Provinsi : Jawa Barat Desa : Tegal Sumedang

Kabupaten : Bandung TAKE OF SHEET Lokasi :


Kecamatan : Rancaekek

I Menghitung Kebutuhan Pagar


1 Penggalian 1 m3 tanah biasa sedalam ≤ 1 m (PermenPUPR No 1-2022 Hal.183)
Panjang : 29.1 + 0 + 29.1 + 0 = 58.2
Jarak antar tiang = 2.5
Banyak tiang : 58.2 / 2.5 = 23.28 = 23
Volume : 0.3 x 0.3 x 0.5 = 0.045
: 23 x 0.045 = 1.035

Pekerja : 0.75 x 1.035 = 0.77625

2 Pekerjaan pemasangan pasir Urug (Permen PUPR No. 1-2022, Hal 185) :
Volume : = 1.04

Pasir Urug : 1.20 x 1.0 = 1.24


Pekerja : 0.30 x 1.2 = 0.37

3 Pekerjaan Rabat Beton (1m3 beton mutu f'c=9,8 Mpa K-125) (PermenPUPR No. 1-2022, Hal 1067) :
Volume beton : 0.30 x 0.3 x 0.5 = 0.05
0.05 x 23 = 1.04
1.08

Semen 50 kg : 5.52 x 1.08 = 5.9616


Pasir Beton : 0.59 x 1.08 = 0.63874
Kerikil/ Split 2/3 : 0.75 x 1.08 = 0.8096
Pekerja : 1.65 x 1.08 = 1.782
Tukang : 0.28 x 1.08 = 0.297

4 Pekerjaan Tiang Pagar (PermenPUPR No. 1-2022, Hal 1091) :


Volume : : Tiang 23 x 3 = 69

Besi hollow 4 x 4 : 69.0 : 6.00 = 11.50


Assesoris : = 1
Pekerja : 0.25 x 69 = 17.25
Tukang : 0.25 x 69 = 17.25

5 Pekerjaan Pagar weirmesh (2,1 m x 5,4 m) (PermenPUPR No. 1-2022) :


Volume : (98,2 x 2,1) / (5,4 x 2,1) = 10.78
Volume penutup jendela : ((1,5 x 1,5)x 3)/ (5,4 x 2,1) = 0.60
Wiremesh : 1.01 x 11.37 = 11.49
Kawat las : 0.1 x 122.22 = 12.22
Pekerja : 0.1 x 122.22 = 12.22

II Menghitung Kebutuhan Kandang


1 Pekerjaan 1 m2 Lantai Kandang
Panjang Kandang = 15 m
Lebar Kandang = 6 m
Lebar teras = 2 m

Kayu Kaso 4 x 6 x 400 cm


: 15 / 0.5 x 8 = 246
(Melintang)
0.04 x 0.06 x 246 = 0.5904
Kayu Balok 10 x 10 x 250 cm
15 x 3 = 45
(Memanjang)
volume : 0.1 x 0.1 x 45 = 0.45
Kayu reng 3 x 6 x 400 cm : 15 / 0.08 x 6 = 1131
0.03 x 0.06 x 1131 = 2.0358
Pemasangan kayu balok lantai kandang (PermenPUPR1-2022Hal. 1171)
Provinsi : Jawa Barat Desa : Tegal Sumedang
Kabupaten : Bandung TAKE OF SHEET Lokasi :
Kecamatan : Rancaekek
Kayu Balok 10 x 10 x 250 cm : 1.1 x 0.45 = 0.495
Paku 8-12 cm : 5.6 x 0.45 = 2.52
Pekerja : 4 x 0.45 = 1.8
Mandor : 12 x 0.45 = 5.4

Pemasangan kayu lantai kandang (PermenPUPR1-2022Hal. 1171)

Kayu Kaso 4 x 6 x 400 cm : 1.1 x 0.5904 = 0.64944

Kayu reng 3 x 6 x 400 cm : 1.1 x 2.0358 = 2.23938


Paku 4-7 cm : 5.6 x 2.6262 = 14.7067
Pekerja : 4 x 2.6262 = 10.5048
Tukang : 12 x 2.6262 = 31.5144

2 Pekerjaan Pagar kandang/Sekat


Kayu Balok 10 x 10 x 250 cm 18 x 2 = 36
0.1 x 0.1 x 36 = 0.36
Kayu Balok 7 x 5 x 400 cm 15 x 4 = 60
0.07 x 0.05 x 60 = 0.21
Kayu reng 3 x 6 x 400 cm : 15 / 0.09 x 0.44 = 73.3333
0.02 x 0.06 x 73.3333 = 0.088
Kayu reng 3 x 6 x 400 cm : 15 / 0.12 x 0.76 = 95
0.02 x 0.06 x 95 = 0.114
Kayu reng 3 x 6 x 400 cm : 15 x 6 x 2 = 180
0.02 x 0.06 x 180 = 0.216
= 0.418
Pemasangan kayu lantai kandang (PermenPUPR1-2022Hal. 1171)
Kayu Balok 10 x 10 x 400 cm : 1.1 x 0.36 = 0.396
Kayu Balok 7 x 5 x 400 cm : 1.1 x 0.21 = 0.231
Kayu reng 3 x 6 x 400 cm : 1.1 x 0.418 = 0.4598
Paku 4-7 cm : 5.6 x 0.988 = 5.5328
Pekerja : 4 x 0.988 = 3.952
Tukang : 12 x 0.988 = 11.856

3 Pekerjaan Tempat makan


Kayu reng 3 x 6 x 400 cm : 5.25 / 0.36 x 1.2 = 17.5
0.02 x 0.06 x 17.5 = 0.021
Kayu reng 3 x 6 x 400 cm : 5.25 x 6 x 1 = 31.5
0.02 x 0.06 x 31.5 = 0.0378
= 0.059
Kayu reng 3 x 6 x 400 cm : 1.1 x 0.059 = 0.06468
Paku 4-7 cm : 5.6 x 0.059 = 0.32928
Pekerja : 4 x 0.0588 = 0.2352
Tukang : 12 x 0.0588 = 0.7056

4 Pemasangan 1 m2 atap asbes gelombang 1,05 m x 3 m x 5 mm


Volume 15.50 x 8.5 x 0.9848078 = 131.75 m2
ukuran asbes 300 x 105 = 3.15 m2

Asbes 3 x 1,05 131.750 / 3.15 = 20.912698 lbr *Asumsi penggunaan asbes 50%
Paku asbes 0.12 X 20.9127 = 2.5095238 kg
Pekerja 0.140 x 20.9127 = 2.9277778 HOK
Tukang 0.075 x 20.9127 = 1.5684524 HOK

Rekapitulasi :
1 Pasir Urug = 1.24 m3 ~ 1.00 m3
2 Semen 50 kg = 5.9616 zak ~ 6.00 zak
Provinsi : Jawa Barat Desa : Tegal Sumedang
Kabupaten : Bandung TAKE OF SHEET Lokasi :
Kecamatan : Rancaekek
3 Pasir Beton = 0.638743 m3 ~ 1.00 m3
4 Kerikil/ Split 2/3 = 0.8096 m3 ~ 1.00 m3
5 Besi hollow 4 x 4 = 11.50 btg ~ 12.00 btg
= ~ 1.00 Ls
6 Assesoris 1 Ls
7 Wiremesh = 11.49 lbr ~ 11.00 lbr
8 Kawat las = 12.22 kg ~ 12.00 kg
9 Kayu Balok 10 x 10 x 250 cm = 0.891 m3 ~ 1.00 m3 0.025 36 batang ~
10 Paku 8-12 cm = 2.52 kg ~ 3.00 kg
11 Kayu Kaso 4 x 6 x 400 cm = 0.64944 m3 ~ 0.50 m3 0.010 68 batang ~
12 Kayu reng 3 x 6 x 400 cm = 2.76386 m3 ~ 3.00 m3 0.007 384 batang ~
13 Paku 4-7 cm = 20.5688 kg ~ 21.00 kg
14 Kayu Balok 7 x 5 x 400 cm = 0.231 m3 ~ 0.50 m3 0.014 17 batang ~
15 Asbes 3 x 1,05 = 20.9127 lbr ~ 21.00 lbr
16 Paku asbes = 2.509524 kg ~ 3.00 kg

17 Pekerja = 51.82 HOK ~ 52.00 HOK


18 Tukang = 63.19145 HOK ~ 63.00 HOK
Tegal Sumedang

m3
m
buah
m3
m3

HOK

m3

m3
OH

m3
m3
m3

zak
m3
m3
HOK
HOK

btg
Ls
HOK
HOK

Lembar

Lembar
kg
OH

m
m3
m
m3
m
m3
Tegal Sumedang

m3
kg
HOK
HOK

m3

m3
kg
HOK
HOK

m
m3
m
m3
m
m3
m
m3
m
m3
m3

m3
m3
m3
kg
HOK
HOK

m
m3
m
m3
m3
m3
kg
HOK
HOK

an asbes 50%
Tegal Sumedang

36 batang

68 batang
384 batang

17 batang
Provinsi : Jawa Barat Desa : Tegal Sumedang
Kabupaten : Bandung TAKE OF SHEET Lokasi :
Kecamatan : Rancaekek

I. PEKERJAAN BETON BERTULANG (1:2:3)


1. Pek. Kolom 15/15
Luas = 0.15 x 0.15 = 0.0225 m2
Tinggi = 1.0 m
Jumlah = 15.0 bh
Volume = 0.02 x 1.0 x 15.00 = 0.34 m3
Keliling = 2 x 0.15 + 2 x 0.15 = 0.6
Luas Bekisting = 0.6 x 15.0 = 9 m2

Kebutuhan Bekisting :
Luas Bekisting = 9.0 m2
Analisa A.4.1.1.23
1 Kayu Kelas III = 0.04 x 9 = 0.4 m3
2 Paku biasa 2'-5" = 0.40 x 9 = 3.6 kg
4 Balok Kayu Kelas II = 0.02 x 9 = 0.2 m3
5 Plywood tebal 9 mm = 0.35 x 9 = 3.2 Lbr
6 Pekerja = 0.66 x 9 = 6 OH
7 Tukang kayu = 0.33 x 9 = 3.0 OH
Kebutuhan Volume Beton Bertulang (1:2:3) (K-225) :
Volume Beton = 0.34 m3
Analisa B.07.b
1 Semen PC (50 kg) = 7.42 x 0.3 = 3 Zak
2 Pasir beton = 0.50 x 0.3 = 0.2 m3
3 Koral beton = 0.78 x 0.3 = 0.3 m3
4 Pekerja = 1.32 x 0.3 = 0.4 OH
5 Tukang = 0.19 x 0.3 = 0.06 OH
6 Sewa Molen Kap. 0.3 m3 = 0.25 x 0.3 = 0.08 Hari

II. PEKERJAAN PEMBESIAN


1. Pek. Kolom 15/15
panjang b = 35 35
=
= 70 cm
= 0.70 m
Besi Tulangan Pokok = 8 Ø 12 mm
Panjang kolom = 15.0 m
Berat Besi :
W Ø 12 = 0.8878 Kg/m
Panjang Besi = 8 x 15 = 120 m + 5% = 126
= 126 = 11 Lente
12
W = 126 x 0.88776 = 112 Kg
Besi Sengkang = Ø8 - 20 cm
Panjang Sengkang = 0.7 m
Berat Besi :
W Ø 8 = 0.393 Kg/m
Jumlah Sengkang = 15.0 = 75 bh
0.2
Pj Sengkang = 1 x 75 = 52.5 m + 5% = 55
= 55 = 5 Lente
12
W = 55 x 0.393 = 21.7 Kg
Berat Total = 111.9 + 21.7 = 134 Kg

Kebutuhan Volume Pembesian :


Analisa B.17.6
1 Besi beton 12 = 1.05 x 126 = 132 m = 12 Lente
3 Besi beton 8 = 1.05 x 55 = 58 m = 5 Lente
4 Kawat beton = 0.02 x 134 = 2 Kg
5 Pekerja = 0.02 x 134 = 3 OH
6 Tukang besi = 0.01 x 134 = 2 OH

III. PEKERJAAN PAGAR


1. Pasangan Dinding Bata Ringan Tebal 10 cm dengan mortar siap pakai (Permen PUPR No. 1 Tahun 2022)
Tinggi Pasangan Bata Ringan (Hebel) = 1.0 m Luas =
Panjang = 50 m
= 50 m2
Analisa A.4.4.1.26 (PermenPUPR No. 1-2022, Hal 1105) :
1 Bata ringan tebal 10 cm = 8.400 x 50.0 = 420
2 Mortar siap pakai (Semen Instan) = 0.063 x 50.0 = 3
4 Pekerja = 0.671 x 50.0 = 34
5 Tukang batu = 0.130 x 50.0 = 7

IV. PEKERJAAN PAVING BLOCK


Lebar = 6.1 m
Panjang = 14 m
Luas = 14.0 x 6.1 = 85 m2

> Galian Tanah kedalaman kurang dari 1 m (Permen PUPR No. 1 Tahun 2022, Hal 183)
Galian = 0.14 x 0.10 = 0.01 m2
Panjang = 14.0 m
Volume = 0.01 x 14.00 = 0.20 m3
2 Sisi = 2 x 0.20 = 0.39 m3
Pekerja = 0.75 x 0.39 = 0.294 OH

> Urugan pasir bawah paving block (Permen PUPR No. 1 Tahun 2022, Hal 185)
Luas = 0.05 x 0.10 = 0.005 m2
Panjang = 14.0 m
Volume = 0.005 x 14.0 = 0.070 m3

Pasir urug = 1.2 x 0.07 = 0.084 m3


Pekerja = 0.3 x 0.07 = 0.021 OH

> Pemasangan paving block = 14 x 6 = 85


Paving block 14 x 1.01 = 14 m2
Pasir beton 14 x 0.05 = 0.70 m3
Pekerja 14 x 0.25 = 4 OH
Tukang 14 x 0.5 = 7 OH

> Pemasangan bata bagian luar pembatas paving block


panjang = 20.1 m
luas = 0.2 x 20.1 = 4 x 2 = 8.04

Bata merah (5x11x22) = 70 x 8.04 = 563 bh


pekerja = 0.3 x 8.04 = 2.41 OH
tukang = 0.1 x 8.04 = 0.80 OH

Pekerjaan plesteran
Luas = 8 x 2 = 16.1 m2

semen (50 kg) = 0.104 x 16.1 = 1.67 zak


pasir pasang = 0.026 x 16.1 = 0.42 m3
pekerja = 0.3 x 16.1 = 4.82 OH
tukang = 0.15 x 16.1 = 2.41 OH

pekerjaan acian
Luas = 16 m2

semen (50 kg) = 0.065 x 16.1 = 1.05 zak


pekerja = 0.2 x 16.1 = 3.22 OH
tukang = 0.1 x 16.1 = 1.61 OH

V. Menghitung Kebutuhan Kandang


1 Pekerjaan 1 m2 Lantai Kandang
Panjang Kandang = 12 m
Lebar Kandang = 5 m

Kayu Kaso 4 x 6
x 400 cm : 12 / 0.5 x 5 = 126 m
(Melintang)
0.04 x 0.06 x 126 = 0.3024 m3
Kayu Balok 12 x
12 x 250 cm 12 x 3 = 36 m
(Memanjang)
volume : 0.12 x 0.12 x 36 = 0.5184 m3
Kayu reng 3 x 6 x
: 12 / 0.08 x 5 = 756 m
400 cm
0.03 x 0.06 x 756 = 1.3608 m3
Pemasangan kayu balok lantai kandang (PermenPUPR1-2022Hal. 1171)
Kayu Balok 12 x
: 1.1 x 0.5184 = 0.5702 m3
12 x 250 cm
Paku 8-12 cm : 5.6 x 0.5184 = 2.903 kg
Pekerja : 4 x 0.5184 = 2.0736 HOK
Mandor : 12 x 0.5184 = 6.2208 HOK

Pemasangan kayu lantai kandang (PermenPUPR1-2022Hal. 1171)


Kayu Kaso 4 x 6
: 1.1 x 0.3024 = 0.3326 m3
x 400 cm
Kayu reng 3 x 6 x
: 1.1 x 1.3608 = 1.4969 m3
400 cm
Paku 4-7 cm : 5.6 x 1.6632 = 9.3139 kg
Pekerja : 4 x 1.6632 = 6.6528 HOK
Tukang : 12 x 1.6632 = 19.958 HOK
2 Pekerjaan Pagar kandang/Sekat
Kayu Balok 12 x
18 x 2 = 36 m
12 x 250 cm
0.12 x 0.12 x 36 = 0.5184 m3
Kayu Balok 7 x 5
x 400 cm 15 x 4 = 60 m
0.07 x 0.05 x 60 = 0.21 m3
Kayu reng 3 x 6 x
: 12 / 0.09 x 0.44 = 58.667 m
400 cm
0.02 x 0.06 x 58.667 = 0.0704 m3
Kayu reng 3 x 6 x
: 12 / 0.12 x 0.76 = 76 m
400 cm
0.02 x 0.06 x 76 = 0.0912 m3
Kayu reng 3 x 6 x
: 12 x 6 x 2 = 144 m
400 cm
0.02 x 0.06 x 144 = 0.1728 m3
= 0.334 m3
Pemasangan kayu lantai kandang (PermenPUPR1-2022Hal. 1171)
Kayu Balok 12 x
: 1.1 x 0.5184 = 0.5702 m3
12 x 400 cm
Kayu Balok 7 x 5
: 1.1 x 0.21 = 0.231 m3
x 400 cm
Kayu reng 3 x 6 x
: 1.1 x 0.334 = 0.3678 m3
400 cm
Paku 4-7 cm : 5.6 x 1.063 = 5.9517 kg
Pekerja : 4 x 1.0628 = 4.2512 HOK
Tukang : 12 x 1.0628 = 12.754 HOK

3 Pekerjaan Tempat makan


Kayu reng 3 x 6 x
: 4.25 / 0.36 x 1.2 = 14.167 m
400 cm
0.02 x 0.06 x 14.167 = 0.017 m3
Kayu reng 3 x 6 x
: 4.25 x 6 x 1 = 25.5 m
400 cm
0.02 x 0.06 x 25.5 = 0.0306 m3
= 0.048 m3
Kayu reng 3 x 6 x
: 1.1 x 0.048 = 0.0524 m3
400 cm
Paku 4-7 cm : 5.6 x 0.048 = 0.2666 kg
Pekerja : 4 x 0.0476 = 0.1904 HOK
Tukang : 12 x 0.0476 = 0.5712 HOK

REKAPITULASI KEBUTUHAN BAHAN

1 Kayu Kelas III = 0.36 ≈ - m3


2 Paku biasa 2'-5" = 3.60 ≈ 4 kg
3 Balok Kayu Kelas II = 0.16 ≈ - m3
4 Plywood tebal 9 mm = 3.15 ≈ 3 Lbr
5 Semen PC (50 kg) = 5.22 ≈ 5 Zak
6 Pasir beton = 0.17 ≈ - m3
7 Koral beton = 0.26 ≈ - m3
8 Besi beton 12 = 12.0 ≈ 12 Lente
9 Besi beton 8 = 5.0 ≈ 5 Lente
10 Kawat beton = 2.0 ≈ 2 Kg
11 Bata ringan tebal 10 cm = 420 ≈ 420 Bh
12 Mortar siap pakai (Semen Instan) = 3.15 ≈ 3 m3
13 Pasir urug = 0.08 ≈ -
14 Paving block = 14.14 ≈ 14 m2
15 Pasir beton = 0.70 ≈ 1 m3
16 Bata merah (5x11x22) = 563 ≈ 563 bh
17 pasir pasang = 0.42 ≈ - m3
Kayu Balok 12 x
= ~ 1.00 m3 0.036 32 batang ~ 32
12 x 250 cm 1.14048 m3
Paku 8-12 cm = 2.90304 kg ~ 3.00 kg
Kayu Kaso 4 x 6
= ~ 0.50 m3 0.010 35 batang ~ 35
x 400 cm 0.33264 m3
Kayu reng 3 x 6 x
= ~ 0.50 m3 0.007 266 batang ~ 266
400 cm 1.91708 m3
Paku 4-7 cm = 15.5322 kg ~ 16.00 kg
Kayu Balok 7 x 5
= ~ 0.50 m3 0.014 17 batang ~ 17
x 400 cm 0.231 m3

1 Sewa Molen = 0.08 ≈ - Hari


2 Pekerja = 70 ≈ 70 OH
3 Tukang = 63 ≈ 63 OH
al Sumedang

m
m

R No. 1 Tahun 2022)


50

Bh
Zak
OH
OH
m2
batang

batang

batang

batang
RENCANA ANGGARAN BIAYA
TAHUN ANGGARAN 2023

No.RAB :
Propinsi : Jawa Barat Program : Dana Desa
Kabupaten : Bandung Jenis Kegiatan : Paket Ternak Domba
Kecamatan : Rancaekek Ukuran/dimensi : 1 unit
Desa : Tegal Sumedang Lokasi :

Volume Jumlah Jumlah


Harga
No URAIAN Dari Satuan Swadaya Dana Desa
Total Dari DD Satuan (Rp)
Swadaya (Rp) (Rp)
1. BAHAN a b c d e f g=cxe
PEMBUATAN KANDANG
1 Kayu Kelas III - - - m3 1,998,000 - -
2 Paku biasa 2'-5" 4.00 - 4.00 kg 22,200 - 88,800
3 Balok Kayu Kelas II - - - m3 1,998,000 -
4 Plywood tebal 9 mm 3.00 - 3.00 Lbr 144,300 - 5,994,000
5 Semen PC (50 kg) 5.00 - 5.00 Zak 83,250 - 416,250
6 Pasir beton - - - m3 271,950 - -
7 Koral beton - - - m3 366,300 - -
8 Besi beton 12 12.00 - 12.00 Lente 144,300 - 1,731,600
9 Besi beton 8 5.00 - 5.00 Lente 66,600 - 333,000
10 Kawat beton 2.00 - 2.00 Kg 25,250 - 50,500
11 Bata ringan tebal 10 cm 420.00 - 420.00 Bh 11,100 - 4,662,000
12 Mortar siap pakai (Semen Instan) 3.00 - 3.00 m3 94,350 - 283,050
13 Pasir urug - - - - - -
14 Paving block 14.00 - 14.00 m2 150,000 - 2,100,000
15 Pasir beton 1.00 - 1.00 m3 271,950 - 271,950
16 Bata merah (5x11x22) 563.00 - 563.00 bh - -
17 pasir pasang - - - m3 - -
18 Kayu Balok 12 x 12 x 250 cm 31.68 - 31.68 batang 150,000 - 4,752,000
19 Paku 8-12 cm - - - - - -
20 Kayu Kaso 4 x 6 x 400 cm 34.65 - 34.65 batang 200,000 - 6,930,000
21 Kayu reng 3 x 6 x 400 cm 266.26 - 266.26 batang 25,000 - 6,656,528
22 Paku 4-7 cm - - - - - -
23 Kayu Balok 7 x 5 x 400 cm 16.50 - 16.50 batang 150,000 - 2,475,000
Sub Total 1) - 36,744,678
2. ALAT
1 Papan Proyek 1.00 - 1.00 bh 110,000 - 110,000
2 Prasasti 1.00 - 1.00 bh 250,000 - 250,000
3 Sewa Molen - - - Hari - -
Sub Total 2) - 360,000
3. UPAH
1 Pekerja 70.00 - 70.00 hok 150,000 - 10,500,000
2 Tukang 63.00 - 63.00 hok 175,000 - 11,025,000
Sub Total 3) - 21,525,000
4. BIAYA UMUM
1 ATK 1.00 - 1.00 ls - - -
2 Desain & RAB 1.00 - 1.00 ls - - -
3 Transportasi Survey 1.00 - 1.00 ls - - -
Sub Total 4) - -
Alokasi Biaya Dana Desa (DD) - 58,629,678
Total Biaya Dana Desa 58,629,678
Sumber Dana
Total Biaya Swadaya -
Total Biaya (DD + Swadaya) 58,629,678

Disetujui/mengesahkan Tegal Sumedang, …..................2023


Kepala Desa Tegal Sumedang Pelaksana Kegiatan

…............................. …..................................

Mengetahui
Tim Pembina Kecamatan Rancaekek

….................................
…............................
58,629,678 1,758,890
BU 3% dari pembutan kandang saja, tidak termasuk pembelian ternak

70,823,200