DAFTAR PERHITUNGAN BAHAN DAN UPAH

Jenis Kegiatan : Jalan Rabat Beton Desa :


UPAH BAHAN
No Sket Gambar Perhitungan Volume Pekerja Tukang Bt Pch 2/3 Bt Pch 5/7 Semen Ps-B
HOK HOK m3 m3 zak m3
Analisa Bangkim Kab. Garut Th 2014 (K-225)
LEBAR PERKERASAN
1. Rabat Beton 23.39 5.53 11.00 - 105.18 7.07
1 1,50 m
= 1.50 x 1.00 x 0.15
Rabat Beton ( L = 1.5 m T = 12 cm )
Camp. (1Pc : 3Ps: 5Kr)

Urugan Tanah 0.5 x 0.12


CL
Urugan Tanah (Biaya Swadaya) = 0.23 m3
6-8 % 4-5 % 4-5 % 6-8 %

V Pas. Tot = 0.23 x 63.00 m


Lantai Kerja Urugan Pasir ( t = 5 cm )
= 14 m3
Konstruksi Existing (Tanah)
Bahu Jalan yang ada telah padat

URAIAN KOEF SAT


BAHAN
1.50 Bt Pecah 2/3 0.7760 m3
Semen (50kg) 7.4200 zak
Pasir 0.4990 m3
Bt Pecah 5/7 m3
UPAH
Pekerja 1.6500 OH
1.00 Tukang 0.3900 OH
Molen 0.1000 hari
vibro - hari

2. Hamparan Pasir untuk Lantai Kerja ( t = 5 cm ) 3.17 -


= 1.50 x 0.05 x 63
2 V Tot = 4.73

URAIAN KOEF SAT


BAHAN
Pasir Urug 1.34 m3
UPAH
Pekerja 0.5000 HOK

3 3. Hamparan Sirtu U/ Bahu ( Kiri dan Kanan ) - -


= - x 0.50 x 0.12
V Tot = -
URAIAN KOEF SAT
BAHAN
Saluran Sirtu 1.34 m3
Bahu
UPAH
0.50 0.50 Pekerja 0.5000 HOK

4. Galian Saluran/ Bahu -


= - x 0.50 ,+ 0.30
x 0.50
2
0.50
= - M3
URAIAN KOEF SAT
Upah
0.30 Pekerja 0.50 HOK
JUMLAH 26.55 5.53 11.00 - 105.18 7.07
DAFTAR PERHITUNGAN BAHAN DAN UPAH
Jenis Kegiatan : Jalan Rabat Beton Desa : .......................
UPAH BAHAN
No Sket Gambar Perhitungan Volume Pekerja Tukang Besi o 10 Paku Kawat Papan
HOK HOK Btg Kg Kg M3

4 5. Bekisting 3.26 3.40 0.34


1.50 Asumsi yang dipakai = 63 m'
1. Memanjang 2.00 x 32 x 0.15 x 0.020
= 0.189 m3
2. Melintang = 63 : 2.00 = 32
= 33 x 1.50 x 0.15 x 0.020
= 0.15 m3
Total = 0.34 m3

Pekerja = 63 x 1.50 x 0.15


= 14.18
5 6. Paku
2 = 32 x 1.50 x 0.15 0.71
= 7.09
URAIAN KOEF SAT
BAHAN
Paku 0.1 Kg
UPAH
Pekerja 0.2300 HOK
Tukang 0.2400 HOK

7. Plastik
= 63 x( 1.50 + 0.15 + 0.15 )
= 113.40
URAIAN KOEF SAT
BAHAN
Plastik 1.05 m2
( PPK III 2005 dan BINA MARGA )

JUMLAH 3.26 3.40 - 0.71 - 0.34


.......................

Ps- U Sirtu Molen


m3 m3 LS

1.42

6.33

-
6.33 - 1.42
Sirtu Plastik
M3 M2

119

- 119
RENCANA ANGGARAN BIAYA
DESA SUKAWENING KECAMATAN SUKAWENING
TAHUN 2017

Kegiatan : Pembangunan Jalan Lingkungan Rabat Beton


Volume : 100 M x 1,5M x 0,15M
Waktu Pelaksanaan :

Harga Satuan
No U R A I A N V o l u m e Total Biaya (Rp)
(Rp)

1 2 3 4 5

A. B A H A N
1 Semen @ 50 Kg 105.0 Zak 60,000 6,300,000
2 Pasir Beton 7.0 M3 300,000 2,100,000
3 Pasir Urug 6.0 M3 300,000 1,800,000
4 Batu Pecah 2/3 11.0 M3 300,000 3,300,000
5 Papan Bekisting - M3 850,000 -
6 Paku 2.0 Kg 20,000 40,000

Sub Total 1) 13,540,000


B. A L A T
1 Papan Proyek 1.0 Ls 100,000 100,000
2 Prasasti 1.0 Ls 150,000 150,000
4 Roda Sorang 1.0 Buah 500,000 500,000
5 Meteran 5 m' 1.0 Buah 25,000 25,000
6 Sekop 2.0 Buah 75,000 150,000
7 Ember 30.0 Buah 10,000 300,000
8 Benang 3.0 Rol 5,000 15,000
9 Cangkul 1.0 Buah 70,000 70,000

Sub Total 2) 1,310,000


C. U P A H
1 Pekerja 30.0 HOK 100,000 3,000,000
2 Tukang 9.0 HOK 120,000 1,080,000

Sub Total 3) 4,080,000


D. Honor TPK
1 Honor TPK 1.0 Paket 1,050,000 500,000
Sub Total 4) 500,000
TOTAL BIAYA 19,430,000

PPN 10 % 1,943,000 323,833


Jumlah 21,373,000
FIX

Kegiatan : Pembangunan Jalan Lingkungan Rabat Beton


Volume : 100 M x 1,5M x 0,15M
Waktu Pelaksanaan :

Harga Total Biaya


URAIAN Volume
Satuan (Rp) (Rp)

2 3 4 5

BAHAN
Semen @ 50 Kg 105 Zak 60,000 6,300,000
Pasir Beton 9 M3 300,000 2,700,000
Pasir Urug 7 M3 300,000 2,100,000
Batu Pecah 2/3 10 M3 300,000 3,000,000
Papan Bekisting 0 M3 850,000 -
Paku 2 Kg 20,000 40,000

14,140,000
ALAT
Papan Proyek 1 Ls 100,000 100,000
Prasasti 1 Ls 150,000 150,000
Roda Sorang 1 Buah 500,000 500,000
Meteran 5 m' 1 Buah 25,000 25,000
Sekop 2 Buah 75,000 150,000
Ember 27 Buah 10,000 270,000
Benang 3 Rol 5,000 15,000
Cangkul 1 Buah 70,000 70,000

1,280,000
UPAH
Pekerja 30 HOK 100,000 3,000,000
Tukang 9 HOK 120,000 1,080,000

4,080,000
Honor TPK
Honor TPK 1 Paket 500,000 500,000
500,000
20,000,000

PPN 10 % 1,943,000
Jumlah 21,373,000