Project : Pa.

Firman and Bu Pipih Puri Arraya 2


Address : Sadeng Leuwisadeng Bogor Jl. Raya Kapten Dasuki Bakri Desa Cobatok 1
Date : 2-Sep-22 Kecamatan Cibungbulang Kab, Bogor Jabar

HARGA
NO URAIAN PEKERJAAN VOL SATUAN JUMLAH KETERANGAN
SATUAN

A.PEKERJAAN PASANGAN
1 BATA HEBEL 10 CM 19 Kbk 550,000 10,450,000
2 SEMEN MORTAR 23 Zak 70,000 1,610,000
3 PASIR PASANG 15 M3 320,000 4,800,000
4 SEMEN 50 KG SCG 90 Zak 68,000 6,120,000
5 BATU SEPLIT 6 M3 300,000 1,800,000
6 PAKU CAMPUR 5.7.10 20 Kg 35,000 700,000
7 BESI 12 35 Btg 95,000 3,325,000
8 BESI 10 95 Btg 85,000 8,075,000
9 BESI 8 15 Btg 75,000 1,125,000
10 KAWAT BESI 7 Kg 30,000 210,000
11 KASO 4/6 40 Btg 15,000 600,000
12 BALOK 10 Btg 50,000 500,000
13 TERIPLEK 9 MM 10 Lmbr 135,000 1,350,000
14 LOSTER BATA/BETON 4.5 Mtr 500,000 2,250,000
15 BAMBU 40 Btg 18,000 720,000
16 BATA EXPOSE 4.5 Mtr 200,000 900,000
17 CONWOOD 17.5 Mtr 350,000 6,125,000
18 CAKAR AYAM 50X50 4 Pcs 125,000 500,000
19 Cincin Besi 6 mm 18 Ikat 250,000 4,500,000
Sub Total : 55,660,000
B.PEKERJAAN ALUMUNIUM
1 PINTU UTAMA 90x210 Cm 1 Bh 4,550,000 4,550,000 PANEL BAJA FORTES
2 PINTU KAMAR, LONDRY 88X214 3 Bh 1,800,000 5,400,000 BAJA ALESSA DOR
3 DAUN JENDELA DOBLE AWNING 4 Bh 2,250,000 9,000,000
4 DAUN JENDELA SINGLE 3 Bh 420,000 1,260,000
5 LOSTER 20 Bh 35,000 700,000
6 JENDELA KACA SLIDING FULL 1 Psg 11,500,000 11,500,000
7 PINTU KM/WC,ALUMUNIUM LENGKAP 1 Psg 120,000 120,000
Sub Total : 32,530,000
C.PEKERJAAN ATAP
1 CNP C75.100 62 Btg 120,000 7,440,000
2 Reng 30.40 45 Btg 42,000 1,890,000
3 Multi Roof 77×80 cm (T 0,25 mm) 40 Lbr 95,000 3,800,000
4 NOK KARPUS ATAS 80 CM 10 Lbr 34,000 340,000
6 LIST PLANK GRC, 3X30 CM 8 Lbr 41,000 328,000
7 GRC BOARD P 1.20 x 2.40 M 29 Lbr 68,500 1,986,500
8 HOLOW GALVANIS 0.50 124 Btg 42,000 5,208,000
9 LIST PLAFOND 152 Btg 13,000 1,976,000
Sub Total : 22,968,500
D.PEKERJAAN LANTAI
1 GRANIT LANTAI RUANG TAMU 60x60 54 Dus 225,000 12,150,000 rustic kayu torch
2 GRANIT LANTAI KAMAR MANDI 60x60 4 Dus 145,000 580,000 cemento grey
3 GRANIT DINDING KAMAR MANDI 30x60 21 Dus 95,000 1,995,000 hexsagon
4 GRANIT LIS KAMAR MANDI 10x60 37 Pcs 29,000 1,073,000 Hitam
5 GRANIT DINDING DAPUR 25x50 5 Dus 150,000 750,000 bricky whaite
6 GRANITMEJA DAPUR 60x60 4 Dus 225,000 900,000 white carera
7 GRANIT LIS DAPUR 10x60 6 Pcs 29,000 174,000 putih
8 GRANIT TERAS DEPAN 2 Dus 225,000 450,000 rustic kayu torch
Sub Total : 18,072,000
E. PEKERJAAN LAIN-LAIN
1 INSTALANSI PIPA 1 Pkt 1,550,000 1,550,000 Paket + Pipa
2 INSTALANSI LISTRIK 1 Pkt 3,500,000 3,500,000 Pakt + Kabel
3 UPAH TUKANG 180 Hok 180,000 32,400,000 dua orang tukang
4 UPAH PEKERJA 180 Hok 130,000 23,400,000 dua orang kenek
5 BIAYA TAK TERDUGA LAINNYA 1 Ls 300,000 300,000 benang, sepidol dll
Sub Total : 61,150,000
Jumlah Sub Total : 190,380,500