RENCANA ANGGARAN BIAYA

PEMBANGUNAN MAJELIS TA'LIM USWATUN HASANAH

VOLUME HARGA BIAYA JUMLAH


NO URAIAN KEGIATAN SATUAN
PEKERJAAN SATUAN RP (RP)
1 2 3 4 5 6 7
I PEKERJAAN BETON
1 Slop, Colom, ceker ayam, 15 M2 150,000.00 2,250,000
2 dan ring besi 16 mili 20 Btg 100,000.00 2,000,000
3 Tiang ring behel 12 mili 50 Btg 60,000.00 3,000,000
4 Ring behel atas 10 mili ful 90 Btg 48,000.00 4,320,000
5 Ring behel atap cor 10 mili 150 Btg 48,000.00 7,200,000
Sub Total 18,770,000
II PEKERJAAN RANGKA BAWAH
1 Papan cor 35 Lbr 90,000.00 3,150,000
2 Tiang cor / bambu 220 Btg 7,000.00 1,540,000
3 kawat Pengikat 100 Kg 10,000.00 1,000,000
4 Triplek 5 mili 30 Lbr 150,000.00 4,500,000
5 Pasir 42 Kbk 200,000.00 8,400,000
6 Sprit 7 Kbk 180,000.00 1,260,000
7 Paku 30 Kg 14,000.00 420,000
Sub Total 20,270,000
III PEKERJAAN RANGKA KUSEN
1 Kusen depan kayu kamper 1 Lbg 2,500,000.00 2,500,000
2 Kusen Belakang 1 Lbg 2,500,000.00 2,500,000
3 Kusen Jendela 5 Lbg 2,100,000.00 10,500,000
4 Pintu kamar 5 Lbg 3,500,000.00 17,500,000
5 daun pintu kusen 3 Lbg 1,200,000.00 3,600,000
6 daun Pintu Kamar 1 Lbg 1,500,000.00 1,500,000
Sub Total 38,100,000
IV PEKERJAAN BATU BATA
1 Batu bata 12000 buah 450.00 5,400,000
2 semen 200 Zak 55,000.00 11,000,000
3 Pengurugan 3 Truk 750,000.00 2,250,000
Sub Total 18,650,000
V PEKERJAAN LANTAI BAWAH
1 Keramik 130 M2 32,000.00 4,160,000
VI PEKERJAAN RANGKA ATAS
1 Genting keramik 2000 buah 2,200.00 4,400,000
2 Kayu Kaso Ukuran 4x6 2 Kbk 3,200,000.00 6,400,000
3 kayu kamper Ukuran 6 x 12 3 Kbk 3,200,000.00 9,600,000
4 Kayu reng 1.5 Kbk 3,500,000.00 5,250,000
Sub Total 29,810,000
VII PENGERJAAN KERANGKA ATAS LT. 2
1 Batu bata 10000 buah 450.00 4,500,000
2 Besi tangga ukuran 10 30 Btg 70,000.00 2,100,000
3 lantai atas Keramik 80 M2 35,000.00 2,800,000
Sub Total 9,400,000
4 kamar mandi WC atas 2,500,000
5 kamar mandi WC bawah 2,500,000
VIII ONGKOS KERJA
1 6 Orang Tukang 100 Hari 100 hari 60,000.00 3,600,000 36,000,000.00
2 6 Orang Knek 100 Hari 100 hari 40,000.00 2,400,000 24,000,000.00

TOTAL 200,000,000
Terbilang : Dua Ratus Juta Rupiah

Sukatani, Mei 2013

Ketua Bendahara

Ust. JAZULI DIMYATI


RENCANA ANGGARAN BIAYA
PEMBANGUNAN MAJELIS TA'LIM USWATUN HASANAH

HARGA
NO BAHAN BAKU BANYAK SATUAN JUMLAH
SATUAN
1 PASIR COR 5 M3 200,000 1,000,000
2 SPLIT 4 M3 250,000 1,000,000
3 SEMEN 5 Zak 60,000 300,000
4 BESI BEHEL 12 MM 35 Btng 55,000 1,925,000
5 BESI BEHEL 10 MM 35 Btng 48,000 1,680,000
6 KAWAT BENDRAT 5 Kg 25,000 125,000
7 PAKU CAMPUR 60 Kg 20,000 1,200,000
8 PAPAN COR 25 Buah 20,000 500,000
9 CAT TEMBOK 25 KG 1 Kaleng 400,000 400,000
10 BATU BATA 750 Buah 500 375,000
11 KERAMIK 40 X 40 15 M2 58,000 870,000
12 KAYU KASO 0.5 M3 4,000,000 2,000,000
13 TERIPLEK 5 MM 15 Lembar 80,000 1,200,000
14 CAT KAYU PLAFON 1 Kg 400,000 400,000
15 AMPLAS 11 Lembar 5,000 55,000
16 ROL CAT 31 Buah 50,000 1,550,000
17 BAK CAT 5 Buah 15,000 75,000
18 KOAS 2 Buah 10,000 20,000
15 EMBER KECIL 5 Buah 10,000 50,000
16 EMBER BESAR 5 Buah 15,000 75,000
17 BAK ADUK 2 Buah 25,000 50,000
18 UPAH TUKANG 2 ORG 5 HOK 70,000 350,000
19 UPAH KNEK 4 ORG 5 HOK 60,000 300,000
20 UPAH TUKANG RELIEF 1 ORG 5 HOK 100,000 500,000
21 KONSUMSI 5 HOK 200,000 1,000,000
TOTAL JUMLAH 15,000,000

Terbilang : Lima Belas Juta Rupiah

Sukatani, Mei 2013

Ketua Bendahara

Ust. JAZULI DIMYATI