Anda di halaman 1dari 20

BILL OF QUANTITY (BOQ)

PEKERJAAN JEMBATAN SUNGAI HOTEL HAVEN BRAWA


BRAWA - BALI

HARGA JUMLAH HARGA


No. ITEM PEKERJAAN VOL. SAT.
SATUAN (Rp.) (Rp.)

I JEMBATAN SUNGAI HOTEL HAVEN BRAWA 122,801,783


I. PERSIAPAN -

1 Biaya Design Dan Perencanaan 1.00 ls -


2 Pembersihan Lahan 1.00 ls -
3 Mobilitas Material 1.00 ls -

II. STRUKTUR JEMBATAN 122,801,783

1 Pondasi Sumuran
a Bongkar Area Senderan 2.25 m3 882,004 1,984,509
b Pembesian 1.70 m3 188,820 320,239
c Bekisting Buis beton 60 3.00 m2 267,847 803,540
d Cor Beton 1.70 m3 969,289 1,643,914

2 Pondasi angkur Block 4.00 titik 741,267 2,965,068

3 Besi WF 200 (pylon)


a Besi WF 200 6.00 btg 3,681,779 22,090,671
b Plat, baut dll 1.00 ls 2,787,830 2,787,830
c Cover Wf Dengan Papan Kayu Ulin 4.00 unit 564,478 2,257,910

4 Kabel Utama dan Asesoris


a Kabel Utama 60.00 m 208,265 12,495,900
b Angkur Block 4.00 bh 469,890 1,879,560
c Clamp Hanger + Hanger 80.00 m 306,728 24,538,240

5 Cross Girder UNP 5x10 15.00 m 231,578 3,473,667

6 Bracing Lantai WF 100 15.00 m 578,935 8,684,030

7 Decking Lantai
a Bantalan kayu bengkirai 5/7 30.00 m 61,709 1,851,270
b Papan Kayu Ulin 21.00 m2 937,250 19,682,250

8 Tali Pengaman + Pegangan Handrailling


a tali pengaman 60.00 m 7,320 439,185
b Hand railing 30.00 m2 496,800 14,904,000

Page 1 of 20
HARGA SATUAN PEKERJAAN PERSIAPAN
No. Analisa Uraian Pekerjaan Kode Satuan
HARGA SATUAN PEKERJAAN PERSIAPAN
20 m2, Pembersihan Lahan
TENAGA KERJA
Pekerja L.01 Oh
Tukang L,02 Oh
Kepla Tukang L.03 Oh
Mandor L,04 Oh

BAHAN / MATERIAL

No. Analisa Uraian Pekerjaan Kode Satuan


II. STRUKTUR JEMBATAN
1 Pondasi Sumuran
a. 1 m3, Bongkar Area Senderan
TENAGA KERJA
Pekerja Oh
Mandor Oh

BAHAN / MATERIAL/ PERALATAN


Jack Hammer Jam

No. Analisa Uraian Pekerjaan Kode Satuan

b 1 m3, Pembesian
TENAGA KERJA
Kepala tukang Oh
tukang Oh
mandor

BAHAN / MATERIAL/ PERALATAN


Besi Ulir 6D13 kg
Begel spiral D8 jarak 20 cm kg
Kawat Bendrat kg

No. Analisa Uraian Pekerjaan Kode Satuan

c 1 m2, Bekisting Buis Beton 60


TENAGA KERJA
Kepala tukang OH
tukang OH
Pekerja OH

BAHAN / MATERIAL/ PERALATAN


Kayu Kelas 3 m3
Paku 5-12 cm kg
Plywood , t=9mm kg

No. Analisa Uraian Pekerjaan Kode Satuan

d 1 m2, Cor Beton K-300


TENAGA KERJA
Pekerja OH
Tukang Batu OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Batu Belah 15-20 cm m3
Semen PC kg
Pasir Beton m3
Kerikil m3

No. Analisa Uraian Pekerjaan Kode Satuan


2 Pondasi Angkur Block
1 m3, Pondasi Angkur Block
TENAGA KERJA
Pekerja OH
Tukang OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Batu Belah 15-20 cm m3
Semen PC kg
Pasir Beton m3
Kerikil m3

No. Analisa Uraian Pekerjaan Kode Satuan


3 Baja WF 200 (pylon)
a 1 btg, Pasang Baja WF 200
TENAGA KERJA
Pekerja OH
Tukang Las OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Baja WF 200 x100 x 3.2 x 4.5 BJ=11.917 kg/m btg
Kawat Las kg
oksigen ls
upah erection ls
No. Analisa Uraian Pekerjaan Kode Satuan

b 1Ls ,Plat Baut Dll


TENAGA KERJA
Pekerja OH
Tukang Las OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Plat penyangga mur baut 5x20cm bh
Mur Baut m16 x 100mm bh

No. Analisa Uraian Pekerjaan Kode Satuan

c 1 unit, Cover Papan Kayu Ulin


TENAGA KERJA
Pekerja OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Papan Kayu ulin m2
wood filler kg
thinner Lt
amplas Lbr

No. Analisa Uraian Pekerjaan Kode Satuan


4 Kabel utama dan aksesoris
a 1 m, Kabel Utama
TENAGA KERJA
Pekerja OH
Tukang OH
Kepala Tukang OH
Mandor OH
BAHAN / MATERIAL/ PERALATAN
Kabel Baja 10mm m
Scafolding hari

No. Analisa Uraian Pekerjaan Kode Satuan

b 1 bh, Angkur Block


TENAGA KERJA
Pekerja OH
Tukang besi OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Angkur L m25 x 400 bh

No. Analisa Uraian Pekerjaan Kode Satuan

c 1 m, Clamp Hanger + Hanger


TENAGA KERJA
Pekerja OH
Tukang OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Clamp + Hanger jembatan 3 x 100 x 230 mm m
No. Analisa Uraian Pekerjaan Kode Satuan
5 Cross Girder UNP 5 x 10
a 1 m, Cross Girder UNP 50x10mm
TENAGA KERJA
Pekerja OH
Tukang Las OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Girder UNP 50x10mm m
Kawat Las ls
oksigen ls

No. Analisa Uraian Pekerjaan Kode Satuan


6 Bracing lantai WF 100
1 m, Bracing Lantai WF100
TENAGA KERJA
Pekerja OH
Tukang Las OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


WF 100 x 5 x 7 BJ=9.333 kg/m m
Kawat Las ls
oksigen ls

No. Analisa Uraian Pekerjaan Kode Satuan


7 Decking Lantai
a 1 m, Bantalan Kayu Bengkirai
TENAGA KERJA
Pekerja OH
Tukang kayu OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Kayu Bengkirai 5/7 m

No. Analisa Uraian Pekerjaan Kode Satuan

b 1 m2, Papan Lantai Kayu ulin


TENAGA KERJA
Pekerja OH
Tukang Kayu OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Papan Kayu Ulin m2
Finish Poly Urethane (PU) ltr

No. Analisa Uraian Pekerjaan Kode Satuan


8 Tali Pengaman + Handrailing
a 1 m, Tali Pengaman
TENAGA KERJA
Pekerja OH
Tukang OH
Kepala Tukang OH
Mandor OH

BAHAN / MATERIAL/ PERALATAN


Tali Tambang 10 mm m

No. Analisa Uraian Pekerjaan Kode Satuan

b 1 m2, Hand railing


TENAGA KERJA
OH
OH
OH
OH

BAHAN / MATERIAL/ PERALATAN


Hand railing tinggi=80cm +jasa (harga di JABODETABEK) m2
Koefisien Harga Satuan Jumlah Harga

100,000.00
120,000.00
120,000.00

Jumlah Tenaga Kerja

Jumlah Harga bahan


Jumlah ( A + B )
Overhead & Profit(15%)
Harga Satuan Pekerjaan

Koefisien Harga Satuan Jumlah Harga

2.2.1.4 1 ttk, Pondasi Sumu


A. TENAGA KERJA
6.670 100,000.00 667,000.00 Pekerja
0.330 120,000.00 39,600.00 Tukang
- Tukang Batu
- Mandor
Jumlah Tenaga Kerja Rp 706,600.00
B. BAHAN / MATERIAL
1.200 50,300.00 60,360.00 Beton K-300
Besi beton
Kawat Bendrat
Jumlah Harga bahan Rp 60,360.00
Jumlah ( A + B ) Rp 766,960.00
Overhead & Profit(15%) Rp 115,044.00
Harga Satuan Pekerjaan Rp 882,004.00

Koefisien Harga Satuan Jumlah Harga


6.670 - -
0.330 120,000.00 39,600.00
-
-
Jumlah Tenaga Kerja Rp 39,600.00

4.167 17,000.00 70,833.33


2.467 17,000.00 41,933.33
0.717 16,500.00 11,825.00
Jumlah Harga bahan Rp 124,591.67
Jumlah ( A + B ) Rp 164,191.67
Overhead & Profit(15%) Rp 24,628.75
Harga Satuan Pekerjaan Rp 188,820.42

Koefisien Harga Satuan Jumlah Harga

0.033 120,000.00 3,960.00


0.330 120,000.00 39,600.00
0.660 100,000.00 66,000.00
-
Jumlah Tenaga Kerja Rp 109,560.00

0.040 1,700,000.00 68,000.00


0.400 22,000.00 8,800.00
0.350 133,000.00 46,550.00
Jumlah Harga bahan Rp 123,350.00
Jumlah ( A + B ) Rp 232,910.00
Overhead & Profit(15%) Rp 34,936.50
Harga Satuan Pekerjaan Rp 267,846.50

Koefisien Harga Satuan Jumlah Harga

2.400 120,000.00 288,000.00


0.800 120,000.00 96,000.00
0.080 100,000.00 8,000.00
0.119 120,000.00 14,280.00
Jumlah Tenaga Kerja Rp 406,280.00

0.450 130,000.00 58,500.00


194.000 1,300.00 252,200.00
0.300 170,000.00 51,000.00
0.468 160,000.00 74,880.00
Jumlah Harga bahan Rp 436,580.00
Jumlah ( A + B ) Rp 842,860.00
Overhead & Profit(15%) Rp 126,429.00
Harga Satuan Pekerjaan Rp 969,289.00

Koefisien Harga Satuan Jumlah Harga

0.800 100,000.00 80,000.00


1.000 120,000.00 120,000.00
0.080 100,000.00 8,000.00
0.119 -
Jumlah Tenaga Kerja Rp 208,000.00

0.450 130,000.00 58,500.00


194.000 1,300.00 252,200.00
0.300 170,000.00 51,000.00
0.468 160,000.00 74,880.00
Jumlah Harga bahan Rp 436,580.00
Jumlah ( A + B ) Rp 644,580.00
Overhead & Profit(15%) Rp 96,687.00
Harga Satuan Pekerjaan Rp 741,267.00

Koefisien Harga Satuan Jumlah Harga

2.312 100,000.00 231,200.00 21.33333


1.512 120,000.00 181,440.00
2.000 100,000.00 200,000.00
1.000 120,000.00 120,000.00
Jumlah Tenaga Kerja Rp 732,640.00

1.000 2,431,068.00 2,431,068.00 11.917


0.596 33,000.00 19,663.05
1.000 300.00 300.00
11.917 1,500.00 17,875.50
Jumlah Harga bahan Rp 2,468,906.55
Jumlah ( A + B ) Rp 3,201,546.55
Overhead & Profit(15%) Rp 480,231.98
Harga Satuan Pekerjaan Rp 3,681,778.53
Koefisien Harga Satuan Jumlah Harga

0.050 100,000.00 5,000.00


0.050 120,000.00 6,000.00
0.060 120,000.00 7,200.00
0.050 120,000.00 6,000.00
Jumlah Tenaga Kerja Rp 24,200.00

48.000 17,000.00 816,000.00 1


48.000 33,000.00 1,584,000.00

Jumlah Harga bahan Rp 2,400,000.00


Jumlah ( A + B ) Rp 2,424,200.00
Overhead & Profit(15%) Rp 363,630.00
Harga Satuan Pekerjaan Rp 2,787,830.00

Koefisien Harga Satuan Jumlah Harga

0.500 100,000.00 50,000.00


0.500 120,000.00 60,000.00
0.050 120,000.00 6,000.00
0.005 120,000.00 600.00
Jumlah Tenaga Kerja Rp 116,600.00

3.200 110,000.00 352,000.00


0.150 35,000.00 5,250.00
0.500 30,000.00 15,000.00
0.500 4,000.00 2,000.00
Jumlah Harga bahan Rp 374,250.00
Jumlah ( A + B ) Rp 490,850.00
Overhead & Profit(15%) Rp 73,627.50
Harga Satuan Pekerjaan Rp 564,477.50

Koefisien Harga Satuan Jumlah Harga

0.500 100,000.00 50,000.00


0.800 120,000.00 96,000.00
0.050 120,000.00 6,000.00
0.005 120,000.00 600.00
Jumlah Tenaga Kerja Rp 152,600.00

1.000 27,000.00 27,000.00


1.000 1,500.00 1,500.00

Jumlah Harga bahan Rp 28,500.00


Jumlah ( A + B ) Rp 181,100.00
Overhead & Profit(15%) Rp 27,165.00
Harga Satuan Pekerjaan Rp 208,265.00

Koefisien Harga Satuan Jumlah Harga

- 100,000.00 -
0.800 120,000.00 96,000.00
0.300 120,000.00 36,000.00
0.005 120,000.00 600.00
Jumlah Tenaga Kerja Rp 132,600.00

4.000 69,000.00 276,000.00

Jumlah Harga bahan Rp 276,000.00


Jumlah ( A + B ) Rp 408,600.00
Overhead & Profit(15%) Rp 61,290.00
Harga Satuan Pekerjaan Rp 469,890.00

Koefisien Harga Satuan Jumlah Harga

0.200 100,000.00 20,000.00


0.231 120,000.00 27,720.00
0.050 120,000.00 6,000.00
0.400 120,000.00 48,000.00
Jumlah Tenaga Kerja Rp 101,720.00

1.000 165,000.00 165,000.00

Jumlah Harga bahan Rp 165,000.00


Jumlah ( A + B ) Rp 266,720.00
Overhead & Profit(15%) Rp 40,008.00
Harga Satuan Pekerjaan Rp 306,728.00

Koefisien Harga Satuan Jumlah Harga

0.200 100,000.00 20,000.00


0.400 120,000.00 48,000.00
0.051 120,000.00 6,120.00
0.052 120,000.00 6,252.00
Jumlah Tenaga Kerja Rp 80,372.00

1.000 111,000.00 111,000.00


1.000 5,000.00 5,000.00
1.000 5,000.00 5,000.00

Jumlah Harga bahan Rp 121,000.00


Jumlah ( A + B ) Rp 201,372.00
Overhead & Profit(15%) Rp 30,205.80
Harga Satuan Pekerjaan Rp 231,577.80

Koefisien Harga Satuan Jumlah Harga

0.423 100,000.00 42,300.00


0.552 120,000.00 66,240.00
0.432 120,000.00 51,840.00
0.131 120,000.00 15,720.00
Jumlah Tenaga Kerja Rp 176,100.00

2.000 158,661.00 317,322.00


1.000 5,000.00 5,000.00
1.000 5,000.00 5,000.00

Jumlah Harga bahan Rp 327,322.00


Jumlah ( A + B ) Rp 503,422.00
Overhead & Profit(15%) Rp 75,513.30
Harga Satuan Pekerjaan Rp 578,935.30

Koefisien Harga Satuan Jumlah Harga


15000
0.038 100,000.00 3,750.00 7500
0.063 120,000.00 7,500.00
0.038 120,000.00 4,560.00
0.030 120,000.00 3,600.00
Jumlah Tenaga Kerja Rp 19,410.00

1.000 34,250.00 34,250.00

Jumlah Harga bahan Rp 34,250.00


Jumlah ( A + B ) Rp 53,660.00
Overhead & Profit(15%) Rp 8,049.00
Harga Satuan Pekerjaan Rp 61,709.00

Koefisien Harga Satuan Jumlah Harga

185000
0.370 100,000.00 37,000.00 0.2
0.771 120,000.00 92,500.00 0.5
0.308 120,000.00 37,000.00 0.2
0.154 120,000.00 18,500.00 0.1
Jumlah Tenaga Kerja Rp 185,000.00

1.000 595,000.00 595,000.00 350000 0.4


0.200 175,000.00 35,000.00

Jumlah Harga bahan Rp 630,000.00


Jumlah ( A + B ) Rp 815,000.00
Overhead & Profit(15%) Rp 122,250.00
Harga Satuan Pekerjaan Rp 937,250.00

Koefisien Harga Satuan Jumlah Harga

0.008 100,000.00 800.00 0.25


0.010 120,000.00 1,200.00 0.25
0.009 120,000.00 1,080.00 0.25
0.005 120,000.00 600.00 0.25
Jumlah Tenaga Kerja Rp 3,680.00
1.000 2,685.00 2,685.00

Jumlah Harga bahan Rp 2,685.00


Jumlah ( A + B ) Rp 6,365.00
Overhead & Profit(15%) Rp 954.75
Harga Satuan Pekerjaan Rp 7,319.75

Koefisien Harga Satuan Jumlah Harga

100,000.00 -
120,000.00 -
120,000.00 -
120,000.00 -
Jumlah Tenaga Kerja Rp -

1.000 432,000.00 432,000.00

Jumlah Harga bahan Rp 432,000.00


Jumlah ( A + B ) Rp 432,000.00
Overhead & Profit(15%) Rp 64,800.00
Harga Satuan Pekerjaan Rp 496,800.00
1 ttk, Pondasi Sumuran (volume=0.424 m3/ttk)
TENAGA KERJA
Pekerja Oh 2.400 100,000.00 240,000.00
Tukang Oh 0.800 100,000.00 80,000.00
Tukang Batu Oh 0.800 100,000.00 80,000.00
Mandor Oh 0.119 100,000.00 11,900.00
Jumlah Tenaga Kerja Rp 411,900.00
BAHAN / MATERIAL
Beton K-300 m3 1.000 865,000.00 865,000.00
Besi beton kg 143.150 17,000.00 2,433,550.00
Kawat Bendrat Kg 2.150 16,500.00 35,475.00
Jumlah Harga bahan Rp 3,334,025.00
Jumlah ( A + B ) Rp 3,745,925.00
Overhead & Profit(15%)
Harga Satuan Pekerjaan Rp 434,000.00
875000
DAFTAR SATUAN UPAH PEKERJA
HARGA SATUAN
NO URAIAN HARGA UPAH SATUAN KETERANGAN
(Rp.)

1 2 3 4

1 Pekerja L.01 OH 100,000.00


2 Tukang L.02 OH 120,000.00
3 Kepala Tukang L.03 OH 120,000.00
4 Mandor L.04 OH 120,000.00
5 Tukang Batu OH 120,000.00
6 Tukang las OH 120,000.00
7 Tukang strouss OH 120,000.00

Anda mungkin juga menyukai