PEMELIHARAAN BERKALA SITU PAMULANG

KOTA TANGERANG SELATAN

LAPORAN BULANAN

BULAN KE - 8 ( DELAPAN )
PERIODE TANGGAL :
21 AGUSTUS - 17 SEPTEMBER 2017
RESUME PROGRESS BULANAN
PEMELIHARAAN BERKALA SITU PAMULANG
KOTA TANGERANG SELATAN
KONTRAKTOR : PT. ANDRE PUTRA MANDIRI

BOBOT RENCANA BOBOT REALISASI


SISA WAKTU
WAKTU YANG (%) (%)
BULAN YANG AKAN DEVIASI
PERIODE TANGGAL TELAH DILALUI KETERANGAN
KE - DILALUI (%)
( HARI )
(HARI) BULAN INI KOMULATIF BULAN INI KOMULATIF

1 9 FEBRUARI - 5 MARET 2017 25 248 8.865 8.865 2.845 2.845 -6.020 (LAMBAT)

2 6 MARET - 2 APRIL 2017 53 220 10.357 19.222 13.419 16.264 -2.958 (LAMBAT)

3 3 APRIL - 30 APRIL 2017 81 192 20.572 39.794 24.839 41.103 1.309 (CEPAT)

4 1 MEI - 28 MEI 2017 109 164 23.324 63.118 20.764 61.867 -1.251 (LAMBAT)

5 29 MEI - 25 JUNI 2017 137 136 10.130 73.248 10.571 72.438 -0.811 (LAMBAT)

6 26 JUNI - 23 JULI 2017 165 108 2.903 76.151 1.281 73.719 -2.432 (LAMBAT)

7 24 JULI - 20 AGUSTUS 2017 193 80 2.903 79.054 1.060 74.779 -4.276 (LAMBAT)

8 21 AGUSTUS - 17 SEPTEMBER 2017 221 52 7.902 86.956 7.290 82.069 -4.887 (LAMBAT)
LAPORAN BULANAN
KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA

BULAN KE : 8 ( DELAPAN )
PEMELIHARAAN BERKALA SITU PAMULANG KOTA TANGERANG SELATAN
PRIODE TGL : 21 AGUSTUS - 17 SEPTEMBER 2017

REALISASI
MC - 0 ( AMD 1 )
BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SAT.
BOBOT
VOLUME Volume Bobot Volume Bobot Volume Bobot
(%)
1 2 3 5 4 5 6 7 8 9 10
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi ls 1.00 6.583 0.957 6.298 - - 0.957 6.298
Sub Jumlah I 6.58 6.298 - 6.298
II PEKERJAAN SITU ###
2.1 Galian Tanah Dengan Alat Berat + Ponton m3 45,971.20 30.100 35,780.260 23.427 3,850.290 2.521 39,630.550 25.948
2.1a Galian Tanah Dengan Alat Berat + Ponton m3 8,094.04 5.300 - - - - - -
2.2 Buangan Tanah Hasil Galian (1 Km - 5 km) Diratakan Dan Dirapihkan m3 28,000.00 44.255 24,855.260 39.285 2,599.770 4.109 27,455.030 43.394
2.3 Buangan Tanah Hasil Galian (0 Km - 1 Km) Diratakan Dan Dirapihkan m3 26,065.24 13.763 10,925.000 5.769 1,250.520 0.660 12,175.520 6.429
Sub Jumlah II 93.42 68.481 7.290 75.771
JUMLAH TOTAL I+II 100.00 74.779 7.290 82.069
RENCANA PROGRES 86.956
DEVIASI -4.887
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN BULANAN

PEKERJAAN : PEMELIHARAAN BERKALA SITU PAMULANG KOTA TANGERANG SELATAN


KONTRAKTOR : PT. ANDRE PUTRA MANDIRI
KONTRAK No./Tgl : HK.02.03/SATKER OPSDA CC/PPK OPSDA II/II/164 Tanggal 9 Februari 2017
SPMK No./Tgl : HK.02.03/SPL/SATKER OPSDA CC/PPK OPSDA II/II/164.b Tanggal 9 Februari 2017
BULAN KE : 8 ( DELAPAN )
PRIODE TGL : 21 AGUSTUS - 17 SEPTEMBER 2017

BOBOT PRESTASI REALISASI


MC-0
(AMD-I) S/D BULAN
BULAN LALU BULAN INI KETERANGAN
NO. JENIS PEKERJAAN INI
TOTAL
Bobot Bobot Bobot
BOBOT
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN 6.583 6.298 - 6.298 (LAMBAT)

II PEKERJAAN SITU 93.417 68.481 7.290 75.771

JUMLAH TOTAL I+II 100.000 74.779 7.290 82.069

PROGRESS RENCANA S/D BULAN KE-8 ( DELAPAN ) 86.956 %

PROGRESS REALISASI S/D BULAN KE-8 ( DELAPAN ) 82.069 %

DEVIASI -4.887 %

Tangerang Selatan, 18 September 2017

Menyetujui, Diperiksa Oleh, Dibuat Oleh,


Direksi Pekerjaan Konsultan Supervisi Perorangan Penyedia Jasa
Pemeliharaan Berkala Situ Pamulang PT. ANDRE PUTRA MANDIRI
Kota Tangerang Selatan

Sudarto, A.Md Endang Kusnadi, ST, MT Paulina Sadoek, ST


NIP. 19630710 200212 1 005 Tenaga Ahli I Project Manager
JADUAL PELAKSANAAN PEKERJAAN REVITALISASI SITU GEDONG DI KAB. BOGOR
Balai : Balai Besar Wilayah Sungai Ciliwung-Cisadane
Satuan Kerja : NVT Pelaksanaan Jaringan Sumber Daya Air Sungai Ciliwung Cisadane
PPK : Prasarana Konservasi Jaringan Sumber Daya Air
Tahun Anggaran : 2015

BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5 BULAN KE 6

NO. JENIS PEKERJAAN BOBOT (%) Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke KETERANGAN

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

I PEKERJAAN PERSIAPAN 100.00%


1.1 Mobilisasi dan Demobilisasi Alat 1.618 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 0.062 Waktu Pelaksanaan :
1.2 Pembersihan Lahan 0.200 0.033 0.033 0.033 0.033 0.033 0.033 180 (seratus delapan puluh )
1.3 Papan Nama Kegiatan 0.030 0.030 Hari Kalender
1.4 Papan Peringatan 0.016 0.016
II PEKERJAAN OPTIMALISASI TAMPUNGAN SITU
2.1 Galian Tanah Dengan Alat Berat + Ponton + Ponton Angkut 11.977 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921
2.1a Galian Tanah Dengan Alat Berat + Ponton + Ponton Angkut 0.012 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
2.2 Buangan Tanah Hasil galian (50 m - 10 km) 15.891 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222 1.222
2.2a Buangan Tanah Hasil galian (50 m - 10 km) 0.016 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
III PERKUATAN TUBUH BENDUNG
3.1
3.1a
Pengadaan PC Flat Sheet Pile Type I 50 x 32 cm panjang 12 m
Pengadaan PC Flat Sheet Pile Type I 50 x 32 cm panjang 12 m
21.620 4.324 4.324 4.324 4.324 4.324 RENCANA AMANDEMEN I (MC-0)
0.366 0.073 0.073 0.073 0.073 0.073
3.2 Pemancangan PC Flat Sheet Pile Type I 50 x 32 cm panjang 12 m 1.868 0.374 0.374 0.374 0.374 0.374
3.2a Pengadaan Back Pile BSQ (35x35) panjang 6 m 0.032 0.006 0.006 0.006 0.006 0.006
3.3 Pengadaan Back Pile BSQ (35x35) panjang 6 m 0.374 0.075 0.075 0.075 0.075 0.075
3.4 Pemancangan Back Pile BSQ (35x35) panjang 6 m 0.119 0.024 0.024 0.024 0.024 0.024
3.5 Pengadaan & Pemasangan Angkur Strand Baja d.12,7 mm 0.064 0.016 0.014 0.011 0.005
3.5a Pengadaan & Pemasangan Angkur Strand Baja d.12,7 mm 0.058 0.014 0.014 0.014 0.014 75.00%
3.6 Pengadaan & Pemasangan pipa HDPE d.20 mm 0.278 0.069 0.069 0.069 0.069
3.6a Pengadaan & Pemasangan pipa HDPE d.20 mm 0.011 0.003 0.003 0.003 0.003
3.7 Pengadaan & Pemasangan Besi Canal UNP 250 mm (klem sling) 0.310 0.077 0.066 0.055 0.041
3.8 Beton Ready Mix K.225 (Pile cap Sheetpile) 0.257 0.086 0.086 0.086
3.8a Beton Ready Mix K.225 (Pile cap Sheetpile) 0.100 0.033 0.033 0.033
3.9 Beton Ready Mix K.225 (Pile Cap Backpile) 0.048 0.024 0.024
3.10 Pembesian (Pile cap Sheetpile) 0.175 0.087 0.087
3.10a Pembesian (Pile cap Sheetpile) 0.248 0.124 0.124
3.11 Pembesian (Pile Cap Backpile) 0.024 0.024
3.11a Pembesian (Pile Cap Backpile) 0.006 0.006
3.12 Bekisting Ringan, Expose Multiplex Tebal 9 mm (Pile cap Sheetpile) 0.332 0.166 0.166
3.13 Bekisting Ringan, Expose Multiplex Tebal 9 mm (Pile Cap Backpile) 0.002 0.002
3.13a Bekisting Ringan, Expose Multiplex Tebal 9 mm (Pile Cap Backpile) 0.061 0.061
IV PEKERJAAN KONSTRUKSI
Pekerjaan Bangunan Pelimpah
4.1 Pasangan Batu Kali 1: 4 (Pondasi) 0.419 0.140 0.140 0.140
4.1a Pasangan Batu Kali 1: 4 (Pondasi) 0.125 0.042 0.042 0.042 50.00%
4.2 Beton Ready Mix K.225 (Pelat Bangunan Pelimpah) 0.144 0.144
4.2a Beton Ready Mix K.225 (Pelat Bangunan Pelimpah) 0.008 0.008
4.3 Beton Ready Mix K.225 (Pelat Injak) 0.007 0.007
Beton Ready Mix K.225 (Pilar Spillway)

C-
-I
4.4

%
M

M
0.037 0.037

N
A

D
E

0
(

)
4.5 Pembesian 0.120 0.120
4.6 Bekisting Ringan, Expose Multiplex Tebal 9 mm (Pile cap Sheetpile) 0.044 0.044
4.7 Pengadaan & Pemasangan Pintu Sorong Baja 2 draad stang 0.757 0.379 0.379
4.8 Pasangan Batu Kali 1: 4 (Dinding spillway) 0.166 0.166
4.8a Pasangan Batu Kali 1: 4 (Dinding spillway) 0.138 0.138
4.9 Handrail Bangunan Pelimpah 0.051 0.051
4.9a Handrail Bangunan Pelimpah 0.002 0.002
V PERKUATAN DAN PERAPIHAN SEKELILING TANGGUL SITU
Pekerjaan Jogging Track
5.1
5.2
Pasir Pasang t = 5 cm
Pengadaan dan pemasangan Interblock (uk. 8x10.5x21 cm) abu-abu (pabrikasi)
0.306
4.098
REALISASI MC-0 % 0.153 0.153
0.585 0.585 0.585 0.585 0.585 0.585 0.585
5.3 Pengadaan dan pemasangan Kansteen (uk. 10x20x40 cm) Pabrikasi 1.423 0.237 0.237 0.237 0.237 0.237 0.237
Pekerjaan Dinding Penahan Tanah
5.4 Galian Konstruksi Manual 2.079 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 25.00%
5.5
5.6
Lantai kerja K.125 t=10cm
Beton Ready Mix K.225
0.473
9.642
REALISASI KONTRAK 0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071
0.059
1.071 1.071
5.7 Pembesian 9.965 1.107 1.107 1.107 1.107 1.107 1.107 1.107 1.107 1.107
5.8 Bekisting Ringan, Expose Multiplex Tebal 9 mm 3.400 0.378 0.378 0.378 0.378 0.378 0.378 0.378 0.378 0.378
5.9 Pipa PVC 2" 0.135 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015
5.1 Geotextil 0.185 0.021 0.021 0.021 0.021 0.021 0.021 0.021 0.021 0.021
5.11 Kerikil 0.018 0.018
5.12 Dowel Bar d. 19mm 0.047 0.047
Pekerjaan Collector Drain
5.13 Galian Konstruksi Manual 0.580 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072
5.14 Pengadaan dan pemasangan U-Ditch 7.683 1.098 1.098 1.098 1.098 1.098 1.098 1.098
Pekerjaan Saluaran Pembuang
5.15 Galian Konstruksi Manual 0.054 0.054
5.16 Pasangan Batu Kali 1: 4 (Pondasi) 0.805 0.402 0.402
Pekerjaan Gorong-gorong Collector Drain
5.17 Pasangan Batu Kali 1: 4 (Pondasi) 0.011 0.011
5.18 Pengadaan dan pemasangan gorong-gorong buis beton d.0,5 0.082 0.082
Pekerjaan Pengaman jalan
5.19 Pasangan Batu Kali 1: 4 (Pondasi) 0.883 0.221 0.221 0.221 0.221
0.00%
TOTAL 100.00

RENCANA PEKERJAAN (%) - 0.062 0.092 0.096 0.096 0.096 1.423 1.423 2.624 2.902 2.891 3.060 3.086 3.563 2.967 3.001 5.486 5.652 5.652 5.909 7.712 7.765 7.870 8.033 8.475 7.320 2.745

RENCANA PEKERJAAN KOMULAITF (%) - 0.062 0.154 0.250 0.345 0.441 1.864 3.286 5.910 8.812 11.703 14.764 17.849 21.412 24.379 27.380 32.866 38.518 44.170 50.079 57.791 65.556 73.427 81.460 89.935 97.255 100.000

KONTRAK REALISASI PEKERJAAN (%) - 0.062 0.092 0.096 0.096 0.096

REALISASI PEKERJAAN KOMULAITF (%) - 0.062 0.154 0.250 0.345 0.345

DEVIASI - - (0.000) (0.000) (0.000) (0.096)

RENCANA PEKERJAAN (%) - 0.062 1.014 2.241 2.241 6.714 7.297 7.283 7.270 8.131 3.617 2.964 2.847 4.689 5.119 4.197 2.973 2.973 2.866 3.524 4.706 4.927 3.447 2.276 2.732 2.551 1.249

RENCANA PEKERJAAN KOMULAITF (%) - 0.062 1.077 3.318 5.559 12.273 19.570 26.854 34.124 42.255 45.872 48.836 51.683 56.371 61.490 65.687 68.660 71.633 74.499 78.024 82.729 87.656 91.104 93.379 96.111 98.662 100.00

AMANDEMEN I (MC-0%) REALISASI PEKERJAAN (%) - - - - - 1.363 7.641 13.151 11.931 13.119

REALISASI PEKERJAAN KOMULAITF (%) - - - - - 1.363 9.004 22.156 34.086 47.205

DEVIASI - (0.062) (1.077) (3.318) (5.559) (10.910) (10.566) (4.698) (0.037) 4.951

Menyetujui, Diperiksa Oleh, Dibuat Oleh,


Pejabat Pembuat Komitmen Konsultan Supervisi Penyedia Jasa
Prasarana Konservasi Sumber Daya Air PT. Widya Graga Asana PT. Daya Hasta Multi Perkasa
SNVT Pelaksanaan Jaringan Sumber Air Ciliwung-Cisadane

Alexsander Nandar, ST Ir. M.A. Sanusi, M.Si Arief Rachman, ST


NIP. 19780405 2005021 001 Team Leader Project Manager
Menyetujui, Diperiksa Oleh, Dibuat Oleh,
Pejabat Pembuat Komitmen Konsultan Supervisi Penyedia Jasa
Prasarana Konservasi Sumber Daya Air PT. Widya Graga Asana PT. Daya Hasta Multi Perkasa
SNVT Pelaksanaan Jaringan Sumber Air Ciliwung-Cisadane

BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5 BULAN KE 6

NO. JENIS PEKERJAAN BOBOT (%) Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke Minggu ke KETERANGAN
Alexsander Nandar, ST Ir. M.A. Sanusi, M.Si Arief Rachman, ST
NIP. 19780405 2005021 001 1 2 3 4 5 6 7 8 9 10 Leader11
Team 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Project Manager
JADWAL PELAKSANAAN

Pekerjaan : Pemeliharaan Berkala Situ Pamulang Kota Tangerang Selatan


Satker : Operasi dan Pemeliharaan SDA Ciliwung-Cisadane
PPK : OP SDA II
Tahun Anggaran : 2017

BOBOT BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4 BULAN KE - 5 BULAN KE - 6 BULAN KE - 7 BULAN KE - 8 BULAN KE - 9 BULAN KE - 10
NO. JENIS PEKERJAAN
[ % ] 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 KETERANGAN

WAKTU PELAKSANAAN 273 ( DUA RATUS TUJUH PULUH TIGA ) HARI KALENDER

I PEKERJAAN PERSIAPAN

100

1.1 Mobilisasi dan Demobilisasi Alat, Tenaga dan Bahan 6.583 0.329 0.329 0.329 0.329 0.329 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
-4.887
0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
RENCANA AMANDEMEN - II 90
PROGRES REALISASI (MC-1)
RENCANA AMANDEMEN - I AMANDEMEN - II (MC-1)
80
(MC-0)
II PEKERJAAN SITU
70

60
2.1 Galian Tanah Dengan Alat Berat + Ponton 30.100 1.710 1.710 1.710 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.527 0.594 0.594 0.594 0.594 0.594 0.594 0.594 0.594

M
-I
M

N
A

D
E

E
N

N
A

D
E

II
-
50
PROGRESS REALISASI
2.1a Galian Tanah Dengan Alat Berat + Ponton 5.300 AMANDEMEN - I (MC-0) 1.325 1.325 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382 0.382
40

PROGRES RENCANA KONTRAK 30


2.2 Buangan Tanah Hasil Galian (1 Km - 5 Km) Diratakan Dan Dirapihkan 44.255 4.128 4.128 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842
20

PROGRES REALISASI KONTRAK


10
2.3 Buangan Tanah Hasil Galian (0 Km - 1 Km) Diratakan Dan Dirapihkan 13.763 2.753 2.753 2.753 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.976 0.976 0.976 0.976 0.976 0.976 0.976 0.976 0.976 0.976 0.976 0.976

0
94.700

Total Bobot Pekerjaan (%) - 0.329 0.329 2.039 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 4.458 0.329

Total Bobot Pekerjaan Komulatif (%) - 0.329 0.658 2.698 8.865 15.033 21.201 27.368 33.536 39.704 45.872 52.039 58.207 64.375 70.542 76.710 82.878 89.046 95.213 99.671 100.00

KONTRAK Bobot Realisasi Pekerjaan (%) 0.000 0.984 0.936 0.925 0.948

Bobot Realisasi Pekerjaan Komulatif (%) 0.000 0.984 1.920 2.845 3.793

Deviasi (%) -0.329 0.326 -0.778 -6.020 -11.240

Total Bobot Pekerjaan (%) - 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 7.896 9.220 9.220 9.220 9.220

Total Bobot Pekerjaan Komulatif (%) - 3.793 8.936 14.079 19.222 24.365 29.508 34.651 39.794 44.937 50.080 55.223 63.118 72.339 81.559 90.780 100.00

AMANDEMEN - I Bobot Realisasi Pekerjaan (%) 1.385 4.603 6.483 6.573 6.903 5.640 5.723 4.895 5.672 4.694 5.503 5.500 4.430

Bobot Realisasi Pekerjaan Komulatif (%) 3.793 5.178 9.781 16.264 22.837 29.740 35.380 41.103 45.998 51.670 56.364 61.867 67.367 71.797

Deviasi (%) -3.758 -4.298 -2.958 -1.528 0.232 0.729 1.309 1.061 1.590 1.141 -1.251 -4.972 -9.762

Total Bobot Pekerjaan (%) - 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 0.726 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.381 1.381 1.381 0.999

Total Bobot Pekerjaan Komulatif (%) - 71.797 72.523 73.248 73.974 74.700 75.426 76.15 76.877 77.603 78.328 79.05 81.030 83.005 84.980 86.96 88.931 90.906 92.882 94.86 96.238 97.620 99.001 100.00

AMANDEMEN - II Bobot Realisasi Pekerjaan (%) 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.320 0.099 1.576 1.789 1.940 1.985

Bobot Realisasi Pekerjaan Komulatif (%) 71.797 72.117 72.438 72.758 73.078 73.399 73.719 74.039 74.359 74.680 74.779 76.355 78.144 80.084 82.069

Deviasi (%) -0.405 -0.811 -1.216 -1.622 -2.027 -2.432 -2.838 -3.243 -3.649 -4.276 -4.675 -4.861 -4.896 -4.887

Menyetujui, Diperiksa Oleh Dibuat Oleh


Direksi Pekerjaan Konsultan Supervisi Perorangan Kontraktor Pelaksana
Pemeliharaan Berkala Situ Pamulang PT. ANDRE PUTRA MANDIRI
Kota Tangerang Selatan

Sudarto, A.Md Endang Kusnadi, ST, MT Paulina Sadoek, ST


NIP. 19630710 200212 1 005 Tenaga Ahli I Project Manager
JADWAL PELAKSANAAN

Pekerjaan : Pemeliharaan Berkala Situ Pamulang Kota Tangerang Selatan


Satker : Operasi dan Pemeliharaan SDA Ciliwung-Cisadane
PPK : OP SDA II
Tahun Anggaran : 2017

BOBOT BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4 BULAN KE - 5


NO. JENIS PEKERJAAN SAT
[ % ] 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 KETERANGAN

WAKTU PELAKSANAAN 150 ( SERATUS LIMA PULUH ) HARI KALENDER

RENCANA AMANDEMEN - I
I PEKERJAAN PERSIAPAN (MC-0%)
100

1.1 Mobilisasi dan Demobilisasi Alat, Tenaga dan Bahan ls 6.583 0.329 0.329 0.329 0.329 0.329 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340 0.340

PROGRES REALISASI -1.251 75


II PEKERJAAN SITU AMANDEMEN - I (MC-0%)

2.1 Galian Tanah Dengan Alat Berat + Ponton m3 30.100 1.710 1.710 1.710 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962 1.962

-I
M

M
N

N
A

D
E

E
50

2.1a Galian Tanah Dengan Alat Berat + Ponton m3 5.300 1.325 1.325 1.325 1.325

PROGRES RENCANA KONTRAK


25
2.2 Buangan Tanah Hasil Galian (1 Km - 5 Km) Diratakan Dan Dirapihkan m3 44.255 4.128 4.128 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842 2.842

PROGRES REALISASI KONTRAK


2.3 Buangan Tanah Hasil Galian (0 Km - 1 Km) Diratakan Dan Dirapihkan m3 13.763 2.753 2.753 2.753 2.753 2.753
0

94.700

Total Bobot Pekerjaan (%) - 0.329 0.329 2.039 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 6.168 4.458 0.329

Total Bobot Pekerjaan Komulatif (%) - 0.329 0.658 2.698 8.865 15.033 21.201 27.368 33.536 39.704 45.872 52.039 58.207 64.375 70.542 76.710 82.878 89.046 95.213 99.671 100.00

KONTRAK Bobot Realisasi Pekerjaan (%) 0.000 0.984 0.936 0.925 0.948

Bobot Realisasi Pekerjaan Komulatif (%) 0.000 0.984 1.920 2.845 3.793

Deviasi (%) -0.329 0.326 -0.778 -6.020 -11.240

Total Bobot Pekerjaan (%) - 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 5.143 7.896 9.220 9.220 9.220 9.220

Total Bobot Pekerjaan Komulatif (%) - 3.793 8.936 14.079 19.222 24.365 29.508 34.651 39.794 44.937 50.080 55.223 63.118 72.339 81.559 90.780 100.00

AMANDEMEN - I Bobot Realisasi Pekerjaan (%) 1.385 4.603 6.483 6.573 6.903 5.640 5.723 4.895 5.672 4.694 5.503

Bobot Realisasi Pekerjaan Komulatif (%) 3.793 5.178 9.781 16.264 22.837 29.740 35.380 41.103 45.998 51.670 56.364 61.867

Deviasi (%) -3.758 -4.298 -2.958 -1.528 0.232 0.729 1.309 1.061 1.590 1.141 -1.251

Menyetujui Diperiksa Oleh Dibuat Oleh


0.000 Konsultan Supervisi Perorangan Kontraktor Pelaksana
Kota Tangerang Selatan PT. ANDRE PUTRA MANDIRI
0.000

NIP. 19630710 200212 1 005 Tenaga Ahli I Paulina Sadoek, ST


0.000 0.000 Project Manager