RENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN MADRASAH IBTIDA'IYAH NAHDLATUL ULAMA DS. AIR ITAM TIMUR


KEC. PENUKAL KAB. PENUKAL ABAB LEMATANG ILIR
TAHUN ANGGARAN 2022

Harga
NO. Uraian Pekerjaan dan Bahan Quantity Satuan Rp JUMLAH
Satuan
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 200 m2 3,000 600,000
2 Pemasangan Bouwplank 60 m' 8,000 480,000
3 Pembelian Alat-alat Pekerjaan 1 paket 1,500,000 1,500,000
4 Pembelian Tempat Air 1 buah 800,000 800,000
Jumlah I 3,380,000
II PEKERJAAN TANAH
1 Galian Tanah Pondasi 117 m3 40,000 4,680,000
2 Pemasangan Pancang Bambu 233 batang 7,000 1,631,000
3 Galian Tanah Cakar Ayam 42 m3 40,000 1,680,000
4 Urugan Pasir Dasar Pondasi 9 m3 130,000 1,170,000
Jumlah II 9,161,000
III PEKERJAAN PASANG PONDASI
1 Batu Kali 70 m3 140,000 9,800,000
2 Pasir Pasang 70 m3 160,000 11,200,000
3 Semen Tiga Roda 163 zak 80,000 13,040,000
4 Ember 47 buah 10,000 470,000
5 Benang Gulung 7 gl 10,000 70,000
Jumlah III 34,580,000
IV PEKERJAAN SLUP BAWAH
1 Besi 12 FL SNI 140 batang 113,000 15,820,000
2 Besi 10 FL SNI 117 batang 74,000 8,658,000
3 Besi 6 FL SNI 70 batang 32,000 2,240,000
4 Tali Kawat 19 kg 20,000 380,000
5 Papan Cor 1 m3 1,400,000 1,400,000
6 Paku 7/5 19 kg 15,000 285,000
7 Semen Tiga Roda 187 zak 65,000 12,155,000
Jumlah IV 40,938,000
V PEKERJAAN BAHAN COR PASIR BETON/BATU
1 Pasir Cor 47 m3 185,000 8,695,000
2 Batu Kerikil 47 m3 200,000 9,400,000
Jumlah V 18,095,000
VI PEKERJAAN KOLOM COR/CAKAR AYAM
1 Besi 12 FL SNI 93 batang 113,000 10,509,000
2 Besi 10 FL SNI 140 batang 74,000 10,360,000
3 Besi 6 FL SNI 93 batang 32,000 2,976,000
4 Tali Kawat 35 kg 20,000 700,000
5 Papan Cor 2 m3 1,400,000 2,800,000
6 Kayu Kaso 2 m3 1,400,000 2,800,000
7 Paku (7 cm, 10, cm dan 5 cm) 28 kg 15,000 420,000
8 Semen Tiga Roda 82 sak 84,000 6,888,000
Jumlah VI 37,453,000
VII PEKERJAAN PASANG BATA/KUSEN
1 Bata Merah 37,300 buah 700 26,110,000
2 Pasir Pasang 35 m3 135,000 4,725,000
3 Semen Tiga Roda 140 sak 84,000 11,760,000
4 Bambu Esteger 140 batang 7,000 980,000
5 Kusen Pintu 9 buah 250,000 2,250,000
6 Kusen Jendela 28 buah 200,000 5,600,000
Jumlah VII 51,425,000
VIII PEKERJAAN COR BALOK ATAS
1 Besi 12 FL SNI 93 batang 113,000 10,509,000
2 Besi 10 FL SNI 93 batang 74,000 6,882,000
3 Besi 6 FL SNI 70 batang 32,000 2,240,000
4 Papan 2 m3 1,400,000 2,800,000
5 Pasir Beton 12 m3 175,000 2,100,000
6 Batu Kerikil 26 m3 200,000 5,200,000
7 Bambu Penunjang 93 batang 7,000 651,000
8 Semen Tiga Roda 58 sak 84,000 4,872,000
9 Tali Kawat 12 kg 20,000 240,000
10 Paku (7 cm, 10 cm, dan 5 cm) 28 kg 18,000 504,000
Jumlah VIII 35,998,000
IX PEKERJAAN ATAP
1 Besi 8 FL SNI 1,167 batang 62,000 72,354,000
2 Besi 6 FL SNI 117 batang 32,000 3,744,000
3 Papan 12 m3 1,400,000 16,800,000
4 Bambu 1,167 batang 10,000 11,670,000
5 Kayu Kaso 6x6 5 m3 1,400,000 7,000,000
6 Tali Kawat 47 kg 20,000 940,000
7 Semen Tiga Roda 187 sak 84,000 15,708,000
8 Ember Aduk 70 buah 10,000 700,000
9 Pasir beton 42 m3 200,000 8,400,000
10 Batu Kerikil 35 m3 214,000 7,490,000
11 Paku (7 cm, 10 cm, dan 5 cm) 7 dus 350,000 2,450,000
Jumlah IX 147,256,000
X PEKERJAAN PELISTER ACI
1 Pasir Pasang 35 m3 200,000 7,000,000
2 Semen Tiga Roda 93 sak 84,000 7,812,000
3 Kelasid 82 bal 22,000 1,804,000
4 Benang 5 gl 10,000 50,000
Jumlah X 16,666,000
XI PEKERJAAN PASANG PLAFOND
1 Kaso Merah 6x6 7 m3 1,800,000 12,600,000
2 GRC 467 m2 22,000 10,274,000
3 Lis Kayu 3x3 583 m3 8,000 4,664,000
4 Paku Jalosi 12 pak 350,000 4,200,000
5 Paku7 cm dan 10 cm 70 kg 18,000 1,260,000
6 Benang 5 gl 10,000 50,000
Jumlah XI 33,048,000
XII PEKERJAAAN PASANG KERAMIK
1 Keramik 40/40 455 m2 60,000 27,300,000
2 Pasir Pasang 23 m3 200,000 4,600,000
3 Semen Tiga Roda 175 sak 84,000 14,700,000
4 Oker Keramik 35 bks 9,000 315,000
5 Benang 5 gl 10,000 50,000
6 Pemotong Keramik 2 buah 350,000 700,000
Jumlah XII 47,665,000
XIII PEKERJAAN PASANG PINTU/RAM KACA
1 Daun Pintu 9 buah 450,000 4,050,000
2 Ram Kaca 56 buah 150,000 8,400,000
3 Kaca Mati 23 buah 50,000 1,150,000
4 Kunci Pintu 5 buah 100,000 500,000
5 Engsel Pintu 14 buah 25,000 350,000
6 Engsel Jendela 56 set 17,500 980,000
7 Aksesoris Jendela 2 set 400,000 800,000
Jumlah XIII 16,230,000
XIV PEKERJAAN PENGECATAN
1 Cat Tembok Romatek 23 pail 280,000 6,440,000
2 Cat Kayu Glotex 23 kg 45,000 1,035,000
3 Dempul Kayu 9 kg 35,000 315,000
4 Thinner/Minyak Cat 23 kg 18,000 414,000
5 Aksesoris Cat 2 paket 300,000 600,000
Jumlah XIV 8,804,000
XV PEKERJAAN PASANG LISTRIK
1 Kabel Interna isi 2 9 gl 380,000 3,420,000
2 Lampu Neon 23 buah 60,000 1,380,000
3 Saklar 19 buah 20,000 380,000
4 Aksesoris Listrik 2 paket 70,000 140,000
Jumlah XV 5,320,000
XVI UPAH TENAGA KERJA
1 Pekerja 467 HOK 80,000 37,360,000
2 Tukang 467 HOK 120,000 56,040,000
3 Kepala Tukang 280 HOK 120,000 33,600,000
Jumlah XVI 127,000,000
XVI I PEKERJAAN MEUBELER
1 Lomari 9 Unit 1,500,000 13,500,000
2 Meja Guru 23 Unit 450,000 10,350,000
3 Kursi Guru 23 Unit 165,000 3,795,000
4 Meja Siswa 93 Unit 195,000 18,135,000
5 Kursi Siswa 187 Unit 120,000 22,440,000
Jumlah XVI 68,220,000

TOTAL 701,239,000

Mengetahui, Penukal, 13 Agustus 2022


Kepala Desa Air Itam Timur Ketua BPD Air Itam Timur Ketua Yayasan

Alamsyah Darmadi Maulana Subhi, S.Pd.I


ustus 2022
asan

hi, S.Pd.I
PEMETAAN LAHAN BANGUNAN MA

SD Negeri 2 Penukal
ANGUNAN MADRASAH IBTIDA'IYAH NAHDLATUL ULAMA DESA

Pemetaan Bangunan
45 Meter
Teras 2 Meter
Wc Siswa 6 5 4 3 2 1
Teras 1 Meter

Teras 1 Meter
3x3

Wc Guru 6x6
3x3 Meter
Teras 2 Meter
23 Meter

Teras 1 Meter
Kantor
Halaman Madrasah
Teras 2 Meter

Teras 2 Meter

38 x 14 Meter
12x12
Meter

Teras 1 Meter

Masjid
Jalan Stapak
Jalan Raya Desa Air Itam Timur
Jalan Stapak Jalan Stapak

LAMA DESA AIR ITAM TIMUR

Jalan Stapak Jalan Stapak