RENCANA ANGGARAN BIAYA

PEMBANGUNAN TPQ AL-MUKHLISIN

VOLUME HARGA BIAYA JUMLAH


NO URAIAN KEGIATAN SATUAN
PEKERJAAN SATUAN RP (RP)
1 2 3 4 5 6 7
I PEKERJAAN PONDASI BETON
1. Batu Kali 5 Truk 750,000 3,750,000
2. Split 4 Truk 1,200,000 4,800,000
3. Pasir 5 Truk 1,250,000 6,250,000
4. Semen 15 sak 55,000 825,000
5. Besi 12 mm 7 btng 30,000 210,000
6. Besi 8 m 7 btng 25,000 175,000
7. Cakar Ayam Jadi 5 buah 1,750,000 8,750,000
8. Bendrat 5 buah 20,000 100,000
9. Papan Cor 5 buah 20,000 100,000
10. Paku 5 kg 20,000 100,000
11. Pekerjaan Penggalian Pondasi 20 Truk 25,000 500,000
12. Pengurugan Pondasi 15 Truk 25,000 375,000
13. Benang Nilon 1 buah 20,000 20,000
14. Ember Cor 10 buah 5,000 50,000
Sub Total 26,005,000
II PEKERJAAN DINDING BETON
1. Batu Bata 5000 Truk 400 2,000,000
2. Pasir 4 Truk 1,300,000 5,200,000
3. Split 2 Truk 1,300,000 2,600,000
4. Semen 29 sak 60,000 1,740,000
5. Besi 10 mm 10 btng 50,000 500,000
6. Bendrat 5 bush 30,000 150,000
7. Besi 10 btng 30,000 300,000
8. Papan Cor 20 buah 25,000 500,000
Sub Total 12,990,000
III PEKERJAAN KAYU TETAP
1. Kusen Pintu 2 buah 350,000 700,000
2. Daun Pintu 2 buah 450,000 900,000
3. Kusen Jendela 4 buah 350,000 1,400,000
4. Balok Kamper 8/12 2 buah 2,500,000 5,000,000
5. Balok Kamper 6/12 2 buah 1,500,000 3,000,000
6. Balok Kamper 5/10 3 buah 1,250,000 3,750,000
7. Kaso Kamper 5 buah 750,000 3,750,000
8. Reng Kamper 2 buah 150,000 300,000
9. Paku 5 buah 12,000 60,000
VOLUME HARGA BIAYA JUMLAH
NO URAIAN KEGIATAN SATUAN
PEKERJAAN SATUAN RP (RP)
10 Baud 5 buah 10,000 50,000
11. Papan Kayu Lispang 2 buah 1,250,000 2,500,000
Sub Total 21,410,000
IV PEKERJAAN LANTAI Barat
1. pasir 5 Truk 1,300,000 6,500,000
2. semen 20 zak 60,000 1,200,000
3. Keramik 20 M2 32,000 640,000
Sub Total 18,750,000
V PEKERJAAN LABURAN CAT DAN KUNCI

1. Residu Kap 15 buah 30,000 450,000


2. Cat Tembok 18 buah 200,000 3,600,000
3. Cat Kayu 6 buah 150,000 900,000
4. Minyak Cat 15 buah 50,000 750,000
5. Minyak Cat 10 buah 75,000 750,000
6. Koas Roll 2 buah 20,000 40,000
7. Engsel Kunci 5 buah 15,000 75,000
8. Engsel Jendela 5 buah 10,000 50,000
Sub Total 7,255,000
VI ONGKOS TUKANG
1 6 Orang Tukang 120 Hari 100 hari 90,000 3,600,000 36,000,000
2 6 Orang Knek 120 Hari 100 hari 60,000 2,400,000 24,000,000

TOTAL 125,000,000
Terbilang : Seratus Dua Puluh Lima Juta Rupiah

Sukawijaya, Mei 2013

Ketua Bendahara

UST. DADANG SUHAIMI,S.Pd.I FUTIHAH


RENCANA ANGGARAN BIAYA
PEMBANGUNAN TPQ AL-MUKHLISIN

HARGA
NO BAHAN BAKU BANYAK SATUAN JUMLAH
SATUAN
1 PASIR COR 9 M3 200,000 1,800,000
2 SPLIT 4 M3 250,000 1,000,000
3 SEMEN 5 Zak 60,000 300,000
4 BESI BEHEL 12 MM 40 Btng 55,000 2,200,000
5 BESI BEHEL 10 MM 40 Btng 48,000 1,920,000
6 KAWAT BENDRAT 5 Kg 25,000 125,000
7 PAKU CAMPUR 60 Kg 20,000 1,200,000
8 PAPAN COR 25 Buah 20,000 500,000
9 CAT TEMBOK 25 KG 3 Kaleng 400,000 1,200,000
10 BATU BATA 10000 Buah 500 5,000,000
11 KERAMIK 40 X 40 30 M2 58,000 1,740,000
12 KAYU KASO 0.5 M3 4,000,000 2,000,000
13 TERIPLEK 5 MM 15 Lembar 80,000 1,200,000
14 CAT KAYU PLAFON 1 Kg 400,000 400,000
15 AMPLAS 11 Lembar 5,000 55,000
16 ROL CAT 31 Buah 50,000 1,550,000
17 BAK CAT 5 Buah 15,000 75,000
18 KOAS 2 Buah 10,000 20,000
15 EMBER KECIL 4 Buah 10,000 40,000
16 EMBER BESAR 5 Buah 15,000 75,000
17 BAK ADUK 2 Buah 25,000 50,000
18 UPAH TUKANG 2 ORG 5 HOK 70,000 350,000
19 UPAH KNEK 4 ORG 5 HOK 60,000 300,000
20 UPAH TUKANG RELIEF 1 ORG 7 HOK 100,000 700,000
21 KONSUMSI 6 HOK 200,000 1,200,000
TOTAL JUMLAH 25,000,000

Terbilang : Dua Puluh Lima Juta Rupiah

Sukawijaya, Mei 2013