Harga Sampai Lokasi Toko Harga Sampai Lokasi Harga Sampai Lokasi
Keterangan
URAIAN Satuan I Toko ll Toko lll
Rp Rp Rp
I. BAHAN
1 Papan Proyek Bh 150,000
2 Prasasti Bh 250,000
3 Batu Belah m³ 75,000 87,500 87,500 87,500
4 Pasir Pasang m³ 60,000 87,500 87,500 87,500
5 Pasir Beton m³ 150,000 150,000 150,000 150,000
6 Sirtu m³ 75,000 75,000 75,000 75,000
7 Semen Zak 52,000 52,500 52,000 52,000
8 Split Batu pecah 2/3 m³ 115,000 150,000 150,000 150,000
18 Papan Alba 3/20 m³ 1,200,000 1,200,000 1,200,000 1,200,000
31 Gorong-gorong D 40 m 60,000 60,000 60,000 60,000
32 Gorong-gorong D 50 m
II. ALAT
1 Molen Unit 250,000
III. UPAH
1 Pekerja Hari 28,500
2 Tukang Hari 36,000
Kabupaten : Tasikmalaya Jenis Kegiatan : Perkerasan Jalan
Kecamatan : Padakembang Take Off Sheet Sub Kegiatan : Rabat Beton
Desa : Padakembang Ukuran : P = 387 m, L = 2.5 m
Pembersihan Lahan
Lbadan Jalan = P x L
= 387 x 3.5 = 1,355 m2
Referensi :
Pompa Air = 0.30 jam Pompa Air = 0.30 x 87.1 @ 26.1 jam
Molen 0.125m3 = 0.15 hari (= 6 jam ) Molen = 0.15 x 87.1 @ 13.1 hari
Pekerja = 1.65 HOK Pekerja = 1.23 x 87.1 @ 107.1 HOK
Tukang = 0.25 HOK Tukang = 0.30 x 87.1 @ 26.1 HOK
Referensi :
27 hari
14
2. ALAT / PERLENGKAPAN
2.1 Molen 14 14 hari 250,000 3,500,000 - 3,500,000
2.2 Prasasti 1 1 ls 250,000 250,000 - 250,000
2.3 Papan nama proyek 1 1 ls 150,000 150,000 - 150,000
3. UPAH
3.1 - Pekerja 462 84 378.00 HOK 28,500 10,773,000 2,394,000 13,167,000
3.2 - Tukang 27 27.00 HOK 36,000 972,000 972,000
A. PEKERJAAN TPT
Rencana Panjang : 61.5 meter
Tinggi 1.5 meter
B. PEKERJAAN TPT
Rencana Panjang : 61.5 meter
Tinggi 1 meter
2 UPAH
3.1 - Pekerja 134 50 84 HOK 28,500 2,393,000 1,425,000 3,818,000
3.2 - Tukang 52 52 HOK 36,000 1,872,000 1,872,000
1.5
Ø = 40 cm
Ø + 0,4
TASIKMALAYA
Kecamatan
POTONGAN B - B PARUNGPONTENG
Desa
DENAH GORONG-GORONG
CIGUNUNG
0.30 Jenis Prasarana
0.25
PENINGKATAN JALAN
Pas. Batu Belah
Adk. 1 pc : 5 psr Lokasi
50
0.
DUSUN Sindangrasa
Judul Gambar
0.25
1.90
GORONG-GORONG
Panjang 5 & 6m', Ø 40 cm
0.60
Selisih ketinggian
ujung 0,10
Dibuat Oleh :
0.25
1.00 FT-TPK/Kader Teknik
0.40
1.50
POTONGAN A - A
YOGA PRAWIRAHARJA, ST
Diperiksa Oleh :
KM-T
URUGAN DAN PEMADATAN No. Patok / Titik Ket. Ir. Basuki Rahmad
BERLAPIS 0,15 MAKSIMAL
1 P7 Baru Diketahui Oleh :
2 PjOK
PASIR
BATU
3
4
Ø + 0,3
5 H.E Agus Muslim,S.Pd.
DETAIL TIMBUNAN TANAH
NIP. 1971 0202 199503 1001
DETAIL TIMBUNAN TANAH
Lembar ke dari
H.E Agus Muslim,S.Pd.
C. PEKERJAAN GORONG-GORONG
Rencana Panjang = 4 meter
Diameter = 40 cm
Jumlah Gorong2 = 3 buah
1.333333
1.333333
0.0864
1.333333
1.333333
PNPM-Mandiri Perdesaan
2 UPAH
3.1 - Pekerja 45.0 - 45 HOK 28,500 1,282,500 - 1,282,500
3.2 - Tukang 11.0 11 HOK 36,000 396,000 396,000
I Bahan - 40,999,500 3,075,000 - 70.96 - 14,769,000 2,375,000 - 75.08 - 4,358,000 - - 72.2 - 60,126,500 5,450,000 - 69.9
III Upah - 11,745,000 2,394,000 - 22.76 - 4,265,000 1,425,000 - 24.92 - 1,678,500 - - 27.8 - 17,688,500 3,819,000 - 20.6
IV JUMLAH - 56,644,500 5,469,000 - 100.00 - 19,034,000 3,800,000 - 100.0 - 6,036,500 - - 100.0 - 81,715,000 9,269,000 - 95.0
Jumlah HOK
489 HOK 186 HOK 56 HOK 731 HOK
Konstruksi
Drs. Kusdiana
NIP. 19560109 198603 1 006 Dede Farid Tera Sugihan, ST / Anjar Indraguna, ST
Kecamatan
ANALISA PEKERJAAN - KEBUTUHAN BAHAN Desa
& UPAH Lokasi
Pekerjaan : SEGITIGA PENAHAN TPT Tanggal : 24 Ma
0,30
11,58cm
Analisa Kebutuhan Bahan dan Upah Pekerjaan/M3
20cm
17,38cm
* Bahan - Batu Pecah 1/2 = 0.78 x ###
- Semen = 323.0 x ###
23,17cm
26cm
0.32
Plesteran ad. 1pc : 5psr Kebutuhan Bahan, Upah dan Alat
* Upah - Pekerja
- Tukang
- Tukang Kayu
- Tukang Besi
ng (Sabuk Pengikat)
m3
= 1.71 ~ 2 m3
= 708.02 ~ 14 sak ( 50 kg )
= 1.14 ~ 1 m3
= 0.59 ~ 0.6 m3
= 6.58 ~ 7 Kg
= 4.67 ~ 5 Lente
= 11.33 ~ 11 Lente
= 4.38 ~ 4 Kg
= 10.63 = 11 Hok
= 3.07 = 3 Hok
= 3.42 = 3 Hok
m3
= 1.36 ~ 1.4 m3
= 4.19 ~ 4 sak ( 50 kg )
= 0.64 ~ 0.6 m3
= ### m3
m3
x 4 = ###
= ### ~ ### m3
= ### ~ ### sak (50 Kg)
= ### ~ ### m3
= ### ~ ### m3
= ### ~ ### Kg
= 8.33 ~ 8 lente
= 7.33 ~ 7 lente 7.3333333
= ### ~ ### Kg
= ### ~ ### m3
= 6.44 m2
= 46.94 ~ 1 sak ( 50 kg )
= 0.18 ~ 0.2 m3
= 1.4 m3 ###
= #VALUE! sak ###
= 0.8 m3 ###
= #VALUE! m3
= #VALUE! m3
= 13 lente
= 19 lente
= 0.6 m3
= #VALUE! m3
= #VALUE! Kg
= #VALUE! Kg
Dibuat Oleh :
KPMD dan TPK
Form IV.4
Kecamatan : Cikoneng
Desa :
Lokasi :
Tanggal :
= 22 m3
= #REF!
1.333
1.333
1.333
1.333
1.333
Dibuat Oleh :
Kader Teknik, FD dan TPKD