETON = 0.00 BH
PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
44.2 x 4 x 0.888 = 157.08 Kg
Panjang x Jumlah x Besi ø 8
44.2 x 2 x 0.395 = 34.91 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 296 x 0.39488 = 81.73 Kg
= 273.72 Kg
PEMBESIAN
Panjang x Jumlah x Besi ø 8 Singgel
ZONA 1
X= 11.55 x 9 x 0.395 x 1 = 42.42 Kg
Y= 4.15 x 24 x 0.395 x 1 = 39.49 Kg
81.91 Kg
2.397 m3
Volume Beton 2.397 M3
PEMBESIAN
Tulangan Pokok
Tinggi x Jumlah x Besi ø 12
4 x 4 x 0.888 = 14.22 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 28 x 0.39488 = 7.65 Kg
= 21.86 Kg
1 Kolom Jumlah Kolom
21.86 x 8 = 174.91 Kg
URAIAN PERHITUNGAN VOLUME
Volume Pembesian 174.906 Kg
BEGESTING
= 8 Titik
Tinggi x Lebar x Jumlah
VOL= 4 x 0.4 x 8 = 12.8 m2
Volume Begesting 12.800 m2
BETON = 8.00 Titik
Panjang x Lebar x Tinggi x Jumlah = Volume
0.15 x 0.2 x 4 x 8.00 = 0.96 m3
PEMBESIAN
Tulangan Pokok
Tinggi x Jumlah x Besi ø 10
4 x 4 x 0.617 = 9.87 Kg
Beugel
Panjang x Jumlah x Besi ø 6
0.58 x 28 x 0.22212 = 3.56 Kg
= 13.44 Kg
1 Kolom Jumlah Kolom
13.44 x 12 = 161.24 Kg
Volume Pembesian 161.235 Kg
BEGESTING
= 12 Titik
Tinggi x Lebar x Jumlah
VOL= 4 x 0.3 x 12 = 14.4 m2
Volume Begesting 14.400 m2
BETON = 12.00 Titik
Panjang x Lebar x Tinggi x Jumlah = Volume
0.15 x 0.15 x 4 x 12.00 = 1.08 m3
PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 8
44.2 x 4 x 0.395 = 69.81 Kg
Beugel
Panjang x Jumlah x Besi ø 6
0.60 x 296 x 0.222 = 39.40 Kg
= 109.22 Kg
Volume Pembesian 109.219 Kg
BEGESTING Panjang = 44.2 M1
Panjang x Lebar x Jumlah
VOL= 44.2 x 0.3 x 1 = 13.26 m2
Volume Begesting 13.260 m2
BETON Panjang = 44.2 M1
60.2 M1
PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
60.2 x 4 x 0.888 = 213.95 Kg
URAIAN PERHITUNGAN VOLUME
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 402 x 0.395 = 111.21 Kg
= 325.16 Kg
Volume Pembesian 325.157 Kg
BEGESTING Panjang = 60.2 M1
Panjang x Lebar x Jumlah
VOL= 60.2 x 0.4 x 1 = 24.08 m2
Volume Begesting 24.080 m2
BETON Panjang = 60.2 M1
ATAS RUANGAN 02
Panjang = 4.85 M
Lebar = 4.15 M
ATAS RUANGAN 01
Pembesian Panjang x Jumlah x Besi ø 10
X= 4.85 x 29 x 0.617 x 1 = 85.78 Kg
Y= 4.15 x 33 x 0.617 x 1 = 85.35 Kg
171.14 Kg
ATAS RUANGAN 02
Pembesian Panjang x Jumlah x Besi ø 10
X= 4.85 x 29 x 0.617 x 1 = 85.78 Kg
Y= 4.15 x 33 x 0.617 x 1 = 85.35 Kg
171.14 Kg
BEGESTING
Panjang x Lebar x Jumlah
ATAS RUANGAN 01 4.85 x 4.15 x 1 = 20.1275 m2
ATAS RUANGAN 02 4.85 x 4.15 x 1 = 20.1275 m2
ATAS Kamar Mandi 01 1.85 x 1.50 x 1 = 2.775 m2
ATAS Kamar Mandi 02 1.85 x 1.50 x 1 = 2.775 m2
45.805 M2
4.581 m3
2.204 m3
PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
44.2 x 4 x 0.888 = 157.08 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 296 x 0.395 = 81.73 Kg
= 238.81 Kg
Volume Pembesian 238.810 Kg
BEGESTING Panjang = 44.2 M1
Panjang x Lebar x Jumlah
VOL= 44.2 x 0.4 x 0.5 = 8.84 m2
Volume Begesting 8.840 m2
BETON Panjang = 44.2 M1
URAIAN PERHITUNGAN VOLUME
PEKERJAAN PASANGAN
1. Pas. Bata merah 1 : 6
Panjang x Tinggi = Volume sat
Depan 12.15 x 3.4 = 41.31 M2
Belakang 11 x 3.4 = 37.4 M2
Kiri 4.15 x 3.4 = 14.11 M2
Kanan 4.15 x 3.4 = 14.11 M2
Kamar Mandi 01 5.3 x 3.6 = 19.08 M2
Kamar Mandi 02 5.3 x 3.6 = 19.08 M2
Atas Balok Gorpal 2 x 1 = 2 M2
Tengah 1 x 3.6 = 3.6 M2
150.69 M2
Pengurang Kusen
Lebar x Tinggi x Jumlah
KP1 Utama 0.92 x 2.62 x 2 = 4.8208 M2
17.6368 M2
PEKERJAAN PLESTERAN
Vol pas bata luar&dalam
Volume pasangan bata = 133.053 x 2 = 266.1064
266.1064 m2
PEKERJAAN ACIAN
Luasan Didnding granit
Volume Plesteran 266.106 - 15.750 250.356 M2
JUMLAH PINTU 2 Bh
KP1
Kusen pintu kayu (KP1) = 2.62 x 2 = 5.24 m1
0.8 x 2 = 1.6 m1
6.84 m1
Engsel Pintu = 3 x 2 = 6 bh
Vol.Engsel 6.000 Bh
Grendel pintu = 1 x 2 = 2 bh
Vol.Grendel 2.000 Bh
Jumlah Pintu 2 Bh
KP2
Kusen pintu kayu (KP1) = 2.62 x 2 = 5.24 m1
0.8 x 2 = 1.6 m1
6.84 m1
Kusen Pintu
Kusen Pintu Alumunium = 6.84 x 2 = 13.680
Engsel Pintu = 3 x 2 = 6 bh
Vol.Engsel 6.000 Bh
Grendel pintu = 1 x 2 = 2 bh
Vol.Grendel 2.000 Bh
JUMLAH JENDELA 2 Bh
KJ1
Kusen Jendela kayu (KJ1) = 1.92 x 3 = 5.76 m1
1.38 x 3 = 4.14 m1
9.9 m1
Engsel Jendela = 4 x 2 = 8 bh
Vol.Engsel 8.000 Bh
Grendel Jendela = 2 x 2 = 4 bh
Vol.Grendel 4.000 Bh
Kait Angin = 2 x 4 = 8 bh
Vol.kait angin 8.000 Bh
JUMLAH BV 1 2 Bh
BV1
Kusen BV1 = 2.04 x 2 = 4.08 m1
0.52 x 4 = 2.08 m1
URAIAN PERHITUNGAN VOLUME
6.16 m1
1.44 m2
0.96 m2
PEKERJAAN ATAP
Nok = 7.8 M
Jurai = 13.6 M
Gording = 9.9 M
= 9.9 M
= 2.35 M
= 2.35 M
Muirplat = 4.3 M
= 4.3 M
= 12 M
= 12 M
78.5 M
VOLUME LUASAN GENTENG SAMA DENGAN LUASAN RENG & KASAU Volume Genteng 81.912 m2
PEKERJAAN LANTAI
Granit pholised 60x60
Panjang x Lebar Vol
Ruang 01 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Ruang 02 = 4.85 x 4.15 = 20.13 M2
0.85 x 0.85 = 0.72 M2
41.70 M2
Granit Pholised 41.700 M2
Granit Unpholised 60x60 Panjang x Lebar Vol
Selasar = 1.25 x 12 = 15.00 M2
WC1 = 1.85 x 1.5 = 2.78 M2
WC2 = 1.85 x 1.5 = 2.78 M2
20.55 M2
Granit unPholised 20.550 M2
Pek. PLAFON
Panjang x Lebar Vol
Ruang 01 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Ruang 02 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Selasar = 1.25 x 12 = 15.00 M2
WC1 = 1.85 x 1.5 = 2.78 M2
WC2 = 1.85 x 1.5 = 2.78 M2
OVER STEAK = 36.940 x 0.65 = 24.01 M2
86.26 M2
VOLUME Plafon 86.261 M2
LIST GYPSUM
Ruang 01 = 4,85+4,85+4,15+1,5+1,5+1+1+1 = 19.85 m1
Ruang 02 = 4,85+4,85+4,15+1,5+1,5+1+1+2 = 19.85 m1
WC1 = 1,85+1,85+1,5+1,5 = 6.70 m1
WC2 = 1,85+1,85+1,5+1,5 = 6.70 m1
OVER STEAK = 12+12+4,3+4,3 = 32.60 m1
85.70 m1
List Plafon 85.700 m1
PLINT GRANIT
Ruang 01 = 4,85+4,85+4,15+1,5+1,5+1+1+1 = 19.85 m1
Ruang 02 = 4,85+4,85+4,15+1,5+1,5+1+1+2 = 19.85 m1
39.70 m1
Plint Granit 39.700 m1
DIAMETER BESI BERAT BESI 12m / btg
BESI Φ16 = 1.0427 =
BESI Φ13 = 1.0427 =
BESI Φ12 = 0.8885 =
BESI Φ10 = 0.6170 =
BESI Φ8 = 0.3949 =
BESI Φ6 = 0.2221 =
TIME SCHEDULE
PAKET PEKERJAAN
LOKASI
SUMBER DANA
TAHUN ANGGARAN
NO
URAIAN PEKERJAAN BOBOT
.
1 2 3
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek 0.024 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) 0.234 0.011 0.011
3. Bongkaran Bangunan lama 0.212 0.071
4. Pembuangan dan pembersihan 0.212
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 0.692 0.231
175/125, FP3 100/100, FP4 100/100)
0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011
0.071 0.071
0.106 0.106
0.231 0.231
0.187 0.187
0.136
0.135
0.097
0.222
0.298
1.040
0.380
0.837
1.220 1.220
0.780
0.088
0.584 0.584
0.197
0.784
0.541
0.132
0.836 0.836
0.227
0.119
0.050
0.374
0.037
0.893
0.079
1.143
0.072
0.247
0.538
2.064 2.064
0.555
0.155
1.769
0.805 0.805
0.487 0.487
0.407 0.407
0.161 0.161
0.163 0.163
0.102 0.102
2.089 2.089
1.773 1.773
2.159
0.337 0.337
0.234 0.234
0.285
0.576
0.338
0.208
1.103
1.354
0.834
0.904
0.272
0.152
0.926
0.055
5.767 6.779 8.781 5.395 3.802 7.491 4.024 4.443 8.794 6.023
6.30 13.08 21.86 27.26 31.06 38.55 42.57 47.02 55.81 61.83
rt Title
14 15 16 17 18 19 20 21 22
0.105
0.320
0.212
0.130
0.048
0.023
0.015
0.239
0.239
0.090
0.514
0.362
0.184
0.438
0.437
0.165
0.858
0.953
0.484
0.368
0.256
0.130
0.540
0.549
0.201
0.246
0.273
0.154
0.192
0.174
0.061
0.240
0.268
0.134
0.177
0.222
0.102
0.088
0.110
0.051
0.042
0.033
0.015
0.326
0.158
0.096
0.516
0.011
0.462
0.096
0.073
0.031
1.056
0.954
1.776 1.776
0.120
0.018
0.044
0.886
2.109 2.109
1.706 1.706
0.262
0.592
0.084
0.124
0.046
0.261
0.211
0.524 0.524
0.241 0.241
0.192
0.110
0.092
0.543
0.117
-
0.041
0.837
0.054
0.043
0.425
0.094
0.108
0.013
0.055
0.242
0.237
0.084
0.098
0.039
0.087
0.069
0.052
0.024
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 - - 0% - 0% -
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 - - 0% - 0% -
3. Bongkaran Bangunan lama OH - - - 0% - 0% -
4. Pembuangan dan pembersihan OH - - - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122
- - 0% - 0% -
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 - - 0% - 0% -
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 - - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395
100/100) - - 0% - 0% -
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 - - 0% - 0% -
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136
100/100, FP4 100/100) - - 0% - 0% -
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136
- - 0% - 0% -
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099
100/100) - - 0% - 0% -
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 - - 0% - 0% -
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 - - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 - - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519
- - 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 - - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672
bata lama) - - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356
- - 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 - - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 - - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000
- - 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893
- - 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 - - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 - - 0% - 0% -
Halaman 48 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 - - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 - - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 - - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 - - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 - - 0% - 0% -
b. Begesting m2 134.46 13,464,704.10 0.987 - - 0% - 0% -
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 - - 0% - 0% -
d. Beton K.225 m3 26.89 24,136,267.36 1.769 - - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 - - 0% - 0% -
c. Beton K.225 m3 12.38 11,113,323.65 0.815 - - 0% - 0% -
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 - - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 - - 0% - 0% -
c. Beton K.225 m3 3.10 2,784,928.04 0.204 - - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 - - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 - - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 - - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 - - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 - - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 - - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 - - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 - - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 - - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 - - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 - - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 - - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 - - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 - - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 - - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 - - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 - - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 - - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 - - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 - - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 - - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 - - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 - - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 - - 0% - 0% -
Halaman 49 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 - - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 - - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 - - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 - - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 - - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 - - 0% - 0% -
b. Kolom m3 4.95 6,118,264.35 0.449 - - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 - - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 - - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 - - 0% - 0% -
920,216,854.01
Halaman 50 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 - - 0% - 0% -
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 - - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 - - 0% - 0% -
6,433,123.77
Halaman 51 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 - - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 - - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 - - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 - - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 - - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 - - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 - - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 - - -
Halaman 52 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 2 (DUA)
Tanggal : 13 Juni 2022 S / D 19 Juni 2022
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 - - 100% 0.024 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 - - 5% 0.012 5% 0.012
3. Bongkaran Bangunan lama OH - - - 0% - 0% -
4. Pembuangan dan pembersihan OH - - - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 -
- 50% 0.061 50% 0.061
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 - - 0% - 0% -
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 - - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 -
100/100) - 50% 0.197 50% 0.197
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 - - 0% - 0% -
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 -
100/100, FP4 100/100) - 50% 0.068 50% 0.068
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 -
- 10% 0.014 10% 0.014
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 -
100/100) - 10% 0.010 10% 0.010
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 - - 20% 0.045 20% 0.045
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 - - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 - - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 -
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 - - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 -
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 -
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 - - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 - - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 -
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 -
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 - - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 - - 0% - 0% -
Halaman 53 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 - - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 - - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 - - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 - - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 - - 0% - 0% -
b. Begesting m2 134.46 13,464,704.10 0.987 - - 0% - 0% -
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 - - 0% - 0% -
d. Beton K.225 m3 26.89 24,136,267.36 1.769 - - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 - - 0% - 0% -
c. Beton K.225 m3 12.38 11,113,323.65 0.815 - - 0% - 0% -
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 - - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 - - 0% - 0% -
c. Beton K.225 m3 3.10 2,784,928.04 0.204 - - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 - - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 - - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 - - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 - - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 - - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 - - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 - - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 - - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 - - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 - - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 - - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 - - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 - - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 - - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 - - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 - - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 - - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 - - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 - - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 - - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 - - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 - - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 - - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 - - 0% - 0% -
Halaman 54 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 - - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 - - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 - - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 - - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 - - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 - - 0% - 0% -
b. Kolom m3 4.95 6,118,264.35 0.449 - - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 - - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 - - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 - - 0% - 0% -
920,216,854.01
Halaman 55 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 - - 0% - 0% -
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 - - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 - - 0% - 0% -
6,433,123.77
Halaman 56 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 - - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 - - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 - - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 - - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 - - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 - - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 - - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 - 0.43 0.4304
Halaman 57 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 3 (TIGA)
Tanggal : 20 Juni 2022 S / D 26 Juni 2022
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 5% 0.012 5% 0.012 10% 0.023
3. Bongkaran Bangunan lama OH - 0% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 50%
0.061 50% 0.061 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 0% - 100% 0.264 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0% - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 50.00%
100/100) 0.197 50% 0.197 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 0.00% - 20% 0.107 20% 0.107
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 50.00%
100/100, FP4 100/100) 0.068 50% 0.068 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 10.00%
0.014 10% 0.014 20% 0.027
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 10.00%
100/100) 0.010 10% 0.010 20% 0.020
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 20.00% 0.045 20% 0.045 40% 0.089
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
Halaman 58 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 0.00% - 50% 2.096 50% 2.096
b. Begesting m2 134.46 13,464,704.10 0.987 0.00% - 50% 0.494 50% 0.494
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 0.00% - 100% 0.133 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 0.00% - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 0.00% - 50% 0.823 50% 0.823
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 0.00% - 50% 0.812 50% 0.812
c. Beton K.225 m3 12.38 11,113,323.65 0.815 0.00% - 25% 0.204 25% 0.204
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 0.00% - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 0.00% - 0% - 0% -
c. Beton K.225 m 3
3.10 2,784,928.04 0.204 0.00% - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
Halaman 59 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 0.00% - 50% 0.103 50% 0.103
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01
Halaman 60 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
Halaman 61 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 0.43 7.18 7.6150
Halaman 62 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 4 (EMPAT)
Tanggal : 27 Juni 2022 S / D 03 Juli 2022
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 10.00% 0.023 5% 0.012 15% 0.035
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 20.00% 0.107 50% 0.267 70% 0.374
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 20.00%
0.027 70% 0.096 90% 0.123
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 20.00%
100/100) 0.020 80% 0.080 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 40.00% 0.089 60% 0.134 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
Halaman 63 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 50.00% 2.096 50% 2.096 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 50.00% 0.494 50% 0.494 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 0.00% - 25% 0.442 25% 0.442
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 50.00% 0.823 50% 0.823 100% 1.646
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 50.00% 0.812 50% 0.812 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 25.00% 0.204 25% 0.204 50% 0.407
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 0.00% - 50% 0.161 50% 0.161
b. Begesting m2 51.72 5,438,215.85 0.399 0.00% - 50% 0.199 50% 0.199
c. Beton K.225 m 3
3.10 2,784,928.04 0.204 0.00% - 25% 0.051 25% 0.051
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
Halaman 64 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 50.00% 0.103 50% 0.103 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01
Halaman 65 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
Halaman 66 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 7.61 9.01 16.6249
Halaman 67 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 5 (LIMA)
Tanggal : 04 Juli 2022 S / D 10 Juli 2022
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 15.00% 0.035 5% 0.012 20% 0.047
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 70.00% 0.374 30% 0.160 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 90.00%
0.123 10% 0.014 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
Halaman 68 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 25.00% 0.442 75% 1.327 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 50.00% 0.407 50% 0.407 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 50.00% 0.161 50% 0.161 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 50.00% 0.199 50% 0.199 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 25.00% 0.051 75% 0.153 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
Halaman 69 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01
Halaman 70 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
Halaman 71 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 16.62 4.09 20.7113
Halaman 72 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 6 (ENAM)
Tanggal : 11 Juli 2022 S / D 17 Juli 2022
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 20.00% 0.047 5% 0.012 25% 0.059
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 100.00% 0.535 0% - 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 100.00%
0.136 0% - 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
Halaman 73 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 100.00% 1.769 0% - 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 100.00% 0.815 0% - 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 100.00% 0.322 0% - 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 100.00% 0.399 0% - 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 100.00% 0.204 0% - 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 60% 1.293 60% 1.293
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 40% 0.528 40% 0.528
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 30% 0.234 30% 0.234
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 60% 0.282 60% 0.282
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 30% 0.117 30% 0.117
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 20% 0.046 20% 0.046
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 40% 0.155 40% 0.155
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 30% 0.119 30% 0.119
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 60% 0.189 60% 0.189
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 40% 0.178 40% 0.178
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 30% 0.038 30% 0.038
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
Halaman 74 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 10% 0.045 10% 0.045
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 10% 0.031 10% 0.031
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01
Halaman 75 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 5% 0.052 5% 0.052
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
Halaman 76 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 20.71 3.32 24.0276
Halaman 77 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 7 (TUJUH)
Tanggal : ### S / D ###
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 20.00% 0.047 5% 0.012 25% 0.059
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 100.00% 0.535 0% - 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 100.00%
0.136 0% - 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
Halaman 78 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 100.00% 1.769 0% - 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 100.00% 0.815 0% - 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 100.00% 0.322 0% - 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 100.00% 0.399 0% - 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 100.00% 0.204 0% - 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 100% 2.154 100% 2.154
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 100% 1.321 100% 1.321
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 100% 0.779 100% 0.779
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 60% 0.282 60% 0.282
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 30% 0.117 30% 0.117
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 20% 0.046 20% 0.046
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 60% 0.189 60% 0.189
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 40% 0.178 40% 0.178
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 30% 0.038 30% 0.038
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 30% 0.620 30% 0.620
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 30% 1.396 30% 1.396
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 15% 0.333 15% 0.333
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 15% 1.264 15% 1.264
c. Beton K.225 m 3
12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 20% 0.057 20% 0.057
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 20% 0.137 20% 0.137
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 30% 0.043 30% 0.043
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 30% 0.093 30% 0.093
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 20% 0.917 20% 0.917
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 20% 2.653 20% 2.653
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
Halaman 79 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 50% 0.224 50% 0.224
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 50% 0.153 50% 0.153
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 50% 0.054 50% 0.054
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 50% 0.362 50% 0.362
920,216,854.01
Halaman 80 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 50% 0.521 50% 0.521
14,218,909.51
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
Halaman 81 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 20.71 15.02 35.7311
Halaman 82 dari 86
Analisa El - 119
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
JUMLAH Rp 640,000.00
OVERHEAD & PROFIT 10% Rp 64,000.00
TOTAL BIAYA KESELAMATAN DAN KESEHATAN KERJA Rp 704,000.00
Catatan :
1. Perkiraan Kuantitas harus disesuaikan dengan kebutuhan di lapangan
2. Harga perlu disesuaikan dengan harga terbaru, termasuk biaya personil
3. Yang dimaksud dengan konsultansi dengan Ahli terkait keselamatan konstruksi termasuk pakar dan praktisi
2 Dihitung MB.K -001 1 BH KURSI KAYU JATI TB 4 CM Ukuran (47cm x 230 cm ) #REF!
A Tenaga #REF!
L.01 0.5 OH Pekerja #REF! #REF!
L.02 1.0 OH Tukang Kayu #REF! #REF!
L.03 0.5 OH Kepala Tukang #REF! #REF!
L.04 0.05 OH Mandor #REF! #REF!
B Bahan #REF!
0.0414 m3 Papan Kayu Jati (dudukan) #REF! #REF!
8.6400 m1 #REF! #REF! #REF!
4.00 Bh Baut Tanam Rp 4,000.00 Rp 16,000.00
0.8 kg Lem Kayu #REF! #REF!
0.2 Kg Paku Biasa 2" - 5" #REF! #REF!
C PERALATAN
D Jumlah A + B + C #REF!
E Overhead & Profit 10% #REF!
F Harga Satuan Pekerjaan (D+E) #REF!
2 Dihitung MB.M -002 1 BH MEJA KAYU JATI TB. 4 CM Ukuran (80cm x 230 cm ) #REF!
A Tenaga #REF!
L.01 0.5 OH Pekerja #REF! #REF!
L.02 1.0 OH Tukang Kayu #REF! #REF!
L.03 0.5 OH Kepala Tukang #REF! #REF!
L.04 0.05 OH Mandor #REF! #REF!
B Bahan #REF!
0.0552 m3 Papan Kayu Jati #REF! #REF!
0.0576 m3 Balok Kayu Jati #REF! #REF!
6.00 Bh Baut Tanam Rp 4,000.00 Rp 24,000.00
0.8 kg Lem Kayu #REF! #REF!
0.25 Kg Paku Biasa 2" - 5" #REF! #REF!
C PERALATAN
D Jumlah A + B + C #REF!
E Overhead & Profit 10% #REF!
F Harga Satuan Pekerjaan (D+E) #REF!
REKAPITULASI
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTRIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI :Jln. Dr . Sutomo No.48 Blora
sumber dana :APBN TAHUN ANGGARAN 2022
MINGGU KE :7
PERIODE :18 JULI s/d 24 JULI 2022
Bulan ke : 1 (SATU)
Bulan : Juni
PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :
7. Reng dan usuk baja ringan merk Giga Steel m2 311.82 - 0.000
8. Atap genteng metal pasir/Rocky merk Kencana Tb. 0,25 mm m2 311.82 - 0.000
9. Nok genteng metal pasir/Rocky merk Kencana Tb. 0,25 mm m1 48.95 - 0.000
10. Atap galvalum tbl 0.35 mm (atap drop off) m2 65.28 - 0.000
11. Nok galvalum (atap drop off) m1 8.40 - 0.000
12. Pekerjaan talang (jurai dalam) m1 11.40 - 0.000
13. Pekerjaan flashing (pertemuan atap dengan dinding bata) m1 9.40 - 0.000