Anda di halaman 1dari 14

DAFTAR HARGA MATERIAL - ALAT - TENAGA

Desa : Wonoagung
Kecamatan : Kasembon
Kabupaten : Malang
Nama Toko :
Nama Pemilik :

Harga Satuan

No. Material / Alat / Tenaga Satuan


Harga Toko Harga Sampai Lokasi

BAHAN
1 Pasir M3
2 Pasir Urug M3
3 Batu Belah M3
4 Bata Merah Bj
5 Batu Pecah M3
6 Semen - 40 KG Zak
7 Semen Warna Kg
8 Paku 2" - 5" Kg
9 Mur baut Kg
10 Kayu Begesting 2/15-2 M Lembar
11 Besi Ø12 Lonjor
12 Besi Ø10 Lonjor
13 Besi Ø6 Lonjor
14 Besi Polos Kg
15 Bendrat Kg
16 kayu Kelas III untuk begisting M3
17 Kayu Reng Kelas II M3
18 Kayu Usuk kelas II M3
19 Minyak Bekisting Liter
20 Balok Kayu 8/12 Kelas II M3
21 Kayu Balok 7/14 Kelas II M3
22 Kayu Papan Kelas II M3
23 Kalsiplank uk 30-3m lembar
24 Upak Ukuran 40/60 Bh
25 Tiang beton Φ 25 Bh
26 Plywood tebal 9 mm Lbr
27 Bambu Bongkotan (2,5 - 3 m) Bh
28 Lem Kayu Kg
29 Gypsum Board 1,2 x 2,4 Lbr
30 List Plafon m'
31 Genteng Bj
32 Bubungan Bj
33 Plamir Kg
34 Cat Tembok Kg
35 Cat Dasar Kg
36 Cat Kayu Kg
37 Plamur Kayu Kg
38 Tinner Liter
39 Cat Meny Kayu Kg
40 Kertas Amplas Lbr
41 Kaca 5 mm M2
42 Keramik 40/40 M2
43 Keramik Dinding 20/25 M2
44 Pintu Bj
45 Handle dan Kunci Pintu Utama Bh
46 Handle Singlle Bh
47 Engsel Pintu Bh
48 Engsel jendela Bh
49 Grendel Pintu Bh
50 Grendel Cendela Bh
51 Hak Angin Sikutan Bh

UPAH PEKERJA
1 Pekerja OH
2 Tukang OH
3 Kepala Tukang OH

Malang,......................2021
Yang Melaksanakan Survey

(.............................................)
KABUPATEN : MALANG JENIS PRASARANA : TPT Kolam Renang
KECAMATAN : KASEMBON BACK UP VOLUME LOKASI :
DESA : WONOAGUANG VOLUME : 80 m
SKET GAMBAR ITEM PEKERJAAN P x L x T x JUMLAH = VOLUME SAT.

I PEKERJAAN PERSIAPAN
Papan Nama Proyek 1.00 1.00 1.00 bh
Pengukuran dan pemasangan bouwplank 0.00 + 0.00 0x 0.00 1.00 80.00 m

II PEKERJAAN GALIAN + URUGAN


Galian Pondasi 512.50 m3
a. Galian Pondasi E3 15.50 x 1.800 x 2.900 x 1.000 = 80.91
Galian Pondasi E4 16.00 x 1.900 x 4.600 x 1.000 = 139.84
Galian Pondasi J4 26.00 x 1.200 x 2.500 x 1.000 = 78.00
Galian Pondasi J5 22.50 x 1.900 x 5.000 x 1.000 = 213.75
Pekerjaan Urugan Tanah Kembali 170.83
=
Pekerjaan Urugan Pasir 6.61 m3
a. Pondasi E3 15.50 x 1.800 x 0.050 x 1.000 = 1.40
Pondasi E4 16.00 x 1.900 ### 0.050 x 1.000 = 1.52
Pondasi J4 26.00 x 1.200 ### 0.050 x 1.000 = 1.56
Pondasi J5 22.50 1.900 0.050 1.000 2.14

III PEKERJAAN PASANGAN BATU KALI


Pekerjaan Pasangan Pondasi Batu Kali 238.66 m3
Pondasi E3 15.50 x 1.800 x 0.400 x 1.000 = 11.16
Pondasi E3 15.50 x 1.000 x 0.900 x 1.000 = 13.95
Pondasi E3 15.50 x 0.450 x 1.600 x 1.000 = 11.16
Pondasi E4 16.00 x 1.900 x 0.400 x 1.000 = 12.16
Pondasi E4 16.00 x 0.800 x 2.200 x 1.000 = 28.16
Pondasi E4 16.00 x 1.000 x 0.400 x 1.000 = 6.40
Pondasi E4 16.00 x 0.450 x 1.600 x 1.000 = 11.52
Pondasi J4 26.00 x 1.200 x 0.400 x 1.000 = 12.48
Pondasi J4 26.00 x 0.450 x 2.100 x 1.000 = 24.57
Pondasi J5 22.50 x 2.000 x 0.500 x 1.000 = 22.50
Pondasi J5 22.50 x 0.800 x 1.500 x 1.000 = 27.00
Pondasi J5 22.50 x 1.200 x 0.400 x 1.000 = 10.80
Pondasi J5 22.50 x 0.600 x 1.600 x 1.000 = 21.60
Pondasi J5 22.50 x 1.000 x 0.400 x 1.000 = 9.00
Pondasi J5 22.50 x 0.450 x 1.600 x 1.000 = 16.20

IV PEKERJAAN PASANGAN PLESTERAN


Pekerjaan Pasangan Pondasi Batu Kali 52.80 m2
Pondasi E3 15.50 x 0.400 x 1.000 x 1.000 = 6.20
Pondasi E4 16.00 x 0.400 x 1.000 x 2.000 = 12.80
Pondasi J4 26.00 x 0.400 x 1.000 x 1.000 = 10.40
Pondasi J5 26.00 x 0.900 x 1.000 x 1.000 = 23.40
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG PEKERJAAN UMUM

Harga sat. Bahan Upah Jumlah


No Uraian Kode Satuan Koefisien Volume Kebutuhan
Rp. Rp. Rp. Rp.
A.2.3.1 PEKERJAAN TANAH
A.2.3.1.1 1 m3 Penggalian Tanah biasa sedalam 1 m
Pekerja L.01 OH 0.34 512.50 172.97 100,000 17,296,875 17,296,875
Kepala Tukang L.03 OH 0.03 512.50 17.30 120,000 2,075,625 2,075,625
Mandor L.04 OH 0.00 512.50 1.73 130,000 224,859 224,859
19,597,359 19,597,359
A.2.3.1.9 1 m3 Pengurugan kembali galian tanah
Pekerja L.01 OH 0.23 170.83 38.44 100,000 3,843,750 3,843,750
Kepala Tukang L.03 OH 0.02 170.83 3.84 120,000 461,250 461,250
Mandor L.04 OH 0.00 170.83 0.38 130,000 49,969 49,969
4,354,969 4,354,969
A.2.3.1.11 1 m3 Pengurugan dengan pasir
Pasir m3 0.54 6.61 3.57 200,000 714,150 714,150
Pekerja L.01 OH 0.30 6.61 1.98 100,000 198,375 198,375
Kepala Tukang L.03 OH 0.03 6.61 0.20 120,000 23,805 23,805
Mandor L.04 OH 0.00 6.61 0.01 130,000 1,289 1,289
714,150 223,469 937,619
A.4.1.1 PEKERJAAN PASANGAN BATU KALI
A.4.1.1.1 1 m3Pasangan Batu Kali campuran 1 Semen : 5 Pasir
Semen Zak 4.90 238.66 1169.434 60,000.00 70,166,040 70,166,040
Pasir m3 0.52 238.66 124.34186 200,000.00 24,868,372 24,868,372
Batu Kali m3 1.20 238.66 286.392 250,000.00 71,598,000 71,598,000
Pekerja L.01 OH 1.50 238.66 357.99 100,000.00 35,799,000 35,799,000
Tukang batu L.02 OH 0.60 238.66 143.196 110,000.00 15,751,560 15,751,560
Kepala Tukang L.03 OH 0.06 238.66 14.3196 120,000.00 1,718,352 1,718,352
Mandor L.03 OH 0.00 238.66 0.71598 130,000.00 93,077 93,077
166,632,412 53,361,989 219,994,401

A.4.4.1 PEKERJAAN PASANGAN DINDING


A.4.4.1.10 1 m2 Pemasangan Plesteran campuran 1 sp : 6 pp
Semen Portland zak 0.09 52.80 4.86 60,000 291,456 291,456
Pasir Pasang m3 0.06 52.80 3.33 200,000 665,280 665,280
Pekerja L.01 OH 0.10 52.80 5.28 100,000 528,000 528,000
Tukang batu L.02 OH 0.15 52.80 7.92 110,000 871,200 871,200
Kepala Tukang L.03 OH 0.02 52.80 0.79 120,000 95,040 95,040
Mandor L.04 OH 0.01 52.80 0.26 130,000 34,320 34,320
956,736 1,528,560 2,485,296

A.4.4.1.10 1 m2 Pemasangan Acian


Semen Portland zak 0.08 52.80 4.29 60,000 257,400 257,400
Pekerja L.01 OH 0.15 52.80 7.92 100,000 792,000 792,000
Tukang batu L.02 OH 0.10 52.80 5.28 110,000 580,800 580,800
Kepala Tukang L.03 OH 0.01 52.80 0.53 120,000 63,360 63,360
Mandor L.04 OH 0.01 52.80 0.26 130,000 34,320 34,320
257,400 1,470,480 1,727,880
DAFTAR HARGA MATERIAL - ALAT - TENAGA

Desa : Wonoagung
Kecamatan : Kasembon
Kabupaten : Malang
Nama Kegiatan : Pembangunan TPT Kolam Renang

Harga Satuan

No. Material / Alat / Tenaga Satuan


PPN PPh 21 PPh 22 PPh 23 Harga satun
Harga Survey
(10 %) (5%) (1,5%) (2 %) RAB

BAHAN
1 Pasir urug M3 100,000 100,000
2 Semen Kg 1,500 2,000
3 Semen zak 60,000 60,000
4 Pasir M3 200,000 200,000
5 Batu pecah 2-3 cm M3 400,000 400,000
6 Batu Kali Kg 250,000 250,000
7 Besi Beton / tulangan beton Kg 15,001 15,000
7 Kawat Beton / bendraat Zak 15,000 15,000
8 Kayu bekisting M3 2,500,000 2,500,000
9 Paku biasa Kg 15,000 15,000
10 Minyak bekisting ltr 12,000 12,000
11 Balok Kayu Kelas III M3 3,500,000 3,500,000
12 Playwood tebal 9 cm lbr 250,000 250,000
13 Dolken btg 12,500 13,000
14 Balok kayu kelas II M3 4,200,000 4,200,000
15 Dolken kayu  8- 10cm panjang 4 lembar 25,000 25,000
16 Bata ringan tebal 10cm buah 8,4 Kg 10,000 10,000
17 Mortar Siap Pakai (Semen Instan) Kg 95,000 95,000
18 Batu Hias Kg 150,000 150,000
19 aluminium 4 inch Liter 100,000 100,000
20 Skrup fixer Kg 25,000 25,000
21 Sealant Lbr 20,000 20,000
22 aluminium M2 100,000 100,000
23 Kaca tebal 8 mm Bj 150,000 150,000
24 Silicone Sealant 300 ml Bh 50,000 50,000
25 Engsel pintu Bh 95,000 95,000
26 Engsel Angin Bh 85,000 85,000
27 Kunci slot Bh 25,000 25,000
28 Kunci tanam antik Bh 225,000 225,000
29 Kunci tanam biasa Bh 75,000 75,000
30 Ubin Keramik 30x30 Bh 6,000 6,000
30 Ubin Keramik 20x20 Bh 55,000 55,000
30 Ubin Keramik 20x25 Bh 5,455 5,000
31 Semen Warna kg 2,000 2,000
41 Besi Baja Profil kg 15,000 15,000
42 Kawat Las RB bh 37,000 37,000
43 Aluminium gelombang m 125,000 125,000
44 Paku pancing kg 15,000 15,000
45 Nok standar m 45,000 45,000
46 Seng pelat 0.05 mm/90 cm m 105,000 105,000
47 Kaso-kaso 5 x 7cm ljr 25,000 25,000
48 Asbes bh 25,000 25,000
49 Paku tripleks kg 20,000 20,000
50 List Kayu profil m1 25,000 25,000
51 Cat Tembok Dasar kg 27,000 27,000
52 Cat Tembok Penutup kg 27,000 27,000
53 Besi Plat m2 121,528 122,000
54 Pipa listrik 5/8” hdpe btg 8,000 8,000
55 Kabel m 1,500 2,000
56 T Dus bh 5,000 5,000
57 L Bow bh 5,000 5,000
58 Las Dop bh 100 -
59 Klem bh 200 -
60 Lampu bh 150,000 150,000
61 Mongkok bh 5,000 5,000
62 Saklar bh 15,000 15,000
63 Fitting bh 15,000 15,000
65 Stopkontak bh 15,000 15,000
66 MCCB (Boks MCB) bh 350,000 350,000
67 MCB bh 350,000 350,000
68 Closet duduk bh 1,500,000 1,500,000
69 Wastafel Lengkap bh 500,000 500,000
70 Pipa PVC 1/2” AW ljr 13,750 14,000
71 Kran air bh 35,000 35,000
72 Sealtape bh 8,500 9,000
73 Floor drain bh 35,000 35,000
74 PVC 4" ljr 46,250 46,000
75 PVC 3" ljr 325,000 325,000
76 PVC 2" ljr 175,000 175,000
76 Pipa stainlees 2" ljr 91,667 92,000

UPAH PEKERJA
1 Pekerja OH 100,000 100,000
2 Tukang OH 110,000 110,000
3 Kepala Tukang OH 120,000 120,000
4 Mandor OH 130,000 130,000
RENCANA ANGGARAN BIAYA ( R.A.B )

KEGIATAN : PENGEMBANGAN USAHA BUMDES


PEKERJAAN : PEMBANGUNAN TPT KOLAM RENANG
LOKASI : DESA WONOAGUNG KEC. KASEMBON

Jumlah Harga ( Rp )
No Uraian Pekerjaan Analisa Sat. Volume
Bahan Upah Total
1 2 3 4 5 7 7 8
I PEKERJAAN PERSIAPAN
1 Papan Nama Proyek - Ls 1.00 1,000,000.00 1,000,000.00
2 Pengukuran dan pemasangan bouwplank - Ls 80.00 8,000,000.00 8,000,000.00

Sub-Total 9,000,000.00 - 9,000,000.00

II PEKERJAAN TANAH
1 Galian tanah A.2.3.1.1 m3 512.50 - 19,597,359.38 19,597,359.38
2 Urug tanah kembali A.2.3.1.9 m3 170.83 - 4,354,968.75 4,354,968.75
3 Urug pasir bawah pondasi dan Lantai A.2.3.1.11 m3 6.61 714,150.00 223,469.44 937,619.44

Sub-Total 714,150.00 24,175,797.56 24,889,947.56

III PEKERJAAN PASANGAN BATU KALI


1 Pasangan Batu Kali campuran 1 Semen : 5 Pasir m3 8.04 166,632,412.00 53,361,989.40 219,994,401.40

Sub-Total 166,632,412.00 53,361,989.40 219,994,401.40

IV PEKERJAAN PLESTERAN DAN ACIAN


1 Plesteran m3 0.00 956,736.00 1,528,560.00 2,485,296.00
2 Acian m3 68.65 257,400.00 1,470,480.00 1,727,880.00
Sub-Total 1,214,136.00 2,999,040.00 4,213,176.00

JUMLAH 177,560,698.00 80,536,826.96 258,097,524.96


PPn 10% BAHAN 17,756,069.80
JUMLAH UPAH + BAHAN 177,560,698.00 80,536,826.96 275,853,594.76
JUMLAH TOTAL 228,031,000.00
TERBILANG : "Dua Ratus Duapuluh Delapan Juta Tigapuluh Satu Ribu Rupiah "
Malang,31 Desember 2022
Mengetahui Dibuat Oleh
Kepala Desa Wonoagung

Edy Istiyono Alun Dulkaidi


KEBUTUHAN MATRIAL DAN UPAH

KEGIATAN : PENGEMBANGAN USAHA BUMDES


PEKERJAAN : PEMBANGUNAN TPT KOLAM RENANG
LOKASI : DESA WONOAGUNG KEC. AKSEMBON

No Nama Bahan Sat. Volume Harga Satuan Jumlah

1 2 4 5 6 7
Bahan
1 Batu Kali m3 286.39 250,000.00 71,598,000.00
2 Pasir m3 127.91 200,000.00 25,582,522.00
3 Pasir Pasang m3 3.33 200,000.00 665,280.00
4 Semen zak 1,169.43 60,000.00 70,166,040.00
5 Semen Portland zak 9.15 60,000.00 548,856.00

Upah
1 Pekerja m3 584.58 100,000.00 58,458,000.00
2 Kepala Tukang m3 36.98 120,000.00 4,437,432.00
3 Tukang batu OH 156.40 110,000.00 17,203,560.00
4 Mandor kg 3.37 130,000.00 437,834.96

JUMLAH 249,097,524.96
TERBILANG : "Duaratus Empatpuluh Sembilan Juta Sembilanpuluh Tujuh Ribu Limaratus Rupiah "
Malang,31 desember 2022
Mengetahui Dibuat Oleh
Kepala Desa
Wonoagung

Edy Istiyono. Alun Dulkaidi


REKAPITULASI RENCANA ANGGARAN BIAYA ( R.A.B )

KEGIATAN : PENGEMBANGAN USAHA BUMDES


PEKERJAAN : PEMBANGUNAN TPT KOLAM RENANG
LOKASI : DESA WONOAGUNG KEC. AKSEMBON

JUMLAH HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN JUMLAH TOTAL ( Rp )
BAHAN ( Rp ) UPAH ( Rp )

I PEKERJAAN PERSIAPAN Rp 9,000,000.00 Rp - Rp 9,000,000.00


II PEKERJAAN TANAH Rp 714,150.00 Rp 24,175,797.56 Rp 24,889,947.56
III PEKERJAAN PASANGAN BATU KALI Rp 166,632,412.00 Rp 53,361,989.40 Rp 219,994,401.40
IV PEKERJAAN PLESTERAN DAN ACIAN Rp 1,214,136.00 Rp 2,999,040.00 Rp 4,213,176.00

JUMLAH Rp 177,560,698.00 Rp 80,536,826.96


PPn 10% BAHAN Rp 17,756,069.80
JUMLAH UPAH + BAHAN Rp 177,560,698.00 Rp 80,536,826.96 Rp 258,097,524.96
JUMLAH TOTAL Rp 275,853,594.76
DIBULATKAN Rp 275,853,000.00
TERBILANG : "Tigaratus Enampuluh Tujuh Juta Sembilan Ratus Enam Puluh Tujuh Ribu Rupiah"

Malang, 31 Desember 2022


Mengetahui Dibuat Oleh
Kepala Desa Wonoagung

Edy Istiyono Alun Dulkaidi


JADWAL PELAKSANAAN PEKERJAAN
KEGIATAN : PEMBANGUNAN / REHAB SARANA DAN PRASARANA PENDIDIKAN
PEKERJAAN : PEMBANGUNAN TPT KOLAM RENANG
LOKASI : DESA WONOAGUNG

NO URAIAN PEKERJAAN NILAI BOBOT (%) BULAN I BULAN II BULAN III


1 2 3 4 1 2 3 4 1 2 3 4
I PEKERJAAN PERSIAPAN ### 3.49% 3.49%
II PEKERJAAN TANAH ### 9.64% 3.21% 3.21% 3.21%
III PEKERJAAN PASANGAN ### 85.24% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75%
IV PEKERJAAN PLESTERAN DAN ACIAN ### 1.63% 0.54% 0.54% 0.54%
JUMLAH ### 100.00%
RENCANA 6.70% 10.96% 10.96% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 8.29% 8.29% 8.29%
KUMULATIF RENCANA 6.70% 17.66% 28.63% 36.38% 44.13% 51.87% 59.62% 67.37% 75.12% 83.41% 91.71% 100.00%
KEMAJUAN FISIK
REALISASI
KUMULATIF REALISAS

Malang,31 Desember 2022


Mengetahui Dibuat Oleh
Kepala Desa Wonoagung

Edy Istiyono Alun Dulkaidi


ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG PEKERJAAN UMUM

No Uraian Kode Satuan Koefisien Volume

Tukang batu L.02 OH 0.60 238.66


Tukang batu L.02 OH 0.15 52.80
Tukang batu L.02 OH 0.10 52.80
SATUAN PEKERJAAN (AHSP)
PEKERJAAN UMUM

Harga sat. Bahan Upah Jumlah


Kebutuhan Rp. Rp. Rp. Rp.
143.196 110,000.00 15,751,560 15,751,560
7.92 110,000 871,200 871,200
5.28 110,000 580,800 580,800

156.40
1.100 M3 Batu Kali
2 Tukang Batu Org 0.100
2 Tukang Batu Org 0.100
Batu Kali m3 1.2 238.66 286.392 250000 71598000
Kepala TukL.03 OH 0.01 0 165.7459 0
Mandor L.04 OH 0.005 0 20.63083 0
Pasir m3 0.521 0 127.9126 110000 14070387.1
Pasir Pasang m3 0.063 52.8 3.3264 200000 665280
Pekerja L.01 OH 0.15 0 583.4889 0
Semen Zak 4.9 238.66 1169.434 60000 70166040
Semen Portland zak 0.08125 0 9.1476 0 0
Tukang batL.02 OH 0.1 0 1445.16 0
71598000 6 OH Kepala Tukang
0 0 3 Kepala Tu Org 0.01
0 0 4 Mandor Org 0.008
14070387.1 0.6 OH Tukang Batu
665280 No Uraian Satuan Koef
0 0 1 Pembantu Org 0.15
70166040 1.5 OH Pekerja
0
0 0 2 Tukang Ba Org 0.1
REKAPITULASI RENCANA ANGGARAN BIAYA ( R.A.B )

KEGIATAN : PENGEMBANGAN USAHA BUMDES


PEKERJAAN : PEMBANGUNAN TPT KOLAM RENANG
LOKASI : DESA WONOAGUNG KEC. AKSEMBON

JUMLAH HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN
UPAH ( Rp ) BAHAN ( Rp )

I PEKERJAAN PERSIAPAN #REF! #REF!


II PEKERJAAN TANAH #REF! #REF!
III PEKERJAAN PASANGAN #REF! #REF!
IV PEKERJAAN KUSEN, PINTU DAN JENDELA #REF! #REF!
V PEKERJAAN BETON BERTULANG #REF! #REF!
VI PEKERJAAN RANGKA ATAP #REF! #REF!
VII PEKERJAAN PENUTUP ATAP #REF! #REF!
VIII PEKERJAAN INSTALASI LISTRIK #REF! #REF!
IX PEKERJAAN PLAFOND #REF! #REF!
X PEKERJAAN KERAMIK #REF! #REF!
XI PEKERJAAN PENGECATAN #REF! #REF!

JUMLAH #REF! #REF!


PPn 10% BAHAN #REF!
JUMLAH UPAH + BAHAN #REF! #REF!
JUMLAH TOTAL #REF!
DIBULATKAN #REF!
TERBILANG : "Dua Ratus Juta Rupiah"