RENCANA 

ANGGARAN  BIAYA (RAB)


TAMAN PENDIDIKAN AL-QUR’AN AL-HIKAMAH
DUSUN BUNTEL DESA KERAS KECAMATAN DIWEK KABUPATEN JOMBANG
TAHUN ANGGARAN 2023
Bidang  : Pelaksanaan Pembanguna
Sub Bidang  : Pekerjaan Umum Dan Penataan Ruang
Kegiatan  : Pembangunan Taman Pendidikan Al-Qura’an
TPQ AL-HIKMAH uk. 5 m x 11 m. 1 unit
Waktu
 : 30 (Tiga puluh hari kalender)
Pelaksanaan

Rincian
 :
Pendanaan

NO. U  R  A  I  A  N VOLUME HARGA JUMLAH (Rp)


BAHAN SATUAN  (Rp)
I.
1 Semen PC 50 Kg 50 Zak 90,000 4,500,000.00
2 Semen Putih 1 Kg 10,000 10,000.00
3 Pasir Beton 14 M³ 160,000 2,240,000.00
4 Pasir Urug 7 M³ 120,000 840,000.00
5 Batu Pecah 2/3 3 M³ 500,000 1,500,000.00
Cm
6 Batako Uk. 7 x 15 x 30 1000 Bh 2,800 2,800,000.00
Cm
7 Keramik 20 x 20 12 Kotak 70,000 840,000.00
cm
8 Kayu Belian 9/9-400 Cm 25 Btg 205,000 5,125,000.00
9 Kayu Belian 8/8-400 Cm 10 Btg 215,000 2,150,000.00
10 Kayu Belian 4/8 - 400 Cm 12 Btg 103,000 1,236,000.00
11 Kayu Klas I 8/8 - 400 Cm 39 Btg 81,000 3,159,000.00
12 Kayu Klas I 5/10 - 400 Cm 4 Btg 75,000 300,000.00
13 Kayu Klas II 8/12 - 400 61 Btg 157,000 9,577,000.00
Cm
14 Kayu Klas II 6/12 - 400 18 Btg 150,000 2,700,000.00
Cm 
15 Kayu Klas II 5/10 - 400 8 Btg 66,000 528,000.00
Cm
16 Kayu Klas II 5/7 - 400 Cm 65 Btg 32,000 2,080,000.00
17 Kayu Klas II 4/6 - 400 Cm 65 Btg 24,000 1,560,000.00
18 Kayu Klas II 2/3 - 400 Cm 50 Btg 15,000 750,000.00
19 Papan Mall Klas III 2/18 - 9 Kpg 21,000 189,000.00
4m
20 Papan Klas I Ketam 2/15 30 Kpg 140,000 4,200,000.00
-4m
21 Alas Kayu Hutan 4/8 - 4 12 Btg 46,000 552,000.00
m
22 Amplas 15 Lbr 5,000 75,000.00
23 Dempul 24 Kg 15,000 360,000.00
24 Cat Tembok 50 Kg 30,000 1,500,000.00
25 Cat Kilat/Cat Minyak 10 Kg 75,000 750,000.00
26 Cat Dasar 10 Kg 25,000 250,000.00
27 Thinner 4 Ltr 27,000 108,000.00
28 Residu/Terr 10 Ltr 28,000 280,000.00
29 Kawat Simpai 50 Kg 20,000 1,000,000.00
30 Besi Plat Beugel 25 Bh 20,000 500,000.00
31 Baut Bangunan 100 bh 5,000 500,000.00
32 Paku Campuran 51 Kg 22,000 1,122,000.00
33 Paku Atap 10 Kg 25,000 250,000.00
34 Paku Triplek 5 Kg 10,000 50,000.00
35 Kunci Pintu  2 set 60,000 120,000.00
36 Engsel Pintu 5 set 40,000 200,000.00
37 Engsel Jendela 10 set 50,000 500,000.00
38 Slot Jendela 10 set 10,000 100,000.00
39 Kait Angin 32 set 10,000 320,000.00
40 Atap Seng Gelombang 100 Lbr 80,000 8,000,000.00
Warna
41 Seng Polos BJLS 0.30 19 Lbr 60,000 1,140,000.00
42 Pintu Panel Kayu Belian 1 Bh 1,500,000 1,500,000.00
43 Pintu Panel Kayu Klas I 1 Bh 1,000,000 1,000,000.00
44 Jendela Kaca Jungkit 10 Bh 350,000 3,500,000.00
45 Ventilasi  10 Bh 250,000 2,500,000.00
46 Triplek 3 mm 10 Bh 47,000 470,000.00
47 Kloset Jongkok  1 Bh 259,000 259,000.00
48 Kran Air 2 Bh 20,000 40,000.00
49 Floordrain 2 Bh 35,000 70,000.00
51 Pipa PVC 4" 2 Btg 190,000 380,000.00
52 Pipa PVC 2" 4 Btg 85,000 340,000.00
53 Pipa Galvanis 2" 1 Btg 350,000 350,000.00
54 Lem Pralon 1 Bh 10,000 10,000.00
55 Talang Air Fiber lengkap 10 M1 17,000 170,000.00

74,550,000.00

II. UPAH
1 Pekerja 90 HOK 85,000.00 7,650,000.00
2 Tukang 30 HOK 120,000.00 3,600,000.00
3 Kepala Tukang 30 HOK 140,000.00 4,200,000.00

J  U  M  L  A  H  HOK 15,450,000.00
(Rp.)

Total Anggaran 90,000,000.00

Jombang, 18 Januari 2023

Pengurus TPQ Al-Hikamh


Ketua                                                                              Sekretaris

MISKAN LAILI HIDAYATI