UPAH
1 Pekerja Hok 110,000
2 Tukang Hok 125,000
3 Mandor Hok 140,000
4
5 Januari 2022
….......................
Kabupaten : KOTA SORONG Pekerjaan : LAPANGAN FOOTSAL
Kecamatan : PUNCAK CENDRAWASIH Lokasi : Dsn BAKAL
Desa : BAKAL TAKE OF SHEET Dimensi : 25 x 38 x 0.12
No. TOS : 01 Volume : 114.0 m3
Data Rencana Konstruksi
38
Panjang Rabat BetonTotal 38 m'
Lebar Rabat Beton 25.0 m
Tebal Rabat Beton 0.12 m
Tebal Lantai Kerja 0.03 m
Lebar Lantai Kerja 25.1 m 25
AL
O
G
O
G
A
L
Panjang Lantai Kerja 38.1 m'
Tebal Urugan Sirtu 0.15 m
Lebar Urugan Sirtu 25.2 m
Panjang Urugan Sirtu 38.5 m'
Tebal Urugan Pasir 0.05 m
Lebar Urugan Pasir 25.1 m
Panjang Urugan Pasir 38.1 m
Cor Rabat
0.12
0.15
Tanah Asli
0.00
Lantai Kerja 0.03 Urugan Sirtu 0.15
01 Beton Rabat
1> KEBUTUHAN BAHAN
Lantai Kerja 1 : 3 : 5 An. SNI ( Revisi ) 6.4.1
A. Volume Bahan
1. Semen @ 50 Kg
28.69 x 0.2 = 5.74 Zak ~ 5.74 Zak
2. Koral 3/5
28.69 x 0.026 = 0.75 m3 ~ 0.75 m3
3. Pasir Cor
28.69 x 0.044 = 20.98 m3 ~ 20.98 m3
4. Plastik
25.10 x 38.1 x 1.2 = 76.2 m2 ~ 76 m2
1. Semen @ 50 Kg
114.00 x 4.36 = 497.04 Zak ~ 497.0 Zak
2. Koral 3/5
114.00 x 0.52 = 59.28 m3 ~ 59.28 m3
3. Pasir Cor
114.0 x 0.87 = 99.18 m3 ~ 99.18 m3
Papan Begisting
• Kebutuhkan papan Begisting 0,2/4 Kayu randu
Ø6- 30
= 25 + 25 + 38 + 38 = 126 m'
25
= 126 : 4 = 32 Lbr
= 32 / 2 (2 x Pemakaian)
15.8 Lbr 16 Lbr ~ 16 Lbr
PEKERJAAN GAWANG
Volume Bidang Pipa Galvanis Ø 2,5"
= 4 + 9 + 8
= 21 m'
= 21 : 6 = 3.50 Lonjor
2.0 x
7.00 Lonjor ~ 7.0 Ljr
2 Unit Keliling = 2 π R
1 = 2.00 x 3.14 x 3.175
3 = 19.94 cm
= 19.94 x 8 x 2 Unit
= 319.0 cm : 10 = 31.9
Luas = 19.9 x 21
2 = 418.7 cm2 4.19 m2 4.2 m2
Jaring Gawang
= 2 + 2 + 6
= 10 m2 = 10.0 m2
2.0 x
20.0 m2 ~ 20.0 m2
1 m2 Pengecatan permukaan baja dengan meni besi An. SNI ( Revisi ) 6.20.1
Pengecatan Lantai
Kebutuhan Molen
1 adukan molen = 0.25 m3
Volume Lantai Kerja dan Rabat Beton
= 142.69 m3
Upah Tenaga Kerja Latai Kerja + Rabat An. SNI ( Revisi ) 6.28.00
a b c=a-b d f g=cxf
1. BAHAN
1.1 Semen @ 50 Kg 503 503 Zak 80,000 40,240,000
1.2 Koral 2/3 61 61 m3 1,200,000 73,200,000
1.3 Pasir Cor 120.2 120 m3 1,200,000 144,192,000
1.4 Pasir Urug/Sirtu 174.6 175 m3 1,200,000 209,563,200
1.5 Plastik 76 76 m2 10,000 760,000
1.6 Papan Randu 2/20 @ 4m 16 16 Lbr 10,000 157,000
1.7 Kayu Meranti 3/5 @ 4m 3 3 Btg 35,000 110,250
1.8 Paku 10 10 Kg 16,000 160,000
1.9 Cat - - Kg 45,000 -
- - - - - -
Sub Total 1) 468,382,450
2. ALAT
2.1 Sekop 4 4 Buah 75,000 300,000
2.2 Cangkul 2 2 Buah 100,000 200,000
2.3 Cetok 2 2 Buah 25,000 50,000
2.4 Palu 1 1 Buah 50,000 50,000
2.5 Ember Cor 22 22 Buah 10,000 220,000
2.6 Cikrak 2 2 Buah 40,000 80,000
2.7 Gerobak Arco 1 1 Unnit 450,000 450,000
2.8 Benang 6 6 Roll 5,000 30,000
2.9 Kuas 2" - - Buah 7,500 -
2.10 - - -
Sub Total 2) 1,380,000
3. ALAT PENDUKUNG
3.1 Demob Molen 1 1 Ls 997,550 997,550
3.2 Sewa Molen 1 1 Hari 200,000 200,000
3.3 Papan Proyek 1 1 Ls 300,000 300,000
3.4 Prasasti 1 1 Ls 450,000 450,000
Sub Total 3) 1,947,550
4. UPAH
4.1 Pekerja 201 201 Hok 110,000 22,110,000
4.2 Tukang 36 36 Hok 125,000 4,500,000
4.3 Mandor 12 12 Hok 140,000 1,680,000
249 Sub Total 4) 28,290,000
38
GAMBAR RENCANA
2,5
2,5 2,5 2,5
KABUPATEN
40 m
20 m 20 m
Touch Line KOTA SORONG
38 KECAMATAN
2,5
PUNCAK CENDRAWASIH
Goal Line
10 m 30 DESA
H=2m
BAKAL
5m
1m
Penalty spot JENIS PRASARANA
GOAL
GOAL
20 25
23 m
3m
3,1 m
3m
3m
Second Penalty spot
LAPANGAN FOOTSAL
6m
Goal Line
LOKASI
5m
Dsn BAKAL
6m
JUDUL GAMBAR
5m
5m
5m 5m 5m
40 cm Inside Pitch
….......................
Rabat Beton
Rabat Beton
Lantai Kerja 3 cm
0.12
GAMBAR RENCANA
0.15 Urugan Pasir 5 cm
Tanah Asli
Urugan Sirtu
0.00 KABUPATEN
Lantai Kerja
Urugan Sirtu Tanah Asli KOTA SORONG
KECAMATAN
POTONGAN PENAMPANG BADAN JALAN DETAIL POTONGAN BADAN JALAN
Non Skala Non Skala PUNCAK CENDRAWASIH
DESA
BAKAL
JENIS PRASARANA
LAPANGAN FOOTSAL
LOKASI
Dsn BAKAL
JUDUL GAMBAR
Digambar Oleh :
….......................
Diperiksa dan Disetujui oleh :
KABUPATEN
KECAMATAN
DESA
JENIS PRASARANA
LOKASI
Dsn
JUDUL GAMBAR
Digambar Oleh :
TAMPAK DEPAN
Non Skala
KABUPATEN
KECAMATAN
DESA
JENIS PRASARANA
LOKASI
Dsn
JUDUL GAMBAR
Digambar Oleh :
TAMPAK SAMPING
Non Skala