Lampiran 1

RENCANA ANGGARAN BIAYA (RAB)


PEMBANGUNA MCK
SMK LENTERA BANGSA KARAWANG
TAHUN ANGGARAN 2021

Kategori Harga Satuan


No Uraian Material Volume Satuan Biaya (Rp ) Jumlah

BAHAN
1 Semen @. 50 Kg 30.00 Zak I-b 51,000 1,530,000
2 Pasir Beton 6.80 M3 I-a 250,000 1,700,000
3 Kerikil Beton 2.36 M3 I-a 200,000 472,000
4 Kawat Harmonika 4.50 M2 I-b 40,000 180,000
5 Hebel 224.00 Bh I-b 7,800 1,747,200
6 Besi Ø 10 mm 6.40 Btng I-b 60,000 384,000
7 Besi Ø 6 mm 12.80 Btng I-b 45,000 576,000
8 Batu Belah 3.28 M3 I-b 350,000 1,146,600
9 Balok Kuda -Kuda 5/7 10.00 Bh I-a 25,000 250,000
10 Balok Kasau 5/5 10.00 Bh I-a 15,000 150,000
11 Papan Lap 2/10 6.00 Bh I-a 15,000 90,000
12 Papan Listplank Ulin 4.00 Kpng I-a 60,000 240,000
13 Atap Seng 8.00 Lbr I-b 60,000 480,000
14 Nok Atap Seng/ Bubungan 4.00 M1 I-b 20,000 80,000
15 Cat Kilap 4.00 Kg I-b 60,000 240,000
16 Klosed Jongkok 1.00 Bh I-b 150,000 150,000
17 Pipa PVC Dia. 4 " 2.00 Btng I-b 180,000 360,000
18 Pipa PVC Dia. 2 " 1.00 Btng I-b 70,000 70,000
19 Lem dan Seal Tape 3.00 Bh I-b 20,000 60,000
20 Engsel dan Kunci 3.00 Bh I-b 200,000 600,000
21 Pintu Panel ( 90 x 180 cm ) 1.00 Bh I-b 700,000 700,000
22 Bak Air Biasa 1.00 Bh I-b 200,000 200,000
23 Sepitank 1.00 Bh I-b 3,000,000 3,000,000
24 Papan Nama Kegiatan 1.00 Bh I-a 200,000 200,000

TOTAL BAHAN 14,605,800


UPAH KERJA
1 Mandor / Kepala Kerja 5.0 Hok 65,000 325,000
2 Tukang 20.0 Hok 60,000 1,200,000
3 Pekerja 20.0 Hok 55,000 1,100,000

TOTAL UPAH 2,625,000.00

TOTAL BIAYA 17,230,800


Total Pembangunan 17,230,800 x 3 Unit = 51,692,400
Karawang, 22 Desember 2020
Ketua Panitia Sekretaris

Heri Maulana Sudirja, S.Pd Pepen Sunarya, S.Pd.

Mengetahui Menyetujui
Ketua Yayasan Kepala Sekolah
Hj. Iyam Mariyam Dr. Ahmad Jaelani, MM