PERHITUNGAN VOLUME PERERJAAN

II PEKERJAAN LANTAI II

A PEKERJAAN STRUKTUR
1 Kolom 30/30 (Tulangan Utama 6 Ǿ 12 mm, beugel Ǿ12 mm)
Jumlah = 16,00 titik
Tinggi = 3,50 m'
Panjang = 0,30 m'
Lebar = 0,30 m'
Volume = 0,30 x 3,50 x 0,30
= 0,32 m3
Total V = 16,00 x 0,32
= 5,04 m3
2 RingBalk 30/30 (Tulangan Utama 6 Ǿ 12 mm, beugel Ǿ10 mm)
Panjang = 99,50 m'
Tinggi = 0,30 m'
Lebar = 0,30 m'
Volume = 99,50 x 0,30 x 0,30
= 8,96 m3
3 Plat Lantai t = 12 cm
Volume = 1,50 x 1,50 x 0,10 = 0,23 m3
= 7,00 x 4,00
= 1,50 x 1,50 x 2,00 x 0,10
Total V = 0,23 x 2,50 = 0,56 m3

B PEKERJAAN DINDING
1 Pasangan Dinding Bata Merah (1/2 Batu)
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Total Volume = 228,00 m2
2 Pekerjaan Plesteran =
= Volume Pekerjaan Bata x 2 x
228,00 x 2= 456,00 m2

C PEKERJAAN LANTAI KERAMIK


1 Pasang keramik 60 x 60
Dihilangkan
2 Pasang Keramik Kamar mandi
Dihilangkan
3 Pasang keramik Dinding Kamar mandi
Dihilangkan

D PEKERJAAN ATAP
1 Rangka Atap Baja Ringan
Volume = Area 1 = 21,00 x 10,00 = 210,00 m2
Area 2 = 5,00 x 4,00 = 20,00 m2
Total Volume = 230,00 m2
2 Penutup Atap
Volume = Area 1 = 22,00 x 10,00 = 220,00 m2
Area 2 = 6,00 x 5,00 = 30,00 m2
250,00 m2

E PEKERJAAN PLAFOND
Volume = Area 1 = 11,00 x 10,00 = 110,00 m2
Area 2 = 7,00 x 10,00 = 70,00 m2
Total Volume = 180,00 m2
E PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Area 4 = 5,00 x 4,00 = 20,00 m2
Area 5 5,00 x 4,00 = 20,00 m2
Area 6 = 3,50 x 4,00 = 14,00 m2
Area 7 = 3,50 x 4,00 = 14,00 m2
Area 8 = 2,50 x 4,00 = 10,00 m2
Area 9 = 1,00 x 4,00 = 4,00 m2
Area 10 = 6,00 x 4,00 = 24,00 m2
Total Volume = 334,00 m2
2 Pengecatan Dinding Luar totalnya adalah
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Area 4 = 5,00 x 4,00 = 20,00 m2
Area 5 5,00 x 4,00 = 20,00 m2
Area 6 = 3,50 x 4,00 = 14,00 m2
Total Volume = 282,00 m2

G PEKERJAAN KUSEN, PINTU & JENDELA


1 Kusen Pintu P1
Dihilangkan
2 Kusen Pintu P2
Dihilangkan
3 Pintu Fremeless
Volume = 1,00 bh
4 Jendela J1
Dihilangkan
5 Jendela Alumunium
Volume = 20,95 m'
6 Pintu kamar Mandi
Dihilangkan

G PEKERJAAN MEKANIKAL & ELEKTRIKAL


1 Titik Lampu = 44,00 titik
2 Stop Kontak = 12,00 titik
3 Kabel Tufur = - m
4 Panel Box = 1,00 Bh
5 MCB = 8,00 bh
6 MCB = - bh
7 Instalasi Air Bersih 1/2" = 60,00 m
8 Instalasi Air Kotor = 48,00 m
9 Pipa Septitank = 36,00 m
10 Instalasi Pipa Air Hujan = 116,00 bh

H PEKERJAAN AKSESORIS & PENGGANTUNG


1 Kloset Jongkok = 1,00 Unit
2 Kran Air = 1,00 Bh