DAFTAR SURVEY HARGA SATUAN BAHAN & ALAT

DESA LEMBANG

HARGA KEC.
HARGA
ENREKANG
No. Uraian Satuan RAB
(KLASTER III)
(Rp)
(Rp)

A. BAHAN & ALAT


1 Batu Kali (Besar) M3 332,550 333,000
2 Batu Gunung / Batu Belah M3 355,650 356,000
3 Batu Belah 2 - 3 Cm M3 464,220 464,000
4 Batu Belah 3 - 5 Cm Kg 441,540 442,000
5 Kerikil Sirtu M2 263,250 263,000
6 Sirtu Gunung M3 251,700 252,000
7 Sirtu Kali M3 245,925 246,000
8 Timbunan Pilihan M3 177,050 177,000
9 Tanah Timbunan M3 139,250 139,000
10 Pasir Ayak Beton M3 243,398 243,000
11 Pasir Pasang M3 222,535 223,000
12 Semen 40 kg (Bosowa) 40 Kg/Zak 75,876 76,000
13 Semen 50 kg (Bosowa) 50 Kg/Zak 87,230 87,000
14 Semen 40 kg (Survey) 40 Kg/Zak 64,000 64,000
15 Besi Beton (per kg) kg 14,223 15,000
16 Besi Beton diameter 6 (survey) batang 55,000
17 Besi Beton diameter 8 batang 77,000
18 Besi Beton diameter 10 batang 105,000
19 Besi Beton diameter 12 batang 144,000
20 Kawat Beton Kg 37,482 37,000
21 Kayu Kelas I (Kumea) M3 8,872,600 8,873,000
22 Kayu Kls. II M3 5,395,500 5,396,000
23 Kayu Perancah M3 3,597,000 3,597,000
24 Bambu Btg 15,000 15,000
25 Paku Campuran Kg 26,026 26,000
26 Tripleks 122 x 244x 0,3 Cm Lbr 65,000 65,000
27 Multipleks 122 x 244x 0,5 Cm Lbr 83,000 83,000
28 Plastik Alas Beton M2 3,000
29 Gorong-gorong Dia. 80 Cm buah 357,000
30 Gorong-gorong Dia. 60 Cm buah 306,000
31 Gorong-gorong Dia. 40 Cm buah 255,000
32 Gorong-gorong Dia. 30 Cm buah 204,000
33 Prasati buah 500,000
34 Tanda Pengenal Proyek buah 150,000
35 Tenda buah 380,000
36 Pipa PVC diameter 1/2" batang 31,850 32,000
m' 8,000 8,000
37 Pipa PVC diameter 1" batang 52,650 53,000
m' 13,250 14,000
38 Pipa PVC diameter 3" batang 174,200 174,000
m' 43,500 44,000
39 Pipa Gip 1" batang 326,918 327,000
m' 81,750 82,000
Bondek Galvanis T = 0.75 mm m2 110,000 110,000

ALAT

1 Sewa Excavator Jam 780,000 780,000


2 Mobilisasi Excavator (PP) 3,000,000 3,000,000
3 Molen (sewa) hari 390,000 390,000
4 Mobilisasi Molen 200,000 200,000
5 Walas (Tandem) paket 2,788,000 2,788,000
6 Pompa Air (sewa) hari 100,000 100,000
7 Selang Air rol 400,000 400,000
8 Skop buah 100,000 100,000
9 Cangkul buah 85,000 85,000
10 Gerobak buah 650,000 650,000
11 Drum buah 390,000 390,000
12 Tali Nylon m' 1,000 1,000
13 Alat Alat Bantu set 145,000 145,000
14 Bensin Ltr 12,000 12,000
15 Piloks buah 23,000 23,000
16 Solar Ltr 11,000 11,000

UPAH
1 Pekerja 110000 110,000
2 Tukang 130000 130,000
3 Mandor 125000 125,000
DAFTAR HARGA BAHAN DAN UPAH

HARGA
NO URAIAN SATUAN
(Rp)

Bahan
1 Semen 40 kg 64,000 zak
2 Pasir 243,000 m3
3 Sirtu Kali 246,000 m3
4 Kerikil Sirtu 263,000 m3
5 Batu Gunung / Batu Belah 356,000 m3
6 Tanah Timbunan 139,000 m3
7 Papan Kls III Cetakan 3,597,000 m3
8 Papan Mal 20/2, P = 4 m 58,000 Lembar
9 Besi Beton (Polos) 15,000 kg
10 Paku Biasa 26,000 kg
11 Kawat Beton 37,000 kg
12 Bondek, t=0,75 mm 110,000 m2
13 Plastik 3,000 m2

Alat
1 Alat Bantu 145,000 set
2 Molen Beton 390,000 hr
3 Excavator 780,000 jam
4 Mobilisasi Excavator 3,000,000 1 Paket (PP)
5 Gerobak Dorong 650,000 buah
6 Skop 100,000 buah
7 Drum 390,000 buah
8 Tali 1,000 m'

Upah
1 Pekerja 110,000 oh
2 Tukang 130,000 oh
3 Mandor Lapangan 125,000 oh
Kabupaten : Jenis Prasarana
Kecamatan : Take Of Sheet Lokasi
Desa : Volume

PEKERJAAN PEMBERSIHAN LAPANGAN & PERATAAN


Panjang = 210.00 m
Lebar = 3.50 m
Volume = 735.00 m2

PEKERJAAN GALIAN PARIT


Panjang = - m
Lebar.a = 0.40 m
Lebar.b = 0.40 m
Tinggi = 0.50 m
Volume = - m3

PEKERJAAN LEVELING
Lapisan Sirtu (Leveling)
Panjang = 206.00 m
Lebar = 3.00 m
Tebal = 0.08 m
Volume = 49.44 m3

Timbunan Bahu Jalan


Panjang = 206.00 m
Lebar = 1.00 m
Tebal = 0.15 m
Volume = 30.90 m3

PEKERJAAN BETON
Panjang = 206.00 m
Lebar = 3.00 m
Tebal = 0.15 m
Volume = 92.70 m3

PEKERJAAN BEKISTING
Bekisting samping
Luasan Bekisting
Panjang = 206.00 m
Tebal = 0.15 m
= 2.00 sisi
= 61.80 m2
Jumlah Papan Bekisting
Panjang = 206.00 m
= 412.00 m 2 sisi
Panjang Papan mall = 4.00 m
Volume = 103.00 Lembar
Total Bekisting = 26.00 Lembar

PLASTIK COR
Luasan Bekisting
Panjang = 206.00 m
Lebar = 3.00 m
= 618.00 m2

Tanggal Survei : Dibuat oleh :


Jenis Prasarana : Rabat Beton
:
: 206.00 m
RABAT BETON JALAN
PERHITUNGAN HOK, BAHAN DAN ALAT
Propinsi : Sulawesi Selatan
Kabupaten : Enrekang
Kecamatan : Enrekang
Desa : Lembang
Permen PUPR28-2016

Upah Bahan
No. Jenis Kegiatan Volume Satuan Tanah Papan Mall
Pekerja Tukang Ka. Kel. Semen 40 kg Pasir Kerikil Sirtu Sirtu Kali
Timbunan Lembar
1 Pembersihan Lapangan & Perataan 735.000 m2 0.100 - 0.050 - - - - - -
AHSP-CK.A.2.2.1.9 [ K3] 74.000 - 37.000 - - - - - -
2 Galian tanah biasa sedalam 1 m 0.000 m3 0.750 - 0.025 - - - - - -
AHSP-CK-A.2.3.1.1 - - - - - - - - -
3 Lapisan Sirtu 49.440 m3 0.300 - 0.010 - - - 1.200 - -
AHSP-CK-A.2.3.1.11 15.000 - - - - - 59.000 - -
4 Tanah Timbunan 30.900 m3 - - - - - - - 1.000 -
AHSP-SDA-B.05 a - - - - - - - 31.000 -
5 Pekerjaan Beton (Alat) 92.700 m3 1.323 0.189 0.132 8.150 0.543 0.762 -
AHSP-SDA-B.05 b 123.000 18.000 12.000 756.000 50.000 71.000 - - -
6 Bekisting 61.800 m2 0.520 0.260 0.026 - - - - - 1.000
AHSP-CK-A4.1.1.20 32.000 16.000 2.000 - - - - - 26.000
7 Plastik 618.000 m2 - -
- - - - - - - - -

Jumlah 244.000 34.000 51.000 756.000 50.000 71.000 59.000 31.000 26.000
Upah & Bahan ( Rp ) 110,000 130,000 125,000 64,000 243,000 263,000 246,000 139,000 58,000
Biaya ( Rp ) 26,840,000 4,420,000 6,375,000 48,384,000 12,150,000 18,673,000 14,514,000 4,309,000 1,508,000
Sub Total ( Rp ) 37,635,000 101,444,000
Alat

Paku Plastik Grobak Molen


- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - 0.250
- - 23.000
0.030 - -
2.000 - -
1.000
- 618.000 - -

2.000 618.000 - 23.000


26,000 3,000 0 390,000
52,000 1,854,000 0 8,970,000
101,444,000 8,970,000
RENCANA ANGGARAN BIAYA
(RAB)
PEMERINTAH DESA LEMBANG KEC. ENREKANG
TAHUN ANGGARAN 2019

BIDANG : PELAKSANAAN PEMBANGUNAN DESA


KEGIATAN : RABAT BETON JALAN TANI BAGEAN LUPPATAN
WAKTU PELAKSANAAN : HARI
VOLUME : 206 x 3 x 0,15 m

VOLUME Jumlah Harga


HARGA
NO URAIAN Dari Dari SATUAN SATUAN SWADAYA
Total ( Rp. )
Swadaya Dana Desa ( Rp. )
I. BAHAN
1 Semen 40 kg 756.00 - 756.00 zak 64,000 -
2 Pasir 50.00 - 50.00 m3 243,000 -
3 Kerikil 71.00 - 71.00 m3 263,000 -
4 Sirtu Kali 59.00 - 59.00 m3 246,000 -
5 Tanah Timbunan (Bahu Jalan) 31.00 - 31.00 m3 139,000 -
6 Papan Mall 27.00 - 27.00 lbr 58,000 -
7 Paku Campuran 2.00 - 2.00 kg 26,000 -
8 Plastik 623.00 - 623.00 m2 3,000 -

Sub Total 1) -
II. ALAT
1 Molen Beton 23.00 - 23.00 hari 390,000 -
2 Skop 2.00 - 2.00 buah 100,000 -
3 Drum 1.00 - 1.00 buah 390,000 -
4 Tali 63.00 - 63.00 m 1,000 -
5 Alat Bantu 2.00 - 2.00 set 145,000 -

Sub Total 2) -
III. U P A H
1 Pekerja 242.00 - 242.00 HOK 110,000 -
2 Tukang 34.00 - 34.00 HOK 130,000 -
3 Kepala Kelompok 51.00 - 51.00 HOK 125,000 -

Sub Total 3) -
IV. TRANSPARANSI
1 Tanda Pengenal Kegiatan 1.00 - 1.00 bh 100,000 -
2 Prasasti 1.00 - 1.00 bh 500,000 -

Sub Total 4) -
V. HONOR TPK
1 Ketua 1.00 - 1.00 OB 175,000 -
2 Sekretaris 1.00 - 1.00 OB 150,000 -
3 Anggota 2.00 - 2.00 OB 115,000 -
Sub Total 5) -

TOTAL BIAYA -

Sumber DANA DESA :


Dana SWADAYA MASYARAKAT :

Lembang, 20
DISETUJUI / MENGESAHKAN TELAH DIVERIFIKASI
KEPALA DESA SEKERTARIS DESA PELAKSANA KEGIATA

0 ______________________
FORMULIR
RAB - DESA

2.2.2

Jumlah Harga
Jumlah
DANA DESA Total
( Rp. ) ( Rp. )

48,384,000 48,384,000
12,150,000 12,150,000
18,673,000 18,673,000
14,514,000 14,514,000
4,309,000 4,309,000
1,566,000 1,566,000
52,000 52,000
1,869,000 1,869,000

101,517,000 101,517,000

8,970,000 8,970,000
200,000 200,000
390,000 390,000
63,000 63,000
290,000 290,000

9,913,000 9,913,000

26,620,000 26,620,000
4,420,000 4,420,000
6,375,000 6,375,000

37,415,000 37,415,000

100,000 100,000
500,000 500,000

600,000 600,000

175,000 175,000
150,000 150,000
230,000 230,000
555,000 555,000

150,000,000 150,000,000

DANA DESA : 150,000,000


SWADAYA MASYARAKAT : -

Lembang, 2019 Err:509


###
PELAKSANA KEGIATAN
RENCANA ANGGARAN BIAYA

PENGGUNAAN DANA DESA


TAHUN ANGGARAN 2019

RABAT BETON JALAN TANI BAGEAN LUPPATAN

DESA LEMBANG
KECAMATAN ENREKANG
KABUPATEN ENREKANG

PROVINSI SULAWESI SELATAN


Propinsi : Sulawesi Selatan
Kabupaten : Enrekang
Kecamatan : Enrekang
Desa : Lembang
Nama Kegiatan : Rabat Beton Jalan Tani Bagean Luppatan
Lokasi :

IDENTITAS APARAT

NAMA KADES BIDANG


NAMA SEKDES KEGIATAN
PELAKSANA KEGIATAN WAKTU PELAKSANAAN
TANGGAL Lembang, 2019

PEMBERSIHAN
Panjang 206.00 m
Lebar 3.50 m

LEVELING
Panjang 206.00 m
Lebar 3.00 m
Tebal 0.05 m

BETON
Panjang 206.00 m
Lebar 3.00 m
Tebal 0.15 m

TIMBUNAN BAHU JALAN


Panjang 206.00 m 150000000
Lebar 1.00 m Rp689,655
Tebal 0.15 m Rp218

BEKISTING
Panjang 206.00 m

URUGAN TANAH
A. BAHU JALAN
Panjang - m
Lebar - m (2sisi)
Tebal - m

B. BAGIAN TENGAH
Panjang - m
Lebar - m
Tebal - m
DESA LEMBANG
KECAMATAN ENREKANG, KABUPATEN ENREKANG
TAHUN ANGGARAN 2019

PELAKSANAAN PEMBANGUNAN DESA


RABAT BETON JALAN TANI BAGEAN LUPPATAN
U PELAKSANAAN HARI