Diketahui :
Panjang : 40.00 m'
A.
Tinggi : 2.00
Lebar Atas (La) : 0.35 Gambar :
Lebar Bawah (Lb) : 0.5 Penampang Tembok Penahan
L Penampang 1 : 0.68 Tanah
L Penampang 2 : 0.2 2.00
Tenaga Kerja
Pekerja oh 0.060 20.00 1.20
Mandor oh 0.006 20.00 0.12
Tenaga Kerja
Tukang oh 0.560 8.00 4.48
Mandor oh 0.056 8.00 0.45
Bahan
Batu belah 15/20 cm m3 1.20 35.20 42.24
Semen PC 50Kg zak 2.70 35.20 95.04
Pasir Pasang m3 0.54 35.20 19.15
Tenaga Kerja
Pekerja oh 1.500 35.20 52.80
Tukang oh 0.750 35.20 26.40
Kepala Tukang oh 0.075 35.20 2.64
Mandor oh 0.075 35.20 2.64
Bahan
Semen PC 50Kg zak 0.10 22.00 2.28
Pasir Pasang m3 0.03 22.00 0.57
Tenaga Kerja
Pekerja oh 0.300 22.00 6.60
Tukang oh 0.150 22.00 3.30
Kepala Tukang oh 0.015 22.00 0.33
Mandor oh 0.015 22.00 0.33
5 . Pemasangan 1 m2 acian
Luas Pas.Batu : (Lebar atas + overlap 20 cm) x Panjang
: 22.00 m2
Bahan
Semen PC 50Kg zak 0.07 22.00 1.43
Tenaga Kerja
Pekerja oh 0.200 22.00 4.40
Tukang oh 0.100 22.00 2.20
Kepala Tukang oh 0.010 22.00 0.22
Mandor oh 0.010 22.00 0.22
Bahan
Semen Portland 50Kg zak 98.75 99.00
Pasir Pasang m3 19.72 20.00
Batu belah 15/20cm m3 42.24 43.00
Bambu 1,5 - 2" btg 8.50 9.00
Alat
Tenaga Kerja
Pekerja Oh 69.48 70.00
Tukang Oh 31.90 32.00
Kepala Tukang Oh 3.19 4.00
Mandor Oh 3.76 4.00
1. BAHAN
1 Semen Portland 50Kg - 99.00 99.00 zak 77,000 - 7,623,000 7,623,000
2 Pasir Pasang - 20.00 20.00 m3 235,000 - 4,700,000 4,700,000
3 Batu belah 15/20cm - 43.00 43.00 m3 270,000 - 11,610,000 11,610,000
4 Bambu - 9.00 9.00 btg 15,000 - 135,000 135,000
2. ALAT
1 Cangkul - 4.00 4.00 bh 82,000 - 328,000 328,000
2 Linggis - 2.00 2.00 bh 121,000 - 242,000 242,000
3 Benang - 3.00 3.00 glg 12,000 - 36,000 36,000
4 Ember - 5.00 5.00 bh 20,000 - 100,000 100,000
5 Papan Kegiatan - 1.00 1.00 ls 150,000 - 150,000 150,000
6 Prasasti - 1.00 1.00 ls 250,000 - 250,000 250,000
3. UPAH
1 Pekerja - 70.00 70.00 OH 100,000 - 7,000,000 7,000,000
2 Tukang - 32.00 32.00 OH 120,000 - 3,840,000 3,840,000
3 Mandor - 4.00 4.00 OH 135,000 - 540,000 540,000
4. BIAYA UMUM
1 Pelaporan dan Dokumentasi - 1.00 1.00 ls 150,000 - 150,000 150,000
2 ATK - 1.00 1.00 ls 100,000 - 100,000 100,000
4 Honor TPKD - 1.00 1.00 ls 500,000 - 500,000 500,000
SUPARMAN ………………
Mengetahui/Menyetujui,
Tim Teknis Disperkimtan Tim Teknis/Pendamping Kecamatan
Catatan :
1 Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya.
2 Nilai RAB didapat dari kolom volume dari dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan.
3 Swadaya dalam bentuk lahan ditulis dalam format lain.