DAFTAR HARGA BAHAN, ALAT, UPAH

HARGA
URAIAN Satuan SATUAN
<Rp.>
Bahan
1 Paku kg 22,000
2 Pasir urug m3 145,000
3 Batu Kali m3 175,000
4 Semen 40 kg zak 58,000
5 Semen warna zak 125,000
6 Pasir pasang m3 145,000
7 Koral 2/3 m3 350,000
8 Besi beton Ø 6 lj 55,000
9 Besi beton Ø 10 lj 85,000
10 Bendrat kg 25,000
11 Begisting lbr 25,000
12 Batu bata bh 700
13 Kayu kusen bh 200,000
14 Kayu 6/10 bh 205,000
15 Kayu 5/7 bendel 250,000
16 Kayu 3/4 bendel 260,000
16 Tripleks lbr 75,000
17 Meni kg 18,500
18 Papan 2/30 Gipsun lbr 85,000
19 Genteng bh 3,000
20 Genteng Bubungan bh 6,000
21 Kalsibot lbr 75,000
22 Keramik 20 x 25 dos 70,000
23 Keramik 20 x 20 dos 75,000
24 Keras gosok lbr 8,000
25 Tiner kg 15,000
26 Kaca 5 mm m2 100,000
27 Cat kayu kg 65,000
28 Plamir kg 33,000
29 Cat tembok kg 30,000
30 Closed bh 280,000
31 Pipa PVC 4" Ljr 250,000
32 L PVC 4" bh 25,000
33 Pipa PVC 3/4" Ljr 45,000
34 L PVC 3/4" bh 8,000
35 Pintu KM bh 380,000
36 Dempul kg 5,000
37 Avor Pembuangan bh 25,000
38 Avor Bak bh 20,000
39 Kran Air bh 30,000
40 Buis Beton Ø 1,0 m bh 145,000
HARGA
URAIAN Satuan SATUAN
<Rp.>
41 Tutup Buis Beton Ø 1,0 m bh 110,000
Alat
1 Meteran bh 48,000
2 Benang bh 7,000
3 Timba bh 11,000

Upah
1 Pekerja Oh 80,000
2 Tukang Oh 90,000
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME

1. Pemasangan bowplank Panjang : 24 m = 24 m'

2. Galian tanah pondasi


Panjang galian = 4.5 m
a. Galian Pondasi Utama
Lebar galian = 0.6 m
Tinggi galian = 0.7 m
0,6

1.89 m3
0,70

b. Galian Pondasi Teras

Panjang galian = 3.6 m


0,65
0.35 Lebar galian = 0.5 m
0.4
0,50 0.40.11
Tinggi galian = 0.65 m

1.17 m3

= 3.06 m3

3. Urugan tanah kembali 1/4 galian tanah = 0.765 m3

4. Urugan pasir di bawah pondasi Bangunan induk


Panjang = 4.5 m
Lebar = 0.7 m
0.05
Tinggi = 0.05 m = 0.1575 m3
0.7

Teras
0.05
Panjang = 3.6 m
Lebar = 0.5 m
0.5
1.1
Tinggi = 0.05 m = 0.09 m3
Volume tot 0.2475 m3
5. Anstamping Bangunan induk
Panjang = 4.5 m
Lebar = 0.7 m
0.2 Tinggi = 0.2 m = 0.63 m3
0,7
Teras
1.1 Panjang = 3.6 m
Lebar = 0.5 m
0.2 Tinggi = 0.2 m = 0.36 m3
0.5 Volume total
6. Pasangan batu 0.99 m3

0,3 Bangunan Utama


Luas penampamg = ((0.3+0.5)/2)*0,7
= 0.2 m2
0.45 Volume 1 = Luas penampang x Panjang
0,20 x 6 = 0.9 m3

0,50
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME
0,50
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME

Volume total
0.900 m3
Bangunan rolag
Luas Penampang = 6 x 0,11
0.396 m2 = 0.396 m2

Pekerjaan beton bertulang


1. Beton sloof 15/17 Panjang = 4.5 m
Luas penampang = 0.026 m2 Beton 0.11 m3
Beton 0,15

0,17
Besi Ø 8
Besi Kebutuhan Begel (39/0,15)+1 31 bh Besi Ø 8 19.84 m
Panjang
0,15 ((0,15+0,17)X2)) 0.64 m
Kebutuhan besi 19.8 m
0,17
Besi Ø 10
Panjang 39 4.50 m Besi Ø 10 18.00 m
Kebutuhan besi 39*4 18 m
Begisting
0,2 Panjang = 4.5 m
Luas penampang = 0.4 m2 Begisting 1.80 m2
0,2 (0,2+0,2)

2. Kolom praktis 15/15 Tinggi = 2.8 m


Luas penampang = 0.023 m2 Beton 0.25 m3
Beton Jumlah = 4 buah
0,15
Besi Ø 8
0,15
Kebutuhan Begel ((4/0,15)+1)*13 79 bh Besi Ø 8 47.20 m
Panjang
((0,15+0,15)X2) 0.60 m
Besi Kebutuhan besi 47.2 m
0,15
Besi Ø 10
0,15
Panjang (13*4) 16.00 m Besi Ø 10 64.00 m
Kebutuhan besi
(13*4)*4 64 m
Begisting
Panjang = 11.2 m
0,2 Luas penampang = 0.4 m2 Begisting 4.48 m2
(0,2+0,2)
0,2
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME
3. Ring balok 15/17 Panjang = 4.5 m
Luas penampang = 0.023 m2 Beton 0.10 m3
0,15

Beton 0,17 Besi Ø 8


Kebutuhan Begel ((39/0,15)+1 31 bh Besi Ø 8 19.84 m
Panjang
((0,15+0,15)X2) 0.64 m
Besi 0,15 Kebutuhan besi 19.8 m

0,17 Besi Ø 10
Panjang 4.50 m Besi Ø 10 18.00 m
Kebutuhan besi
39*4 18 m
Begisting
0,2 Panjang = 4.5 m
Luas penampang = 0.4 m2 Begisting 1.80 m2
0,2 (0,2+0,2)

4. Gewel 15/17 Panjang = 5.77 m


Luas penampang = 0.0255 m2 Beton 0.15 m3
Beton Jumlah = 1 buah
0,15

0,17 Besi Ø 8
Kebutuhan Begel ((7/0,15)+1)*3 39 bh Besi Ø 8 25.27 m
Panjang
Besi ((0,15+0,17)X2) 0.64 m
0,15 Kebutuhan besi 25.27 m

0,17 Besi Ø 10
Panjang (7*1) 5.77 m Besi Ø 10 23.09 m
Kebutuhan besi
(7*1)*4*3 23.08801 m

Begisting 0,2
Panjang = 5.772002 m
0,2 Luas penampang = 0.4 m2 Begisting 2.31 m2
(0,2+0,2)

5. Balok konsol + Pengaku 15/17


Panjang = m
Luas penampang = m2 Beton 0.00 m3
Beton 0,15 Jumlah = buah

0,17
Besi Ø 8
Kebutuhan Begel ((4/0,10)+1)*5 bh Besi Ø 8 0.00 m
Besi Panjang
0,15 ((0,15+0,17)X2) 0.64 m
Kebutuhan besi 0.0 m
0,17
Besi Ø 12
Panjang (4*1) 0.00 m Besi Ø 12 0.00 m
Kebutuhan besi
(4*1)*5*5 0 m
Begisting 0,2
Panjang = 0 m
0,2 Luas penampang = 0.55 m2 Begisting 0.00 m2
(0,2+0,2+0,15)

Bambu (2/0,4)*5 = 0 btg Bambu 0.00 btg

6. Pekerjaan kuda-kuda
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME
Sudut A=B=37
C
E F CD=DC = 1
A B
AD=BD = 0.75 Volume kuda-kuda beton 15/20
AC = (AD^2+CD^2)^0,5 AC=CB
D
AC = (3^2+2^2)^0,5 = 4.272 M
5m
AC = 2.136 m ED=DF
ED = 1/2 AC = 2.136 M
ED = 1.068 m CD
= 2.000 M
AB
= 6.15 M
Kabupaten : Situbondo Jenis Prasarana : Kamar Mandi PAUD
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Setonggek
Desa : Cipta Desa Volume : 22 x 6 m
GAMBAR HITUNGAN VOLUME
Pekerjaan dinding/ Pasangan bata
1. Bangunan induk 1:4 Panjang = 4.5 m
Tinggi = 2.28 m
Luas = 10.26 m

= 9.98 m2

2. Pas kuda - kuda gewel Tinggi = 1.000 m


Panjang = 1.5 m = 0.750 m2
jumlah = 1 bh Total 10.730 m2
Volume = 11.126 m2

Pekerjaan Kusen 6/15

0.4.
3 Jumlah = 1 buah
0.7 Jendela
J1
Panjang = = 2.2 m
Luas = 0.28 m2
Panjang total Kayu
2.2 m

10% kayu hilang


0.22 m
2.42 m
Volume 0.022 m3
2. Daun jendela = kaca Luas Kaca
Luas Kaca J1
Jumlah = 1 buah
Tinggi = 0.7 m
Lebar = 0.4 m Volume = 0.280 m2
Vol total = 0.2800 m3
Pekerjaan rangka atap
1. Mamasang atap
Lebar = 3.00 m
Panjang = 3.00 m
Luas = 9.000 m
3. Liskplank papan 3/20 Panjang = 12.0 m Volume = 3.00 m
4. Papan ruiter Panjang = 3.00 m Volume = 3 m
5. Kayu Balok tembok, nok dan gord Panjang = 3.00 m Volume = 0.029 m3
6. Kayu plafon
Luas Bangunan (8*14)
24 m2
Luas plafon Volume = 24.00 m2

Pekerjaan lantai
1. Urugan pasir tebal = 0.1 m
Luas lantai = luas urugan pasir Volume = 0.225 m3
= 2 m2
2. Pasang tegel polos 40 x 40 Luas lantai = 9 m2 Volume = 9 m2
3. Batu dinding Luas lantai = m3 Volume = 0 m2
Pekerjaan plesteran

Plesteran dinding 1:4 Luas = 19.960 m2 Volume = 29.960 m2


Gewel Luas 10.000 m2

Pekerjaan cat
Dinding dan = 53.960 m2 = 53.960 m2
Liskplank = 2 m2 = 2 m2
Kusen = 0.594 m2 = 0.594 m2
ANALISA PERHITUNGAN GEDUNG (KAMAR MANDI)
ANALISA BANGUNAN SNI ( Standar Nasional Indonesia )

Harga sat. Bahan Upah Total


No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
1 Pemasangan bowplank
Kayu 0.0120 24.0 m1 0.288 m3 25,000 7,200 7,200
Papan 0.0070 24.0 m1 0.168 m3 25,000 4,200 4,200
Paku 0.0200 24.0 m1 0.48 kg 22,000 10,560 10,560
Pekerja 0.1000 24.0 m1 2.40 Oh 80,000 192,000 192,000
Tukang 0.1000 24.0 m1 2.40 Oh 90,000 216,000 216,000
Sub total 429,960
2 Galian Tanah pondasi untuk tiap m3
Pekerja 0.4000 3.06 m3 1.22 HOK 80,000 97,920 97,920
Sub total 97,920
3 Timbunan Kembali untuk tiap m3
Pekerja 0.1920 0.76 m3 0.15 HOK 80,000 11,750 11,750
Sub total 11,750
4 Urugan pasir bawah temasuk penyiramannya ( m3 )
Pasir Urug 1.2000 0.47 m3 0.57 m3 145,000 82,215 82,215
Pekerja 0.3000 0.47 m3 0.14 HOK 80,000 11,340 11,340
Sub total 93,555
5 Pekerjaan Astampeng
Batu 1.2000 0.99 m3 1.19 m3 175,000 207,900 207,900
Pasir Urug 0.3000 0.99 m3 0.30 m3 145,000 43,065 43,065
Tukang 0.390 0.99 m3 0.39 Oh 90,000 34,749 34,749
Pekerja 0.780 0.99 m3 0.77 Oh 80,000 61,776 61,776
Sub total 347,490
6 Pas Batu Kali Pondasi 1 : 5 untuk tiap m3
Batu Belah 1.100 0.90 m3 0.99 m3 175,000 173,250 173,250
Semen 40 kg 3.400 0.90 m3 3.06 zak 58,000 177,480 177,480
Pasir Pasang 0.544 0.90 m3 0.49 m3 145,000 70,992 70,992
Tukang 0.600 0.90 m3 0.54 Oh 90,000 48,600 48,600
Pekerja 1.500 0.90 m3 1.35 Oh 80,000 108,000 108,000
Sub total 578,322
7 Pekerjaan Beton
a Pekerjaan Beton Sloof 15/17per m'
Pek Beton 1:2:3 untuk tiap m3
Semen 40 kg 8.4000 0.11 m3 0.96 zak 58,000 55,906 55,906
Pasir Pasang 0.5400 0.11 m3 0.06 m3 145,000 8,985 8,985
Kerikil 2/3 0.8100 0.11 m3 0.09 m3 350,000 32,532 32,532
Tukang batu 0.3500 0.11 m3 0.04 Oh 90,000 3,615 3,615
Pekerja 2.0000 0.11 m3 0.23 Oh 80,000 18,360 18,360

Pembesian Begel dengan besi polos dia 8 mm /m' (An. Membuat)


Besi Ø 6 mm 1.0500 7.80 kg 0.74 LJ 55,000 40,935 40,935
Bendrat 0.0150 7.80 kg 0.12 Kg 25,000 2,924 2,924
Pekerja 0.0070 7.80 kg 0.05 Oh 80,000 4,366 4,366
Tukang Besi 0.0070 7.80 kg 0.05 Oh 90,000 4,912 4,912

Pembesian Pokok dengan besi polos dia 10 mm /m' (An. Membuat)


Besi Ø 10 mm 1.0500 11.16 kg 1.02 LJ 85,000 86,611 86,611
Pekerja 0.0070 11.16 kg 0.08 Oh 80,000 6,250 6,250
Tukang Besi 0.0070 11.16 kg 0.08 Oh 90,000 7,031 7,031

Pasangan begisting /m2


Kayu 0.0450 1.80 m2 0.08 m2 25,000 2,025 2,025
Paku 0.3000 1.80 m2 0.54 kg 22,000 11,880 11,880
Pekerja 0.3000 1.80 m2 0.54 Oh 80,000 43,200 43,200
Tukang Kayu 0.2600 1.80 m2 0.47 Oh 90,000 42,120 42,120
Sub total 371,651
b Pekerjaan beton kolom praktis
Pek Beton 1:2:3 untuk tiap m3
Semen 40 kg 8.4000 0.25 m3 2.12 zak 58,000 122,774 122,774
Pasir Pasang 0.5400 0.25 m3 0.14 m3 145,000 19,732 19,732

Analisa hal 9 dari 4 hal


Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
Kerikil 2/3 0.8100 0.25 m3 0.20 m3 350,000 71,442 71,442
Tk Kayu 0.3500 0.25 m3 0.09 Oh 90,000 7,938 7,938
Pekerja 2.0000 0.25 m3 0.50 Oh 80,000 40,320 40,320

Pembesian dengan besi polos dia 8 mm /m' (An. Membuat)


Besi Ø 6 mm 1.0500 18.55 Kg 1.69 lj 55,000 93,151 93,151
Bendrat 0.0150 18.55 Kg 0.28 Kg 25,000 6,956 6,956
Pekerja 0.0700 18.55 Kg 1.30 Oh 80,000 103,878 103,878
Tukang Besi 0.0070 18.55 Kg 0.13 Oh 90,000 11,686 11,686

Analisa hal 10 dari 4 hal


Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
Pembesian dengan besi polos dia 10 mm /m' (An. Membuat)
Besi Ø 10 mm 1.0500 39.68 kg 3.62 lj 85,000 307,951 307,951
Pekerja 0.0070 39.68 kg 0.28 Oh 80,000 22,221 22,221
Tukang Besi 0.0070 39.68 kg 0.28 Oh 90,000 24,998 24,998

Pasangan begisting /m2


Kayu 0.0450 4.48 m2 0.20 m2 25,000 5,040 5,040
Paku 0.3000 4.48 m2 1.34 kg 22,000 29,568 29,568
Pekerja 0.3000 4.48 m2 1.34 Oh 80,000 107,520 107,520
Tukang Kayu 0.2600 4.48 m2 1.16 Oh 90,000 104,832 104,832
Sub total 1,080,008
c Pekerjaan Beton Ring Balk
Pek Beton 1:2:3 untuk tiap m3
Semen 40 kg 8.4000 0.10 m3 0.85 zak 58,000 49,329 49,329
Pasir Pasang 0.5400 0.10 m3 0.05 m3 145,000 7,928 7,928
Kerikil 2/3 0.8100 0.10 m3 0.08 m3 350,000 28,704 28,704
Tukang batu 0.3500 0.10 m3 0.04 Oh 90,000 3,189 3,189
Pekerja 2.0000 0.10 m3 0.20 Oh 80,000 16,200 16,200

Pembesian Begel dengan besi polos dia 8 mm /m' (An. Membuat)


Besi Ø 6 mm 1.0500 7.80 kg 0.71 lj 55,000 39,155 39,155
Bendrat 0.0150 7.80 kg 0.12 Kg 25,000 2,924 2,924
Pekerja 0.0070 7.80 kg 0.05 Oh 80,000 4,366 4,366
Tukang Besi 0.0070 7.80 kg 0.05 Oh 90,000 4,912 4,912

Pembesian dengan besi polos dia 10 mm /m' (An. Membuat)


Besi Ø 10 mm 1.0500 11.16 kg 1.02 lj 85,000 86,611 86,611
Pekerja 0.0070 11.16 kg 0.08 Oh 80,000 6,250 6,250
Tukang Besi 0.0070 11.16 kg 0.08 Oh 90,000 7,031 7,031

Pasangan begisting /m2


Kayu 0.0450 1.80 m2 0.08 m2 25,000 2,025 2,025
Paku 0.3000 1.80 m2 0.54 kg 22,000 11,880 11,880
Pekerja 0.3000 1.80 m2 0.54 Oh 80,000 43,200 43,200
Tukang Kayu 0.2600 1.80 m2 0.47 Oh 90,000 42,120 42,120
Sub total 355,825
8 Pasangan bata merah tebal 1/2 batu (/m2) 1 PC : 6 Ps
Batu Bata 70.00 11.13 m2 778.82 biji 700 545,174 545,174
Semen 40 kg 0.2080 11.13 m2 2.31 zak 58,000 134,224 134,224
Pasir 0.0490 11.13 m2 0.55 m3 145,000 79,050 79,050
Tukang Batu 0.1000 11.13 m2 1.11 Oh 90,000 100,134 100,134
Pekerja 0.3200 11.13 m2 3.56 Oh 80,000 284,826 284,826
Sub total 1,143,408
9 Plesteran dan Acian Dinding Luar Dalam ( 1 : 6 ) m2
Semen 40 kg 0.0920 29.96 m2 2.76 zak 58,000 159,867 159,867
Pasir Pasang 0.0230 29.96 m2 0.69 m3 145,000 99,917 99,917
Tukang Batu 0.1500 29.96 m2 4.49 Oh 90,000 404,460 404,460
Pekerja 0.2000 29.96 m2 5.99 Oh 80,000 479,360 479,360
Sub total 1,143,603
10 Membuat dan Memasang Kosen ( m3 )
Kayu 6/12 Kusen 1.100 1.00 m3 1.10 m3 200,000 220,000 220,000
Tukang 2.000 1.00 m3 2.00 Oh 90,000 180,000 180,000
Pekerja 1.000 1.00 m3 1.00 Oh 80,000 80,000 80,000
Sub total 480,000
11 Membuat / Memasang Jendela Kaca ( m2 )
Kaca 1.0000 0.50 m2 0.50 m2 100,000 50,000 50,000
Tukang 0.1500 0.50 m2 0.08 Oh 90,000 6,750 6,750
Pekerja 6.0000 0.50 m2 3.00 Oh 80,000 240,000 240,000
Sub total 296,750
12 Memasang Rangka plafond dan langit langit ( m2 )
Kayu 5/7 0.0120 5.00 m2 0.01 bende 250,000 3,704 3,704
Eternit 0.3640 5.00 m2 1.82 Lbr 75,000 136,500 136,500
Paku 0.1100 5.00 m2 0.55 kg 22,000 12,100 12,100
Tukang 0.0500 5.00 m2 0.25 Oh 90,000 22,500 22,500
Analisa hal 11 dari 4 hal
Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
Pekerja 0.1000 5.00 m2 0.50 Oh 80,000 40,000 40,000
Sub total 214,804
13 Memasang Kap / Kuda-kuda ( m3 )
Kayu 8/12 Gording 1.1000 0.30 m3 4.00 ljr 250,000 1,000,000 1,000,000
Paku 0.8000 0.30 m3 0.24 kg 22,000 5,280 5,280
Tukang 0.7000 0.30 m3 0.21 Oh 90,000 18,900 18,900
Pekerja 0.8000 0.30 m3 0.24 Oh 80,000 19,200 19,200
Sub total 1,043,380

Analisa hal 12 dari 4 hal


Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
14 Memasang Rangka Atap ( m2 )
Kayu 5/7 0.014 9.00 m2 2.00 bende 250,000 500,000 500,000
Kayu 3/5 0.0072 9.00 m2 1.00 bende 250,000 250,000 250,000
Paku 0.250 9.00 m2 2.25 kg 22,000 49,500 49,500
Tukang 0.1000 9.00 m2 0.90 Oh 90,000 81,000 81,000
Pekerja 0.1000 9.00 m2 0.90 Oh 80,000 72,000 72,000
Sub total 952,500

15 Memasang Genteng ( m2 )
Asbes gelombang kecil 25.0000 9.00 m2 225.00 biji 3,000 675,000 675,000
Tukang 0.0750 9.00 m2 0.67 Oh 90,000 60,750 60,750
Pekerja 0.1500 9.00 m2 0.67 Oh 80,000 54,000 54,000
Sub total 789,750

16 m1 - genteng bubungan
Bubung 5.0000 3.00 m' 15.00 bh 6,000 90,000 90,000
Semen 0.2000 3.00 m' 0.60 zak 22,000 13,200 13,200
Papan riter 1.1000 3.00 m' 3.30 ljr 85,000 280,500 280,500
Pasir Pasang 0.0320 3.00 m' 0.10 m3 145,000 13,920 13,920
Tukang 0.2000 3.00 m' 0.60 Oh 90,000 54,000 54,000
Pekerja 0.4000 3.00 m' 1.20 Oh 80,000 96,000 96,000
Sub total 547,620
17 Membuat dan Memasang Lisplank ( m2 )
Kasiplnk 0,8 / 20 x 400 0.8000 10.00 m' 2.00 lbr 85,000 170,000 170,000
Paku 3 cm 0.0500 10.00 m' 0.50 kg 22,000 11,000 11,000
Tukang 0.2000 10.00 m' 2.00 Oh 90,000 180,000 180,000
Pekerja 0.1000 10.00 m' 1.00 Oh 80,000 80,000 80,000
Sub total 441,000
18 Mlamir dan Mengecat dengan cat Tembok dinding luar dalam dan langit langit ( m 2 )
Cat Tembok 0.3000 53.96 m2 16.19 kg 30,000 485,640 485,640
Plamer 0.1100 53.96 m2 5.94 kg 33,000 195,875 195,875
Kertas Amplas 0.0500 53.96 m2 24.00 lbr 8,000 192,000 192,000
Tukang Cat 0.0630 53.96 m2 3.40 Oh 90,000 305,953 305,953
Pekerja 0.0200 53.96 m2 1.08 Oh 80,000 86,336 86,336
Sub total 1,265,804

19 Memasang lantai dalam Keramik 20 / 20 ( 1 : 4 ) untuk tiap m2 Kamar mandi


Keramik 1.0000 3.60 m2 3.60 m2 75,000 270,000 270,000
Semen 40 kg 11.3800 3.60 m2 1.02 zak 58,000 59,404 59,404
Pasir Pasang 0.0420 3.60 m2 0.15 m3 145,000 21,924 21,924
Tukang Batu 0.3500 3.60 m2 1.26 Oh 90,000 113,400 113,400
Pekerja 0.6200 3.60 m2 2.23 Oh 80,000 178,560 178,560
Seman warna 1.5000 3.60 m3 5.40 kg 6,250 33,750 33,750
Sub total 677,038
20 Memasang Keramik dinding 20 / 25 ( 1 : 4 ) untuk tiap m2
Keramik 1.0000 16.50 m2 16.50 m2 70,000 1,155,000 1,155,000
Semen 40 kg 11.3800 16.50 m2 4.69 zak 58,000 272,266 272,266
Pasir Pasang 0.0420 16.50 m2 0.69 m3 145,000 100,485 100,485
Tukang Batu 0.3500 16.50 m2 5.77 Oh 90,000 519,750 519,750
Pekerja 0.6200 16.50 m2 10.23 Oh 80,000 818,400 818,400
Seman warna 1.5000 16.50 m3 0.62 kg 6,250 3,867 3,867
Sub total 2,869,769
21 Mendempul, Melamer, Mengecat, Pintu / jendela, Daun pintu, Lisplank ( M2)
Cat Kayu 0.4300 2.57 m2 1.11 kg 65,000 71,943 71,943
Tiner 0.0800 2.57 m2 0.21 ltr 15,000 3,089 3,089
Plamer 0.1500 2.57 m2 0.39 kg 33,000 12,741 12,741
Dempul Jadi 0.0750 2.57 m2 0.19 kg 5,000 965 965
Kertas Amplas 0.1000 2.57 m2 0.26 lbr 8,000 2,059 2,059
Tukang Cat 0.0090 2.57 m2 0.02 Oh 90,000 2,085 2,085
Pekerja 0.0700 2.57 m2 0.18 Oh 80,000 14,414 14,414
Sub total 107,297
22 set - Pintu Aluminium KM
Pintu Aluminium 1.000 1 1.00 bh 380,000 380,000 380,000
Analisa hal 13 dari 4 hal
Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
Pekerja 2.000 1 2.00 Oh 80,000 160,000 160,000
Tukang 1.000 1 1.00 Oh 90,000 90,000 90,000
Sub total 630,000

Analisa hal 14 dari 4 hal


Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
23 1 bh - Kloset duduk
Kloset duduk 1.000 1 1.00 ljr 280,000 280,000 280,000
Pekerja 3.300 1 3.30 Oh 80,000 264,000 264,000
Tukang batu 1.100 1 1.10 Oh 90,000 99,000 99,000
Sub total 643,000
24 unit - Septictank, 1x2x1,3 m3
Bata merah 1,800.000 1 1,800.00 bh 700 1,260,000 1,260,000
Pasir 1.066 1 1.07 m3 145,000 154,535 154,535
Koral beton 0.186 1 0.19 m3 350,000 65,184 65,184
Semen / PC (40 kg) 10.796 1 10.80 zak 58,000 626,145 626,145
Besi beton 39.514 1 3.59 ljr 85,000 305,332 305,332
Bendrat 0.564 1 1.00 bh 25,000 25,000 25,000
Paku 0.500 1 2.00 bh 22,000 44,000 44,000
Kayu hutan balok 0.040 1 0.04 bh 250,000 10,000 10,000
Plywood 0.700 1 0.70 bh 75,000 52,500 52,500
Pekerja 7.220 1 7.22 Oh 80,000 577,626 577,626
Tukang 3.393 1 3.39 Oh 90,000 305,370 305,370
Sub total 3,425,692

Analisa hal 15 dari 4 hal


RENCANA ANGGARAN BIAYA

Propinsi : Jawa Timur Panjang : 1,5 x 2,0 M


Kabupaten : Situbondo Jumlah : 1 unit
Kecamatan : Cipta Desa
Desa : Cipta Desa

Volume Harga Dana Desa Dana Jumlah


URAIAN Dari Dari Satuan Satuan DD Swadaya Total
Total
Swadaya DD Rp. Rp. Rp. Rp.
Bahan
1 Paku 6.00 6 kg 22,000 132,000 - 132,000
2 Pasir urug 1.00 1 m3 145,000 145,000 - 145,000
3 Batu belah 2.00 2 m3 175,000 350,000 - 350,000
4 Semen 40 kg 29.00 29 zak 58,000 1,682,000 - 1,682,000
5 Pasr pasang 4.00 4 m3 145,000 580,000 - 580,000
6 Koral 1.00 1 m3 350,000 350,000 - 350,000
7 Besi beton Ø 6 4.00 4 lj 55,000 220,000 - 220,000
8 Besi beton Ø 10 9.00 9 lj 85,000 765,000 - 765,000
9 Bendrat 2.00 2 kg 25,000 50,000 - 50,000
10 Begisting 8.00 8 lbr 25,000 200,000 - 200,000
11 Tripleks 1.00 1 lbr 75,000 75,000 - 75,000
12 Batu bata 2,500.00 2500 bh 700 1,750,000 - 1,750,000
13 Kayu Kusen 1.00 1 ljr 200,000 200,000 - 200,000
14 Kasiplnk 0,8/20 3.00 3 lbr 85,000 255,000 - 255,000
15 Kramik 20 x 20 4.00 4 dos 75,000 300,000 - 300,000
16 Kramik 20 x 25 17.00 17 dos 70,000 1,190,000 - 1,190,000
17 Kayu 6/10 2.00 2 ljr 205,000 410,000 - 410,000
18 Kayu 5/7 3.00 3 bendel 205,000 615,000 - 615,000
19 Kayu 3/5 1.00 1 bendel 260,000 260,000 - 260,000
20 Kalsibord 4.00 4 lbr 75,000 300,000 - 300,000
21 Genteng 200.00 200 bh 3,000 600,000 - 600,000
22 Genteng nok 15.00 15 bh 6,000 90,000 - 90,000
23 Kaca 5 mm 0.50 1 m2 100,000 50,000 - 50,000
24 Cat kayu 2.00 2 kg 65,000 130,000 - 130,000
25 Plamir 8.00 8 kg 33,000 264,000 - 264,000
26 Kertas gosok 4.00 4 lbr 8,000 32,000 - 32,000
27 Tiner 2.00 2 kg 15,000 30,000 - 30,000
28 Cat tembok 16.00 16 kg 30,000 480,000 - 480,000
29 Daun pintu PVC 1.00 1 bh 380,000 380,000 - 380,000
30 Pipa PVC 4" 2.00 2 bh 250,000 500,000 - 500,000
31 Pipa PVC 3/4" 1.00 1 bh 45,000 45,000 - 45,000
32 L PVC 4" 3.00 3 bh 25,000 75,000 - 75,000
33 L PVC 3/4" 1.00 1 bh 8,000 8,000 - 8,000
32 Buis Beton Ø 1,0 m 3.00 3 bh 145,000 435,000 - 435,000
33 Tutup Buis Beton Ø 1,0 m 1.00 1 bh 110,000 110,000 - 110,000
33 Avor Pembuangan 1.00 1 bh 25,000 25,000 - 25,000
34 Avor Bak 1.00 1 bh 20,000 20,000 - 20,000
35 Maenhole 2.00 2 bh 150,000 300,000 - 300,000
36 Kran Air 1.00 1 bh 30,000 30,000 - 30,000
37 Klosed 1.00 1 bh 280,000 280,000 - 280,000

Sub Total 1) Ia 13,713,000 - 13,713,000


Alat
1 Timba 2.00 2.00 bh 11,000 22,000 - 22,000
2 Benang 1.00 1.00 bh 7,000 7,000 - 7,000
3 Meteran 0.00 bh 48,000 0 - 0
4 Perencanaan 1.00 1.00 bh 250,000 250,000 - 250,000
Sub Total 2) IIa 279,000 - 279,000
Upah
1 Pekerja 43.00 43.00 Oh 80,000 3,440,000 - 3,440,000
2 Tukang 28.00 28.00 Oh 90,000 2,520,000 - 2,520,000
###
Sub Total 3) IIIa 5,960,000 - 5,960,000
Total Biaya DD (a+b ) 19,952,000
Sumber Dana
Volume Harga Dana Desa Dana Jumlah
URAIAN Dari Dari Satuan Satuan DD Swadaya Total
Total
Swadaya DD Rp. Rp. Rp. Rp.
Sumber Dana Total Biaya Swadaya (a+ b) -
JUMLAH TOTAL ( DD + Swadaya ) 19,952,000
Terbilang : Sembilan belas juta sembilan ratus lima puluh dua ribu rupiah ###
Mengesahkan Dibuat Oleh,
Kepala Desa ................. Tim Pengelola Kegiatan (TPK) ###
###
###
......................................... ......................................... ###
Perencana,

.........................................