Bahan
Kayu Begisting 0.013 29.96 0.39 m3
Paku 0.100 9.99 1.00 kg
Upah
1. Pekerja 0.520 29.96 15.58 HOK
2. Tukang 0.260 29.96 7.79 HOK
4. PEK. COR BETON K 125 (pakai mesin) (Distarkim Kab. Tasikmlaya A. 4.1.1.2.)
Volume = 3.92 m3
Bahan
1. Semen 5.52 3.92 21.64 sak
2. Pasir Cor 0.59 3.92 2.31 m3
3. Batu pecah 2-3 0.75 3.92 2.94 m3
Upah
1. Pekerja 1.323 3.92 5.19 HOK
2. Tukang 0.189 3.92 0.74 HOK
5. KEBUTUHAN MOLEN
Sewa Molen 0.250 3.92 0.98 hari
REKAPITULASI TOS
Jenis Bahan Volume Dibulatkan
Bahan
Semen 21.64 22.00
Pasir Cor 2.31 2.00
Batu pecah/split 2.94 3.00
Cabluk 1.27 1.00
Kayu Begisting 0.39 0.00
Plastik 65.80 66.00
Paku 1.00 1.00
Alat
Sewa Molen 0.98 1.00
Upah
Pekerja 21.46 21.00
Tukang 8.53 9.00
RENCANA KEGIATAN DAN ANGGARAN
Propinsi : Jawa Barat No. RAB : 05
Kabupaten : Tasikmalaya Program : Bankeu
Kecamatan : Taraju Jenis Kegiatan : Kp. Bayongbong
Desa : Taraju Ukuran : P 70 m x 0,8 m
VOLUME Harga BIAYA (Rp)
Satuan
URAIAN Dana Satuan
Total Swadaya Swadaya Dana Desa Total
Desa (Rp)
I. Bahan
1 Semen 50 kg 22 22 sak 55,000 - 1,210,000 1,210,000
2 Pasir Cor / Beton 2 2 m3 300,000 - 600,000 600,000
3 Batu pecah/split 2-3 3 3 m3 300,000 - 900,000 900,000
4 Kayu Begisting kelas III 0 0 m3 1,600,000 - - -
5 Plastik 66 66 m2 5,000 - 330,000 330,000
6 Paku ragam 1 1 kg 15,000 - 15,000 15,000
Sub Total 1) - 3,055,000 3,055,000
II. Alat
1 Papan Proyek 1 0 unit 150,000 - - 150,000
2 Prasasti 1 0 unit 300,000 - - 300,000
3 Mobilisasi Molen 1 1 ls 300,000 - 300,000 300,000
4 Sewa Molen 1 1 hari 350,000 - 350,000 350,000
5 Operator 1 1 hari 85,000 - 85,000 85,000
6 Ember Cor 10 10 buah 15,000 - 150,000 150,000
375,000
Sub Total 2) - 885,000 1,335,000
III. Upah
1 Pekerja 21 21 HOK 65,000 - 1,365,000 1,365,000
2 Tukang 9 9 HOK 85,000 - 765,000 765,000
Sub Total 4) - 2,130,000 2,130,000
TOTAL 6,813,265
......... .............
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Barat No. RAB : 05
Kabupaten : Tasikmalaya Program : Bankeu
Kecamatan : Taraju Jenis Kegiatan : Kp. Bayongbong
Desa : Taraju Ukuran : P 70 m x 0,8 m
VOLUME Harga BIAYA (Rp)
Satuan
URAIAN Dana Satuan
Total Swadaya Swadaya Dana Desa Total
Desa (Rp)
I. Bahan
1 Semen 50 kg 24 0 24 sak 61,700 - 1,480,800 1,480,800
2 Pasir Cor / Beton 2 0 2 m3 336,700 - 673,400 673,400
3 Batu pecah/split 2-3 3 0 3 m3 336,700 - 1,010,100 1,010,100
4 Kayu Begisting kelas III 1.0 0 1 m3 1,795,900 - 1,795,900 1,795,900
5 Plastik 66 0 66 m2 5,600 - 369,600 369,600
6 Paku ragam 1 0 1 kg 16,800 - 16,800 16,800
Sub Total 1) - 5,346,600 5,346,600
II. Alat
1 Papan Proyek 1 0 1 unit 168,400 - 168,400 168,400
2 Prasasti 1 0 1 unit 336,700 - 336,700 336,700
3 Mobilisasi Molen 4 0 4 ls 336,700 - 1,346,800 1,346,800
4 Sewa Molen 4 0 4 hari 392,900 - 1,571,600 1,571,600
5 Operator 4 0 4 hari 95,400 - 381,600 381,600
6 Ember Cor 10 0 10 buah 16,800 - 168,000 168,000
7 Angkong 2 0 2 Bh 420,900 841,800 841,800
Sub Total 2) - 4,814,900 4,814,900
III. Biaya Umum
1 LPJ & Pelaporan 1 0 1 Ls 208,500 208,500 208,500
Sub Total 3) 208,500 208,500
IV. Upah
1 Pekerja 21 0 21 HOK 65,000 - 1,365,000 1,365,000
2 Tukang 9 0 9 HOK 85,000 - 765,000 765,000
Sub Total 4) - 2,130,000 2,130,000
12,500,000
TOTAL
ANDRIANA ....................
RENCANA PELAKSANAAN PEMBANGUNAN JALAN LINGKUNGAN
DESA TARAJU
TAHUN ANGGARAN 2021
KECAMATAN TARAJU - KABUPATEN TASIKMALAYA
Rp 3,055,000 46.86 1.4 2.3 4.7 4.7 4.7 5.6 4.7 4.7 4.7 4.7 2.3 2.3
Pengadaan Bahan 3 5 10 10 10 12 10 10 10 10 5 5
1
Pelaksanaan
Rp 1,335,000 20.48 1.02 0.6 4.10 3.48 3.69 3.69 2.25 1.02 1.02
Pengadaan Alat
2
Pelaksanaan
3 3 20 17 18 18 11 5 5
Rp 2,130,000 32.67 0.7 1.0 4.9 4.9 4.9 4.9 4.9 3.3 1.6 1.6
Pembayaran Upah 2 3 15 15 15 15 15 10 5 5
3
Pelaksanaan
............. ...........
DAFTAR HARGA UPAH, BAHAN DAN ALAT
PEKERJAAN : Pembangunan Jalan Lingkungan
DESA : Taraju
LOKASI : ................
II. BAHAN
1 Batu Belah m3 - 275,000 -
2 Pasir Pasang m3 - 200,000 -
3 Pasir cor m3 - 300,000 -
4 Batu Bata Merah bh - 700 -
5 Semen sak - 55,000 -
6 Semen Warna Kg - 85,000 -
7 Sirtu m3 - 100,000 -
8 Batu Pecah 1/2 ( split ) m3 - 300,000 -
9 Batu Pecah 2/3 ( split ) btg - 300,000 -
10 Plastik m2 - 5,000 -
11 Besi Beton Ø 6 mm btg - 22,500 -
12 Besi Beton Ø 10 mm btg - 70,000 -
13 Besi Beton Ø 12 mm btg - 125,000 -
14 Kawat Beton kg - 25,000 -
15 Kayu Papan (bekisting) Kelas III m3 - 1,600,000 -
16 Besi Pipa Galvanis 2" (3,60mm) btg/6m - 600,500 -
17 Cat Besi kg - 58,000
18 Bambu btg - 10,000 -
19 Paku 1-3 cm kg - 16,700 -
20 Paku 5-7 cm kg - 13,000 -
21 Paku 7-10 cm kg - 13,000 -
22 Paku 5-10 cm kg - 15,000 -
23 Paku 12 cm kg - 16,000 -
24 Balok Kayu Kelas II 6/12 ( kusen ) m3 - 2,500,000 -
25 Balok Kayu Lokal 6/12-8/12 ( atap ) m3 - 2,500,000 -
26 Balok Kayu Lokal ( kaso 5/7 - 5/10 ) m3 - 2,500,000 -
27 Kayu Papan (Kelas 1 atau Kelas II) btg - 24,000 -
28 Besi Plat Penguat Kuda2 Tebal 5 cm kg - 18,000 -
29 Kaca Polos 3 mm m2 - 65,000 -
30 Keramik 30/30 dus - 55,000 -
31 Keramik 20/20 (Anti Slip) Lantai KM dus - 55,000 -
32 Keramik 20/20 Dinding KM dus - 55,000 -
33 Glass Block 9 mm (20 x 20) bh - 110,000 -
34 Rooster 10 x 20 bh - 6,000 -
35 Batu Alam (Batu Tempel Hitam) m2 - 120,000 -
36 Genteng Pelentong bh - 2,000 -
37 Genteng Bubung m' - 4,700 -
38 Plafon Gypsum 120 x 240 cm (tbl 9 mm) lbr - 63,000 -
39 ListProfil Gypsum (5 cm) m' - 5,300 -
40 Plamir kg - 20,000 -
41 Cat Meni Kayu kg - 24,000 -
42 Cat Tembok kg - 22,000 -
43 Cat Kayu kg - 50,000 -
44 Gagang Pintu bh - 150,000 -
45 Kunci Tanam Biasa bh - 13,000 -
46 Engsel Pintu bh - 16,900 -
47 Engsel Jendela bh - 27,500 -
48 Hak Kait Angin bh - 40,000 -
49 rooster bh - 5,000 -
50 Pipa AW 3 " lt - 110,000 -
51 Belokan 3 " bh - 15,000 -
52 Pipa AW 1/2 " lt - 14,500 -
53 Pipa Belokan 1/2 " bh - 12,000 -
54 Kran Air bh - 62,500 -
55 Kitchen Zink Stanless (1 Lobang) bh - 200,000 -
56 Bak Fiber Glass bh - 275,000 -
57 Closet Duduk bh - 270,000 -
58 Floor and Drain bh - 27,500 -
59 Minyak Bekisting ltr - 8,000 -
60 Stop Kontak Ganda (Broco ) bh - 14,000 -
61 Stop Kontak Tunggal (Broco ) bh - 12,000 -
62 Out Blow Steker (Broco ) bh - 43,500 -
63 Fitting/Mangkok Lampu (Broco) bh - 11,000 -
64 Lampu Hemat (Led Philips 7 Watt) bh - 65,000 -
65 Kabel NYA (2 x 2,5) mm rol/100 m' - 368,000 -
66 T Doss (Kotak Sambungan) 1/2 " bh - 3,500 -
67 Pengencer ( Thiner ) Kg - 20,000 -
68 Lem Kayu Kg - 7,000 -
69 Sealen Kg - 10,000 -
70 Amplas lbr - 3,500 -
71 Kuas bh - 12,000 -
III. A L A T
1 Sekop bh - - 75,000
2 Cangkul bh - - 125,000
3 Garpu bh 150,000
4 Benang bh - - 6,000
5 Kuas bh - - 12,000
6 Ember bh - - 15,000
7 Saringan Pasir bh - - 100,000
III. A L A T
1 Papan Nama Kegiatan bh - - 150,000
2 Sewa Mesin Molen 0.125m3 /hari - - 350,000
3 Sekop bh - - 75,000
4 Cangkul bh - - 75,000
5 Garpu/Linggis bh 150,000
6 Benang bh - - 5,000
7 Kuas bh - - 12,000
8 Kape bh 8,000
9 Ember bh - - 10,000
10 Saringan Pasir bh - - 100,000
11 Prasasti bh - - 300,000
12 Angkong bh - 535000 375000
............
DAFTAR HARGA UPAH, BAHAN DAN ALAT
PEKERJAAN : Pembangunan Tembok Penahan Tanah
DESA : .............
LOKASI :.................
77 Kansteen m 54,000
III. A L A T
1 Papan Proyek bh - 40,000 100,000
2 Prasasti bh - 160,000 350,000
3 Sewa Mesin Molen 0.125 m3 /hari - 325,000 350,000
4 Angkong bh - 535,000 375,000
5 Sekop bh - 100,000 75,000
6 Cangkul bh - 65,000 125,000
7 Garpu/Linggis bh - 70,000 150,000
8 Benang bh - 4,000 6,000
9 Kuas bh - 10,000 12,000
10 Kape bh - 5,000 8,000
11 Ember bh - 15,000 15,000
12 Saringan Pasir bh - 15,000 100,000
13 Mobilisasi Tandem Roller 6-8 T Ls - - 1,950,000
14 Sewa Genset Ls - - 700,000
15 Compressor 4000-6500 l/m Ls - - 150,000 8 Jam /Hari
16 Tandem Roller 6-8 T hr - - 500,000 8 Jam /Hari
17 Asphalt Sprayer hr - - 250,000 8 Jam /Hari
19 Alat Bantu Ls - - 1,000,000
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA ...
JENIS KEGIATAN
PEMBANGUNAN TPT
LOKASI
.............
JUDUL GAMBAR
DETAIL TPT
DIBUAT OLEH
..........
DIPERIKSA OLEH
PDPKEC. TARAJU
.........
DISETUJUI OLEH
KEPALA DESA ...
.......
Lembar 1 Dari 1
PROPINSI JAWA BARAT
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA ...
JENIS KEGIATAN
PEMBANGUNAN JALAN DAN
SARANA PELENGKAP
LOKASI
.............
JUDUL GAMBAR
DETAIL TPT
DIBUAT OLEH
.................
DIPERIKSA OLEH
PDPKEC. TARAJU
.........
DISETUJUI OLEH
KEPALA DESA ...
.......
Lembar 1 Dari
PROPINSI JAWA BARAT
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA TARAJU
250 Cm
JENIS KEGIATAN
PEMBANGUNAN TPT LAPANG
BALEKER
LOKASI
DESA TARAJU
JUDUL GAMBAR
DIBUAT OLEH
Kaur Perencanaan
111 Cm
.........
DISETUJUI OLEH
KEPALA DESA TZRZJU
Andriana
Lembar 2 Dari
PROPINSI JAWA BARAT
0,8 m
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA TARAJU
JENIS KEGIATAN
7 Cm
Pembangunan Rabat Beton
LOKASI
Kp. Bayongbong
JUDUL GAMBAR
Detail Rabat
DIBUAT OLEH
......................
DIPERIKSA OLEH
PDPKEC. TARAJU
ANDRIANA
Lembar 3 Dari
PROPINSI JAWA BARAT
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA ...
JENIS KEGIATAN
PEMBANGUNAN JALAN DAN
SARANA PELENGKAP
LOKASI
.............
JUDUL GAMBAR
POTONGAN A-A
DIBUAT OLEH
..........
DIPERIKSA OLEH
PDPKEC. TARAJU
.........
DISETUJUI OLEH
KEPALA DESA ...
.......
Lembar 4 Dari
PROPINSI JAWA BARAT
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA ...
JENIS KEGIATAN
PEMBANGUNAN JALAN DAN
SARANA PELENGKAP
LOKASI
.............
JUDUL GAMBAR
POTONGAN A-A
DIBUAT OLEH
..........
DIPERIKSA OLEH
PDPKEC. TARAJU
.........
DISETUJUI OLEH
KEPALA DESA ...
.......
Lembar 5 Dari
PROPINSI JAWA BARAT
KABUPATEN TASIKMALAYA
KECAMATAN TARAJU
DESA ...
JENIS KEGIATAN
PEMBANGUNAN JALAN DAN
SARANA PELENGKAP
LOKASI
.............
JUDUL GAMBAR
POTONGAN A-A
DIBUAT OLEH
..........
DIPERIKSA OLEH
PDPKEC. TARAJU
.........
DISETUJUI OLEH
KEPALA DESA ...
.......
Lembar 6 Dari