Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PROYEK : JALAN AREA WTP (ALTERNATIF - 3 - SECTION TENGAH BETON) & SALURAN TERUSAN WTP KE THK
LOKASI : ARTHA INDUTRIAL HILL (AIH), KARAWANG, JAWA BARAT
PEMILIK : PT. BUMI ANUGERAH MAKMUR (BAM)
15 FEBRUARI 2019
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI TEKNIS SAT. VOLUME SATUAN HARGA
(Rp.) (Rp.)
I PEKERJAAN PERSIAPAN
1 Mobilisasi/demobilisasi, akomodasi/pekerja, peralatan ls 1.00 15,000,000 15,000,000
2 Direksikeet dan gudang ls 1.00 12,000,000 12,000,000
3 Keamanan proyek ls 1.00 30,000,000 30,000,000
4 Air kerja ls 1.00 4,000,000 4,000,000
5 Listrik kerja ls 1.00 4,000,000 4,000,000
6 Pembersihan selama konstruksi + buang ls 1.00 6,000,000 6,000,000
7 Pengukuran/staking out ls 1.00 6,000,000 6,000,000
8 As built drawing, dalam kertas A3 (3 set) + soft copy ls 1.00 4,000,000 4,000,000

Sub total I 81,000,000


II PEKERJAAN JALAN
II.1 PEKERJAAN JALAN BETON (AKSES RAMPWAY)
STA. 0+000 SD STA. 0+058,7 Panjang = 58,70 m
1.01 Galian tanah Buang tanah, di kavling, dipadatkan m3 223.05 23,000 5,130,242
1.02 Pemadatan tanah dasar CBR ≥ 5 % m2 343.16 5,500 1,887,380
1.03 Lapisan pondasi bawah, lime stone 30 cm, padat CBR ≥ 45 % m3 97.67 300,000 29,299,500
1.04 Lapisan pondasi atas, agregate batu pecah klas A 15 cm, padat CBR ≥ 80 % m3 43.11 345,000 14,872,691
1.05 Plastik cor m2 255.11 5,000 1,275,550
1.06 Wiremesh M6 m2 486.74 44,000 21,416,560
1.07 Besi beton untuk expantion joint, dowel bar dan chair spacing Dowel D25-300, ℓ = 450 mm kg 1,025.07 12,000 12,300,893
1.08 Bekisting m2 46.22 130,000 6,008,600
1.09 Joint filler dilatasi antar blok m' 126.70 20,000 2,534,000
1.10 Beton ready mix 20 cm, Tℓ = 45 kg/cm2 + finish alur permukaan Beton teg. lentur Tℓ = 45 kg/cm2, t=25 cm m3 48.67 1,160,000 56,461,840
1.11 Urugan tanah kembali, dipadatkan m3 33.61 20,000 672,115
1.12 Kanstin 60 x 30 x 20/15 cm precast, terpasang lengkap K 400, setara ex. Cisangkan, Precon, SCG m' 119.40 258,000 30,805,200
1.13 Upah gutter drop 10 x 2,5 cm (type T1), samping kiri kanan bagian dalam m' 119.40 25,000 2,985,000
1.14 Pasang dowel (L J) dan (TJ) ke beton existng THK Bor + dowel D 16 mm / dowel D 32 mm m' 13.00 348,000 4,524,000
II.2 PEKERJAAN JALAN BETON (ALTERNATIF - 3)
STA. 0+058,7 SD STA. 0+190 Panjang = 131,70 m
1.01 Galian tanah Buang tanah, di kavling, dipadatkan m3 487.95 23,000 11,222,816
1.02 Pemadatan tanah dasar CBR ≥ 5 % m2 750.69 5,500 4,128,795
1.03 Lapisan pondasi bawah, lime stone 30 cm, padat CBR ≥ 45 % m3 213.35 300,000 64,006,200
1.04 Lapisan pondasi atas, agregate batu pecah klas A 15 cm, padat CBR ≥ 80 % m3 93.84 345,000 32,373,506
1.05 Plastik cor m2 553.14 5,000 2,765,700
1.06 Wiremesh M6 m2 1,053.60 44,000 46,358,400
1.07 Besi beton untuk expantion joint, dowel bar dan chair spacing Dowel D25-300, ℓ = 450 mm kg 2,218.88 12,000 26,626,579
1.08 Bekisting m2 100.62 130,000 13,080,600
1.09 Joint filler dilatasi antar blok m' 239.70 20,000 4,794,000
1.10 Beton ready mix 20 cm, Tℓ = 45 kg/cm2 + finish alur permukaan Beton teg. lentur Tℓ = 45 kg/cm2, t=25 cm m3 105.36 1,160,000 122,217,600
1.11 Urugan tanah kembali, dipadatkan m3 75.40 20,000 1,507,965
1.12 Kanstin 60 x 30 x 20/15 cm precast, terpasang lengkap K 400, setara ex. Cisangkan, Precon, SCG m' 264.00 258,000 68,112,000
II.3 PEKERJAAN JALAN PAVING BLOCK (Area Kantor WTP)
STA. 0+190 SD STA. 0+226,5 (Halaman & Area Kantor WTP) Panjang = 226,50 m
1.01 Galian tanah/lime stone ex. Bestindo sebagian Buang tanah, di kavling, dipadatkan m3 382.45 42,500 16,254,190
1.02 Pemadatan tanah dasar/lime stone ex. Bestindo sebagian CBR ≥ 5 % m2 637.42 5,500 3,505,806
1.03 Lapisan pondasi bawah, lime stone 30 cm, padat CBR ≥ 45 % m3 140.17 300,000 42,051,600
1.04 Lapisan pondasi atas, agregate batu pecah klas A 20 cm, padat CBR ≥ 80 % m3 93.45 345,000 32,239,560
1.05 Urugan abu batu 4 cm + filler 2 cm (6 cm) m3 20.94 280,000 5,864,208
1.06 Lapisan paving block tebal 6 cm, type bata/truepave, natural ex. Cisangkan m2 349.06 186,000 64,925,160
1.07 Urugan tanah kembali/buang sisa, dipadatkan m3 106.94 20,000 2,138,886
1.08 Kanstin 60 x 30 x 20/15 cm precast, terpasang lengkap K 400, setara ex. Cisangkan, Precon, SCG m' 118.20 258,000 30,495,600

Sub total II 784,842,742


III PEKERJAAN DRAINASE
III.1 DRAINASE BUIS BETON 1/2 Ø 30 CM
STA. 0+058,7 SD STA. 0+190 Panjang = 131,70 m
1.01 Drainase buis beton 1/2 Ø 30 cm, termasuk galian, lengkap, terpasang m' 131.70 111,000 14,618,700
1.02 Tali air lateral buis beton 1/2 Ø 30 cm, termasuk galian, lengkap, terpasang Dipasang setiap @ 10,8 m m' 14.00 111,000 1,554,000
III.2 DRAINASE CROSSING GUTTER 25 x 25 CM (TYPE T2)
STA. 0+058,7 Panjang = 6,70 m
2.01 Drainase crossing gutter 25 x 25 cm, termasuk galian, lengkap, terpasang Sampai dengan saluran existing m' 6.70 882,000 5,909,400
III.3 DRAINASE CROSSING BOX CULVERT 50 x 50 CM, PRECAST
STA. 0+005 Panjang = 8,40 m
3.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 11.89 23,000 273,494
3.02 Pemadatan tanah dasar By stamper m2 8.06 12,000 96,768
3.03 Blinding stone 15 cm m3 1.21 285,000 344,736
3.04 Lean concrete 5 cm m3 0.40 840,000 338,688

Page 1 of 2
RENCANA ANGGARAN BIAYA
PROYEK : JALAN AREA WTP (ALTERNATIF - 3 - SECTION TENGAH BETON) & SALURAN TERUSAN WTP KE THK
LOKASI : ARTHA INDUTRIAL HILL (AIH), KARAWANG, JAWA BARAT
PEMILIK : PT. BUMI ANUGERAH MAKMUR (BAM)
15 FEBRUARI 2019
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI TEKNIS SAT. VOLUME SATUAN HARGA
(Rp.) (Rp.)
3.05 Box culvert, uk. 50 x 50 x 120 cm, t = 10 cm ex. Precon, Indonusa, SCG, setara m' 8.40 1,470,400 12,351,360
3.06 Urugan tanah kembali m3 4.15 20,000 82,992
III.4 Bak kontrol, uk. 70 x 80 x 80 cm, insitu K 250 (2 UNIT) Tinggi = 80 cm, adjustable on site
4.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 8.06 23,000 185,472
4.02 Pemadatan tanah dasar By stamper m2 4.20 12,000 50,400
4.03 Blinding stone 20 cm m3 0.62 285,000 177,840
4.04 Lean concrete 5 cm m3 0.16 840,000 131,040
4.05 Bak kontrol, uk. 70 x 80 x 80 cm, t = 15 cm (2 unit)
- Bekisting m2 13.48 130,000 1,752,400
- Besi beton Termasuk step bar kg 299.20 12,000 3,590,451
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 1.28 1,200,000 1,530,000
4.06 Urugan tanah kembali m3 4.99 20,000 99,700
III.5 Pipa PVC AW 3" DAN TANGGULAN (2 SET)
5.01 Pipa PVC AW 3" dan tanggulan (2 SET), meliputi set 2.00 450,000 900,000
- Tanggulan beton pengarah aliran air, tbl.8 cm, tgg.15 cm (0,01 m3/bh)
- Pipa PVC AW 3" (drain vertikal) (1,5m/bh)
- Bor top box culvert 50x50 cm, untuk pipa PVC AW 3" (drain vertikal)

Sub total III 43,987,441


TOTAL 909,830,183
DIBULATKAN 909,000,000
I PEKERJAAN SALURAN TERUSAN WTP KE THK
Saluran U-Ditch uk. 50x60x120 cm precast Panjang 39,6 m' (7 segmen)
1.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 35.95 23,000 826,852
1.02 Pasir urug 10 cm, dipadatkan m3 3.05 280,000 854,112
1.03 Lean concrete 5 cm m3 1.53 840,000 1,281,168
1.04 Saluran U-Ditch, uk. 50x60x120 cm, t = 5,8/6,5 cm ex. Precon, BEP, Duracon, SCG m' 37.20 703,000 26,151,600
1.05 Urugan tanah kembali, dipadatkan m3 15.92 20,000 318,432

Sub total I 29,432,164


II PEKERJAAN BAK KONTROL & DROP TERJUNAN
II.1 Bak Kontrol (uk. 80x70x70 cm) tbl.12 cm, insitu 1 Unit
1.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 3.57 23,000 82,090
1.02 Pasir urug 10 cm, dipadatkan m3 0.14 280,000 39,581
1.03 Lean concrete 5 cm m3 0.07 840,000 59,371
1.04 Bak drop terjunan, uk. 80x70x70 cm, t = 12 cm
- Bekisting m2 5.29 130,000 688,272
- Besi beton kg 29.07 12,500 363,369
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 0.38 1,200,000 453,542
1.05 Urugan tanah kembali, dipadatkan m3 2.56 20,000 51,109

II.2 Drop terjunan 1 (uk. 136,1x74,6x93,5 cm) tbl.12 cm/15 cm var, insitu 6 Unit
2.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 21.03 23,000 483,659
2.02 Pasir urug 10 cm, dipadatkan m3 0.89 280,000 248,087
2.03 Lean concrete 5 cm m3 0.44 840,000 372,130
2.04 Bak drop terjunan, uk. 136,1x74,6x93,5 cm, t = 12 cm/15 cm variasi
- Bekisting m2 58.08 130,000 7,550,696
- Besi beton Termasuk step bar kg 504.53 12,500 6,306,656
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 4.27 1,200,000 5,126,952
2.05 Urugan tanah kembali, dipadatkan m3 10.09 20,000 201,725

II.3 Drop terjunan 1 (uk. 157x74,6x91,9 cm) tbl.12 cm/15 cm var, insitu 1 Unit
3.01 Galian tanah Buang tanah galian, di kavling, dipadatkan m3 3.78 23,000 86,852
3.02 Pasir urug 10 cm, dipadatkan m3 0.17 280,000 46,884
3.03 Lean concrete 5 cm m3 0.08 840,000 70,326
3.04 Bak drop terjunan, uk. 157x74,6x91,9 cm, t = 12 cm/15 cm variasi
- Bekisting m2 10.41 130,000 1,353,770
- Besi beton Termasuk step bar kg 91.90 12,500 1,148,721
- Beton ready mix K 250/site mix Insitu beton K 250/site mix m3 0.78 1,200,000 933,845
3.05 Urugan tanah kembali, dipadatkan m3 2.40 20,000 48,050

Sub total II 25,715,687


TOTAL 55,147,851
DIBULATKAN 55,100,000
GRAND TOTAL 964,100,000

Catatan :
- Penawaran harga sudah termasuk Profit, Overhead & Pph (included), tetapi tidak termasuk PPN (excluded)