2 Pekerjaan pemasangan pasir Urug (Permen PUPR No. 1-2022, Hal 185) :
Volume : = 1.04
3 Pekerjaan Rabat Beton (1m3 beton mutu f'c=9,8 Mpa K-125) (PermenPUPR No. 1-2022, Hal 1067) :
Volume beton : 0.30 x 0.3 x 0.5 = 0.05
0.05 x 23 = 1.04
1.08
Asbes 3 x 1,05 131.750 / 3.15 = 20.912698 lbr *Asumsi penggunaan asbes 50%
Paku asbes 0.12 X 20.9127 = 2.5095238 kg
Pekerja 0.140 x 20.9127 = 2.9277778 HOK
Tukang 0.075 x 20.9127 = 1.5684524 HOK
Rekapitulasi :
1 Pasir Urug = 1.24 m3 ~ 1.00 m3
2 Semen 50 kg = 5.9616 zak ~ 6.00 zak
Provinsi : Jawa Barat Desa : Tegal Sumedang
Kabupaten : Bandung TAKE OF SHEET Lokasi :
Kecamatan : Rancaekek
3 Pasir Beton = 0.638743 m3 ~ 1.00 m3
4 Kerikil/ Split 2/3 = 0.8096 m3 ~ 1.00 m3
5 Besi hollow 4 x 4 = 11.50 btg ~ 12.00 btg
= ~ 1.00 Ls
6 Assesoris 1 Ls
7 Wiremesh = 11.49 lbr ~ 11.00 lbr
8 Kawat las = 12.22 kg ~ 12.00 kg
9 Kayu Balok 10 x 10 x 250 cm = 0.891 m3 ~ 1.00 m3 0.025 36 batang ~
10 Paku 8-12 cm = 2.52 kg ~ 3.00 kg
11 Kayu Kaso 4 x 6 x 400 cm = 0.64944 m3 ~ 0.50 m3 0.010 68 batang ~
12 Kayu reng 3 x 6 x 400 cm = 2.76386 m3 ~ 3.00 m3 0.007 384 batang ~
13 Paku 4-7 cm = 20.5688 kg ~ 21.00 kg
14 Kayu Balok 7 x 5 x 400 cm = 0.231 m3 ~ 0.50 m3 0.014 17 batang ~
15 Asbes 3 x 1,05 = 20.9127 lbr ~ 21.00 lbr
16 Paku asbes = 2.509524 kg ~ 3.00 kg
m3
m
buah
m3
m3
HOK
m3
m3
OH
m3
m3
m3
zak
m3
m3
HOK
HOK
btg
Ls
HOK
HOK
Lembar
Lembar
kg
OH
m
m3
m
m3
m
m3
Tegal Sumedang
m3
kg
HOK
HOK
m3
m3
kg
HOK
HOK
m
m3
m
m3
m
m3
m
m3
m
m3
m3
m3
m3
m3
kg
HOK
HOK
m
m3
m
m3
m3
m3
kg
HOK
HOK
an asbes 50%
Tegal Sumedang
36 batang
68 batang
384 batang
17 batang
Provinsi : Jawa Barat Desa : Tegal Sumedang
Kabupaten : Bandung TAKE OF SHEET Lokasi :
Kecamatan : Rancaekek
Kebutuhan Bekisting :
Luas Bekisting = 9.0 m2
Analisa A.4.1.1.23
1 Kayu Kelas III = 0.04 x 9 = 0.4 m3
2 Paku biasa 2'-5" = 0.40 x 9 = 3.6 kg
4 Balok Kayu Kelas II = 0.02 x 9 = 0.2 m3
5 Plywood tebal 9 mm = 0.35 x 9 = 3.2 Lbr
6 Pekerja = 0.66 x 9 = 6 OH
7 Tukang kayu = 0.33 x 9 = 3.0 OH
Kebutuhan Volume Beton Bertulang (1:2:3) (K-225) :
Volume Beton = 0.34 m3
Analisa B.07.b
1 Semen PC (50 kg) = 7.42 x 0.3 = 3 Zak
2 Pasir beton = 0.50 x 0.3 = 0.2 m3
3 Koral beton = 0.78 x 0.3 = 0.3 m3
4 Pekerja = 1.32 x 0.3 = 0.4 OH
5 Tukang = 0.19 x 0.3 = 0.06 OH
6 Sewa Molen Kap. 0.3 m3 = 0.25 x 0.3 = 0.08 Hari
> Galian Tanah kedalaman kurang dari 1 m (Permen PUPR No. 1 Tahun 2022, Hal 183)
Galian = 0.14 x 0.10 = 0.01 m2
Panjang = 14.0 m
Volume = 0.01 x 14.00 = 0.20 m3
2 Sisi = 2 x 0.20 = 0.39 m3
Pekerja = 0.75 x 0.39 = 0.294 OH
> Urugan pasir bawah paving block (Permen PUPR No. 1 Tahun 2022, Hal 185)
Luas = 0.05 x 0.10 = 0.005 m2
Panjang = 14.0 m
Volume = 0.005 x 14.0 = 0.070 m3
Pekerjaan plesteran
Luas = 8 x 2 = 16.1 m2
pekerjaan acian
Luas = 16 m2
Kayu Kaso 4 x 6
x 400 cm : 12 / 0.5 x 5 = 126 m
(Melintang)
0.04 x 0.06 x 126 = 0.3024 m3
Kayu Balok 12 x
12 x 250 cm 12 x 3 = 36 m
(Memanjang)
volume : 0.12 x 0.12 x 36 = 0.5184 m3
Kayu reng 3 x 6 x
: 12 / 0.08 x 5 = 756 m
400 cm
0.03 x 0.06 x 756 = 1.3608 m3
Pemasangan kayu balok lantai kandang (PermenPUPR1-2022Hal. 1171)
Kayu Balok 12 x
: 1.1 x 0.5184 = 0.5702 m3
12 x 250 cm
Paku 8-12 cm : 5.6 x 0.5184 = 2.903 kg
Pekerja : 4 x 0.5184 = 2.0736 HOK
Mandor : 12 x 0.5184 = 6.2208 HOK
m
m
Bh
Zak
OH
OH
m2
batang
batang
batang
batang
RENCANA ANGGARAN BIAYA
TAHUN ANGGARAN 2023
No.RAB :
Propinsi : Jawa Barat Program : Dana Desa
Kabupaten : Bandung Jenis Kegiatan : Paket Ternak Domba
Kecamatan : Rancaekek Ukuran/dimensi : 1 unit
Desa : Tegal Sumedang Lokasi :
…............................. …..................................
Mengetahui
Tim Pembina Kecamatan Rancaekek
….................................
…............................
58,629,678 1,758,890
BU 3% dari pembutan kandang saja, tidak termasuk pembelian ternak
70,823,200
12,193,522