DAFTAR HARGA MATERIAL DAN UPAH
Program Pembangunan dan Pemberdayaan Masyarakat Desa ( P3MD )
HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN KETERANGAN
( Rp. )
A. UPAH KERJA
1 Tukang Kayu 150,000.00 HOK
2 Tukang Batu 150,000.00 HOK
3 Tukang Besi 150,000.00 HOK
4 Pekerja 100,000.00 HOK
5 Operator terlatih 100,000.00 HOK
6 Pembantu masinis/ sopir 100,000.00 HOK
7 Buruh terampil/terlatih 100,000.00 HOK
8 Masinis/sopir 150,000.00 HOK
9 Buruh tak terlatih 80,000.00 HOK
10 Kepala Tukang 150,000.00 HOK
11 Mandor 150,000.00 HOK
B. MATERIAL
1 Tanah Urug 170,000.00 m3
2 Pasir pasang 240,000.00 m3
3 Pasir Beton/Cor 250,000.00 m3
4 Pasir Urug/Sirtu 150,000.00 m3
5 Base Coarse 270,000.00 m3
6 Semen 68,000.00 zak
7 Batu Kali 252,000.00 m3
8 Batu pecah 5/7 266,500.00 m3
9 Batu pecah 3/5 290,000.00 m3
10 Batu pecah 2/3 270,000.00 m3
11 Batu pecah 0,5 /ciping 185,000.00 m3
12 Batu pecah mesin 1/2 282,500.00 m3
13 Batu split ( 2/3 ) 270,000.00 m3
14 Batu bata 650.00 bh
15 Besi F 8 45,000.00 btg
16 Besi F 10 65,000.00 btg
17 Besi F 12 89,000.00 btg
18 Kawat bendrat 20,000.00 kg
19 Kayu 5/7 Klas III @ 3m 18,000.00 btg
20 Papan Cor 30,000.00 lbr
21 Genteng 1,500.00 buah
22 Wuwung 4,500.00 buah
23 Buis Beton F 60 100,000.00 buah
24 Buis Beton F 30 50,000.00 buah
25 Pengeras Beton 35,000.00 lbr
26 Kayu 8/12 110,000.00 btg
27 Kayu 6/12 75,000.00 btg
28 Kaso 5/7 40,000.00 btg
29 Kaso 4/6 36,000.00 btg
30 Reng 3/4 19,000.00 btg
31 ready mix K 300 820,000.00 m3
HARGA SATUAN
NO JENIS TENAGA KERJA SATUAN KETERANGAN
( Rp. )
A BAHAN / MATERIAL
1 Semen 50 kg Zak 68,000 7,109 75,200
2 Pasir Pasang M3 240,000 3,273 243,300
3 Pasir Urug M3 150,000 2,045 152,100
4 Batu Kali/Batu Pecah M3 252,000 26,345 278,400
5 Kayu papan 3/20 lbr 30,000 3,136 33,200
6 Kayu Balok 5/7 Btg 40,000 4,182 44,200
7 Paku 2"-3" Kg 18,000 1,882 19,900
B PERALATAN
1 Gerobak Dorong/ Lory Bh 450,000 47,045 497,100
2 Cangkul Bh 45,000 4,705 49,800
3 Sekop Bh 45,000 4,705 49,800
4 Ember Bh 9,000 941 10,000
5 Pengki Bh 15,000 1,568 16,600
6 Benang Rol 2,000 209 2,300
7 Selang timbang m 2,000 209 2,300
8 Prasasti Bh 400,000 41,818 441,900
9 Papan Proyek Bh 300,000 31,364 331,400
10 Palu Bh 25,000 2,614 27,700
C UPAH
1 Pekerja HOK 100,000 100,000
2 Tukang HOK 150,000 150,000
3 Kepala Tukang HOK 150,000 150,000
4 Mandor HOK 150,000 150,000
DATA PERHITUNGAN - Panjang Jalan = 30 meter - Tebal Rabat Beton = 0.50 meter
- Lebar Badan Jalan = 0.40 meter
0.2 m
0.4 m
0.05 m
0.4 m
Upah :
Pekerja = 0.300 x 1.20 = 0.36 HOK
Mandor = 0.010 x 1.20 = 0.01 HOK
Upah :
Pekerja = 1.500 x 15.30 = 22.95 HOK
Tukang = 0.750 x 15.30 = 11.48 HOK
Ka. Tukang = 0.075 x 15.30 = 1.15 HOK
Mandor = 0.075 x 15.30 = 1.15 HOK
Upah :
Pekerja = 0.300 x 24.00 = 7.20 HOK
Tukang = 0.150 x 24.00 = 3.60 HOK
Ka. Tukang = 0.015 x 24.00 = 0.36 HOK
Mandor = 0.015 x 24.00 = 0.36 HOK
Harga Satuan (
No URAIAN Volume Satuan Jumlah ( Rp )
Rp )
1 2 3 4 5 6
I BAHAN
1 Semen @ 50 Kg 44 zak 75,200 3,308,800
2 Pasir Pasang 9 m3 243,300 2,189,700
3 Batu Belah 18 m3 278,400 5,011,200
4 Pasir Urug 1 m3 152,100 152,100
................ ................
KIRI KANAN
Kp Limo Rt 003/003
Muka Tanah asli Muka Tanah asli
0.2 m 0.2 m
GAMBAR RENCANA
0.05 m
0.05 m Urugan Pasir POT. MELINTANG
DIBUAT OLEH :
0.4 m 0.4 m
Pelaksana Kegiatan
................
Panjang = 30 m kiri
30 m kanan
DIKETAHUI OLEH :
Kepala Desa
................
PROP : Jawa Barat
KAB. : Bekasi
KEC. : Cibarusah
DESA : Cibarusah Jaya
JENIS PRASARANA :
LOKASI :
Kp Limo Rt 003/003
GAMBAR RENCANA
DETAIL PATOK DAN BEKISTING
DETAIL POTONGAN
DIBUAT OLEH :
Pelaksana Kegiatan
................
DIPERIKSA OLEH :
DISETUJUI OLEH :
Kepala Desa
................
PROP : Jawa Barat
KAB. : Bekasi
KEC. : Cibarusah
DESA : Cibarusah Jaya
JENIS PRASARANA :
0 m LOKASI :
Kp Limo Rt 003/003
GAMBAR RENCANA
POT. MEMANJANG
POT. MELINTANG
DIBUAT OLEH :
Pelaksana Kegiatan
................
DIPERIKSA OLEH :
DIKETAHUI OLEH :
Kepala Desa
................
Jawa Barat
Bekasi
Cibarusah
Cibarusah Jaya
ENIS PRASARANA :
LOKASI :
Kp Limo Rt 003/003
AMBAR RENCANA
POT. MELINTANG
DIBUAT OLEH :
elaksana Kegiatan
................
DIKETAHUI OLEH :
Kepala Desa
................
Jawa Barat
Bekasi
Cibarusah
Cibarusah Jaya
ENIS PRASARANA :
LOKASI :
Kp Limo Rt 003/003
AMBAR RENCANA
AIL PATOK DAN BEKISTING
DETAIL POTONGAN
DIBUAT OLEH :
elaksana Kegiatan
................
DIPERIKSA OLEH :
DISETUJUI OLEH :
Kepala Desa
................
Jawa Barat
Bekasi
Cibarusah
Cibarusah Jaya
ENIS PRASARANA :
LOKASI :
Kp Limo Rt 003/003
AMBAR RENCANA
POT. MEMANJANG
POT. MELINTANG
DIBUAT OLEH :
elaksana Kegiatan
................
DIPERIKSA OLEH :
DIKETAHUI OLEH :
Kepala Desa
................