PROYEK : JALAN AREA WTP (ALTERNATIF - 3 - SECTION TENGAH BETON) & SALURAN TERUSAN WTP KE THK
LOKASI : ARTHA INDUTRIAL HILL (AIH), KARAWANG, JAWA BARAT
PEMILIK : PT. BUMI ANUGERAH MAKMUR (BAM)
15 FEBRUARI 2019
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI TEKNIS SAT. VOLUME SATUAN HARGA
(Rp.) (Rp.)
I PEKERJAAN PERSIAPAN
1 Mobilisasi/demobilisasi, akomodasi/pekerja, peralatan ls 1.00 15,000,000 15,000,000
2 Direksikeet dan gudang ls 1.00 12,000,000 12,000,000
3 Keamanan proyek ls 1.00 30,000,000 30,000,000
4 Air kerja ls 1.00 4,000,000 4,000,000
5 Listrik kerja ls 1.00 4,000,000 4,000,000
6 Pembersihan selama konstruksi + buang ls 1.00 6,000,000 6,000,000
7 Pengukuran/staking out ls 1.00 6,000,000 6,000,000
8 As built drawing, dalam kertas A3 (3 set) + soft copy ls 1.00 4,000,000 4,000,000
Page 1 of 2
RENCANA ANGGARAN BIAYA
PROYEK : JALAN AREA WTP (ALTERNATIF - 3 - SECTION TENGAH BETON) & SALURAN TERUSAN WTP KE THK
LOKASI : ARTHA INDUTRIAL HILL (AIH), KARAWANG, JAWA BARAT
PEMILIK : PT. BUMI ANUGERAH MAKMUR (BAM)
15 FEBRUARI 2019
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI TEKNIS SAT. VOLUME SATUAN HARGA
(Rp.) (Rp.)
3.05 Box culvert, uk. 50 x 50 x 120 cm, t = 10 cm ex. Precon, Indonusa, SCG, setara m' 8.40 1,470,400 12,351,360
3.06 Urugan tanah kembali m3 4.15 20,000 82,992
III.4 Bak kontrol, uk. 70 x 80 x 80 cm, insitu K 250 (2 UNIT) Tinggi = 80 cm, adjustable on site
4.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 8.06 23,000 185,472
4.02 Pemadatan tanah dasar By stamper m2 4.20 12,000 50,400
4.03 Blinding stone 20 cm m3 0.62 285,000 177,840
4.04 Lean concrete 5 cm m3 0.16 840,000 131,040
4.05 Bak kontrol, uk. 70 x 80 x 80 cm, t = 15 cm (2 unit)
- Bekisting m2 13.48 130,000 1,752,400
- Besi beton Termasuk step bar kg 299.20 12,000 3,590,451
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 1.28 1,200,000 1,530,000
4.06 Urugan tanah kembali m3 4.99 20,000 99,700
III.5 Pipa PVC AW 3" DAN TANGGULAN (2 SET)
5.01 Pipa PVC AW 3" dan tanggulan (2 SET), meliputi set 2.00 450,000 900,000
- Tanggulan beton pengarah aliran air, tbl.8 cm, tgg.15 cm (0,01 m3/bh)
- Pipa PVC AW 3" (drain vertikal) (1,5m/bh)
- Bor top box culvert 50x50 cm, untuk pipa PVC AW 3" (drain vertikal)
II.2 Drop terjunan 1 (uk. 136,1x74,6x93,5 cm) tbl.12 cm/15 cm var, insitu 6 Unit
2.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 21.03 23,000 483,659
2.02 Pasir urug 10 cm, dipadatkan m3 0.89 280,000 248,087
2.03 Lean concrete 5 cm m3 0.44 840,000 372,130
2.04 Bak drop terjunan, uk. 136,1x74,6x93,5 cm, t = 12 cm/15 cm variasi
- Bekisting m2 58.08 130,000 7,550,696
- Besi beton Termasuk step bar kg 504.53 12,500 6,306,656
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 4.27 1,200,000 5,126,952
2.05 Urugan tanah kembali, dipadatkan m3 10.09 20,000 201,725
II.3 Drop terjunan 1 (uk. 157x74,6x91,9 cm) tbl.12 cm/15 cm var, insitu 1 Unit
3.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 3.78 23,000 86,852
3.02 Pasir urug 10 cm, dipadatkan m3 0.17 280,000 46,884
3.03 Lean concrete 5 cm m3 0.08 840,000 70,326
3.04 Bak drop terjunan, uk. 157x74,6x91,9 cm, t = 12 cm/15 cm variasi
- Bekisting m2 10.41 130,000 1,353,770
- Besi beton Termasuk step bar kg 91.90 12,500 1,148,721
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 0.78 1,200,000 933,845
3.05 Urugan tanah kembali, dipadatkan m3 2.40 20,000 48,050
Catatan :
- Penawaran harga sudah termasuk Profit, Overhead & Pph (included), tetapi tidak termasuk PPN (excluded)
Page 2 of 2