URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

1 2 3 4 5
I PEKERJAAN PERSIAPAN

1 Pembersihan Lahan 400 m2 3,000 1,200,000

2 Pemasangan Bouwplank 60 m' 8,000 480,000

3 Pembelian Alat-alat Pekerjaan 1 paket 3,000,000 3,000,000

4 Pembelian Tempat Air 1 buah 1,500,000


1,500,000
Jumlah I 6,180,000

II PEKERJAAN TANAH
1 Galian Tanah Pondasi 50 m3 75,000 3,750,000

1,500,000
2 Pemasangan Pancang Bambu 100 batang 15,000

3 Galian Tanah Cakar Ayam 18 m3 75,000 1,350,000

600,000
4 Urugan Pasir Dasar Pondasi 4 m3 150,000

Jumlah II 7,200,000

III PEKERJAAN PASANG PONDASI


1 Batu Kali 30 m3 200,000 6,000,000

2 Pasir Pasang 30 m3 350,000 10,500,000

3 Semen Tiga Roda 70 zak 120,000 8,400,000

4 Ember 20 buah 20,000 400,000

50,000
5 Benang Gulung 5 gl 10,000

Jumlah III 25,350,000

IV PEKERJAAN SLUP BAWAH


1 Besi 12 FL SNI 60 batang 112,500 6,750,000

5,000,000
2 Besi 10 FL SNI 50 batang 100,000

3 Besi 6 FL SNI 30 batang 50,000 1,500,000

4 Tali Kawat 15 kg 25,000 375,000

5 Papan Cor 0.5 m3 1,800,000 900,000

6 Paku 7/5 8 kg 200,000 1,600,000

7 Semen Tiga Roda 80 zak 90,000 7,200,000

Jumlah IV 23,325,000

V PEKERJAAN BAHAN COR PASIR


1 BETON/BATU
Pasir Cor 20 m3 185,000 3,700,000

4,000,000
2 Batu Kerikil 20 m3 200,000

Jumlah V 7,700,000
VI PEKERJAAN KOLOM COR/CAKAR AYAM
1 Besi 12 FL SNI 40 batang 98,000 3,920,000

4,440,000
2 Besi 10 FL SNI 60 batang 74,000

3 Besi 6 FL SNI 40 batang 32,000 1,280,000

4 Tali Kawat 15 kg 20,000 300,000

5 Papan Cor 1 m3 1,400,000 1,400,000

1,400,000
6 Kayu Kaso 1 m3 1,400,000

7 Paku (7 cm, 10, cm dan 5 cm) 12 kg 15,000 180,000

2,940,000
8 Semen Tiga Roda 35 sak 84,000

Jumlah VI 15,860,000

VII PEKERJAAN PASANG BATA/KUSEN


1 Bata Merah 32,000 buah 1000 32,000,000

2 Pasir Pasang 20 m3 150,000 3,000,000

6,720,000
3 Semen Tiga Roda 80 sak 84,000

4 Bambu Esteger 60 batang 10,000 600,000

300,000
5 Kusen Pintu 6 buah 50,000

6 Kusen Jendela 24 buah 200,000 4,800,000

Jumlah VII 47,420,000

VIII PEKERJAAN COR BALOK ATAS


1 Besi 12 FL SNI 60 batang 112,500 6,750,000

2 Besi 10 FL SNI 50 batang 100,000 5,000,000

3 Besi 6 FL SNI 30 batang 50,000 1,500,000

4 Papan 1 m3 1,400,000 1,400,000

5 Pasir Beton 7 m3 175,000 1,225,000

3,000,000
6 Batu Kerikil 15 m3 200,000

7 Bambu Penunjang 80 batang 7,000 560,000

2,940,000
8 Semen Tiga Roda 35 sak 84,000

9 Tali Kawat 10 kg 20,000 200,000

288,000
10 Paku (7 cm, 10 cm, dan 5 cm) 16 kg 18,000

Jumlah VIII 22,863,000

IX PEKERJAAN ATAP

1 Besi 8 FL SNI 700 batang 62,000 43,400,000

2 Besi 6 FL SNI 50 batang 40,000 2,000,000

3 Papan 7 m3 1,400,000 9,800,000

4 Bambu 700 batang 10,000 7,000,000

5 Kayu Kaso 6x6 4 m3 1,800,000 7,200,000

6 Tali Kawat 35 kg 20,000 700,000

7 Semen Tiga Roda 100 sak 84,000 8,400,000

8 Ember Aduk 30 buah 20,000 600,000


9 Pasir beton 18 m3 200,000 3,600,000

10 Batu Kerikil 15 m3 250,000 3,750,000

11 Paku (7 cm, 10 cm, dan 5 cm) 3 dus 450,000 1,350,000

Jumlah IX 87,800,000

X PEKERJAAN PELISTER ACI

1 Pasir Pasang 17 m3 200,000 3,400,000

2 Semen Tiga Roda 80 sak 84,000 6,720,000


3 Kelasid 50 bal 22,000 1,100,000

4 Benang 4 gl 15,000 60,000

Jumlah X 11,280,000

XI PEKERJAAN PASANG PLAFOND


1 Kaso Merah 6x6 4 m3 2,000,000 8,000,000

9,000,000
2 GRC 400 m2 22,500

3 Lis Kayu 3x3 750 m3 8,000 6,000,000

5,250,000
4 Paku Jalosi 15 pak 350,000

5 Paku 7 cm dan 10 cm 60 kg 20,000 1,200,000

6 Benang 4 gl 15,000 60,000

Jumlah XI 29,510,000

XII PEKERJAAAN PASANG KERAMIK

1 Keramik 60/60 250 m2 120,000 30,000,000

2 Pasir Pasang 15 m3 200,000 3,000,000

3 Semen Tiga Roda 85 sak 84,000 7,140,000

4 Oker Keramik 25 bks 8,500 212,500

5 Benang 4 gl 15,000 60,000

6 Pemotong Keramik 1 buah 500,000 500,000

Jumlah XII 40,912,500

XIII PEKERJAAN PASANG PINTU/RAM KACA


1 Daun Pintu 8 buah 600,000 4,800,000

8,640,000
2 Ram Kaca 48 buah 180,000

3 Kaca Mati 12 buah 80,000 960,000

800,000
4 Kunci Pintu 8 buah 100,000

5 Engsel Pintu 16 buah 30,000 480,000

6 Engsel Jendela 48 set 17,500 840,000

7 Aksesoris Jendela 1 set 800,000 800,000

Jumlah XIII 17,320,000

XIV PEKERJAAN PENGECATAN


1 Cat Tembok Romatek 20 pail 350,000 7,000,000

1,500,000
2 Cat Kayu Glotex 20 kg 75,000

3 Dempul Kayu 8 kg 50,000 400,000

500,000
4 Thinner/Minyak Cat 20 kg 25,000
5 Aksesoris Cat 1 paket 500,000 500,000

Jumlah XIV 9,900,000

XV PEKERJAAN PASANG LISTRIK


1 Kabel Interna isi 2 6 gl 400,000 2,400,000

1,200,000
2 Lampu Neon 20 buah 60,000

3 Saklar 20 buah 15,000 300,000

600,000
4 Aksesoris Listrik 1 paket 600,000

Jumlah XV 4,500,000

XVI UPAH TENAGA KERJA


1 Pekerja 200 HOK 100,000 20,000,000

2 Tukang 200 HOK 120,000 24,000,000

3 Kepala Tukang 120 HOK 150,000 18,000,000

Jumlah XVI 62,000,000

XVI PEKERJAAN MEUBELER


I
1 Lemari 6 Unit 3,000,000 18,000,000

2 Meja Guru 10 Unit 800,000 8,000,000


3 Kursi Guru 10 Unit 180,000 1,800,000
4 Meja Siswa 159 Unit 195,000 31,005,000
5 Kursi Siswa 159 Unit 119,999 19,079,841
6 Papan tulis 10 Unit 300,000 3,000,000
Jumlah XVI 80,884,841
Grand TOTAL 500,005,341