TAKE OFF SHEET JALAN RABAT

Jenis Kegiatan Jalan Rabat Beton Lokasi :


Volume Panjang (m') : 200 Lebar : 2.5 m' Desa :
Tebal (m') : 0.12 m'

Papan Bekisting
Pasir Urug t 5 cm
Rabat Beton t 12 cm

2,5 m

A 1 m3 BETON NON STRUKTURAL/RABAT KELAS B0(K.719)


Panjang Jalan (P) 200 meter
Lebar Jalan (L) 2.5 meter
Tebal Rabat (t) 0.12 meter
· Volume Rabat = P x L x t
= 200 x 2.5 x 0.12
= 60 m 3

Kebutuhan Bahan dan Upah


Bahan Koef Vol Jumlah Sat
Semen portland 4.431 60.00 265.86 zak
Pasir Beton 0.461 60.00 27.66 m3
Split 2/3 0.769 60.00 46.14 m3
Upah Koef Vol Jumlah Sat
Pekerja 1.846 60.00 110.76 HOK
Tukang 0.462 60.00 27.72 HOK

B Mengurug 1 M3 Pasir Urug (ABK.200.11)


Panjang Jalan (P) 200 meter
Lebar Jalan (L) 2.5 meter
Tebal Urugan (t) 0.05 meter
· Volume Urugan = P x L x t
= 200 x 2.5 x 0.05
= 25 m 3

Kebutuhan Bahan dan Upah


Bahan Koef Vol Jumlah Sat
Pasir urug 1.200 25.00 30.00 m3
Upah Koef Vol Jumlah Sat
Pekerja 0.300 25.00 7.50 HOK
TAKE OFF SHEET JALAN RABAT
Jenis Kegiatan Jalan Rabat Beton Lokasi :
Volume Panjang (m') : 200 Lebar : 2.5 m' Desa :
Tukang 0.010 25.00 0.25 HOK

C Pekerjaan Bekisting (K.710)


2 2 2 2 2

Panjang Jalan (P) 200 m'


Lebar Jalan (L) 2.50 m'
Tebal Bekisting (t) 0.12 m'
· Volume Jalan = P x 2 sisi
= 200 x 2 sisi
= 400 m' ==> Volume 1
· Vol. Delatasi = P / 2 + 1 x L
(per 2 meter) = 200 / 2 + 1 x 2.5
= 252.5 m' ==> Volume 2
· Volume Total = Vol. 1 + Vol. 2 x t
= 400 + 252.5 x 0.12
= 78.3 m2

Bahan Koef Vol Jumlah Sat atau per btg Jml Sat
Papan Bekisting 3/20 0.030 78.30 0.78 m3 2/30 0.018 43.50 btg
Paku biasa 2" - 5" 0.200 78.30 5.22 Kg --> Paku + papan utk 3 x pakai
Upah Koef Sat Jumlah Sat
Pekerja 0.350 78.30 27.41 HOK
Tukang 0.150 78.30 11.75 HOK

D Kebutuhan Mesin Molen


Produktivitas/kemampuan alat untuk Molen 1 hr 6 m3

Volume rabat = 60 m3
Sewa molen = 60 = 10 hari
6
REKAPITULASI KEBUTUHAN BAHAN, ALAT DAN UPAH

Bahan Vol Sat Sat


Semen portland 265.86 266.00 Zak
Pasir Beton 27.66 28.00 M3
Split 2/3 46.14 46.00 M3
Pasir urug 30.00 30.00 M3
Papan Bekisting 3/20 0.78 1.00 M3
TAKE OFF SHEET JALAN RABAT
Jenis Kegiatan Jalan Rabat Beton Lokasi :
Volume Panjang (m') : 200 Lebar : 2.5 m' Desa :
43.50 44.00 btg
Paku biasa 2" - 5" 5.22 5.00 Kg
Sewa molen 10.00 10.00 hr
Upah Koef Sat Sat
Pekerja 145.67 146.00 HOK
Tukang 39.72 40.00 HOK
RENCANA ANGGARAN BIAYA
(Jalan Rabat Beton)

Propinsi : Jawa Barat No. RAB : 01


Kabupaten : Jenis Kegia : Jalan Rabat Beton
Kecamatan : Lokasi :
Desa : Ukuran/dim: 500 x 2,5 meter

Harga JUMLAH
Volume
No. Uraian Satuan satuan TOTAL
Total
(Rp) (Rp)
BAHAN
1 Semen portland 266 zak 61,000 16,226,000
2 Pasir Beton 28 m 3
120,000 3,360,000
3 Split 2/3 46 m3 200,000 9,200,000
4 Pasir urug 30 m 3
90,000 2,700,000
5 Papan Bekisting 3/20 1.0 m3 1,400,000 1,400,000
6 Paku biasa 2" - 5" 5 m 3
12,000 60,000
7 Err:509 Err:509 m2 5,000 Err:509
Sub Total 1) Err:509
ALAT
1 Ember 20 bh 5,000 100,000
2 Meteran 2 bh 10,000 20,000
3 Palu 2 bh 35,000 70,000
4 Cangkul 4 bh 50,000 200,000
5 Sekop 2 bh 35,000 70,000
6 Kereta dorong 1 b 500,000 500,000
7 Sewa molen 10 hr 400,000 4,000,000
Sub Total 2) 4,960,000
UPAH
1 Pekerja 146 HOK 52,000 7,592,000
2 Tukang 40 HOK 60,000 2,400,000
Sub Total 3) 9,992,000
Total Biaya Err:509
A. Format Rencana Anggaran Biaya (RAB)

RENCANA ANGGARAN BIAYA (RAB)


DESA ........................... KECAMATAN .......................
TAHUN ANGGARAN 2016

No.RAB : ……...……..………………
Bidang : Pelaksanaan Pemb. Desa
Kegiatan : Pemb. Jalan Rabat Beton
Waktu Pelaksanaan : ……...… Hari kerja
Lokasi : ……...……..………………
Volume : 200 m'

Harga Satuan Jumlah Total Format Kebutuhan B


No. URAIAN Volume Satuan Rp Rp
1 2 3 4 5 6=5x3 No.
1 Belanja Barang dan Jasa
a. Biaya Perencanaan 1.0 Paket Rp - Rp - 1
b. Honor Panitia Pelaksana 1.0 Ls Rp - Rp - 2
c. Prasasti Kegiatan 1.0 Bh Rp - Rp - 3
d. Papan Proyek 1.0 Bh Rp - Rp - 4
e. Dokumentasi 1.0 Paket Rp - Rp - 5
f. Alat Tulis Kantor (ATK) 1.0 Paket Rp - Rp - 6
g. Pengki 10.0 Bh Rp - Rp - 8
h. Ember 10.0 Bh Rp - Rp - 9
i. Meteran 1.0 Bh Rp - Rp - 10
j. Sekop 2.0 Bh Rp - Rp - 11
k. Sewa Mesin Molen 10.0 Hari Rp - Rp - 12
l. Pekerja 146.0 Hok Rp - Rp - 16
m. Tukang 40.0 Hok Rp - Rp - 17
n.
o.
p.

Sub Total (1) Rp -


2 Belanja Modal Rp -
a. Semen portland 266.0 Zak Rp - Rp -
b. Pasir Beton 28.0 M3 Rp - Rp -
c. Split 2/3 46.0 M3 Rp - Rp -
d. Pasir urug 30.0 M3 Rp - Rp -
e. Papan Bekisting 3/20 44.0 Batang Rp - Rp -
f. Paku biasa 2" - 5" 5.0 Kg Rp - Rp -
Rp -

Sub Total (2 ) Rp -

TOTAL RAB Rp -

………..,Tanggal…….,…….,…
Disetujui/mengesahkan :
Kepala Desa Pelaksana Kegiatan
(………………………………..) (………………………………..)
Format Kebutuhan Bahan Alat Upah Untuk RAB

Uraian/Bahan Volume Satuan Harga Sat Jumlah PPN PPH Jumlah Harga + PPN+PPH Pembulata
Harga PPN+PPH Harga Sat n
Semen portland 266.0 Zak - - - - - -
Pasir Beton 28.0 M3 - - - - - -
Split 2/3 46.0 M3 - - - - -
Pasir urug 30.0 M3 - - - - - -
Papan Bekisting 3/20 44.0 Batang - - - - - -
Paku biasa 2" - 5" 5.0 Kg - - - - - -
Pengki 10.0 Bh - - - - - -
Ember 10.0 Bh - - - - - -
Meteran 1.0 Bh - - - - - -
Sekop 2.0 Bh - - - - - -
Sewa Mesin Molen 10.0 Bh - - - - - -
Pekerja 146.0 Hok - Nihil
Tukang 40.0 Hok - Nihil
Jumlah PPN + PPH Yang Harus dibayar - -
Harga Sat
RAB
-
-
-
-
-
-
-
-
-
-
-