pekerjaan bowblank
SNI 03-2835-2002-6.2
panjang = 5M
lebar = 4M
bahan
kayu 5/7 bowlank = 0.012 x 0.056 = 0.000672
16 / 4 = 4
papan 3/20 = 0.007 x 0.096 = 0.000672
16 / 4 = 4
Paku Kayu 2-5 Inchi = 0.02 x 16 = 0.32
UPAH
pekerja = 0.1 x 16 = 1.6
tukang = 0.1 x 16 = 1.6
kepala tukang = 0.01 x 16 = 0.16
urugan pasir
SNI 2835 : 2008-6.10
pondasi = 16 x 0.1 x 0.5 = 0.8
bahan
pasir urug = 1.2 x 0.8 = 0.96
UPAH
pekerja = 0.3 x 0.8 = 0.24
mandor = 0.01 x 0.8 = 0.008
bahan
Batu Belah/Batu Kali 15/20cm = 1.200 x 0.297 = 0.356
Semen Portland = 12 x 0.297 = 0.085
Pasir pasang = 0.520 x 0.297 = 0.154
UPAH
pekerja = 1.500 x 0.297 = 0.4455
tukang = 0.750 x 0.297 = 0.22275
kepala tukang = 0.075 x 0.297 = 0.022275
PEKERJAAN PEMBESIAN
UPAH
Pekerja = 0.520 x 12.8 = 6.656
Tukang = 0.26 x 12.8 = 3.328
Kepala Tukang = 0.060 x 12.8 = 0.768
PEKERJAAN BETON
membuat 1 Mᶟ balok sloof beton bertulang
Sni 03-3435-2002-E
Bahan
Pasir beton = 0.52 x 16.35 = 8.502
Koral/krikil beton = 0.78 x 16.35 = 12.753
Semen Porland = 0.58 x 16.35 = 9.483
air = 21.5 x 16.35 = 351.525
UPAH
Pekerja = 1.65 x 16.35 = 26.9775
Tukang = 0.275 x 16.35 = 4.49625
Kepala Tukang = 0.028 x 16.35 = 0.4578
1 M3 Beton mutu f'c = 7,4 Mpa (K100), slump (12 ± 2) cm, w/c = 0,87
SNI DT-91-0008-2007-6.1
Pasir Beton 869.000 X 0.4275 = 371.4975 Kg
Kerikil Beton 999.000 X 0.4275 = 427.0725 Kg
Semen Portland 247.000 X 0.4275 = 105.5925 Kg
Air 215.000 X 0.4275 = 91.9125 Liter
upah
Pekerja 1.650 X 0.4275 = 0.705375 HOK
Tukang 0.275 X 0.4275 = 0.1175625 HOK
Kepala Tukang 0.028 X 0.4275 = 0.01197 HOK
Mandor 0.083 X 0.4275 = 0.0354825 HOK
Pekerjaan Lain-lain
Volume = 1/2 { 2 x ( 0.26 x 16) } = 4.00 M2
pekerjaan kayu
panjang kayu 4 m
BAHAN
PAPAN KAYU = 0.04 X 2.8 = 0.112
PAKU 2 m'- 6cm' = 0.05 X 2.8 = 0.14
UPAH
pekerja = 0.35 X 2.8 = 0.98
tukang kayu = 1.105 X 2.8 = 3.094
kepala tukang = 1.105 X 2.8 = 3.094
mandor = 0.018 X 2.8 = 0.0504
bahan
balok kayu kelas II = 1.100 x 0.048 = 0.053
Paku 5''-12'' = 5.600 x 0.048 = 0.269
Besi Strip = 15.000 x 0.048 = 0.720
seng 6 kaki = 0.700 x 64.8 = 45.360
UPAH
Pekerja = 4.000 x 0.048 = 0.192
Tukang Kayu = 12.000 x 0.048 = 0.576
Kepala tukang = 1.200 x 0.048 = 0.058
Mandor = 0.200 x 0.048 = 0.010
UPAH
Pekerja = 0.100 x 0.16 = 0.016
Mandor = 0.005 x 0.16 = 0.001
Tukang Kayu = 0.200 x 0.16 = 0.032
Kepala tukang = 0.025 x 0.16 = 0.004
M
Mᶟ
Mᶟ
Mᶟ
Btg
Mᶟ
Btg
Kg
Hok
Hok
Hok
Mᶟ
Hok
Hok
Mᶟ
Hok
Hok
Mᶟ
Mᶟ
Hok
Hok
Mᶟ
Mᶟ
Mᶟ
Hok
Hok
Hok
Hok
Mᶟ
Zak
Mᶟ
Hok
Hok
Hok
M²
M²
Kg
M²
btg
Hok
Hok
Hok
Mᶟ
Mᶟ
Zak
liter
Hok
Hok
Hok
Hok
Kg
Kg
Lbr
Hok
Hok
Hok
Hok
M2
M2
M2
Hok
Hok
Hok
Hok
RENCANA ANGGARAN BIAYA
Mengetahui : Mengetahui :
PELAKSANA TEKNIS PENGELOLAAN
TIM PENGELOLA KEGIATAN
KEGIATAN KAMPONG UJUNG LIMUS
KAMPONG UJUNG LIMUS KECAMATAN SIMPANG
KANAN
KECAMATAN SIMPANG KANAN
.............................. ...............................
Mengetahu:
PENGGUNA ANGARAN
KAMPONG UJUNG LIMUS
KECAMATAN SIMPANG KANAN
...............................
20,660,809
20,660,809
28,520,809
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
Bidang :
Kegiatan :
Waktu Pelaksanaan :
Sumber Dana :
Output/Kelurahan :