LAPORAN BULANAN
BULAN KE - 8 ( DELAPAN )
PERIODE TANGGAL :
21 AGUSTUS - 17 SEPTEMBER 2017
RESUME PROGRESS BULANAN
PEMELIHARAAN BERKALA SITU PAMULANG
KOTA TANGERANG SELATAN
KONTRAKTOR : PT. ANDRE PUTRA MANDIRI
1 9 FEBRUARI - 5 MARET 2017 25 248 8.865 8.865 2.845 2.845 -6.020 (LAMBAT)
2 6 MARET - 2 APRIL 2017 53 220 10.357 19.222 13.419 16.264 -2.958 (LAMBAT)
3 3 APRIL - 30 APRIL 2017 81 192 20.572 39.794 24.839 41.103 1.309 (CEPAT)
4 1 MEI - 28 MEI 2017 109 164 23.324 63.118 20.764 61.867 -1.251 (LAMBAT)
5 29 MEI - 25 JUNI 2017 137 136 10.130 73.248 10.571 72.438 -0.811 (LAMBAT)
6 26 JUNI - 23 JULI 2017 165 108 2.903 76.151 1.281 73.719 -2.432 (LAMBAT)
7 24 JULI - 20 AGUSTUS 2017 193 80 2.903 79.054 1.060 74.779 -4.276 (LAMBAT)
8 21 AGUSTUS - 17 SEPTEMBER 2017 221 52 7.902 86.956 7.290 82.069 -4.887 (LAMBAT)
LAPORAN BULANAN
KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
BULAN KE : 8 ( DELAPAN )
PEMELIHARAAN BERKALA SITU PAMULANG KOTA TANGERANG SELATAN
PRIODE TGL : 21 AGUSTUS - 17 SEPTEMBER 2017
REALISASI
MC - 0 ( AMD 1 )
BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SAT.
BOBOT
VOLUME Volume Bobot Volume Bobot Volume Bobot
(%)
1 2 3 5 4 5 6 7 8 9 10
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi ls 1.00 6.583 0.957 6.298 - - 0.957 6.298
Sub Jumlah I 6.58 6.298 - 6.298
II PEKERJAAN SITU ###
2.1 Galian Tanah Dengan Alat Berat + Ponton m3 45,971.20 30.100 35,780.260 23.427 3,850.290 2.521 39,630.550 25.948
2.1a Galian Tanah Dengan Alat Berat + Ponton m3 8,094.04 5.300 - - - - - -
2.2 Buangan Tanah Hasil Galian (1 Km - 5 km) Diratakan Dan Dirapihkan m3 28,000.00 44.255 24,855.260 39.285 2,599.770 4.109 27,455.030 43.394
2.3 Buangan Tanah Hasil Galian (0 Km - 1 Km) Diratakan Dan Dirapihkan m3 26,065.24 13.763 10,925.000 5.769 1,250.520 0.660 12,175.520 6.429
Sub Jumlah II 93.42 68.481 7.290 75.771
JUMLAH TOTAL I+II 100.00 74.779 7.290 82.069
RENCANA PROGRES 86.956
DEVIASI -4.887
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN BULANAN
DEVIASI -4.887 %
NO. JENIS PEKERJAAN BOBOT (%) Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C-
-I
4.4
%
M
M
0.037 0.037
N
A
D
E
0
(
)
4.5 Pembesian 0.120 0.120
4.6 Bekisting Ringan, Expose Multiplex Tebal 9 mm (Pile cap Sheetpile) 0.044 0.044
4.7 Pengadaan & Pemasangan Pintu Sorong Baja 2 draad stang 0.757 0.379 0.379
4.8 Pasangan Batu Kali 1: 4 (Dinding spillway) 0.166 0.166
4.8a Pasangan Batu Kali 1: 4 (Dinding spillway) 0.138 0.138
4.9 Handrail Bangunan Pelimpah 0.051 0.051
4.9a Handrail Bangunan Pelimpah 0.002 0.002
V PERKUATAN DAN PERAPIHAN SEKELILING TANGGUL SITU
Pekerjaan Jogging Track
5.1
5.2
Pasir Pasang t = 5 cm
Pengadaan dan pemasangan Interblock (uk. 8x10.5x21 cm) abu-abu (pabrikasi)
0.306
4.098
REALISASI MC-0 % 0.153 0.153
0.585 0.585 0.585 0.585 0.585 0.585 0.585
5.3 Pengadaan dan pemasangan Kansteen (uk. 10x20x40 cm) Pabrikasi 1.423 0.237 0.237 0.237 0.237 0.237 0.237
Pekerjaan Dinding Penahan Tanah
5.4 Galian Konstruksi Manual 2.079 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 25.00%
5.5
5.6
Lantai kerja K.125 t=10cm
Beton Ready Mix K.225
0.473
9.642
REALISASI KONTRAK 0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071 1.071
5.7 Pembesian 9.965 1.107 1.107 1.107 1.107 1.107 1.107 1.107 1.107 1.107
5.8 Bekisting Ringan, Expose Multiplex Tebal 9 mm 3.400 0.378 0.378 0.378 0.378 0.378 0.378 0.378 0.378 0.378
5.9 Pipa PVC 2" 0.135 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015
5.1 Geotextil 0.185 0.021 0.021 0.021 0.021 0.021 0.021 0.021 0.021 0.021
5.11 Kerikil 0.018 0.018
5.12 Dowel Bar d. 19mm 0.047 0.047
Pekerjaan Collector Drain
5.13 Galian Konstruksi Manual 0.580 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072
5.14 Pengadaan dan pemasangan U-Ditch 7.683 1.098 1.098 1.098 1.098 1.098 1.098 1.098
Pekerjaan Saluaran Pembuang
5.15 Galian Konstruksi Manual 0.054 0.054
5.16 Pasangan Batu Kali 1: 4 (Pondasi) 0.805 0.402 0.402
Pekerjaan Gorong-gorong Collector Drain
5.17 Pasangan Batu Kali 1: 4 (Pondasi) 0.011 0.011
5.18 Pengadaan dan pemasangan gorong-gorong buis beton d.0,5 0.082 0.082
Pekerjaan Pengaman jalan
5.19 Pasangan Batu Kali 1: 4 (Pondasi) 0.883 0.221 0.221 0.221 0.221
0.00%
TOTAL 100.00
RENCANA PEKERJAAN (%) - 0.062 0.092 0.096 0.096 0.096 1.423 1.423 2.624 2.902 2.891 3.060 3.086 3.563 2.967 3.001 5.486 5.652 5.652 5.909 7.712 7.765 7.870 8.033 8.475 7.320 2.745
RENCANA PEKERJAAN KOMULAITF (%) - 0.062 0.154 0.250 0.345 0.441 1.864 3.286 5.910 8.812 11.703 14.764 17.849 21.412 24.379 27.380 32.866 38.518 44.170 50.079 57.791 65.556 73.427 81.460 89.935 97.255 100.000
RENCANA PEKERJAAN (%) - 0.062 1.014 2.241 2.241 6.714 7.297 7.283 7.270 8.131 3.617 2.964 2.847 4.689 5.119 4.197 2.973 2.973 2.866 3.524 4.706 4.927 3.447 2.276 2.732 2.551 1.249
RENCANA PEKERJAAN KOMULAITF (%) - 0.062 1.077 3.318 5.559 12.273 19.570 26.854 34.124 42.255 45.872 48.836 51.683 56.371 61.490 65.687 68.660 71.633 74.499 78.024 82.729 87.656 91.104 93.379 96.111 98.662 100.00
AMANDEMEN I (MC-0%) REALISASI PEKERJAAN (%) - - - - - 1.363 7.641 13.151 11.931 13.119
DEVIASI - (0.062) (1.077) (3.318) (5.559) (10.910) (10.566) (4.698) (0.037) 4.951
NO. JENIS PEKERJAAN BOBOT (%) Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke KETERANGAN
Alexsander Nandar, ST Ir. M.A. Sanusi, M.Si Arief Rachman, ST
NIP. 19780405 2005021 001 1 2 3 4 5 6 7 8 9 10 Leader11
Team 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Project Manager
JADWAL PELAKSANAAN
BOBOT BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4 BULAN KE - 5 BULAN KE - 6 BULAN KE - 7 BULAN KE - 8 BULAN KE - 9 BULAN KE - 10
NO. JENIS PEKERJAAN
[ % ] 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 KETERANGAN
WAKTU PELAKSANAAN 273 ( DUA RATUS TUJUH PULUH TIGA ) HARI KALENDER
I PEKERJAAN PERSIAPAN
100
1.1 Mobilisasi dan Demobilisasi Alat, Tenaga dan Bahan 6.583 0.329 0.329 0.329 0.329 0.329 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
-4.887
0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
RENCANA AMANDEMEN - II 90
PROGRES REALISASI (MC-1)
RENCANA AMANDEMEN - I AMANDEMEN - II (MC-1)
80
(MC-0)
II PEKERJAAN SITU
70
60
2.1 Galian Tanah Dengan Alat Berat + Ponton 30.100 1.710 1.710 1.710 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.594 0.594 0.594 0.594 0.594 0.594 0.594 0.594
M
-I
M
N
A
D
E
E
N
N
A
D
E
II
-
50
PROGRESS REALISASI
2.1a Galian Tanah Dengan Alat Berat + Ponton 5.300 AMANDEMEN - I (MC-0) 1.325 1.325 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382
40
0
94.700
Total Bobot Pekerjaan (%) - 0.329 0.329 2.039 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 4.458 0.329
Total Bobot Pekerjaan Komulatif (%) - 0.329 0.658 2.698 8.865 15.033 21.201 27.368 33.536 39.704 45.872 52.039 58.207 64.375 70.542 76.710 82.878 89.046 95.213 99.671 100.00
KONTRAK Bobot Realisasi Pekerjaan (%) 0.000 0.984 0.936 0.925 0.948
Bobot Realisasi Pekerjaan Komulatif (%) 0.000 0.984 1.920 2.845 3.793
Total Bobot Pekerjaan (%) - 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 7.896 9.220 9.220 9.220 9.220
Total Bobot Pekerjaan Komulatif (%) - 3.793 8.936 14.079 19.222 24.365 29.508 34.651 39.794 44.937 50.080 55.223 63.118 72.339 81.559 90.780 100.00
AMANDEMEN - I Bobot Realisasi Pekerjaan (%) 1.385 4.603 6.483 6.573 6.903 5.640 5.723 4.895 5.672 4.694 5.503 5.500 4.430
Bobot Realisasi Pekerjaan Komulatif (%) 3.793 5.178 9.781 16.264 22.837 29.740 35.380 41.103 45.998 51.670 56.364 61.867 67.367 71.797
Deviasi (%) -3.758 -4.298 -2.958 -1.528 0.232 0.729 1.309 1.061 1.590 1.141 -1.251 -4.972 -9.762
Total Bobot Pekerjaan (%) - 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.381 1.381 1.381 0.999
Total Bobot Pekerjaan Komulatif (%) - 71.797 72.523 73.248 73.974 74.700 75.426 76.15 76.877 77.603 78.328 79.05 81.030 83.005 84.980 86.96 88.931 90.906 92.882 94.86 96.238 97.620 99.001 100.00
AMANDEMEN - II Bobot Realisasi Pekerjaan (%) 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.099 1.576 1.789 1.940 1.985
Bobot Realisasi Pekerjaan Komulatif (%) 71.797 72.117 72.438 72.758 73.078 73.399 73.719 74.039 74.359 74.680 74.779 76.355 78.144 80.084 82.069
Deviasi (%) -0.405 -0.811 -1.216 -1.622 -2.027 -2.432 -2.838 -3.243 -3.649 -4.276 -4.675 -4.861 -4.896 -4.887
RENCANA AMANDEMEN - I
I PEKERJAAN PERSIAPAN (MC-0%)
100
1.1 Mobilisasi dan Demobilisasi Alat, Tenaga dan Bahan ls 6.583 0.329 0.329 0.329 0.329 0.329 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340
2.1 Galian Tanah Dengan Alat Berat + Ponton m3 30.100 1.710 1.710 1.710 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962
-I
M
M
N
N
A
D
E
E
50
2.1a Galian Tanah Dengan Alat Berat + Ponton m3 5.300 1.325 1.325 1.325 1.325
94.700
Total Bobot Pekerjaan (%) - 0.329 0.329 2.039 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 4.458 0.329
Total Bobot Pekerjaan Komulatif (%) - 0.329 0.658 2.698 8.865 15.033 21.201 27.368 33.536 39.704 45.872 52.039 58.207 64.375 70.542 76.710 82.878 89.046 95.213 99.671 100.00
KONTRAK Bobot Realisasi Pekerjaan (%) 0.000 0.984 0.936 0.925 0.948
Bobot Realisasi Pekerjaan Komulatif (%) 0.000 0.984 1.920 2.845 3.793
Total Bobot Pekerjaan (%) - 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 7.896 9.220 9.220 9.220 9.220
Total Bobot Pekerjaan Komulatif (%) - 3.793 8.936 14.079 19.222 24.365 29.508 34.651 39.794 44.937 50.080 55.223 63.118 72.339 81.559 90.780 100.00
AMANDEMEN - I Bobot Realisasi Pekerjaan (%) 1.385 4.603 6.483 6.573 6.903 5.640 5.723 4.895 5.672 4.694 5.503
Bobot Realisasi Pekerjaan Komulatif (%) 3.793 5.178 9.781 16.264 22.837 29.740 35.380 41.103 45.998 51.670 56.364 61.867
Deviasi (%) -3.758 -4.298 -2.958 -1.528 0.232 0.729 1.309 1.061 1.590 1.141 -1.251