II PEKERJAAN LANTAI II
A PEKERJAAN STRUKTUR
1 Kolom 30/30 (Tulangan Utama 6 Ǿ 12 mm, beugel Ǿ12 mm)
Jumlah = 16,00 titik
Tinggi = 3,50 m'
Panjang = 0,30 m'
Lebar = 0,30 m'
Volume = 0,30 x 3,50 x 0,30
= 0,32 m3
Total V = 16,00 x 0,32
= 5,04 m3
2 RingBalk 30/30 (Tulangan Utama 6 Ǿ 12 mm, beugel Ǿ10 mm)
Panjang = 99,50 m'
Tinggi = 0,30 m'
Lebar = 0,30 m'
Volume = 99,50 x 0,30 x 0,30
= 8,96 m3
3 Plat Lantai t = 12 cm
Volume = 1,50 x 1,50 x 0,10 = 0,23 m3
= 7,00 x 4,00
= 1,50 x 1,50 x 2,00 x 0,10
Total V = 0,23 x 2,50 = 0,56 m3
B PEKERJAAN DINDING
1 Pasangan Dinding Bata Merah (1/2 Batu)
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Total Volume = 228,00 m2
2 Pekerjaan Plesteran =
= Volume Pekerjaan Bata x 2 x
228,00 x 2= 456,00 m2
D PEKERJAAN ATAP
1 Rangka Atap Baja Ringan
Volume = Area 1 = 21,00 x 10,00 = 210,00 m2
Area 2 = 5,00 x 4,00 = 20,00 m2
Total Volume = 230,00 m2
2 Penutup Atap
Volume = Area 1 = 22,00 x 10,00 = 220,00 m2
Area 2 = 6,00 x 5,00 = 30,00 m2
250,00 m2
E PEKERJAAN PLAFOND
Volume = Area 1 = 11,00 x 10,00 = 110,00 m2
Area 2 = 7,00 x 10,00 = 70,00 m2
Total Volume = 180,00 m2
E PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Area 4 = 5,00 x 4,00 = 20,00 m2
Area 5 5,00 x 4,00 = 20,00 m2
Area 6 = 3,50 x 4,00 = 14,00 m2
Area 7 = 3,50 x 4,00 = 14,00 m2
Area 8 = 2,50 x 4,00 = 10,00 m2
Area 9 = 1,00 x 4,00 = 4,00 m2
Area 10 = 6,00 x 4,00 = 24,00 m2
Total Volume = 334,00 m2
2 Pengecatan Dinding Luar totalnya adalah
Volume = Area 1 = 23,00 x 4,00 = 92,00 m2
Area 2 = 10,00 x 4,00 = 40,00 m2
Area 3 = 24,00 x 4,00 = 96,00 m2
Area 4 = 5,00 x 4,00 = 20,00 m2
Area 5 5,00 x 4,00 = 20,00 m2
Area 6 = 3,50 x 4,00 = 14,00 m2
Total Volume = 282,00 m2
Rizki Yustiawan