Vol
I PEKERJAAN PENDAHULUAN
1 Pembersihan lahan V = 10.00 x 10.00 = 100.00 M2
2 Pemasangan Bouwplank v = 9.00 X 7.00 = 63.00 M2
3 Papan proyek V = 1 set
Sub jumlah total
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak V = 1.00 X 1.00 X 0.50 x 4 = 2
M3
2 Galian Tanah Pondasi Menerus V = 0.80 X 0.50 X 33.00 = 13.2 M3
JUMLAH 15.2 M3
3 Galian Tanah tanah timbunan peninggian Lantai V = 3.60 X 7.50 X 6.00 = 162 M3
Urugan tanah V = 15.20 : 2.00 7.6 m3
JUMLAH 169.6 m3
3 Pekerjaan Pengecoran Balok Ring,Ps. 1:2:3 VBR = 32.80 X 0.2 X 0.25 = 1.64 m3
Pembesian ø 12, P = 10 m VCBR = 10.00 X 4 Btg X 2.00 Titik X 0.006165 X 144.00 = 71.0208 Kg
Pembesian ø 12, P = 8 m VBR = 8.00 X 4 Btg X 2.00 Titik X 0.006165 X 144.00 = 56.81664 Kg
Pembesian ø 8, P = 1,05 m VBR =(( 32.00 : 0.15 )X( 0.90 X 0.006165 X 64 ))'= 75.75552 Kg
JUMLAH 203.593 Kg
4 Pekerjaan Pengecoran Kolom,Ps. 1:2:3 VK1 = 6.00 X 0.2 X 0.20 X 5 Titik'= 1.2 m3
VK2 = 3.30 X 0.2 X 0.20 X 3 Titik'= 0.396 m3
JUMLAH 1.596 m3
Pembesian ø 12, P = 7,1 m VK1 = 7.10 X 4 Btg X 5.00 Titik X 0.006165 X 144.00 = 126.06192 Kg
Pembesian ø 12, P = 4,5 m VK2 = 4.50 X 4 Btg X 3.00 Titik X 0.006165 X 144.00 = 47.93904 Kg
Pembesian ø 8, P =5 m VCK1 =(( 6.00 : 0.15 )X( 0.90 X 5 Titik X 0.006165 X 64 ))'= 71.0208 Kg
Pembesian ø 8, P =3,5 m VCK1 =(( 6.00 : 0.15 )X( 0.90 X 3 Titik X 0.006165 X 64 ))'= 42.61248 Kg
JUMLAH = VK1 + VK2 + VCK1 + VCK2 287.63424 Kg
4 Pekerjaan Pengecoran Balok Tembok Layar,Ps. 1:2:3 VBTL1 = 5.00 X 0.15 X 0.15 X 4 Titik'= 0.45 m3
Pekerjaan Pengecoran Balok Tembok Layar,Ps. 1:2:3 VKTL 1 = 2.30 X 0.15 X 0.15 X 2 Titik'= 0.1035 m3
JUMLAH 0.5535 m3
Pembesian ø 12, P = 5,2 m VBTL1 = 5.20 X 4 Btg X 0.006165 X 144.00 X 4.00 Titik'= 73.861632 Kg
Pembesian ø 12, P = 2,3 m VKTL1 = 2.30 X 4 Btg X 2.00 Titik X 0.006165 X 144.00 = 16.334784 Kg
VCBTL1 =(( 5.00 : 0.15 )X( 0.70 X 4 Titik X 0.006165 X 64 ))'= 36.8256 Kg
VCKTL1 =(( 2.00 : 0.15 )X( 0.70 X 2 Titik X 0.006165 X 64 ))'= 7.36512 Kg
JUMLAH 134.38714 Kg
Pekerjaan Pasangan dinding Tembok Layar ,Ps. 1:4 VLDTl =(( 7.00 X 2.2 : 2 )X 2 ))Titik = 15.4 m2
2 Pekerjaan lantai ruang Kelas beton tumbuk t = 7 cm ,Ps. 1:2:4 V = 6.80 X 8.8 X 0.07 = 4.1888 m3
Pekerjaan lantai Teras beton tumbuk t = 7 cm ,Ps. 1:2:4 V = 1.50 X 9 X 0.07 = 0.945 m3
JUMLAH 5.1338 m3
VI PEKERJAAN PELESTERAN
1 Pekerjaan Dinding t= 15 mm Ps. 1 : 4 VLd = 48.95 + 15.4 X 2.00 = 79.75 m2
2 Pekerjaa Pelesteran Lantai t= 15 mm Ps. 1 : 4 V = 8.30 x 18 = 149.40 m2
JUMLAH 229.15 m2
2.c Kosen Jendela Type J1 VJ1 = 0.05 X 0.12 X 2.25 X 3 Btg = 0.0405 M3
VJ1 = 0.05 X 0.12 X 1.35 X 5 Btg = 0.0405 M3
X PEKERJAAN PENGECATAN
1.a Pengecatan dinding dan kolom
Volume Pengecatan = Volume Pengacian pada dinding dan kolom : V = 229.15 M2
1.b Volume Pengecatan = V Dinding +V Plafond + VLis Plafond + Kosen : V = 48.95 + 93.94 + 9.56 + 35.17 = 187.62 M2
2.a Kosen Jendela Type J1 VJ1 = 0.12 + 0.15 X 2.34 X 45 Btg = 15.915 M2
3. Kosen Daun Pintu Type P1 VP1 = 2.00 + 1.2 X 6.00 Unit = 9.2 M2
DIBUAT OLEH :
PANITIA PELAKSANA
KETUA BENDAHARA
CAT
1 Cat vinotex Kg 50,150.00
2 Cat kilat platon Kg 57,200.00
3 Plamir Kg 45,600.00
4 Cat menie Kg 66,654.00
5 Cat dasar Kg 42,145.00
6 Minyak Ter Kg 10,200.00
7 Soda Api Kg 40,000.00
8 Dempul Kg 55,000.00
9 Kuas2"-4" Bh 15,000.00
10 Kuas- Rol Bh 35,000.00
11
KERAMIK
1 Keramik uk. 50 x 50 cm Lbr 28,300.00
2 Keramik uk. 40 x 40 cm Lbr 17,260.00
3 Keramik uk. 30 x 30 cm Lbr 12,300.00
4 Keramik uk. 20 x 25 cm Lbr 8,350.00
5 Keramik uk. 20 x 20 cm Lbr 7,500.00
6 Ubin Keramik Lbr 2,650.00
7 Bon-bon keramik M' 1,850.00
GANTUNGAN KUNCI
1 Kunci tanam besar cap angker 8" Bh 138,750.00
2 Kunci tanam 808 Bh 78,600.00
3 Engsel Kupu-kupu (0,4) Psg 14,300.00
4 Kran Air 1/2 " Bh 36,000.00
5 Kran Air 3/4 " Bh 49,000.00
Engsel uk. Besar union Psg 47,000.00
6 Engsel uk. Kecil union Psg 37,200.00
7 Grendel uk. Kecil Bh 17,500.00
8 Grendel uk. Besar Bh 26,000.00
9 Handel uk. Besar Bh 38,000.00
10 Handel uk. Kecil Bh 8,400.00
11 Hak Angin ( Kait Angin ) Bh 9,700.00
SENG
56 Kaca bening tbl 5 mm Lbr 186,000.00
57 Seng Gelombang 3 " x 6 " BJLS 28 Lbr 53,690.00
58 Seng plat BJLS 0,2 mm uk. 6 K Lbr 45,000.00
59 Atap Seng BJLS 0,2 mm 7 K Lbr 46,000.00
60 Rabung Seng BJLS 0,2 mm 6 K Lbr 27,000.00
61 Seng plat 35 K Lbr 54,000.00
69 Atap Genteng Metal M2 62,950.00
70 Rabung Genteng Metal tebal 0,2 mm Lbr 21,600.00
PLAFOND
1 Gypsum board ( 9 mm) Lbr 117,290.00
2 Profil Gypsum M' 182,650.00
3 Furing C Zink Alume M' 8,080.00
75 Tripleks tebal 3 mm Lbr 60,000.00
76 Tripleks tebal 4 mm Lbr 75,000.00
77 Tripleks tebal 6 mm Lbr 105,000.00
LAMPU
1 Lampu TL 1 x 10 Watt Philips + Sarang Bh 73,900.00
2 Lampu PL 1 x 20 Watt Philips + Srang Bh 75,300.00
3 Lampu TL 1 x 40 Watt + Sarang Bh 96,350.00
4 Stop Kontak Bh 16,650.00
5 Saklar tuggal Bh 14,600.00
6 Saklar ganda Bh 19,800.00
7 Saklar triple Bh 21,300.00
8 Sekring Bh 45,200.00
9 Kabel Listrik NYM 2 x 2,5 mm M' 12,500.00
10 Terali besi( Anti Maling) M2 275,000.00
KOSEN PINTU, KOSEN JENDELA, DAUN PINTU DAN DAUN JENDELA
1 Daun Pintu Panel Unit 750,000.00
2 Daun Jendela Bingkai dan Kaca 5 mm Unit 325,000.00
3 Kosen Pintu 2,5 X 100 Unit 560,000.00
4 Kosen Jendela 3 Daun Unit 950,000.00
5 Kosen Jendela 4 Daun Unit 1,200,000.00
6 Jalusi Lbr 15,000.00
TANDRAZOMBOI ZEBUA
ANALISA HARGA SATUAN
KEGIATAN : DINAS PENDIDIKAN KABUPATEN NIAS SELATAN
PEKERJAAN : PEMBANGUNAN GEDUNG PERPUSTAKAAN SMKN. 2 LAHUSA
LOKASI : DESA SIHAREO KECAMATAN LAHUSA
8. SNI DT 91-0006 -2007-6.15 Mengurung 1 M3 timbunan tanah untuk peninggian lantai bangunan
1.200 M3 Tanah Timbunan pilihan @RP 55,000.00 @RP 66,000.00
0.250 HOK Pekerja @RP 73,000.00 @RP 18,250.00
0.025 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 84,250.00
11. SNI DT 91 - 2007 - 2006 - 6.2 Memasang 1 m3 Pondasi Batu belah, camp. 1 : 4 PP
1.20 M3 Batu Belah 15 cm/20 cm @RP 180,000.00 @RP 216,000.000
163.00 Kg Portland cement @RP 1,260.00 @RP 205,380.00
0.52 M3 Pasir pasang @RP 180,000.00 @RP 93,600.00
1.50 HOK Pekerja @RP 73,000.00 @RP 109,500.00
0.75 HOK Tukang batu @RP 80,000.00 @RP 60,000.00
0.08 HOK Kepala tukang @RP 90,000.00 @RP 6,750.00
0.08 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 691,230.00
12. SNI DT 91-2007-2006 Memasang 1M3 batu kosong (aanstamping)
1.200 M3 Batu belah 15 cm/20cm @RP 180,000.00 @RP 216,000.000
0.432 M3 pasir urung @RP 75,000.00 @RP 32,400.00
0.780 HOK pekerja @RP 73,000.00 @RP 56,940.00
0.390 HOK Tukang batu @RP 80,000.00 @RP 31,200.00
0.039 HOK kepala tukang @RP 90,000.00 @RP 3,510.00
0.039 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 340,050.00
15. SNI DT 91-2008-2007-6.17 Pembesian 10 kg dengan besi Polos atau besi ulir
10.500 Kg Besi beton (polos/ulir) @RP 11,150.00 @RP 117,075.000
0.150 Kg Kawat beton @RP 30,000.00 @RP 4,500.00
0.070 HOK pekerja @RP 73,000.00 @RP 5,110.00
0.070 HOK Tukang besi @RP 80,000.00 @RP 5,600.00
0.007 HOK Kepala tukang @RP 90,000.00 @RP 630.00
0.004 HOK Mandor @RP 0 @RP -
Jumlah @RP 132,915.00
Jumlah harga satuan pekerjaan @RP 13,291.50
26. SNI DT 91 - 0012 - 2007 6.35 Memasang 1 m2 lantai keramik ukuran (40x40) cm
6.250 Bh Keramik @RP 17,260.00 @RP 107,875.000
8.190 Kg Portland Cement @RP 1,260.00 @RP 10,319.400
0.045 M3 Pasir pasang @RP 180,000.00 @RP 8,100.00
1.620 Kg semen warna @RP 3,950.00 @RP 6,399.000
0.700 HOK Pekerja @RP 73,000.00 @RP 51,100.00
0.350 HOK Tukang batu @RP 80,000.00 @RP 28,000.00
0.035 HOK kepala tukang @RP 90,000.00 @RP 3,150.00
0.035 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 214,943.40
30.SNI DT 91-0011-2007-6.2 Membuat dan memasang 1 m3 kusen pintu dan kosen jendela, kayu kelas II dan III
1.200 M3 Balok kayu @RP 2,700,000.00 @RP 3,240,000.00
1.250 Kg paku 10 cm @RP 25,000.00 @RP 31,250.00
1.000 Kg lem kayu @RP - @RP -
6.000 HOK Pekerja @RP 73,000.00 @RP 438,000.00
18.000 HOK Tukang batu @RP 80,000.00 @RP 1,440,000.00
1.800 HOK kepala tukang @RP 90,000.00 @RP 162,000.00
0.300 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan 5,311,250.00
31.SNI DT 91-0011-2007-6.5 Membuat dan memasang 1 m3 daun pintu panel, kayu kelas I dan III
0.040 M3 papan kayu @RP 2,700,000.00 @RP 108,000.000
0.500 Kg lem kayu @RP - @RP -
1.000 HOK pekerja @RP 73,000.00 @RP 73,000.00
3.000 HOK tukang kayu @RP 80,000.00 @RP 240,000.000
0.300 HOK kepala tukang @RP 90,000.00 @RP 27,000.00
0.050 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 448,000.00
32.SNI DT 91-0011-2007-6.6 Membuat dan memasang 1 m2 Pintu dan jendela kaca,kayu kelas I atau II
0.024 M3 papan kayu @RP 2,700,000.00 @RP 64,800.000
0.300 Kg lem kayu @RP - @RP -
0.800 HOK pekerja @RP 73,000.00 @RP 58,400.00
2.400 HOK tukang kayu @RP 80,000.00 @RP 192,000.000
0.240 HOK kepala tukang @RP 90,000.00 @RP 21,600.00
0.040 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 336,800.00
33.SNI DT 91-0011-2007-6.13 Memasang 1 m3 kostruksi kuda kuda konvensional,kayu kelas I, II dan III
1.100 M3 Balok kayu @RP 2,700,000.00 @RP 2,970,000.00
15.000 Kg Besi strip tabel 5 mm @RP 7,500.00 @RP 112,500.00
5.600 Kg Paku 12 cm @RP 25,000.00 @RP 140,000.00
4.000 HOK pekerja @RP 73,000.00 @RP 292,000.00
12.000 HOK Tukang kayu @RP 80,000.00 @RP 960,000.00
1.200 HOK Kepala tukang @RP 90,000.00 @RP 108,000.00
0.200 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 4,582,500.00
SNI.DT 91-0014-2007-6.19 Memasang 1m talang 1/2 lingkaran D-15 cm,seng plat BJLS
1.0500 Lbr Seng plat @RP 45,000.00 @RP 47,250.00
0.0100 Kg Paku 1 cm-2,5 cm @RP 46,000.00 @RP 460.00
0.5000 Kg Besi strip @RP 7,500.00 @RP 3,750.00
0.1500 HOK Pekerja @RP 73,000.00 @RP 10,950.00
0.3000 HOK Tukang besi @RP 80,000.00 @RP 24,000.00
0.0300 HOK Kepala tukang @RP 90,000.00 @RP 2,700.00
0.0080 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 89,110.00
37.SNI.DT 91-0011-2007-6.21 Memasang 1m1 lisplank ukuran (2x20) cm, kayu kelas I atau kelas II
0.0108 M3 Papan kayu @RP 29,160.00 @RP 314.93
0.1000 Kg Paku 5 cm daN 7 Cm @RP 25,000.00 @RP 2,500.00
0.1000 HOK Pekerja @RP 73,000.00 @RP 7,300.00
0.2000 HOK Tukang kayu @RP 80,000.00 @RP 16,000.00
0.0200 HOK Kepala tukang @RP 90,000.00 @RP 1,800.00
0.0050 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 27,914.93
39.SNI.DT 91-0011-2007-6.19 Memasang 1 m2 rangka langit langit kayu kelas II atau III
0.015 M3 Kaso-Kaso (5x7)cm @RP 2,700,000.00 @RP 41,580.00
0.200 Kg Paku 7 cm-10 cm @RP 25,000.00 @RP 5,000.00
0.015 HOK Pekerja @RP 73,000.00 @RP 1,095.00
0.030 HOK Tukang kayu @RP 80,000.00 @RP 2,400.00
0.030 HOK Kepala tukang @RP 90,000.00 @RP 2,700.00
0.075 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 52,775.00
42.PT.T-38.2000-C 1 m2 Pengecatan Bidang kayu baru (1 lapis plamir), 1 lapis cat Dasar, 2 lapis cat penutup
0.200 Kg Cat meni @RP 66,654.00 @RP 13,330.80
0.150 Kg Plamir @RP 45,600.00 @RP 6,840.00
0.170 Kg Cat dasar @RP 42,145.00 @RP 7,164.65
0.260 Kg Cat kayu glotek/platon @RP 57,200.00 @RP 14,872.00
0.070 HOK Pekerja @RP 73,000.00 @RP 5,110.00
0.009 HOK Tukang cat @RP 80,000.00 @RP 720.00
0.006 HOK Kepala tukang @RP 90,000.00 @RP 540.00
0.003 HOK Mandor @RP 0.00 @RP -
Jumlah harga satuan pekerjaan @RP 48,577.45
43.PT.T-38.2000-C-1 1 m2 Pengecatan Bidang Temdok baru (1 plamir, 1 lapis cat Dasar, 2 lapis cat penutup )
0.1000 Kg Pelamir @RP 45,600.00 @RP 4,560.00
0.1000 Kg Cat dasar @RP 42,145.00 @RP 4,214.50
0.2600 Kg Cat tembok @RP 50,150.00 @RP 13,039.00
0.0200 HOK Pekerja @RP 73,000.00 @RP 1,460.00
0.0630 HOK Tukang cat @RP 80,000.00 @RP 5,040.00
0.0063 HOK Kepala tukang @RP 90,000.00 @RP 567.00
0.0025 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 28,880.50
44.PT.T-38.2000-C-2 1 m2 Pengecatan plafond baru ( plamir, 1 lapis cat Dasar, 2 lapis cat penutup )
0.1000 Kg Pelamir @RP 45,600.00 @RP 4,560.00
0.1000 Kg Cat dasar @RP 42,145.00 @RP 4,214.50
0.2600 Kg Cat tembok @RP 50,150.00 @RP 13,039.00
0.0200 HOK Pekerja @RP 73,000.00 @RP 1,460.00
0.0630 HOK Tukang cat @RP 80,000.00 @RP 5,040.00
0.0063 HOK Kepala tukang @RP 90,000.00 @RP 567.00
0.0025 HOK Mandor @RP - @RP -
Jumlah harga satuan pekerjaan @RP 28,880.50
NO URAIAN PEKERJAAN
JUMLAH
I PEKERJAAN PENDAHULUAN 3,450,000.00
II PEKERJAAN TANAH 13,976,760.00
III PEKERJAAN PONDASI 45,877,983.51
IV PEKERJAAN BETON BERTULANG 41,804,280.37
V PEKERJAAN PASANGAN 69,243,754.75
VI PEKERJAAN PELESTERAN 9,993,748.89
VII PEKERJAAN KOSEN PINTU DAN JENDELA 12,765,290.40
VIII PEKERJAAN RANGKA ATAP 15,857,792.86
IX PEKERJAAN RANGKA PLAFOND 18,273,998.75
X PEKERJAAN PENGECATAN 12,204,353.04
XI PEKERJAAN MOBILER 17,353,237.42
XII PEMASANGAN GANTUNGAN 4,748,800.00
XIII PEKERJAAN LAIAN 2,450,000.00
JUMLAH TOTAL BIAYA 268,000,000.00
DIBULATKAN 2,680,000,000.00
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M3 7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00
Sub jumlah total 13,976,760.00
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00
Sub jumlah total 69,243,754.75
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89
Sub jumlah total 9,993,748.89
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50
Sub jumlah total 12,204,353.04
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00
Sub jumlah total 17,353,237.42
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0 0.2451
3 Galian Tanah Pondasi Menerus 13.20 M 3
6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0 0.2697
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M3 7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 0 Seluruh
4.7004
Sub jumlah total 13,976,760.00 5.2152 0 Pekerjaan
5.2152
%
III PEKERJAAN PONDASI
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 0 15.6120
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M3 12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 0 1.2638
3 Pekerjaan Lantai Kerja 6.13 M3 23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0 0.0959
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0 0.1470
Sub jumlah total 45,877,983.51 17.1187 0 17.1187
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 0 1.7495
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0 0.7770
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0 0.7877
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 0 8.8085
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M 2
26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 0 25.8372
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XI PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 Seluruh
0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M3 7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004
Pekerjaan0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152
%
0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 0 8.8085
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M 2
26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 0 25.8372
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
Bobot Penyelesaian
(RP ) ( RP ) % %
I PEKERJAAN PENDAHULUAN
I PEKERJAAN PENDAHULUAN -
1 Pekerjaan Pembersihan lokasi 1.00 - Ls 1,200,000.00 1,200,000.00 0.4478 0.4478 0.0000
2 Pembuatan Los Kerja dan Gudang bahan 1.00 - Ls 1,250,000.00 1,250,000.00 0.4664 0.4664 0.0000
3 Pekerjaan Pengukuran dan Pembuatan Bouwplak 1.00 - Ls 650,000.00 650,000.00 0.2425 0.2425 0.0000
4 Pembuatan Papan Pengenal Proyek 1.00 - Ls 350,000.00 350,000.00 0.1306 0.1306 0.0000
Sub. Jumlah - I 3,450,000.00 1.2873 1.2873 0.0000
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 Seluruh
0.0000
M3 Pekerjaan
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
%
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 0 8.8085
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M 2
26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 0 25.8372
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 0 8.8085
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 0 25.8372
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 0 8.8085
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 0 25.8372
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 2.9362 5.8724
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 2.9362 22.9010
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 8.8085 17.0287
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 8.8085 17.0287
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 0 7.4044
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 8.8085 17.0287
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 0 3.7290
Sub jumlah total 9,993,748.89 3.7290 0 3.7290
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 0 2.5683
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0 0.0997
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 0 1.8859
Sub jumlah total 12,204,353.04 4.5539 0 4.5539
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN LAIAN
1 Pembersihan Akhir 1.00 Ls Dihitung 1,200,000.00 1,200,000.00 0.4478 0 0.4478
2 Dokumentasi 1.00 Ls Dihitung 500,000.00 500,000.00 0.1866 0 0.1866
3 Pembuatan Laporan (SPJ) 1.00 Ls Dihitung 750,000.00 750,000.00 0.2799 0 0.2799
Sub jumlah total 2,450,000.00 0.9142 0 0.9142
JUMLAH TOTAL 268,000,000.00
Dibulatkan 268,000,000.00 100.0000 74.2756 25.7244
Dibaca DUA RATUS ENAM PULUH DELAPAN JUTA RUPIAH
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 2.5683 0.0000
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0.0997 0.0000
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 1.8859 0.0000
Sub jumlah total 12,204,353.04 4.5539 4.5539 0.0000
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 0 2.9676
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 0 2.6119
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0 0.8955
Sub jumlah total 17,353,237.42 6.4751 0 6.4751
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 2.5683 0.0000
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0.0997 0.0000
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 1.8859 0.0000
Sub jumlah total 12,204,353.04 4.5539 4.5539 0.0000
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 1.4838 1.4838
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 2.6119 0.0000
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0.4478 0.4478
Sub jumlah total 17,353,237.42 6.4751 4.5435 1.9316
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0 0.0673
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0 0.0917
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0 0.7339
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0 0.5006
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0 0.3784
Sub jumlah total 4,748,800.00 1.7719 0 1.7719
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 2.5683 0.0000
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0.0997 0.0000
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 1.8859 0.0000
Sub jumlah total 12,204,353.04 4.5539 4.5539 0.0000
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 2.9676 0.0000
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 2.6119 0.0000
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0.8955 0.0000
Sub jumlah total 17,353,237.42 6.4751 6.4751 0.0000
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0.0673 0.0000
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0.0917 0.0000
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0.7339 0.0000
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0.5006 0.0000
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0.3784 0.0000
Sub jumlah total 4,748,800.00 1.7719 1.7719 0.0000
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 0 9.6243
Sub jumlah total 69,243,754.75 25.8372 16.2129 9.6243
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 2.5683 0.0000
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0.0997 0.0000
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 1.8859 0.0000
Sub jumlah total 12,204,353.04 4.5539 4.5539 0.0000
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 2.9676 0.0000
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 2.6119 0.0000
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0.8955 0.0000
Sub jumlah total 17,353,237.42 6.4751 6.4751 0.0000
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0.0673 0.0000
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0.0917 0.0000
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0.7339 0.0000
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0.5006 0.0000
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0.3784 0.0000
Sub jumlah total 4,748,800.00 1.7719 1.7719 0.0000
NOMOR :
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Umpak 12.00 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 657,000.00 0.2451 0.2451 0.0000
3 Galian Tanah Pondasi Menerus 13.20 M3 6. SNIDt 91-0006-2007- 6.1 54,750.00 722,700.00 0.2697 0.2697 0.0000
2 Urugan tanah dan tanah timbunan peninggian lantai ruang kelas 149.52 M 3
7. 1/2 SNI. DT 91-0006 -2007-6.9 84,250.00 12,597,060.00 4.7004 4.7004 0.0000
Sub jumlah total 13,976,760.00 5.2152 5.2152 0.0000
Seluruh
III PEKERJAAN PONDASI Pekerjaan
1 Pekerjaan Pondasi Menerus, Pas.Batu Kali,Ps. 1:4 60.53 M3 11. SNI DT 91 - 2007 - 2006 - 6.2 691,230.00 41,840,151.90 15.6120 15.6120 %
0.0000
2 Pekerjaan Pondasi Menerus, Pas.Batu Kosong, Ps. 1:4 9.96 M 3
12. SNI DT 91-2007-2006 340,050.00 3,386,898.00 1.2638 1.2638 0.0000
3 Pekerjaan Lantai Kerja 6.13 M 3
23.SNI DT 91-0010-2007-6.4 41,932.40 257,045.61 0.0959 0.0959 0.0000
4 Pekerjaan Pasir Urug 3.52 M3 9. SNI DT 91 -0006 -2007-6.11 111,900.00 393,888.00 0.1470 0.1470 0.0000
Sub jumlah total 45,877,983.51 17.1187 17.1187 0.0000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan Pengecoran Pondasi Tapak,Ps. 1:2:3
a. Cor beton K-175 4.85 M3 18.SNI DT 91-0008-2007-6.28 966,720.50 4,688,594.41 1.7495 1.7495 0.0000
b. Pekerjaan Pembesian 156.68 Kg 15. SNI DT 91-2008-2007-6.17 13,291.50 2,082,472.35 0.7770 0.7770 0.0000
c. Pekerjaan Bekesting 21.60 M2 16.SNI DT- 0008-2007-6.22 97,728.00 2,110,924.80 0.7877 0.7877 0.0000
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan dinding ,Ps. 1:4 146.85 M2 20.SNI DT 91-0010-2007-6.17 160,755.00 23,606,871.75 8.8085 8.8085 0.0000
2 Pekerjaan lantai beton tumbuk t = 7 cm ,Ps. 1:2:4 8.50 M3 22.SNI DT 91-0008-2007-6.13 2,334,550.00 19,843,675.00 7.4044 7.4044 0.0000
3 Memasang 1 m2 lantai keramik ukuran (40x40) cm 120.00 M2 26. SNI DT 91 - 0012 - 2007 6.35 214,943.40 25,793,208.00 9.6243 9.6243 0.0000
Sub jumlah total 69,243,754.75 25.8372 25.8372 0.0000
VI PEKERJAAN PELESTERAN
1 Pekerjaan Plesteran Dinding dan Lantai t= 15 mm Ps. 1 : 4 238.33 M2 23.SNI DT 91-0010-2007-6.4 41,932.40 9,993,748.89 3.7290 3.7290 0.0000
Sub jumlah total 9,993,748.89 3.7290 3.7290 0.0000
X PEKERJAAN PENGECATAN
238.33 M 43.PT.T-38.2000-C-1
2
1 Pekerjaan Pengecatan Dinding 28,880.50 6,883,089.57 2.5683 2.5683 0.0000
5.5 M 42.PT.T-38.2000-C
2
2 Pekerjaan Pengecatan Kosen dan daun Kosen 48,577.45 267,175.98 0.0997 0.0997 0.0000
175 M 44.PT.T-38.2000-C-2
2
3 Pekerjaan Pengecatan Plafond 28,880.50 5,054,087.50 1.8859 1.8859 0.0000
Sub jumlah total 12,204,353.04 4.5539 4.5539 0.0000
XI PEKERJAAN MOBILER
1 Rak Buku 4 Unit Harga Satuan + Upah 1,988,309.36 7,953,237.42 2.9676 2.9676 0.0000
2 Meja Siswa 20 Unit Harga Satuan + Upah 350,000.00 7,000,000.00 2.6119 2.6119 0.0000
3 Kursi Siswa 10 Unit Harga Satuan + Upah 240,000.00 2,400,000.00 0.8955 0.8955 0.0000
Sub jumlah total 17,353,237.42 6.4751 6.4751 0.0000
XII PEMASANGAN GANTUNGAN
1 Memasang Kunci tanam pada pintu 1.00 Ls 45.PT.T-30.2000-C 180,380.00 180,380.00 0.0673 0.0673 0.0000
2 Memasang engsel pintu 4.00 Ls 46.PT.T-38.2000-C-1 61,445.00 245,780.00 0.0917 0.0917 0.0000
3 Memasang engsel jendela 42.00 Ls 47.PT.T-30.2000-C-2 46,830.00 1,966,860.00 0.7339 0.7339 0.0000
4 Memasang grendel jendela 42.00 Ls 48.PT.T-30.2000-C-3 31,945.00 1,341,690.00 0.5006 0.5006 0.0000
5 Memasang Kait angin 42.00 Ls 49. PT.T-30.2000-C-4 24,145.00 1,014,090.00 0.3784 0.3784 0.0000
Sub jumlah total 4,748,800.00 1.7719 1.7719 0.0000
PENERIMAAN PENYETORAN
PPh PPH PPn DN Lain 2 Jumlah PPN Psl PPH PPn DN Lain 2 Jumlah
Psl 21
NO TGL URAIAN Psl 22 Psl 21 NO TGL URAIAN 22 Psl 21 Psl 21
RP RP RP RP (RP) RP RP RP RP (RP)
1 30-09-2013 Terima pajak dari UD. Oliver 13,295.45 88,636.36 101,931.82 1 30-09-2013 Terima pajak dari UD. Oliver 13,295.45 - 88,636.36 101,931.82
2 30-11-2013 Terima pajak PPN Psl dari UD. Oliver - - - 30-11-2013 Terima pajak PPN Psl dari UD. Oliver - - -
Sihareo, 2014
NO. JUMLAH
TANGGAL BUKTI JENIS DAN URAIAN
KAS BIAYA
Pembelian Bahan Kayu Pembangunan Gedung
14-09-2014 01 11,174,000.00
Perpustakaan SMKN. 4 Lahusa Bapak Bena Hulu
Pembelian Barang Bahan Bangunan Gedung Perpustakaan
14-09-2014 02 975,000.00
SMKN. 4 Lahusa Kepada UD. MARDIN di Gomo
Pembelian Bahan Material Pembangunan Gedung
14-09-2013 03 Perpustakaan SMKN. 4 Lahusa Kepada Bapak Antonius di 20,033,000.00
Helezalulu
Pembayaran Transportasi Pengangkutan Bahan
21-09-2013 04 Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa 1,109,000.00
Nomor terlampir Kepada Bapak Awalan Laia
Pembayaran Honor Jaga Malam Bulan September Pada
30-09-2013 05 Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa 1,000,000.00
Kepada Bapak Ogamota Ndruru
Pembayaran Upah Tukang dan pekerja pada
Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa dari
30-09-2013 06 11,480,000.00
Tanggal 02 s/d 28 September 2013 Kepada Bapak
Waspada Hulu
JUMLAH 45,771,000.00
Catatan : Pajak belum tercantum didalamnya
NO. JUMLAH
TANGGAL BUKTI JENIS DAN URAIAN
KAS BIAYA
Pembayaran Upah Petugas Jaga Malam pada
Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa dari
12-10-2013 07 1,000,000.00
tanggal 30 September s/d 12 Oktober 2013, Kepada
Bapak Ogamota Ndruru
Pembayaran Upah tukang dan pekerja pada Pembangunan
31-10-2013 08 Gedung Perpustakaan SMKN. 4 Lahusa Kepada Bapak 5,740,000.00
Waspada Hulu
JUMLAH 6,740,000.00
1,093,000.00
75,978,000.00 268,000,061.51
45,771,000.00 107,200,024.60
30,207,000.00
251,940,000.860
100,776,000.344
30,207,000.00
6,740,000.00
-
#REF!
LAPORAN BULANAN PENYERAPAN DANA DAK
PEMBANGUNAN GEDUNG PERPUSTAKAAN SMKN. 2 LAHUSA
(Untuk Biaya Konstruksi )
Bulan November 2013
120,600,000.00
102,008,000.00
18,592,000.00 2,000.00
LAPORAN BULANAN PENYERAPAN DANA DAK
PEMBANGUNAN GEDUNG PERPUSTAKAAN SMKN. 4 LAHUSA
(Untuk Biaya Konstruksi )
Bulan Desember 2013
NO. JUMLAH
TANGGAL BUKTI JENIS DAN URAIAN
KAS BIAYA
Pembelian bahan barang untuk Bangunan Gedung
28-12-2013 16 13,930,000.00
Perpustakaan SMKN. 4 Lahusa Kepada Bapak Antonius
Pembelian Bahan Barang Pembangunan Gedung
28-12-2013 17 19,385,000.00
Perpustakaan SMKN. 4 Lahusa Kepada Bapak Awalan Laia
Pembayaran Honor jaga malam Bulan November pada
28-12-2013 18 Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa 1,000,000.00
Kepada Bapak Ogamota Ndruru
Pembayaran Upah Tukang dan pekerja pada Pembangunan
s
1,762,272.73 17,622,727.27 264,340.91 2,026,613.64
231,000.00
KAS UMUM DANA PEMBANGUNAN GEDUNG PERPUSTAKAAN SMKN. 4 LAHUSA TA. 2013
TGL URAIAN PAJAK BANK KAS TGL URAIAN PAJAK BANK KAS
KAS
1 2 3 4 5 6 7 8 9 10 11 12
30-08-2013 1 Terima Dana DAK Rehap dari Bank SUMUT 80,400,000
09-09-2013 2 Penarikan dari Bank 1 80,400,000 Penarikan dana DAK dari Bank SUMUT 80,400,000
Pembelian Bahan Kayu Pembangunan Gedung Perpustakaan SMKN.
30-09-2013 3 Terima Pajak PPn 21 dari UD. OLIVER 88,636.36 14-09-2014 01 11,174,000
4 Lahusa Bapak Bena Hulu
Pembelian Barang Bahan Bangunan Gedung Perpustakaan SMKN. 4
30-09-2013 4 Terima Pajak PPh 22 dari UD. OLIVER 13,295.45 14-09-2014 02 975,000
Lahusa Kepada UD. MARDIN di Gomo
Pembelian Bahan Material Pembangunan Gedung Perpustakaan
14-09-2013 03 20,033,000
SMKN. 4 Lahusa Kepada Bapak Antonius di Helezalulu
Pembayaran Transportasi Pengangkutan Bahan Pembangunan
21-09-2013 04 Gedung Perpustakaan SMKN. 4 Lahusa Nomor terlampir Kepada 1,109,000
Bapak Awalan Laia
Pembayaran Honor Jaga Malam Bulan September Pada
30-09-2013 05 Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa Kepada 1,000,000
Bapak Ogamota Ndruru
Pembayaran Upah Tukang dan pekerja pada Pembangunan Gedung
2 Saldo Pajak 101,931.82 12-10-2013 07 Perpustakaan SMKN. 4 Lahusa dari tanggal 30 September s/d 12 5,740,000
PENERIMAAN PENGELUARAN
NO. NO.
TGL BUKTI URAIAN PAJAK BANK KAS TGL BUKTI URAIAN PAJAK BANK KAS
KAS KAS
1 2 3 4 5 6 7 8 9 10 11 12
31-10-2013 1 Terima Dana DAK Rehap dari Bank SUMUT 120,600,000
16-12-2013 2 Penarikan dari Bank 1 120,600,000 Penarikan dana DAK dari Bank SUMUT 120,600,000
Pembelian Bahan Kosen Pintu, Jendela, Daun Pintu , Daun Jendela dan Kayu Rangkap Atap pada
30-09-013 3 Saldo Kas Bulan Lalu 101,931.82 05-11-2013 09 18,766,000
Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa Kepada Bapak Bena Hulu
Pembelian Bahan Barang Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa Kepada Bapak Awalan
05-11-2013 10 24,930,000
Laia
Pembayaran Honor jaga malam Bulan November pada Pembangunan Gedung Perpustakaan SMKN. 4
05-11-2013 11 1,000,000
Lahusa Kepada Bapak Ogamota Ndruru
Pembelian Bahan barang Pembangunan Gedung Perpustakaan SMKN. 4 LAHUSA Kepada UD. MARDIN
05-11-2013 12 3,745,500
Pembelian Batu, Pasir Beton, dan Kerikil Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa
05-11-2013 13 31,545,000
kepada Bapak Awalan Laia
Pembayaran Transportasi pengangkutan bahan Pembangunan Gedung Perpustakaan SMKN. 2 Lahusa
05-11-2013 14 1,931,500
Nomor terlampir Kepada Tandrazomboi Zebua
Pembayaran Upah Tukang dan pekerja pada Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa
05-11-2013 15 20,090,000
dari tgl 14 Oktober s/d 30 November 2013 Kepada Bapak Waspada Hulu
JUMLAH 101,931.82 120,600,000 120,600,000 JUMLAH - 120,600,000 102,008,000
101,931.82 SALDO - 18,592,000
JUMLAH TOTAL 101,931.82 120,600,000 120,600,000 JUMLAH TOTAL - 120,600,000 120,600,000
Lahusa, 30 November 2013
PENERIMAAN PENGELUARAN
NO. BUKTI NO.
TGL URAIAN PAJAK BANK KAS TGL BUKTI URAIAN PAJAK BANK KAS
KAS KAS
1 2 3 4 5 6 7 8 9 10 11 12
18-12-2013 1 Terima Dana DAK Rehap dari Bank SUMUT 67,000,000
20-12-2013 2 Penarikan dari Bank 1 67,000,000 Penarikan dana DAK dari Bank SUMUT 67,000,000.00
Pembelian bahan barang untuk Bangunan Gedung Perpustakaan SMKN. 4 Lahusa
3 Saldo Kas Bulan Lalu 101,931.82 28-12-2013 16 13,930,000.00
Kepada Bapak Antonius
Pembelian Bahan Barang Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa Kepada
28-12-2013 17 19,385,000.00
Bapak Awalan Laia
Pembayaran Honor jaga malam Bulan November pada Pembangunan Gedung
28-12-2013 18 1,000,000.00
Perpustakaan SMKN. 4 Lahusa Kepada Bapak Ogamota Ndruru
Pembayaran Upah Tukang dan pekerja pada Pembangunan Gedung Perpustakaan
28-12-2013 19 SMKN. 4 Lahusa dari tanggal 02 s/d 28 Desember 2013 Kepada Bapak Waspada 11,480,000.00
Hulu
Pembelian Bahan barang Pembangunan Gedung Perpustakaan SMKN. 4 Lahusa Kepada
28-12-2013 20 9,450,000.00
Bapak Bena Hulu
Pembayaran Transportasi pengangkutan bahan Pembangunan Gedung Perpustakaan
28-12-2013 21 1,131,000.00
SMKN. 4 Lahusa Nomor terlampir Kepada Bapak Awalan Laia
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan 3 Ruang Kelas
SMK Negeri 4 Lahusa
Uang Sebesar : Sebelas Juta Seratus Tujuh Puluh Empat Ribu Rupiah
: RP. 11,174,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 04 September 2013,
Nomor : 900 / 01 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
: RP. 975,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
: RP. 995,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md
NIP. 196904032006111001
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md MUDIANUS LAIA, S.Pd
NIP. 196904032006111001 Ketua
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 975,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
: RP. 980,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Lahusa , 14 September 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Faktur / Nota Nomor : 02
Jumlah Barang / Harga Satuan Jumlah Harga RP
NO URAIAN
Satuan RP
1 Semen padang @ 50 Kg 13 Sak 75,000.00 975,000.00
KWITANSI
Nomor 02
: RP. 975,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
: RP. 975,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
: RP. 975,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md
NIP. 196904032006111001
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Lahusa , 14 September 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md MUDIANUS LAIA, S.Pd
NIP. 196904032006111001 Ketua
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md
NIP. 196904032006111001
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PENDIDIKAN
SMK NEGERI 4 LAHUSA
Setuju di bayar :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor 02
Uang Sebesar : Enam Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 16,385,000.00
Untuk Pembayaran : Bahan bangunan Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 06 September 2013,
Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth:
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor : 03
Uang Sebesar : Dua Puluh Juta Tiga Puluh Tiga Ribu Rupiah
: RP. 20,033,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 04
: RP. 1,109,000.00
Untuk Pembayaran : Transportasi Pengangkutan Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
dengan rincian seperti dalam faktur / Nota terlampir, Tanggal
06 September 2013, Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 05
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
pada bulan September 2013,
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 06
Uang Sebesar : Sembilan Belas Juta Sembilan Ratus Dua Puluh Tujuh Ribu Rupiah
: RP. 11,480,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
periode :
- 02 s.d 07 September 2013
- 09 s.d 14 September 2013
- 16 s.d 21 September 2013
- 23 s.d 28 September 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 07
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
pada bulan Oktober 2013,
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 08
: RP. 5,740,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
periode :
- 30 September s.d 05 Oktober 2013
- 07 s.d 12 Oktober 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor : 09
Uang Sebesar : Delapan belas Juta Tujuh Ratus Enam Puluh Enam Ribu Rupiah
: RP. 18,766,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan
rincian seperti dalam faktur / Nota terlampir,Tanggal 03 Oktober 2013,
Nomor : 900 / 09 -KEU / 2013
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
ARONAZISOKHI HULU, A.Md MUDIANUS LAIA, S.Pd
NIP. 196904032006111001 Ketua
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor : 10
Uang Sebesar : Dua Puluh Empat Juta Sembilan Ratus Tiga Puluh Ribu Rupiah
: RP. 24,930,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan
rincian seperti dalam faktur / Nota terlampir,Tanggal 09 Oktober 2013,
Nomor : 900 / 10 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
KWITANSI
Nomor : 11
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
pada bulan November 2013,
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
KWITANSI
Nomor : 15
Uang Sebesar : Tiga Puluh Delapan Juta Enam Ratus Delapan Puluh Dua Ribu Rupiah
: RP. 20,090,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada Bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
Negeri 4 Lahusa periode :
- 14 s.d 19 Oktober 2013
- 21 s.d 26 Oktober 2013
- 28 Oktober s.d 02 November 2013
- 04 s.d 09 November 2013
- 11 s.d 16 November 2013
- 18 s.d 23 November 2013
- 25 s.d 30 November 2013
Lunas Dibayar :
Tanggal, 30 November 2013 Yang menerima:
Bendahara, Kepala Tukang
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor : 13
Uang Sebesar : Tiga Puluh Satu Juta Lima Ratus Empat Puluh Lima Ribu Rupiah
: RP. 31,545,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan
rincian seperti dalam faktur / Nota terlampir,Tanggal 09 September
2013, Nomor : 900 / 13 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
KWITANSI
Nomor : 12
Uang Sebesar : Tiga Juta Tujuh Ratus Empat Puluh Lima Ribu Lima Ratus Rupiah
: RP. 3,745,500.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 09 Oktober 2013,
Nomor : 900 / 12 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 14
Uang Sebesar : Satu Juta Sembilan Ratus Tiga Puluh Satu Ribu Lima Ratus Rupiah
: RP. 1,931,500.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Sihareo
Nomor : 16
Uang Sebesar : Tiga Belas Juta Sembilan Ratus Tiga Puluh Ribu Rupiah
: RP. 13,930,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan
rincian seperti dalam faktur / Nota terlampir,Tanggal November 2013,
Nomor : 900 / 16 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor : 17
Uang Sebesar : Sembilan Belas Juta Tiga Ratus Delapan Puluh Lima Ribu Rupiah
: RP. 19,385,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan
rincian seperti dalam faktur / Nota terlampir,Tanggal 04 November 2013,
Nomor : 900 / 17 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 18
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa
pada bulan Desember 2013,
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Nomor : 19
Uang Sebesar : Dua Puluh Dua Juta Seratus Empat Ribu Rupiah
: RP. 11,480,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada bangunan Gedung Perpustakaan SMK Negeri 4
Lahusa periode :
- 02 s.d 07 Desember 2013
- 09 s.d 14 Desember 2013
- 16 s.d 21 Desember 2013
- 23 s.d 28 Desember 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md
NIP. 196904032006111001
KWITANSI
Nomor : 21
Uang Sebesar : Satu Juta Seratus Tiga Puluh Satu Ribu Rupiah
: RP. 1,131,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
ARONAZISOKHI HULU, A.Md
NIP. 196904032006111001
Diketahui Oleh :
Kepala Sekolah SMKN. 4 Lahusa Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Ketua Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 4 Lahusa
di-
Lahusa
Nomor : 20
Uang Sebesar : Sembilan Juta Empat Ratus Lima Puluh Ribu Rupiah
: RP. 9,450,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 4 Lahusa dengan rincian
seperti dalam faktur /Nota terlampir, Tanggal 28 November 2013,
Nomor : 900 / 20 -KEU / 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 4 Lahusa
Kepada Yth,
Bapak Bena Hulu
Taluzusua
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Lahusa , 05 September 2013
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
Gomo
ELIAN BAHAN
TEN NIAS SELATAN
DIDIKAN
Telukdalam Km. 68
Kepada Yth,
Bapak Antonius
Helezalulu
Kepada Yth,
Bapak Bena Hulu
Taluzusua
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Awalan Laia
Gomo
ELIAN BAHAN
Lahusa , 07 September 2013
Kepada Yth,
Pimpinan UD.MARDIN
Gomo
ELIAN BAHAN
1,958,000.00
113967000
Thp II -
113,967,000.00
Lahusa , 03 Desember 2013
Kepada Yth,
Bapak Antonius
Helezalulu
Kepada Yth,
Bapak Awalan Laia
Gomo
Kepada Yth,
Bapak Bena Hulu
Taluzusua
158
1,000,000.00
11,643,000.00
30,093,000.00
1,452,000.00
6.75
742,000.00
PERHITUNGAN VOLUME PEKERJAAN
1 Galian Tanah V= La + Lb X P X T
2
2 Batu Kali V= La + Lb X P X T
2
3 Batu Kosong V= P X L X T X 16
V= 0.9 X 0.8 X 0.15 X 16 = 1.728 m3
4 Lantai Kerja V= P X L X T
V= 0.9 X 0.8 X 0.15 = 0.108 m3
5 Pasir Urug V= P X L X T
V= 0.9 X 0.8 X 0.05 X 16 = 0.576 m3
6 Slof V= P x L X T
V= 40.8 x 0.2 X 0.25 = 2.04 m3
7 Kolom V= P x L X T X @
V= 3.5 + 0.2 X 0.2 x 14 = 1.96 m3
8 Ring Balok V= P x L X T
V= 40.8 x 0.2 X 0.2 = 1.632 m3
9 Cor Lantai V= P x L X T
V= 11 x 14 X 0.07 = 10.78 m3
L d2 = P x L X @
L d2 = 2.8 x 3.5 X 8 = 78.4 m2
L d3 = P x L X @
L d3 = 1 x 2 X 7.6 X 2 = 15.2 m2
2
Jumlah total 145.47 m2
LP1 = P x L X @ =
LP1 = 2.5 x 1.3 X 1 = 3.25 m2
Jumlah total = 26.07 m2
15 Kosen Jendela V1 = P x L X T X @
V1 = 1.63 x 0.15 X 0.05 28 = 0.3423 m3
V2 = P x L X T X @
V2 = 2 x 0.15 X 0.05 21 = 0.315 m3
Jumlah total 0.6573 m3
16 Kosen Pintu P1 = P x L X T X @
P1 = 2.5 x 0.15 X 0.05 2 = 0.0375 m3
P2 = P x L X T X @
P2 = 1.3 x 0.15 X 0.05 2 = 0.0195 m3
Jumlah total 0.057 m3
23 papan Jalusi Jendela dan pintu PJls = 0.6 X 0.15 X 0.02 X 84 = 0.1512
24 Keramik Vkrmk = p X L
= 0.3 X 0.3 = 0.09
Banyaknyak Keramik yang digunakan Yaitu = Luas Lantai / satu Lembar Keramik
132 m2 Kotak X 0.09 = 1466.667 Lbr
= 130 Lbr
DAFTAR PENERIMAAN UPAH TUKANG DAN PEKERJA
Lunas dibayar :
Setuju di bayar : Tanggal : 07 September 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
Lunas dibayar :
Setuju di bayar : Tanggal : 14 September 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 21 September 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 28 Oktober 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
ARONASOKHI HULU, A.Md DUHUASA NDRURU, S.Pd
NIP. 196904032006111001
Lunas dibayar :
Setuju di bayar : Tanggal : 12 Oktober 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
ARONASOKHI HULU, A.Md DUHUASA NDRURU, S.Pd
NIP. 196904032006111001
Lunas dibayar :
Setuju di bayar : Tanggal : 19 Oktober 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
Lunas dibayar :
Setuju di bayar : Tanggal : 26 Oktober 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
Lunas dibayar :
Setuju di bayar : Tanggal : 09 November 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
Lunas dibayar :
Setuju di bayar : Tanggal : 16 November 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
Lunas dibayar :
Setuju di bayar : Tanggal : 23 November 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 07 Desember 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 14 Desember 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 21 Desember 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
NO NAMA JABATAN JLH. HARI BESAR UPAH JLH. DITERIMA TANDA TANGAN
KERJA ( Rp ) ( RP )
1 WASPADA HULU Kepala Tukang 6 80,000 480,000 1.
2 ASAZOHAU LAIA Tukang 2 70,000 140,000 2.
3 ASAMONI LAIA Tukang 3 70,000 210,000 3.
4 AMONI MBOWO BAENE Tukang 3 70,000 210,000 4.
5 TEMAATO NDRURU Tukang 3 70,000 210,000 5.
6 DARMAN BAENE Pekerja 3 60,000 180,000 6.
7 FAOGOZINEMA BAENE Pekerja 3 60,000 180,000 7.
8 HONOGO BAENE Pekerja 3 60,000 180,000 8.
9 BUAOZATULO HULU Pekerja 3 60,000 180,000 9.
10 ARONAFAUDU HULU Pekerja 3 60,000 180,000 10.
11 ASAHATI BAENE Pekerja 6 60,000 360,000 11.
12 OGAMOTA NDRURU Pekerja 6 60,000 360,000 12.
JUMLAH 2,870,000
Lunas dibayar :
Setuju di bayar : Tanggal : 28 Desember 2013
Kepala Sekolah SMK Negeri 4 Lahusa Bendahara ,
sebagai berikut :
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Barang tersebut di atas telah diterima dalam keadaan baik dan lengkap
Nomor : 01
: RP. 175,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMKN. 2 Lahusa dengan rincian
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 02
Uang Sebesar : Enam Juta Empat Ratus Dua Puluh Dua Ribu Rupiah
: RP. 6,422,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 03
Uang Sebesar : Tiga Juta Tiga Ratus Dua Puluh Satu Ribu Dua Ratus Rupiah
: RP. 3,321,200.00
Untuk Pembayaran : Biaya pembuatan gambar rencana bangunan Gedung Perpustakaan SMK
Negeri 2 Lahusa Tahun Abggaran 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 04
: RP. 3,000,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 05
: RP. 1,500,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 06
: RP. 1,500,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 07
: RP. 960,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 08
Uang Sebesar Satu Juta Seratus Empat Puluh Empat Ribu Sembilan Ratus Empat Puluh Rupiah
: RP. 1,144,940.00
KUITANSI
Nomor : 09
Sudah terima dari : Bendahara Pengeluaran Pembangunan Gedung Perpustakaan SMK
Negeri 2 Lahusa
Kabupaten Nias Selatan
: RP. 1,095,000.00
Untuk Pembayaran : Biaya pembuatan Laporan Tahab II ( 100 % ) bangunan Gedung Perpustakaan
SMKN. 2 Lahusa Tahun Abggaran 2013
KUITANSI
Nomor : 10
: RP. 440,000.00
Untuk Pembayaran : Biaya Monitoring dan Pengawasan oleh Kepala Sekolah selama pelaksanaan
Pembangunan Gedung Perpustakaan SMKN. 2 Lahusa TA. 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Barang tersebut di atas telah diterima dalam keadaan baik dan lengkap
Sihareo, 04 September 2013
KUITANSI
Nomor : 11
: RP. 315,000.00
Untuk Pembayaran : Biaya Pembuatan SPJ Dana perencanaan dan pengawasan Pembangunan Gedung
PerpustakaanSMK Negeri 2 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 15 Februari 2013, Nomor :
900 / 92 -KEU / 2013
Sihareo , 20 Februari 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
315,000 -
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PENDIDIKAN
SMK NEGERI 2 LAHUSA
Alamat : Jln. Lintas Gunung Sitoli Telukdalam Km. 68
sebagai berikut :
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Barang tersebut di atas telah diterima dalam keadaan baik dan lengkap
Nomor : 01
: RP. 175,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMKN. 2 Lahusa dengan rincian
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 02
Uang Sebesar : Enam Juta Empat Ratus Dua Puluh Dua Ribu Rupiah
: RP. 5,422,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 03
Uang Sebesar : Tiga Juta Tiga Ratus Dua Puluh Satu Ribu Dua Ratus Rupiah
: RP. 3,321,200.00
Untuk Pembayaran : Biaya pembuatan gambar rencana bangunan Gedung Perpustakaan SMK
Negeri 2 Lahusa Tahun Abggaran 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 04
: RP. 2,000,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Nomor : 05
: RP. 1,500,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 06
: RP. 1,500,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 07
: RP. 960,000.00
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
APRIANUS AMAZIHONO, S.PAK
NIP. 198104062011011002
KUITANSI
Nomor : 08
Uang Sebesar Satu Juta Seratus Empat Puluh Empat Ribu Sembilan Ratus Empat Puluh Rupiah
: RP. 1,000,000.00
KUITANSI
Nomor : 09
Sudah terima dari : Bendahara Pengeluaran Pembangunan Gedung Perpustakaan SMK
Negeri 2 Lahusa
Kabupaten Nias Selatan
: RP. 1,095,000.00
Untuk Pembayaran : Biaya pembuatan Laporan Tahab II ( 100 % ) bangunan Gedung Perpustakaan
SMKN. 2 Lahusa Tahun Abggaran 2013
KUITANSI
Nomor : 10
: RP. 440,000.00
Untuk Pembayaran : Biaya Monitoring dan Pengawasan oleh Kepala Sekolah selama pelaksanaan
Pembangunan Gedung Perpustakaan SMKN. 2 Lahusa TA. 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
Barang tersebut di atas telah diterima dalam keadaan baik dan lengkap
Sihareo, 04 September 2013
KUITANSI
Nomor : 11
: RP. 315,000.00
Untuk Pembayaran : Biaya Pembuatan SPJ Dana perencanaan dan pengawasan Pembangunan Gedung
PerpustakaanSMK Negeri 2 Lahusa dengan rincian
seperti dalam faktur / Nota terlampir,Tanggal 15 Februari 2013, Nomor :
900 / 92 -KEU / 2013
Sihareo , 20 Februari 2013
Setuju di bayar :
Kepala Sekolah SMK Negeri 2 Lahusa
315,000 -
SURAT PERTANGGUNG JAWABAN
DANA PERENCANAAN DAN PENGAWASAN DAK
PEMBANGUNAN REHAB 3
RUANG KELAS SMK NEGERI 2 LAHUSA TAHUN 2013
Tanggal dan No Bukti
No Buku Kas Uraian Penerimaan ( Pengeluaran Sisa Dana ( Rp )
Tanggal No Rp ) ( Rp )
900 / 01 -KEU /
Nomor : 2013 Kepada Yth,
Lamp :- UD. Yohanes
Hal : Pesanan Kayu di -
Sihareo
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Nomor : 01
Uang Sebesar : Sebelas Juta Seratus Enam Puluh Enam Ribu Rupiah
: RP. 11,166,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 04 September 2013, Nomor : 900 / 01
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Sihareo
Nomor 02
Uang Sebesar : Sembilan Belas Juta Dua Ratus Enam Puluh Ribu Rupiah
: RP. 19,260,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 06 September 2013, Nomor : 900 / 02
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
900 / 03 -KEU /
Nomor : Kepada Yth,
2013
Lamp :- Bapak Nemambowo Waruwu
Pesanan Bahan
Hal : di -
Material
Sihareo
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Sihareo
Nomor : 03
Uang Sebesar : Empat Belas Juta Enam Ratus Lima Puluh Ribu Rupiah
: RP. 14,650,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 09 September 2013, Nomor : 900 / 03
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
APRIANUS AMAZIHONO, S.PAK
NIP. NIP. 19810406 2011 1 002
KUITANSI
Nomor : 04
Uang Sebesar : Satu Juta Seratus Empat Puluh Dua Ribu Rupiah
: RP. 1,154,000.00
Untuk Pembayaran : Transportasi Pengangkutan Bahan bangunan Gedung Perpustakaan SMK Negeri 2
Lahusa dengan rincian seperti dalam faktur / Nota terlampir,Tanggal 06
September 2013, Nomor : 900 / 02 -KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
APRIANUS AMAZIHONO, S.PAK
NIP. NIP. 19810406 2011 1 002
KUITANSI
Nomor : 05
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Pembangunan Gedung Perpustakaan SMK Negeri 2 Lahusa
pada bulan September 2013,
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
APRIANUS AMAZIHONO, S.PAK
NIP. NIP. 19810406 2011 1 002
KUITANSI
Nomor : 06
: RP. 17,230,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada pembangunan Gedung Perpustakaan SMK Negeri 2
Lahusa periode :
- 02 s.d 07 September 2013
- 09 s.d 14 September 2013
- 16 s.d 21 September 2013
- 23 s.d 28 September 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 07
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Pembangunan Gedung Perpustakaan SMK Negeri 2 Lahusa
pada bulan Oktober 2013,
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 08
Uang Sebesar : Sembilan Juta Sembilan Puluh Enam Ribu Rupiah Rupiah
: RP. 14,940,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada pembangunan Gedung Perpustakaan SMK Negeri 2
Lahusa periode :
- 30 September s.d 05 Oktober 2013
- 07 s.d 12 Oktober 2013
- 14 s.d 19 Oktober 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
TANDRAZOMBOI ZEBUA
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
KUITANSI
Nomor : 09
Uang Sebesar : Empat Puluh Sembilan Juta Sembilan Ratus Sembilan Puluh Lima Ribu Rupiah
: RP. 40,995,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur /Nota terlampir,Tanggal 03 Oktober 2013, Nomor : 900 / 09
-KEU / 2013
Sihareo , 30 November 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
900 / 10 -KEU /
Nomor : Kepada Yth,
2013
Lamp :- Pimpinan UD. Putri
Hal : Pesanan Barang di -
Sihareo
TANDRAZOMBOI ZEBUA
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Faktur / Nota Nomor : 10
Jumlah Harga Satuan Jumlah
NO URAIAN Harga
Barang / Satuan RP RP
1 Seng BJLS 6 Kaki 10 Kodi 900,000.00 9,000,000.00
2 Rabung Seng 10 Lbr 25,000.00 250,000.00
3 Paku Seng 13 Kotak 35,000.00 455,000.00
4 Semen @ 50 Kg 130 Sak 70,000.00 9,100,000.00
5 Keramik uk. 30 X 30 20 Kotak 52,000.00 1,040,000.00
6 Semen Putih @ 50 Kg 1 Sak 130,000.00 130,000.00
7 Paku 30 Kg 25,000.00 750,000.00
JUMLAH TOTAL 20,725,000.00
KUITANSI
Nomor : 10
Uang Sebesar : Dua Puluh Juta Tujuh Ratus Dua puluh Puluh Lima Ribu Rupiah
: RP. 20,725,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 09 Oktober 2013, Nomor : 900 / 10
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 11
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Pembangunan Gedung Perpustakaan SMK Negeri 2 Lahusa
pada bulan November 2013,
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 15
Uang Sebesar : Dua Puluh Sembilan Juta Delapan Ratus Delapan Puluh Ribu Rupiah
: RP. 29,880,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada pembangunan Gedung Perpustakaan SMK Negeri 2
Lahusa periode :
- 21 s.d 26 Oktober 2013
- 28 Oktober s.d 02 November 2013
- 04 s.d 09 November 2013
- 11 s.d 16 November 2013
- 18 s.d 23 November 2013
- 25 s.d 30 November 2013
Lunas Dibayar :
Tanggal, 30 November 2013 Yang menerima:
Bendahara, Kepala Tukang
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Nomor : 13
Uang Sebesar : Enam Belas Juta Tujuh Ratus Dua Puluh Lima Ribu Rupiah
: RP. 16,725,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 09 September 2013, Nomor : 900 / 13
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Nomor : 13
: RP. 9,606,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 09 Oktober 2013, Nomor : 900 / 12 -KEU / 2013
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
Nomor : 14
Uang Sebesar : Satu JutaEnam Ratus Enam Puluh Sembilan Ribu Rupiah
: RP. 1,669,000.00
Untuk Pembayaran : Transportasi Pengangkutan Bahan bangunan Gedung Perpustakaan SMK Negeri 2
Lahusa dengan rincian seperti dalam faktur / Nota terlampir, Tanggal
Oktober 2013, Nomor : 900 / -KEU / 2013; Tanggal Oktober 2013, Nomor : 900 /
-KEU / 2013 Tanggal Oktober 2013, Nomor : 900 / -KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
900 / 16 -KEU /
Nomor : Kepada Yth,
2013
Lamp :- Bapak Nemambowo Waruwu
Hal : Pesanan Kayu di -
Rangka Plafond Lolowau
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
Nomor : 16
Uang Sebesar : Delapan Juta Sembilan Ratus Tiga Puluh Ribu Rupiah
: RP. 11,930,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal November 2013, Nomor : 900 / 16
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
APRIANUS AMAZIHONO, S.PAK
NIP. NIP. 19810406 2011 1 002
900 / 17 -KEU /
Nomor : 2013 Kepada Yth,
Lamp :- Pimpinan UD. Putri
Hal : Pesanan Barang di -
Sihareo
TANDRAZOMBOI ZEBUA
FAKTUR / NOTA PEMBELIAN BAHAN
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
KUITANSI
Nomor : 17
Uang Sebesar : Dua Puluh Delapan Juta Dua Ratus Sembilan Puluh Tujuh Ribu Rupiah
: RP. 20,641,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal 04 November 2013, Nomor : 900 / 17
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 18
: RP. 1,000,000.00
Untuk Pembayaran : Petugas jaga malam pada Pembangunan Gedung Perpustakaan SMK Negeri 2 Lahusa
pada bulan Desember 2013,
KUITANSI
Nomor : 19
Uang Sebesar : Sembilan Belas Juta Sembilan Ratus Dua Puluh Ribu Rupiah
: RP. 19,920,000.00
Untuk Pembayaran : Upah tukang dan pekerja pada pembangunan Gedung Perpustakaan SMK Negeri 2
Lahusa periode :
- 02 s.d 07 Desember 2013
- 09 s.d 14 Desember 2013
- 16 s.d 21 Desember 2013
- 23 s.d 28 Desember 2013
Lunas Dibayar :
Tanggal, 28 Desember 2013 Yang menerima:
Bendahara, Kepala Tukang
YARTINUS AMAZIHONO, Amd FATIELI WARUWU
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
KUITANSI
Nomor : 21
Uang Sebesar : Satu JutaTujuh Ratus Tiga Puluh Tujuh Ribu Rupiah Puluh Dua Ribu Rupiah
: RP. 1,794,000.00
Untuk Pembayaran : Transportasi Pengangkutan Bahan bangunan Gedung Perpustakaan SMK Negeri 2
Lahusa dengan rincian seperti dalam faktur / Nota terlampir,Tanggal
Desember 2013, Nomor : 900 / -KEU / 2013; Tanggal Desember 2013, Nomor : 900 /
-KEU / 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
900 / 20 -KEU /
Nomor : 2013 Kepada Yth,
Lamp :- Bapak Nemambowo Waruwu
Hal : Pesanan Mobiler di -
Sihareo
TANDRAZOMBOI ZEBUA
Kepada Yth,
Panitia Pembangunan Gedung Perpustakaan
SMK Negeri 2 Lahusa
di-
Sihareo
KUITANSI
Nomor : 20
Uang Sebesar : Sebelas Juta Tujuh Ratus Lima Belas Ribu Rupiah
: RP. 11,715,000.00
Untuk Pembayaran : Bahan bangunan Gedung Perpustakaan SMK Negeri 2 Lahusa dengan rincian seperti
dalam faktur / Nota terlampir,Tanggal November 2013, Nomor : 900 / 20
-KEU / 2013
Sihareo , Desember 2013
Setuju di bayar :
Kepala SMK Negeri 2 Lahusa,
158
###
02 s.d 07 September 2013
09 s.d 14 September 2013
16 s.d 21 September 2013
23 s.d 28 September 2013
###
###
###
(89.12)