( EE )
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR
PEKERJAAN : PENATAAN LANDSCAPE PERPUSTAKAAN DAN ARSIP DAERAH KAB. KEPULAUAN YAPEN
LOKASI : SERUI, KAB. KEPULAUAN YAPEN
T/A : 2012
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )
A. PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Proyek 1.00 bh 0.00
2 Pembersihan Lokasi Proyek 841.00 m2 11,224.00 9,439,384.00
3 Pas. Bouwplank 223.60 m' 59,541.06 13,313,381.02
4 Dokumentasi Proyek 1.00 ls 0.00
Sub Total
B. PEKERJAAN PENATAAN HALAMAN
1 Urugan Pasir 168.20 m3 321,558.40 54,086,122.88
2 Pas. Paving Blok 712.00 m2 0.00
3 Cor Kerb 4.28 m3 0.00
4 Galian Tanah Saluran Air Hujan 6.00 m3 0.00
5 Pas. Batu Tela Saluran Air hujan Camp. 1 : 2 40.00 m2 0.00
6 Pas. Batu Tela Pembatas Taman Camp. 1 : 3 12.08 m2 0.00
7 Plesteran Dinding Saluran Air Hujan Camp. 1 : 2 80.00 m2 0.00
8 Plesteran Dinding Pembatas taman Camp. 1 : 3 151.00 m2 0.00
9 Acian Dinding Saluran Air Hujan dan Pembatas Taman 231.00 m2 0.00
10 Cor Lantai Saluran Air Hujan 0.50 m3 0.00
11 Pas. Batu tela kaki kursi taman 3.00 m2 0.00
12 Cor plat tempat duduk dan sandaran kursi taman 0.86 m3 0.00
13 Plesteran kursi taman 7.80 m2 0.00
14 Acian kursi taman 7.80 m2 0.00
Sub Total
C. PEKERJAAN RUANG PERTEMUAN
1 Pekerjaan Tanah Dan Pondasi
Galian tanah pondasi 45.00 m3 44,896.00 2,020,320.00
Urugan pasir bawah pondasi 2.25 m3 321,558.40 723,506.40
Pas. Batu kosong 6.75 m3 500,005.46 3,375,036.88
Pas. Pondasi camp. 1 : 3 21.00 m3 1,045,260.95 21,950,479.95
Urugan kembali 1/4 galian 11.25 m3 14,965.33 168,360.00
Urugan tanah bawah lantai 14.98 m3 320,436.00 4,798,529.10
Urugan pasir bawah lantai 3.00 m3 321,558.40 963,067.41
2 Pekerjaan Beton Dan Dinding
Pas. Sloof praktis 15/20 1.50 m3 0.00
Pek. Kolom 20/20 1.92 m3 0.00
Pek. Kolom praktis 10/10 0.40 m3 0.00
Pek. Ringbalk praktis 10/20 2.44 m3 0.00
Pek. Dak beton 2.60 m3 0.00
Pas. Dinding batu tela camp. 1 : 3 104.40 m2 0.00
Plesteran dinding camp. 1 : 3 223.15 m2 0.00
Acian dinding 223.15 m2 0.00
Pas. Keramik dinding KM/WC uk. 20x25 18.00 m2 0.00
3 Pekerjaan Lantai
Cor lantai kerja tebal 5 cm 3.00 m3 0.00
Pas. Keramik lantai uk. 40x40 55.40 m2 0.00
Pas. Keramik latai uk. 20x20 4.50 m2 0.00
4 Pekerjaan Kayu Dan Atap 0.00
Pek. Kuda-kuda kayu kls. I 5/10 1.99 m3 0.00
Pek. Gording kayu kls. II 1.53 m3 0.00
Pek. Lesplank kayu kls. I 20.52 m2 0.00
Pas. Atap seng BJLS 30 127.59 m2 0.00
Pas. Nok seng plat BJLS 30 15.17 m2 0.00
Pek. Ornamen kayu kls. I 5/10 0.97 m3 0.00
Pas. Ornamen kayu kls. I 2/10 0.37 m3 0.00
Pek. Kusen kayu kls. I 5/10 0.10 m3 0.00
Pas. Pintu panil kayu kls. I 2.94 m2 0.00
Pas. Plafond+rangka kayu kls. II 99.00 m2 0.00
5 Pek. Sanitair
Pas. Closed jongkok 2.00 bh 0.00
Pas. Pipa air bersih pipa PVC 1/2" 12.00 m' 0.00
Pas. Kran air 1/2" 2.00 bh 0.00
Pas. Floor drain 2.00 bh 0.00
Pas. Pipa pembuangan air kotor PVC 3" 6.00 m' 0.00
Pas. Pipa septic tank PVC 4" 12.00 m' 0.00
Pek. Septic tank 1.00 unit 0.00
6 Pek. Penggantung Dan Asesoris
Pas. Engsel pintu panil 6.00 bh 0.00
Pas. Kunci 2 slaag 2.00 bh 0.00
7 Pekerjaan Pengecatan
Pek. cat dinding 223.15 m2 0.00
Pek. cat plafond 99.00 m2 0.00
Pek. cat meni kayu 367.84 m2 0.00
Pek. Cat kayu 367.84 m2 0.00
8 Pekerjaan Instalasi Listrik
Pas. Stop kontak 2.00 ttk 0.00
Pas. Saklar ganda 2.00 ttk 0.00
Pas. Saklar tunggal 1.00 ttk 0.00
Pas. Lampu TL 2.00 ttk 0.00
Pas. Lampu XL 3.00 ttk 0.00
Sub Total
D. PEKERJAAN GASEBO ( 3 BUAH )
1 Pekerjaan Tanah Dan Pondasi
Galian tanah pondasi 21.60 m3 0.00
Urugan pasir bawah pondasi 1.08 m3 0.00
Pas. Batu kosong 3.24 m3 0.00
Pas. Pondasi camp. 1 : 3 10.08 m3 0.00
Urugan kembali 1/4 galian 5.40 m3 0.00
Urugan tanah bawah lantai 7.20 m3 0.00
Urugan pasir bawah lantai 0.60 m3 0.00
2 Pekerjaan Beton Dan Dinding
Pas. Sloof praktis 15/20 0.72 m3 0.00
Pek. Meja beton bertulang 0.11 m3 0.00
Pas. batu tela untuk tangga camp. 1 : 3 0.75 m3 0.00
Pas. Batu tela kaki meja camp. 1 : 3 0.11 m3 0.00
Plesteran dinding camp. 1 : 3 18.84 m2 0.00
Acian dinding 18.84 m2 0.00
3 Pekerjaan Lantai
Cor lantai kerja tebal 5 cm 0.60 m3 0.00
Pas. Keramik lantai uk. 30x30 12.00 m2 0.00
4 Pekerjaan Kayu Dan Atap
Pek. Kolom kayu kls. I 10/10 0.12 m3 0.00
Pek. Mur plat kayu kls. I 5/10 0.12 m3 0.00
Pek. Kuda-kuda kayu kls. I 5/10 0.66 m3 0.00
Pek. Gording kayu kls. II 0.48 m3 0.00
Pek. Lesplank kayu kls. I 14.26 m2 0.00
Pas. Atap seng BJLS 30 58.32 m2 0.00
Pas. Nok seng plat BJLS 30 15.02 m2 0.00
Pek. Ornamen kayu kls. I 5/10 0.87 m3 0.00
Pas. Ornamen kayu kls. I 2/10 0.09 m3 0.00
Pas. Plafond+rangka kayu kls. II 27.00 m2 0.00
7 Pekerjaan Pengecatan
Pek. cat dinding 18.84 m2 0.00
Pek. cat plafond 27.00 m2 0.00
Pek. cat meni kayu 186.81 m2 0.00
Pek. Cat kayu 186.81 m2 0.00
Sub Total
E. PEKERJAAN POS PENITIPAN BARANG UK. 2x3 M
1 Pekerjaan Tanah Dan Pondasi
Galian tanah pondasi 9.00 m3 0.00
Urugan pasir bawah pondasi 0.45 m3 0.00
Pas. Batu kosong 1.35 m3 0.00
Pas. Pondasi camp. 1 : 3 4.20 m3 0.00
Urugan kembali 1/4 galian 2.25 m3 0.00
Urugan tanah bawah lantai 2.00 m3 0.00
Urugan pasir bawah lantai 0.50 m3 0.00
2 Pekerjaan Beton Dan Dinding
Pas. Sloof praktis 15/20 0.30 m3 0.00
Pek. Kolom praktis 10/10 0.24 m3 0.00
Pek. Ringbalk praktis 10/20 0.30 m3 0.00
Pas. Dinding batu tela camp. 1 : 3 31.00 m2 0.00
Pas. Retaining wall batu tela camp. 1 : 3 2.72 m2 0.00
Plesteran dinding camp. 1 : 3 64.72 m2 0.00
Acian dinding 64.72 m2 0.00
3 Pekerjaan Lantai
Cor lantai kerja tebal 5 cm 0.50 m3 0.00
Plesteran lantai camp. 1 : 3 9.99 m2 0.00
Acian lantai 9.99 m2 0.00
4 Pekerjaan Kayu Dan Atap
Pek. Kuda-kuda kayu kls. I 5/10 0.24 m3 0.00
Pek. Gording kayu kls. II 0.20 m3 0.00
Pek. Lesplank kayu kls. I 5.33 m2 0.00
Pas. Atap seng BJLS 30 24.68 m2 0.00
Pas. Nok seng plat BJLS 30 5.47 m2 0.00
Pek. Ornamen kayu kls. I 5/10 0.05 m3 0.00
Pas. Ornamen kayu kls. I 2/10 0.02 m3 0.00
Pas. Plafond+rangka kayu kls. II 17.39 m2 0.00
7 Pekerjaan Pengecatan
Pek. cat dinding 64.72 m2 0.00
Pek. cat plafond 17.39 m2 0.00
Pek. cat meni kayu 42.96 m2 0.00
Pek. Cat kayu 42.96 m2 0.00
Sub Total
D. PEKERJAAN POS PEMERIKSAAN BARANG UK. 2x2 M
1 Pekerjaan Tanah Dan Pondasi
Galian tanah pondasi 7.20 m3 0.00
Urugan pasir bawah pondasi 0.36 m3 0.00
Pas. Batu kosong 1.08 m3 0.00
Pas. Pondasi camp. 1 : 3 3.36 m3 0.00
Urugan kembali 1/4 galian 1.80 m3 0.00
Urugan tanah bawah lantai 1.46 m3 0.00
Urugan pasir bawah lantai 0.36 m3 0.00
2 Pekerjaan Beton Dan Dinding
Pas. Sloof praktis 15/20 0.24 m3 0.00
Pek. Kolom praktis 10/10 0.24 m3 0.00
Pek. Ringbalk praktis 10/20 0.20 m3 0.00
Pas. Dinding batu tela camp. 1 : 3 30.32 m2 0.00
Pas. Retaining wall batu tela camp. 1 : 3 2.32 m2 0.00
Plesteran dinding camp. 1 : 3 62.96 m2 0.00
Acian dinding 62.96 m2 0.00
3 Pekerjaan Lantai
Cor lantai kerja tebal 5 cm 0.36 m3 0.00
Plesteran lantai camp. 1 : 3 7.29 m2 0.00
Acian lantai 7.29 m2 0.00
4 Pekerjaan Kayu Dan Atap
Pek. Kuda-kuda kayu kls. I 5/10 0.22 m3 0.00
Pek. Gording kayu kls. II 0.16 m3 0.00
Pek. Lesplank kayu kls. I 4.75 m2 0.00
Pas. Atap seng BJLS 30 19.44 m2 0.00
Pas. Nok seng plat BJLS 30 5.01 m2 0.00
Pas. Plafond+rangka kayu kls. II 9.00 m2 0.00
7 Pekerjaan Pengecatan
Pek. cat dinding 62.96 m2 0.00
Pek. cat plafond 9.00 m2 0.00
Pek. cat meni kayu 32.30 m2 0.00
Pek. Cat kayu 32.30 m2 0.00
Sub Total
SURVEY HARGA UPAH DAN BAHAN / MATERIAL
( Rp.)
1 2 3 4
A. MATERIAL LOKAL :
GALIAN C / BATU CETAK
1 Pasir Beton M3 287,500.00
2 Pasir Pasang M3 319,000.00
3 Pasir plester halus / dari Aromarea M3 660,000.00
3 Koral / kerikil beton M3 253,000.00
4 Batu Kali M3 253,000.00
5 Batu karang / gunung M3 253,000.00
6 Pasir / sirtu urug M3 253,000.00
7 Karang urug M3 253,000.00
8 Tanah urug M3 253,000.00
9 Batu Pecah 3 - 5 Cm M3 583,000.00
10 Batu Pecah 2 - 3 Cm M3 715,000.00
11 Batu Pecah 1 - 2 Cm M3 715,000.00
12 Batu Tela 17 x 24 x 7 cm Bh 2,915.00
13 Paving Block segi 6 (Ø 20) Cm tebal 5 Cm Bh 4,895.00
KAYU
1 Kayu balok / papan tinang M3 1,815,000.00
2 Kayu balok / papan besi (Klas I) M3 4,828,000.00
3 Kayu balok / papan matoa (Klas II) M3 2,255,000.00
KERAMIK / PORSELIN
1 Keramik 20 X 25 BH 5,462.00
2 Keramik 20 X 20 BH 2,653.20
3 Keramik 40 X 40 ROMAN BH 13,855.00
4 Washtavel INA & aksesoris + Cermin BH 940,500.00
5 Washtavel Aluminium ( 2 Lobang ) & aksesoris BH 708,944.00
6 Kloset Duduk INA & aksesoris BH 1,930,500.00
7 Floor Drain KM/WC BH 11,894.40
8 Floor Drain Bak Air BH 11,894.40
9 Kloset duduk / mono block & aksesoris BH 2,959,440.00
KAYU LAPIS / DINDING & PLAFOND
1 Tripleks Tebal 3 MM Lbr 78,833.33
2 Tripleks Tebal 4 MM Lbr 100,833.33
3 Teak Wood 4mm Lbr 191,666.67
4 Playwood 4 MM Lbr 145,666.67
A T A P
1 Multi Roof / Metal Roof LBR 61,600.00
2 Nok Multi Roof / Metal Roof LBR 67,760.00
3 Talang Paralon Dia. 4" M' 27,544.00
4 "T" Paralon BH 19,294.00
10 Aluminium Foil M2 55,000.00
C A T /MINYAK
1 Cat Kilap Kayu KG 41,394.40
2 Cat Besi KG 41,394.40
3 Teak Oil KG 41,394.40
4 Vernis Ltr 56,734.40
5 Minyak Cat LTR 38,775.00
6 Meni kayu KG 35,475.00
7 Cat Dinding / Tembok KG 16,775.00
8 Dempul KG 35,475.00
9 Amplas Kayu LBR 5,994.40
10 Lem kayu KG 23,600.00
11 Plamur kayu KG 29,594.40
INSTALASI LAMPU
1 Lampu TL 20 Watt BH 18,172.00
2 Box Lampu TL 10 Watt BH 35,872.00
3 Box Lampu TL 20 Watt BH 55,932.00
4 Stop Kontak BH 33,275.00
5 Sekring Kas 2 Group BH 59,472.00
6 Kabel NGA M' 7,975.00
7 Pipa Paralon 1/4 " M' 8,200.00
8 Saklar BH 33,275.00
9 Isolator BH 16,000.00
10 Instalasi TTK 71,775.00
PEKERJAAN PERSIAPAN
( Edisi Revisi SNI 03-2835-2002)
I. PEKERJAAN TANAH
( SNI DT 91-0006-2007)
Bahan; 6.29.1
0.270 M3 Kayu Kls III 1,815,000.00 490,050.00
2.000 Kg Paku 5 Cm - 12 Cm 26,675.00 53,350.00
0.600 Ltr Minyak Bekisting 4,130.00 2,478.00
210.000 Kg Besi beton polos 28,799.00 6,047,790.00
3.000 Kg Kawat beton 32,487.00 97,461.00
430.000 Kg Sement Portland 2,076.38 892,841.25
0.516 M3 Pasir Beton 287,500.00 148,350.00
0.690 M3 Kerikil 253,000.00 174,570.00
(1) 812,970.00 7,093,920.25 7,906,890.25
Tenaga ; 6.29.2
5.650 OH Pekerja 56,120.00 317,078.00
0.275 OH Tukang Batu 89,792.00 24,692.80
1.560 OH Tukang Kayu 89,792.00 140,075.52
1.400 OH Tukang Besi 89,792.00 125,708.80
0.323 OH Kepala Tukang 101,016.00 32,628.17
0.283 OH Mandor 112,240.00 31,763.92
(2) 671,947.21 671,947.21
Bahan; 6.30.1
0.400 M3 Kayu Kls III 1,815,000.00 726,000.00
4.000 Kg Paku 5 Cm - 12 Cm 26,675.00 106,700.00
2.000 Ltr Minyak Bekisting 4,130.00 8,260.00
262.500 Kg Besi beton polos 28,799.00 7,559,737.50
4.500 Kg Kawat beton 32,487.00 146,191.50
430.000 Kg Sement Portland 2,076.38 892,841.25
0.516 M3 Pasir Beton 287,500.00 148,350.00
0.690 M3 Kerikil 253,000.00 174,570.00
0.150 M3 Kayu Kelas II balok 2,255,000.00 338,250.00
3.500 Lbr Plywood 9 mm 85,400.00 298,900.00
20.000 Btg Dolken Kayu Galam, Ø (8-10) Cm 50,833.33 1,016,666.60
Panjang 4 mm
(1) 2,403,836.60 9,012,630.25 11,416,466.85
Tenaga ; 6.30.2
7.050 OH Pekerja 56,120.00 395,646.00
0.275 OH Tukang Batu 89,792.00 24,692.80
1.650 OH Tukang Kayu 89,792.00 148,156.80
2.100 OH Tukang Besi 89,792.00 188,563.20
0.403 OH Kepala Tukang 101,016.00 40,709.45
0.353 OH Mandor 112,240.00 39,620.72
(2) 837,388.97 837,388.97
Bahan; 6.31.1
0.320 M3 Kayu Kls III 1,815,000.00 580,800.00
3.200 Kg Paku 5 Cm - 12 Cm 26,675.00 85,360.00
1.600 Ltr Minyak Bekisting 4,130.00 6,608.00
210.000 Kg Besi beton polos 28,799.00 6,047,790.00
3.000 Kg Kawat beton 32,487.00 97,461.00
430.000 Kg Sement Portland 2,076.38 892,841.25
0.516 M3 Pasir Beton 287,500.00 148,350.00
0.690 M3 Kerikil 253,000.00 174,570.00
0.140 M3 Kayu Kelas II balok 2,255,000.00 315,700.00
2.800 Lbr Plywood 9 mm 85,400.00 239,120.00
16.000 Btg Dolken Kayu Galam, Ø (8-10) Cm 50,833.33 813,333.28
Panjang 4 mm
(1) 2,032,753.28 7,369,180.25 9,401,933.53
Tenaga ; 6.31.2
6.350 OH Pekerja 56,120.00 356,362.00
0.275 OH Tukang Batu 89,792.00 24,692.80
1.650 OH Tukang Kayu 89,792.00 148,156.80
1.400 OH Tukang Besi 89,792.00 125,708.80
0.333 OH Kepala Tukang 101,016.00 33,638.33
0.318 OH Mandor 112,240.00 35,692.32
(2) 724,251.05 724,251.05
Bahan; 6.24.1
35.000 Bh Batu Tela 2,915.00 102,025.00
14.000 Kg Semen portland 2,076.38 29,069.25
0.032 M3 Pasir Pasang 319,000.00 10,208.00
(1) 112,233.00 29,069.25 141,302.25
Tenaga ; 6.24.2
0.300 OH Pekerja 56,120.00 16,836.00
0.150 OH Tukang Batu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.015 OH Mandor 112,240.00 1,683.60
(2) 33,503.64 33,503.64
V. PEKERJAAN PLESTERAN
( SNI DT 91-0010-2007)
Bahan; 6.2.1
10.224 Kg Semen Portland 2,076.38 21,228.86
0.020 M3 Pasir Pasang 660,000.00 13,200.00
(1) 13,200.00 21,228.86 34,428.86
Tenaga ; 6.2.2
0.300 OH Pekerja 56,120.00 16,836.00
0.150 OH Tukang Batu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.010 OH Mandor 112,240.00 1,122.40
(2) 32,942.44 32,942.44
Bahan; 6.3.1
7.776 Kg Semen Portland 2,076.38 16,145.89
0.023 M3 Pasir Halus 660,000.00 15,180.00
(1) 15,180.00 16,145.89 31,325.89
Tenaga ; 6.3.2
0.300 OH Pekerja 56,120.00 16,836.00
0.150 OH Tukang Batu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.010 OH Mandor 112,240.00 1,122.40
(2) 32,942.44 32,942.44
Bahan; 6.38.1
0.700 Lbr Seng gelombang 3" x 6" bjls 28 92,500.00 64,750.00
0.020 Kg paku biasa 1/2" - 1" 33,275.00 665.50
(1) 65,415.50 65,415.50
Tenaga ; 6.38.2
0.120 OH Pekerja 56,120.00 6,734.40
0.060 OH Tukang Kayu 89,792.00 5,387.52
0.006 OH Kepala Tukang 101,016.00 606.10
0.006 OH Mandor 112,240.00 673.44
(2) 13,401.46 13,401.46
Bahan; 6.39.1
0.300 Lbr Seng plat 3" x 6" bjls 28 92,500.00 27,750.00
0.040 Kg paku biasa 1/2" - 1" 33,275.00 1,331.00
(1) 29,081.00 29,081.00
Tenaga ; 6.39.2
0.150 OH Pekerja 56,120.00 8,418.00
0.070 OH Tukang Kayu 89,792.00 6,285.44
0.008 OH Kepala Tukang 101,016.00 808.13
0.006 OH Mandor 112,240.00 673.44
(2) 16,185.01 16,185.01
Bahan; 6.32.1
2.041 Lbr genteng metal 61,600.00 125,714.29
0.200 Kg paku biasa 2" - 5" 33,275.00 6,655.00
(1) 132,369.29 132,369.29
Tenaga ; 6.32.2
0.200 OH Pekerja 56,120.00 11,224.00
0.100 OH Tukang Kayu 89,792.00 8,979.20
0.010 OH Kepala Tukang 101,016.00 1,010.16
0.010 OH Mandor 112,240.00 1,122.40
(2) 22,335.76 22,335.76
Bahan; 6.36.1
1.100 Bh genteng dectra bond 67,760.00 74,536.00
0.050 Kg paku biasa 1/2" - 1" 33,275.00 1,663.75
(1) 76,199.75 76,199.75
Tenaga ; 6.36.2
0.250 OH Pekerja 56,120.00 14,030.00
0.150 OH Tukang Kayu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.013 OH Mandor 112,240.00 1,459.12
(2) 30,473.16 30,473.16
Bahan; 6.2.1
1.000 Bh Kunci tanam biasa 175,000.00 175,000.00
(1) 175,000.00 175,000.00
Tenaga ; 6.2.2
0.010 OH Pekerja 56,120.00 561.20
0.500 OH Tukang Kayu 89,792.00 44,896.00
0.010 OH Kepala Tukang 101,016.00 1,010.16
0.005 OH Mandor 112,240.00 561.20
(2) 47,028.56 47,028.56
Bahan; 6.5.1
1.000 Bh Engsel pintu 53,414.67 53,414.67
(1) 53,414.67 53,414.67
Tenaga ; 6.5.2
0.015 OH Pekerja 56,120.00 841.80
0.150 OH Tukang Kayu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.00075 OH Mandor 112,240.00 84.18
(2) 15,910.02 15,910.02
Bahan; 6.9.1
1.000 Bh Kait Angin 23,914.67 23,914.67
(1) 23,914.67 23,914.67
Tenaga ; 6.9.2
0.015 OH Pekerja 56,120.00 841.80
0.150 OH Tukang Kayu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.00075 OH Mandor 112,240.00 84.18
(2) 15,910.02 15,910.02
Bahan; 6.11.1
1.000 Bh Kunci Selot 41,614.67 41,614.67
(1) 41,614.67 41,614.67
Tenaga ; 6.11.2
0.020 OH Pekerja 56,120.00 1,122.40
0.200 OH Tukang Kayu 89,792.00 17,958.40
0.020 OH Kepala Tukang 101,016.00 2,020.32
0.001 OH Mandor 112,240.00 112.24
(2) 21,213.36 21,213.36
Bahan; 6.17.1
1.100 M2 Kaca 204,050.00 224,455.00
(1) 224,455.00 224,455.00
Tenaga ; 6.17.2
0.015 OH Pekerja 56,120.00 841.80
0.150 OH Tukang Kayu 89,792.00 13,468.80
0.015 OH Kepala Tukang 101,016.00 1,515.24
0.00075 OH Mandor 112,240.00 84.18
(2) 15,910.02 15,910.02