Anda di halaman 1dari 2

BAB III

REKAPITULASI KEGIATAN DAN BIAYA RKM

Tabel Kegiatan dan Biaya RKM

Harga
Jumlah Biaya
No. Kegiatan Volume Satuan Satu-an
(Rp)
(Rp)
(1) (2) (3) (4) (5) (6)

A. BAHAN MATERIAL
SEPTIC TANK DAN WC
1 Semen Zak 160 75,000 12,000,000
2 Paralon 2” Batang 22 50,000 1,100,000
3 Paralon 1” Batang 7 40,000 280,000
4 Kine 3” Buah 20 30,000 600,000
5 Sock T 3” Buah 20 30,000 600,000
6 Sock T 2” Buah 40 25,000 1,000,000
7 Knee 1” Buah 41 20,000 820,000
8 Closet Keramik Buah 16 250,000 4,000,000
9 Besi Beton D. 0,8 m Batang 40 90,000 3,600,000
10 Batako Buah 800 5,000 4,000,000
11 Slap Deker/Tutup Buah 10 70,000 700,000
12 Pasir Truk 20 500,000 10,000,000
13 Batu hutan Truk 10 500,000 5,000,000
14 Besi 6 mm Batang 30 40,000 1,200,000
15 Besi 8 mm Batang 30 58,000 1,740,000
16 Seng Lembar 80 70,000 5,600,000
`17 Paku Seng Ons 6 40,000 240,000
18 Seng Licin 90 cm Lembar 20 50,000 1,000,000
19 Paku 7 cm Ons 10 30,000 300,000
20 Kayu Koseng 5 x 10 Batang 50 60,000 3,000,000
21 Engsel Buah 640 15,000 9,600,000
22 Oker Tembok Buah 8 200,000 1,600,000
23 Dudukan Closet Buah 16 70,000 1,120,000
24 Paralon 3” Batang 20 90,000 1,800,000
25 Media CTPS Buah 16 100,000 1,600,000
JUMLAH 72,500,000
B UPAH TENAGA KERJA
1 Pekerjaan Jamban 20 unit 1.125.000 22,500,000
c OPERASIONAL
Pembuatan Stempel 1 Buah 150.000 150.000
Biaya Konsumsi Rembuk 4 Kali 500.0000 2.000.000
Pengawasan Pekerjaan 2 Kali 225.000 450.000
Pembelian ATK 1 paket 700.000 700.000
Transport lokal 2 Kali 100.000 100.000
bendahara
Transportasi pencairan 8 OH 200,000 1,600,000
dana
JUMLAH 5,000,000
JUMLAH 100,000,000
Terbilang : Seratus Juta Rupiah