Anda di halaman 1dari 25

DAFTAR HARGA SATUAN BAHAN DAN UPAH

Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS


Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017

No Uraian Harga Bahan dan Upah H. Satuan Satuan Keterangan

A. HARGA UPAH

1 Pekerja 85,000.00 hari


2 Tukang 100,000.00 hari
3 Kepala Tukang 105,000.00 hari
4 Mandor 110,000.00 hari

B. HARGA BAHAN

1 Batu Kali 185,000.00 m3


2 Pasir pasang/beton 160,000.00 m3
3 Pasir Urug 145,000.00 m3
4 Tanah Urug Didatangkan 85,000.00 m3
5 Batu Koral 200,000.00 m3
6 Batu Sepelit/Batu Pecah 350,000.00 m3
7 Semen PC Type I ( Proptland) 1,200.00 Kg
8 Besi beton 13,000.00 Kg
9 Kawat Ikat 22,500.00 Kg
10 Kayu klas II 3,500,000.00 M3
11 Kayu klas IV / Papan cor 2,150,000.00 M3
12 Kayu dolken 7,500.00 Btg
13 Pliwood 3 mm 45,000.00 lbr
14 Multiplek 9 mm 125,000.00 lbr
15 Gipsum 9 mm 85,000.00 lbr
16 Plapon GRC Board 3,8 mm 115,000.00 lbr
17 Lis plapon propil gipsum 7 cm 15,000.00 m1
18 Kaca bening 3 mm 90,000.00 M2
19 Kaca Rybend 5 mm 151,000.00 M2
20 Kaca bening 5 mm 110,000.00 M2
21 Paku seng 25,000.00 Kg
22 Paku Genteng Metal 20,000.00 Kg
23 Paku Genteng Metal 20,000.00 Kg
24 Paku Berbagai Ukuran 18,000.00 Kg
25 Paku Halus 22,500.00 Kg
26 Paku Skroup 25,000.00 Kg
27 Cat Tembok Setara Metrolit 18,000.00 Kg
28 Cat Kayu/ Besi Setara Avian 25,000.00 Kg
29 Cat Kayu Dasar 15,000.00 Kg
30 Cat Tembok Dasar 20,000.00 Kg
31 Meni Kayu 12,500.00 Kg
32 Meni Besi 13,000.00 Kg
33 Plamir Kayu 15,000.00 Kg
34 Plamir Tembok 15,000.00 Kg
No Uraian Harga Bahan dan Upah H. Satuan Satuan Keterangan

35 Minyak Cat 25,000.00 Kg


36 Minyak Bekisting 20,000.00 Ltr
37 Amplas 7,500.00 Lbr
38 Batu Bata 625.00 Bh
39 Paving Blok Tebal 6cm 642.86 Bh
No Uraian Harga Bahan dan Upah H. Satuan Satuan Keterangan

40 Genteng Metal warna Berpasir 90,000.00 M2


41 Bubungan Genteng Metal. Roop 35,000.00 M1
42 Seng Gelombang Warna 37,000.00 Lbr
43 Seng Plat BJLS 30 75,000.00 Lbr
44 Granit 40 x 40 setara " NIRO GRANITO " 48,000.00 Bh
45 Keramik 30 x 30 6,750.00 Bh
46 Keramik 20 x 20 3,000.00 Bh
47 Keramik Lantai 25 x 25 4,687.50 Bh
48 Granit Pelapis Dinding Setara " NIRO GRANITO " 30 x 60 54,000.00 Bh
49 Granit 60 x 60 " NIRO GRANITO " 108,000.00 Bh
50 Klosed Jongkok Porselin Setara " KIA " 350,000.00 Bh
51 Klosed duduk Porselin setara " TOT " Type CW 665IJSW660J 1,500,000.00 Bh
52 Wastafel Tipe Gantung Setara '' TOTO " + Asesoris 650,000.00 Bh
53 Kran Air Setara '' SAN EI /DUPONT '' 75,000.00 Bh
54 Floor Drain Lantai KM/WC ( stenlis Stel ) 65,000.00 Bh
55 Soap Holder Poselin 45,000.00 Bh
56 Jet Water/Shower Spray Setara ''TOTO '' + Komlit Asesoris 350,000.00 Bh
57 Semen Warna 1,800.00 kg
58 Lem Kayu 35,000.00 kg
59 Semen putih 90,000.00 Zak
60 Konci Dobol Slinder 250,000.00 Bh
61 Konci tubular set Setara " YALE " KM/WC 150,000.00 Bh
62 Grendel Tanam Jendela stenlies stell setara " DEKSON " 35,000.00 Bh
63 Engsel pintu kuningan 18,000.00 Bh
64 Gerendel Pintu kuningan 22,500.00 Bh
65 Engsel Jendela kuningan 15,000.00 Bh
66 Gerendel Jendela setara ''DEKSON '' 22,500.00 Bh
67 Hak angin jendela staenliss steil 45,000.00 Bh
68 Tarikan jendela staenliss stell 30,000.00 Bh
69 Bunga pucuk merah 15,000.00 Btg
70 Bunga kalipah 25,000.00 / Pelibek
71 Bunga sabrina 45,000.00 / Pelibek
72 Pengadaan Bunga Bougenfil 115,000.00 / Btg
73 Pupuk kandang 15,000.00 Karung
74 Kornis Penyambung Setara ''Jaya Boart'' 25,000.00 kg
75 Kanstin Beton 42,500.00 Bh
76 Wal Paper L.50 cm 90,000.00 M1
77 Batu Alam 15 x 40 cm Andesid berukir 225,000.00 M2

Bengkulu,13 Agustus 2017


Dibuat Oleh
Penawar
CV. RAJA PERMATA

JULIZAR
Direktur
DAFTAR ANALISA

Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS


Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017

JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

TN.6.1 1 M3 GALIAN TANAH BIASA


0.7500 oh Pekerja 85,000.00 63,750.00
0.0250 oh Mandor 110,000.00 2,750.00
66,500.00
Overhead & Profit 10% 6,650.00
Harga Satuan Pekerjaan 73,150.00

TN.6.9 1 M3 URUGAN TANAH KEMBALI


0.2500 oh Pekerja 85,000.00 21,250.00
0.0083 oh Mandor 110,000.00 913.00
22,163.00
Overhead & Profit 10% 2,216.30
Harga Satuan Pekerjaan 24,379.30

TN.6.11a 1 M3 TIMBUNAN TANAH DIPADATKAN


1.2000 M3 Tanah 85,000.00 102,000.00
0.5000 oh Pekerja 85,000.00 42,500.00
0.0500 oh Mandor 110,000.00 5,500.00
150,000.00
Overhead & Profit 10% 15,000.00
Harga Satuan Pekerjaan 165,000.00

TN.6.11a 1 M3 URUGAN PASIR BAWAH LANTAI/PONDASI


1.2000 M3 Pasir Urug 145,000.00 174,000.00
0.3000 Hari pekerja 85,000.00 25,500.00
0.0100 Hari Mandor 110,000.00 1,100.00
200,600.00
Overhead & Profit 10% 20,060.00
Harga Satuan Pekerjaan 220,660.00

PERSP.6.4 1 M1 Pasangan Bowplank


0.0120 M3 Kayu 5/7 3,500,000.00 42,000.00
0.0200 M 3
Besi Paku 18,000.00 360.00
0.0070 M3 Papan Bowplank 2,150,000.00 15,050.00
0.1000 Hari pekerja 85,000.00 8,500.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0050 Hari Mandor 110,000.00 550.00
77,510.00
Overhead & Profit 10% 7,751.00
Harga Satuan Pekerjaan 85,261.00

POND. 6.14 1 M3 PEKERJAAN BATU KOSONG


1.2000 M3 Batu Kali 185,000.00 222,000.00
0.4320 M3 Pasir Urug 145,000.00 62,640.00
0.7800 Hari pekerja 85,000.00 66,300.00
0.3900 Hari Tukang 100,000.00 39,000.00
0.0390 Hari Kepala Tukang 105,000.00 4,095.00
0.0390 Hari Mandor 110,000.00 4,290.00
398,325.00
Overhead & Profit 10% 39,832.50
Harga Satuan Pekerjaan 438,157.50

POND. 6.5 1 M3 PAS.Pondasi BATU KALI 1:4


JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

1.2000 M3 Batu Kali 185,000.00 222,000.00


163.0000 Kg Semen PC 1,200.00 195,600.00
0.5200 M3 Pasir pasang 160,000.00 83,200.00
1.5000 Hari pekerja 85,000.00 127,500.00
0.6000 Hari Tukang 100,000.00 60,000.00
0.0600 Hari Kepala Tukang 105,000.00 6,300.00
0.0750 Hari Mandor 110,000.00 8,250.00
702,850.00
Overhead & Profit 10% 70,285.00
Harga Satuan Pekerjaan 773,135.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

PLEST. 6.2 1 M2 Pek. Pelesteran 1:2 tbl. 15 mm


8.5200 Kg Semen PC 1,200.00 10,224.00
0.0170 M3 Pasir pasang 160,000.00 2,720.00
0.2000 Hari pekerja 85,000.00 17,000.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0100 Hari Mandor 110,000.00 1,100.00
47,619.00
Overhead & Profit 10% 4,761.90
Harga Satuan Pekerjaan 52,380.90

PLEST. 6.4 1 M2 Pek. Pelesteran 1:4 tbl. 15 mm


6.2400 Kg Semen Type I 1,200.00 7,488.00
0.0240 M3 Pasir pasang 160,000.00 3,840.00
0.2000 Hari pekerja 85,000.00 17,000.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0100 Hari Mandor 110,000.00 1,100.00
46,003.00
Overhead & Profit 10% 4,600.30
Harga Satuan Pekerjaan 50,603.30

DIND. 6.9 1 M2 Pas. Batu Bata Merah Tebal I/2 batu 1:2
70.0000 Bh Batu Bata 625.00 43,750.00
18.9500 Kg Semen Type I 1,200.00 22,740.00
0.0380 M3 Pasir pasang 160,000.00 6,080.00
0.3200 Hari pekerja 85,000.00 27,200.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0150 Hari Mandor 110,000.00 1,650.00
112,470.00
Overhead & Profit 10% 11,247.00
Harga Satuan Pekerjaan 123,717.00

DIND. 6.11 1 M2 Pas. Batu Bata Merah Tebal 1/2 Bata 1:4
70.0000 Bh Batu Bata 625.00 43,750.00
11.5000 Kg Semen Type I 1,200.00 13,800.00
0.0430 M 3
Pasir pasang 160,000.00 6,880.00
0.3000 Hari pekerja 85,000.00 25,500.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0150 Hari Mandor 110,000.00 1,650.00
102,630.00
Overhead & Profit 10% 10,263.00
Harga Satuan Pekerjaan 112,893.00

DIND. 6.2 1 M2 Pas. Batu Bata Merah Tebal I batu 1:2


140.0000 Bh Batu Bata 625.00 87,500.00
43.5000 Kg Semen Type I 1,200.00 52,200.00
0.0800 M3 Pasir pasang 160,000.00 12,800.00
0.6500 Hari pekerja 85,000.00 55,250.00
0.2000 Hari Tukang 100,000.00 20,000.00
0.0200 Hari Kepala Tukang 105,000.00 2,100.00
0.0300 Hari Mandor 110,000.00 3,300.00
233,150.00
Overhead & Profit 10% 23,315.00
Harga Satuan Pekerjaan 256,465.00

DIND. 6.4 1 M2 Pas. Batu Bata Merah Tebal 1 Bata 1:4


140.0000 Bh Batu Bata 625.00 87,500.00
26.5500 Kg Semen Type I 1,200.00 31,860.00
0.0930 M3 Pasir pasang 160,000.00 14,880.00
0.6500 Hari pekerja 85,000.00 55,250.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

0.2000 Hari Tukang 100,000.00 20,000.00


0.0200 Hari Kepala Tukang 105,000.00 2,100.00
0.0300 Hari Mandor 110,000.00 3,300.00
214,890.00
Overhead & Profit 10% 21,489.00
Harga Satuan Pekerjaan 236,379.00

LANT. 6.1 1 M3 Pek. Beton tumbuk 1:3:5


0.8700 M3 Batu Koral 200,000.00 174,000.00
218.0000 Kg Semen PC 1,200.00 261,600.00
0.5200 M3 Pasir pasang 160,000.00 83,200.00
1.6500 Hari pekerja 85,000.00 140,250.00
0.0800 Hari Mandor 100,000.00 8,000.00
0.2500 Hari Tukang 105,000.00 26,250.00
0.0250 Hari Kepala Tukang 110,000.00 2,750.00
696,050.00
Overhead & Profit 10% 69,605.00
Harga Satuan Pekerjaan 765,655.00

Anl.Pt.1 1 m2 Acian
3.2500 Kg Semen Type I 1,200.00 3,900.00
0.1500 Hari pekerja 85,000.00 12,750.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0080 Hari Mandor 110,000.00 880.00
28,580.00
Overhead & Profit 10% 2,858.00
Harga Satuan Pekerjaan 31,438.00

LANT. 6.47 1 m2 Pek. Lantai Keramik 30 x 30


11.8700 Bh Keramik 30 x 30 6,750.00 80,122.50
10.0000 Kg Semen Type I 1,200.00 12,000.00
0.0450 M3 Pasir Pasang 160,000.00 7,200.00
1.5000 Kg Semen Putih 1,800.00 2,700.00
0.6200 Hari pekerja 85,000.00 52,700.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.0300 Hari Mandor 110,000.00 3,300.00
196,697.50
Overhead & Profit 10% 19,669.75
Harga Satuan Pekerjaan 216,367.25

LANT. 6.47.a 1 m2 Pek. Lapis Dinding Granit 40 x 40.


6.2500 Bh Keramik 40 x 40cm 48,000.00 300,000.00
9.8000 Kg Semen Type I 1,200.00 11,760.00
0.0450 M 3
Pasir Pasang 160,000.00 7,200.00
1.3000 Kg Semen Putih 1,800.00 2,340.00
0.6200 Hari pekerja 85,000.00 52,700.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.0300 Hari Mandor 110,000.00 3,300.00
415,975.00
Overhead & Profit 10% 41,597.50
Harga Satuan Pekerjaan 457,572.50

LANT. 6.47 1 m2 Pek. Lantai Keramik 25x25


16.0000 Bh Keramik 25 x 25 cm 4,687.50 75,000.00
10.0000 Kg Semen Type I 1,200.00 12,000.00
0.0450 M3 Pasir Pasang 160,000.00 7,200.00
1.5000 Kg Semen Putih 1,800.00 2,700.00
0.6200 Hari pekerja 85,000.00 52,700.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.0300 Hari Mandor 110,000.00 3,300.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

191,575.00
Overhead & Profit 10% 19,157.50
Harga Satuan Pekerjaan 210,732.50

LANT 6,9 1 m2 Pek. Pas Lantai geranit kasar 60 x 60.


3.0000 Bh geranit kasar 60 x 60. 108,000.00 324,000.00
9.8000 Kg Semen Type I 1,200.00 11,760.00
0.0450 M3 Pasir Pasang 160,000.00 7,200.00
1.3000 Kg Semen Putih 1,800.00 2,340.00
0.2500 Hari pekerja 85,000.00 21,250.00
0.1200 Hari Tukang 100,000.00 12,000.00
0.0120 Hari Kepala Tukang 105,000.00 1,260.00
0.0130 Hari Mandor 110,000.00 1,430.00
381,240.00
Overhead & Profit 10% 38,124.00
Harga Satuan Pekerjaan 419,364.00

DD. 6,9.a 1 m2 Pek. Pas geranit Lapis Dinding 30 x 60.


6.2000 Bh Batu geranit 30 x 60 54,000.00 334,800.00
9.8000 Kg Semen Type I 1,200.00 11,760.00
0.0450 M3 Pasir Pasang 160,000.00 7,200.00
1.3000 Kg Semen Putih 1,800.00 2,340.00
0.2500 Hari pekerja 85,000.00 21,250.00
0.1200 Hari Tukang 100,000.00 12,000.00
0.0120 Hari Kepala Tukang 105,000.00 1,260.00
0.0130 Hari Mandor 110,000.00 1,430.00
392,040.00
Overhead & Profit 10% 39,204.00
Harga Satuan Pekerjaan 431,244.00

LANT. 6.51 1 m2 Pek. Lantai Marmer


1.0000 M2 Lantai Marmer 1,250,000.00 1,250,000.00
14.1500 Kg Semen Type I 1,200.00 16,980.00
0.0300 M3 Pasir Pasang 160,000.00 4,800.00
2.0000 Kg Semen Putih 1,800.00 3,600.00
0.6200 Hari pekerja 85,000.00 52,700.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.0300 Hari Mandor 110,000.00 3,300.00
1,370,055.00
Overhead & Profit 10% 137,005.50
Harga Satuan Pekerjaan 1,507,060.50

DD.. 6.74 1 m2 Pek. Pas dinding batu alam /Andesit


1.0000 M2 batu alam 225,000.00 225,000.00
11.7500 Kg Semen Type I 1,200.00 14,100.00
0.0350 M3 Pasir Pasang 160,000.00 5,600.00
0.6200 Hari pekerja 85,000.00 52,700.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.0300 Hari Mandor 110,000.00 3,300.00
339,375.00
Overhead & Profit 10% 33,937.50
Harga Satuan Pekerjaan 373,312.50

PB 1 M2 Pas Paving Blok 10 x 20. ( 70 Bh )


70.0000 Bh Paving Blok 10 x 20 642.86 45,000.00
0.1000 M3 Pasir Pasir Urug 145,000.00 14,500.00
0.1200 M3 Sirtu 155,000.00 18,600.00
0.2500 Hari Tukang 100,000.00 25,000.00
0.0250 Hari Kepala Tukang 105,000.00 2,625.00
0.5000 Hari pekerja 85,000.00 42,500.00
0.0200 Hari Mandor 110,000.00 2,200.00
150,425.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

Overhead & Profit 10% 15,042.50


Harga Satuan Pekerjaan 165,467.50

LANT. 6.51 1 Bh Pas.Wastapel Duduk Setara " TOTO "


1.0000 Bh Wastafel 650,000.00 650,000.00
6.0000 Kg Semen 1,200.00 7,200.00
0.1200 Perlengkapan 78,000.00 9,360.00
0.0100 M3 Pasir Pasang 155,000.00 1,550.00
1.2000 Hari pekerja 85,000.00 102,000.00
1.4500 Hari Tukang 100,000.00 145,000.00
0.1500 Hari Kepala Tukang 105,000.00 15,750.00
0.1000 Hari Mandor 110,000.00 11,000.00
941,860.00
Overhead & Profit 10% 94,186.00
Harga Satuan Pekerjaan 1,036,046.00

KAYU. 6.5 1 M' Pek. Lisplank papan 3/28


0.0110 M3 Kayu Papan kls. II 3,500,000.00 38,500.00
0.1000 Kg Besi Paku 18,000.00 1,800.00
0.1000 Hari pekerja 85,000.00 8,500.00
0.2000 Hari Tukang 100,000.00 20,000.00
0.0200 Hari Kepala Tukang 105,000.00 2,100.00
0.0050 Hari Mandor 110,000.00 550.00
71,450.00
Overhead & Profit 10% 7,145.00
Harga Satuan Pekerjaan 78,595.00

KAYU. 6.3 1 M3 Pek. Kayu kuda-kuda/gording.


1.1000 M3 Kayu Papan kls. II 3,500,000.00 3,850,000.00
15.0000 Kg Besi strip 13,000.00 195,000.00
5.6000 Kg Paku 18,000.00 100,800.00
1.0000 Hari pekerja 85,000.00 85,000.00
12.0000 Hari Tukang 100,000.00 1,200,000.00
1.2000 Hari Kepala Tukang 105,000.00 126,000.00
0.2000 Hari Mandor 110,000.00 22,000.00
5,578,800.00
Overhead & Profit 10% 557,880.00
Harga Satuan Pekerjaan 6,136,680.00

KAYU. 6.2 1 M3 Pek. Kayu kusen pintu/jendela.


1.2000 M3 Kayu kls. II 3,500,000.00 4,200,000.00
1.2500 Kg Paku 18,000.00 22,500.00
1.0000 Ltr Lem Kayu 35,000.00 35,000.00
6.0000 Hari pekerja 85,000.00 510,000.00
18.0000 Hari Tukang 100,000.00 1,800,000.00
1.8000 Hari Kepala Tukang 105,000.00 189,000.00
0.3000 Hari Mandor 110,000.00 33,000.00
6,789,500.00
Overhead & Profit 10% 678,950.00
Harga Satuan Pekerjaan 7,468,450.00

KAYU. 6.67 1 M2 Pek. Partisi (Dinding Pemisah Pliwood )


0.0280 M3 Kayu kls. II 3,500,000.00 98,000.00
0.0070 M3 Kayu Papan 2,150,000.00 15,050.00
0.8600 Lbr Plywood 125,000.00 107,500.00
0.5600 Ltr Lem Kayu 35,000.00 19,600.00
0.1500 Kg Paku 18,000.00 2,700.00
0.2000 Hari pekerja 85,000.00 17,000.00
0.6000 Hari Tukang 100,000.00 60,000.00
0.0600 Hari Kepala Tukang 105,000.00 6,300.00
0.0100 Hari Mandor 110,000.00 1,100.00
327,250.00
Overhead & Profit 10% 32,725.00
Harga Satuan Pekerjaan 359,975.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

KAYU. 6.7 1 M2 Pek. Pintu Panil Papan


0.0400 M3 Kayu kls. II 3,500,000.00 140,000.00
0.5000 Kg Lem Kayu 35,000.00 17,500.00
1.0000 Hari pekerja 85,000.00 85,000.00
3.0000 Hari Tukang 100,000.00 300,000.00
0.3000 Hari Kepala Tukang 105,000.00 31,500.00
0.0500 Hari Mandor 110,000.00 5,500.00
579,500.00
Overhead & Profit 10% 57,950.00
Harga Satuan Pekerjaan 637,450.00

KAYU. 6.7.b 1 M2 Pek. Pintu Panil Papan + seng plat


0.0400 M3 Kayu kls. II 3,500,000.00 140,000.00
1.0000 M2 Seng Plat 26,041.67 26,041.67
1.0000 Hari pekerja 85,000.00 85,000.00
2.5000 Hari Tukang 100,000.00 250,000.00
0.2500 Hari Kepala Tukang 105,000.00 26,250.00
0.0500 Hari Mandor 110,000.00 5,500.00
532,791.67
Overhead & Profit 10% 53,279.17
Harga Satuan Pekerjaan 586,070.83
Harga Satuan Pekerjaan 639,350.00

KAYU.6.16 1 M2 Pek. Pintu Kaca Kayu Kelas II


0.0240 M3 Papan Kayu 3,500,000.00 84,000.00
0.3000 Kg Paku 5 - 7 cm 18,000.00 5,400.00
0.8000 Hari pekerja 85,000.00 68,000.00
2.4000 Hari Tukang 100,000.00 240,000.00
0.2400 Hari Kepala Tukang 105,000.00 25,200.00
0.0400 Hari Mandor 110,000.00 4,400.00
427,000.00
Overhead & Profit 10% 42,700.00
Harga Satuan Pekerjaan 469,700.00

LANGIT 6.21 1 M2 Pek. Plapon Plywood + Rangka.


0.0140 M3 Kayu Kelas II 3,500,000.00 49,000.00
0.0600 Kg Paku 5 - 7 cm 18,000.00 1,080.00
0.3750 Lbr Plywood 4mm 65,000.00 24,375.00
0.0700 Hari pekerja 85,000.00 5,950.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0035 Hari Mandor 110,000.00 385.00
91,840.00
Overhead & Profit 10% 9,184.00
Harga Satuan Pekerjaan 101,024.00

LANGIT 6.21.A 1 M2 Pek. Plapon Plywood .


0.0300 Kg Paku Halus 22,500.00 675.00
0.3640 Lbr Plywood 4mm 65,000.00 23,660.00
0.1000 Hari pekerja 85,000.00 8,500.00
0.0500 Hari Tukang 100,000.00 5,000.00
0.0050 Hari Kepala Tukang 105,000.00 525.00
0.0050 Hari Mandor 110,000.00 550.00
38,910.00
Overhead & Profit 10% 3,891.00
Harga Satuan Pekerjaan 42,801.00

LANGIT. 6.19 1.M' List Langit Langi Kayu Propil.


1.1000 M1 Kayu Papan Kelas II 3,500,000.00 3,850,000.00
0.0100 Kg Paku 18,000.00 180.00
0.0500 Hari pekerja 85,000.00 4,250.00
0.0500 Hari Tukang 100,000.00 5,000.00
0.0005 Hari Kepala Tukang 105,000.00 52.50
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

0.0030 Hari Mandor 110,000.00 330.00


3,859,812.50
Overhead & Profit 10% 385,981.25
Harga Satuan Pekerjaan 4,245,793.75

LANGIT 6.21.A 1 M2 Pek. Plapon GRC Boart 3,6 mm + Rangka.


0.0140 M3 Kayu Kelas II 3,500,000.00 49,000.00
0.4500 Kg Serbuk Penyambung 25,000.00 11,250.00
0.0500 Rol Kasa Gypsum 18,000.00 900.00
0.0500 Kg Paku Sekrup 25,000.00 1,250.00
0.0600 Kg Paku Biasa 18,000.00 1,080.00
0.3640 Lbr Birc Boart 3.8mm 115,000.00 41,860.00
0.2400 Hari pekerja 85,000.00 20,400.00
0.3700 Hari Tukang 100,000.00 37,000.00
0.0370 Hari Kepala Tukang 105,000.00 3,885.00
0.0120 Hari Mandor 110,000.00 1,320.00
167,945.00
Overhead & Profit 10% 16,794.50
Harga Satuan Pekerjaan 184,739.50

WALL.P.6,21 1 M2 WALLPAPER.
2.2000 M Walpaper Lebar 50 cm 90,000.00 198,000.00
0.2500 Kg Lem 50,000.00 12,500.00
0.7500 Hari pekerja 85,000.00 63,750.00
0.1700 Hari Tukang 100,000.00 17,000.00
0.0170 Hari Kepala Tukang 105,000.00 1,785.00
0.0040 Hari Mandor 110,000.00 440.00
293,475.00
Overhead & Profit 10% 29,347.50
Harga Satuan Pekerjaan 322,822.50

LANGIT 6.21..b 1 M2 Pek. Plapon GRC Board 3.8 mm


0.4500 Kg kornis peny.GRC 25,000.00 11,250.00
0.0500 Rol kasa GRC 18,000.00 900.00
0.1100 Kg Paku Sekrup 25,000.00 2,750.00
0.0600 Kg Paku Biasa 18,000.00 1,080.00
0.3640 Lbr GiRC Boart 3,8 mm 115,000.00 41,860.00
0.2400 Hari pekerja 85,000.00 20,400.00
0.3700 Hari Tukang 100,000.00 37,000.00
0.0370 Hari Kepala Tukang 105,000.00 3,885.00
0.0120 Hari Mandor 110,000.00 1,320.00
120,445.00
Overhead & Profit 10% 12,044.50
Harga Satuan Pekerjaan 132,489.50

LANGIT. 6.19.a 1.M' List Plapon Propil Gipsum.


1.1000 M1 Lis plapon propil gipsum 15,000.00 16,500.00
0.8750 Kg teoung gypsum 1,500.00 1,312.50
0.1125 Hari pekerja 85,000.00 9,562.50
0.0375 Hari Tukang 100,000.00 3,750.00
0.0037 Hari Kepala Tukang 105,000.00 388.50
0.0065 Hari Mandor 110,000.00 715.00
32,228.50
Overhead & Profit 10% 3,222.85
Harga Satuan Pekerjaan 35,451.35

JK. 6.16 1.M2 Jalusi Kayu.


0.0600 M3 Kayu Papan 3,500,000.00 210,000.00
0.1500 Kg Paku 18,000.00 2,700.00
0.6700 Hari pekerja 85,000.00 56,950.00
2.0000 Hari Tukang 100,000.00 200,000.00
0.2000 Hari Kepala Tukang 105,000.00 21,000.00
0.3350 Hari Mandor 110,000.00 36,850.00
527,500.00
Overhead & Profit 10% 52,750.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

Harga Satuan Pekerjaan 580,250.00

KAYU. 6.35 1 M2 Pek. Rangka Atap (Pas.Kaso + Reng Kayu


0.0140 M3 kayu kaso 5/7 3,500,000.00 49,000.00
0.0072 M3 kayu reng 3/5 3,500,000.00 25,200.00
0.2500 Kg Paku 18,000.00 4,500.00
0.1000 Hari pekerja 85,000.00 8,500.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0050 Hari Mandor 110,000.00 550.00
98,800.00
Overhead & Profit 10% 9,880.00
Harga Satuan Pekerjaan 108,680.00

CAT.6.7 1. M2 Pengecatan Warna Bid Lama.


0.1500 Kg Plamir 15,000.00 2,250.00
0.1700 Kg Cat dasar 20,000.00 3,400.00
0.1700 Kg Cat warna 18,000.00 3,060.00
0.0700 Hari pekerja 85,000.00 5,950.00
0.0750 Hari Tukang 100,000.00 7,500.00
0.0075 Hari Kepala Tukang 105,000.00 787.50
0.0025 Hari Mandor 110,000.00 275.00
23,222.50
Overhead & Profit 10% 2,322.25
Harga Satuan Pekerjaan 25,544.75

CAT. 6.9 1. M2 Pengecatan Warna Bid Baru 3 Kali Cat.


0.2000 Kg Cat Meni 12,500.00 2,500.00
0.1500 Kg Plamir 15,000.00 2,250.00
0.1700 Kg Cat Dasar 20,000.00 3,400.00
0.2600 Kg Cat Warna 18,000.00 4,680.00
0.0700 Hari pekerja 85,000.00 5,950.00
0.0090 Hari Tukang 100,000.00 900.00
0.0060 Hari Kepala Tukang 105,000.00 630.00
0.0030 Hari Mandor 110,000.00 330.00
20,640.00
Overhead & Profit 10% 2,064.00
Harga Satuan Pekerjaan 22,704.00

CAT. 6.14 1. M2 Pengecatan Tembok Baru .


0.1000 Kg Plamir 15,000.00 1,500.00
0.1000 Kg Cat Dasar 20,000.00 2,000.00
0.2600 Kg Cat Tembok 18,000.00 4,680.00
0.0200 Hari pekerja 85,000.00 1,700.00
0.0630 Hari Tukang 100,000.00 6,300.00
0.0063 Hari Kepala Tukang 105,000.00 661.50
0.0025 Hari Mandor 110,000.00 275.00
17,116.50
Overhead & Profit 10% 1,711.65
Harga Satuan Pekerjaan 18,828.15

CAT.6.15 1. M2 Pengecatan Tembok Lama


0.1200 Kg Cat Dasar 20,000.00 2,400.00
0.1800 Kg Cat Tembok 18,000.00 3,240.00
0.0280 Hari pekerja 85,000.00 2,380.00
0.0420 Hari Tukang 100,000.00 4,200.00
0.0042 Hari Kepala Tukang 105,000.00 441.00
0.0025 Hari Mandor 110,000.00 275.00
12,936.00
Overhead & Profit 10% 1,293.60
Harga Satuan Pekerjaan 14,229.60

ATP. 6.32 1. M2 Atap Genteng Metal warna


1.0200 M2 Genteng Metal Warna Berpasir 90,000.00 91,800.00
0.2000 Kg Paku 20,000.00 4,000.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

0.2000 Hari pekerja 85,000.00 17,000.00


0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0010 Hari Mandor 110,000.00 110.00
123,960.00
Overhead & Profit 10% 12,396.00
Harga Satuan Pekerjaan 136,356.00

ATP. 6.36 1. M' Bubungan Genteng Metal


1.1000 Bh Bubungan Genteng Metal Warna Berpasir 35,000.00 38,500.00
0.0500 Kg Paku 20,000.00 1,000.00
0.2500 Hari pekerja 85,000.00 21,250.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0130 Hari Mandor 110,000.00 1,430.00
78,755.00
Overhead & Profit 10% 7,875.50
Harga Satuan Pekerjaan 86,630.50

ABK-ATP. 6,32.a 1. M2 Atap seng gelombang.warna


0.7500 Lbr Atap Seng Gelombang 37,000.00 27,750.00
0.1200 Kg Paku Seng 25,000.00 3,000.00
0.1400 Hari pekerja 85,000.00 11,900.00
0.0700 Hari Tukang 100,000.00 7,000.00
0.0070 Hari Kepala Tukang 105,000.00 735.00
0.0070 Hari Mandor 110,000.00 770.00
51,155.00
Overhead & Profit 10% 5,115.50
Harga Satuan Pekerjaan 56,270.50

ABK-ATP. 6,36.b 1. M' Bubungan Atap asbes


1.1000 M1 bubungan asbes 20,000.00 22,000.00
0.0500 Kg Paku Baut 25,000.00 1,250.00
0.2500 Hari pekerja 85,000.00 21,250.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0130 Hari Mandor 110,000.00 1,430.00
62,505.00
Overhead & Profit 10% 6,250.50
Harga Satuan Pekerjaan 68,755.50

KNC. 6.2 Pas Konci Tanam Pintu Utama.


1.0000 Bh Kunci 250,000.00 250,000.00
0.0100 Hari pekerja 85,000.00 850.00
0.5000 Hari Tukang 100,000.00 50,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0050 Hari Mandor 110,000.00 550.00
302,450.00
Overhead & Profit 10% 30,245.00
Harga Satuan Pekerjaan 332,695.00

KNC.6.3 Pas Konci Tanam Kamar Mandi.


1.0000 Bh Kunci 150,000.00 150,000.00
0.0050 Hari pekerja 85,000.00 425.00
0.5000 Hari Tukang 100,000.00 50,000.00
0.0005 Hari Kepala Tukang 105,000.00 52.50
0.0025 Hari Mandor 110,000.00 275.00
200,752.50
Overhead & Profit 10% 20,075.25
Harga Satuan Pekerjaan 220,827.75

KNC.6.5 Pas Engsel Pintu


1.0000 Bh Engsel Pintu 18,000.00 18,000.00
0.0150 Hari pekerja 85,000.00 1,275.00
0.1500 Hari Tukang 100,000.00 15,000.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

0.0150 Hari Kepala Tukang 105,000.00 1,575.00


0.0007 Hari Mandor 110,000.00 81.40
35,931.40
Overhead & Profit 10% 3,593.14
Harga Satuan Pekerjaan 39,524.54

KNC.6.6 Pas Engsel Jendela


1.0000 Bh Engsel Jendela 15,000.00 15,000.00
0.0100 Hari pekerja 85,000.00 850.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0005 Hari Mandor 110,000.00 55.00
26,955.00
Overhead & Profit 10% 2,695.50
Harga Satuan Pekerjaan 29,650.50
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

KNC. 6.8 Pas Tarikan JendelaJendela


1.0000 Bh Tarikan Jendela 30,000.00 30,000.00
0.0150 Hari pekerja 85,000.00 1,275.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0007 Hari Mandor 110,000.00 81.40
47,931.40
Overhead & Profit 10% 4,793.14
Harga Satuan Pekerjaan 52,724.54

KNC.6.9 Pas Kaitan Angin Jendela.


1.0000 Bh Kaitan Angin Jendela 45,000.00 45,000.00
0.0150 Hari pekerja 85,000.00 1,275.00
0.1500 Hari Tukang 100,000.00 15,000.00
0.0150 Hari Kepala Tukang 105,000.00 1,575.00
0.0007 Hari Mandor 110,000.00 81.40
62,931.40
Overhead & Profit 10% 6,293.14
Harga Satuan Pekerjaan 69,224.54

SANT,7.1 1 Bh Pasangan Klosed Duduk Setara " TOTO "


1.0000 Bh Kloset Duduh Porselin 1,500,000.00 1,500,000.00
0.0600 Bh Perlengkapan 650,000.00 39,000.00
3.3000 Hari pekerja 85,000.00 280,500.00
1.1000 Hari Tukang 100,000.00 110,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.1600 Hari Mandor 110,000.00 17,600.00
1,948,150.00
Overhead & Profit 10% 194,815.00
Harga Satuan Pekerjaan 2,142,965.00

SANT,7.2 1 Bh Pasangan Wastafel Setara " TOTO "


1.0000 Bh Wastafel Type Gantung 650,000.00 650,000.00
6.0000 Kg Semen Portland 1,200.00 7,200.00
0.0100 M3 Pasir Pasang 160,000.00 1,600.00
1.2000 Hari pekerja 85,000.00 102,000.00
1.4500 Hari Tukang 100,000.00 145,000.00
0.1500 Hari Kepala Tukang 105,000.00 15,750.00
0.1000 Hari Mandor 110,000.00 11,000.00
932,550.00
Overhead & Profit 10% 93,255.00
Harga Satuan Pekerjaan 1,025,805.00

SANT,7.3 1 Bh Pasangan Kran Air Diameter 3/4 '' atau 1/2 ''
1.0000 Bh Kran Air 75,000.00 75,000.00
2.0000 Set Seal Tape 3,000.00 6,000.00
0.0100 Hari pekerja 85,000.00 850.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0500 Hari Mandor 110,000.00 5,500.00
98,400.00
Overhead & Profit 10% 9,840.00
Harga Satuan Pekerjaan 108,240.00

SANT,7.4 1 Bh Pasangan Floor Drain


1.0000 Bh Floor Drain 65,000.00 65,000.00
0.0100 Hari pekerja 85,000.00 850.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0500 Hari Mandor 110,000.00 5,500.00
82,400.00
Overhead & Profit 10% 8,240.00
Harga Satuan Pekerjaan 90,640.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

BT.6.13 Membuat Beton bertulang, 1 PC : 2 Ps : 3 Kr untuk 1,00 m3


336.0000 Kg Semen PC 1,200.00 403,200.00
0.5400 M3 Pasir Pasang 160,000.00 86,400.00
0.8100 M3 Koral Bersih 200,000.00 162,000.00
2.0000 Hari pekerja 85,000.00 170,000.00
0.3500 Hari Tukang 100,000.00 35,000.00
0.0350 Hari Kepala Tukang 105,000.00 3,675.00
0.1000 Hari Mandor 110,000.00 11,000.00
871,275.00
Overhead & Profit 10% 87,127.50
Harga Satuan Pekerjaan 958,402.50

B.6.17 Pembesian 10 kg besi polos atau besi ulir


10.5000 Kg Besi Beton 13,000.00 136,500.00
0.1500 Kg Kawat Ikat 22,500.00 3,375.00
0.0700 Hari pekerja 85,000.00 5,950.00
0.0700 Hari Tukang 100,000.00 7,000.00
0.0070 Hari Kepala Tukang 105,000.00 735.00
0.0040 Hari Mandor 110,000.00 440.00
154,000.00
Overhead & Profit 10% 15,400.00
Harga Satuan Pekerjaan 169,400.00
Harga Satuan Pekerjaan Pembesian / Kg 16,940.00

B.6.29 1 m2 Begisting Sloof


0.0450 M3 Kayu Bekisting 2,150,000.00 96,750.00
0.3000 Kg Paku 18,000.00 5,400.00
0.1000 Ltr Minyak Bekisting 20,000.00 2,000.00
0.5200 Hari pekerja 85,000.00 44,200.00
0.2600 Hari Tukang 100,000.00 26,000.00
0.0260 Hari Kepala Tukang 105,000.00 2,730.00
0.0260 Hari Mandor 110,000.00 2,860.00
179,940.00
Overhead & Profit 10% 17,994.00
Harga Satuan Pekerjaan 197,934.00

B.6.28 1 M2 BEGESTING PONDASI


0.0400 M3 Kayu Bekisting 2,150,000.00 86,000.00
0.3000 Kg Paku 18,000.00 5,400.00
0.1000 Ltr Minyak Bekisting 20,000.00 2,000.00
0.5200 Hari pekerja 85,000.00 44,200.00
0.2600 Hari Tukang 100,000.00 26,000.00
0.0260 Hari Kepala Tukang 105,000.00 2,730.00
0.0260 Hari Mandor 110,000.00 2,860.00
169,190.00
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

B.6.30 1 M2 BEGESTING KOLOM


0.0400 M3 Kayu Bermutu Baik 3,500,000.00 140,000.00
0.4000 Kg Paku 18,000.00 7,200.00
0.2000 Ltr Minyak Bekisting 20,000.00 4,000.00
0.3500 Lbr Multiplek 9mm 125,000.00 43,750.00
2.0000 Btg Dolken 7,500.00 15,000.00
0.6600 Hari pekerja 85,000.00 56,100.00
0.3300 Hari Tukang 100,000.00 33,000.00
0.0330 Hari Kepala Tukang 105,000.00 3,465.00
0.0330 Hari Mandor 110,000.00 3,630.00
306,145.00

BT.6.31. 1 m2 Begisting Balok beton


0.0400 M3 Kayu Bekisting 2,150,000.00 86,000.00
0.4000 Kg Paku 18,000.00 7,200.00
0.2000 Ltr Minyak Bekisting 20,000.00 4,000.00
0.3500 Lbr Multiplek 9mm 125,000.00 43,750.00
2.0000 Btg Dolken 7,500.00 15,000.00
0.6600 Hari pekerja 85,000.00 56,100.00
0.3300 Hari Tukang 100,000.00 33,000.00
0.0330 Hari Kepala Tukang 105,000.00 3,465.00
0.0330 Hari Mandor 110,000.00 3,630.00
252,145.00

B.6.32a 1 m2 Begisting beton cetak


0.0400 M3 Kayu Bekisting 2,150,000.00 86,000.00
0.4000 Kg Paku 18,000.00 7,200.00
0.2000 Ltr Minyak Bekisting 20,000.00 4,000.00
0.6600 Hari pekerja 85,000.00 56,100.00
0.3300 Hari Tukang 100,000.00 33,000.00
0.0330 Hari Kepala Tukang 105,000.00 3,465.00
0.0330 Hari Mandor 110,000.00 3,630.00
193,395.00

B.6.32 1 m2 Begisting Plat lantai


0.0400 M3 Kayu Bekisting 2,150,000.00 86,000.00
0.4000 Kg Paku 18,000.00 7,200.00
0.2000 Ltr Minyak Bekisting 20,000.00 4,000.00
0.3500 Lbr Multiplek 9mm 125,000.00 43,750.00
6.0000 Btg Dolken 7,500.00 45,000.00
0.6600 Hari pekerja 85,000.00 56,100.00
0.3300 Hari Tukang 100,000.00 33,000.00
0.0330 Hari Kepala Tukang 105,000.00 3,465.00
0.0330 Hari Mandor 110,000.00 3,630.00
282,145.00

Anl.Bp.1 1 M3 PONDSAI PLAT


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
98.6400 Kg Besi Beton 16,940.00 1,670,961.60
3.3330 M2 Begisting 169,190.00 563,910.27
3,193,274.37
Overhead & Profit 10% 319,327.44
Harga Satuan Pekerjaan 3,512,601.81

Anl.Bs.2a 1 m3 Beton Sloof 15/15


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
219.9937 Kg Besi Beton 16,940.00 3,726,693.28
13.3333 M2 Begisting 197,934.00 2,639,113.40
7,324,209.18
Overhead & Profit 10% 732,420.92
Harga Satuan Pekerjaan 8,056,630.10
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

Anl.Bs.2b 1 m3 Beton Sloof 15/20


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
151.0000 Kg Besi Beton 16,940.00 2,557,940.00
13.3333 M2 Begisting 197,934.00 2,639,113.40
6,155,455.90
Overhead & Profit 10% 615,545.59
Harga Satuan Pekerjaan 6,771,001.49
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA

Anl.Bk.1a 1 m3 Beton kolom praktis 13/13


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
204.0000 Kg Besi Beton 16,940.00 3,455,760.00
15.3846 M2 Begisting 306,145.00 4,709,918.37
9,124,080.87
Overhead & Profit 10% 912,408.09
Harga Satuan Pekerjaan 10,036,488.95

Anl.Bk.3b 1 m3 Beton kolom struktur 20/20


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
95.5000 Kg Besi Beton 16,940.00 1,617,770.00
15.0000 M 2
Begisting 306,145.00 4,592,175.00
7,168,347.50
Overhead & Profit 10% 716,834.75
Harga Satuan Pekerjaan 7,885,182.25

Anl.Br.1f 1 m3 Beton ring balok 15/20


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
151.0000 Kg Besi Beton 16,940.00 2,557,940.00
13.3333 M2 Begisting 252,145.00 3,361,932.49
6,878,274.99
Overhead & Profit 10% 687,827.50
Harga Satuan Pekerjaan 7,566,102.49

Anl.Br.1g 1 m3 Beton ring balok 10/13


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
118.0000 Kg Besi Beton 16,940.00 1,998,920.00
15.3800 M2 Begisting 252,145.00 3,877,990.10
6,835,312.60
Overhead & Profit 10% 683,531.26
Harga Satuan Pekerjaan 7,518,843.86

Anl.Br.Lant 1 m3 Beton plat lantai


1.0000 M3 Beton 1 : 2 : 3 958,402.50 958,402.50
110.0000 Kg Besi Beton 16,940.00 1,863,400.00
8.3333 M2 Begisting 282,145.00 2,351,198.93
5,173,001.43
Overhead & Profit 10% 517,300.14
Harga Satuan Pekerjaan 5,690,301.57

Bengkulu,13 Agustus 2017


Dibuat Oleh
Penawar
CV. RAJA PERMATA

JULIZAR
Direktur
-
RENCANA ANGGARAN BIAYA

Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS


Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017

H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
I PEKERJAAN PERSIAPAN
1 Papan nama proyek 1.00 Unit Ls 325,000.00 325,000.000
2 ADM/ Dokumentasi, 1.00 Unit Ls 3,500,000.00 3,500,000.000
3 Pengadaan air kerja 1.00 Unit Ls 500,000.00 500,000.000
4 P 3 K. 1.00 Unit Ls 750,000.00 750,000.000
5 Steger woood 1.00 Unit Ls 1,500,000.00 1,500,000.000
TOTAL 1 ………………….. 6,575,000.00

2 REHAB RUMAH DINAS


H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
I PEKERJAAN PASANGAN
1 Pek pas Saluran Air Hujan 25.00 m1 Ls 75,000.00 1,875,000.000
2 Pek Pembongkaran lantai KM/WC 6.00 m2 Ls 15,000.00 90,000.000
3 Beton tumbuk bawah lantai KM/WC 1:3 : 5 0.60 m2 LANT. 6.1 765,655.00 459,393.000
4 Pek Pas lantai Geranit KM/WC 60 x 60 6.00 m2 LANT 6,9 419,364.00 2,516,184.000
5 Pek Beton Meja Dapur 0.25 m3 Anl.Br.Lant 5,690,301.57 1,422,575.393
6 Pas Keramik Meja dapur 25 x 25 3.50 m2 LANT. 6.47 210,732.50 737,563.750
7 Pas Bak Cuci piring Stanlis 1.00 Bh Ls 500,000.00 500,000.000
8 Pas Flour Drain Stenlis Steel 3.00 Bh SANT,7.4 90,640.00 271,920.000
9 Pas Kran Air Setara " SAN EI/DOPONT" 4.00 Bh SANT,7.3 108,240.00 432,960.000
10 Pas Intalasi Air bersih Piva AW 0,5 " 120.00 m1 Ls 17,500.00 2,100,000.000
Total I……………………… 10,405,596.14
II PEK PENGECATAN
1 Pek cat warna kayu ulang Rumah dinas 290.55 m2 CAT.6.7 25,544.75 7,422,027.113
2 Pek cat tembok + kolom ulang rumah dina 1593.40 m2 CAT.6.15 14,229.60 22,673,444.640
3 Pek cat plapon ulang Rumah dinas 503.06 m2 CAT.6.15 14,229.60 7,158,342.576
Total II……………………… 37,253,814.329
III PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 150,000.00 150,000.000
Total III……………………… 150,000.000
TOTAL 2 ( I + II+III ) ………………….. 47,809,410.47
3 REHAB GEDUNG UTAMA
H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
I PEKERJAN PASANGAN
1 Pek.Perbaikan Bak mandi Yang bocor 1.00 Unit Ls 125,000.00 125,000.000
2 Pek Pembongkaran lantai KM/WC 18.00 M2 Ls 15,000.00 270,000.000
3 3 Beton tumbuk bawah lantai KM/WC 1:3:5 0.12 M2 LANT. 6.1 765,655.00 91,878.600
4 Pek Pas lantai Geranit KM/WC 60 x 60 14.00 M2 LANT 6,9 419,364.00 5,871,096.000
5 Pek pembongkaran keramik dinding 115.00 M2 Ls 15,000.00 1,725,000.000
6 Pas dinding geranit KM/WC 30x60 115.00 M2 DD. 6,9.a 431,244.00 49,593,060.000
7 Pas Kran Air Setara " SAN EI/DOPONT" 4.00 SANT,7.3 108,240.00 432,960.000
8 Pas Soap Holder Poselen 3.00 Ls 45,000.00 135,000.000
9 Pas Cermin Depan Wastafel Singel 4.00 Ls 150,000.00 600,000.000
10 Pas Flour Drain Stenlis Steel 3.00 SANT,7.4 108,240.00 324,720.000
11 Pas.Wastafel Porselin gantung Setara TOTO 4.00 SANT,7.2 1,025,805.00 4,103,220.000
12 12 Pas.Jet Shower + Aksesoris 2.00 Ls 350,000.00 700,000.000
13 Pas Intalasi Air bersih Piva AW 0,5 " 20.00 Ls 17,500.00 350,000.000
Total I……………………… 64,321,934.60
II PEK PASANGAN KAYU
1 Pas Wallpaper dinding 338.50 M2 WALL.P.6,21 322,822.50 109,275,416.250
2 Pek Ganti pintu gedung utama 4.95 M2 KAYU.6.16 469,700.00 2,325,015.000
3 Pek Plapon GRC + Rangka 10.50 M2 LANGIT 6.21.A 184,739.50 1,939,764.750
4 Pek Pas plapon GRC 215.40 M2 LANGIT 6.21..b 132,489.50 28,538,238.300
5 Pek Pas Lis plapon Gipsum 170.00 M1 LANGIT. 6.19.a 35,451.35 6,026,729.500
6 Rehab Atap & Talang yang bocor 1.00 Unit Ls 450,000.00 450,000.000
Total II……………………… 148,555,163.80
III PEK PASANGAN KONCI.
1 Pas Konci pintu 1.00 bh KNC. 6.2 332,695.00 332,695.000
2 Pas Konci pintu KM/WC 1.00 bh KNC.6.3 220,827.75 220,827.750
3 Pas Grrendel Pintu Tanam Stenles steel 1.00 Unit Ls 75,000.00 75,000.000
4 Pas Engsel pintu 8.00 bh KNC.6.5 39,524.54 316,196.320
Total III……………………… 944,719.07
IV PEK PENGECATAN.
1 Pek cat warna ulang Gedung Utama 93.75 M2 CAT. 6.9 22,704.00 2,128,500.000
2 Pek cat tembok Gedung Utama 292.20 M2 CAT.6.15 14,229.60 4,157,889.120
3 Pek cat plapon. Gedung Utama 225.90 M2 CAT. 6.14 18,828.15 4,253,279.085
Total IV……………………… 10,539,668.21
V PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 1,250,000.00 1,250,000.000
Total V……………………… 1,250,000.000
TOTAL 3 ( I + II+III+IV+V ) ………………….. 225,611,485.68
4 PEMASANGAN PAVING BLOK DAN PENATAAN TAMAN
I PEKERJAAN TANAH
1 Pek pemotongan tanah 66.41 M3 TN.6.1 73,150.00 4,857,891.500
2 Pek Perbaikan paving blok lama 21.50 M2 Ls 25,000.00 537,500.000
3 Pek Pemasangan Paving Baru 166.85 M2 PB 165,467.50 27,608,252.375
3 Pek Kanstin 21.00 M1 Ls 42,500.00 892,500.000
Total I……………………… 33,896,143.875
II PEK PASANGAN POT BUNGA,
1 Pek Galian tanah pot bunga 2.70 M3 TN.6.1 73,150.00 197,505.000
2 Pek Urugan tanah untuk pot bunga 4.32 M3 TN.6.11a 165,000.00 712,800.000
3 Pek Beton lantai kerja pot bunga 1:3:5 0.54 M3 LANT. 6.1 765,655.00 413,453.700
4 Pek Pas batu bata pot bunga 35.10 M2 DIND. 6.11 112,893.00 3,962,544.300
5 Pek pelesteran 1:4 70.20 M2 PLEST. 6.4 50,603.30 3,552,351.660
6 Pek Ring balok pot bunga. 1:2:3 0.81 M3 Anl.Br.1g 7,518,843.86 6,090,263.527
7 Pek Pas batu alam /Andesit depan + belakang 13.50 M2 DD.. 6.74 373,312.50 5,039,718.750
8 Pek plituran batu alam 13.50 M2 Ls 25,000.00 337,500.000
9 Pek Pengadaan pupuk kandang 30.00 Krg Ls 15,000.00 450,000.000
10 Pengadaan Bunga Pucuk merah 30.00 Btg Ls 15,000.00 450,000.000
11 Pengadaan Bunga Halipah 180.00 Polk Ls 25,000.00 4,500,000.000
H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
12 Pengadaan Bunga Sabrina 180.00 Polk Ls 45,000.00 8,100,000.000
13 Pengadaan Bunga Bougenfil 10.00 Btg Ls 115,000.00 1,150,000.000
Total II ……………………… 34,956,136.94
III PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 350,000.00 350,000.000
Total III……………………… 350,000.000
TOTAL 4 ( I + II+III ) ………………….. 69,202,280.81
5 PEMBUATAN PAGAR TEMBOK
I PEKERJAAN TANAH
1 Pek galian tanah pondasi 1.80 M3 TN.6.1 73,150.00 131,670.000
2 Pek Urugan tanah kembali 0.45 M3 TN.6.9 24,379.30 10,970.685
Total I……………………… 142,640.685
II PEKERJAAN PASANGAN
1 Pek Pembongkaran Pagar Lama 6.00 m2 Ls 45,000.00 270,000.000
2 Pek Pondasi plat setempat 0.36 m3 Anl.Bp.1 3,512,601.81 1,264,536.651
3 Pek Beton Sloop 15/20 0.09 m3 Anl.Bs.2b 6,771,001.49 609,390.134
4 Pek Beton Kolom Struktur 0.50 m3 Anl.Bk.3b 7,885,182.25 3,942,591.125
5 Pek Beton Ring balok 15/20 0.60 m3 Anl.Br.1f 7,566,102.49 4,539,661.495
6 Pek Pas batu Bata 1:4 6.00 m2 DIND. 6.11 112,893.00 677,358.000
7 Pek Pelesteran 1: 4 12.00 m2 PLEST. 6.4 50,603.30 607,239.600
8 Pek Acian Tembok 12.00 m2 Anl.Pt.1 31,438.00 377,256.000
9 Pas Besi Besi Siku 15.00 Btg Ls 35,000.00 525,000.000
10 Pas Kawat Duri 140.00 M1 Ls 2,500.00 350,000.000
Total II……………………… 13,163,033.01
III PEKERJAAN PENGECATAN
1 Pek. Cat tembok 80.00 m2 CAT. 6.14 18,828.15 1,506,252.000
Total III……………………… 1,506,252.00
IV. PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 350,000.00 350,000.000
Total IV……………………… 350,000.000
TOTAL 5 ( I +II+IIII+IV ) ………………….. 15,161,925.69

6 PEMBUATAN PAPAN MEREK DARI BETON.


No URAIAN PEKERJAAN VOLUME ANALISA

I PEKERJAAN TANAH
1 Pek Pembongkaran Pagar 1.00 Unit Ls 2,000,000.00 2,000,000.000
2 Pek Stek Besi tiang Existing 4.00 Unit Ls 250,000.00 1,000,000.000
Total I……………………… 3,000,000.00
II PEKERJAAN PASANGAN
1 Pek Beton slop 20/15 0.39 m3 Anl.Bs.2b 6,771,001.49 2,640,690.582
2 Pek Beton Kolom Struktur 20/20 0.14 m3 Anl.Bk.3b 7,885,182.25 1,103,925.515
3 Pek Beton Ring balok 15/20 0.11 m3 Anl.Br.1f 7,566,102.49 832,271.274
4 Pek Beton Pet 10/40 0.15 m3 Anl.Br.Lant 5,690,301.57 853,545.236
5 Pek Beton Kolom Praktis 13/13 0.03 m3 Anl.Bk.1a 10,036,488.95 301,094.669
6 Pek beton kanstin 1.14 m3 LANT. 6.1 765,655.00 872,846.700
7 Pek Pas batu Bata 1:4 9.36 m2 DIND. 6.11 112,893.00 1,056,678.480
8 Pek Pelesteran 1: 4 18.72 m2 PLEST. 6.4 50,603.30 947,293.776
9 Pek Acian Tembok 12.00 m2 Anl.Pt.1 31,438.00 377,256.000
10 Pek pas Hurup nama gedung dari stanlis 1.00 Unit Ls 3,500,000.00 3,500,000.000
11 Pas Granit dinding 40/40 6.20 m2 LANT. 6.47.a 457,572.50 2,836,949.500
12 Pas Batu andsit 5.50 m2 DD.. 6.74 373,312.50 2,053,218.750
13 Pas lambang Pemerintah Bengkulu 1.00 Unit Ls 1,250,000.00 1,250,000.000
14 Pas Bunga Raflesia ( Beton Bertulang Lengkap ) 2.00 Unit Ls 1,000,000.00 2,000,000.000
Total II……………………… 20,625,770.48
H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
III PEKERJAAN INTT.TITIK API
1 Pas.Titik Api 2.00 Bh Ls 150,000.00 300,000.000
2 Pas.Kabel 2,25 NYY Dalam Tanah 35.00 M1 Ls 90,000.00 3,150,000.000
3 Pas.Lampu Taman Atas Tiang ( TO.2 ) 2.00 Bh Ls 750,000.00 1,500,000.000
4 Pas.Lampu Tembak + Intalasi 2.00 Bh Ls 1,750,000.00 3,500,000.000
5 Pas.Stop Kontak 2.00 Bh Ls 45,000.00 90,000.000
Total III……………………… 8,540,000.00
IV PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 1,000,000.00 1,000,000.000
Total IV……………………… 1,000,000.000
TOTAL 6 ( I + II + III + IV ) ………………….. 33,165,770.48
REKAPITULASI

Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS


Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017

NO URAIAN PEKERJAAN JUMLA HARGA (Rp)

I PEKERJAAN PERSIAPAN 6,575,000.00

2 REHAB RUMAH DINAS 47,809,410.47

3 REHAB GEDUNG UTAMA 225,611,485.68

4 PEMASANGAN PAVING BLOK DAN PENATAAN TAMAN 69,202,280.81

5 PEMBUATAN PAGAR TEMBOK 15,161,925.69

6 PEMBUATAN PAPAN MEREK DARI BETON. 33,165,770.48

Jumlah Fisik 397,525,873.13


Pajak Pertambahan Nilai (PPn) 10% 39,752,587.31
Jumlah Total 437,278,460.44
Dibulatkan 437,278,000.00

Terbilang : Empat Ratus Tiga Puluh Tujuh Juta Dua Ratus Tujuh Puluh Delapan Ribu Rupiah

Bengkulu,13 Agustus 2017


Dibuat Oleh
Penawar
CV. RAJA PERMATA

JULIZAR
Direktur
-TIME SCHEDULE-
Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS
Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017

JANGKA WAKTU PELAKSANAAN 90 ( SEMBILAN PULUH ) HARI KALENDER

BOBOT KET.
URAIAN PEKERJAAN
NO. % MINGGU KE MINGGU KE MINGGU KE MINGGU KE PERSENT
1 2 3 4 5 6 7 8 9 10 11 12 13 (%)

I PEKERJAAN PERSIAPAN 1.654 0.064 0.073 0.077 0.081 0.085 0.097 0.112 0.123 0.154 0.177 0.195 0.195 0.222 100 %

2 REHAB RUMAH DINAS 12.027 0.601 1.503 2.255 3.383 2.142 2.142
75 %

3 REHAB GEDUNG UTAMA 56.754 0.568 1.703 2.554 3.831 5.746 14.366 15.084 12.903

50 %
4 PEMASANGAN PAVING BLOK DAN PENATAAN TAMAN 17.408 0.870 1.871 2.152 2.475 2.846 6.119 1.074

5 PEMBUATAN PAGAR TEMBOK 3.814 1.907 1.907 25 %

6 PEMBUATAN PAPAN MEREK DARI BETON. 8.343 8.343


0%
Jumlah Bobot = ……… 100.000

RencanaKemajuan Fisik % 0.064 0.674 2.148 4.909 7.893 8.223 10.476 17.335 21.357 16.061 10.445 0.195 0.222

Rencana kumulatif Kemajuan Fisik 0.000 0.064 0.738 2.886 7.795 15.687 23.910 34.385 51.720 73.078 89.139 99.583 99.778 100.000 RENC

Bengkulu,13 Agustus 2017


Dibuat Oleh
Penawar
CV. RAJA PERMATA

JULIZAR
Direktur

Anda mungkin juga menyukai