RENCANA ANGGARAN BIAYA

Kegiatan : Saung Tani


Lokasi :
Panjang : 3 x 6 Meter

Harga Satuan Jumlah


No. URAIAN Volume Satuan
Rp. Rp.
Bahan
1 Paku 20.00 kg 22,000 440,000
2 Batu belah 40.00 m3 164,000 6,560,000
3 Semen 40 kg 50.00 zak 75,000 3,750,000
4 Pasr pasang 35.00 m3 150,000 5,250,000
5 Pasr Urug 12.00 m3 100,000 1,200,000
6 Koral 4.00 m3 300,000 1,200,000
7 Besi beton Ø 6 21.00 lj 65,000 1,365,000
8 Besi beton Ø 10 45.00 lj 105,000 4,725,000
9 Bendrat 5.00 kg 30,000 150,000
10 Begisting 40.00 lbr 25,000 1,000,000
11 Batako 1300.00 bh 2,500 3,250,000
12 Kalsibord 68.00 lbr 95,000 6,460,000
13 Kayu 6/15 22.00 ljr 250,000 5,500,000
14 Kayu 8/12 35.00 ljr 250,000 8,750,000
15 Kayu 5/7 43.00 bendel 275,000 11,825,000
16 Papan Lisplank 18.00 ljr 150,000 2,700,000
17 Kayu 3/5 9.00 bendel 360,000 3,240,000
18 Kayu 3/10 12.00 ljr 250,000 3,000,000
19 Atap Asbes Gelombang 25.00 bh 115,000 2,875,000
20 Wuwung Asbes 40.00 bh 25,000 1,000,000
21 Keramik 40 x 40 20.00 Dus 75,000 1,500,000
22 Roster Kayu 18.00 bh 125,000 2,250,000
23 Plamir 39.00 kg 38,000 1,482,000
24 Kertas gosok 10.00 lbr 10,000 100,000
25 Cat tembok 124.00 kg 37,000 4,588,000
26 Cat Kayu 16.00 kg 72,000 1,152,000
27 Daun Pintu 2.00 bh 1,500,000 3,000,000
28 Tiner 3.00 ltr 20,000 60,000
29 Batu Candi 13.00 m2 200,000 2,600,000
30 Grendel Pintu 2.00 bh 35,000 70,000
31 Engasel Jendela 16.00 bh 35,000 560,000
32 Pegangan Jendela 16.00 bh 25,000 400,000
33 Kunci 2.00 bh 250,000 500,000
34 Engsel Pintu 6.00 bh 56,000 336,000
35 Intalasi Listrik A 2.00 Titik 350,000 700,000

Sub Total 1 93,538,000.00


Upah
1 Pekerja 100.0 Hok 100,000 10,000,000
2 Tukang 100.0 Hok 130,000 13,000,000

Sub Total 2 23,000,000.00


Harga Satuan Jumlah
No. URAIAN Volume Satuan
Rp. Rp.
Alat Kamar Mandi
1 Kolset Jongkok 1.00 bh 250,000 250,000
2 Torn 1000 Lt 1.00 bh 1,500,000 1,500,000
3 Pintu Kamar Mandi 1.00 bh 450,000 450,000
4 Kran 4.00 bh 15,000 60,000
5 Paralon 2" 10.00 bt 35,000 350,000
6 Paralon 3" 2.00 bh 25,000 50,000
7 Paralon 1/2" 2.00 bh 20,000 40,000
8 Mesin Pompa Air 1.00 bh 65,000 65,000
9 Pembuatan Septitank 1.00 Unit 2,000,000 2,000,000
Sub Total 3 2,765,000.00
JUMLAH TOTAL 119,303,000.00

Terbilang : Seratus sembilan belas juta tiga puluh tiga ribu rupiah
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

3 meter

DISETUJUI OLEH

DIKETAHUI OLEH

6 meter
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

DISETUJUI OLEH

DIKETAHUI OLEH
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

DISETUJUI OLEH

DIKETAHUI OLEH
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

3 meter

DISETUJUI OLEH

DIKETAHUI OLEH

6 meter
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

3 meter

DISETUJUI OLEH

6 meter
DIKETAHUI OLEH
GAMBAR
BANGUNAN SAUNG TANI

UKURAN

3 X 6 METER PERSEGI

LOKASI

DISETUJUI OLEH

DIKETAHUI OLEH

Anda mungkin juga menyukai