Papan Bekisting
Pasir Urug t 5 cm
Rabat Beton t 12 cm
1 mm
2,5
Bahan Koef Vol Jumlah Sat atau per btg Jml Sat
Papan Bekisting 3/20 0.030 7.02 0.07 m3 2/30 0.018 3.90 btg
Paku biasa 2" - 5" 0.200 7.02 0.47 Kg --> Paku + papan utk 3 x pakai
Upah Koef Sat Jumlah Sat
Pekerja 0.350 7.02 2.46 HOK
Tukang 0.150 7.02 1.05 HOK
D Kebutuhan Mesin Molen
Produktivitas/kemampuan alat untuk Molen 1 hr 6 m3
Volume rabat = 2.76 m3
Sewa molen = 2.76 = 0.46 hari
6
REKAPITULASI KEBUTUHAN BAHAN, ALAT DAN UPAH
Harga JUMLAH
Volume
No. Uraian Satuan satuan TOTAL
Total
(Rp) (Rp)
BAHAN
1 Semen portland 12 zak 61,000 732,000
2 Pasir Beton 1 m 3
120,000 120,000
3 Split 2/3 2 m3 200,000 400,000
4 Pasir urug 1 m 3
90,000 90,000
5 Papan Bekisting 3/20 - m3 1,400,000 -
6 Paku biasa 2" - 5" - m 3
12,000 -
7 #REF! #REF! m2 5,000 #REF!
Sub Total 1) #REF!
ALAT
1 Ember 20 bh 5,000 100,000
2 Meteran 2 bh 10,000 20,000
3 Palu 2 bh 35,000 70,000
4 Cangkul 4 bh 50,000 200,000
5 Sekop 2 bh 35,000 70,000
6 Kereta dorong 1 b 500,000 500,000
7 Sewa molen - hr 400,000 -
Sub Total 2) 960,000
UPAH
1 Pekerja 8 HOK 52,000 416,000
2 Tukang 2 HOK 60,000 120,000
Sub Total 3) 536,000
Total Biaya #REF!
RENCANA ANGGARAN BIAYA (RAB)
DESA CIWARU KECAMATAN CIWARU
TAHUN ANGGARAN 2020
No.RAB : ……...……..………………
Bidang : Pelaksanaan Pemb. Desa
Kegiatan : Pemb. Jalan Rabat Beton
Waktu Pelaksanaan : ……...… Hari kerja
Lokasi : Dusun Cisereh
Volume : 23 m'
………..,Tanggal…….,…….,…
Disetujui/mengesahkan :
Kepala Desa Pelaksana Kegiatan
(………………………………..) (………………………………..)