PERHITUNGAN DIPA

NILAI TOTAL PROYEK : Rp 600,000,000.00


PERENCANAAN PENGAWASAN PENGELOLA TOTAL BIAYA KONST
Rp 10,016,670.00 Rp 6,535,420.00 Rp 2,125,000.00 Rp 143,677,090.00
Rp 11,665,000.00 Rp 7,660,000.00 Rp 2,475,000.00 Rp 171,800,000.00

PERENCANAAN :
A= 143,677,090.00 D= 10,016,670.00
B= 600,000,000.00 X= ?
C= 171,800,000.00 E= 11,665,000.00
B - A = 456,322,910.00 E - D = 1,648,330.00

C - A = 28,122,910.00 ((B-A)x(E-D)/(E-D) = 26,745,836.13

( B - A ) x ( C - A ) = 752,170,742,240,300.00

BIAYA PENGELOLA = Rp 36,762,506.13


DIBULATKAN =

PENGAWASAN :
A= 143,677,090.00 D= 6,535,420.00
B= 600,000,000.00 X= ?
C= 171,800,000.00 E= 7,660,000.00
B - A = 456,322,910.00 E - D = 1,124,580.00
C - A = 28,122,910.00 ((B-A)x( -D)/(E-D) = 18,247,457.97
( B - A ) x ( C - A ) = 513,171,618,127,800.00
BIAYA PENGELOLA = Rp 24,782,877.97
DIBULATKAN =

BIAYA PENGELOLAAN PROYEK :


A= 143,677,090.00 D= 2,125,000.00
B= 600,000,000.00 X= ?
C= 171,800,000.00 E= 2,475,000.00
B - A = 456,322,910.00 E - D = 350,000.00
C - A = 28,122,910.00 ((B-A)x(E-D)/(E-D) = 5,679,107.12
( B - A ) x ( C - A ) = 159,713,018,500,000.00

BIAYA PENGELOLA = Rp 7,804,107.12

DIBULATKAN =

TIADA KEMULIAAN
TIADABIAYA
KEMULIAAN TANPA
TANPA
FISIK BANGUNAN ISLAM
= Rp
ISLAM 530,650,508.78
TIADA
TIADAISLAM
ISLAM TANPA
TANPASYARIAH
DIBULATKANSYARIAH
=
TIADA
TIADASYARIAH
SYARIAHTANPA
TANPADAULAH
DAULAHKHILAFAH
KHILAFAHISLAMIYAH
ISLAMIYAH

data file
HITUNGAN BERAT BESI BETON TIAP M3

PONDASI STP. 15/80/80 CM TYPE B


Tulangan pokok dia 10 mm = 1.600 x 3.684 x 0.610 = 3.596 Kg
Beugel dia 10 mm = 1.600 x 3.684 x 0.610 = 3.596 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > PONDASI STP. 15/80/80 CM TYPE B = 7.192 Kg
-------------- -----
BERAT TIAP M3 = 74.912 Kg
DIBULATKAN = 75.000 Kg

SLOOF 15/20 CM
- panjang tiap M3 = 1.000 : ( 0.500 x 0.300 ) = 6.667 M!
Tulangan pokok dia 10 mm = 6.000 x 6.667 x 0.620 = 24.800 Kg
Beugel dia 8 mm = 1.440 x 33.333 x 0.393 = 18.864 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > SLOOF 15/20 CM = 43.664 Kg
-------------- -----
DIBULATKAN = 121.000 Kg

SLOOF 20/35 CM
- panjang tiap M3 = 1.000 : ( 0.200 x 0.350 ) = 14.286 M!
Tulangan pokok dia 10 mm = 6.000 x 14.286 x 0.620 = 53.143 Kg
Beugel dia 8 mm = 0.980 x 71.429 x 0.393 = 27.510 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > SLOOF 20/35 CM = 80.653 Kg
-------------- -----
DIBULATKAN = 81.000 Kg

KOLOM 15/15 CM
- panjang tiap M3 = 1.000 : ( 0.150 x 0.150 ) = 44.444 M!
Tulangan pokok dia 10 mm = 4.000 x 44.444 x 0.620 = 110.222 Kg
Beugel dia 8 mm = 0.480 x 222.222 x 0.390 = 41.600 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > KOLOM 15/15 CM = 151.822 Kg
-------------- -----
DIBULATKAN = 152.000 Kg

KOLOM 20/30 CM
- panjang tiap M3 = 1.000 : ( 0.200 x 0.300 ) = 16.667 M!
Tulangan pokok dia 10 mm = 6.000 x 16.667 x 0.620 = 62.000 Kg
Beugel dia 8 mm = 0.880 x 83.333 x 0.393 = 28.820 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > KOLOM 20/30 CM = 90.820 Kg
-------------- -----
DIBULATKAN = 91.000 Kg
KOLOM L 15/55 CM
- panjang tiap M3 = 1.000 : ( 0.150 x 0.550 ) = 12.121 M!
Tulangan pokok dia 10 mm = 6.000 x 12.121 x 0.620 = 45.091 Kg
Beugel dia 8 mm = 1.240 x 60.606 x 0.393 = 29.535 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > KOLOM L 15/55 CM = 74.625 Kg
-------------- -----
DIBULATKAN = 75.000 Kg

BALOK 15/25 CM
- panjang tiap M3 = 1.000 : ( 0.150 x 0.250 ) = 26.667 M!
Tulangan pokok dia 10 mm = 6.000 x 26.667 x 0.620 = 99.200 Kg
Beugel dia 8 mm = 0.680 x 133.333 x 0.393 = 35.632 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > BALOK 15/25 CM = 134.832 Kg
-------------- -----
DIBULATKAN = 135.000 Kg

BALOK 15/20 CM
- panjang tiap M3 = 1.000 : ( 0.150 x 0.200 ) = 33.333 M!
Tulangan pokok dia 10 mm = 4.000 x 33.333 x 0.620 = 82.667 Kg
Beugel dia 8 mm = 0.580 x 166.667 x 0.393 = 37.990 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > BALOK 15/20 CM = 120.657 Kg
-------------- -----
DIBULATKAN = 121.000 Kg

RINKBALK 15/20 CM
- panjang tiap M3 = 1.000 : ( 0.150 x 0.200 ) = 33.333 M!
Tulangan pokok dia 8 mm = 4.000 x 33.333 x 0.620 = 82.667 Kg
Beugel dia 8 mm = 0.580 x 166.667 x 0.393 = 37.990 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > RINKBALK 15/20 CM = 120.657 Kg
-------------- -----
DIBULATKAN = 121.000 Kg

RINKBALK 20/20 CM
- panjang tiap M3 = 1.000 : ( 0.200 x 0.200 ) = 25.000 M!
Tulangan pokok dia 8 mm = 4.000 x 25.000 x 0.620 = 62.000 Kg
Beugel dia 8 mm = 0.680 x 125.000 x 0.393 = 33.405 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > RINKBALK 20/20 CM = 95.405 Kg
-------------- -----
DIBULATKAN = 96.000 Kg

PLAT CANOPI 7,5 CM


- panjang tiap M3 = 1.000 : ( 0.075 x 0.650 ) = 20.513 M!
Tulangan pokok dia 8 mm = 4.000 x 20.513 x 0.393 = 32.246 Kg
Beugel dia 8 mm = 0.790 x 136.752 x 0.620 = 66.981 Kg
-------------- -----
BERAT BESI TULANGAN TIAP M3 > PLAT CANOPI 7,5 CM = 99.227 Kg
-------------- -----
DIBULATKAN = 100.000 Kg
BACKUP DATA PERHITUNGAN
PROGRAM
PEKERJAAN

LOKASI
TAHUN ANGGARAN

Halaman 1
NO. URAIAN PEKERJAAN DIMENSI VOLUME
1 2 3 4

I Pekerjaan Pendahuluan
1 Pembuatan papan nama kegiatan 1.00 Bh
2 Persiapan dan Pembersihan lokasi 27.000 M' 16.000 M' 432.00 M2
3 Pengukuran dan pasang bouwplank 14.550 M' 14.000 M' 2.000 ss 57.10 M'

II Pekerjaan Tanah
1 Galian tanah pondasi
Footplat type F-1 0.900 M' 0.900 M' 1.200 M' 20.000 Bh 19.44 M3
Pondasi batu belah P1 0.700 M' 0.700 M' 0.600 M' 63.000 M' 26.46 M3
45.90 M3
2 Timbunan kembali
Volume Galian 45.90 M3
dikurang Volume pondasi 20.53 M3
Total Volume urugan kembali 25.37 M3
3 Tanah urug dibawah lantai
Lantai ruang ganti dan pertemuan 150.000 M2 0.400 M' 60.00 M3

III Pekerjaan Pondasi


1 Pondasi Batu Belah camp. 1 Pc : 4 Ps
Pondasi batu belah P2 0.200 M' 0.500 M' 0.600 M' 63.000 M' 13.23 M3
13.23 M3
2 Pondasi Rollag Bata tangga 0.500 M' 25.900 M' 12.95 M2
3 Pondasi Footplat beton bertulang besi 70 Kg
Telapak type F-1 0.800 M' 0.800 M' 0.200 M' 20.000 Bh 2.56 M3
Limas 0.150 M2 0.810 M2 0.100 M' 20.000 Bh 0.96 M3
Kaki 0.300 M' 0.300 M' 0.630 M' 20.000 Bh 3.78 M3
7.30 M3

Halaman 2
1 2 3 4

IV. Pekerjaan Beton


1 Sloof 15/20 cm beton bertulang 0.150 M' 0.200 M' 63.000 M' 1.89 M3
2 Sloof 20/30 cm beton bertulang 0.200 M' 0.300 M' 41.500 M' 2.49 M3
3 Kolom 15/15 cm beton bertulang 0.150 M' 0.150 M' 3.850 M' 4.000 Bh 0.35 M3
0.35 M3
4 Kolom 15/25 cm beton bertulang 0.150 M' 0.250 M' 3.850 M' 14.000 Bh 2.02 M3
5 Kolom 30/30 cm beton bertulang besi 91 kg 0.300 M' 0.300 M' 3.800 M' 12.000 Bh 4.10 M3
6 Kolom 30/50 cm beton bertulang besi 91 kg 0.300 M' 0.500 M' 3.600 M' 8.000 Bh 4.32 M3
7 Balok 15/25 cm Beton bertulang \ 0.150 M' 0.250 M' 78.400 M' 2.94 M3
8 Balok 20/30 cm Beton bertulang 0.200 M' 0.300 M' 24.250 M' 1.46 M3
9 Balok 30/50 cm beton bertulang 0.300 M' 0.500 M' 42.900 M' 6.44 M3
10 Dinding beton dibawah kubah tebal 0.090 M' 8.250 M' 0.74 M3
11 Dak atap cor beton bertulang tebal 10 cm 113.850 M' 0.100 M' 11.39 M3
12 Pembuatan hiasan dinding (Ornamen beton) 1.000 Unit

V Pekerjaan Dinding dan pasangan


1 Pasangan dinding bata camp. 1 : 4
bagian dalam 3.600 M' 29.600 M' 106.56 M2
KM/wc 3.600 M' 10.600 M' 38.16 M2
luar 4.750 M' 26.600 M' 126.35 M2
Dibawah menara 1.150 M' 12.800 M' 14.72 M2
dibawah kubah 0.800 M' 15.000 M' 12.00 M2
297.79 M2
Dikurang Luas Kusen dan ventilasi
Pintu utama 4.050 M2 3.000 Bh 12.15 M2
Pintu 1.680 M2 2.000 Bh 3.36 M2
Jendela 1.120 M2 18.000 Bh 20.16 M2
Ventilasi 0.120 M2 18.000 Bh 2.16 M2
Ventilasi WC 0.500 M2 2.000 Bh 1.00 M2
Ventilasi ruang imam 0.840 M2 1.000 Bh 0.84 M2
Hiasan dinding bata kerawang 3.200 M2 6.000 Bh 19.20 M2
Hiasan dinding bata kerawang smping 1.850 M2 4.000 Bh 7.40 M2
66.27 M2
Total pasangan Bataco 231.52 M2
2 Plesteran dinding camp. 1 pc : 4 ps 231.520 M2 2.000 SS 463.04 M2
Dikurang Dinding Keramik KM/WC 12.88 M2
Total Plesteran 450.16 M2
4 Dinding keramik 20/20 cm KM/WC & ruang udhu 1.400 M' 4.600 M2 2.000 Bh 12.88 M2
5 Dinding plin 10/20 cm KM/WC & ruang udhu 4.600 M' 2.000 Bh 9.20 M2
3 Pasangan hiasan Bata terawang 0.700 2.000 M' 6.000 Bh 8.40 M2
Motif garis 0.150 3.000 SS 6.000 Bh 2.70 M2
11.10 M2
7 Plesteran Bentuk Kotak-kotak dan hiasan dinding 1.00 Ls
8 Pembuatan Motif Pasir dinding luar bag. bawah 1.00 Ls

Halaman 3
1 2 3 4

VI Pekerjaan Rangka Kap dan Atap


1 Gording Murplat, Nuk kayu lanan 6/12 cm
Gording atap bangunan 6/12cm 0.06 M' 0.120 M' 67.000 M' 1.000 Bh 0.48 M3
Jurai 6/12 cm 0.06 M' 0.120 M' 2.600 M' 4.000 Bh 0.07 M3
0.56 M3
3 ### Kasau 5/7 cm & reng 3/5 cm kayu lanan
Atap Bangunan 16.640 M2 4.000 M' 66.56 M2
3 Atap Metal prima color 0.3 mm 66.56 M2
5 #NAME?
Listplank Atap Atas 55.95 M'
Listplank Atap Teras
Depan teras 17.750 M' 1.000 Bh 17.75 M'
samping Teras 15.750 M' 2.000 Bh 31.50 M'
105.20 M'
6 Bubungan metal color type U
Atas datar 10.35 M'
Mereng 31.40 M'
Teras 31.75 M'
73.50 M'
6 Kubah bahan plat tembaga diameter 3 m 1.00 Ls

VII Pekerjaan Kusen/Daun Pintu, Jendela


dan asesiorisnya
1 Kusen pintu dan jendela kayu klas I (Benuas)
Pintu utama 0.050 M' 0.100 M' 6.900 M' 3.000 Bh 0.10 M2
Pintu 0.050 M' 0.100 M' 5.200 M2 2.000 Bh 0.05 M3
Jendela 0.050 M' 0.100 M' 5.500 M2 18.000 Bh 0.50 M4
Ventilasi 0.050 M' 0.100 M' 10.460 M2 0.000 Bh 0.00 M5
Ventilasi WC 0.050 M' 0.100 M' 4.500 M2 2.000 Bh 0.05 M6
Ventilasi ruang imam 0.050 M' 0.100 M' 5.000 M2 1.000 Bh 0.03 M7
Hiasan dinding bata kerawang 0.050 M' 0.100 M' 4.500 M2 0.000 Bh 0.00 M8
Hiasan dinding bata kerawang smping 0.050 M' 0.100 M' 4.500 M2 0.000 Bh 0.00 M9
0.72 M2
2 Pintu Panel kayu Klas I Benuas Km/Wc
Pintu utama 3.710 M2 3.000 Bh 11.13 M2
Pintu 1.470 M2 2.000 Bh 2.94 M2
14.07 M2
4 Rangka Jendela kaca kayu lanan 0.260 M2 18.000 Bh 4.68 M2
5 Kaca raybean mati dan hidup 5 mm 0.600 M2 18.000 Bh 10.80 M2
Kaca Hidup
Pintu 2.764 M2 #REF! Bh #REF! M2
Jendela 0.500 M2 18.000 Bh 9.00 M2
Kaca mati dan hidup
Ventilasi 2.860 M2 0.000 Bh 0.00 M2
Kusen Hiasan Teras 1.200 M2 #REF! Bh #REF! M2
#REF! M2

Halaman 4
1 2 3 4

6 Kunci Tanam dan pasang Pintu Utama 4.00 Bh


7 Kunci Tanam dan pasang KM/WC 2.00 Bh
8 Engsel pintu dan pasang 20.00 Bh
9 Engsel jendela dan pasang 84.00 Bh
10 Hak angin 84.00 Bh
11 Gredel Pintu/Door closer 4.00 Bh
12 Grendel jendela 42.00 Bh
13 Hendle pintu exsotis/door holder 3.00 Bh
14 Hendle Jendela 42.00 Bh

VIII Pekerjaan Plafond


1 Rangka Plafond givsum 60 x 120 cm
kayu lanan 5/7 cm Dalam #REF! M2
Teras 62.90 M2
#REF! M2
### #NAME?
#NAME? 62.79 M2
2 Plafond givsum #REF! M2
### #NAME? 62.79 M2
3 List givsum
Bagian dalam 163.20 M'
Teras 139.10 M'
302.30 M'
IX Pekerjaan Lantai dan Keramik
1 Lantai cor beton tumbuk
Panggung #REF! M2 0.050 M' #REF! M3
Tangga Panggung #REF! M2 0.050 M' #REF! M3
KM/WC #REF! M2 0.050 M' #REF! M3
Lantai bangunan 150.000 M2 0.050 M' 7.50 M3
Teras 45.310 M2 0.050 M' 2.27 M3
#REF! M3
2 Lantai keramik 30/30 cm
Lantai #REF! M2
Dinding Tangga 47.200 M' 0.200 M' 9.44 M2
#REF! M2
3 Lantai keramik 20/20 cm Km/Wc & air udhu #REF! M2

X Pekerjaan Listrik
2 Pasangan Titik Lampu dan Instalasinya 40.00 Titik
3 Stop Kontak dan Instalasi 6.00 Titik
4 Schaler tunggal 3.00 Titik
5 Schaler Ganda 8.00 Titik
6 Pasang Lampu SL panjang 18 watt 26.00 Bh
7 Lampu TL 40 wat bambu + rangka 12.00 Bh
8 Lampu Pijar 2.00 Bh
9 Box central/MCB 2 group (untuk jalur lampu
dan stop kontak) 1.00 Bh
### #NAME? 3.00 Titik

Halaman 5
1 2 3 4

XI Pekerjaan Sanitair
1 Kloset jongkok 2.00 Bh
2 Bak Mandi 70 x 70 fiber 2.00 Bh
3 Kran air 2.00 Bh
4 Pipa PVC 3/4 tebal 48.00 M'
5 Pipa PVC 2 " tebal 20.00 M'
6 Pipa PVC 3 " tebal 20.00 M'
7 Saringan/floor drain 2.00 Bh
8 Aseseoris pipa (Elbou, sambugan T, Lem,dll) 3.00 Bh
9 Septitank Kapasitas 3 m3 konstruksi beton 2.00 Bh

XII Pekerjaan Finishing


1 Mengecat kilap kusen,listplank & daun pintu
rangka daun jendela
Kusen
Pintu utama 0.240 M' 6.900 M' 3.000 Bh 4.97 M2
Pintu 0.240 M' 5.200 M' 2.000 Bh 2.50 M2
Jendela 0.240 M' 5.500 M' 18.000 Bh 23.76 M2
Ventilasi 0.240 M' 10.460 M' 0.000 Bh 0.00 M2
Ventilasi WC 0.240 M' 4.500 M' 2.000 Bh 2.16 M2
Rangka Jendela kaca kayu lanan 4.680 M' 2.000 ss 9.36 M2
Listplank 105.200 M' 0.300 M' 31.56 M2
74.30 M2
2 Mengecat matex plafond dan dinding #REF! M2 #REF! M2 #REF! M2
### #NAME? 62.79 M2
4 Ter rangka kap atap 66.56 M2
5 Pembersihan akhir 1.00 Unit
RENCANA ANGGARAN BIAYA
(RAB)

PROGRAM :
PEKERJAAN :
LOKASI :
Halaman 1
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME ANALISA SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6

I Pekerjaan Pendahuluan
1 Pembuatan papan nama kegiatan 1.00 Bh Ls 300,000.00 300,000.00
2 Persiapan dan Pembersihan lokasi 1.00 Ls Ls 750,000.00 750,000.00
3 Pengukuran dan pasang bouwplank 57.10 M' 01.6.4 49,356.75 2,818,270.43
Jumlah 3,868,270.43

II Pekerjaan Tanah
1 Galian tanah pondasi 45.90 M3 02.6.1 29,442.00 1,351,387.80
2 Timbunan kembali 25.37 M3 02.6.9 14,115.15 358,101.36
3 Tanah urug dibawah lantai 60.00 M3 02.6.11 104,680.50 6,280,830.00
Jumlah 7,990,319.16

III Pekerjaan Pondasi


1 Pondasi Batu Belah camp. 1 Pc : 4 Ps 13.23 M3 03.6.5 1,118,745.75 14,801,006.27
2 Pondasi Rollag Bata tangga 12.95 M3 04.6.11 115,924.25 1,501,219.04
3 Pondasi Footplat beton bertulang besi 70 Kg 7.30 M3 07.6.38.a 3,087,724.78 22,540,390.93
Jumlah 38,842,616.24

IV. Pekerjaan Beton


1 Sloof 15/20 cm beton bertulang 1.89 M3 07.6.39.a 4,039,753.91 7,635,134.89
2 Sloof 20/30 cm beton bertulang 2.49 M3 07.6.39.b 3,094,839.72 7,706,150.91
3 Kolom 15/15 cm beton bertulang 0.35 M3 07.6.40.a 5,522,887.57 1,913,680.54
4 Kolom 15/25 cm beton bertulang 2.02 M3 07.6.40.d 4,724,368.54 9,549,129.91
5 Kolom 30/30 cm beton bertulang 4.10 M3 07.6.40.b 4,657,825.29 19,115,714.98
6 Kolom 30/50 cm beton bertulang 4.32 M3 07.6.40.c 4,192,022.52 18,109,537.28
7 Balok 15/25 cm Beton bertulang \ 2.94 M3 07.6.41.a 4,290,696.94 12,614,649.00
8 Balok 20/30 cm Beton bertulang 1.46 M3 07.6.41.c 4,224,153.69 6,146,143.61
9 Balok 30/50 cm beton bertulang 6.44 M3 07.6.41.b 3,758,350.92 24,184,988.17
10 Dinding beton dibawah kubah tebal 0.74 M3 07.6.41.a 4,290,696.94 3,185,842.48
11 Dak atap cor beton bertulang tebal 10 cm 11.39 M3 7.6.43.a 4,778,622.90 54,404,621.72
Jumlah 164,565,593.50

V Pekerjaan Dinding dan pasangan


1 Pasangan dinding bata camp. 1 : 4 231.52 M2 04.6.11 115,924.25 26,838,782.36
2 Plesteran dinding camp. 1 pc : 4 ps 450.16 M2 05.6.4 39,418.50 17,744,631.96
3 Pasangan hiasan Bata terawang 26.60 M2 04.6.25 311,776.50 8,293,254.90
4 Plesteran Bentuk Kotak-kotak dan hiasan dinding 1.00 Ls Ls 1,000,000.00 1,000,000.00
5 Pembuatan Motif Pasir dinding luar bag. bawah 1.00 Ls Ls 2,500,000.00 2,500,000.00
Jumlah 56,376,669.22
Halaman 2
1 2 3 4 5 6

VI Pekerjaan Rangka Kap dan Atap


1 Gording Murplat, Nuk kayu lanan 6/12 cm
jurai 6/12 cm dan Ikatan Angin 6/12 cm 0.56 M3 SNI 02. 6.6.15 4,096,690.00 2,283,003.40
2 Kasau 5/7 cm & reng 3/5 cm kayu lanan 66.56 M2 06.6.31 52,502.25 3,494,549.76
3 Atap Metal prima color 0.3 mm 66.56 M2 08.6.32 70,282.05 4,677,973.25
5 Bubungan metal color type U 10.40 M' 08.6.36 65,621.15 682,459.96
6 Kubah bahan plat tembaga diameter 3 m 1.00 Bh Ls 15,000,000.00 15,000,000.00
Jumlah 26,137,986.37

VII Pekerjaan Kusen/Daun Pintu, Jendela


dan asesiorisnya
1 Kusen pintu dan jendela kayu klas I (Benuas) 0.72 M3 06.6.1 5,377,765.00 3,874,679.68
2 Pintu Panel kayu Klas I Benuas Km/Wc 14.07 M2 06.6.7 403,152.50 5,672,355.68
4 Rangka Jendela kaca kayu lanan 4.68 M2 06.6.10 331,334.50 1,550,645.46
5 Kaca raybean mati dan hidup 5 mm 10.80 M2 12.6.17 143,884.90 1,553,956.92
6 Kunci Tanam dan pasang Pintu Utama 3.00 Psg 12.6.2 217,198.25 651,594.75
7 Kunci Tanam dan pasang KM/WC 2.00 Psg 12.6.3 171,727.63 343,455.25
8 Engsel pintu dan pasang 16.00 bh 12.6.5 43,924.85 702,797.60
9 Engsel jendela dan pasang 36.00 bh 12.6.6 27,353.25 984,717.00
10 Hak angin 36.00 bh 12.6.9 22,859.90 822,956.40
11 Gredel Pintu/Door closer 3.00 bh 12.6.10 89,852.63 269,557.88
12 Grendel jendela 18.00 bh 12.6.9.b 22,884.90 411,928.20
13 Hendle pintu exsotis/door holder 3.00 bh 12.6.12 75,477.63 226,432.88
14 Hendle Jendela 18.00 bh 12.6.9.a 24,634.90 443,428.20
Jumlah 17,508,505.89

VIII Pekerjaan Plafond


1 Rangka Plafond givsum 60 x 120 cm
kayu lanan 5/7 cm 64.00 M2 06.6.40 72,533.75 4,642,160.00
2 Plafond givsum 64.00 M2 09.6.10 24,325.43 1,556,827.20
3 List givsum 122.50 M' Ls 15,000.00 1,837,500.00
Jumlah 8,036,487.20

IX Pekerjaan Lantai dan Keramik


1 Lantai cor beton tumbuk 11.25 M3 07.6.2 1,328,004.00 14,940,045.00
2 Lantai keramik 30/30 cm 133.20 M2 13.6.47 160,328.25 21,355,722.90
3 Lantai keramik 20/20 cm Km/Wc & air udhu 16.80 M2 13.6.44 157,978.25 2,654,034.60
4 Dinding keramik 20/20 cm KM/WC & ruang udhu 41.25 M2 13.6.68 157,576.25 6,500,020.31
5 Dinding plin 10/20 cm KM/WC & ruang udhu 27.50 M' 13.6.37 26,326.45 723,977.38
Jumlah 46,173,800.19
Halaman 3
1 2 3 4 5 6

X Pekerjaan Listrik
1 Pasang Saluran Listrik 1.00 Ls Ls 500,000.00 500,000.00
2 Pasangan Titik Lampu dan Instalasinya 19.00 Ttk Ls 195,375.00 3,712,125.00
3 Stop Kontak dan Instalasi 2.00 Ttk Ls 195,375.00 390,750.00
4 Schaler tunggal 1.00 Bh Ls 25,000.00 25,000.00
5 Schaler Ganda 4.00 Bh Ls 35,400.00 141,600.00
6 Pasang Lampu SL panjang 18 watt 5.00 Bh Ls 70,500.00 352,500.00
7 Lampu TL 40 wat bambu + rangka 12.00 Bh Ls 195,000.00 2,340,000.00
8 Lampu Pijar 2.00 Bh Ls 25,000.00 50,000.00
9 Box central/MCB 2 group (untuk jalur lampu
dan stop kontak) 1.00 Bh Ls 86,250.00 86,250.00
Jumlah 7,598,225.00

XI Pekerjaan Sanitair
1 Kloset jongkok 2.00 Bh Ls 255,000.00 510,000.00
2 Bak Mandi 70 x 70 fiber 2.00 Bh Ls 372,083.33 744,166.67
3 Kran air 2.00 Bh Ls 31,250.00 62,500.00
4 Pipa PVC 3/4 tebal 48.00 M" Ls 6,462.50 310,200.00
5 Pipa PVC 2 " tebal 12.00 M" Ls 19,093.75 229,125.00
6 Pipa PVC 3 " tebal 12.00 M" Ls 38,187.50 458,250.00
7 Saringan/floor drain 2.00 Bh Ls 15,603.25 31,206.50
8 Aseseoris pipa (Elbou, sambugan T, Lem,dll) 3.00 Set Ls 50,000.00 150,000.00
9 Septitank Kapasitas 3 m3 konstruksi beton 1.00 Bh Ls 3,476,800.00 3,476,800.00
Jumlah 5,972,248.17

XII Pekerjaan Finishing


1 Mengecat kilap kusen,listplank & daun pintu
rangka daun jendela 74.30 M2 14.6.8 20,573.78 1,528,713.78
2 Mengecat matex plafond dan dinding 514.16 M2 14.6.14 13,333.89 6,855,750.31
4 Ter rangka kap atap 66.56 M2 14.6.12 16,479.05 1,096,845.57
5 Pembersihan akhir 1.00 Ls Ls 309,752.03 309,752.03
Jumlah 9,791,061.68

REKAPITULASI:
I Pekerjaan Pendahuluan . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 3,868,270.43
II Pekerjaan Tanah . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 7,990,319.16
III Pekerjaan Pondasi . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .... . . . Rp. 38,842,616.24
IV Pekerjaan Beton . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 164,565,593.50
V Pekerjaan Dinding dan pasangan . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 56,376,669.22
VI Pekerjaan Rangka Kap dan Atap . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 26,137,986.37
VII Pekerjaan Kusen/Daun Pintu, Jendela . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 17,508,505.89
VIII Pekerjaan Plafond . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 8,036,487.20
IX Pekerjaan Lantai dan Keramik . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 46,173,800.19
X Pekerjaan Listrik . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 7,598,225.00
XI Pekerjaan Sanitair . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 5,972,248.17
XII Pekerjaan Finishing . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . Rp. 9,791,061.68
Jumlah = . . . . . . . . . Rp. 392,861,783.03

Halaman 4

Jumlah Konstruksi Rp. 392,861,783.03


Perencanaan Rp. 30,104,566.09
Pengawasan Rp. 20,876,827.35
Biaya Pengelola Teknis Rp. 6,156,823.53
Kuasa Pengguna Anggaran Rp 4,001,935.29
Pengelola Teknis PU Rp 2,154,888.24

Total Biaya keseluruhan : 450,000,000.00

/// Terbilang : Empat ratus lima puluh juta rupiah ///

Pangkalanbun, Nopember 2012

Dibuat Oleh :
Konsultan Perencana :
CV. Xx

xx
Direktur
ANALISA BIAYA PEKERJAAN
PROGRAM :
PEKERJAAN :
LOKASI :

Halaman 1
ANALISA
URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAH JUMLAH
(SNI 2007)
1 2 3 4 5 6

01.6.4 1 M' Pengukuran dan pasang bouwplank


0.0120 M³ Kasau 5/7 cm Rp 1,762,500.00 Rp 21,150.00
0.0070 M³ Kayu papan 3/20 cm kelas III Rp 1,762,500.00 Rp 12,337.50
0.0200 Kg Paku kayu Rp 14,100.00 Rp 282.00
0.1000 Pekerja Rp 65,100.00 Rp 6,510.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala Tukang Rp 84,700.00 Rp 847.00
0.0050 Mandor Rp 85,050.00 Rp 425.25
Rp 15,587.25 Rp 33,769.50 Rp 49,356.75

01.6.8 1 M² Membersihkan lapangan dan perataan.


0.1000 Pekerja Rp 65,100.00 Rp 6,510.00
0.0500 Mandor Rp 85,050.00 Rp 4,252.50
Rp 10,762.50 Rp - Rp 10,762.50

02.6.1 1 M³ Galian tanah biasa sedalam 1 meter.


0.4000 Pekerja Rp 65,100.00 Rp 26,040.00
0.0400 Mandor Rp 85,050.00 Rp 3,402.00
Rp 29,442.00 Rp - Rp 29,442.00

02.6.9 1 M³ Urugan kembali


0.1920 Pekerja Rp 65,100.00 Rp 12,499.20
0.0190 Mandor Rp 85,050.00 Rp 1,615.95
Rp 14,115.15 Rp - Rp 14,115.15

02.6.11 1 M³ Urugan Tanah


1.2000 M³ Pasir urug Rp 70,250.00 Rp 84,300.00
0.3000 Pekerja Rp 65,100.00 Rp 19,530.00
0.0100 Mandor Rp 85,050.00 Rp 850.50
Rp 20,380.50 Rp 84,300.00 Rp 104,680.50

03.6.14 1 M³ Pasang pondasi batu kosong


1.2000 M³ Batu belah 10/15 cm Rp 533,625.00 Rp 640,350.00
0.3000 M³ Pasir urug Rp 170,250.00 Rp 51,075.00
0.7800 Pekerja Rp 65,100.00 Rp 50,778.00
0.3900 Tukang batu Rp 78,050.00 Rp 30,439.50
0.0390 Kepala tukang Rp 84,700.00 Rp 3,303.30
0.0390 Mandor Rp 85,050.00 Rp 3,316.95
Rp 87,837.75 Rp 691,425.00 Rp 779,262.75

03.6.5 1 M³ Pasang pondasi batu kali, camp. 1Pc : 4Ps


1.1000 M³ Batu belah 10/15 cm Rp 533,625.00 Rp 586,987.50
163.0000 Kg Semen PC Rp 1,762.50 Rp 287,287.50
0.5200 M³ Pasir pasang Rp 170,250.00 Rp 88,530.00
1.5000 Pekerja Rp 65,100.00 Rp 97,650.00
0.6000 Tukang batu Rp 78,050.00 Rp 46,830.00
0.0600 Kepala tukang Rp 84,700.00 Rp 5,082.00
0.0750 Mandor Rp 85,050.00 Rp 6,378.75
Rp 155,940.75 Rp 962,805.00 Rp 1,118,745.75

04.6.9 1 M² Pasang bata merah tebal ½ bata, camp.1Pc : 2Ps.


70.0000 Bh Batu bata Rp 822.50 Rp 57,575.00
18.9500 Kg Semen PC Rp 1,762.50 Rp 33,399.38
0.0380 M³ Pasir pasang Rp 170,250.00 Rp 6,469.50
0.3200 Pekerja Rp 65,100.00 Rp 20,832.00
0.1000 Tukang batu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0150 Mandor Rp 85,050.00 Rp 1,275.75
Rp 30,759.75 Rp 97,443.88 Rp 128,203.63
Halaman 2
1 2 3 4 5 6

04.6.11 1 M² Pasang bata merah tebal ½ bata, camp. 1Pc : 4Ps.


70.0000 Bh Batu bata Rp 822.50 Rp 57,575.00
11.5000 Kg Semen PC Rp 1,762.50 Rp 20,268.75
0.0430 M³ Pasir pasang Rp 170,250.00 Rp 7,320.75
0.3200 Pekerja Rp 65,100.00 Rp 20,832.00
0.1000 Tukang batu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0150 Mandor Rp 85,050.00 Rp 1,275.75
Rp 30,759.75 Rp 85,164.50 Rp 115,924.25

04.6.23 1 M² Pasangan dinding conblock / bataco uk. 10 x 20 x 40 cm


12.5000 Bh Concrete block / bataco Rp 2,115.00 Rp 26,437.50
7.2000 Kg Semen PC Rp 1,762.50 Rp 12,690.00
0.0230 M³ Pasir pasang Rp 170,250.00 Rp 3,915.75
0.3400 Pekerja Rp 65,100.00 Rp 22,134.00
0.1070 Tukang batu Rp 78,050.00 Rp 8,351.35
0.0070 Tukang besi Rp 78,050.00 Rp 546.35
0.0114 Kepala tukang Rp 84,700.00 Rp 965.58
0.0170 Mandor Rp 85,050.00 Rp 1,445.85
Rp 33,443.13 Rp 43,043.25 Rp 76,486.38

04.6.25 1 M² Pasangan dinding roster / kerawang (12 x 11 x 24) cm


36.0000 Bh Roster / kerawang Rp 7,050.00 Rp 253,800.00
12.8000 Kg Semen PC Rp 1,762.50 Rp 22,560.00
0.0350 M³ Pasir pasang Rp 170,250.00 Rp 5,958.75
0.3000 Pekerja Rp 65,100.00 Rp 19,530.00
0.1000 Tukang batu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0150 Mandor Rp 85,050.00 Rp 1,275.75
Rp 29,457.75 Rp 282,318.75 Rp 311,776.50

05.6.2 1 M² Plesteran 1 Pc : 2 Ps, tebal 15 mm


8.5200 Kg Semen PC Rp 1,762.50 Rp 15,016.50
0.0170 M³ Pasir pasang Rp 170,250.00 Rp 2,894.25
0.2000 Pekerja Rp 65,100.00 Rp 13,020.00
0.1500 Tukang batu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0100 Mandor Rp 85,050.00 Rp 850.50
Rp 26,848.50 Rp 17,910.75 Rp 44,759.25

05.6.4 1 M² Plesteran 1 Pc : 4 Ps, tebal 15 mm


5.2000 Kg Semen PC Rp 1,762.50 Rp 9,165.00
0.0200 M³ Pasir pasang Rp 170,250.00 Rp 3,405.00
0.2000 Pekerja Rp 65,100.00 Rp 13,020.00
0.1500 Tukang batu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0100 Mandor Rp 85,050.00 Rp 850.50
Rp 26,848.50 Rp 12,570.00 Rp 39,418.50

06.6.1 1 M³ Pasang kosen pintu dan jendela kayu klas I (Benuas)


1.1000 M³ Balok kayu Benuas Rp 2,937,500.00 Rp 3,231,250.00
6.0000 Pekerja Rp 65,100.00 Rp 390,600.00
20.0000 Tukang kayu Rp 78,050.00 Rp 1,561,000.00
2.0000 Kepala tukang Rp 84,700.00 Rp 169,400.00
0.3000 Mandor Rp 85,050.00 Rp 25,515.00
Rp 2,146,515.00 Rp 3,231,250.00 Rp 5,377,765.00

06.6.7 1 M² Pasang pintu panel kayu klas I Benuas


0.0400 M³ Papan kayu Benuas Rp 2,937,500.00 Rp 117,500.00
1.0000 Pekerja Rp 65,100.00 Rp 65,100.00
2.5000 Tukang kayu Rp 78,050.00 Rp 195,125.00
0.2500 Kepala tukang Rp 84,700.00 Rp 21,175.00
0.0500 Mandor Rp 85,050.00 Rp 4,252.50
Rp 285,652.50 Rp 117,500.00 Rp 403,152.50
Halaman 3
1 2 3 4 5 6

06.6.10 1 M² Pasang pintu dan jendela kaca kayu lanan


0.0350 M³ Papan kayu lanan Rp 2,937,500.00 Rp 102,812.50
0.8000 Pekerja Rp 65,100.00 Rp 52,080.00
2.0000 Tukang kayu Rp 78,050.00 Rp 156,100.00
0.2000 Kepala tukang Rp 84,700.00 Rp 16,940.00
0.0400 Mandor Rp 85,050.00 Rp 3,402.00
Rp 228,522.00 Rp 102,812.50 Rp 331,334.50

SNI 02. 6.6.15 Memasang 1 M3 gordeng kayu kelas II


0.1200 Mandor Rp 85,050.00 Rp 10,206.00
0.7200 Kepala tukang Rp 84,700.00 Rp 60,984.00
7.2000 Tukang kayu Rp 78,050.00 Rp 561,960.00
2.4000 Pekerja Rp 65,100.00 Rp 156,240.00
1.1000 M3 balok kayu kls II Rp 2,900,000.00 Rp 3,190,000.00
3.0000 Kg paku kayu 12 Rp 14,100.00 Rp 42,300.00
3.0000 Kg besi strip tebal 5 mm Rp 25,000.00 Rp 75,000.00
Rp 789,390.00 Rp 3,307,300.00 Rp 4,096,690.00

06.6.28 1 M³ Pasang konstruksi kuda-kuda kayu lanan


1.1000 M³ Balok kayu lanan Rp 2,900,000.00 Rp 3,190,000.00
15.0000 Kg Besi strip Rp 22,200.00 Rp 333,000.00
0.8000 Kg Paku kayu Rp 14,100.00 Rp 11,280.00
4.0000 Pekerja Rp 65,100.00 Rp 260,400.00
12.0000 Tukang kayu Rp 78,050.00 Rp 936,600.00
1.2000 Kepala tukang Rp 84,700.00 Rp 101,640.00
0.2000 Mandor Rp 85,050.00 Rp 17,010.00
Rp 1,315,650.00 Rp 3,534,280.00 Rp 4,849,930.00

06.6.31 1 M² Pasang kasau + reng genteng metal kayu lanan


0.0120 M³ Balok kayu lanan Rp 2,900,000.00 Rp 34,800.00
0.1500 Kg Paku kayu Rp 14,100.00 Rp 2,115.00
0.1000 Pekerja Rp 65,100.00 Rp 6,510.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0050 Mandor Rp 85,050.00 Rp 425.25
Rp 15,587.25 Rp 36,915.00 Rp 52,502.25

06.6.39 1 M² Pasang rangka langit-langit (1,00 x 1,00) m kayu lanan


0.0120 M³ Balok kayu lanan Rp 2,900,000.00 Rp 34,800.00
0.1000 Kg Paku kayu Rp 14,100.00 Rp 1,410.00
0.1500 Pekerja Rp 65,100.00 Rp 9,765.00
0.2500 Tukang kayu Rp 78,050.00 Rp 19,512.50
0.0250 Kepala tukang Rp 84,700.00 Rp 2,117.50
0.0750 Mandor Rp 85,050.00 Rp 6,378.75
Rp 37,773.75 Rp 36,210.00 Rp 73,983.75

06.6.40 1 M² Pasang rangka langit-langit (60 x 120) cm kayu lanan


0.0115 M³ Balok kayu lanan Rp 2,900,000.00 Rp 33,350.00
0.1000 Kg Paku kayu Rp 14,100.00 Rp 1,410.00
0.1500 Pekerja Rp 65,100.00 Rp 9,765.00
0.2500 Tukang kayu Rp 78,050.00 Rp 19,512.50
0.0250 Kepala tukang Rp 84,700.00 Rp 2,117.50
0.0750 Mandor Rp 85,050.00 Rp 6,378.75
Rp 37,773.75 Rp 34,760.00 Rp 72,533.75

06.6.52 1 M' Pasang lisplang ukuran 2 x (2 x 20) cm, kayu Benuas


0.0086 M³ Papan kayu benuas Rp 2,937,500.00 Rp 25,262.50
0.0600 Kg Paku ulin Rp 17,625.00 Rp 1,057.50
0.1000 Pekerja Rp 65,100.00 Rp 6,510.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0500 Mandor Rp 85,050.00 Rp 4,252.50
Rp 19,414.50 Rp 26,320.00 Rp 45,734.50
Halaman 4
1 2 3 4 5 6

06.6.60 1 M' Pasang list plafond kayu profil


1.0500 M' Kayu profil Rp 2,937.50 Rp 3,084.38
0.0100 Kg Paku biasa Rp 14,100.00 Rp 141.00
0.0210 Pekerja Rp 65,100.00 Rp 1,367.10
0.0210 Tukang kayu Rp 78,050.00 Rp 1,639.05
0.0020 Kepala tukang Rp 84,700.00 Rp 169.40
0.0010 Mandor Rp 85,050.00 Rp 85.05
Rp 3,260.60 Rp 3,225.38 Rp 6,485.98

07.6.2 1 M³ Membuat beton tumbuk, camp. 1Pc : 3Ps : 6Kr.


197.0000 Kg Semen PC Rp 1,762.50 Rp 347,212.50
0.4700 M³ Pasir beton Rp 170,250.00 Rp 80,017.50
0.9400 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 764,925.00
1.6500 Pekerja Rp 65,100.00 Rp 107,415.00
0.2500 Tukang batu Rp 78,050.00 Rp 19,512.50
0.0250 Kepala tukang Rp 84,700.00 Rp 2,117.50
0.0800 Mandor Rp 85,050.00 Rp 6,804.00
Rp 135,849.00 Rp 1,192,155.00 Rp 1,328,004.00

07.6.38.a 1 M³ Membuat pondasi beton bertulang


70 kg besi + bekisting
0.2000 M³ Papan kayu klas III Rp 1,762,500.00 Rp 352,500.00
1.5000 Kg Paku kayu Rp 14,100.00 Rp 21,150.00
0.4000 Lt Minyak bekisting Rp 27,025.00 Rp 10,810.00
70.0000 Kg Besi beton polos Rp 12,991.40 Rp 909,398.03
1.0500 Kg Kawat beton Rp 21,150.00 Rp 22,207.50
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
3.9000 Pekerja Rp 65,100.00 Rp 253,890.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
1.0400 Tukang kayu Rp 78,050.00 Rp 81,172.00
1.0500 Tukang besi Rp 78,050.00 Rp 81,952.50
0.2450 Kepala tukang Rp 84,700.00 Rp 20,751.50
0.1650 Mandor Rp 85,050.00 Rp 14,033.25
Rp 479,116.75 Rp 2,608,608.03 Rp 3,087,724.78

07.6.39.a 1 M³ Membuat sloof beton bertulang


121 kg besi + bekisting
0.2700 M³ Papan kayu klas III Rp 1,762,500.00 Rp 475,875.00
2.0000 Kg Paku kayu Rp 14,100.00 Rp 28,200.00
0.6000 Lt Minyak bekisting Rp 27,025.00 Rp 16,215.00
121.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,571,959.46
1.8150 Kg Kawat beton Rp 21,150.00 Rp 38,387.25
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
4.8500 Pekerja Rp 65,100.00 Rp 315,735.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
1.5600 Tukang kayu Rp 78,050.00 Rp 121,758.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.3310 Kepala tukang Rp 84,700.00 Rp 28,035.70
0.1700 Mandor Rp 85,050.00 Rp 14,458.50
Rp 616,574.70 Rp 3,423,179.21 Rp 4,039,753.91
Halaman 5
1 2 3 4 5 6

07.6.39.b 1 M³ Membuat sloof beton bertulang


50 kg besi + bekisting
0.2700 M³ Papan kayu klas III Rp 1,762,500.00 Rp 475,875.00
2.0000 Kg Paku kayu Rp 14,100.00 Rp 28,200.00
0.6000 Lt Minyak bekisting Rp 27,025.00 Rp 16,215.00
50.0000 Kg Besi beton polos Rp 12,991.40 Rp 649,570.02
0.7500 Kg Kawat beton Rp 21,150.00 Rp 15,862.50
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
4.8500 Pekerja Rp 65,100.00 Rp 315,735.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
1.5600 Tukang kayu Rp 78,050.00 Rp 121,758.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.3310 Kepala tukang Rp 84,700.00 Rp 28,035.70
0.1700 Mandor Rp 85,050.00 Rp 14,458.50
Rp 616,574.70 Rp 2,478,265.02 Rp 3,094,839.72
07.6.39.c 1 M3 Membuat ringbalok beton bertulang
07.6.39.c 1 M3 Membuat ringbalok beton bertulang
121 kg besi + bekisting
0.2700 M³ Papan kayu klas III Rp 1,762,500.00 Rp 475,875.00
2.0000 Kg Paku kayu Rp 14,100.00 Rp 28,200.00
0.6000 Lt Minyak bekisting Rp 27,025.00 Rp 16,215.00
121.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,571,959.46
1.8150 Kg Kawat beton Rp 21,150.00 Rp 38,387.25
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
4.8500 Pekerja Rp 65,100.00 Rp 315,735.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
1.5600 Tukang kayu Rp 78,050.00 Rp 121,758.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.3310 Kepala tukang Rp 84,700.00 Rp 28,035.70
0.1700 Mandor Rp 85,050.00 Rp 14,458.50
Rp 616,574.70 Rp 3,423,179.21 Rp 4,039,753.91

07.6.39.d 1 M3 Membuat ringbalok beton bertulang


96 kg besi + bekisting
0.2700 M³ Papan kayu klas III Rp 1,762,500.00 Rp 475,875.00
2.0000 Kg Paku kayu Rp 14,100.00 Rp 28,200.00
0.6000 Lt Minyak bekisting Rp 27,025.00 Rp 16,215.00
96.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,247,174.45
1.4400 Kg Kawat beton Rp 21,150.00 Rp 30,456.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
4.8500 Pekerja Rp 65,100.00 Rp 315,735.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
1.5600 Tukang kayu Rp 78,050.00 Rp 121,758.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.3310 Kepala tukang Rp 84,700.00 Rp 28,035.70
0.1700 Mandor Rp 85,050.00 Rp 14,458.50
Rp 616,574.70 Rp 3,090,462.95 Rp 3,707,037.65
Halaman 6
1 2 3 4 5 6

07.6.40.a 1 M³ Membuat kolom beton bertulang


140 kg besi + bekisting
0.4000 M³ Papan kayu klas III Rp 1,762,500.00 Rp 705,000.00
4.0000 Kg Paku kayu Rp 14,100.00 Rp 56,400.00
2.0000 Lt Minyak bekisting Rp 27,025.00 Rp 54,050.00
140.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,818,796.07
2.1000 Kg Kawat beton Rp 21,150.00 Rp 44,415.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1500 M³ Balok kayu klas III Rp 1,762,500.00 Rp 264,375.00
20.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 293,750.00
7.3000 Pekerja Rp 65,100.00 Rp 475,230.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
3.3000 Tukang kayu Rp 78,050.00 Rp 257,565.00
2.1000 Tukang besi Rp 78,050.00 Rp 163,905.00
0.5700 Kepala tukang Rp 84,700.00 Rp 48,279.00
0.2500 Mandor Rp 85,050.00 Rp 21,262.50
Rp 993,559.00 Rp 4,529,328.57 Rp 5,522,887.57

07.6.40.b 1 M³ Membuat kolom beton bertulang


75 kg besi + bekisting
0.4000 M³ Papan kayu klas III Rp 1,762,500.00 Rp 705,000.00
4.0000 Kg Paku kayu Rp 14,100.00 Rp 56,400.00
2.0000 Lt Minyak bekisting Rp 27,025.00 Rp 54,050.00
75.0000 Kg Besi beton polos Rp 12,991.40 Rp 974,355.04
1.1250 Kg Kawat beton Rp 21,150.00 Rp 23,793.75
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1500 M³ Balok kayu klas III Rp 1,762,500.00 Rp 264,375.00
20.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 293,750.00
7.3000 Pekerja Rp 65,100.00 Rp 475,230.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
3.3000 Tukang kayu Rp 78,050.00 Rp 257,565.00
2.1000 Tukang besi Rp 78,050.00 Rp 163,905.00
0.5700 Kepala tukang Rp 84,700.00 Rp 48,279.00
0.2500 Mandor Rp 85,050.00 Rp 21,262.50
Rp 993,559.00 Rp 3,664,266.29 Rp 4,657,825.29

07.6.40.c 1 M³ Membuat kolom beton bertulang


40 kg besi + bekisting
0.4000 M³ Papan kayu klas III Rp 1,762,500.00 Rp 705,000.00
4.0000 Kg Paku kayu Rp 14,100.00 Rp 56,400.00
2.0000 Lt Minyak bekisting Rp 27,025.00 Rp 54,050.00
40.0000 Kg Besi beton polos Rp 12,991.40 Rp 519,656.02
0.6000 Kg Kawat beton Rp 21,150.00 Rp 12,690.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1500 M³ Balok kayu klas III Rp 1,762,500.00 Rp 264,375.00
20.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 293,750.00
7.3000 Pekerja Rp 65,100.00 Rp 475,230.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
3.3000 Tukang kayu Rp 78,050.00 Rp 257,565.00
2.1000 Tukang besi Rp 78,050.00 Rp 163,905.00
0.5700 Kepala tukang Rp 84,700.00 Rp 48,279.00
0.2500 Mandor Rp 85,050.00 Rp 21,262.50
Rp 993,559.00 Rp 3,198,463.52 Rp 4,192,022.52
Halaman 7
1 2 3 4 5 6

07.6.40.d 1 M³ Membuat kolom beton bertulang


80 kg besi + bekisting
0.4000 M³ Papan kayu klas III Rp 1,762,500.00 Rp 705,000.00
4.0000 Kg Paku kayu Rp 14,100.00 Rp 56,400.00
2.0000 Lt Minyak bekisting Rp 27,025.00 Rp 54,050.00
80.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,039,312.04
1.2000 Kg Kawat beton Rp 21,150.00 Rp 25,380.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1500 M³ Balok kayu klas III Rp 1,762,500.00 Rp 264,375.00
20.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 293,750.00
7.3000 Pekerja Rp 65,100.00 Rp 475,230.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
3.3000 Tukang kayu Rp 78,050.00 Rp 257,565.00
2.1000 Tukang besi Rp 78,050.00 Rp 163,905.00
0.5700 Kepala tukang Rp 84,700.00 Rp 48,279.00
0.2500 Mandor Rp 85,050.00 Rp 21,262.50
Rp 993,559.00 Rp 3,730,809.54 Rp 4,724,368.54

07.6.41.a 1 M³ Membuat balok beton bertulang


80 kg besi + bekisting
0.3200 M³ Papan kayu klas III Rp 1,762,500.00 Rp 564,000.00
3.2000 Kg Paku kayu Rp 14,100.00 Rp 45,120.00
1.6000 Lt Minyak bekisting Rp 27,025.00 Rp 43,240.00
80.0000 Kg Besi beton polos Rp 12,991.40 Rp 1,039,312.04
1.2000 Kg Kawat beton Rp 21,150.00 Rp 25,380.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1400 M³ Balok kayu klas III Rp 1,762,500.00 Rp 246,750.00
16.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 235,000.00
5.9600 Pekerja Rp 65,100.00 Rp 387,996.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
2.8000 Tukang kayu Rp 78,050.00 Rp 218,540.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.4550 Kepala tukang Rp 84,700.00 Rp 38,538.50
0.2080 Mandor Rp 85,050.00 Rp 17,690.40
Rp 799,352.40 Rp 3,491,344.54 Rp 4,290,696.94

07.6.41.b 1 M³ Membuat balok beton bertulang


40 kg besi + bekisting
0.3200 M³ Papan kayu klas III Rp 1,762,500.00 Rp 564,000.00
3.2000 Kg Paku kayu Rp 14,100.00 Rp 45,120.00
1.6000 Lt Minyak bekisting Rp 27,025.00 Rp 43,240.00
40.0000 Kg Besi beton polos Rp 12,991.40 Rp 519,656.02
0.6000 Kg Kawat beton Rp 21,150.00 Rp 12,690.00
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1400 M³ Balok kayu klas III Rp 1,762,500.00 Rp 246,750.00
16.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 235,000.00
5.9600 Pekerja Rp 65,100.00 Rp 387,996.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
2.8000 Tukang kayu Rp 78,050.00 Rp 218,540.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.4550 Kepala tukang Rp 84,700.00 Rp 38,538.50
0.2080 Mandor Rp 85,050.00 Rp 17,690.40
Rp 799,352.40 Rp 2,958,998.52 Rp 3,758,350.92
Halaman 8
1 2 3 4 5 6

07.6.41.c 1 M³ Membuat balok beton bertulang


75 kg besi + bekisting
0.3200 M³ Papan kayu klas III Rp 1,762,500.00 Rp 564,000.00
3.2000 Kg Paku kayu Rp 14,100.00 Rp 45,120.00
1.6000 Lt Minyak bekisting Rp 27,025.00 Rp 43,240.00
75.0000 Kg Besi beton polos Rp 12,991.40 Rp 974,355.04
1.1250 Kg Kawat beton Rp 21,150.00 Rp 23,793.75
323.0000 Kg Semen PC Rp 1,762.50 Rp 569,287.50
0.5200 M³ Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 M³ Bt pecah 1/2, 2/3 cm Rp 813,750.00 Rp 634,725.00
0.1400 M³ Balok kayu klas III Rp 1,762,500.00 Rp 246,750.00
16.0000 Bt Kayu bulat Ø 8 - 10 / 400 cm Rp 14,687.50 Rp 235,000.00
5.9600 Pekerja Rp 65,100.00 Rp 387,996.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
2.8000 Tukang kayu Rp 78,050.00 Rp 218,540.00
1.4000 Tukang besi Rp 78,050.00 Rp 109,270.00
0.4550 Kepala tukang Rp 84,700.00 Rp 38,538.50
0.2080 Mandor Rp 85,050.00 Rp 17,690.40
Rp 799,352.40 Rp 3,424,801.29 Rp 4,224,153.69

7.6.43.a 1 M3 Membuat lantai beton bertulang


75 kg besi + bekisting
0.1930 Mandor Rp 85,050.00 Rp 16,414.65
0.4000 Kepala tukang Rp 84,700.00 Rp 33,880.00
2.6400 Tukang kayu Rp 78,050.00 Rp 206,052.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
5.6000 Pekerja Rp 65,100.00 Rp 364,560.00
1.0500 Tukang besi Rp 78,050.00 Rp 81,952.50
0.2400 M3 kayu terentang Rp 1,762,500.00 Rp 423,000.00
3.2000 Kg paku Rp 14,100.00 Rp 45,120.00
1.6000 Lt minyak beskiting Rp 27,025.00 Rp 43,240.00
75.0000 Kg besi beton polos Rp 21,150.00 Rp 1,586,250.00
1.1250 Kg kawat beton Rp 21,150.00 Rp 23,793.75
323.0000 Kg semen portland Rp 1,762.50 Rp 569,287.50
0.5200 M3 Pasir beton Rp 170,250.00 Rp 88,530.00
0.7800 Koral Rp 813,750.00 Rp 634,725.00
0.1600 M3 Kayu borneo balok Rp 1,762,500.00 Rp 282,000.00
24.0000 Dolken dia - 8 cm/400 cm Rp 14,687.50 Rp 352,500.00
Rp 1,927,042.50 Rp 2,851,580.40 Rp 4,778,622.90

08.6.32 1 M² Pasang atap genteng metal


1.0200 M² Genteng metal colour Rp 45,000.00 Rp 45,900.00
0.0750 Kg Paku anti karat Rp 35,000.00 Rp 2,625.00
0.2000 Pekerja Rp 65,100.00 Rp 13,020.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0010 Mandor Rp 85,050.00 Rp 85.05
Rp 21,757.05 Rp 48,525.00 Rp 70,282.05

08.6.36 1 M' Pasang nok genteng metal


1.0000 M' Bubungan metal Rp 35,000.00 Rp 35,000.00
0.0075 Kg Paku anti karat Rp 35,000.00 Rp 262.50
0.2500 Pekerja Rp 65,100.00 Rp 16,275.00
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0130 Mandor Rp 85,050.00 Rp 1,105.65
Rp 30,358.65 Rp 35,262.50 Rp 65,621.15

09.6.10 1 M² Langit-langit plywood (60 x 120) cm, tebal 3 mm.


0.3750 Lb Plywood 4' x 8' x 4 mm Rp 25,850.00 Rp 9,693.75
0.0300 Kg Paku plywood Rp 37,500.00 Rp 1,125.00
0.0700 Pekerja Rp 65,100.00 Rp 4,557.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0035 Mandor Rp 85,050.00 Rp 297.68
Rp 13,506.68 Rp 10,818.75 Rp 24,325.43

Halaman 9
1 2 3 4 5 6

11.6.19 1 M' Pasang talang miring, seng BJLS 28


0.5000 Lbr Seng plat 3' x 6' BJLS 28 Rp 16,202.75 Rp 8,101.38
0.0150 Kg Paku anti karat Rp 35,000.00 Rp 525.00
0.0190 M³ Papan kayu lanan Rp 2,937,500.00 Rp 55,812.50
0.3000 Kg Flincote / menie besi Rp 15,000.00 Rp 4,500.00
0.0400 Pekerja Rp 65,100.00 Rp 2,604.00
0.4000 Tukang kayu Rp 78,050.00 Rp 31,220.00
0.0250 Kepala tukang Rp 84,700.00 Rp 2,117.50
0.0130 Mandor Rp 85,050.00 Rp 1,105.65
Rp 37,047.15 Rp 68,938.88 Rp 105,986.03

12.6.2 1 Buah pasang kunci tanam


1.0000 Bh Kunci tanam biasa Rp 176,250.00 Rp 176,250.00
0.0100 Pekerja Rp 65,100.00 Rp 651.00
0.5000 Tukang kayu Rp 78,050.00 Rp 39,025.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0050 Mandor Rp 85,050.00 Rp 425.25
Rp 40,948.25 Rp 176,250.00 Rp 217,198.25

12.6.3 1 Buah pasang kunci tanam kamar mandi


1.0000 Bh Kunci tanam kamar mandi Rp 125,000.00 Rp 125,000.00
0.0500 Pekerja Rp 65,100.00 Rp 3,255.00
0.5000 Tukang kayu Rp 78,050.00 Rp 39,025.00
0.0500 Kepala tukang Rp 84,700.00 Rp 4,235.00
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 46,727.63 Rp 125,000.00 Rp 171,727.63

12.6.5 1 Buah pasang engsel pintu


1.0000 Bh Engsel pintu Rp 29,375.00 Rp 29,375.00
0.0150 Pekerja Rp 65,100.00 Rp 976.50
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0070 Mandor Rp 85,050.00 Rp 595.35
Rp 14,549.85 Rp 29,375.00 Rp 43,924.85

12.6.6 1 Buah pasang engsel jendela kupu-kupu


1.0000 Bh Engsel jendela Rp 17,625.00 Rp 17,625.00
0.0100 Pekerja Rp 65,100.00 Rp 651.00
0.1000 Tukang kayu Rp 78,050.00 Rp 7,805.00
0.0100 Kepala tukang Rp 84,700.00 Rp 847.00
0.0050 Mandor Rp 85,050.00 Rp 425.25
Rp 9,728.25 Rp 17,625.00 Rp 27,353.25

12.6.9 1 Buah pasang kait angin


1.0000 Bh Kait angin Rp 8,225.00 Rp 8,225.00
0.0150 Pekerja Rp 65,100.00 Rp 976.50
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0080 Mandor Rp 85,050.00 Rp 680.40
Rp 14,634.90 Rp 8,225.00 Rp 22,859.90

12.6.9.a 1 Buah pasang Hendel jendela


1.0000 Bh Hendel Jendela Rp 10,000.00 Rp 10,000.00
0.0150 Pekerja Rp 65,100.00 Rp 976.50
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0080 Mandor Rp 85,050.00 Rp 680.40
Rp 14,634.90 Rp 10,000.00 Rp 24,634.90
12.6.9.b 1 Buah pasang Grendel Jendela
1.0000 Bh Grendel Jendela Rp 8,250.00 Rp 8,250.00
0.0150 Pekerja Rp 65,100.00 Rp 976.50
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0080 Mandor Rp 85,050.00 Rp 680.40
Rp 14,634.90 Rp 8,250.00 Rp 22,884.90

Halaman 10
1 2 3 4 5 6

12.6.10 1 Buah pasang door closer


1.0000 Bh Door closer Rp 43,125.00 Rp 43,125.00
0.0500 Pekerja Rp 65,100.00 Rp 3,255.00
0.5000 Tukang kayu Rp 78,050.00 Rp 39,025.00
0.0500 Kepala tukang Rp 84,700.00 Rp 4,235.00
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 46,727.63 Rp 43,125.00 Rp 89,852.63

12.6.12 1 Buah pasang pegangan pintu / door holder


1.0000 Bh Door holder Rp 28,750.00 Rp 28,750.00
0.0500 Pekerja Rp 65,100.00 Rp 3,255.00
0.5000 Tukang kayu Rp 78,050.00 Rp 39,025.00
0.0500 Kepala tukang Rp 84,700.00 Rp 4,235.00
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 46,727.63 Rp 28,750.00 Rp 75,477.63

12.6.17 1 M² pasang kaca, tebal 5 mm


1.1000 M² Kaca tebal 5 mm Rp 117,500.00 Rp 129,250.00
0.0150 Pekerja Rp 65,100.00 Rp 976.50
0.1500 Tukang kayu Rp 78,050.00 Rp 11,707.50
0.0150 Kepala tukang Rp 84,700.00 Rp 1,270.50
0.0080 Mandor Rp 85,050.00 Rp 680.40
Rp 14,634.90 Rp 129,250.00 Rp 143,884.90

13.6.37 1 M' pasang plint keramik 10 x 20 cm


0.0045 Mandor Rp 85,050.00 Rp 382.73
0.0090 Kepala tukang Rp 84,700.00 Rp 762.30
0.0900 Tukang batu Rp 78,050.00 Rp 7,024.50
0.0900 Pekerja Rp 65,100.00 Rp 5,859.00
5.0000 Bh plint keramik Rp 1,675.00 Rp 8,375.00
1.6500 Kg Semen portland Rp 1,762.50 Rp 2,908.13
0.0032 M3 Pasir pasang Rp 170,250.00 Rp 544.80
0.1000 Kg semen warna Rp 4,700.00 Rp 470.00
Rp 18,156.93 Rp 8,169.53 Rp 26,326.45

13.6.44 1 M² Pasang lantai keramik 20 x 20 cm


1.0000 M² Keramik 20 x 20 cm Rp 50,525.00 Rp 50,525.00
11.3800 Kg Semen PC Rp 1,762.50 Rp 20,057.25
0.0420 M³ Pasir pasang Rp 170,250.00 Rp 7,150.50
1.5000 Kg Semen warna Rp 4,700.00 Rp 7,050.00
0.6200 Pekerja Rp 65,100.00 Rp 40,362.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
0.0350 Kepala tukang Rp 84,700.00 Rp 2,964.50
0.0300 Mandor Rp 85,050.00 Rp 2,551.50
Rp 73,195.50 Rp 84,782.75 Rp 157,978.25

13.6.47 1 M² Pasang lantai keramik 30 x 30 cm


1.0000 M² Keramik 30 x 30 cm Rp 52,875.00 Rp 52,875.00
11.3800 Kg Semen PC Rp 1,762.50 Rp 20,057.25
0.0420 M³ Pasir pasang Rp 170,250.00 Rp 7,150.50
1.5000 Kg Semen warna Rp 4,700.00 Rp 7,050.00
0.6200 Pekerja Rp 65,100.00 Rp 40,362.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
0.0350 Kepala tukang Rp 84,700.00 Rp 2,964.50
0.0300 Mandor Rp 85,050.00 Rp 2,551.50
Rp 73,195.50 Rp 87,132.75 Rp 160,328.25

13.6.68 1 M² Pasang dinding keramik 20 x 20 cm


1.0000 M² Keramik 20 x 20 cm Rp 50,525.00 Rp 50,525.00
9.3000 Kg Semen PC Rp 1,762.50 Rp 16,391.25
0.0180 M³ Pasir pasang Rp 170,250.00 Rp 3,064.50
1.5000 Kg Semen warna Rp 4,700.00 Rp 7,050.00
0.6000 Pekerja Rp 65,100.00 Rp 39,060.00
0.4500 Tukang batu Rp 78,050.00 Rp 35,122.50
0.0450 Kepala tukang Rp 84,700.00 Rp 3,811.50
0.0300 Mandor Rp 85,050.00 Rp 2,551.50
Rp 80,545.50 Rp 77,030.75 Rp 157,576.25

Halaman 11
1 2 3 4 5 6

13.6.74 1 M² Pasang dinding batu tempel hitam


1.0500 M² Batu tempel hitam Rp 275,000.00 Rp 288,750.00
11.7500 Kg Semen PC Rp 1,762.50 Rp 20,709.38
0.0350 M³ Pasir pasang Rp 170,250.00 Rp 5,958.75
0.6200 Pekerja Rp 65,100.00 Rp 40,362.00
0.3500 Tukang batu Rp 78,050.00 Rp 27,317.50
0.0350 Kepala tukang Rp 84,700.00 Rp 2,964.50
0.0300 Mandor Rp 85,050.00 Rp 2,551.50
Rp 73,195.50 Rp 315,418.13 Rp 388,613.63

14.6.8 1 M² Pengecatan Kilap bidang kayu baru (1 lapis plamir,


1 lapis cat dasar, 2 lapis cat penutup)
0.1500 Kg Plamir Rp 11,750.00 Rp 1,762.50
0.2600 Kg Cat kilap penutup 2 kali Rp 49,350.00 Rp 12,831.00
0.0700 Pekerja Rp 65,100.00 Rp 4,557.00
0.0090 Tukang cat Rp 78,050.00 Rp 702.45
0.0060 Kepala tukang Rp 84,700.00 Rp 508.20
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 5,980.28 Rp 14,593.50 Rp 20,573.78

14.6.10 1 M² Pelaburan bidang kayu dengan teak oil


0.3600 Ltr Teak oil Rp 52,875.00 Rp 19,035.00
0.0400 Pekerja Rp 65,100.00 Rp 2,604.00
0.0630 Tukang cat Rp 78,050.00 Rp 4,917.15
0.0630 Kepala tukang Rp 84,700.00 Rp 5,336.10
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 13,069.88 Rp 19,035.00 Rp 32,104.88

14.6.12 1 M² Pelaburan bidang kayu dengan residu / ter


0.3500 Ltr Ter atau residu Rp 27,025.00 Rp 9,458.75
0.1000 Pekerja Rp 65,100.00 Rp 6,510.00
0.0060 Mandor Rp 85,050.00 Rp 510.30
Rp 7,020.30 Rp 9,458.75 Rp 16,479.05

14.6.14 1 M² Pengecatan bidang tembok baru (1 lapis plamir,


2 lapis cat penutup).
0.1000 Kg Plamir Rp 11,750.00 Rp 1,175.00
0.2600 Kg Cat penutup 2 x merk Vinylex Rp 19,975.00 Rp 5,193.50
0.0200 Pekerja Rp 65,100.00 Rp 1,302.00
0.0630 Tukang cat Rp 78,050.00 Rp 4,917.15
0.0063 Kepala tukang Rp 84,700.00 Rp 533.61
0.0025 Mandor Rp 85,050.00 Rp 212.63
Rp 6,965.39 Rp 6,368.50 Rp 13,333.89

D.12b 1 M² Plafond papan moulding tidak termasuk rangka


3.5000 Kp Papan moulding lanan Rp 26,250.00 91,875.00
0.0200 Kg Paku kayu Rp 14,100.00 282.00
0.0330 Pekerja Rp 65,100.00 2,148.30
0.5000 Tukang kayu Rp 78,050.00 39,025.00
0.0250 Kepala tukang Rp 84,700.00 2,117.50
0.0020 Mandor Rp 85,050.00 170.10
43,460.90 92,157.00 135,617.90
DAFTAR HARGA SATUAN UPAH DAN BAHAN

PROGRAM :
PEKERJAAN :
LOKASI :

UPAH
Halaman 1

NO. URAIAN TENAGA SATUAN KETERANGAN

1 Mandor Orang Rp 85,050.00


2 Kepala Tukang Orang Rp 84,700.00
3 Tukang Batu Orang Rp 78,050.00
4 Tukang Kayu Orang Rp 78,050.00
5 Tukang Besi Orang Rp 78,050.00
6 Tukang Cat Orang Rp 78,050.00
7 Tukang Gali Tanah Orang Rp 78,750.00
8 Pekerja Orang Rp 65,100.00

B. BAHAN BANGUNAN

1 2 3 4

1 Pasir urug M³ Rp 170,250.00


2 Pasir pasang M³ Rp 170,250.00
3 ###Pasir beton M³ Rp 170,250.00
4 ###Tanah urug biasa M³ Rp 70,250.00
5 ###Batu pecah 1/ 2 cm , 2/ 3 cm (koral beton M³ Rp 813,750.00
6 Batu belah M³ Rp 533,625.00
7 ###Semen PC ( isi 50 Kg ) Kg Rp 1,762.50
8 ###Semen warna Kg Rp 4,700.00
9 Batu Bata / Bata merah Bh Rp 822.50
10 Bataco Bh Rp 2,115.00
11 Keramik 20 x 20 cm M² Rp 50,525.00
12 Keramik 30 x 30 cm M² Rp 52,875.00
13 Keramik Plin 10/x 20 cm Bh Rp 1,675.00
14 Balok kayu ulin M³ Rp 4,700,000.00
15 Balok Kayu Benuas M³ Rp 2,937,500.00
16 Balok kayu lanan M³ Rp 2,900,000.00
17 Balok kayu kelas III (campuran) M³ Rp 1,762,500.00
18 Balok kayu kelas IV (campuran) M³ Rp 1,762,500.00
19 Papan kayu ulin M³ Rp 6,415,500.00
20 Papan Banuas M³ Rp 2,937,500.00
21 Papan kayu lanan M³ Rp 2,937,500.00
22 Papan kayu kelas III (campuran) M³ Rp 1,762,500.00
Halaman 2
1 2 3 4

21 Papan kayu klas IV (campuran) M³ Rp 1,762,500.00


21 Kayu dolken Ø 8 - 10 cm - 4 m Btg Rp 14,687.50
22 Kayu list profil panjang 4 m Btg Rp 11,750.00
23 Besi Beton Polos Ø 6 mm - 19 mm Kg Rp 12,991.40
24 Kawat Beton / bindrat Kg Rp 21,150.00
25 Paku Kayu Kg Rp 14,100.00
26 Paku Ulin Kg Rp 17,625.00
27 Besi strip Kg Rp 22,200.00
28 Paku Triplek Kg Rp 37,500.00
29 Paku anti karat Kg Rp 35,000.00
30 Genteng metal Prima colour tebal 0,3 mm Lbr Rp 45,000.00
31 Bubungan Genteng metal Type U M' Rp 35,000.00
32 Seng plat 3" x 6" BJLS 40 Lbr Rp 16,202.75
33 Papan Lap-lapan Lanan Kpg Rp 26,250.00
34 Plywood 3 mm Lbr Rp 25,850.00
35 Bak Mandi Fibreglass 70x70 Bh Rp 372,083.33
36 Closed jongkok porselen Bh Rp 255,000.00
38 Kran Leiding Bh Rp 31,250.00
39 Floor drain acsesories Bh Rp 5,875.00
40 Pipa PVC diameter ¾" AW (Maspion) Btg Rp 25,850.00
41 Pipa PVC diameter 2" AW (Maspion) Btg Rp 76,375.00
42 Pipa PVC diameter 3" AW (Maspion) Btg Rp 152,750.00
43 Cat Tembok Kg Rp 19,975.00
44 Cat Kayu Mengkilat merk Platon / sejenis Kg Rp 49,350.00
45 Cat Besi Mengkilat Kg Rp 49,350.00
46 Cat Menie Kg Rp 25,850.00
47 Plamur Tembok Kg Rp 11,750.00
48 Dempul Kayu Kg Rp 66,387.50
49 Residu / ter Ltr Rp 27,025.00
50 Politur jadi Ltr Rp 52,875.00
51 Flincote Kg Rp 15,000.00
53 Engsel jendela 4 ' kuningan Bh Rp 17,625.00
54 Engsel pintu 3' kuningan Bh Rp 29,375.00
55 Kunci tanam 2 slag ( merk YALE/setara) Bh Rp 176,250.00
56 Kunci tanam kamar mandi Bh Rp 125,000.00
57 Grendel Bh Rp 8,250.00
58 Hak angin kuningan merk FEDEL / setara Bh Rp 8,225.00
59 Door closer Pintu Bh Rp 43,125.00
60 Door holder Bh Rp 28,750.00
61 Kaca rayben ukuran 5 mm M² Rp 117,500.00
62 Stop kontak + Instalasi (bangunan beton) Ttk Rp 195,375.00
63 Titik lampu + Instalasi (bangunan beton) Ttk Rp 195,375.00
64 Sakelar tunggal (merk BROCO) Bh Rp 25,000.00
65 Sakelar ganda (merk BROCO) Bh Rp 35,400.00
66 MCB 2 group Bh Rp 86,250.00
67 Lampu pijar + fitting Bh Rp 12,100.00
68 Lampu SL 18 watt (Philips) Bh Rp 70,500.00
69 Lampu Down laight SL 18 Bh Rp 99,875.00
70 Batu tempet hitam/batu alam M2 Rp 275,000.00