A. HARGA UPAH
B. HARGA BAHAN
JULIZAR
Direktur
DAFTAR ANALISA
JUMLAH HARGA
KD. ANALISA URAIAN (Rp)
TENAGA
DIND. 6.9 1 M2 Pas. Batu Bata Merah Tebal I/2 batu 1:2
70.0000 Bh Batu Bata 625.00 43,750.00
18.9500 Kg Semen Type I 1,200.00 22,740.00
0.0380 M3 Pasir pasang 160,000.00 6,080.00
0.3200 Hari pekerja 85,000.00 27,200.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0150 Hari Mandor 110,000.00 1,650.00
112,470.00
Overhead & Profit 10% 11,247.00
Harga Satuan Pekerjaan 123,717.00
DIND. 6.11 1 M2 Pas. Batu Bata Merah Tebal 1/2 Bata 1:4
70.0000 Bh Batu Bata 625.00 43,750.00
11.5000 Kg Semen Type I 1,200.00 13,800.00
0.0430 M 3
Pasir pasang 160,000.00 6,880.00
0.3000 Hari pekerja 85,000.00 25,500.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0150 Hari Mandor 110,000.00 1,650.00
102,630.00
Overhead & Profit 10% 10,263.00
Harga Satuan Pekerjaan 112,893.00
Anl.Pt.1 1 m2 Acian
3.2500 Kg Semen Type I 1,200.00 3,900.00
0.1500 Hari pekerja 85,000.00 12,750.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0080 Hari Mandor 110,000.00 880.00
28,580.00
Overhead & Profit 10% 2,858.00
Harga Satuan Pekerjaan 31,438.00
191,575.00
Overhead & Profit 10% 19,157.50
Harga Satuan Pekerjaan 210,732.50
WALL.P.6,21 1 M2 WALLPAPER.
2.2000 M Walpaper Lebar 50 cm 90,000.00 198,000.00
0.2500 Kg Lem 50,000.00 12,500.00
0.7500 Hari pekerja 85,000.00 63,750.00
0.1700 Hari Tukang 100,000.00 17,000.00
0.0170 Hari Kepala Tukang 105,000.00 1,785.00
0.0040 Hari Mandor 110,000.00 440.00
293,475.00
Overhead & Profit 10% 29,347.50
Harga Satuan Pekerjaan 322,822.50
SANT,7.3 1 Bh Pasangan Kran Air Diameter 3/4 '' atau 1/2 ''
1.0000 Bh Kran Air 75,000.00 75,000.00
2.0000 Set Seal Tape 3,000.00 6,000.00
0.0100 Hari pekerja 85,000.00 850.00
0.1000 Hari Tukang 100,000.00 10,000.00
0.0100 Hari Kepala Tukang 105,000.00 1,050.00
0.0500 Hari Mandor 110,000.00 5,500.00
98,400.00
Overhead & Profit 10% 9,840.00
Harga Satuan Pekerjaan 108,240.00
JULIZAR
Direktur
-
RENCANA ANGGARAN BIAYA
H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
I PEKERJAAN PERSIAPAN
1 Papan nama proyek 1.00 Unit Ls 325,000.00 325,000.000
2 ADM/ Dokumentasi, 1.00 Unit Ls 3,500,000.00 3,500,000.000
3 Pengadaan air kerja 1.00 Unit Ls 500,000.00 500,000.000
4 P 3 K. 1.00 Unit Ls 750,000.00 750,000.000
5 Steger woood 1.00 Unit Ls 1,500,000.00 1,500,000.000
TOTAL 1 ………………….. 6,575,000.00
I PEKERJAAN TANAH
1 Pek Pembongkaran Pagar 1.00 Unit Ls 2,000,000.00 2,000,000.000
2 Pek Stek Besi tiang Existing 4.00 Unit Ls 250,000.00 1,000,000.000
Total I……………………… 3,000,000.00
II PEKERJAAN PASANGAN
1 Pek Beton slop 20/15 0.39 m3 Anl.Bs.2b 6,771,001.49 2,640,690.582
2 Pek Beton Kolom Struktur 20/20 0.14 m3 Anl.Bk.3b 7,885,182.25 1,103,925.515
3 Pek Beton Ring balok 15/20 0.11 m3 Anl.Br.1f 7,566,102.49 832,271.274
4 Pek Beton Pet 10/40 0.15 m3 Anl.Br.Lant 5,690,301.57 853,545.236
5 Pek Beton Kolom Praktis 13/13 0.03 m3 Anl.Bk.1a 10,036,488.95 301,094.669
6 Pek beton kanstin 1.14 m3 LANT. 6.1 765,655.00 872,846.700
7 Pek Pas batu Bata 1:4 9.36 m2 DIND. 6.11 112,893.00 1,056,678.480
8 Pek Pelesteran 1: 4 18.72 m2 PLEST. 6.4 50,603.30 947,293.776
9 Pek Acian Tembok 12.00 m2 Anl.Pt.1 31,438.00 377,256.000
10 Pek pas Hurup nama gedung dari stanlis 1.00 Unit Ls 3,500,000.00 3,500,000.000
11 Pas Granit dinding 40/40 6.20 m2 LANT. 6.47.a 457,572.50 2,836,949.500
12 Pas Batu andsit 5.50 m2 DD.. 6.74 373,312.50 2,053,218.750
13 Pas lambang Pemerintah Bengkulu 1.00 Unit Ls 1,250,000.00 1,250,000.000
14 Pas Bunga Raflesia ( Beton Bertulang Lengkap ) 2.00 Unit Ls 1,000,000.00 2,000,000.000
Total II……………………… 20,625,770.48
H. SATUAN JUMLAH
No URAIAN PEKERJAAN VOLUME ANALISA
( Rp) ( Rp)
III PEKERJAAN INTT.TITIK API
1 Pas.Titik Api 2.00 Bh Ls 150,000.00 300,000.000
2 Pas.Kabel 2,25 NYY Dalam Tanah 35.00 M1 Ls 90,000.00 3,150,000.000
3 Pas.Lampu Taman Atas Tiang ( TO.2 ) 2.00 Bh Ls 750,000.00 1,500,000.000
4 Pas.Lampu Tembak + Intalasi 2.00 Bh Ls 1,750,000.00 3,500,000.000
5 Pas.Stop Kontak 2.00 Bh Ls 45,000.00 90,000.000
Total III……………………… 8,540,000.00
IV PEKERJAAN LAIN LAIN
1 Pek. Finissing/Pemb sisa pekerjaan 1.00 Unit Ls 1,000,000.00 1,000,000.000
Total IV……………………… 1,000,000.000
TOTAL 6 ( I + II + III + IV ) ………………….. 33,165,770.48
REKAPITULASI
Terbilang : Empat Ratus Tiga Puluh Tujuh Juta Dua Ratus Tujuh Puluh Delapan Ribu Rupiah
JULIZAR
Direktur
-TIME SCHEDULE-
Kegiatan : REHAB SEDANG/BERAT RUMAH DINAS
Pekerjaan : REHAB DAN PENGECATAN RUMAH DINAS WAKIL GUBERNUR.
Lokasi : KOTA BENGKULU.
Thn. Anggaran : 2017
BOBOT KET.
URAIAN PEKERJAAN
NO. % MINGGU KE MINGGU KE MINGGU KE MINGGU KE PERSENT
1 2 3 4 5 6 7 8 9 10 11 12 13 (%)
I PEKERJAAN PERSIAPAN 1.654 0.064 0.073 0.077 0.081 0.085 0.097 0.112 0.123 0.154 0.177 0.195 0.195 0.222 100 %
2 REHAB RUMAH DINAS 12.027 0.601 1.503 2.255 3.383 2.142 2.142
75 %
3 REHAB GEDUNG UTAMA 56.754 0.568 1.703 2.554 3.831 5.746 14.366 15.084 12.903
50 %
4 PEMASANGAN PAVING BLOK DAN PENATAAN TAMAN 17.408 0.870 1.871 2.152 2.475 2.846 6.119 1.074
RencanaKemajuan Fisik % 0.064 0.674 2.148 4.909 7.893 8.223 10.476 17.335 21.357 16.061 10.445 0.195 0.222
Rencana kumulatif Kemajuan Fisik 0.000 0.064 0.738 2.886 7.795 15.687 23.910 34.385 51.720 73.078 89.139 99.583 99.778 100.000 RENC
JULIZAR
Direktur