II PEKERJAAN TANAH
1 Galian tanah pondasi Panjang Lebar Tinggi Jumlah
Pondasi Set. Batu Kali 35.00 x 0.70 x 0.70 x 1.00 = 17.15
Pondasi Batu Kali 27.00 x 0.70 x 0.70 x 1.00 = 13.23 =
30.38 = 30.38 M3
2 Urug tanah kembali
Pondasi Set. Batu Kali 35.00 x 0.70 x 0.70 x 1.00 = 17.15
Pondasi Batu Kali 27.00 x 0.70 x 0.70 x 1.00 = 13.23 +
30.38 = 30.38 M3
3 Pasir urug
Bawah pondasi Tebal
Pondasi Set. Batu Kali 35.00 x 0.70 x 0.05 x 1.00 = 1.23
Pondasi Batu Kali 27.00 x 0.70 x 0.05 x 1.00 = 0.95 +
2.17
= 2.17 M3
III PEKERJAAN PASANGAN
1 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu 1 sp : 3 pp
Memanjang x 36.00 x 0.15 x 6.60 = 35.64
Melintang y 26.00 x 0.15 x 5.00 = 19.50 +
55.14
Pengurangan
P1 0.92 x 2.50 x 4.00 = 9.20
P2 0.72 x 2.05 x 1.00 = 1.48
PJ1 1.58 x 2.50 x 1.00 =
J1 1.38 x 2.00 x 3.00 = 8.28
18.96 +
X PEKERJAAN KERAMIK
1 Pemasangan lantai keramik polos ukuran 60 x 60 cm Tambal Sulam
Ruang LT.1 9.15 x 7.15 x 4.00 x 10% = 26.17
Kamar 1 & 2 3.50 x 3.00 x 2.00 x 10% = 2.10 +
28.27 = 28.27 M2
2 Pemasangan lantai keramik polos ukuran 30 x 30 cm
Teras LT.1 3.50 x 1.00 x 2.00 = 7.00
Kamar Mandi 1.50 x 1.50 x = 2.25
9.25 = 9.25 M2
XI PEKERJAAN CAT-CATAN
1 Pengecatan tembok baru (1 lapis plamuur , 1 lapis dasar , 2 lapis cat penutup)
Sama dengan pekerjaan plesteran dinding = 64.46 M2
2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 2 lapis cat penutup)
P1 0.90 x 2.50 x 0.15 = 0.34
P2 1.58 x 2.50 x 0.15 = 0.59
J1 1.38 x 2.00 x 0.15 = 0.41
1.34 = 1.34 M2
4 Pengecatan Langit-Langit (Plafond)
Sama dengan pekerjaan plafond = 403.33 M2
JUMLAH 54,653,177.34
JUMLAH UPAH + BAHAN
PEMBULATAN
TERBILANG " SERATUS ENAM PULUH LIMA JUTA SERATUS RIBU RUPIAH "
JUMLAH HARGA
BAHAN ( Rp )
8=4x6
300,000.00
350,000.00
-
650,000.00
-
-
536,424.00
536,424.00
1,317,047.44
1,317,047.44
4,970,126.61
1,090,031.49
6,060,158.10
3,371,067.98
1,034,064.92
1,440,910.14
2,356,311.88
1,949,466.66
449,224.93
16,951.88
1,754,519.99
576,364.06
979,364.93
1,259,055.00
1,014,695.55
1,990,077.75
722,800.35
54,987.30
1,153,833.98
1,419,391.80
793,968.00
4,417,420.00
8,823,164.00
2,985,164.00
875,700.00
54,488.00
2,685,480.00
1,109,220.00
44,064.00
245,160.00
388,800.00
389,772.00
48,600.00
3,024.00
149,040.00
61,560.00
44,617,713.10
888,960.15
906,887.70
146,122.24
1,419,163.20
136,000.00
117,000.00
486,000.00
171,000.00
4,271,133.29
14,479,757.88
2,157,724.80
16,637,482.68
9,886,800.00
444,364.80
10,331,164.80
8,691,704.36
1,675,359.35
280,282.00
10,647,345.71
792,213.40
2,033,011.15
948,265.20
992,912.97
4,766,402.72
-
-
408,000.00
24,500.00
90,000.00
522,500.00
100,357,371.84
155,010,549.18
165,100,000.00
Rp 185,000,000
Rp 155,010,549
#REF!
Rp 10,068,827
rooster 40000 20/20
Rp 13,695,331.12
Rp 15,557,359.36
Rp 26,094,278.86
107,046.70
107,046.70
Rp 84,358,295.84 #REF!
Rp 91,719,807.00
Rp 116,544,493.18
Rp 185,000,000
Rp 155,010,549 #REF!
#REF! #REF!
REKAPITULASI
PEKERJAAN RUMAH TIPE 36
KEGIATAN :
LOKASI :
SUMBER DANA :
SISTIM :
PEMBULATAN 155,000,000.00
TERBILANG: Seratus Enam Puluh Lima Juta Seratus Rib
PROSEN
ANALISA HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM
TAHUN ANGGARAN 2020
1 2 3 4 5
1
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.1.13 Batu koral putih M2 201,740.00
2.2.1.14 Batu koral sikat M2 197,010.00
2.2.1.15 Batu koral warna M2 209,990.00
2.2.1.16 Batu lempeng M2 122,100.00
2.2.1.17 Batu lempeng hijau M2 120,780.00
2.2.1.18 Batu lempeng coklat M2 82,610.00
2.2.1.19 Batu marmo biasa M2 102,740.00
2.2.1.20 Batu paras putih M2 139,810.00
2.2.1.21 Batu paras grobongan M2 121,110.00
2.2.1.22 Batu pecah 0,5-1 cm M3 282,370.00
2.2.1.23 Batu pecah 1-2 cm M3 300,000.00
2
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.1.24 Batu pecah 2-3 cm M3 283,500.00
2.2.1.25 Batu pecah 3-5 cm M3 288,000.00
2.2.1.26 Batu pecah 5-7 cm M3 270,000.00
2.2.1.27 Batu pecah 8-10 cm M3 275,000.00
2.2.1.28 Batu pecah 10-15 cm (15-20) M3 265,000.00
2.2.1.29 Batu plontos 5/7 cm M3 282,700.00
2.2.1.30 Batu putih / gunung M3 281,600.00
2.2.1.31 Batu putih pecah , 5 - 7 cm M3 275,000.00
2.2.1.32 Grasak M3 162,030.00
2.2.1.33 Ijuk Kg 8,470.00
2.2.1.34 Kapur Batu ( sirih ) Kg 1,980.00
2.2.1.35 Kapur Batu M3 1,397,550.00
2.2.1.36 Pasir pasang / beton M3 245,000.00
2.2.1.37 Pasir Urug M3 206,000.00
2.2.1.38 PC / Portland cement Kg 1,450.00
2.2.1.39 Semen Merah M3 181,000.00
2.2.1.40 Semen Putih / warna Kg 3,600.00
2.2.1.41 Sirtu royalti M3 205,700.00
2.2.1.42 Sirtu Urug M3 199,430.00
2.2.1.43 Tali ijuk Kg 12,100.00
2.2.1.44 Tanah liat M3 54,450.00
2.2.1.45 Tanah urug M3 57,500.00
2.2.1.46 Urugan Taman M3 114,950.00
2.2.1.47 Tanah subur ( humus ) Rit 254,100.00
2.2.1.48 Pasir putih halus Rit 1,149,500.00
2.2.1.49 Solar Ltr 6,820.00
2.2.1.50 Tanah Padas M3 123,750.00
3
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.2.21 Kayu Kempas Papan M3 9,377,500.00
2.2.2.22 Kayu Kruing Balok M3 8,310,000.00
2.2.2.23 Kayu Kruing Papan M3 10,610,000.00
2.2.2.24 Kayu Meranti Balok M3 7,320,000.00
2.2.2.25 Kayu Meranti Papan M3 8,050,000.00
2.2.2.26 Kayu Tahun Balok ( Mauni/ Akasia ) M3 5,980,000.00
2.2.2.27 Kayu Tahun papan ( Mauni/akasia) M3 6,320,000.00
2.2.2.28 Kornis kayu jati lebar 10 cm + Finishing M' 121,000.00
4
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.3.40 Nok atap genteng metal Lbr 40,590.00
2.2.3.41 Nok genteng keramik Bh 59,290.00
2.2.3.42 Nok Stel Asbes Gelombang besar 108 Lbr 66,550.00
2.2.3.43 Nok Stel Asbes Gelombang kecil 105 Lbr 43,670.00
2.2.3.44 Partikel board t = 18 mm (1.22 m x 2.42 m ) Lbr 230,010.00
2.2.3.45 Seng Plat BJLS 27 lebar 0,90 m M' 47,000.00
2.2.3.46 Seng Plat BJLS 30 lebar 0,45 m M' 29,000.00
2.2.3.47 Seng Plat BJLS 30 lebar 0,90 m M' 51,000.00
2.2.3.48 Kalsiboard 1,2 x 2,4m tebal 4mm Lbr 68,200.00
2.2.3.49 Talang Karet L=90cm M' 38,170.00
2.2.3.50 Talang PVC U 4" M' 45,980.00
5
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.4.37 Pintu PVC Lipat (70x210)cm Unit 548,900.00
2.2.4.38 Pintu PVC Polos (70x210)cm M2 241,450.00
2.2.4.39 Pintu Roling Door aluminium M2 416,680.00
2.2.4.40 Pintu Roling Door besi unit 603,570.00
2.2.4.41 Profil daun pintu almunium coklat / hitam M' 98,230.00
2.2.4.42 Profil kusen almunium coklat / hitam 4" M' 112,090.00
2.2.4.43 Profil kusen aluminium 4" M2 99,330.00
2.2.4.44 Profil kusen aluminium 4"ykk M2 / Psg 193,930.00
2.2.4.45 Ralling tangga / grill stainlees Dia 2" M2 / Psg 1,016,400.00
2.2.4.46 Ralling tangga / pagar besi Unit 603,570.00
2.2.4.47 Teralis Besi btg 311,960.00
2.2.4.48 Teralis stainlees M2 520,960.00
6
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.6.14 Cat Tembok interior premium Kg 66,000.00
2.2.6.15 Cat Untuk Pekerjaan Baja Jembatan Kg 63,580.00
2.2.6.16 Clear melamin impra dof / gloos Kg 69,960.00
2.2.6.17 Coatting Ltr 82,610.00
2.2.6.18 Dempul Kayu Kg 39,000.00
2.2.6.19 HCL / air keras Ltr 14,500.00
2.2.6.20 Kalsium Kg 2,000.00
2.2.6.21 Kertas gosok ( rempelas ) Lbr 4,000.00
2.2.6.22 Kuas 3 " Kg 18,000.00
2.2.6.23 Kuas 4 " Bj 24,000.00
2.2.6.24 Lem ( Kayu + Tembok ) Bh 16,500.00
2.2.6.25 Lem PVC Tube 9,500.00
2.2.6.26 Meni besi Kg 41,500.00
2.2.6.27 Minyak bekisting Ltr 6,500.00
2.2.6.28 Minyak Cat / Thiner A Ltr 36,000.00
2.2.6.29 Minyak Cat / Thiner B Ltr 19,500.00
2.2.6.30 Minyak Pelumas Ltr 41,250.00
2.2.6.31 Minyak Tanah Ltr 13,970.00
2.2.6.32 Oli Gardan Ltr 44,550.00
2.2.6.33 Oli rem Ltr 82,610.00
2.2.6.34 Oli Hidrolis Ltr 33,000.00
2.2.6.35 Oli Presneleng Ltr 44,550.00
2.2.6.36 Paint Stone Zak 470,140.00
2.2.6.37 Plamur kayu Kg 32,500.00
2.2.6.38 Plamur Tembok Kg 18,500.00
2.2.6.39 Politur jadi Ltr 66,500.00
2.2.6.40 Residu ( Ter ) Ltr 6,380.00
2.2.6.41 Rol kuas Bh 20,900.00
2.2.6.42 Sabun Kg 13,900.00
2.2.6.43 Sending impra ( melamine) Kg 73,700.00
2.2.6.44 Soda api Kg 22,000.00
2.2.6.45 Spiritus Ltr 17,820.00
2.2.6.46 Stempet / Gemuk Kg 38,170.00
2.2.6.47 Teak oil Ltr 8,910.00
2.2.6.48 Vernis Ltr 44,550.00
7
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
8
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
2.2.12.1 Paku biasa Kg 18,000.00
2.2.12.2 Paku Eternit / Triplek Kg 22,000.00
2.2.12.3 Paku Gypsum Kg 26,500.00
2.2.12.4 Paku Kayu Uk.2,5"-5" Kg 16,500.00
2.2.12.5 Paku Reng Kayu 2" Kg 17,000.00
2.2.12.6 Paku Usuk 3" Kg 17,000.00
2.2.12.7 Paku Asbes Kg 29,500.00
2.2.12.8 Paku beton 5cm Bh 650.00
2.2.12.9 Paku Kait ( pancing ) Bh 1,300.00
2.2.12.10 Paku Sekrup Bh 650.00
2.2.12.11 Paku Seng ( Paku payung ) Kg 28,500.00
2.2.12.12 Paku Sumbat Bh 1,900.00
2.2.12.13 Skrup Fixer Bh 850.00
9
HARGA DAN PAJAK 10%
NO. JENIS BAHAN SAT. (Rp) KET.
1 2 3 4 5
3.6.1.11 Philips jari essential 5 w Bh 25,300.00
3.6.1.12 Philips jari essential 65 w Bh 150,150.00
3.6.1.13 Philips jari essential 8 w Bh 27,500.00
3.6.1.14 Saklar Panasonic (ganda) Bh 24,500.00
3.6.1.15 Saklar Panasonic (tunggal) Bh 15,000.00
3.6.1.16 Stop kontak IB / tanem Bh 12,000.00
10
HSPK PADA DINAS PU- BINA MARGA DAN CIPTA KARYA
KABUPATEN TULUNGAGUNG
KABUPATEN : TULUNGAGUNG
SISTEM : KONTRAK
HARGA : BAWAH
Overhead dan profit = 0.0000
A.2.2.1.17 10 m2 Membongkar lantai lama, berikut membersihkan bata-bata lama atau ubin-ubin yang dibongkar
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 1.0000 80,000.00 80,000.00
Mandor 1.2.7.4 oh 0.1000 - -
80,000.00 - -
Overhead dan profit - - - -
80,000.00 - -
A.2.2.1.17b 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap akan dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.2000 80,000.00 16,000.00
Mandor 1.2.7.4 oh 0.1000 - -
16,000.00 - -
Overhead dan profit - - - -
16,000.00 - -
A.2.2.1.17c 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap tidak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.2000 80,000.00 16,000.00
Mandor 1.2.7.4 oh 0.1000 - -
16,000.00 - -
Overhead dan profit - - - -
16,000.00 - -
A.2.2.1.17d 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran hendak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 1.0000 80,000.00 80,000.00
Tukang kayu 1.2.7.20 oh 0.2500 105,000.00 26,250.00
Kepala Tukang 1.2.7.2 oh 0.2500 108,000.00 27,000.00
Mandor 1.2.7.4 oh 0.0500 - -
133,250.00 - -
Overhead dan profit - - - -
133,250.00 - -
A.2.2.1.17e 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran tidak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 1.0000 80,000.00 80,000.00
Mandor 1.2.7.4 oh 0.0500 - -
80,000.00 - -
Overhead dan profit - - - -
80,000.00 - -
1
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.2.2.1.17g 1 m3 Membongkar kuda-kuda jika tidak dipakai lagi
Mukomoko Tenaga
Tukang kayu 1.2.7.20 6.0000 105,000.00 630,000.00
Kepala Tukang 1.2.7.2 0.6000 108,000.00 64,800.00
694,800.00 - -
Overhead dan profit - - - -
694,800.00 - -
Utk.bangunan yg tingginya kurang dari 3,5 m
/m3 = 2/3 x total
2
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Pasir pasang / beton 2.2.1.49 m3 0.4320 245,000.00 105,840.00
103,662.00 423,840.00 -
Overhead dan profit - - - -
103,662.00 423,840.00 -
3
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.4.1.1 PEKERJAAN BETON
4
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Pekerja / Buruh tak terlatih 1.2.7.9 Oh 4.0000 80,000.00 320,000.00
320,000.00 - -
Overhead dan profit - - - -
320,000.00 - -
A.4.2.1.1 1m Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.1500 80,000.00 12,000.00
Tukang las 1.2.7.22 oh 0.3000 105,000.00 31,500.00
Kepala Tukang 1.2.7.2 oh 0.0300 108,000.00 3,240.00
Mandor 1.2.7.4 oh 0.0080 - -
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.228 kg 1.0500 51,000.00 53,550.00
Paku biasa 2.2.12 kg 0.0100 18,000.00 180.00
Besi strip + Mur Baut 2.2.4.17 kg 0.5000 22,500.00 11,250.00
46,740.00 64,980.00 -
Overhead dan profit - - - -
46,740.00 64,980.00 -
5
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Sealant 2.2.9.29 Tube 0.0600 20,500.00 1,230.00
8,419.40 112,193.00 -
Overhead dan profit - - - -
8,419.40 112,193.00 -
A.4.2.1.19 1m Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.1500 80,000.00 12,000.00
Tukang las 1.2.7.22 oh 0.3000 105,000.00 31,500.00
Kepala Tukang 1.2.7.2 oh 0.0300 108,000.00 3,240.00
Mandor 1.2.7.4 oh 0.0080 - -
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.228 m 1.0500 51,000.00 53,550.00
Paku biasa 2.2.12 kg 0.0100 18,000.00 180.00
Besi strip + Mur Baut 2.2.4.17 kg 0.5000 22,500.00 11,250.00
46,740.00 64,980.00 -
Overhead dan profit - - - -
46,740.00 64,980.00 -
6
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.4.4.1 PEKERJAAN PASANGAN DINDING
7
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.7000 80,000.00 56,000.00
Tukang batu 1.2.7.15 oh 0.3500 95,000.00 33,250.00
Kepala Tukang 1.2.7.2 oh 0.0350 108,000.00 3,780.00
Mandor 1.2.7.4 oh 0.0350 - -
Bahan
Keramik putih Uk. 50 cm x 50 cm 2.2.5.10 m2 1.0608 65,500.00 69,482.40
PC / Portland cement 2.2.1.51 kg 10.0000 1,450.00 14,500.00
Pasir pasang / beton 2.2.1.49 m3 0.0450 245,000.00 11,025.00
Semen Putih / warna 2.2.1.53 kg 1.5000 3,600.00 5,400.00
93,030.00 100,407.40 -
Overhead dan profit - - - -
93,030.00 100,407.40 -
8
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
9
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.4.5.2 HARGA SATUAN PENUTUP ATAP
A.4.6.1.1g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu tahun ( mahuni/akasia ) KELAS III
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 6.0000 80,000.00 480,000.00
Tukang kayu 1.2.7.20 oh 18.0000 105,000.00 1,890,000.00
Kepala Tukang 1.2.7.2 oh 1.8000 108,000.00 194,400.00
Mandor 1.2.7.4 oh 0.3000 - -
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.12 m3 1.2000 5,980,000.00 7,176,000.00
Paku biasa 2.2.6.23 kg 1.2500 18,000.00 22,500.00
Lem ( Kayu + Tembok ) 2.2.6.23 kg 1.0000 16,500.00 16,500.00
2,564,400.00 7,215,000.00 -
Overhead dan profit - - - -
2,564,400.00 7,215,000.00 -
10
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.4.6.1.5g 1 m2 Pembuatan dan pemasangan pintu panel, kayu tahun ( mauni / akasia ) KELAS III
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 1.0000 80,000.00 80,000.00
Tukang kayu 1.2.7.20 oh 3.0000 105,000.00 315,000.00
Kepala Tukang 1.2.7.2 oh 0.3000 108,000.00 32,400.00
Mandor 1.2.7.4 oh 0.0500 - -
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.34 m3 0.0400 6,320,000.00 252,800.00
Lem ( Kayu + Tembok ) 2.2.6.23 kg 0.0500 16,500.00 825.00
427,400.00 253,625.00 -
Overhead dan profit - - - -
427,400.00 253,625.00 -
A.4.6.1.6g 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Tahun papan ( Mauni/akasia) KELAS III
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.8000 80,000.00 64,000.00
Tukang kayu 1.2.7.20 oh 2.4000 105,000.00 252,000.00
Kepala Tukang 1.2.7.2 oh 0.2400 108,000.00 25,920.00
Mandor 1.2.7.4 oh 0.0400 - -
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.34 m3 0.0240 6,320,000.00 151,680.00
Lem ( Kayu + Tembok ) 2.2.6.23 kg 0.3000 16,500.00 4,950.00
341,920.00 156,630.00 -
Overhead dan profit - - - -
341,920.00 156,630.00 -
A.4.6.1.14g 1 m3 Pemasangan konstruksi kuda kuda expose kayu Tahun Mauni / Akasia
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 6.7000 80,000.00 536,000.00
Tukang kayu 1.2.7.20 oh 20.1000 105,000.00 2,110,500.00
Kepala Tukang 1.2.7.2 oh 2.0100 108,000.00 217,080.00
Mandor 1.2.7.4 oh 0.3350 - -
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.33 m3 1.2000 5,980,000.00 7,176,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 22,500.00 337,500.00
Paku biasa 2.2.12 kg 5.6000 18,000.00 100,800.00
2,863,580.00 7,614,300.00 -
Overhead dan profit - - - -
2,863,580.00 7,614,300.00 -
A.4.6.1.16g 1 m2 Pemasangan rangka atap genteng keramik, kayu Tahun ( mauni / akasia ) KELAS III
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.1000 80,000.00 8,000.00
Tukang kayu 1.2.7.20 oh 0.1000 105,000.00 10,500.00
Kepala Tukang 1.2.7.2 oh 0.0100 108,000.00 1,080.00
Mandor 1.2.7.4 oh 0.0050 - -
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.33 m3 0.0140 5,980,000.00 83,720.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.33 m3 0.0036 5,980,000.00 21,528.00
Paku biasa 2.2.12 kg 0.2500 18,000.00 4,500.00
19,580.00 109,748.00 -
Overhead dan profit - - - -
19,580.00 109,748.00 -
A.4.6.1.19g 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Tahun ( mauni / akasia )(KELAS III)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.1500 80,000.00 12,000.00
Tukang kayu 1.2.7.20 oh 0.3000 105,000.00 31,500.00
Kepala Tukang 1.2.7.2 oh 0.0300 108,000.00 3,240.00
Mandor 1.2.7.4 oh 0.0750 - -
11
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.33 m3 0.0154 5,980,000.00 92,092.00
Paku biasa 2.2.12 kg 0.2000 18,000.00 3,600.00
46,740.00 95,692.00 -
Overhead dan profit - - - -
46,740.00 95,692.00 -
A.4.6.1.21g 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Tahun ( mauni / akasia ) (KELAS III)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.1000 80,000.00 8,000.00
Tukang kayu 1.2.7.20 oh 0.2000 105,000.00 21,000.00
Kepala Tukang 1.2.7.2 oh 0.0200 108,000.00 2,160.00
Mandor 1.2.7.4 oh 0.0050 - -
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.34 m3 0.0108 6,320,000.00 68,256.00
Paku biasa 2.2.12 kg 0.1000 18,000.00 1,800.00
31,160.00 70,056.00 -
Overhead dan profit - - - -
31,160.00 70,056.00 -
12
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Kepala Tukang 1.2.7.2 oh 0.0200 108,000.00 2,160.00
Mandor 1.2.7.4 oh 0.0005 - -
Bahan
Hak angin Merk SES 2.2.7.35 bh 1.0000 40,500.00 40,500.00
31,160.00 40,500.00 -
Overhead dan profit - - - -
31,160.00 40,500.00 -
A.4.6.2.11c 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.0200 80,000.00 1,600.00
Tukang kayu 1.2.7.20 oh 0.2000 105,000.00 21,000.00
Kepala Tukang 1.2.7.2 oh 0.0200 108,000.00 2,160.00
Mandor 1.2.7.4 oh 0.0010 - -
Bahan -
Selot ( kunci pintu ) merk SES 2.2.7.55 bh 1.0000 342,000.00 342,000.00
24,760.00 342,000.00 -
Overhead dan profit - - - -
24,760.00 342,000.00 -
13
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.4.7.1 PEKERJAAN PENGECATAN
A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 2 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.0700 80,000.00 5,600.00
Tukang cat 1.2.7.17 oh 0.0090 95,000.00 855.00
Kepala Tukang 1.2.7.2 oh 0.0060 108,000.00 648.00
Mandor 1.2.7.4 oh 0.0030 - -
Bahan
Cat Meny kayu 2.2.6.10 kg 0.2000 32,500.00 6,500.00
Plamur kayu 2.2.6.36 kg 0.1500 32,500.00 4,875.00
Cat Dasar Kayu 2.2.6.5 kg 0.1700 107,500.00 18,275.00
Cat Kayu 2.2.6.7 kg 0.2600 74,500.00 19,370.00
Kuas 3 " 2.2.6.21 Bh 0.0100 18,000.00 180.00
Minyak Cat / Thiner B 2.2.6.28 kg 0.0300 19,500.00 585.00
Kertas gosok ( rempelas ) 2.2.6.20 Lbr 0.2000 4,000.00 800.00
7,103.00 50,585.00 -
Overhead dan profit - - - -
7,103.00 50,585.00 -
A.4.7.1.10 1 m2 Pengecatan tembok baru (1 lapis plamuur , 1 lapis dasar , 2 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.9 oh 0.0200 80,000.00 1,600.00
Tukang cat 1.2.7.17 oh 0.0630 95,000.00 5,985.00
Kepala Tukang 1.2.7.2 oh 0.0063 108,000.00 680.40
Mandor 1.2.7.4 oh 0.0030 - -
Bahan
Plamur Tembok 2.2.6.37 Kg 0.1000 18,500.00 1,850.00
Cat Tembok 2.2.6.11 Kg 0.1000 29,000.00 2,900.00
Cat Tembok 2.2.6.11 Kg 0.2600 29,000.00 7,540.00
8,265.40 12,290.00 -
Overhead dan profit - - - -
8,265.40 12,290.00 -
14
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG
15
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Tukang batu 1.2.7.15 oh 0.4000 95,000.00 38,000.00
Kepala Tukang 1.2.7.2 oh 0.0400 108,000.00 4,320.00
Mandor 1.2.7.4 oh 0.0050 - -
Bahan
Stop Kran Dia 3/4 " 2.2.8.117 M 1.0000 22,220.00 22,220.00
Seal Tape 2.2.8.114 Buah 0.0025 25,500.00 63.75
43,120.00 22,283.75 -
Overhead dan profit - - - -
43,120.00 22,283.75 -
16
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6)
Overhead dan profit - - - -
50,502.00 152,515.00 -
17
NAS PU- BINA MARGA DAN CIPTA KARYA
KABUPATEN TULUNGAGUNG
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
80,000.00
-
80,000.00
40,000.00
-
40,000.00
16,000.00
-
16,000.00
16,000.00
-
16,000.00
133,250.00
-
133,250.00
80,000.00
-
80,000.00
1,014,800.00
-
1,014,800.00
18
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
694,800.00
-
694,800.00
60,000.00
-
60,000.00
40,000.00
-
40,000.00
271,200.00
-
271,200.00
89,000.00
-
89,000.00
824,445.00
-
824,445.00
19
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
527,502.00
-
527,502.00
118,149.00
-
118,149.00
20
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
906,960.50
-
906,960.50
1,008,743.20
-
1,008,743.20
141,831.00
-
141,831.00
14,183.10
266,308.00
-
266,308.00
28,590.00
-
28,590.00
21
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
320,000.00
-
320,000.00
111,720.00
-
111,720.00
27,434.00
-
27,434.00
193,210.80
-
193,210.80
45,612.00
-
45,612.00
22
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
120,612.40
-
120,612.40
245,930.00
-
245,930.00
111,720.00
-
111,720.00
23
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
124,716.50
-
124,716.50
118,149.00
-
118,149.00
56,780.20
-
56,780.20
52,888.20
-
52,888.20
31,292.50
-
31,292.50
24
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
193,437.40
-
193,437.40
25
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
183,232.50
-
183,232.50
298,401.00
-
298,401.00
457,676.60
-
457,676.60
28,951.00
-
28,951.00
13,760.00
-
13,760.00
26
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
115,685.00
-
115,685.00
103,400.00
-
103,400.00
9,779,400.00
-
9,779,400.00
27
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
681,025.00
-
681,025.00
498,550.00
-
498,550.00
10,477,880.00
-
10,477,880.00
9,833,080.00
-
9,833,080.00
129,328.00
-
129,328.00
28
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
142,432.00
-
142,432.00
101,216.00
-
101,216.00
35,570.00
-
35,570.00
31,880.00
-
31,880.00
40,880.00
-
40,880.00
74,880.00
-
74,880.00
29
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
71,660.00
-
71,660.00
366,760.00
-
366,760.00
148,295.00
-
148,295.00
30
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
57,688.00
-
57,688.00
20,555.40
-
20,555.40
18,705.40
-
18,705.40
43,222.50
-
43,222.50
25,433.60
-
25,433.60
31
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
3,212,420.00
-
3,212,420.00
1,838,733.00
-
1,838,733.00
676,130.00
-
676,130.00
23,700.00
-
23,700.00
81,683.75
-
81,683.75
32
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
65,403.75
-
65,403.75
25,503.00
-
25,503.00
29,378.00
-
29,378.00
79,926.50
-
79,926.50
109,423.00
-
109,423.00
203,017.00
33
JUMLAH
(Rp)
10 = ( 7 + 8 + 9 )
-
203,017.00
34
TIME SCHEDULE
KEGIATAN : -
LOKASI : -
SUMBER DANA : -
SISTIM : -
Bobot
No Uraian Pekerjaan Harga Pekerjaan 1 2 3 4 5 6 7 8
% PROSEN
1 2 3 4
VI PEKERJAAN KUSEN PINTU DAN JENDELA 7,361,511.16 4.749 1.583 1.583 1.583
50
- -
VII PEKERJAAN RANGKA ATAP 24,824,686.18 16.015 4.004 4.004 4.004 4.004
- - 40
VIII PEKERJAAN PENUTUP ATAP 12,873,845.55 8.305 2.768 2.768 2.768
- - 30
IX PEK. INSTALASI LISTRIK 16,538,173.89 10.669 3.556 3.556 3.556
- -
20
X PEKERJAAN PENGECETAN 6,716,536.56 4.333 2.166 2.166
10
XI PEKERJAAN LISTRIK 2,337,500.00 1.508 0.754 0.754
- - 0
JUMLAH 155,011,000.00 100.00
MINGGUAN 3.248 4.418 11.167 21.751 24.707 21.308 10.480 2.920
RENCANA
KOMULATIF 3.248 7.665 18.832 40.584 65.291 86.599 97.079 100.000
MINGGUAN 1.730 7.130 3.240 1.110 5.974 2.410 11.278 14.043
REALISASI
KOMULATIF 1.730 8.860 12.100 13.210 19.184 21.594 32.872 46.915
kurva S
120.000
100.000
80.000
60.000
40.000