HASIL SURVEY HARGA BAHAN / ALAT

Sumurbor + Bak Penampungan


Kecamatan : Leuwidamar Desa : Jalupangmulya

No. Jenis Material Satuan Karya Harga RAB


Bangunan

1 Batu Belah M3 120,000 155,000


2 Pasir urug M3 80,000 100,000
3 Pasir pasang M3 150,000 150,000
4 Tanah Urug M3 45,000 50,000
5 Kerikil/Split M3 200,000 170,000
6 Batu bata Buah 350 700
7 Semen Holcim(50 kg) Sak 55,000 70,000
8 Kayu 5/7 x 400 cm M3 2,000,000 900,000
9 Papan 2/20 x 400 cm M3 800,000 900,000
10 Papan 3/20 x 400 cm M3 900,000 900,000
11 Besi beton Ø 10 mm Btg 50,000 50,000
12 Besi beton Ø 6 mm Btg 26,000 35,000
13 Kawat beton Kg 16,000 22,000
14 Paku Kg 12,000 25,000
15 Cat tembok Kg 8,000 45,000
16 Cat plamur Kg 6,000 50,000
17 Kertas amplas Lbr 2,000 5,000
18 Socket drat dalam 1" Buah 5,000
19 Knie Elbow 1" Buah 5,000
20 Socket drat luar 1" Buah 5,000
21 Lem PVC Buah 13,000
22 Sealtif Buah 5,000
23 Tambang Meter 5,000
24 Pipa Inlet 1/2" PVC AW Btg 30,000
25 Stop kran Valve 1/2" Buah 25,000
26 Socket drat dalam 1/2" Buah 19,000
27 Pompa Submersible Unit 4,000,000
28 Pipa PVC 1 1/4" (pipa udara) Btg 80,000
29 Pipa PVC 1" (pipa isap) Btg 50,000
30 Pipa HDPE Ø 1 1/4" Meter 50,000

PERALATAN
1 Benang Buah 5,000
2 Pacul Buah 65,000
3 Ember Buah 15,000
4 Papan Proyek Buah 100,000
5 Prasasti Buah 250,000

UPAH
1 Pekerja HOK 80,000
2 Tukang HOK 90,000
3 Pemasangan Kwh Set 1,800,000
4 Jasa Pengeboran Unit 2,000,000

Jalupangmulya, 08 Maret 2018

Mengetahui Dibuat Oleh ;


Kasi Ekbang Kesra Ketua TPK

( ASEP SUPRIADI ) ( ASEP SUPRIATNA )


PROGRAM PEMBANGUNAN DAN PEMBERDAYAAN MASYARAKAT DAN DESA (P3MD)
SWAKELOLA DAN POLA PADAT KARYA

RENCANA ANGGARAN BIAYA


Propinsi : Banten No. RAB : 04
Kabupaten : Lebak Lokasi : Kp. Saninten
Kecamatan : Leuwidamar Bidang : Pelaksanaan Pembangunan Desa
Desa : Jalupangmulya Kegiatan : Sumur Bor+Bak Penampung Air
Volume : 2,5 x 1,5 meter ( 1 unit )
3
VOLUME HARGA JUMLAH JUMLAH
Kategori SATUAN SWADAYA TOTAL
URAIAN Dari Dana Dari Satuan
Biaya
Desa Swadaya ( Rp. ) ( Rp. ) ( Rp. )
1. BAHAN
1.1 Batu Belah (Cadas) 2.00 0.00 M3 I.a 155,000 - 310,000
1.2 Batu Bata 735.00 0.00 Buah I.a 700 - 514,500
1.3 Kerikil/Split 1.00 0.00 M3 I.a 170,000 - 170,000
1.4 Pasir Urug 0.50 0.00 M3 I.a 100,000 - 50,000
1.5 Pasir Pasang 2.00 0.00 M3 I.a 150,000 - 300,000
1.6 Semen Holcim 50 kg 20.00 0.00 Zak I.b 70,000 - 1,400,000
1.7 Besi Ø 10 mm 7.00 0.00 Btg I.b 50,000 - 350,000
1.8 Besi Ø 6 mm 6.00 0.00 Btg I.b 35,000 - 210,000
1.9 Kawat beton 1.00 0.00 Kg I.b 22,000 - 22,000
1.10 Papan 2/20 x 400 cm Kls IV 0.30 0.00 M3 I.b 900,000 - 270,000
1.11 Kaso 5/7 x 400 cm Kls IV 0.30 0.00 M3 I.b 900,000 - 270,000
1.12 Paku 1.00 0.00 Kg I.b 25,000 - 25,000
1.13 Amplas 1.00 0.00 Lbr I.b 5,000 - 5,000
1.14 Plamur Tembok 1.00 0.00 Kg I.b 50,000 - 50,000
1.15 Cat Tembok 3.00 0.00 Kg I.b 45,000 - 135,000
1.16 Lem PVC 1.00 0.00 Buah I.b 13,000 - 13,000
1.17 Sealtif 2.00 0.00 Buah I.b 5,000 - 10,000
1.18 Pipa Inlet 1/2" PVC AW 2.00 0.00 Btg I.b 30,000 - 60,000
1.19 Stop kran Valve 1/2" 6.00 0.00 Buah I.b 25,000 - 150,000
1.20 Socket drat dalam 1/2" 6.00 0.00 Buah I.b 19,000 - 114,000
1.21 Pompa Submersible 1.00 0.00 Unit I.b 4,000,000 - 4,000,000

Sub Total 1) - 8,428,500


2. PERALATAN
2.2 Papan Proyek 1.00 0.00 Buah II.a 100,000 - 100,000
2.3 Prasasti 1.00 0.00 Buah II.a 250,000 - 250,000

Sub Total 2) - 350,000


3. UPAH
3.1 Jasa Pengeboran 1.00 0.00 Unit III.a 2,000,000 - 2,000,000
3.2 Pemasangan Kwh 1.00 0.00 Set III.a 1,800,000 - 1,800,000
3.3 Pekerja 22.00 0.00 HOK III.a 80,000 - 1,760,000
3.4 Tukang 10.00 0.00 HOK III.a 90,000 - 900,000
32.00
Sub Total 3) - 6,460,000

Total Biaya - 15,238,500

Total Biaya Kontruksi 15,238,500


OP TPK (5%) 761,500
Total Biaya (Termasuk Pajak) 16,000,000

Kategori :
I - a Pembelian bahan hasil tenaga manusia
I - b Pembelian bahan hasil industri

II - a Pembelian alat tangan


II - b Pembelian / penyewaan alat mesin

III - a Pembayaran tenaga kerja untuk konstruksi


III - b Pembayaran tenaga untuk pengumpulan bahan
Jalupangmulya, 30 April 2018

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


Kasi Ekbang Kesra TA.ID/ PDTI Ketua TPK Kader Teknik Desa

( ASEP SUPRIADI ) ( ERWIN FURQONI, ST ) ( ASEP SUPRIATNA ) ( IQBAL RAMADHAN, ST )


ANALISA KEBUTUHAN MATERIAL
Kabupaten : Lebak Jenis Kegiatan : Sumur Bor+ Bak Penampungan
Kecamatan : Leuwidamar Lokasi : Kp. Saninten
Desa : Jalupangmulya Dimensi/Ukuran : 2 x 1,5 Meter / Unit

Item Pekerjaan Satuan Volume Kebutuhan

I. PEKERJAAN PERSIAPAN
1.1. Pek. Bouplank M' 15.00
0.007 M3 Papan 2/20 x 400 cm 0.11 M3
0.012 M3 Kaso 5/7 x 400 cm 0.18 M3
0.020 Kg Paku 0.30 Kg
0.100 HOK Pekerja 1.50 HOK
0.100 HOK Tukang kayu 1.50 HOK

II. PEKERJAAN PONDASI


2.1. Galian Tanah M3 2.63
0.750 HOK Pekerja 1.97 HOK

2.2. Urugan Pasir M3 0.35


1.200 M3 Pasir Urug 0.42 M3
0.300 HOK Pekerja 0.11 HOK

2.3. Pasangan Batu Kosong M3 0.53


1.200 M3 Batu Belah 0.63 M3
0.780 HOK Pekerja 0.41 HOK

2.4. Pek. Pas. Batu Belah ad. 1 : 4 M3 1.26


1.200 M3 Batu Belah 1.51 M3
0.522 M3 Pasir Pasang 0.66 M3
3.260 Sak Semen 4.11 Sak
1.500 HOK Pekerja 1.89 HOK
0.750 HOK Tukang 0.95 HOK

2.5. Pek. Urugan Kembali M3 0.66


Biaya dihitung 1/3 dari biaya galian
0.750 Pekerja 0.49 HOK

III. PEKERJAAN SLOOF BETON


3.1. Pek. Bekesting M2 2.80
0.045 M3 Papan 2/20 x 400cm 0.13 M3
0.028 M3 Kaso 5/7 x 400 cm 0.08 M3
0.300 Kg Paku 0.84 Kg
0.520 HOK Pekerja 1.46 HOK
0.260 HOK Tukang 0.73 HOK

3.2. Pek. Beton ad. 1 : 2 : 3 M3 0.21


0.780 M3 Kerikil/Split 0.16 M3
0.520 M3 Pasir Pasang 0.11 M3
6.640 Sak Semen 1.39 Sak
1.650 HOK Pekerja 0.35 HOK
0.250 HOK Tukang 0.05 HOK

3.3. Pek. Pembesian Per 100 kg 0.28


2.71 Btg Besi Ø 10 mm 2.71 Btg
2.99 Btg Besi Ø 6 mm 2.99 Btg
0.150 kg Kawat beton 0.04 kg
0.070 HOK Pekerja 0.02 HOK
0.070 HOK Tukang besi 0.02 HOK

IV. PEKERJAAN DINDING


4.1. Pek. Pas. 1/2 batu untuk Batu M2 10.50
bata ad. 1 : 2
70.00 buah Batu bata 735.00 buah
0.038 M3 Pasir pasangan 0.40 M3
0.379 Sak Semen 3.98 Sak
0.300 HOK Pekerja 3.15 HOK
0.100 HOK Tukang batu 1.05 HOK
Item Pekerjaan Satuan Volume Kebutuhan

4.3. Pek. Plesteran dinding dan M2 21.00


acian ad. 1 : 2
0.020 M3 Pasir pasangan 0.42 M3
0.204 Sak Semen 4.28 Sak
0.300 HOK Pekerja 6.30 HOK
0.150 HOK Tukang batu 3.15 HOK

V. PEKERJAAN KOLOM PRAKTIS


5.1. Pek. Bekesting M2 0.60
Material tidak dihitung menggunakan
bekas pek. Sloof
0.520 HOK Pekerja 0.31 HOK
0.260 HOK Tukang 0.16 HOK

5.2. Pek. Beton ad. 1 : 2 : 3 M3 0.06


0.780 M3 Kerikil/Split 0.05 M3
0.520 M3 Pasir Pasang 0.03 M3
4.640 Sak Semen 0.28 Sak
1.650 HOK Pekerja 0.10 HOK
0.250 HOK Tukang 0.02 HOK

5.3. Pek. Pembesian Per 10 kg 1.97


2.35 Btg Besi Ø 10 mm 2.35 Btg
0.87 Btg Besi Ø 6 mm 0.87 Btg
0.150 kg Kawat beton 0.30 kg
0.070 HOK Pekerja 0.14 HOK
0.070 HOK Tukang besi 0.14 HOK

VI. PEKERJAAN RING BALK


6.1. Pek. Bekesting M2 2.80
Material tidak dihitung menggunakan
bekas pek. Sloof
0.007 M3 Papan 2/20 x 400 cm 0.02 M3
0.012 M3 Kaso 5/7 x 400 cm 0.03 M3
0.02 Kg Paku 0.06 Kg
0.520 HOK Pekerja 1.46 HOK
0.260 HOK Tukang 0.73 HOK

6.2. Pek. Beton ad. 1 : 2 : 3 M3 0.21


0.780 M3 Kerikil/Split 0.16 M3
0.520 M3 Pasir Pasang 0.11 M3
4.640 Sak Semen 0.97 Sak
1.650 HOK Pekerja 0.35 HOK
0.250 HOK Tukang 0.05 HOK

6.3. Pek. Pembesian Per 10 kg 2.52


1.52 Btg Besi Ø 10 mm 1.52 Btg
1.93 Btg Besi Ø 6 mm 1.93 Btg
0.150 kg Kawat beton 0.38 kg
0.070 HOK Pekerja 0.18 HOK
0.070 HOK Tukang besi 0.18 HOK

VII. PEKERJAAN LANTAI / RABAT BETON


7.1 Pek. Beton ad. 1 : 2 : 3 M3 1.00
0.780 M3 Kerikil/Split 0.78 M3
0.520 M3 Pasir Pasang 0.52 M3
4.640 Sak Semen 4.64 Sak
1.650 HOK Pekerja 1.65 HOK
0.250 HOK Tukang 0.25 HOK

VIII. PEKERJAAAN PENGECATAN


8.1 Pek. Pengecatan dinding M2 10.50

0.260 kg Cat tembok 2.73 kg


0.100 kg Cat plamur 1.05 kg
0.050 lbr Kertas amplas 0.53 lbr
0.02 HOK Pekerja 0.21 HOK
0.06 HOK Tukang Cat 0.66 HOK
Item Pekerjaan Satuan Volume Kebutuhan

IX. PEKERJAAAN PENGEBORAN DAN PERALATAN


9.1 Instalasi Air Unit 1.00

1.00 Buah Lem PVC 1.00 Buah


2.00 Buah Sealtif 2.00 Buah
2.00 Btg Pipa Inlet 1/2" PVC AW 2.00 Btg
6.00 Buah Stop kran Valve 1/2" 6.00 Buah
6.00 Buah Socket drat dalam 1/2" 6.00 Buah
1.00 Buah Pompa Submersible 1.00 Unit

9.2 Upah Pengeboran (Submersible) Ls 1.00


1.00 Ls 1.00 Ls

REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA (UPAH) / UNIT

BAHAN JUMLAH SATUAN


Batu Belah 2.00 M3 1
Batu Bata 735.00 Buah 1
Kerikil/Split 1.00 M3 1
Pasir Urug 0.50 M3 1
Pasir Pasang 2.00 M3 1
Semen Holcim 50 kg 20.00 Zak 1
Besi Ø 10 mm 7.00 Btg 1
Besi Ø 6 mm 6.00 Btg 1
Kawat beton 1.00 Kg 1
Papan 2/20 x 400 cm Kls IV 0.30 M3 1
Kaso 5/7 x 400 cm Kls IV 0.30 M3 1
Paku 1.00 Kg 1
Amplas 1.00 Lbr 1
Plamur Tembok 1.00 Kg 1
Cat Tembok 3.00 Kg 1
Lem PVC 1.00 Buah 1
Sealtif 2.00 Buah 1
Pipa Inlet 1/2" PVC AW 2.00 Btg 1
Stop kran Valve 1/2" 6.00 Buah 1
Socket drat dalam 1/2" 6.00 Buah 1
Pompa Submersible 1.00 Unit 1

TENAGA
Pekerja 22.00 HOK 1
Tukang 10.00 HOK 1
Pengeboran 1.00 Ls
Pemasangan KWH Listrik 1.00 Ls 1
Kabupaten : Lebak Jenis Prasarana : Sumur Bor + Bak Penampungan
Kecamatan : Leuwidamar Lokasi : Kp. Monggor Kandang,
Desa : Jalupangmulya
Take Of Sheet : Kp, Impres, dan Kp. Cigintung
Volume : 2 x 1,5 m / Unit

I. PEKERJAAN PERSIAPAN

1.1. Pek. Bouplank


Panjang bowplank = 4.00 Meter
3,50
3,00 Lebar bowplank = 3.50 Meter

Total panjang = (4,00+3,50) x 2 meter = 15.00 Meter


4,00

II. PEKERJAAN PONDASI


2.1. Galian Tanah
1,50 Lebar galian = 0.50 Meter
Tinggi galian = 0.75 Meter

Panjang Pondasi = ( 2,00 x 2 ) + (1,50 x 2 ) = 7.00 Meter


2,00

Volume Galian = (7,00) x ( 0,50 x 0,75) meter = 2.63 M3

0,75

0,50

2.2. Urugan Pasir tebal 10 cm


Panjang = 7.00 Meter
0,10
Lebar = 0.50 Meter
0,50 Tebal urugan = 0.10 Meter

Volume Urugan = (7,00 x 0,50 x 0,10) = 0.35 M3

2.3. Pek. Pasangan Batu Kosong


Panjang = 7.00 Meter
Lebar = 0.50 Meter
0,15 Tebal = 0.15 Meter
0,50
Luas Pasangan Batu = (7,00 x 0,50x0,15) = 0.53 M2

2.4. Pek. Pas. Batu Belah ad. 1 : 4


0,20 Panjang = 7.00 Meter
Lebar atas = 0.20 Meter
Lebar bawah = 0.40 Meter
0,60 Tinggi pondasi = 0.60 Meter

0,40 Volume Pas. Pondasi = (7,00 x ((0,40 + 0,20) / 2) x 0,60 = 1.26 M3

2.5. Pek. Urugan Kembali


Dihitung 25 % dari total galian
Volume Urugan kembali = 0,25 x 2,63 = 0.66 M3

III. PEKERJAAN SLOOF BETON


3.1. Pek. Bekesting
Panjang sloof = 7.00 Meter
Lebar sloof = 0.15 Meter
Tebal sloof = 0.20 Meter

Luas Bekesting = (7,00 x 0,20) x 2 = 2.80 M2

3.2. Pek. Beton ad. 1 : 2 : 3


Panjang sloof = 7.00 Meter
0,20
Lebar sloof = 0.15 Meter
0,15 Tebal sloof = 0.20 Meter

Volume beton = (7,00 x 0,15 x 0,20) meter = 0.21 M3


3.3. Pek. Pembesian
0,05 a. Besi Ø 10 mm
Ø 10
Jumlah besi / sloof = 4.00 Buah
L = …. m Panjang besi = ((2,10 x2) + (1,60x2)) x 4 x 1,10 = 32.56 Meter

Besi Ø 10 mm = 32.56 / 12 = 2.71 Btg

Volume Besi = 32.56 m x 0,617 kg/m = 20.09 Kg

b. Besi Ø 6 mm
0,03 Jumlah sloof = 4.00 Buah
Panjang sloof = 7.00 Meter
0,17
Panjang besi = 0.64 Meter
Ø6 Jarak cincin = 0.15 Meter
Jumlah cincin sloof = 51.00 Buah
0,12
Panjang besi = 51.00 x 0,64 ) x 1,10 = 35.90 Meter
Besi Ø 6 mm = 35.90 / 12 = 2.99 Btg

Volume Besi = 35.90 m x 0,222 kg/m = 7.97 Kg

Total Volume Besi = 20.09 + 7.97 = 28.06 Kg


= 28.06 / 100 kg ) = 0.28

IV. PEKERJAAN DINDING


4.1 Pek. Pas. 1/2 batu untuk Batu bata ad. 1 : 2
Panjang = 7.00 Meter
Tinggi = 1.50 Meter
1,50
Tebal pasangan = 0.10 Meter

Luas dinding = 7.00 x 1,50 = 10.50 M2


L= …m

4.3. Pek. Plesteran dinding dan acian ad. 1 : 2

Luas Plesteran = (Luas Pas. Dinding ad. 1 : 2) x 2


= (10,50 x 2) = 21.00 M2
V. PEKERJAAN KOLOM PRAKTIS
Type 2
3,00 5.4. Pek. Bekesting
Jumlah Kolom = 4.00 Buah
Tinggi Kolom = 1.50 Meter
3,00 3,00

Lebar 1 = 0.10 Meter


Lebar 2 = 0.10 Meter
6,00

Luas Bekesting = (4 x 1,5 x 0,10) x 2 = 0.60 M2

5.5. Pek. Beton ad. 1 : 2 : 3


0,10 Jumlah Kolom = 4.00 Buah
Panjang Kolom = 1.50 Meter
0,10
Lebar Kolom = 0.10 Meter
Tebal Kolom = 0.10 Meter

Volume beton = (1,50 x 0,10 x 0,10) x 4 = 0.06 M3

5.6. Pek. Pembesian


a. Besi Ø 10 mm
0,05 Jumlah besi/Kolom = 4.00 Buah
Ø 10
Jumlah Kolom = 4.00 Buah
L = …. m Tinggi Kolom = 1.50 Meter
Panjang besi = (1,50 + 0,10) x 6 x 4 x 1,10 = 28.16 Meter
Besi Ø 10 mm = (28,16/ 12) = 2.35 Btg

Volume Besi = (28,16 m x 0,617 kg/m) = 17.37 Kg


0,03
b. Besi Ø 6 mm
Jumlah kolom = 4.00 Buah
Ø6 0,07
Panjang kolom = 1.50 Meter
Panjang besi = 0.34 Meter
Jarak cincin = 0.25 Meter
0,07
Jumlah cincin kolom = 28.00 Buah
Panjang besi = (28,00 x 0,34) x 1,10 = 10.47 Meter
Besi Ø 6 mm = (10,47 / 12) = 0.87 Btg

Volume Besi = (10,47 m x 0,222 kg/m) = 2.32 Kg

Total Volume Besi = (17,37 + 2,32) = 19.70 Kg


= (19,70/ 10 kg ) = 1.97

VI. PEKERJAAN RING BALOK

6.1. Pek. Bekesting


1,50 Panjang Ring Balok = 7.00 Meter
Lebar Ring Balok = 0.20 Meter
Tebal Ring Balok = 0.15 Meter

Luas Bekesting = (7,00 x 0,20 ) x 2 = 2.80 M2


2,00

6.2. Pek. Beton ad. 1 : 2 : 3


Panjang Ring Balok = 7.00 Meter
Lebar Ring Balok = 0.20 Meter
Tebal Ring Balok = 0.15 Meter

Volume beton = (0,20 x 0,15 ) x 7 = 0.21 M3

0,05 6.3. Pek. Pembesian


Ø 10 a. Besi Ø 10 mm
Jumlah Ringbalk = 4.00 Buah
L = …. m Panjang besi = (2,10 x2) + (1,60x2)) x 4 x 1,10 = 32.56 Meter

Besi Ø 10 mm = 32.56 / 12 = 1.52 Btg

Volume Besi = 32.56 m x 0,617 kg/m = 20.09 Kg

b. Besi Ø 6 mm
0,03
Jumlah Ringbalk = 4.00 Meter
Panjang Ringbalk = 7.00 Meter
Ø6 0,12 Panjang besi = 0.54 Meter
Jarak cincin = 0.20 Meter
0,12 Jumlah cincin sloof = 39.00 Buah

Panjang besi = (39 x 0,54) x 1,10 = 23.17 Meter


Besi Ø 6 mm = 23.17 /12 = 1.93 Btg

Volume Besi = 23.17 m x 0,222 kg/m = 5.14 Kg

Total Volume Besi = (20,09 + 5,14 ) = 25.23 Kg


= 25.23 /10kg = 2.52 Kg

VII. PEKERJAAN LANTAI / RABAT BETON

7.1 Pek. Beton ad. 1 : 2 : 3


Panjang Lantai = 4.00 Meter
Lebar Lantai = 2.50 Meter
Tebal Lantai = 0.10 Meter

Volume beton = (4,00 x 2,50) x 0,10 = 1.00 M3

VIII. PENGECATAN
8.1 Panjang Dinding = 7.00 Meter
Tinggi Dinding = 1.50 Meter

Luas Pengecatan = ( 7,00 x 1,50 ) x 2 = 10.50 M2

Tanggal Survey : Dibuat oleh :


3/3/2017 ( Kader Teknik )
4,00

1,00 2,00 1,00


Propinsi : Banten

Kabupaten : Lebak

A A Kecamatan : Leuwidamar

1,50
Desa : Jalupangmulya

2,50
Tampak Depan Jenis Prasarana
Sumur Bor + Bak Penampung
Lokasi :
Kp. Saninten

1,00
JUDUL GAMBAR
-Denah
-Tampak Depan
-Tampak Belakang
DENAH -Tampak Samping Kiri
-Tampak Samping Kanan
Dibuat oleh :
Kader Teknik / Tenaga Profesional

Tampak Belakang
( Iqbal Ramadhan, ST )
Diperiksa oleh :
TA. Infrastruktur

1.50 1.50 ( Erwin Furqoni, ST )


Diperiksa Oleh :
Kasi Ekbang Kesra

( Asep Supriadi )
Tampak Samping Kiri Tampak Samping Kanan
Lembar ke …. dari ….
B + 1,50
+ 1,35

Ring Balok
uk. 15/15 cm
Propinsi : Banten
Pas. 1/2 batu Stop Kran
bata ad. 1 : 4 1/2" Kabupaten : Lebak

C Kolom Kecamatan : Leuwidamar


Uk. 10/10
Sloof Desa : Jalupangmulya
Uk. 15/20 Jenis Prasarana
Rabat Beton Rabat Beton
ad.1:2:3 Sumur Bor + Bak Penampung
ad.1:2:3 0,15 ± 0,00
D Lokasi :
-
0,10, Kp. Saninten
Pasir urug Pondasi Pas. Batu - 0,20
- 0,53 JUDUL GAMBAR
tebal 10 cm belah ad. 1 : 4 0,2
5 - 0,40 - Detail Pot A-A
- - Detail Penulangan Sloof
Batu Kosong - 0,65 0,55,
Pasir urug - Denah Ring Balok
0,40 - Detail Penulangan Kolom
0,50
DETAIL POT A-A Dibuat oleh :
Kader Teknik / Tenaga Profesional

4Ø10
4Ø1 Beton ad. 1 : 2 : 3
0,15
0 1,50 ( Iqbal Ramadhan, ST )
0,20 Diperiksa oleh :
Ø6 - 15 4Ø10 TA. Infrastruktur
5,00 Ø6 -15

Detail Penulangan Sloof (Pot. D)

Beton ad. 1 : 2 : ( Erwin Furqoni, ST )


4Ø10 3 0,15 0,10
Beton ad. 1 : 2 : 3 Diperiksa Oleh :
Kasi Ekbang Kesra
0,10
0,15
Ø6 - 20 4Ø10
L = …. m
( Asep Supriadi )
Detail Penulangan Ringbalk (Pot. B) Detail Penulangan Kolom (Pot. C)
Lembar ke …. dari ….
Propinsi : Banten

Kabupaten : Lebak

Kecamatan : Leuwidamar

Desa : Jalupangmulya
Jenis Prasarana
Sumur Bor + Bak Penampung
Lokasi :

Kp. Saninten
JUDUL GAMBAR

- Detail Pompa (Submersible)


± 70 M

Dibuat oleh :
Kader Teknik / Tenaga Profesional

( Iqbal Ramadhan, ST )
Diperiksa oleh :
TA. Infrastruktur

( Erwin Furqoni, ST )
Diperiksa Oleh :
Kasi Ekbang Kesra

( Asep Supriadi )

Lembar ke …. dari ….
SERTIFIKASI PENERIMAAN PEKERJAAN
Tahap I

Desa : Kanekes
Kecamatan : Leuwidamar
Kabupaten : Lebak
Tanggal : 23 - 09 - 2016
pekerjaan : Rehabilitasi Poskesdes, Ukuran : 12 x 9 m = 108 M2

Pekerjaan yang Dapat Diterima


Jenis Pekerjaan Ukuran Lokasi Keterangan Kualitas

PEKERJAAN RANGKA ATAP #REF! M3 Kp. Ciranji Cukup


PEKERJAAN ATAP #REF! M2 Cukup
PEKERJAAN KUSEN PINTU DAN JENDELA #REF! M2 Cukup
PEKERJAAN AKSESORIS PINTU DAN JENDELA 21.00 Set Cukup
PEKERJAAN PLAFOND #REF! M2 Cukup
PEKERJAAN LANTAI RUANGAN #REF! M2 Cukup
PEKERJAAN PENGECATAN #REF! M2 Belum dikerjakan

Bahan dan Alat yang Dapat Diterima


Jenis Bahan dan Alat Volume Keterangan

#REF! #REF! ### Cukup


#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! 0.00 ### Belum dikerjakan
#REF! 0.00 ### Belum dikerjakan
#REF! 0.00 ### Belum dikerjakan
#REF! 0.00 ### Belum dikerjakan
#REF! 0.00 ### Belum dikerjakan
#REF! #REF! ### Cukup
#REF! #REF! M Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! 0.00 Bh Belum dikerjakan
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup

Ketua TPK PD PLD

( Lamri ) (Asep Ahmad Taftazani) ( Septian Dwiyana )


SERTIFIKASI PENERIMAAN PEKERJAAN
Tahap II

Desa : Kanekes
Kecamatan : Leuwidamar
Kabupaten : Lebak
Tanggal : 23 - 12 - 2016
pekerjaan : Rehabilitasi Poskesdes, Ukuran : 12 x 9 m = 108 M2

Pekerjaan yang Dapat Diterima


Jenis Pekerjaan Ukuran Lokasi Keterangan Kualitas

PEKERJAAN RANGKA ATAP #REF! M3 Kp. Ciranji Cukup


PEKERJAAN ATAP #REF! M2 Cukup
PEKERJAAN KUSEN PINTU DAN JENDELA #REF! M2 Cukup
PEKERJAAN AKSESORIS PINTU DAN JENDELA 21.00 Set Cukup
PEKERJAAN PLAFOND #REF! M2 Cukup
PEKERJAAN LANTAI RUANGAN #REF! M2 Cukup
PEKERJAAN PENGECATAN #REF! M2 Cukup

Bahan dan Alat yang Dapat Diterima


Jenis Bahan dan Alat Volume Keterangan

#REF! #REF! ### Cukup


#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! M Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup

Ketua TPK PD PLD

( Lamri ) (Asep Ahmad Taftazani) ( Septian Dwiyana )


SERTIFIKASI PENERIMAAN PEKERJAAN
Tahap I

Desa : Kanekes
Kecamatan : Leuwidamar
Kabupaten : Lebak
Tanggal : 23 - 12 - 2016
pekerjaan : Rehabilitasi Poskesdes, Ukuran : 12 x 9 m = 108 M2

Pekerjaan yang Dapat Diterima


Jenis Pekerjaan Ukuran Lokasi Keterangan Kualitas

PEKERJAAN RANGKA ATAP #REF! M3 Kp. Ciranji Cukup


PEKERJAAN ATAP #REF! M2 Cukup
PEKERJAAN KUSEN PINTU DAN JENDELA #REF! M2 Cukup
PEKERJAAN AKSESORIS PINTU DAN JENDELA 21.00 Set Cukup
PEKERJAAN PLAFOND #REF! M2 Cukup
PEKERJAAN LANTAI RUANGAN #REF! M2 Cukup
PEKERJAAN PENGECATAN #REF! M2 Cukup

Bahan dan Alat yang Dapat Diterima


Jenis Bahan dan Alat Volume Keterangan

#REF! #REF! ### Cukup


#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! ### Cukup
#REF! #REF! M Cukup
#REF! #REF! ### Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup
#REF! #REF! Bh Cukup

Ketua TPK PD PLD

( Lamri ) (Asep Ahmad Taftazani) ( Septian Dwiyana )


ANALISA HARGA SATUAN PEKERJAAN

Kabupaten : Lebak Jenis Prasarana : Pekerjaan Pagar BRC


Kecamatan : Leuwidamar Lokasi : Kp. Ciranji
Desa : Kanekes Volume/Dimensi : 56 M'
Referensi :-Buku Menghitung Anggaran Biaya
Buku SNI Tahun 2002, 2008

Ref. Volume Total Harga


Item Pekerjaan Satuan
Analisa Gambar Volume Satuan

I. PEKERJAAN PERSIAPAN
1.1. Pek. Bouplank A.004 M' 6.00
0.01 M3 Papan 2/20 x 400 cm SNI 2002 0.04 900,000
0.01 M3 Kaso 5/7 x 400 cm 0.07 900,000
0.02 Kg Paku 0.12 25,000
0.1 HOK Pekerja 0.60 80,000
0.1 HOK Tukang kayu 0.60 90,000

II. PEKERJAAN PONDASI 6.1


2.1. Galian Tanah SNI 2835 M3 21.00
0.75 HOK Pekerja 2008 15.75 80,000

2.2. Urugan Pasir 6.1 M3 2.80


1.2 M3 Pasir Urug SNI 2835 3.36 80,000
0.3 HOK Pekerja 2008 0.84 80,000

2.3. Pasangan Batu Kosong 6.1 M3 4.20


1.2 M3 Batu Belah SNI 2835 5.04 150,000
0.78 HOK Pekerja 2008 3.28 80,000

2.4. Pek. Pas. Batu Belah ad. 1 : 4 6.2 M3 10.08


1.2 M3 Batu Belah SNI 2836 12.10 150,000
0.52 M3 Pasir Pasang 2008 5.26 120,000
3.26 Sak Semen 32.86 75,000
1.5 HOK Pekerja 15.12 80,000
0.75 HOK Tukang 7.56 90,000

2.5. Pek. Urugan Kembali 6.9 M3 5.25


Biaya dihitung 1/3 dari biaya gali SNI 2835
0.75 Pekerja 2008 3.94 80,000

III. PEKERJAAN PASANGAN DINDING DAN PAGAR BRC

3.1 Kebutuhan Pagar dan Pintu Dorong BRC M' 19.00


### Lembar BRC 90 x 240 cm 19.00 200,000
1.00 Lembar Pintu Dorong BRC 3 x 1,2 1.00 1,800,000

3.2. Pek. Pas. 1 batu untuk Batu 6.9 M2 18.00


bata ad. 1 : 4 SNI 6897
140 Bh Bata Merah 2008 2,520.00 700
0.53 Sak Semen 9.56 75,000
0.09 M³ Pasir Pasang 1.67 120,000
0.6 OH Pekerja 10.80 80,000
0.3 OH Tukang Batu 5.40 90,000
Ref. Volume Total Harga
Item Pekerjaan Satuan
Analisa Gambar Volume Satuan
3.3. Pek. Pas. 1/2 batu untuk Batu 6.9 M2 8.36
bata ad. 1 : 4 SNI 6897
70 buah Batu bata 2008 585.20 700
0.04 M3 Pasir pasangan 0.36 120,000
0.23 Sak Semen 1.92 75,000
0.3 HOK Pekerja 2.51 80,000
0.1 HOK Tukang batu 0.84 90,000

IV. PEKERJAAAN PLESTERAN DAN ACIAN


4.1. Pek. Plesteran dinding dan 6.4 M2 76.87
acian ad. 1 : 4 SNI 2837
0.02 M3 Pasir pasangan 2008 1.84 120,000
0.13 Sak Semen 9.61 75,000
0.3 HOK Pekerja 23.06 80,000
0.15 HOK Tukang batu 11.53 90,000

V. PEKERJAAAN PENGECATAN
5.1 Pek. Pengecatan dinding N.008 M2 76.87
SNI 2002
0.26 kg Cat tembok 19.99 25,000
0.1 kg Cat plamur 7.69 19,000
0.05 lbr Kertas amplas 3.84 4,500
0.02 HOK Pekerja 1.54 80,000
0.06 HOK Tukang Cat 4.84 90,000

VI. PERALATAN Buah

JUMLAH

HARGA BANGUNAN / M'

KEBUTUHAN BAHAN :

Pagar BRC 90 x 240 cm = 19.00 Lembar


Pintu Dorong BRC 300 x 120 cm = 1.00 Lembar
Batu Belah = 17.00 m3
Pasir urug = 3.00 m3
Pasir pasang = 9.00 m3
Tanah Urug = - m3
Kerikil/Split = - m3
Batu bata = 3,110.00 Bh
Semen Holcim (50 Kg) = 54.00 Sak
Kayu 5/7 x 400 cm Kls III = 0.07 M3
Papan 2/20 x 400 cm Kls III = 0.04 M3
Paku = 0.12 Kg
Cat tembok = 20.00 Kg
Cat plamur = 8.00 Kg
Kertas amplas = 4.00 Bh

UPAH :
Pekerja = 77.00 HOK
Tukang = 31.00 HOK
ung Anggaran Biaya
2002, 2008

Biaya

207,600.00

37,800.00
64,800.00
3,000.00
48,000.00
54,000.00

9,729,451.20

1,260,000.00

268,800.00
67,200.00

756,000.00
262,080.00

1,814,400.00
631,411.20
2,464,560.00
1,209,600.00
680,400.00

315,000.00

10,504,597.60

3,800,000.00
1,800,000.00

1,764,000.00
716,850.00
200,880.00
864,000.00
486,000.00
Biaya

409,640.00
43,137.60
144,210.00
200,640.00
75,240.00

3,824,666.85

221,385.60
720,656.25
1,844,880.00
1,037,745.00

1,221,848.65

499,655.00
146,053.00
17,295.75
122,992.00
435,852.90

25,488,164.30

455,145.79
REKAPITULASI ANGGARAN BIAYA
Propinsi : Banten Kecamatan : Leuwidamar
Kabupaten : Lebak Desa : Kanekes

Kegiatan : Pos Pengamanan Kegiatan : Rehab Poskesdes Kegiatan : Jembatan Gantung


Ukuran : 4 x 4 m : 16 m2 Ukuran : 12 x 9 m : 108 m2 Ukuran : 50 meter
No. URAIAN Bobot % Bobot % Bobot % TOTAL Bobot %
Jumlah : 1 Unit Jumlah : 1 Unit Jumlah : 1 Unit

Dana Desa Swadaya Dana Desa Swadaya Dana Desa Swadaya Dana Desa Swadaya

I BAHAN #REF! 0 #REF! #REF! 0 #REF! 280,761,000 0 71.53 #REF! 0 #REF!


(tidak perlu dirinci)
II PERALATAN #REF! 0 #REF! #REF! 0 #REF! 3,748,000.00 0 0.95 #REF! 0 #REF!
(tidak perlu dirinci)
III UPAH #REF! 174 #REF! #REF! 190 #REF! 58,140,000.00 0 14.81 #REF! 364 #REF!
(tidak perlu dirinci)
JUMLAH #REF! #REF! #REF! #REF! 342,649,000 87.30 #REF! #REF!
IV Operasional TPK (5 %) #REF! #REF! #REF! #REF! 17,132,450 4.36 #REF! #REF!
V PPN (10%) #REF! #REF! #REF! #REF! 28,450,900 7.25 #REF! #REF!
VI PPh (1,5%) #REF! #REF! #REF! #REF! 4,267,650 1.09 #REF! #REF!
JUMLAH TOTAL #REF! 174 #REF! #REF! 190 #REF! 392,500,000 0 100.00 #REF! 364 #REF!
Jumlah Biaya Upah #REF! 174 #REF! #REF! 190 #REF! 58,140,000.00 0 100.00 #REF! 364 #REF!
Jumlah HOK Konstruksi #REF! #REF! HOK #REF! #REF! HOK 772.00 0 #REF! #REF! HOK

Kanekes, 20 Mei 2016


Mengetahui :
Pendamping Teknik Desa Penanggung Jawab Operasional Kegiatan Ketua TPK
Kasi Ekbang

( Kamaludin Malik, ST ) ( Arman ) (........................................)