HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA
( Rp. ) ( Rp. )
A PEKERJAAN LANTAI I ( Satu )
I. PEKERJAAN PERSIAPAN
1 Uitzet/ prngukuran 66.00 m' 5,000
330,000
2 Bouplank 66.00 m' 18,000
1,188,000
3 Brak/gudang kerja 15.00 125,000
m2 1,875,000
4 Alat bantu kerja 1.00 ls 1,500,000
1,500,000
5 Bongkar bangunan lama 125,000
106.88 m2 13,360,000
6 Buang puing + bekas bongkaran 15.00 rit 105,000
1,575,000
Jumlah I
19,828,000
PEKERJAAN GALIAN TANAH +
II.
URUGAN
1 Galian tanah untuk foot plat 65.87 m3 25,000
1,646,750
2 Galian tanah untuk pondasi batu kali 42.84 m3 17,500
749,700
3 Urugan tanah kembali 27.00 m3 12,000
324,000
4 Pasir urug bawah footplat + pondasi 9.00 m3 87,250
785,250
Jumlah II
3,505,700.00
III. PEKERJAAN BETON
1 Foot plat 10.00 2,750,000
m3 27,500,000
2 Sloof struktur 26/30 4.00 2,900,000
m3 11,600,000
3 Kolom Struktur 40/50 21.60 3,400,000
m3 73,440,000
4 Kolom struktur 25/30 1.65 3,225,000
m3 5,321,250
5 Kolom bulat 30 1.00 3,100,000
m3 3,100,000
6 Kolom praktis 15/15 3.95 2,600,000
m3 10,270,000
7 Kolom struktur 25/25 1.50 3,225,000
m3 4,837,500
8 Sloof struktur 20/25 1.93 2,850,000
m3 5,500,500
9 Pondasi tangga 0.47 2,900,000
m3 1,363,000
10 Balok latai 10/20 0.28 2,800,000
m3 784,000
11 Balok struktur 30/50 10.05 3,400,000
m3 34,170,000
12 Balok struktur 20/40 1.68 3,200,000
m3 5,376,000
13 Balk struktur 20/30 2.29 3,200,000
m3 7,328,000
14 Plat lantai tebal 12 cm 13.69 3,250,000
m3 44,492,500
15 Lisplank beton t. 7 cm 3.30 3,300,000
m3 10,890,000
16 Plat leuvel t. 7 cm 0.84 3,300,000
m3 2,772,000
17 Plat tangga t. 12 cm 1.79 3,250,000
m3 5,817,500
18 Rabat lantai t. 5 cm 5.43 1,950,000
m3 10,588,500
Jumlah III
265,150,750
IV. PEKERJAAN PASANGAN
1 Pasang pondasi batu kali 27.51 285,000
m3 7,840,350
2 Pasang dinding bata 87,500
158.20 m2 13,842,500
3 Plesteran dinding 22,500
395.25 m2 8,893,125
4 Acian dinding 13,000
395.25 m2 5,138,250
5 Pasang keramik lt. 40/40 150,000
138.00 m2 20,700,000
6 Pasang keramik lt. 20/30 18.00 105,000
m2 1,890,000
7 Pasamg keramik dinding 20/25 37.50 115,000
m2 4,312,500
8 Pasang keramik plint 10/40 61.00 m' 48,500
2,958,500
Jumlah VI
65,575,225
V. PEKERJAAN KUSEN PINTU + JENDELA
1 Pasang kusen + daun pintu gundul 3.00 1,800,000
unt 5,400,000
2 pasang kusen + daun pintu kupu tarung 2.00 4,750,000
unt 9,500,000
3 Pasang kusen jendela + daun 4.00 2,450,000
unt 9,800,000
4 Pasang kusen BV + kaca 4.00 1,050,000
unt 4,200,000
Jumlah V
28,900,000
II . PEKERJAAN PASANGAN
1Pasang bata m2 96,250
147.80 14,225,750
2Plesteran dinding m2 24,750
369.50 9,145,125
3Acian dinding m2 14,300
369.50 5,283,850
4pasang keramik 40/40 79.00 m2 143,000
11,297,000
5Pasang keramik plint 10/40 53.40 m' 53,350
2,848,890
Jumlah II
42,800,615
III . PEKERJAAN JENDELA
1Pasang kusen jendela + daun 11.00 unt 2,450,000
26,950,000
Jumlah III
26,950,000
IV. PEKERJAAN ATAP
1Pasang rangka atap baja ringan 67.50 m2 165,000
11,137,500
2Pasang genteng galvalum 67.50 m2 130,000
8,775,000
3Pasang talang tegak PVC 3'' 40.00 m' 65,000
2,600,000
Jumlah IV
22,512,500
V . PEKERJAAN PLAFON
1 Pasang plafon + rangka m2 125,000
128.31 16,038,750
2Liss gypsum m' 90,000
111.10 9,999,000
Jumlah V
26,037,750
VI. PEKERJAAN ELECTRICAL
Pasang instalasi lampu 45.00 ttk 115,000
5,175,000
Pasanng isntalasi stop kontak 4.00 ttk 115,000
460,000
Pasang lampu downlight 10.00 bh 85,000
850,000
Pasang lampu slimp 20.00 bh 92,500
1,850,000
Jumlah VI
8,335,000
VII. PEKERJAAN CAT
1Cat dinding m2 25,000
369.50 9,237,500
2Cat kusen m' 65,000
107.80 7,007,000
3Cat daun jendela m' 65,000
112.40 7,306,000
Jumlah VII
23,550,500
VIII.PEKERJAAN LAIN-LAIN
1Pasamg reilling void + tangga 23.00 m' 375,000
8,625,000
2Andang kerja 1.00 ls 7,500,000
7,500,000
Jumlah VIII
16,125,000
JUMLAH B ( I s/d VIII) 290,182,540
JUMLAH A + B 759,043,215
DIBULATKAN 759,000,000
Terbilang : Tujuh ratus lima puluh
sembilan juta rupiah.
Yogyakarta, 18 Juli
2012
Hormat kami
Panitia