BACKUP DATA

URAIAN PERHITUNGAN VOLUME

1. GALIAN TANAH
A. GALIAN TANAH FOOTPLAT
Panjang x Lebar x dalam Jml titik Volume
FP1= 0.7 x 0.7 x 1.5 x 8 = 5.88 M3

B. GALIAN TANAH PONDASI PAS BATU


Panjang = 12+12 = 24 m1
= 4,3+4,3 = 8.6 m1
= 1,65+2+1,65 = 5.3 m1
= 1,65+2+1,65 = 5.3 m1
= 1 = 1 m1

44.2 m1

Panjang x Lebar x dalam Volume


44.2 x 0.60 x 0.3 = 7.96 M3

VOLUME GALIAN TANAH 13.84 M3

URUGAN TANAH KEMBALI 1/3 DARI GALIAN 4.612 M3


2. URUGAN TANAH PILIHAN
Panjang x Lebar x dalam Volume
11.5 x 4 x 0.2 = 9.20 M3

VOLUME URUGAN TANAH PILIHAN 9.20 M3


2. URUGAN PASIR
Bawah Footplat
Panjang x Lebar Tebal Jumlah
FP1= 0.7 x 0.7 x 0.05 x 8 = 0.20 M3

Bawah Pondasi Pasangan Batu


Panjang x Lebar Tebal
Vol = 44.2 x 0.60 x 0.05 = 1.33 M3

Urugan Bawah Lantai


11.00 x 8.00 x 0.05 - 0.20 = 4.20 M3
5.73 M3

VOLUME URUGAN PASIR 5.73 M3


3. LANTAI KERJA
Bawah Footplat
Panjang x Lebar Tebal Jumlah
FP1= 0.7 x 0.7 x 0.05 x 8 = 0.20 M3

0.20 M3

VOLUME LANTAI KERJA 0.20 M3

PONDASI PASANGAN BATU Panjang = 44.20 M1

L atas L bawah Volume Tinggi Panjang


0.25 + 0.5 0.375 x 0.5 x 44.20 = 8.2875
=
2

VOLUME PONDASI PAS BATU 8.288 M3


URAIAN PERHITUNGAN VOLUME
ANSTAMPENG
L atas L bawah Volume Tinggi Panjang
0.6 + 0.6 0.6 x 0.15 x 44.20 = 3.978 3.978 M3
=
2
URAIAN PERHITUNGAN VOLUME
PEKERJAAN BETON

1. FOOTPLAT FP1 (60x60) JUMLAH = 8 Titik

PEMBESIAN
Telapak
Panjang x Jumlah x Besi ø 10
X 2 x 6 x 0.617 = 7.40 Kg
Y 2 x 6 x 0.617 = 7.40 Kg
14.81 x 8 = 118.464
Peudestail
Panjang x Jumlah x Besi ø 12
2 x 4 x 0.888 = 7.11 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 14 x 0.39488 = 3.96 Kg
= 11.07 Kg

JUMLAH 1 FOOTPLAT = 11.070 x 8 = 88.5584

Volume Pembesian 207.022 Kg


BEGESTING = 8 Titik
Panjang x Lebar x Jumlah
Telapak 2.8 x 0.2 x 8 = 4.48 m2

Peudestail Tinggi x Lebar x Jumlah


1 x 0.6 x 8 = 4.8 m2
9.28
Volume Begesting 9.280 m2
BETON
= 8.00 Titik
TELAPAK
Panjang x Lebar x Tinggi x Jumlah = Volume
0.7 x 0.7 x 0.25 x 8.00 = 0.98 m3
PEUDESTAIL
Panjang x Lebar x Tinggi x Jumlah = Volume
0.15 x 0.2 x 1.3 x 8.00 = 0.31 m3

Volume Beton 1.292 M3

2. PEKERJAAN STROUISPAL = 0.00 Bh

PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 10
2.5 x 4 x 0.617 = 6.17 Kg
Beugel
Panjang x Jumlah x Besi ø 8
6.00 x 1 x 0.39488 = 2.37 Kg
= 8.54 Kg
1 STR Jumlah STR
8.54 x 0 = 0.00 Kg
Volume Pembesian 0.000 Kg
BETON = 0.00 BH

3.14 x 0.01 x 2 x 0.00 = 0 m3

Volume Beton 0.000 M3


URAIAN PERHITUNGAN VOLUME

3. SLOOF (15 x 25) PANJANG = 44.2 M1

PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
44.2 x 4 x 0.888 = 157.08 Kg
Panjang x Jumlah x Besi ø 8
44.2 x 2 x 0.395 = 34.91 Kg

Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 296 x 0.39488 = 81.73 Kg
= 273.72 Kg

Volume Pembesian 273.718 Kg


BEGESTING = 44.2 M1
Panjang x Lebar x Jumlah
VOL= 22.1 x 0.5 x 1 = 11.05 m2
Volume Begesting 11.050 m2

BETON Panjang = 44.2 M1

Lebar x Tinggi x Panjang = Volume


0.15 x 0.25 x 44.2 = 1.658 m3

Volume Beton 1.658 M3

4. BETON LANTAI DASAR TB. 5 Cm

PEMBESIAN
Panjang x Jumlah x Besi ø 8 Singgel
ZONA 1
X= 11.55 x 9 x 0.395 x 1 = 42.42 Kg
Y= 4.15 x 24 x 0.395 x 1 = 39.49 Kg
81.91 Kg

Volume Pembesian 81.910 Kg


BETON

Panjang x Lebar x Tebal = Volume


= 11.55 x 4.15 x 0.05 = 2.397 m3

2.397 m3
Volume Beton 2.397 M3

5. KOLOM 15 x 20 JUMLAH = 8 Titik

PEMBESIAN
Tulangan Pokok
Tinggi x Jumlah x Besi ø 12
4 x 4 x 0.888 = 14.22 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 28 x 0.39488 = 7.65 Kg
= 21.86 Kg
1 Kolom Jumlah Kolom
21.86 x 8 = 174.91 Kg
URAIAN PERHITUNGAN VOLUME
Volume Pembesian 174.906 Kg
BEGESTING
= 8 Titik
Tinggi x Lebar x Jumlah
VOL= 4 x 0.4 x 8 = 12.8 m2
Volume Begesting 12.800 m2
BETON = 8.00 Titik
Panjang x Lebar x Tinggi x Jumlah = Volume
0.15 x 0.2 x 4 x 8.00 = 0.96 m3

Volume Beton 0.960 M3


URAIAN PERHITUNGAN VOLUME

5. KOLOM 15 x 15 JUMLAH = 12 Titik

PEMBESIAN
Tulangan Pokok
Tinggi x Jumlah x Besi ø 10
4 x 4 x 0.617 = 9.87 Kg
Beugel
Panjang x Jumlah x Besi ø 6
0.58 x 28 x 0.22212 = 3.56 Kg
= 13.44 Kg
1 Kolom Jumlah Kolom
13.44 x 12 = 161.24 Kg
Volume Pembesian 161.235 Kg
BEGESTING
= 12 Titik
Tinggi x Lebar x Jumlah
VOL= 4 x 0.3 x 12 = 14.4 m2
Volume Begesting 14.400 m2
BETON = 12.00 Titik
Panjang x Lebar x Tinggi x Jumlah = Volume
0.15 x 0.15 x 4 x 12.00 = 1.08 m3

Volume Beton 1.080 M3

6. BALOK LATEY 13x20 Panjang = 44.2 M1

PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 8
44.2 x 4 x 0.395 = 69.81 Kg
Beugel
Panjang x Jumlah x Besi ø 6
0.60 x 296 x 0.222 = 39.40 Kg
= 109.22 Kg
Volume Pembesian 109.219 Kg
BEGESTING Panjang = 44.2 M1
Panjang x Lebar x Jumlah
VOL= 44.2 x 0.3 x 1 = 13.26 m2
Volume Begesting 13.260 m2
BETON Panjang = 44.2 M1

Lebar x Tinggi x Panjang = Volume


0.13 x 0.2 x 44.2 = 1.149 m3

Volume Beton 1.149 M3


6. BALOK 15 x 25 Memanjang = 12 M1
Memanjang = 12 M1
Melintang = 25.8 M1 Panjang Dari = 4,3 x 6
Overstek Bawah listplank = 4.8 M1 Panjang Dari = 1,2 x 4
Overstek Bawah listplank = 5.6 M1 Panjang Dari = 0,7 x 8

60.2 M1

PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
60.2 x 4 x 0.888 = 213.95 Kg
URAIAN PERHITUNGAN VOLUME
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 402 x 0.395 = 111.21 Kg
= 325.16 Kg
Volume Pembesian 325.157 Kg
BEGESTING Panjang = 60.2 M1
Panjang x Lebar x Jumlah
VOL= 60.2 x 0.4 x 1 = 24.08 m2
Volume Begesting 24.080 m2
BETON Panjang = 60.2 M1

Lebar x Tinggi x Panjang = Volume


0.15 x 0.25 x 60.2 = 2.258 m3

Volume Beton 2.258 M3


URAIAN PERHITUNGAN VOLUME

Plat Dak Beton = 10 cm


ATAS RUANGAN 01
Panjang = 4.85 M
Lebar = 4.15 M

ATAS RUANGAN 02
Panjang = 4.85 M
Lebar = 4.15 M

ATAS Kamar Mandi 01


Panjang = 1.85 M
Lebar = 1.50 M

ATAS Kamar Mandi 02


Panjang = 1.85 M
Lebar = 1.50 M

ATAS RUANGAN 01
Pembesian Panjang x Jumlah x Besi ø 10
X= 4.85 x 29 x 0.617 x 1 = 85.78 Kg
Y= 4.15 x 33 x 0.617 x 1 = 85.35 Kg
171.14 Kg
ATAS RUANGAN 02
Pembesian Panjang x Jumlah x Besi ø 10
X= 4.85 x 29 x 0.617 x 1 = 85.78 Kg
Y= 4.15 x 33 x 0.617 x 1 = 85.35 Kg
171.14 Kg

ATAS Kamar Mandi 01


Pembesian Panjang x Jumlah x Besi ø 10
X= 1.85 x 11 x 0.617 x 1 = 12.56 Kg
Y= 1.50 x 13 x 0.617 x 1 = 12.34 Kg
24.90 Kg
ATAS Kamar Mandi 02
Pembesian Panjang x Jumlah x Besi ø 10
X= 1.85 x 11 x 0.617 x 1 = 12.56 Kg
Y= 1.50 x 13 x 0.617 x 1 = 12.34 Kg
24.90 Kg

Volume Pembesian 392.062 Kg

BEGESTING
Panjang x Lebar x Jumlah
ATAS RUANGAN 01 4.85 x 4.15 x 1 = 20.1275 m2
ATAS RUANGAN 02 4.85 x 4.15 x 1 = 20.1275 m2
ATAS Kamar Mandi 01 1.85 x 1.50 x 1 = 2.775 m2
ATAS Kamar Mandi 02 1.85 x 1.50 x 1 = 2.775 m2

45.805 M2

Volume Begesting 45.805 m2


BETON

Panjang x Lebar x Tebal Jumlah = Volume


ATAS RUANGAN 01 4.85 x 4.15 x 0.10 x 1.00 = 2.013 m3
ATAS RUANGAN 02 4.85 x 4.15 x 0.10 x 1.00 = 2.013 m3
URAIAN PERHITUNGAN VOLUME
ATAS Kamar Mandi 01 1.85 x 1.50 x 0.10 x 1.00 = 0.278 m3
ATAS Kamar Mandi 02 1.85 x 1.50 x 0.10 x 1.00 = 0.278 m3

4.581 m3

Volume Beton 4.581 M3


URAIAN PERHITUNGAN VOLUME

Listplank Beton Tb. 7 cm

Listplank Belakang & Samping Kanan Kiri


Panjang = 24.40 M
Lebar = 0.70 M

Listplank Sambungan Antar Gedung


Panjang = 12.00 M
Lebar = 1.20 M

Listplank Belakang & Samping Kanan Kiri


Pembesian Panjang x Jumlah x Besi ø 10
X= 24.40 x 6 x 0.617 x 1 = 85.31 Kg
Y= 0.70 x 164 x 0.617 x 1 = 70.69 Kg
156.00 Kg
Listplank Sambungan Antar Gedung
Pembesian Panjang x Jumlah x Besi ø 10
X= 12.00 x 9 x 0.617 x 1 = 66.64 Kg
Y= 1.20 x 81 x 0.617 x 1 = 59.97 Kg
126.61 Kg

Volume Pembesian 282.607 Kg


BEGESTING
Panjang x Lebar x Jumlah
Listplank Belakang & Samping Kanan Kiri 24.40 x 0.70 x 1 = 17.08 m2
Listplank Sambungan Antar Gedung 12.00 x 1.20 x 1 = 14.4 m2
31.48 M2

Volume Begesting 31.480 m2


BETON

Panjang x Lebar x Tebal Jumlah = Volume


24.40 x 0.70 x 0.07 x 1.00 = 1.196 m3
12.00 x 1.20 x 0.07 x 1.00 = 1.008 m3

2.204 m3

Volume Beton 2.204 M3

RINGBALK 15X20 Panjang = 44.2 M1

PEMBESIAN
Tulangan Pokok
Panjang x Jumlah x Besi ø 12
44.2 x 4 x 0.888 = 157.08 Kg
Beugel
Panjang x Jumlah x Besi ø 8
0.70 x 296 x 0.395 = 81.73 Kg
= 238.81 Kg
Volume Pembesian 238.810 Kg
BEGESTING Panjang = 44.2 M1
Panjang x Lebar x Jumlah
VOL= 44.2 x 0.4 x 0.5 = 8.84 m2
Volume Begesting 8.840 m2
BETON Panjang = 44.2 M1
URAIAN PERHITUNGAN VOLUME

Lebar x Tinggi x Panjang = Volume


0.15 x 0.2 x 44.2 = 1.326 m3

Volume Beton 1.326 M3


URAIAN PERHITUNGAN VOLUME

PEKERJAAN PASANGAN
1. Pas. Bata merah 1 : 6
Panjang x Tinggi = Volume sat
Depan 12.15 x 3.4 = 41.31 M2
Belakang 11 x 3.4 = 37.4 M2
Kiri 4.15 x 3.4 = 14.11 M2
Kanan 4.15 x 3.4 = 14.11 M2
Kamar Mandi 01 5.3 x 3.6 = 19.08 M2
Kamar Mandi 02 5.3 x 3.6 = 19.08 M2
Atas Balok Gorpal 2 x 1 = 2 M2
Tengah 1 x 3.6 = 3.6 M2

150.69 M2
Pengurang Kusen
Lebar x Tinggi x Jumlah
KP1 Utama 0.92 x 2.62 x 2 = 4.8208 M2

KP2 WC 0.9 x 2.2 x 2 = 3.96 M2

Kusen Jendela 1.38 x 1.92 x 2 = 5.2992 M2

Kusen Bouven (BV1) 2.04 x 0.52 x 2 = 2.1216 M2

Kusen Bouven (BV2) 1.38 x 0.52 x 2 = 1.4352 M2

17.6368 M2

Volume Pasangan Bata 133.053 m2

PEKERJAAN PLESTERAN
Vol pas bata luar&dalam
Volume pasangan bata = 133.053 x 2 = 266.1064

266.1064 m2

VOLUME PLESTERAN 266.106 M2

PEKERJAAN ACIAN
Luasan Didnding granit
Volume Plesteran 266.106 - 15.750 250.356 M2

PEKERJAAN KUSEN , PINTU , JENDELA & BOUVEN

JUMLAH PINTU 2 Bh
KP1
Kusen pintu kayu (KP1) = 2.62 x 2 = 5.24 m1
0.8 x 2 = 1.6 m1
6.84 m1

Panjang x Tebal x Lebar Jmlh Pintu


Kusen Pintu Kayu 6x12 = 6.84 x 0.06 x 0.12 x 2 = 0.098

Volume Kusen 0.098 m3


URAIAN PERHITUNGAN VOLUME
Lebar x Tinggi x Jumlah
Daun Pintu = 0.8 x 2.1 x 2 = 3.36

Volume daun Pintu 3.360 m2


Kaca Bening 5 mm = Lebar x Tinggi x Jumlah
0.8 x 0.4 x 2 = 0.64

Volume kaca 0.640 m2

Engsel Pintu = 3 x 2 = 6 bh
Vol.Engsel 6.000 Bh

Grendel pintu = 1 x 2 = 2 bh
Vol.Grendel 2.000 Bh

Handle dan kunci tanam = 1 x 2 = 2 bh


Vol.handle & kunci tanam 2.000 Bh
URAIAN PERHITUNGAN VOLUME

Jumlah Pintu 2 Bh
KP2
Kusen pintu kayu (KP1) = 2.62 x 2 = 5.24 m1
0.8 x 2 = 1.6 m1
6.84 m1

Kusen Pintu
Kusen Pintu Alumunium = 6.84 x 2 = 13.680

Volume Kusen 13.680 M1


Lebar x Tinggi x Jumlah
Daun Pintu = 0.75 x 2.1 x 2 = 3.15

Volume daun Pintu 3.150 m2


Kaca Bening 5 mm = Lebar x Tinggi x Jumlah
0.75 x 0.4 x 2 = 0.6

Volume kaca 0.600 m2

Engsel Pintu = 3 x 2 = 6 bh
Vol.Engsel 6.000 Bh

Grendel pintu = 1 x 2 = 2 bh
Vol.Grendel 2.000 Bh

Handle dan kunci tanam = 1 x 2 = 2 bh


Vol.handle & kunci tanam 2.000 Bh

JUMLAH JENDELA 2 Bh
KJ1
Kusen Jendela kayu (KJ1) = 1.92 x 3 = 5.76 m1
1.38 x 3 = 4.14 m1
9.9 m1

Panjang x Tebal x Lebar Jmlh Jendela


Kusen Jendela Kayu 6x12 = 9.9 x 0.06 x 0.12 x 2 = 0.143

Volume Kusen 0.143 m3


Lebar x Tinggi x Jumlah
Daun Jendela = 0.6 x 1.34 x 4 = 3.216

Volume daun Jendela 3.216 m2


Kaca Bening 5 mm = Lebar x Tinggi x Jumlah
= 0.44 x 1.2 x 4 = 2.112 m2
= 0.44 x 0.4 x 4 = 0.704 m2
2.816 m2

Volume kaca 2.816 m2

Engsel Jendela = 4 x 2 = 8 bh
Vol.Engsel 8.000 Bh

Grendel Jendela = 2 x 2 = 4 bh
Vol.Grendel 4.000 Bh

Kait Angin = 2 x 4 = 8 bh
Vol.kait angin 8.000 Bh

JUMLAH BV 1 2 Bh
BV1
Kusen BV1 = 2.04 x 2 = 4.08 m1
0.52 x 4 = 2.08 m1
URAIAN PERHITUNGAN VOLUME
6.16 m1

Panjang x Tebal x Lebar Jmlh BV1


Kusen BV 1 6x12 = 6.16 x 0.06 x 0.12 x 2 = 0.089

Volume Kusen 0.089 m3

Kaca Bening 5 mm = Lebar x Tinggi x Jumlah


= 0.6 x 0.4 x 6 = 1.44 m2

1.44 m2

Volume kaca 1.440 m2


URAIAN PERHITUNGAN VOLUME
JUMLAH BV 2 2 Bh
BV2
Kusen BV2 = 1.38 x 2 = 2.76 m1
0.52 x 3 = 1.56 m1
4.32 m1

Panjang x Tebal x Lebar Jmlh BV2


Kusen BV 1 6x12 = 4.32 x 0.06 x 0.12 x 2 = 0.062

Volume Kusen 0.062 m3

Kaca Bening 5 mm = Lebar x Tinggi x Jumlah


= 0.6 x 0.4 x 4 = 0.96 m2

0.96 m2

Volume kaca 0.960 m2

PEKERJAAN ATAP

KUDA KUDA KAYU 4 Bh


KUDA KUDA 1
Balok Tarik = 4.3 M
Tuwoh = 1.35 M
Penyangga Gording Kanan = 0.7 M
Penyangga Gording Kiri = 0.7 M
Kuda Kuda Kanan = 2.35 M
Kuda Kuda Kiri = 2.35 M
Dudukan Tuwoh = 0.6 M
12.35 M

1/2 KUDA KUDA


Balok Tarik = 2.15 M
Penyangga Gording Kanan = 0.7 M
Kuda Kuda = 2.35 M
5.2 M

Panjang x Tebal x Lebar Jml KD


KUDA KUDA 1 = 12.35 x 0.08 x 0.1 x 4 = 0.395
1/2 KUDA KUDA = 5.2 x 0.08 x 0.1 x 2 = 0.083
0.478

Volume Kuda-kuda= 0.478 m3

NOK,JURAI ,GORDING &MUIRPLAT

Nok = 7.8 M
Jurai = 13.6 M
Gording = 9.9 M
= 9.9 M
= 2.35 M
= 2.35 M
Muirplat = 4.3 M
= 4.3 M
= 12 M
= 12 M
78.5 M

Panjang x Tebal x Lebar


Kayu 8x10 = 78.5 x 0.08 x 0.1 = 0.628
URAIAN PERHITUNGAN VOLUME
Volume Nok, Gording & Muirplat 0.628 m3
URAIAN PERHITUNGAN VOLUME

RANGKA ATAP KASAU & RENG

Bawah Atas Lebar/sisi miring


Trapesium Utara 13.06 + 7.7 10.38 x 3.13 = 32.4894 m2
=
2

Bawah Atas Lebar/sisi miring


Trapesium Selatan 13.06 + 7.7 10.38 x 3.13 = 32.4894 m2
=
2

Lebar Bawah sisi miring


Segitiga Barat 5.41 x 3.13 = 8.46665 m2
=
2

Lebar Bawah sisi miring


Segitiga Timur 5.41 x 3.13 = 8.46665 m2
=
2
Jumlah Total Luasan = 81.9121 m2

Volume Reng Kasau 81.912 m2

VOLUME LUASAN GENTENG SAMA DENGAN LUASAN RENG & KASAU Volume Genteng 81.912 m2

GENTENG KERPUS = 7,8+3,4+3,4+3,4+3,4 = 21.4 M1


Volume Kerpus 21.400 m1

Listplank Kayu = 13,06+13,06+5,41+5,41 = 36.94 M1


Volume Panjang Listplank 36.940 m1

PEKERJAAN LANTAI
Granit pholised 60x60
Panjang x Lebar Vol
Ruang 01 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Ruang 02 = 4.85 x 4.15 = 20.13 M2
0.85 x 0.85 = 0.72 M2

41.70 M2
Granit Pholised 41.700 M2
Granit Unpholised 60x60 Panjang x Lebar Vol
Selasar = 1.25 x 12 = 15.00 M2
WC1 = 1.85 x 1.5 = 2.78 M2
WC2 = 1.85 x 1.5 = 2.78 M2
20.55 M2
Granit unPholised 20.550 M2

Granit Dinding Pholised 60x60 Panjang x Tinggi Vol


WC1 = 5.25 x 1.5 = 7.88 M2
WC2 = 5.25 x 1.5 = 7.88 M2
15.75 M2
Granit unPholised 15.750 M2
URAIAN PERHITUNGAN VOLUME

Pek. PLAFON
Panjang x Lebar Vol
Ruang 01 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Ruang 02 = 4.85 x 4.15 = 20.13 M2
= 0.85 x 0.85 = 0.72 M2
Selasar = 1.25 x 12 = 15.00 M2
WC1 = 1.85 x 1.5 = 2.78 M2
WC2 = 1.85 x 1.5 = 2.78 M2
OVER STEAK = 36.940 x 0.65 = 24.01 M2

86.26 M2
VOLUME Plafon 86.261 M2
LIST GYPSUM
Ruang 01 = 4,85+4,85+4,15+1,5+1,5+1+1+1 = 19.85 m1
Ruang 02 = 4,85+4,85+4,15+1,5+1,5+1+1+2 = 19.85 m1
WC1 = 1,85+1,85+1,5+1,5 = 6.70 m1
WC2 = 1,85+1,85+1,5+1,5 = 6.70 m1
OVER STEAK = 12+12+4,3+4,3 = 32.60 m1
85.70 m1
List Plafon 85.700 m1

PLINT GRANIT
Ruang 01 = 4,85+4,85+4,15+1,5+1,5+1+1+1 = 19.85 m1
Ruang 02 = 4,85+4,85+4,15+1,5+1,5+1+1+2 = 19.85 m1

39.70 m1
Plint Granit 39.700 m1
DIAMETER BESI BERAT BESI 12m / btg
BESI Φ16 = 1.0427 =
BESI Φ13 = 1.0427 =
BESI Φ12 = 0.8885 =
BESI Φ10 = 0.6170 =
BESI Φ8 = 0.3949 =
BESI Φ6 = 0.2221 =
TIME SCHEDULE
PAKET PEKERJAAN
LOKASI
SUMBER DANA
TAHUN ANGGARAN

NO
URAIAN PEKERJAAN BOBOT
.

1 2 3
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek 0.024 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) 0.234 0.011 0.011
3. Bongkaran Bangunan lama 0.212 0.071
4. Pembuangan dan pembersihan 0.212
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 0.692 0.231
175/125, FP3 100/100, FP4 100/100)

2. Galian tanah Pondasi Batu Belah 0.561 0.187


3. Urugan tanah kembali Footplat (FP1 0.136
200/150, FP2 175/125, FP3 100/100, FP4
100/100)
4. Urugan tanah kembali Pondasi Batu Belah 0.135
5. Urugan pasir Footplat (FP1 200/150, FP2 0.097
175/125, FP3 100/100, FP4 100/100)

6. Urugan pasir Pondasi Batu Belah 0.222


7. Urugan pasir Bawah lantai 0.298
8. urugan tanah pemadatan 1.040
9. Pemadatan urugan tanah per 20 cm 0.380
III PEKERJAAN PONDASI
1. Batu Kosong/Anstamping 0.837
2. Pondasi Batu Belah 1SP : 6 PP 2.441
IV PEKERJAAN PASANGAN DINDING
1. Bata merah 1/2 batu campuran 1PPC : 5PP- 0.780
Lantai 1
2. Bata merah 1/2 batu campuran 1PPC : 5PP- 0.657
Lantai 2
3. Bata merah 1/2 batu campuran 1PPC : 5PP- 0.105
Gavel
4. Bata merah 1/2 batu campuran 1PPC : 5PP- 0.088
tangga teras
5. Bata merah 1/2 batu campuran 1PPC : 5PP- 1.167
Penebalan Kolom K-4 dan Tampak depan
6. Pasangan Bata Expose Campuran 1SP : 5PP- 0.197
Lantai 1
7. Pasangan Bata Expose Campuran 1SP : 5PP- 0.784
Lantai 2
8. Pasang dinding partisi gypsum 2 muka (luar 0.541
dalam) / m2 - Lantai 1 (Ruang Kepala dan
Kasubag TU)
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak 0.132
Pondasi dan Sloof
2. Plesteran campuran 1PPC : 5PP-dinding 1.672
bata Lantai 1 (bata baru dan bata lama)

3. Plesteran campuran 1PPC : 5PP-balok latay 0.227


dan Kolom Praktis Lantai 1
4. Plesteran campuran 1PPC : 5PP-Gavel 0.119
5. Plesteran campuran 1PPC : 5PP-Bata tangga 0.050
teras
6. Plesteran campuran 1PPC : 5PP-dinding 0.374
bata Lantai 2
7. Plesteran campuran 1PPC : 5PP-balok latay 0.037
dan Kolom Praktis Lantai 2
8. Plesteran campuran 1PPC : 5PP-Bata 0.893
Penebalan Kolom K4 dan Tampak
9. Acian-Tampak Pondasi dan Sloof 0.079
10. Acian-Lantai 1 1.143
11. Acian-Gavel 0.072
12. Acian-Lantai 2 0.247
13. Acian-Kolom K4 dan Tampak 0.538
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian 4.128
b. Begesting 0.555
c. Beton K.100 tb. 5 cm 0.155
d. Beton K.225 1.769
2. Sloof S1 20/40
a. Pembesian 1.610
b. Begesting 0.974
c. Beton K.225 0.815
3. Sloof S2 15/30
a. Pembesian 0.321
b. Begesting 0.325
c. Beton K.225 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian 2.144
b. Begesting 1.264
c. Beton K.225 0.779
5. Kolom K2 40/40 LANTAI 1
a. Pembesian 0.467
b. Begesting 0.372
c. Beton K.225 0.229
6. Kolom KP 15/15 LANTAI 1
a. Pembesian 0.384
b. Begesting 0.185
c. Beton K.225 0.116
7. Kolom K4 20/20 LANTAI 1
a. Pembesian 0.312
b. Begesting 0.409
c. Beton K.225 0.126
8. Balok B1 35/70 elevasi +4.35
a. Pembesian 2.076
b. Begesting 1.203
c. Beton K.225 1.190
9. Balok B2 20/50 elevasi +4.35
a. Pembesian 2.220
b. Begesting 1.246
c. Beton K.225 0.792
10. Balok B4 15/35 elevasi +4.35
a. Pembesian 0.284
b. Begesting 0.203
c. Beton K.225 0.106
11. Balok B7 15/25 elevasi +4.35
a. Pembesian 0.141
b. Begesting 0.089
c. Beton K.225 0.050
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian 4.177
b. Begesting 3.546
c. Beton K.225 2.159
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian 0.673
b. Begesting 0.468
c. Beton K.225 0.285
14. KOLOM K1 40/40 LANTAI 2
a. Pembesian 0.576
b. Begesting 0.338
c. Beton K.225 0.208
15. KOLOM K3 40/40 LANTAI 2
a. Pembesian 1.103
b. Begesting 1.354
c. Beton K.225 0.834
16. KOLOM K4 20/20 LANTAI 2
a. Pembesian 0.320
b. Begesting 0.212
c. Beton K.225 0.130
17. KOLOM KP 15/15 LANTAI 2
a. Pembesian 0.048
b. Begesting 0.023
c. Beton K.225 0.015
18. Balok B4 15/35 elevasi +7.55
a. Pembesian 0.239
b. Begesting 0.239
c. Beton K.225 0.090
19. Balok B2 20/50 elevasi +8.70
a. Pembesian 0.514
b. Begesting 0.362
c. Beton K.225 0.184
20. Balok B4 15/35 elevasi +8.70
a. Pembesian 0.438
b. Begesting 0.437
c. Beton K.225 0.165
21. PLAT DAK ATAP TYPE C ELEVASI +8.70 tb. 10 cm
a. Pembesian 0.858
b. Begesting 0.953
c. Beton K.225 0.484
22. Balok B2 20/50 elevasi +9.30
a. Pembesian 0.368
b. Begesting 0.256
c. Beton K.225 0.130
23. Balok B5 15/30 elevasi +9.30
a. Pembesian 0.540
b. Begesting 0.549
c. Beton K.225 0.201
24. Tangga
a. Pembesian 0.246
b. Begesting 0.273
c. Beton K.225 0.154
25. Kuda2 Beton Teras
a. Pembesian 0.192
b. Begesting 0.174
c. Beton K.225 0.061
26. Beton Entrance
a. Pembesian 0.240
b. Begesting 0.268
c. Beton K.225 0.134
27. Balok Latay 11/20-Lantai 1
a. Pembesian 0.177
b. Begesting 0.222
c. Beton K.225 0.102
28. Balok Latay 11/20-Lantai 2
a. Pembesian 0.088
b. Begesting 0.110
c. Beton K.225 0.051
29. Ringbalk 11/11-Gavel
a. Pembesian 0.042
b. Begesting 0.033
c. Beton K.225 0.015
30. Sofi-sofi Pintu dan Jendela
a. Pembesian 0.326
b. Begesting 0.158
c. Beton K.225 0.096
31. Droop Off
a. Pembesian 0.516
b. Begesting 0.011
c. Beton K.225 0.462
32. Talang Droop Off tb. 7 cm
a. Pembesian 0.096
b. Begesting 0.073
c. Beton K.225 0.031
33. Beton K. 100 Lantai
a. Pembesian 1.056
b. Beton K.100 0.954
VII PEKERJAAN PENUTUP ATAP
1. Kuda-kuda Besi Siku 4.170
75.75.7;70.70.7;60.60.6 dan 40.40.4 (KK1, 1/2
KK1, KK2 dan KK3)
2. Gording dan Jurai 3.553
3. Base Plat 6mm 0.120
4. Baut ∅ 5/8 inch panjang 5 cm 0.018
5. Watermoor ∅ 16 0.044
6. Pengelasan, pengecatan kuda-kuda, gording 0.886
dan perlengkapannya
7. Reng dan usuk baja ringan merk Giga Steel 4.217

8. Atap genteng metal pasir/Rocky merk 3.411


Kencana Tb. 0,25 mm
9. Nok genteng metal pasir/Rocky merk 0.262
Kencana Tb. 0,25 mm
10. Atap galvalum tbl 0.35 mm (atap drop off) 0.592
11. Nok galvalum (atap drop off) 0.084
12. Pekerjaan talang (jurai dalam) 0.124
13. Pekerjaan flashing (pertemuan atap dengan 0.046
dinding bata)
14. Pemasangan lisplank kalsiplank lb. 25 cm -
VIIIPEKERJAAN LANGIT-LANGIT
1. Rangka plafond hollow galvanis 40.40.0,4 0.904
mm, modul 60 x 60 cm (Ruang Kepala dan
Kasubag TU)
2. Plafond gypsum 9 mm - merk Jayaboard 0.272
(Ruang Kepala dan Kasubag TU)

3. Pek. list plafon shadowline (Ruang Kepala 0.152


dan Kasubag TU)
IX PEKERJAAN PENUTUP LANTAI dan DINDING
1. Lantai L1 -Ruang Kepala dan Kasubag TU 0.926
(granito ex. Lokal 60 x 60 cm polis) - merk
Pegasus
2. Plint granito ex. Lokal 8 x 60 cm polish 0.055
warna hitam
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac 0.261
2. Cat dinding partisi sekualitas Catylac 0.211
XI PEKERJAAN PINTU dan JENDELA
1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna 1.049
putih)
b. Daun Jendela Kaca Rangka Alumunium 0.482
(powder coating warna putih)
c. Kaca polos 5 mm 0.192

d. Engsel jendela 110 mm 0.110


e. Grendel/Spring Knif jendela 0.092
f. Hak Angin Stainless Steel 0.543
g. Pasang Rambucis 0.117
3. Pekerjaan Pintu Utama/PU -
a. Kusen aluminium 4" (powder coating warna 0.041
putih)
b. Pintu frameless (kaca tempered 12 mm 0.837
polos) 90 cm x 230 cm floor hinge sekualitas
DORMA BTS; Kunci Stainless
XII PEKERJAAN SANITASI
1. Saluran Pipa Kotoran (Kloset) Pipa PVC 0.054
Maspion tipe D diameter 4"
2. Saluran air kotor (floor drain dan wastafel) 0.043
Pipa PVC Maspion tipe D diameter 3"
3. Saluran air hujan (dari roof drain ke bak 0.425
kontrol) Pipa PVC Maspion tipe D diameter 3"
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 0.094
cm (taman)
5. Saluran air hujan (taman) Pipa PVC Maspion 0.108
tipe D diameter 4"
6. Saluran air Bersih Pipa PVC Maspion tipe 0.013
AW diameter 3/4"
7. Roof drain / saringan dak Kuningan 3 inchi 0.055

XIIIPEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu 0.242
b. Lampu Downlight LED Panel Philips DN027B 0.237
G2 14 watt - Cool Daylight
2. Pek. Instalasi Stop Kontak -
a. instalasi titik stop kontak 0.084
b. instalasi titik stop kontak AC 0.098
c. Stop kontak sekwa Broco 0.039
d. Stop kontak AC sekwa Broco 0.087
3. Pek. Instalasi Saklar -
a. instalasi titik Saklar 0.069
b. saklar ganda sekwa Broco 0.052
c. Saklar Tunggal sekwa Broco 0.024
100.00
- 0.035 0.500
- 0.04 0.53
Chart Title
4 5 6 7 8 9 10 11 12 13

0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011
0.071 0.071
0.106 0.106

0.231 0.231

0.187 0.187
0.136

0.135
0.097

0.222
0.298
1.040
0.380

0.837
1.220 1.220

0.780

0.088

0.584 0.584

0.197

0.784

0.541

0.132

0.836 0.836

0.227

0.119
0.050

0.374

0.037

0.893

0.079
1.143
0.072
0.247
0.538

2.064 2.064
0.555
0.155
1.769

0.805 0.805
0.487 0.487
0.407 0.407

0.161 0.161
0.163 0.163
0.102 0.102

0.715 0.715 0.715


0.632 0.632
0.779

0.156 0.156 0.156


0.186 0.186
0.229

0.128 0.128 0.128


0.092 0.092
0.116

0.104 0.104 0.104


0.204 0.204
0.126

0.692 0.692 0.692


0.601 0.601
0.595 0.595

0.740 0.740 0.740


0.623 0.623
0.396 0.396

0.095 0.095 0.095


0.101 0.101
0.053 0.053

0.047 0.047 0.047


0.044 0.044
0.025 0.025

2.089 2.089
1.773 1.773
2.159

0.337 0.337
0.234 0.234
0.285

0.576
0.338
0.208

1.103
1.354
0.834
0.904

0.272

0.152

0.926

0.055
5.767 6.779 8.781 5.395 3.802 7.491 4.024 4.443 8.794 6.023
6.30 13.08 21.86 27.26 31.06 38.55 42.57 47.02 55.81 61.83
rt Title
14 15 16 17 18 19 20 21 22

0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011


0.657

0.105
0.320
0.212
0.130

0.048
0.023
0.015

0.239
0.239
0.090

0.514
0.362
0.184

0.438
0.437
0.165

0.858
0.953
0.484

0.368
0.256
0.130

0.540
0.549
0.201

0.246
0.273
0.154

0.192
0.174
0.061
0.240
0.268
0.134

0.177
0.222
0.102

0.088
0.110
0.051

0.042
0.033
0.015

0.326
0.158
0.096

0.516
0.011
0.462

0.096
0.073
0.031

1.056
0.954

1.390 1.390 1.390

1.776 1.776
0.120
0.018
0.044
0.886

2.109 2.109

1.706 1.706

0.262

0.592
0.084
0.124
0.046

0.261
0.211

0.524 0.524

0.241 0.241

0.192

0.110
0.092
0.543
0.117
-
0.041

0.837

0.054

0.043

0.425
0.094

0.108

0.013

0.055

0.242
0.237

0.084
0.098
0.039
0.087

0.069
0.052
0.024

2.758 5.878 3.060 4.185 3.098 7.496 8.060 2.826 0.805


64.59 70.47 73.53 77.72 80.81 88.31 96.37 99.20 100.00
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 1 (SATU)
Tanggal : 10 Juni 2022 S / D 12 Juni 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 - - 0% - 0% -
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 - - 0% - 0% -
3. Bongkaran Bangunan lama OH - - - 0% - 0% -
4. Pembuangan dan pembersihan OH - - - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122
- - 0% - 0% -
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 - - 0% - 0% -
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 - - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395
100/100) - - 0% - 0% -
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 - - 0% - 0% -
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136
100/100, FP4 100/100) - - 0% - 0% -
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136
- - 0% - 0% -
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099
100/100) - - 0% - 0% -
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 - - 0% - 0% -
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 - - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 - - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519
- - 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 - - 0% - 0% -
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 - - 0% - 0% -
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 - - 0% - 0% -
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 - - 0% - 0% -
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 - - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 - - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 - - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167
Tampak depan - - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 - - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 - - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541
(Ruang Kepala dan Kasubag TU) - - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589
- - 0% - 0% -
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 - - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672
bata lama) - - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356
- - 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 - - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 - - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000
- - 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893
- - 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 - - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 - - 0% - 0% -

Halaman 48 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 - - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 - - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 - - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 - - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 - - 0% - 0% -
b. Begesting m2 134.46 13,464,704.10 0.987 - - 0% - 0% -
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 - - 0% - 0% -
d. Beton K.225 m3 26.89 24,136,267.36 1.769 - - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 - - 0% - 0% -
c. Beton K.225 m3 12.38 11,113,323.65 0.815 - - 0% - 0% -
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 - - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 - - 0% - 0% -
c. Beton K.225 m3 3.10 2,784,928.04 0.204 - - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 - - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 - - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 - - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 - - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 - - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 - - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 - - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 - - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 - - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 - - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 - - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 - - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 - - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 - - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 - - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 - - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 - - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 - - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 - - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 - - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 - - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 - - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 - - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 - - 0% - 0% -

Halaman 49 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 - - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 - - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 - - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 - - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 - - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 - - 0% - 0% -
b. Kolom m3 4.95 6,118,264.35 0.449 - - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 - - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 - - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 - - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 50 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 - - 0% - 0% -
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904
Kepala dan Kasubag TU)
- - 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272
TU) - - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 - - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 - - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926
polis) - merk Pegasus - - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 - - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 - - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 - - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 - - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482
- - 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 - - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 - - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 - - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 - - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 - - 0% - 0% -
3. Pekerjaan Pintu Utama/PU
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 - - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837
sekualitas DORMA BTS; Kunci Stainless
- - 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054
- - 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043
diameter 3" - - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425
D diameter 3" - - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 - - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108
- - 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 - - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 - - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 - - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237
- - 0% - 0% -

Halaman 51 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 - - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 - - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 - - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 - - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 - - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 - - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 - - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 - - -

Jumlah Kemajuan Pekerjaan (%) 0.0000


Rencana Kemajuan Pekerjaan (%) -
Devisiasi (%) -
Keterangan : TERLAMBAT / CEPAT TERLAMBAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 3 hari kalender
SISA WAKTU 147 hari kalender

Blora, 13 Juni 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 52 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 2 (DUA)
Tanggal : 13 Juni 2022 S / D 19 Juni 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 - - 100% 0.024 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 - - 5% 0.012 5% 0.012
3. Bongkaran Bangunan lama OH - - - 0% - 0% -
4. Pembuangan dan pembersihan OH - - - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 -
- 50% 0.061 50% 0.061
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 - - 0% - 0% -
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 - - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 -
100/100) - 50% 0.197 50% 0.197
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 - - 0% - 0% -
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 -
100/100, FP4 100/100) - 50% 0.068 50% 0.068
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 -
- 10% 0.014 10% 0.014
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 -
100/100) - 10% 0.010 10% 0.010
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 - - 20% 0.045 20% 0.045
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 - - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 - - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 -
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 - - 0% - 0% -
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 - - 0% - 0% -
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 - - 0% - 0% -
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 - - 0% - 0% -
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 - - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 - - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 - - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 -
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 - - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 - - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 -
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 -
- 0% - 0% -
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 - - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 -
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 -
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 - - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 - - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 - - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 -
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 -
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 - - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 - - 0% - 0% -

Halaman 53 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 - - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 - - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 - - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 - - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 - - 0% - 0% -
b. Begesting m2 134.46 13,464,704.10 0.987 - - 0% - 0% -
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 - - 0% - 0% -
d. Beton K.225 m3 26.89 24,136,267.36 1.769 - - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 - - 0% - 0% -
c. Beton K.225 m3 12.38 11,113,323.65 0.815 - - 0% - 0% -
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 - - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 - - 0% - 0% -
c. Beton K.225 m3 3.10 2,784,928.04 0.204 - - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 - - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 - - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 - - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 - - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 - - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 - - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 - - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 - - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 - - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 - - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 - - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 - - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 - - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 - - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 - - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 - - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 - - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 - - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 - - 0% - 0% -
b. Begesting m2 - - 0.000 - - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 - - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 - - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 - - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 - - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 - - 0% - 0% -
b. Begesting m2 0.000 - - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 - - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 - - 0% - 0% -

Halaman 54 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 - - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 - - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 - - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 - - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 - - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 - - 0% - 0% -
b. Kolom m3 4.95 6,118,264.35 0.449 - - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 - - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 - - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 - - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 55 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 - - 0% - 0% -
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 -
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 -
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 - - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 - - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 -
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 - - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 - - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 - - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 - - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 -
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 - - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 - - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 - - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 - - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 - - 0% - 0% -
3. Pekerjaan Pintu Utama/PU - -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 - - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 -
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 -
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 -
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 -
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 - - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 -
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 - - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 - - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 - - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 -
- 0% - 0% -

Halaman 56 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 - - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 - - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 - - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 - - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 - - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 - - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 - - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 - 0.43 0.4304

Jumlah Kemajuan Pekerjaan (%) 0.4304


Rencana Kemajuan Pekerjaan (%) 0.035
Devisiasi (%) 0.40
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 10 hari kalender
SISA WAKTU 140 hari kalender

Blora, 20 Juni 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 57 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 3 (TIGA)
Tanggal : 20 Juni 2022 S / D 26 Juni 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 5% 0.012 5% 0.012 10% 0.023
3. Bongkaran Bangunan lama OH - 0% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 50%
0.061 50% 0.061 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 0% - 100% 0.264 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0% - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 50.00%
100/100) 0.197 50% 0.197 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 0.00% - 20% 0.107 20% 0.107
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 50.00%
100/100, FP4 100/100) 0.068 50% 0.068 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 10.00%
0.014 10% 0.014 20% 0.027
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 10.00%
100/100) 0.010 10% 0.010 20% 0.020
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 20.00% 0.045 20% 0.045 40% 0.089
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 0.00% - 0% - 0% -
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 0.00% - 0% - 0% -
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 0.00% - 50% 1.228 50% 1.228
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 0.00% - 50% 0.156 50% 0.156
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00% - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 0.00%
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 0.00%
- 10% 0.359 10% 0.359
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -

Halaman 58 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 0.00% - 50% 2.096 50% 2.096
b. Begesting m2 134.46 13,464,704.10 0.987 0.00% - 50% 0.494 50% 0.494
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 0.00% - 100% 0.133 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 0.00% - 0% - 0% -
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 0.00% - 50% 0.823 50% 0.823
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 0.00% - 50% 0.812 50% 0.812
c. Beton K.225 m3 12.38 11,113,323.65 0.815 0.00% - 25% 0.204 25% 0.204
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 0.00% - 0% - 0% -
b. Begesting m2 51.72 5,438,215.85 0.399 0.00% - 0% - 0% -
c. Beton K.225 m 3
3.10 2,784,928.04 0.204 0.00% - 0% - 0% -
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -

Halaman 59 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 0.00% - 50% 0.103 50% 0.103
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 60 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 0.00%
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 0.00%
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00% - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 0.00%
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 0.00%
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 0.00%
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 0.00%
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 0.00%
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00% - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 0.00%
- 0% - 0% -

Halaman 61 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 0.43 7.18 7.6150

Jumlah Kemajuan Pekerjaan (%) 7.6150


Rencana Kemajuan Pekerjaan (%) 0.535
Devisiasi (%) 7.08
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 17 hari kalender
SISA WAKTU 133 hari kalender

Blora, 27 Juni 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 62 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 4 (EMPAT)
Tanggal : 27 Juni 2022 S / D 03 Juli 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 10.00% 0.023 5% 0.012 15% 0.035
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 20.00% 0.107 50% 0.267 70% 0.374
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 20.00%
0.027 70% 0.096 90% 0.123
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 20.00%
100/100) 0.020 80% 0.080 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 40.00% 0.089 60% 0.134 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 0.00% - 50% 0.422 50% 0.422
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 0.00% - 50% 1.231 50% 1.231
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 50.00% 1.228 50% 1.228 100% 2.456
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 50.00% 0.156 50% 0.156 100% 0.313
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00% - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 0.00%
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 10.00%
0.359 0% - 10% 0.359
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -

Halaman 63 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 50.00% 2.096 50% 2.096 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 50.00% 0.494 50% 0.494 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 0.00% - 25% 0.442 25% 0.442
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 50.00% 0.823 50% 0.823 100% 1.646
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 50.00% 0.812 50% 0.812 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 25.00% 0.204 25% 0.204 50% 0.407
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 0.00% - 50% 0.161 50% 0.161
b. Begesting m2 51.72 5,438,215.85 0.399 0.00% - 50% 0.199 50% 0.199
c. Beton K.225 m 3
3.10 2,784,928.04 0.204 0.00% - 25% 0.051 25% 0.051
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -

Halaman 64 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 50.00% 0.103 50% 0.103 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 65 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 0.00%
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 0.00%
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00% - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 0.00%
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 0.00%
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 0.00%
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 0.00%
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 0.00%
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00% - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 0.00%
- 0% - 0% -

Halaman 66 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 7.61 9.01 16.6249

Jumlah Kemajuan Pekerjaan (%) 16.6249


Rencana Kemajuan Pekerjaan (%) 6.302
Devisiasi (%) 10.32
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 24 hari kalender
SISA WAKTU 126 hari kalender

Blora, 04 Juli 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 67 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 5 (LIMA)
Tanggal : 04 Juli 2022 S / D 10 Juli 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 15.00% 0.035 5% 0.012 20% 0.047
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 70.00% 0.374 30% 0.160 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 90.00%
0.123 10% 0.014 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 50.00% 0.422 50% 0.422 100% 0.844
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 50.00% 1.231 50% 1.231 100% 2.462
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 100.00% 2.456 0% - 100% 2.456
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 100.00% 0.313 0% - 100% 0.313
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00% - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 0.00%
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 10.00%
0.359 0% - 10% 0.359
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -

Halaman 68 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 25.00% 0.442 75% 1.327 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 50.00% 0.407 50% 0.407 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 50.00% 0.161 50% 0.161 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 50.00% 0.199 50% 0.199 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 25.00% 0.051 75% 0.153 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -

Halaman 69 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 70 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 0.00%
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 0.00%
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00% - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 0.00%
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 0.00%
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 0.00%
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 0.00%
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 0.00%
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00% - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 0.00%
- 0% - 0% -

Halaman 71 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 16.62 4.09 20.7113

Jumlah Kemajuan Pekerjaan (%) 20.7113


Rencana Kemajuan Pekerjaan (%) 13.081
Devisiasi (%) 7.63
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 31 hari kalender
SISA WAKTU 119 hari kalender

Blora, 11 Juli 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 72 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 6 (ENAM)
Tanggal : 11 Juli 2022 S / D 17 Juli 2022

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 20.00% 0.047 5% 0.012 25% 0.059
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 100.00% 0.535 0% - 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 100.00%
0.136 0% - 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 100.00% 0.844 0% - 100% 0.844
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 100.00% 2.462 0% - 100% 2.462
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 100.00% 2.456 0% - 100% 2.456
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 100.00% 0.313 0% - 100% 0.313
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00% - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 0.00%
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 10.00%
0.359 0% - 10% 0.359
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -

Halaman 73 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 100.00% 1.769 0% - 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 100.00% 0.815 0% - 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 100.00% 0.322 0% - 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 100.00% 0.399 0% - 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 100.00% 0.204 0% - 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 60% 1.293 60% 1.293
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 40% 0.528 40% 0.528
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 30% 0.234 30% 0.234
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 60% 0.282 60% 0.282
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 30% 0.117 30% 0.117
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 20% 0.046 20% 0.046
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 40% 0.155 40% 0.155
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 30% 0.119 30% 0.119
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 60% 0.189 60% 0.189
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 40% 0.178 40% 0.178
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 30% 0.038 30% 0.038
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -

Halaman 74 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 10% 0.045 10% 0.045
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 10% 0.031 10% 0.031
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 75 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 5% 0.052 5% 0.052
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 0.00%
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 0.00%
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00% - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 0.00%
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 0.00%
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 0.00%
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 0.00%
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 0.00%
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00% - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 0.00%
- 0% - 0% -

Halaman 76 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 20.71 3.32 24.0276

Jumlah Kemajuan Pekerjaan (%) 24.0276


Rencana Kemajuan Pekerjaan (%) 21.862
Devisiasi (%) 2.17
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 38 hari kalender
SISA WAKTU 112 hari kalender

Blora, 18 Juli 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 77 dari 86
LAPORAN KEMAJUAN PEKERJAAN
Minggu ke : 7 (TUJUH)
Tanggal : ### S / D ###

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Jumlah Harga Minggu Lalu Minggu ini Prestasi Pek. S/D Minggu Ini
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 20.00% 0.047 5% 0.012 25% 0.059
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.814 0.00% - 0% - 0% -
19,896,336.53

II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 53.30 5,381,870.29 0.395 100.00%
100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 100.00% 0.535 0% - 100% 0.535
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 100.00%
0.136 0% - 100% 0.136
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 m3 5.54 1,356,913.68 0.099 100.00%
100/100) 0.099 0% - 100% 0.099
6. Urugan pasir Pondasi Batu Belah m 3
12.43 3,051,558.72 0.224 100.00% 0.224 0% - 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00%
- 0% - 0% -
51,335,948.57

III PEKERJAAN PONDASI


1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 100.00% 0.844 0% - 100% 0.844
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 100.00% 2.462 0% - 100% 2.462
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 100.00% 2.456 0% - 100% 2.456
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 60.00% 0.313 0% - 60% 0.313
82,861,615.28

IV PEKERJAAN PASANGAN DINDING


1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00% - 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 dan m2 151.14 15,922,375.86 1.167 0.00%
Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai 1 m2 36.52 7,375,801.84 0.541 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m 3
71.37 48,959,896.90 3.589 10.00%
0.359 30% 1.077 40% 1.436
96,704,508.11

V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00% - 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata baru dan m2 381.00 22,802,674.93 1.672 0.00%
bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 1 m2 84.32 4,853,382.16 0.356 0.00%
- 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis Lantai 2 m2 11.77 - 0.000 0.00%
- 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan Tampak m2 203.49 12,178,547.68 0.893 0.00%
- 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -

Halaman 78 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15

VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 100.00% 4.192 0% - 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 100.00% 0.987 0% - 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 100.00% 1.769 0% - 100% 1.769
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 100.00% 1.646 0% - 100% 1.646
b. Begesting m2 167.17 22,157,725.80 1.624 100.00% 1.624 0% - 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 100.00% 0.815 0% - 100% 0.815
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 100.00% 0.322 0% - 100% 0.322
b. Begesting m2 51.72 5,438,215.85 0.399 100.00% 0.399 0% - 100% 0.399
c. Beton K.225 m3 3.10 2,784,928.04 0.204 100.00% 0.204 0% - 100% 0.204
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 100% 2.154 100% 2.154
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 100% 1.321 100% 1.321
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 100% 0.779 100% 0.779
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 60% 0.282 60% 0.282
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 30% 0.117 30% 0.117
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 20% 0.046 20% 0.046
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 60% 0.189 60% 0.189
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 40% 0.178 40% 0.178
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 30% 0.038 30% 0.038
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 30% 0.620 30% 0.620
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 30% 1.396 30% 1.396
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 15% 0.333 15% 0.333
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 15% 1.264 15% 1.264
c. Beton K.225 m 3
12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 20% 0.057 20% 0.057
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 20% 0.137 20% 0.137
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 30% 0.043 30% 0.043
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 30% 0.093 30% 0.093
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 20% 0.917 20% 0.917
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 20% 2.653 20% 2.653
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -

Halaman 79 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 100.00% 0.205 0% - 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 50% 0.224 50% 0.224
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 50% 0.153 50% 0.153
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 50% 0.054 50% 0.054
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 50% 0.362 50% 0.362
920,216,854.01

VII PEKERJAAN PENUTUP ATAP

Halaman 80 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 50% 0.521 50% 0.521
14,218,909.51

VIII PEKERJAAN LANGIT-LANGIT


1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm (Ruang m2 90.15 12,325,294.97 0.904 0.00%
Kepala dan Kasubag TU)
- 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan Kasubag m2 90.15 3,717,198.40 0.272 0.00%
TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00% - 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03

IX PEKERJAAN PENUTUP LANTAI dan DINDING


1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x 60 cm m2 67.23 12,637,832.47 0.926 0.00%
polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54

X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77

XI PEKERJAAN PINTU dan JENDELA


1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna putih) m2 18.65 6,573,298.65 0.482 0.00%
- 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm floor hinge unit 2.00 11,416,350.00 0.837 0.00%
sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65

XII PEKERJAAN SANITASI


1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion tipe D m1 10.00 586,058.63 0.043 0.00%
diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC Maspion tipe m1 99.00 5,801,980.46 0.425 0.00%
D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00% - 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95

XIII PEKERJAAN INSTALASI LISTRIK


1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Daylight Set 19.00 3,230,460.75 0.237 0.00%
- 0% - 0% -

Halaman 81 dari 86
NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%) THP Peny-Tiap Nilai Bobot (%)
MC - 50 MC - 50
Pek. (%) Pek. (%) Pek. (%)
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 20.71 15.02 35.7311

Jumlah Kemajuan Pekerjaan (%) 35.7311


Rencana Kemajuan Pekerjaan (%) 27.257
Devisiasi (%) 8.47
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 45 hari kalender
SISA WAKTU 105 hari kalender

Blora, Monday, July 25, 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan

Halaman 82 dari 86
Analisa El - 119
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 1.19


JENIS PEKERJAAN : Keselamatan Dan Kesehatan Kerja
SATUAN PEMBAYARAN : Lump Sum

PERKIRAAN HARGA JUMLAH


No. URAIAN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Keselamatan dan Kesehatan Kerja


1 Sosialisasi dan Promosi Dan Pelatihan:
a. Papan Informasi K3 Buah - Rp - Rp -

2 Alat Pelindung Diri (APD)


Alat Pelindung Diri (APD) terdiri atas:
a. Topi pelindung (Safety helmet) Pekerja, Staf, dan Tamu Buah 6.00 Rp 30,000.00 Rp 180,000.00
b. Pelindung mata (Goggles, Spectacles) Sesuai Kebutuhan Psg - Rp - Rp -
c. Pelindung pernafasan dan mulut (Masker) Sesuai Kebutuhan Buah 20.00 Rp 10,000.00 Rp 200,000.00
d. Sarung tangan (Safety gloves) Sesuai Kebutuhan Psg 5.00 Rp 12,000.00 Rp 60,000.00
e. Sepatu keselamatan (Sepatu boot) Pekerja, Staf, dan Tamu Psg - Rp - Rp -

3 Fasilitas sarana kesehatan


a. Peralatan P3K (Kotak P3K, Obat Luka, Perban, Dll) Ls 1.00 Rp 200,000.00 Rp 200,000.00

JUMLAH Rp 640,000.00
OVERHEAD & PROFIT 10% Rp 64,000.00
TOTAL BIAYA KESELAMATAN DAN KESEHATAN KERJA Rp 704,000.00

Catatan :
1. Perkiraan Kuantitas harus disesuaikan dengan kebutuhan di lapangan
2. Harga perlu disesuaikan dengan harga terbaru, termasuk biaya personil
3. Yang dimaksud dengan konsultansi dengan Ahli terkait keselamatan konstruksi termasuk pakar dan praktisi
2 Dihitung MB.K -001 1 BH KURSI KAYU JATI TB 4 CM Ukuran (47cm x 230 cm ) #REF!
A Tenaga #REF!
L.01 0.5 OH Pekerja #REF! #REF!
L.02 1.0 OH Tukang Kayu #REF! #REF!
L.03 0.5 OH Kepala Tukang #REF! #REF!
L.04 0.05 OH Mandor #REF! #REF!
B Bahan #REF!
0.0414 m3 Papan Kayu Jati (dudukan) #REF! #REF!
8.6400 m1 #REF! #REF! #REF!
4.00 Bh Baut Tanam Rp 4,000.00 Rp 16,000.00
0.8 kg Lem Kayu #REF! #REF!
0.2 Kg Paku Biasa 2" - 5" #REF! #REF!
C PERALATAN
D Jumlah A + B + C #REF!
E Overhead & Profit 10% #REF!
F Harga Satuan Pekerjaan (D+E) #REF!

2 Dihitung MB.M -002 1 BH MEJA KAYU JATI TB. 4 CM Ukuran (80cm x 230 cm ) #REF!
A Tenaga #REF!
L.01 0.5 OH Pekerja #REF! #REF!
L.02 1.0 OH Tukang Kayu #REF! #REF!
L.03 0.5 OH Kepala Tukang #REF! #REF!
L.04 0.05 OH Mandor #REF! #REF!
B Bahan #REF!
0.0552 m3 Papan Kayu Jati #REF! #REF!
0.0576 m3 Balok Kayu Jati #REF! #REF!
6.00 Bh Baut Tanam Rp 4,000.00 Rp 24,000.00
0.8 kg Lem Kayu #REF! #REF!
0.25 Kg Paku Biasa 2" - 5" #REF! #REF!
C PERALATAN
D Jumlah A + B + C #REF!
E Overhead & Profit 10% #REF!
F Harga Satuan Pekerjaan (D+E) #REF!
REKAPITULASI

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTRIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI :Jln. Dr . Sutomo No.48 Blora
sumber dana :APBN TAHUN ANGGARAN 2022
MINGGU KE :7
PERIODE :18 JULI s/d 24 JULI 2022

NO URAIAN PEKERJAAN BOBOT (%) PROGRES (%) DOKUMENTASI


I PEKERJAAN PERSIAPAN 1.459 0.469
II PEKERJAAN TANAH 3.763 1.525
III PEKERJAAN PONDASI 6.074 6.074
IV PEKERJAAN DINDING 7.089 1.436
V PEKERJAAN PLESTERAN 4.674 -
VI PEKERJAAN BETON 67.458 25.706
VII PEKERJAAN PENUTUP ATAP 1.042 0.521
VIII PEKERJAAN LANGIT-LANGIT 1.800 -
IX PEKERJAAN PENUTUP LANTAI dan DINDING 0.982 -
X PEKERJAAN PENGECATAN 0.472 -
XI PEKERJAAN PINTU DAN JENDELA 3.462 -
XII PEKERJAAN SANITASI 0.793 -
XIII PEKERJAAN INSTALASI LISTRIK 0.932 -
JUMLAH TOTAL 100.000 35.731

REALISASI (Komulatif) : 35,731 %


RENCANA (Komulatif) : 27,257 %
DEVIASI : +8,47 %
PRESENTASI : Cepat (+)
SISA PROGRES : 64,269 %
SISA WAKTU (Hari Kalender) : 105 hari
PROGRES MINGGU LALU : 24,027 %

CATATAN : 1. Segera Melakukan Percepatan Pekerjaan Dengan Menambah Jumlah Pekerja

Mengetahui : BLORA, 25 JULI 2022


Pejabat Pembuat komitmen Konsultan Perencana
CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I SUHARIYAWAN, S.T


NIP. 198405082005011001 DIREKTUR
LAPORAN KEMAJUAN PEKERJAAN

Bulan ke : 1 (SATU)
Bulan : Juni

PAKET PEKERJAAN : REHAB GEDUNG BANGUNAN KANTOR KEMENTERIAN AGAMA KABUPATEN BLORA TAHUN 2022
LOKASI : Jln. Dr. Sutomo No. 48 Blora
SUMBER DANA : APBN Tahun Anggaran 2022
TAHUN ANGGARAN : 2022
Tanggal Kontrak : 10 Juni 2022
Kontrator Penyedia : CV. Anggrek Maju Jaya
Nilai Kontrak : 1,364,142,221.42
Jangka Waktu Pelaksanaan : 150 Hari Kalender
Serah Terima I (pertama) :
Masa Pemeliharaan : 6 Bulan
Serah Terima II (kedua) :

Prestasi Pek. S/D


Jumlah Harga Minggu Lalu Minggu ini
Minggu Ini
THP Peny-Tiap Nilai THP Nilai THP Nilai Bobot (%)

NO. URAIAN PEKERJAAN SATUAN Bobot MC. 50 Peny- Peny-


MC - 50 MC - 50 Bobot Bobot
Tiap Tiap
Pek. (%) (%) Pek. (%) (%) Pek. (%)
I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek Bh 1.00 327,716.40 0.024 100% 0.024 0% - 100% 0.024
2. Keselamatan Dan Kesehatan Kerja (K3) Lump Sum 1.00 3,196,120.13 0.234 10.00% 0.023 5% 0.012 15% 0.035
3. Bongkaran Bangunan lama OH - 0.00% - 0% - 0% -
4. Pembuangan dan pembersihan OH - 0.00% - 0% - 0% -
5. Pembongkaran Tembok dan PemasanganPintu Sliding ( 2) Buah BH 2.00 1,665,000.00 0.122 100.00%
0.122 0% - 100% 0.122
6 Pemindahan Jaringan & Instalasi Listrik Unit 1.00 3,607,500.00 0.264 100.00% 0.264 0% - 100% 0.264
7 Pemindahan Panel, Meteran, & Jaringan ( Pasang Kmbali) Unit 1.00 11,100,000.00 0.00%
0.814 - 0% - 0% -
19,896,336.53
II PEKERJAAN TANAH
1. Galian tanah Footplat (FP1 200/150, FP2 175/125, FP3 100/100, m3 53.30 5,381,870.29 0.395 100.00%
FP4 100/100) 0.395 0% - 100% 0.395
2. Galian tanah Pondasi Batu Belah m3 96.00 7,294,133.52 0.535 20.00% 0.107 50% 0.267 70% 0.374
3. Urugan tanah kembali Footplat (FP1 200/150, FP2 175/125, FP3 m3 33.96 1,856,739.21 0.136 100.00%
100/100, FP4 100/100) 0.136 0% - 100% 0.136
4. Urugan tanah kembali Pondasi Batu Belah m3 34.07 1,861,152.21 0.136 20.00% 0.027 70% 0.096 90% 0.123
5. Urugan pasir Footplat (FP1 200/150, FP2 175/125, FP3 m3 5.54 1,356,913.68 0.099 20.00%
100/100, FP4 100/100) 0.020 80% 0.080 100% 0.099
6. Urugan pasir Pondasi Batu Belah m3 12.43 3,051,558.72 0.224 40.00% 0.089 60% 0.134 100% 0.224
7. Urugan pasir Bawah lantai m3 16.55 4,065,021.65 0.298 0.00% - 0% - 0% -
8. urugan tanah pemadatan m3 133.34 19,387,344.90 1.421 0.00% - 0% - 0% -
9. Pemadatan urugan tanah per 20 cm m3 133.34 7,081,214.38 0.519 0.00% - 0% - 0% -
51,335,948.57
III PEKERJAAN PONDASI
1. Batu Kosong/Anstamping m3 24.87 11,507,344.44 0.844 0.00% - 50% 0.422 50% 0.422
2. Pondasi Batu Belah 1SP : 6 PP m3 45.13 33,590,050.91 2.462 0.00% - 50% 1.231 50% 1.231
3. Pembongkaran Pasangan Batu ( Manual ) m3 46.39 33,499,166.47 2.456 50.00% 1.228 50% 1.228 100% 2.456
4. Bongkaran Rabat Beton m3 6.22 4,265,053.46 0.313 50.00% 0.156 50% 0.156 100% 0.313
82,861,615.28
IV PEKERJAAN PASANGAN DINDING
1. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 1 m2 190.50 19,133,888.14 1.403 0.00% - 0% - 0% -
2. Bata merah 1/2 batu campuran 1PPC : 5PP-Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
3. Bata merah 1/2 batu campuran 1PPC : 5PP-Gavel m2 13.60 1,432,716.22 0.105 0.00% - 0% - 0% -
4. Bata merah 1/2 batu campuran 1PPC : 5PP-tangga teras m2 11.36 1,196,212.70 0.088 0.00%
- 0% - 0% -
5. Bata merah 1/2 batu campuran 1PPC : 5PP-Penebalan Kolom K-4 m2 151.14 15,922,375.86 1.167 0.00%
dan Tampak depan - 0% - 0% -
6. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 1 m2 15.26 2,683,616.44 0.197 0.00% - 0% - 0% -
7. Pasangan Bata Expose Campuran 1SP : 5PP-Lantai 2 m2 60.80 - 0.000 0.00% - 0% - 0% -
8. Pasang dinding partisi gypsum 2 muka (luar dalam) / m2 - Lantai m2 36.52 7,375,801.84 0.541 0.00%
1 (Ruang Kepala dan Kasubag TU) - 0% - 0% -
9. Pembongkaran Dinding Tembok Bangunan Lama m3 71.37 48,959,896.90 3.589 10.00% 0.359 0% - 10% 0.359
96,704,508.11
V PEKERJAAN PLESTERAN
1. Plesteran campuran 1PPC : 5PP-Tampak Pondasi dan Sloof m2 30.00 1,795,495.64 0.132 0.00%
- 0% - 0% -
2. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 1 (bata m2 381.00 22,802,674.93 1.672 0.00%
baru dan bata lama) - 0% - 0% -
3. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis m2 84.32 4,853,382.16 0.356 0.00%
Lantai 1 - 0% - 0% -
4. Plesteran campuran 1PPC : 5PP-Gavel m2 27.20 1,627,916.05 0.119 0.00% - 0% - 0% -
5. Plesteran campuran 1PPC : 5PP-Bata tangga teras m2 11.36 679,595.10 0.050 0.00% - 0% - 0% -
6. Plesteran campuran 1PPC : 5PP-dinding bata Lantai 2 m2 85.14 - 0.000 0.00% - 0% - 0% -
7. Plesteran campuran 1PPC : 5PP-balok latay dan Kolom Praktis m2 11.77 - 0.000 0.00%
Lantai 2 - 0% - 0% -
8. Plesteran campuran 1PPC : 5PP-Bata Penebalan Kolom K4 dan m2 203.49 12,178,547.68 0.893 0.00%
Tampak - 0% - 0% -
9. Acian-Tampak Pondasi dan Sloof m2 30.00 1,081,226.03 0.079 0.00% - 0% - 0% -
10. Acian-Lantai 1 m2 465.32 16,654,147.19 1.221 0.00% - 0% - 0% -
11. Acian-Gavel m2 27.20 980,311.60 0.072 0.00% - 0% - 0% -
12. Acian-Lantai 2 m2 96.91 - 0.000 0.00% - 0% - 0% -
13. Acian-Kolom K4 dan Tampak m2 11.77 1,108,803.78 0.081 0.00% - 0% - 0% -
14. Plesteran Skoning m1 - - 0.000 0.00% - 0% - 0% -
63,762,100.15
VI PEKERJAAN BETON
1. Footplat (FP1 200/150, FP2 175/125, FP3 100/100, FP4 100/100)
a. Pembesian kg 4,033.01 57,180,218.37 4.192 50.00% 2.096 50% 2.096 100% 4.192
b. Begesting m2 134.46 13,464,704.10 0.987 50.00% 0.494 50% 0.494 100% 0.987
c. Beton K.100 tb. 5 cm m3 2.27 1,813,318.73 0.133 100.00% 0.133 0% - 100% 0.133
d. Beton K.225 m3 26.89 24,136,267.36 1.769 0.00% - 25% 0.442 25% 0.442
2. Sloof S1 20/40
a. Pembesian kg 1,584.82 22,453,616.63 1.646 50.00% 0.823 50% 0.823 100% 1.646
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 167.17 22,157,725.80 1.624 50.00% 0.812 50% 0.812 100% 1.624
c. Beton K.225 m3 12.38 11,113,323.65 0.815 25.00% 0.204 25% 0.204 50% 0.407
3. Sloof S2 15/30
a. Pembesian kg 309.20 4,390,601.27 0.322 0.00% - 50% 0.161 50% 0.161
b. Begesting m2 51.72 5,438,215.85 0.399 0.00% - 50% 0.199 50% 0.199
c. Beton K.225 m3 3.10 2,784,928.04 0.204 0.00% - 25% 0.051 25% 0.051
4. Kolom K1 40/40 LANTAI 1
a. Pembesian kg 2,070.57 29,389,974.00 2.154 0.00% - 0% - 0% -
b. Begesting m2 124.24 18,020,986.48 1.321 0.00% - 0% - 0% -
c. Beton K.225 m3 11.83 10,620,020.47 0.779 0.00% - 0% - 0% -
5. Kolom K2 40/40 LANTAI 1
a. Pembesian kg 451.51 6,407,521.23 0.470 0.00% - 0% - 0% -
b. Begesting m2 36.54 5,300,290.14 0.389 0.00% - 0% - 0% -
c. Beton K.225 m3 3.48 3,123,535.43 0.229 0.00% - 0% - 0% -
6. Kolom KP 15/15 LANTAI 1
a. Pembesian kg 371.95 5,277,726.18 0.387 0.00% - 0% - 0% -
b. Begesting m2 53.24 5,394,990.53 0.395 0.00% - 0% - 0% -
c. Beton K.225 m3 1.76 1,581,289.81 0.116 0.00% - 0% - 0% -
7. Kolom K4 20/20 LANTAI 1
a. Pembesian kg 302.28 4,289,868.80 0.314 0.00% - 0% - 0% -
b. Begesting m2 42.11 6,081,626.02 0.446 0.00% - 0% - 0% -
c. Beton K.225 m3 1.91 1,717,944.49 0.126 0.00% - 0% - 0% -
8. Balok B1 35/70 elevasi +4.35
a. Pembesian kg 1,985.01 28,203,782.79 2.068 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 123.33 63,490,311.45 4.654 0.00% - 0% - 0% -
c. Beton K.225 m3 18.09 16,239,915.94 1.190 0.00% - 0% - 0% -
9. Balok B2 20/50 elevasi +4.35
a. Pembesian kg 2,130.16 30,254,841.64 2.218 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 245.55 114,976,492.34 8.428 0.00% - 0% - 0% -
c. Beton K.225 m3 12.04 10,804,021.84 0.792 0.00% - 0% - 0% -
10. Balok B4 15/35 elevasi +4.35
a. Pembesian kg 273.92 3,888,361.19 0.285 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 20.03 9,377,038.13 0.687 0.00% - 0% - 0% -
c. Beton K.225 m3 1.62 1,451,838.12 0.106 0.00% - 0% - 0% -
11. Balok B7 15/25 elevasi +4.35
a. Pembesian kg 136.56 1,937,570.38 0.142 0.00% - 0% - 0% -
b. Begesting m2 - - 0.000 0.00% - 0% - 0% -
b. Begesting m2 9.05 4,235,153.92 0.310 0.00% - 0% - 0% -
c. Beton K.225 m3 0.75 676,541.62 0.050 0.00% - 0% - 0% -
12. PLAT LANTAI 2 TYPE A ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 4,446.65 62,539,006.65 4.584 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 273.49 180,930,635.78 13.263 0.00% - 0% - 0% -
d. Beton K.225 m3 32.82 29,457,362.56 2.159 0.00% - 0% - 0% -
13. PLAT LANTAI 2 TYPE B ELEVASI +4.35 tb. 12 cm
a. Pembesian kg 742.07 10,404,197.71 0.763 0.00% - 0% - 0% -
b. Begesting m2 0.000 0.00% - 0% - 0% -
c. Begesting m2 36.08 23,865,636.85 1.749 0.00% - 0% - 0% -
d. Beton K.225 m3 4.33 3,885,570.37 0.285 0.00% - 0% - 0% -
14. KOLOM K1 40/40 LANTAI 2
a. Pembesian kg 556.29 - 0.000
b. Begesting m2 33.26 - 0.000
c. Beton K.225 m3 3.17 - 0.000
15. KOLOM K3 40/40 LANTAI 2
a. Pembesian kg 1,071.85 - 0.000
b. Begesting m2 129.89 - 0.000
c. Beton K.225 m3 12.67 - 0.000
16. KOLOM K4 20/20 LANTAI 2
a. Pembesian kg 311.61 - 0.000
b. Begesting m2 43.56 - 0.000
c. Beton K.225 m3 1.98 - 0.000
17. KOLOM KP 15/15 LANTAI 2
a. Pembesian kg 46.53 - 0.000
b. Begesting m2 6.73 - 0.000
c. Beton K.225 m3 0.22 - 0.000
18. Balok B4 15/35 elevasi +7.55
a. Pembesian kg 232.43 - 0.000
b. Begesting m2 23.23 - 0.000
c. Beton K.225 m3 1.37 - 0.000
19. Balok B2 20/50 elevasi +8.70
a. Pembesian kg 494.87 - 0.000
b. Begesting m2 34.72 - 0.000
c. Beton K.225 m3 2.80 - 0.000
20. Balok B4 15/35 elevasi +8.70
a. Pembesian kg 425.98 - 0.000
b. Begesting m2 42.47 - 0.000
c. Beton K.225 m3 2.51 - 0.000
21. PLAT DAK ATAP TYPE C ELEVASI +8.70 tb. 10 cm
a. Pembesian kg 877.78 - 0.000
b. Begesting m2 73.50 - 0.000
c. Beton K.225 m3 7.35 - 0.000
22. Balok B2 20/50 elevasi +9.30
a. Pembesian kg 359.42 - 0.000
b. Begesting m2 24.55 - 0.000
c. Beton K.225 m3 1.98 - 0.000
23. Balok B5 15/30 elevasi +9.30
a. Pembesian kg 521.44 - 0.000
b. Begesting m2 53.64 - 0.000
c. Beton K.225 m3 3.06 - 0.000
24. Tangga
a. Pembesian kg 286.05 3,992,325.95 0.293 0.00% - 0% - 0% -
b. Begesting m2 21.03 3,719,224.96 0.273 0.00% - 0% - 0% -
c. Beton K.225 m3 2.34 2,099,051.71 0.154 0.00% - 0% - 0% -
25. Kuda2 Beton Teras
a. Pembesian kg 185.60 - 0.000
b. Begesting m2 17.11 - 0.000
c. Beton K.225 m3 0.93 - 0.000
26. Beton Entrance
a. Pembesian kg 253.83 - 0.000
b. Begesting m2 24.86 - 0.000
c. Beton K.225 m3 2.04 - 0.000
27. Balok Latay 11/20-Lantai 1
a. Pembesian kg 173.31 - 0.000
b. Begesting m2 31.08 - 0.000
c. Beton K.225 m3 1.55 - 0.000
28. Balok Latay 11/20-Lantai 2
a. Pembesian kg 85.54 - 0.000
b. Begesting m2 16.80 - 0.000
c. Beton K.225 m3 0.77 - 0.000
29. Ringbalk 11/11-Gavel
a. Pembesian kg 41.24 - 0.000
b. Begesting m2 4.14 - 0.000
c. Beton K.225 m3 0.23 - 0.000
30. Sofi-sofi Pintu dan Jendela
a. Pembesian kg 448.13 - 0.000
b. Begesting m2 14.62 - 0.000
c. Beton K.225 m3 1.46 - 0.000
31. Droop Off
a. Pembesian kg 490.85 - 0.000
b. Begesting m2 1.35 - 0.000
c. Beton K.225 m3 7.02 - 0.000
32. Talang Droop Off tb. 7 cm
a. Pembesian kg 90.69 - 0.000
b. Begesting m2 6.80 - 0.000
c. Beton K.225 m3 0.48 - 0.000
33. Beton K. 100 Lantai
a. Pembesian kg 996.40 14,175,998.70 1.039 0.00% - 0% - 0% -
b. Beton K.100 m3 16.55 13,013,200.76 0.954 0.00% - 0% - 0% -
34. Pembongkaran Beton Lama
a. Sloof m3 2.27 2,799,569.45 0.205 50.00% 0.103 50% 0.103 100% 0.205
b. Kolom m3 4.95 6,118,264.35 0.449 0.00% - 0% - 0% -
c. Kolom Praktis m3 3.38 4,171,543.88 0.306 0.00% - 0% - 0% -
d. Tiang m3 1.20 1,483,215.60 0.109 0.00% - 0% - 0% -
e. RingBalok m3 8.00 9,887,485.99 0.725 0.00% - 0% - 0% -
920,216,854.01
VII PEKERJAAN PENUTUP ATAP
1. Kuda-kuda Besi Siku 75.75.7;70.70.7;60.60.6 dan 40.40.4 (KK1, kg 1,837.14 - 0.000
1/2 KK1, KK2 dan KK3)
2. Gording dan Jurai kg 1,565.39 - 0.000
3. Base Plat 6mm kg 52.75 - 0.000
4. Baut ∅ 5/8 inch panjang 5 cm Bh 18.00 - 0.000

5. Watermoor ∅ 16 Bh 18.00 - 0.000

6. Pengelasan, pengecatan kuda-kuda, gording dan perlengkapannya Ls 1.00 - 0.000

7. Reng dan usuk baja ringan merk Giga Steel m2 311.82 - 0.000
8. Atap genteng metal pasir/Rocky merk Kencana Tb. 0,25 mm m2 311.82 - 0.000

9. Nok genteng metal pasir/Rocky merk Kencana Tb. 0,25 mm m1 48.95 - 0.000

10. Atap galvalum tbl 0.35 mm (atap drop off) m2 65.28 - 0.000
11. Nok galvalum (atap drop off) m1 8.40 - 0.000
12. Pekerjaan talang (jurai dalam) m1 11.40 - 0.000
13. Pekerjaan flashing (pertemuan atap dengan dinding bata) m1 9.40 - 0.000

14. Pemasangan lisplank kalsiplank lb. 25 cm m1 - - 0.000


15. Pembongkaran 1 m2 penutup atap termasuk kuda - kuda m2 240.58 14,218,909.51 1.042 0.00% - 0% - 0% -
14,218,909.51
VIII PEKERJAAN LANGIT-LANGIT
1. Rangka plafond hollow galvanis 40.40.0,4 mm, modul 60 x 60 cm m2 90.15 12,325,294.97 0.904 0.00%
(Ruang Kepala dan Kasubag TU) - 0% - 0% -
2. Plafond gypsum 9 mm - merk Jayaboard (Ruang Kepala dan m2 90.15 3,717,198.40 0.272 0.00%
Kasubag TU) - 0% - 0% -
3. Pek. list plafon shadowline (Ruang Kepala dan Kasubag TU) m1 53.97 2,072,076.90 0.152 0.00%
- 0% - 0% -
4. Pek. Pembongkaran Plafond/Internit Gedung Lama m1 545.06 6,442,638.75 0.472 0.00% - 0% - 0% -
24,557,209.03
IX PEKERJAAN PENUTUP LANTAI dan DINDING
1. Lantai L1 -Ruang Kepala dan Kasubag TU (granito ex. Lokal 60 x m2 67.23 12,637,832.47 0.926 0.00%
60 cm polis) - merk Pegasus - 0% - 0% -
2. Plint granito ex. Lokal 8 x 60 cm polish warna hitam m2 4.02 756,408.06 0.055 0.00% - 0% - 0% -
13,394,240.54
X PEKERJAAN PENGECATAN
1. Cat plafon interior sekualitas Catylac m2 90.15 3,553,731.10 0.261 0.00% - 0% - 0% -
2. Cat dinding partisi sekualitas Catylac m2 73.05 2,879,392.67 0.211 0.00% - 0% - 0% -
6,433,123.77
XI PEKERJAAN PINTU dan JENDELA
1. Pekerjaan Jendela (J1, J2 dan BV)
a. Kusen aluminium 4" (powder coating warna putih) m1 176.40 14,305,314.93 1.049 0.00% - 0% - 0% -
b. Daun Jendela Kaca Rangka Alumunium (powder coating warna m2 18.65 6,573,298.65 0.482 0.00%
putih) - 0% - 0% -
c. Kaca polos 5 mm m2 20.84 2,612,417.39 0.192 0.00% - 0% - 0% -
d. Engsel jendela 110 mm Bh 56.00 1,495,913.03 0.110 0.00% - 0% - 0% -
e. Grendel/Spring Knif jendela Bh 28.00 1,257,485.92 0.092 0.00% - 0% - 0% -
f. Hak Angin Stainless Steel Bh 28.00 7,411,325.92 0.543 0.00% - 0% - 0% -
g. Pasang Rambucis Bh 28.00 1,599,365.92 0.117 0.00% - 0% - 0% -
3. Pekerjaan Pintu Utama/PU 0.00% -
a. Kusen aluminium 4" (powder coating warna putih) m1 6.84 554,695.88 0.041 0.00% - 0% - 0% -
b. Pintu frameless (kaca tempered 12 mm polos) 90 cm x 230 cm unit 2.00 11,416,350.00 0.837 0.00%
floor hinge sekualitas DORMA BTS; Kunci Stainless
- 0% - 0% -
47,226,167.65
XII PEKERJAAN SANITASI
1. Saluran Pipa Kotoran (Kloset) Pipa PVC Maspion tipe D diameter 4" m1 10.00 737,462.63 0.054 0.00%
- 0% - 0% -
2. Saluran air kotor (floor drain dan wastafel) Pipa PVC Maspion m1 10.00 586,058.63 0.043 0.00%
tipe D diameter 3" - 0% - 0% -
3. Saluran air hujan (dari roof drain ke bak kontrol) Pipa PVC m1 99.00 5,801,980.46 0.425 0.00%
Maspion tipe D diameter 3" - 0% - 0% -
4. Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm (taman) Buah 2.00 1,288,310.07 0.094 0.00% - 0% - 0% -
5. Saluran air hujan (taman) Pipa PVC Maspion tipe D diameter 4" m1 20.00 1,474,925.27 0.108 0.00%
- 0% - 0% -
6. Saluran air Bersih Pipa PVC Maspion tipe AW diameter 3/4" m1 10.00 181,269.66 0.013 0.00%
- 0% - 0% -
7. Roof drain / saringan dak Kuningan 3 inchi bh 11.00 754,184.23 0.055 0.00% - 0% - 0% -
10,824,190.95
XIII PEKERJAAN INSTALASI LISTRIK
1. Pek. Instalasi titik Lampu
a. instalasi titik lampu Titik 21.00 3,303,201.83 0.242 0.00% - 0% - 0% -
b. Lampu Downlight LED Panel Philips DN027B G2 14 watt - Cool Set 19.00 3,230,460.75 0.237 0.00%
Daylight - 0% - 0% -
2. Pek. Instalasi Stop Kontak
a. instalasi titik stop kontak Titik 6.00 1,141,468.46 0.084 0.00% - 0% - 0% -
b. instalasi titik stop kontak AC Titik 5.00 1,338,454.10 0.098 0.00% - 0% - 0% -
c. Stop kontak sekwa Broco Bh 6.00 529,303.50 0.039 0.00% - 0% - 0% -
d. Stop kontak AC sekwa Broco Bh 5.00 1,185,896.25 0.087 0.00% - 0% - 0% -
3. Pek. Instalasi Saklar
a. instalasi titik Saklar Titik 6.00 943,771.95 0.069 0.00% - 0% - 0% -
b. saklar ganda sekwa Broco Bh 3.00 711,537.75 0.052 0.00% - 0% - 0% -
c. Saklar Tunggal sekwa Broco Bh 3.00 326,922.75 0.024 0.00% - 0% - 0% -
12,711,017.33
1,364,142,221.42 100.00 7.61 9.01 16.6249
Jumlah Kemajuan Pekerjaan (%) 16.6249
Rencana Kemajuan Pekerjaan (%) 6.302
Devisiasi (%) 10.32
Keterangan : TERLAMBAT / CEPAT CEPAT

JANGKA WAKTU PELAKSANAAN 150 hari kalender


WAKTU YANG SUDAH BERJALAN 24 hari kalender
SISA WAKTU 126 hari kalender

Blora, 04 Juli 2022


Dibuat oleh :
Mengetahui : Konsultan Pengawas
Pejabat Pembuat komitmen CV. TEGAS SKALA TEKNIK

PARSAN,S.Sy.M.S.I WISNU ARIF SAPUTRA


NIP. 198405082005011001 Pengawas Lapangan