A. UPAH
1 Mandor Orang 170,000.00
2 Kepala Tukang Orang 175,000.00
3 Tukang Orang 165,000.00
4 Pekerja Orang 150,000.00
B. HARGA BAHAN
1 Air Liter 125.00
2 Batu Bata Buah 1,000.00
3 Batu Gunung/Batu Kali M3 250,000.00
4 Besi Beton Polos Kg 17,000.00
5 Besi Beton Uir Kg 25,000.00
6 Bubungan Genteng M1 60,000.00
7 Bubungan SENG M 1
55,000.00
8 Cat Dasar tembok/Sealer Setara Vinilex Kg 40,000.00
9 Cat Kayu Dasar Kg 45,000.00
10 Cat Kayu Mengkilat Kg 60,000.00
11 Cat Menie Besi Kg 40,000.00
12 Cat tembok Setara Vinilex Kg 50,000.00
13 Dempul Kayu Kg 18,000.00
14 Dolken Kayu Ø 8-10/400 cm Batang 75,000.00
15 Dool Holder Pasang 135,000.00
16 Engsel Jendela Pasang 25,000.00
17 Engsel Pintu Pasang 30,000.00
18 Floor Drain Buah 27,000.00
19 Gypsum Board tebal 9 mm Lembar 125,000.00
20 Jaring Kawat Baja Kg 36,000.00
21 Hak Angin Pasang 18,000.00
22 Kaca Bening Uk. 2 mm M2 75,000.00
23 Kaca Bening Uk. 3 mm M 2
85,000.00
24 Kaca Bening Uk. 5 mm M 2
120,000.00
25 Kaca Rayband Uk. 3 mm M 2
130,000.00
26 Kaca Rayband Uk. 5 mm M 2
135,000.00
27 Kaso-kaso (5 x 7) cm M 3
3,500,000.00
28 Kawat Beton Kg 25,000.00
29 Kawat Duri Kg 50,000.00
30 Kawat Harmonika M2 60,000.00
31 Kawat Nyamuk / Kasa Logam M 2
40,000.00
32 Kawat Nyamuk / Kasa Plastik M 2
30,000.00
33 Kayu Bakau 10 cm Batang 60,000.00
34 Kayu Klas I ( Seumantok / Ulim / dll ) M3 5,500,000.00
35 Kayu Klas II ( Kamper / Kruing / dll ) M3 4,800,000.00
36 Kayu Klas III ( Borneo / dll ) M 3
3,900,000.00
37 Kayu Klas IV ( Sengon / dll ) M3 3,750,000.00
38 Keramik Non Pholised 20 x 20 cm Setara Ikad Buah 3,000.00
39 Keramik UK. 20 x 25 cm Buah 3,500.00
40 Keramik UK. 40 x 40 cm Buah 12,000.00
41 Keramik UK. 20 x 25 cm Buah 3,500.00
42 Keramik UK. 30 x 30 cm Buah 6,200.00
43 Kertas Amplas Lembar 3,000.00
44 Kloset Duduk Keramik Setara toto + tabung Buah 1,500,000.00
45 Kloset Jongkok Keramik Setara toto Buah 350,000.00
46 Kran Air 3/4" Buah 10,000.00
47 Kuas Cat Buah 15,000.00
48 Kunci Pintu ( Standar ) Buah 150,000.00
49 Kunci Pintu Biasa Buah 100,000.00
50 Lampu Hemat Energi 11 Watt setara Hannochs Buah 35,000.00
51 Lampu Hemat Energi 18 Watt setara Hannochs Buah 40,000.00
52 Lampu Hemat Energi 11 Watt setara Hannochs Buah 45,000.00
53 Lem Kayu Kg 18,000.00
54 List Eternit Kayu M1 8,000.00
55 Marmer M 2
50,000.00
56 Minyak Cat Liter 25,000.00
57 Minyak Bekisting Liter 5,000.00
58 Multipleks 3 mm Lembar 70,000.00
59 Multipleks 4 mm Lembar 75,000.00
60 Multipleks 6 mm Lembar 125,000.00
61 Multipleks 9 mm Lembar 155,000.00
62 Pacok Jendela dan Ventilasi Pasang 7,500.00
63 Paku Asbes Kg 20,000.00
64 Paku Beton 8 inci Kotak 19,000.00
65 Paku Kait Buah 1,000.00
66 Paku Kayu Kg 18,000.00
67 Paku Triplek Kg 19,000.00
68 Paku Seng Kg 20,000.00
69 Paku Sumbat Buah 1,200.00
70 Paku Sekrup Kg 23,000.00
71 Kerikil M3 200,000.00
72 Pasir Beton M 3
250,000.00
73 Pasir Pasang M 3
190,000.00
74 Pasir Urug M 3
150,000.00
75 Pelumas / Oil Liter 40,000.00
76 Pipa Leading Ø 1" Galvanis Tebal 3,2 mm Batang 75,000.00
77 Pipa Leading Ø 2" Galvanis Tebal 3,2 mm Batang 85,000.00
78 Pipa Leading Ø 3" Galvanis Tebal 3,2 mm Batang 90,000.00
79 Pipa PVC Ø 1" Batang 40,000.00
80 Pipa PVC Ø 2" Batang 50,000.00
81 Pipa PVC Ø 3" Batang 60,000.00
82 Plamur Tembok Kg 30,000.00
83 Plin Keramik Buah 5,000.00
84 Plywood tebal 9 mm Lembar 150,000.00
85 Pemasangan Atap Baja Ringan M2 350,000.00
86 Residu Kg 10,000.00
87 Reservoir Air 500 ltr Buah 2,500,000.00
88 Reservoir Air 1000 ltr Buah 4,000,000.00
89 Reservoir Air 500 ltr Stainless Steel Buah 2,000,000.00
90 Schakelar Buah 12,500.00
91 Semen @ 40 Kg Zak 55,000.00
92 Semen @ 40 Kg Kg 1,375.00
93 Semen Putih @ 50 Kg Zak 220,000.00
94 Semen Putih @ 50 Kg Kg 4,400.00
95 Semen Warna Kg 7,500.00
96 Seng Genteng Metal M2 75,000.00
97 Seng BJLS 0,20 Cat Pabrik M 2
70,000.00
98 Seng Gelombang BJLS 30 M 2
50,000.00
99 Seng Gelombnag 30 Cat Pabrik M 2
55,000.00
100 Seng Plat BJLS 20 M 2
60,000.00
101 Seng Plat BJLS 30 M 2
65,000.00
102 Solar ( Industri ) Liter 12,500.00
103 Sekrup Fixer Buah 500.00
104 Sealant Kg 15,500.00
105 Sumur + Pompa Tangan Terpasang Unit 2,000,000.00
106 Tanah Timbun M3 75,000.00
107 Tiang Pancang M 1
300,000.00
108 Teralis Besi M 2
380,000.00
109 Titik Lampu + Instalasi Titik 150,000.00
110 Urinoir Keramik Unit 2,500,000.00
111 Vinyl M2 25,000.00
112 WireMesh ( Ulir ) Kg 175,000.00
113 Zakering ( Kast Lokal 1 Zekering ) Unit 350,000.00
114 Besi Strip tebal 15 mm Kg 15,000.00
115 Jendela UPVC M2 120,000.00
C. ALAT
1 Stamper Hari-Sewa 50,000.00
2 Dump Tuck Jam 200,000.00
3 Molen Jam 100,000.00
Catatan : bila bahan tidak tercantun di tabel ini boleh ditambah
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Beton Mutu F'c = 7,4 Mpa (K 100), Slump (12 + 2) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.1
Jenis Pekerjaan : Membuat Beton Mutu F'c = 9,8 Mpa (K 125), Slump (12 + 2) cm, W/c = 0,78
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.2
Jenis Pekerjaan : Membuat Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 + 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jenis Pekerjaan : Membuat Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 + 2) cm, W/c = 0,61
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.6
Jenis Pekerjaan : Membuat Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 + 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
Jenis Pekerjaan : Membuat Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 + 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Membuat Beton Mutu F'c = 24,0 Mpa (K 275), Slump (12 + 2) cm, W/c = 0,53
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Membuat Beton Mutu F'c = 26,4 Mpa (K 300), Slump (12 + 2) cm, W/c = 0,52
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Memasang Listplank Uk. 2,5 x 20 Cm Kayu Kelas I atau Kelas II
Satuan / Unit : M1
Analisa : AHSP PU A.4.6.1.21
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 2 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.7
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.8
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.10
Jenis Pekerjaan : Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 4 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
Jenis Pekerjaan : Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas I
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.1
Jenis Pekerjaan : Membuat dan Memasang Daun Pintu Panel Kayu Kelas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.5
A. Pembersian Lapangan
Lebar = 18 m
Panjang = 14 m
Luas = (PxL)
= 14 x 18 252 M²
B. Pemasangan Bouwplank
Lebar = 16 m LOKASI 1400
Panjang = 12 m
PEMBANGUNAN
Keliling = 2x(P+L)
= 2 x ( 12 + 16 ) 56 M¹
1600
LOKASI 1200
PEMBANGUNAN
NO PERHITUNGAN VOLUME SAT
Ø 8 - 10
TIANG 30/30
± 0.00 ± 0.00
0.07
0.15
0.60
0.38 SLOOF 25/40
MT.a
0.000 M³
1.80
0.000 M³ 1.95
Ø 14 - 15
1.c Alas Pasir Pondasi Tapak
Tinggi = 0.05 m
Lebar = 1.4 m 0.10
Panjang = 1.4 m 0.25
Jumlah = 22 Unit
0.10
0.05
Volume = ( P x L x T ) x Unit
= ( 1,4 x 1,4 x 0,05 ) x 22 Unit 2.156 M³ 0.10 1.20 0.10
1.d Aastamping
Tinggi = 0.1 m
Lebar = 1.4 m
Panjang = 1.4 m
Jumlah = 22 unit
1.20
Volume = ( P x L x T ) Unit
= (1,4 x 1,4 x 0,1) x 22 4.312 M³
Tinggi = 0.25 m
1.20 0.30
Lebar = 1.4 m 0.10
Panjang = 1.4 m 0.25
Jumlah = 22 Unit
Ø 14 - 15 1.20
1 4 - 15
1.20 0.30
0.10
0.25
Ø 14 - 15 1.20
Volume = ( P x L x T ) x Unit
= ( 1,4 x 1,4 x 0,25 ) x 22 Unit 10.780 M³
Ø 8 - 10
2.c Alas Pasir Pondasi Tapak
Tinggi = 0.05 m
Lebar = 1.2 m
Panjang = 1.2 m ± 0.00 ± 0.00
Jumlah = 6 Unit 0.07
0.15
2.d Aastamping
Tinggi = 0.1 m
Lebar = 1.2 m
1.80
1.95
0.38 SLOOF 25/40
MT.a
Panjang = 1.2 m
Jumlah = 6 unit 1.80
1.95
Ø 14 - 15
Volume = ( P x L x T ) Unit
= (1,2 x 1,2 x 0,1) x 6 0.864 M³
0.10
0.25
0.10
0.05
Tinggi = 0.25 m
Lebar = 1.2 m 1.00
Panjang = 1.2 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit
0.30
= ( 1,2 x 1,2 x 0,25 ) x 6 Unit 2.160 M³
X X
Ø 14 - 15
2.f Stick Kolom Pondasi Tapak (B)
1.00 0.30
Tinggi = 1.8
Lebar = 0.3
Panjang = 0.3 Ø 14 - 15
Jumlah = 6
Volume = ( P x L X T ) x Unit
= ( 0,3 x 0,3 x 1,8 ) x 6 Unit 0.972 M³
0.10
0.25
1.00
Ø 8 - 10
SLOOF 25/40
SLOOF 25/40
1.80
Ø 14 - 15
0.10
0.25
NO PERHITUNGAN VOLUME SAT
1.00
Volume = (P x L x T )
= ( 29,4 x 0,8 x 0,7 ) 16.464 M³ 480 600
2.d. Alas Pasir Pondasi Menerus 100 200 200 200 200
Tinggi = 0.05 m 1400
Lebar = 0.8 m
Panjang = 90 m
Volume = (PxLxT)
= ( 90 x 0,9 x 0,05 ) 3.600 M³ - 0.05 25
4
2.e. Aanstamping 3
15
60
37
- 0.05 25
4
3
15
Tinggi = 0.1 m
Lebar = 0.9 m 60
Panjang = 90 m 37
Volume = (PxLxT)
= ( 90 x 0,9 x 0,1) 8.100 M³ Angker Ø 10 - 100
55 Tanah urug
Aanstamping
10
Pas ir alas
5
30
60
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 90 x 0,7) 26.775 M³
NO PERHITUNGAN VOLUME SAT
Volume = (PxLxT)
200 300 300 300 300
= (28 x 0,25 x 0,4 ) 2.800 M³
SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
b. vertikal
Tinggi = 0.4 m
Lebar = 0.25 m
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
Panjang = 24 m
300
Volume = (PxLxT)
= (24 x 0,25 x 0,4 ) 2.400 M³ SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
= ( 2,800 + 2,400 ) 5.200 M³
300
1.b sloof gantung 25 / 40
a. Horizontal SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
Tinggi = 0.4 m
Lebar = 0.25 m
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
Panjang = 28 m 200
SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
SL 25/40
200
SL 25/40 SL 25/40 SL 25/40 SL 25/40 SL 25/40
Volume = (PxLxT)
= (28 x 0,25 x 0,4 ) 2.800 M³
b. vertikal
Tinggi = 0.4 m
Lebar = 0.25 m
Panjang = 24 m TYPE - TYPE SLOOF (SL)
25 25
LEGENDA
POT 3 - 3 POT 3' - 3'
SELIMUT BETON 40 MM 40 MM
BESI ATAS 2 Ø 14 3 Ø 14
NO PERHITUNGAN VOLUME SAT BESI TENGAH 2Ø 12 2Ø 12
BESI BAWAH 3 Ø 14 2 Ø 14
Tinggi = 3.70 m
Lebar = 0.3 m
Panjang = 0.3 m
Unit = 16 Unit
Volume = ( P x L x T ) x Unit
= ( 0,3 x 0,3 x 3,70 ) x 16 5.328 M³
200
300
200
Volume = ( P x L x T ) x unit
= (0,20 x 0,25 x 3,7 ) x 6 1.110 M³
KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20
2.d Kolom 25/20 Lantai 2
Tinggi = 3.7 m
Lebar = 0.25 m 200 300 300 300 300
Panjang = 0.20 m
Unit = 6 unit
KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30
Volume = ( P x L x T ) x unit
= (0,20 x 0,25 x 3,7 ) x 6 1.110 M³ 300
300
3.e Balok Latai 11/13 Lantai 1 dan 2 KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20
Volume = (PxLxT)
= (104 x 0,13 x 0,15 ) 1.487 M³
TYPE KLM (K1) LT 1 30X30 KLM (K1) LT 2 30X30 KLM TERAS(K2) 30X30
30 30 20
30 30 25
LEGENDA
POT 1 - 1 POT 2 - 2 POT 2' - 2'
SELIMUT BETON 40 MM 40 MM 40 MM
TULANGAN POKOK 8 Ø 14 8 Ø 14 6 Ø 12
PENGIKAT - - -
TULANGAN POKOK 8 Ø 14 8 Ø 14 6 Ø 12
PENGIKAT - - -
300
300
200
13
11
Volume = (PxLxT)
= ( 54x 0,25 x 0,35 ) 4.725 M³
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
= ( 4,725 + 4,200 ) 8.925 M³
300
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
300
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
300
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
200
BL 25/35 BL 25/35 BL 25/35 BL 25/35 BL 25/35
TYPE BALOK 25 X 35
TUMPUAN LAPANGAN
35 35
25 25
LEGENDA
POT 6 - 6 POT 6' - 6'
NO PERHITUNGAN VOLUME SAT SELIMUT BETON 30 MM 30 MM
BESI ATAS 3 Ø 14 2 Ø 14
BESI TENGAH 4Ø 12 4Ø 12
5.a Plat Lantai BESI BAWAH 2 Ø 14 3 Ø 14
Volume = (P x L x T) x Ruang
= ( 2,75 x 2,75 x 0,12 ) x 8 7.260 M³
Ruas B
Tinggi = 0.12 m²
Lebar = 2.75 m²
Panjang = 1.75 m
Jumlah = 4 Ruang 1400
Volume = (P x L x T) x Ruang
A
300
1400
Ruas C 300
Tinggi = 0.12 m²
Ø 10 - 20
Ø 10 - 20
Ø 10 - 20
Ø 10 - 20
Lebar = 1.75 m²
Panjang = 1.75 m B Ø 10 - 20
600
Jumlah = 1 Ruang
300 Ø 10 - 20
Ø 10 - 20
Ø 10 - 20
Volume = (P x L x T) x Ruang Ø 10 - 20
1 2 3 4 5 6
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
300
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
300
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
200
RB 20/25 RB 20/25 RB 20/25 RB 20/25 RB 20/25
TUMPUAN LAPANGAN
25 25
240
830
50
20
NO PERHITUNGAN VOLUME SATUAN
Volume = ( P x L x T ) x Unit
= ( 7,40 x 0,06 x 0,15 ) x 2 Unit 0.133 M³
Luas = ( P x L ) Unit
= ( 2,1 x 0,90 ) x 2 Unit 3.780 M²
PINTU PANEL
Volume = ( P x L x T ) x Unit
( 8,40 x 0,06 x 0,15 ) x 2 Unit 0.151 M³ 210
Volume = (PxLxT)
POT. B-B
POT. A-A 5 90 5
Kaca Jendela J1
Panjang = 0.86 m
Lebar = 0.36 m
Jumlah = 2
Kaca Jendela J2
Panjang = 0.56 m
Lebar = 0.64 m
Jumlah = 2
B
Luas Kaca Jendela J2 untuk (1 Unit)
= (PxL)x2
= ( 0,56 x 0,64 ) x 2 0.717 M²
5
A
Luas Kaca Jendela J2 untuk (4 Unit)
= Luas Kaca J1 ( 1 Unit) x 4 unit KACA 5 MM KACA 5 MM 50
= 10,717 x 4 Unit 2.867 M²
KACA 5 MM KACA 5 MM
86 100
5
36
50 POT. B-B
KACA 5 MM KACA 5 MM
86 100
Volume = ( P x L x T )x 2
= ( 2,48 x 0,06 x 0,13) x 2 0.039 M³
Kaca Jendela J3
Panjang = 0.5 m
Lebar = 0.5 m
Jumlah = 2
5
A
KACA 5 MM KACA 5 MM KACA 5 MM 50
5
36
KACA 5 MM KACA 5 MM KACA 5 MM
86 100
= PxLxU 21 M²
DETAIL J 2 = 6 UNIT
Ventilasi
Skala 1 : 20
Panjang = 0.65 m
Lebar = 1.20 m
Jumlah = 14 Unit
= PxLxU 10.920 M²
= PxLxU 3 M²
Ventilasi
Panjang = 0.65 m
Lebar = 0.60 m
Jumlah = 4 Unit
= PxLxU 1.560 M²
= PxT 48 M²
= PxLxU 6.24 M²
= PxT 418.900 M²
= PxT 34.88 M²
= PxLxU 14.1 M²
Ventilasi
Panjang = 0.30 m
Lebar = 0.90 m
Jumlah = 6 Unit
= PxLxU 1.620 M²
= PxLxU 9 M²
NO PERHITUNGAN VOLUME SATUAN
Ventilasi
Panjang = 0.65 m
Lebar = 1.20 m
Jumlah = 6 Unit
= PxLxU 4.680 M²
= PxLxU 3.75 M²
Ventilasi
Panjang = 0.65 m
Lebar = 0.60 m
Jumlah = 5 Unit
= PxLxU 1.950 M²
= PxLxU 1.56 M²
Ventilasi
Panjang = 0.5 m
Lebar = 0.2 m
Jumlah = 10 Unit
= (PxL)U
= ( 0,5 x 0,2 ) x 10 1.000 M²
Luas = P x L x Sisi
= 3,84 x 0,30 x 24 Sisi M²
Luas = PxL
= 90 x 0,4
Luas = P x L x Sisi
= 3,25 x 0,30 x 54 Sisi 52.65 M²
Luas = P x L x Sisi
= 3,25 x 0,4 x 17 Sisi 22.10 M²
Volume = ( P x L x T ) x Unit
= ( 6,75 x 0,06 x 0,15 ) x 3 Unit 0.182 M³
Luas = ( P x L ) Unit
= ( 2,35 x 1,85 ) x 3 Unit 13.043 M²
3.A Tipe P2
Tinggi = 0.15 m
Lebar = 0.06 m
Panjang = 5 m
Jumlah = 13 Unit
Volume = ( P x L x T ) x Unit
= ( 5 x 0,06 x 0,15 ) x 13 Unit 0.585 M³
Luas = ( P x L ) Unit
= ( 1,95 x 0,90 ) x 13 Unit 22.815 M²
5.A Tipe P3
Tinggi = 0.15 m
Lebar = 0.06 m
Panjang = 4.8 m
Jumlah = 6 Unit
Volume = ( P x L x T ) x Unit
= ( 4,8 x 0,06 x 0,15 ) x 6 Unit 0.259 M³
Luas = ( P x L ) Unit
= ( 1,95 x 0,80 ) x 6 Unit 9.360 M²
Volume = ( P x L x T ) x Unit
( 11,9 x 0,06 x 0,13) x 12 Unit 1.114 M³
2.b Daun Jendela J1
Panjang = 2.4 m
Lebar = 0.1 m
Jumlah = 3
Volume
= ( P x L ) Unit
= (0,45 x 0,13 ) x 27 Unit 1.580 M²
Volume = ( P x L x T ) x Unit
= ( 8,4 x 0,06 x 0,13) x 4 Unit 0.131 M³
Volume = ( P x L x T )x 2
= ( 2,48 x 0,06 x 0,13) x 2 0.039 M³
Kaca Jendela J3
Panjang = 0.5 m
Lebar = 0.5 m
Jumlah = 2
Volume = (PxLxT)
= ( 17,75 x 6,50 x 0,50) 57.688 M³
Volume = (PxLxT)
= ( 17,75 x 1,74 x 0,44) 13.589 M³
Vol.Total Timbunan
= (A+B)
= ( 57,69 + 13,59 ) 71.277 M³
Volume = (PxLxT)
= ( 17,75 x 8,24 x 0,10) 14.626 M³
Volume = (PxLxT)
= ( 17,75 x 8,24 x 0,04) 5.850 M³
Volume = (PxL )
= ( 18,81 x 8,7 ) 103 M²
Volume = (PxL )
= ( 21,30 x 11,30 ) 241 M²
Volume = (PxL )
= ( 21,30 x 11,30 ) 241 M²
Volume = (p x L x T)
= (21,25 x 1,15 x 0,25) 6.109 M³
Volume = (P x L x T)
= (5,34 x 0,90 x 0,05) 0.240 M³
Volume = (P x L x T)
= (5,34 x 0,90 x 0,15) 0.721 M³
Volume = (P x L)
= ( 5,34 x 0,40 ) 2.136 M³
Volume = (P x L)
= ( 5,34 x 0,55 ) 2.937 M³
Volume = (P x L x T)
= (5,34 x 0,17 x 0,15) 0.136 M³
Volume = (P x L x T)
= (5,34 x 0,17 x 0,30) 0.272 M³
Volume = (P x L x T)
= (5,34 x 0,17 x 0,10) 0.091 M³
Volume = (P x L x T)
= (5,34 x 0,17 x 0,10) 0.091 M³
Volume = (P x L x T)
= (5,34 x 0,17 x 0,10) 0.091 M³
Volume = (PxLxT)
= ( 5,34 x 0,35 x 0,05) 0.093 M³
NO PERHITUNGAN VOLUME SATUAN
9. PEKERJAAN PENGECETAN
9.a Cat Pada Dinding/Tembok
Lantai 1
Luas Total Plsteran Dinding Trasram 1 : 2
= 0.270 m 0.270 M²
Lantai 2
Luas Total Plsteran Dinding Bata 1 : 4
= 2 x ( Luas Total Plasteran 1:4 )
= 0.00 m 0.00 M²
Luas = (P x L)
= ( 38,85 x 0,13) 4.055 M²
Luas = (P x L)
= ( 38,85 x 0,06) x 2 3.743 M²
Luas = (P x L)
= ( 9,00 x 2) 14.420 M²
3 Sakelar Ganda 3 Bh
4 Sakelar Tunggal 6 Bh
5 Stop Kontak 4 Bh
2. Kunci Tanam
Jumlah = 1
Jumlah Unit = 4 unit
Jumlah Total = ( Jumlah x Jumlah Unit )
= ( 1 x 4 Unit ) 4 Bh
3 Tipe Jendela ( J1 )
Engsel
Jumlah = 6
Jumlah Unit = 12 unit
4 Hak angin
Jumlah = 3
Jumlah Unit = 12 unit
5 Pacok Jendela
Jumlah = 3
Jumlah Unit = 12 unit
1 Tipe Jendela ( J2 )
Engsel
Jumlah = 4
Jumlah Unit = 4 unit
2 Hak angin
Jumlah = 4
Jumlah Unit = 4 unit
Jumlah Total = ( Jumlah x Jumlah Unit )
= ( 4 x 4 Unit ) 16 Bh
3 Tarikan Jendela
Jumlah = 2
Jumlah Unit = 4 unit
1. PEKERJAAN PERSIAPAN
Luas = (PxL)
= 18,65 x 17,30 323 M² LOKASI
1730
PEMBANGUNAN
B. Pemasangan Bouwplank
Lebar = 14.30 m
Panjang = 17.65 m
1765
Keliling = 2x(P+L)
= 2 x ( 17,65 + 14,30 ) 64 M¹
LOKASI
1430
PEMBANGUNAN
No. PERHITUNGAN VOL SAT GAMBAR
2. PEKERJAAN TANAH
Volume = ( P x L x T ) x Unit
= ( 1,2 x 1,2 x 1,5 ) x 22 Unit 47.52 M³
Volume = ( P x L x T ) x Unit
= ( 1,2 x 1,2 x 0,10 ) x 22 Unit 3.17 M³
1.d Aastamping
Tinggi = 0.5 m
Lebar = 1.2 m
Panjang = 1.2 m
Jumlah = 22 unit
Volume = ( P x L x T ) Unit
= (1,2 x 1,2 x 0,5) x 22 Unit 15.84 M³
Volume = ( P x L x T ) x Unit
= ( 1,2 x 1,2 x 0,30 ) x 22 Unit 9.50 M³
Volume = ( P x L X T ) x Unit
= ( 0,4 x 0,4 x 1,05 ) x 22 Unit 3.70 M³
2 Pondasi Menerus
2.a Galian Pondasi Menerus A
Pondasi Horizontal
Tinggi = 0.7 m
Lebar = 0.8 m
Panjang = 29.8 m
Volume = (P x L x T )
= ( 29,8 x 0,8 x 0,7 ) 16.69 M³
Pondasi Vertikal
Tinggi = 0.7 m
Lebar = 0.8 m
Panjang = 61 m
Volume = (P x L x T )
= ( 61 x 0,8 x 0,7 ) 34.16 M³
Volume = (PxLxT)
= ( 90,8 x 0,8 x 0,05 ) 3.63 M³
2.d Aanstamping A
Tinggi = 0.1 m
Lebar = 0.8 m
Panjang = 90.8 m
Volume = (PxLxT)
= ( 90,8x 0,8 x 0,1) 7.26 M³
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 90,8 x 0,65) 34.45 M³
3.a Galian Pondasi Menerus B
Pondasi Horizontal
Tinggi = 0.7 m
Lebar = 0.8 m
Panjang = 13.06 m
Volume = (P x L x T )
= ( 13,06 x 0,8 x 0,7 ) 7.31 M³
Pondasi Vertikal
Tinggi = 0.7 m
Lebar = 0.8 m
Panjang = 6.65 m
Volume = (P x L x T )
= ( 6,65 x 0,8 x 0,7 ) 3.72 M³
Volume = (PxLxT)
= ( 19,71 x 0,8 x 0,05 ) 0.79 M³
3.d Aanstamping B
Tinggi = 0.1 m
Lebar = 0.8 m
Panjang = 19.71 m
Volume = (PxLxT)
= ( 19,71 x 0,8 x 0,1) 1.58 M³
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 19,71 x 0,65) 5.44 M³
Volume = (P X L X T) 1.76 M³
Anak Tangga 2
Tinggi = 0.55 m
Lebar = 0.80 m
Panjang = 1.12 m
Volume = (P X L X T) 0.49 M³
Volume = (P X L X T) 1.58 M³
Anak Tangga 2
Tinggi = 0.55 m
Lebar = 0.80 m
Panjang = 0.96 m
Volume = (P X L X T) 0.42 M³
Anak Tangga 2
Tinggi = 0.05 m
Lebar = 0.80 m
Panjang = 1.12 m
Volume = (P X L X T) 0.04 M³
Volume = (P X L X T) 0.14 M³
Anak Tangga 2
Tinggi = 0.05 m
Lebar = 0.80 m
Panjang = 0.96 m
Volume = (P X L X T) 0.04 M³
Volume = (PxLxT)
= (29,95 x 0,3 x 0,5) 4.49 M³
b. vertikal
Tinggi = 0.5 m
Lebar = 0.3 m
Panjang = 61.55 m
Volume = (PxLxT)
= (61,55 x 0,3 x 0,5 ) 9.23 M³
Volume = (PxLxT)
= (60,2 x 0,15 x 0,25 ) 2.258 M³
b. vertikal
Tinggi = 0.25 m
Lebar = 0.15 m
Panjang = 61 m
Volume = (PxLxT)
= (61 x 0,15 x 0,25 ) 2.288 M³
Tinggi = 3.85 m
Lebar = 0.4 m
Panjang = 0.4 m
Unit = 22 Unit
Volume = ( P x L x T ) x Unit
= ( 0,4 x 0,4 x 3,85 ) x 22 13.552 M³
Tinggi = 4.10 m
Lebar = 0.4 m
Panjang = 0.4 m 200 300 300 300 300
Unit = 22 Unit
KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30
Tinggi = 3.85 m
KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30 KL 30/30
200
Lebar = 0.25 m
Panjang = 0.25 m
KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20 KL 25/20
KOLOM LANTAI 2
Unit = 1 unit
TYPE KLM (K1) LT 1 30X30 KLM (K1) LT 2 30X30 KLM TERAS(K2) 30X30
Volume = ( P x L x T ) x unit
= (0,20 x 0,25 x 3,7 ) x 6 0.24 M³
30 30 20
30 30 25
LEGENDA
POT 1 - 1 POT 2 - 2 POT 2' - 2'
SELIMUT BETON 40 MM 40 MM 40 MM
TULANGAN POKOK 8 Ø 14 8 Ø 14 6 Ø 12
3.b Kolom Sedang 25/25 Lantai 2 30 30 25
LEGENDA
POT 1 - 1 POT 2 - 2 POT 2' - 2'
Tinggi = 4.10 m SELIMUT BETON 40 MM 40 MM 40 MM
BEUGEL TUMPUAN
8 Ø 14
Ø 10 - 100
8 Ø 14
Ø 10 - 100
6 Ø 12
Ø 10 - 100
Unit = 1 unit - - -
PENGIKAT
300
4.a Kolom Praktis 13/13 Lantai 1
Volume = ( P x L x T ) x unit
= (0,13 x 0,13 x 3,85 ) x 12 0.78 M³
Tinggi = 4.10 m
Lebar = 0.13 m
Panjang = 0.13 m
Unit = 12.00 unit
Volume = ( P x L x T ) x unit
= (0,13 x 0,13 x 4,1 ) x 12 0.83 M³
5. Balok Latai
Volume = (PxLxT)
TYPE
= (15,2 x 0,13 x 0,15 ) 0.30 M³ BALOK LATAI 11X13
Tinggi = 0.15 m 13
Lebar = 0.13 m 11
Panjang = 11.2 m
LEGENDA POT 5 - 5
Volume = (PxLxT)
SELIMUT BETON 30 MM
BESI ATAS 2Ø 10
= (11,2x 0,13 x 0,15 ) 0.22 M³ BESI TENGAH 2Ø 10
BESI BAWAH -
Tinggi = 0.15 m
Lebar = 0.13 m
Panjang = 3.00 m
Volume = (PxLxT)
= (3,0x 0,13 x 0,15 ) 0.06 M³
Tinggi = 0.15 m
Lebar = 0.13 m
Panjang = 42.40 m
Volume = (PxLxT)
= (3,0x 0,13 x 0,15 ) 0.83 M³
No. PERHITUNGAN VOL SAT GAMBAR
Lebar = 0.25 m
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
Panjang = 60.2 m 300
Volume = (PxLxT)
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
= ( 60,2x 0,25 x 0,40 ) 6.020 M³ 300
Vertikal
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
BL 25/35
200
Tinggi = 0.40 m BL 25/35 BL 25/35 BL 25/35 BL 25/35 BL 25/35
Lebar = 0.25 m
TYPE BALOK 25 X 35
Panjang = 61 m
TUMPUAN LAPANGAN
Volume = (PxLxT)
= ( 61 x 0,25 x 0,40 ) 6.100 M³ 35 35
BESI ATAS 3 Ø 14 2 Ø 14
BESI TENGAH 4Ø 12 4Ø 12
Volume = (PxLxT)
= ( 4,00x 0,25 x 0,40 ) 0.130 M³
Vertikal
Tinggi = 0.25 m
Lebar = 0.13 m
Panjang = 2.30 m
Volume = (PxLxT)
= ( 2,30 x 0,25 x 0,40 ) 0.075 M³
Ruas A
Tinggi = 0.12 m²
Lebar = 3.25 m 1400
Panjang = 3.35 m A
Ø 10 - 20
Ø 10 - 20
Ø 10 - 20
Ø 10 - 20
B Ø 10 - 20
600
Ø 10 - 20
Ø 10 - 20
= ( 3,35 x 3,25 x 0,12 ) x 6 7.84 M³
Ø 10 - 20
C
Ø 10 - 20
Ø 10 - 20
200 200
Ø 10 - 20
D
Ruas B
Tinggi = 0.12 m² 200 300 300 300 300
Lebar = 3.25 m
1 2 3 4 5 6
Panjang = 3.75 m
Jumlah = 3 Ruang
Volume = (P x L x T) x Ruang
= ( 3,75 x 3,25 x 0,12 ) x 3 4.39 M³
Ruas C
Tinggi = 0.12 m²
Lebar = 2.75 m
Panjang = 3.35 m
Jumlah = 2 Ruang
Volume = (P x L x T) x Ruang
= ( 3,35 x 2,75 x 0,12 ) x 2 2.21 M³
Ruas D
Tinggi = 0.12 m²
Lebar = 2.75 m
Panjang = 3.75 m
Jumlah = 1 Ruang
Volume = (P x L x T) x Ruang
= ( 3,35 x 2,75 x 0,12 ) x 2 1.24 M³
Ruas E
Tinggi = 0.12 m
Lebar a = 0.75 m
Lebar b = 1.35 m
Panjang = 3.5 m
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 19,71 x 0,65) 0.44 M³
Ruas F
Tinggi = 0.12 m
Lebar a = 1.10 m
Lebar b = 1.85 m
Panjang = 3.5 m
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 19,71 x 0,65) 0.62 M³
Ruas G
Tinggi = 0.12 m²
Lebar = 1.15 m
Panjang = 4.00 m
Jumlah = 1 Ruang
Volume = (P x L x T) x Ruang
= ( 3,35 x 2,75 x 0,12 ) x 2 0.55 M³
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 19,71 x 0,65) 0.44 M³
Ruas B
Tinggi = 0.12 m
Lebar a = 1.10 m
Lebar b = 1.85 m
Panjang = 3.5 m
Volume = (( a + b )/2 x P x T ))
= (( 0,25 + 0,6)/2 x 19,71 x 0,65) 0.62 M³
Lebar = 0.25 m
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
300
Panjang = 4.2 m
Volume = (PxLxT) RB 20/25 RB 20/25 RB 20/25 RB 20/25 RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
300
Tinggi = 0.30 m
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
RB 20/25
200
Panjang = 14 m
Volume = (PxLxT)
= ( 14 x 0,25 x 0,30 ) 1.050 M³ TYPE - TYPE RING BALK
TYPE RING BALK 20 X 25
= (Horizontal + Vertikal )
= (0,315 + 1,050) 1.365 M³
25 25
20 20
LEGENDA
POT 4 - 4 POT 4' - 4'
8.b Ring Balok 20/30 EL. +7.95 SELIMUT BETON 30 MM 30 MM
BESI TENGAH
3 Ø 12
2 Ø 12
2 Ø 12
2 Ø 12
Panjang = 56 m
Volume = (PxLxT)
= ( 56 x 0,20 x 0,30 ) 3.360 M³
1
4. PEKERJAAN TANGGA 200
KOLOM 30/30
+ 2.55
130
RELING
14 15
13 16
12 17
11
10
390
7
30
2
30
1
30
0
- 0.05 1
N
91
169
+ 4.00
PLAFOND TRIPLEKS 3 MM
+ 2.55
20
18 BESI 4
KAYU 8/8
BESI 4
BESI 4
PAPAN 2/20
PAS. 1/2 BATA
RABATA BETON
BESI 4
BESI 4
PAPAN 2/20
PAS. 1/2 BATA
RABATA BETON
50
100
SLOOF 25/40
100
10
25
5
38 18 38
93
536
POTONGAN 1 - 1
SKALA 1: 40
30 30
Ø 10 - 15
32 18
Ø 10 - 15
Ø 10 - 15
18
Ø 10 - 15
Volume = ( P x L x T)
= ( 4,68 x 0,9 x 0,12 ) 0.505 M³
No. PERHITUNGAN VOL SAT GAMBAR
20
Volume = ( P x L x T)
= ( 2,6 x 0,9 x 0,12 ) 0.281 M³
91
169
Panjang = 4.00 m
+ 4.00
PLAFOND TRIPLEKS 3 MM
Volume = (PxLxT) B
+ 2.55
20
BESI 4 18
18
KAYU 8/8
Tinggi = 0.12 m
BESI 4
BESI 4
PAS. 1/2 BATA
PAPAN 2/20 BESI 4
= 1.3
81
m
RABATA BETON
Lebar - 0.05
PASIR URUG
TANAH URUG
PAS. TRASRAM 1 : 2
Panjang = 2.0 m
50
SLOOF 25/40
Volume = (PxLxT)
= ( 2,0 x 1,3 x 0, 12 ) 0.312 M³
536
Lebar = 0.3 m
30
Panjang = 0.9 m
Jumlah = 14 unit
Luas = ( 1/2 x T )x L 0.027 M²
30
Volume = (Luas Anak Tangga x P) x Unit 0.340 M³
Tinggi = 0.18 m
Ø 10 - 15
Lebar = 0.3 m Ø 10 - 15
Panjang = 0.9 m Ø 10 - 15 18
Jumlah = 9 unit
Luas = ( 1/2 x T )x L
= ( 1/2 x 0,18 )x0,3 0.027 M²
Ø 10 - 15
130
RELING
Luas Papan Ralling
= ( P x L ) Unit 14 15
= (2,6 x 0,2 ) x 1 Unit 0.520 M² 13 16
30
12 17
1.o Ralling Tangga
Panjang ralling A + Panjang ralling B
90
= 4,68 + 2,6 7.28 M
5. PEKERJAAN DINDING
= ( 24 + 26 ) x 3,39 180.0 M² 5
2.b Jendela J1
Lebar = 1.15 m PINTU PANEL
Unit = 2 Unit
Luas Jendela = ( P x L ) x Unit
= ( 1,65 x 1,15 ) x 2 3.795 M²
POT. B-B
2.c Jendela J2
Lebar = 1.70 m POT. A-A 5 90 5
Panjang = 1.65 m
DETAIL P1 = 4 UNIT
Unit = 6 unit Skala 1 : 20
Luas Jendela = ( P x L ) x Unit B
= ( 1,65 x 1,70 ) x 6 16.830 M²
5
A
2.d Pintu KACA 5 MM KACA 5 MM 50
Panjang = 2.70 m
5
Lebar = 1.00 m
Unit = 2 unit
Luas Pintu = ( P x L ) x Unit KACA 5 MM KACA 5 MM
86 100
Volume = (P+L)xT
= ( 24 + 26 ) x 3,7 185.0 M² KACA 5 MM KACA 5 MM KACA 5 MM
100
3.b Jendela J1 5
Lebar = 1.15 m POT. B-B
Panjang = 1.65 m
Unit = 2 Unit POT. A-A 5 50 5 50 5 50 5
80
3.c Jendela J2
Lebar = 1.70 m
Panjang = 1.65 m
Unit = 6 unit
Luas Jendela = ( P x L ) x Unit
= ( 1,65 x 1,70 ) x 6 16.830 M²
3.d Pintu
Panjang = 2.70 m
Lebar
Unit
=
=
1.00
2
m
unit 180
Luas Pintu = ( P x L ) x Unit
= ( 1,00 x 2,70 ) x 2 5.400 M²
Volume = ( P x L ) x unit
= ( 0,20 x 0,20 ) x 27 1.080 M²
5
Volume = ( P x L x T ) x Unit 0.2664 M³
Lebar = 0.15 m
Jumlah = 4 Unit POT. A-A 5 90 5
5
2.b Daun Jendela J1
Panjang = 1 m
Lebar = 0.5 m
KACA 5 MM KACA 5 MM
= 2 86 100
Jumlah
Panjang = 0.86 m
Lebar = 0.36 m
Jumlah = 2
Volume = ( P x L x T ) x Unit
( 11,70 x 0,06 x 0,15 ) x 12 Unit 1.264 M³ KACA 5 MM KACA 5 MM KACA 5 MM
100
POT. A-A 5 50 5 50 5 50 5
Luas Daun Jendela Untuk 1 Unit
= (PxL)x3
DETAIL J 2 = 12 UNIT
= ( 1 x 0,5 ) x 3 1.500 M²
Skala 1 : 20
Skala 1 : 20
Kaca Jendela J2
Panjang = 0.86 m
Lebar = 0.36 m
Jumlah = 3
7. PEKERJAAN LANTAI
Panjang = 16.20 m
BETON COR
PASIR URUG
TANAH URUG
- 0.05
Volume = (PxLxT) 4
3
15
= ( 16,20 x 5,40 x 0,37 ) 32.368 M³ 60
37
Volume = (PxLxT)
= ( 16,20 x 1,75 x 0,32) 9.072 M³
Vol.Total Timbunan
= (A+B)
- 0.05
= ( 32,368 + 9,072 ) 41.440 M³
Volume = (PxLxT)
= ( 16,20 x 7,15 x 0,15 ) 17.375 M³
3.a Beton Cor Bawah lantai
Tinggi = 0.03 m
Lebar = 7.15 m
Panjang = 16.20 m 185 578 578
Volume = (PxLxT)
= ( 16,20 x 7,15 x 0,03 ) 3.475 M³
KERAMIK 40/40 KERAMIK 40/40
0.00 0.00
570
Lebar = 7.78 m
KERAMIK 40/40
0.00 208
Luas = (PxL)
= ( 13,41 x 7,78 ) 104.3298 M²
DENAH KERAMIK LANTAI 1
4.b Lantai 2 ( Keramik 40 x 40 )
Panjang = 13.41 m
Lebar = 7.78 m 185 578 578
Void = 9.92 m
TURUN
KERAMIK 40/40
0.00 208
8. PEKERJAAN ATAP
Volume = (PxLxT)
110 110
= ( 5,93 x 16,25 x 2,00 ) 192.725 M³
Volume = (PxLxT)
= ( 5,93 x 16,25 x 2,00 ) 192.725 M³
20
3.a Rabung Seng Genteng
Panjang = 32.30 m 32.30 M¹
110
4.a Papan Lisplank
Panjang = 30.31 m
Lebar = 0.20 m
Keliling = 2x(P+L)
= 2 x (30,31 + 0,20) 61.02 M¹
No. PERHITUNGAN VOL SAT GAMBAR
9. PEKERJAAN PLAFOND
Lebar = 11.56 m
Panjang = 5.70 m
Volume = (PxL )
= ( 18,81 x 8,7 ) 65.89 M² DENAH PLAFOND LANTAI 1
Lebar = 13.41 m
Panjang = 7.78 m
Lantai 2
Luas Total Plsteran Dinding Bata 1 : 4
= 2 x ( Luas Total Plasteran 1:4 )
= 420.710 m 841.42 M²
Panjang = 8.40 m
Jumlah = 4 Unit POT. A-A 5 90 5
DETAIL P1 = 4 UNIT
Volume = ( P x L x T ) x Unit 0.3024 M³ Ska la 1 : 20
5
Volume = ( P x L x T ) x Unit
( 11,70 x 0,06 x 0,15 ) x 12 Unit 1.264 M³
KACA 5 MM KACA 5 MM KACA 5 MM
100
POT. B-B
5.b Daun Jendela J2
Panjang = 1 m 5
Lebar = 0.5 m POT. B-B
Jumlah = 3
POT. A-A 5 50 5 50 5 50 5
Luas Daun Jendela Untuk 1 Unit
= (PxL)x3 DETAIL J 2 = 12 UNIT
= ( 1 x 0,5 ) x 3 1.500 M² Ska la 1 : 20
Lantai 2
1 Bola Lampu Pijar 40 Watt 3 Bh
600
2 Bola Lampu TL 20 Watt 220 V 4 Bh
TURUN
3 Sakelar Ganda 1 Bh
200
4 Sakelar Tunggal 3 Bh
A. Tipe Pintu ( P1 )
1. Engsel
Jumlah = 3
Jumlah Unit = 4 unit
2. Kunci Tanam
Jumlah = 1
Jumlah Unit = 4 unit
B. Tipe Jendela ( J1 )
1. Engsel
Jumlah = 4
Jumlah Unit = 4 unit
2. Hak angin
Jumlah = 2
Jumlah Unit = 4 unit
3. Pacok Jendela
Jumlah = 2
Jumlah Unit = 4 unit
4. Tarikan Jendela
Jumlah = 2
Jumlah Unit = 4 unit
1 Tipe Jendela ( J2 )
Engsel
Jumlah = 6
Jumlah Unit = 12 unit
2 Hak angin
Jumlah = 3
Jumlah Unit = 12 unit
3. Pacok Jendela
Jumlah = 3
Jumlah Unit = 12 unit
4. Tarikan Jendela
Jumlah = 3
Jumlah Unit = 12 unit
TIME SCHEDULE
JANUARI'21 FEBRUARI'21 MARET'21 APRIL'21
NO PEKERJAAN HARGA BOBOT KETERANGAN
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16
1 2 3
Ø 8 - 10
2. Untuk Bidang 1.00 Meter
Panjang Besi (Pjb) = 1.20 M
TIANG 30/30
Jumlah Baris Besi (Jb) = 8.00 M
± 0.00 ± 0.00 Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 14.00 mm
SLOOF 25/40
MT.a Berat besi Ø 14, = Pjg*Jb*Jl*0.006162*d*d
= 11.594 Kg
0.10
Luas Bekisting Untuk 1 m3 Beton = 4.000 M2 / M3 Beton
0.25
1 2 3
Ø 8 - 150 = 30.40 kg
2 Ø 14 4. Papan mal =
=
Pjg balok untuk 1 m3 beton x luas permukaan papan
8.000 m2 -------> 50%
1 2 3
4 Ø 12
395 btg
1 2 3
Ø 10 - 150
30
Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2
2Ø 12 = 48.55 kg
3 Ø 14 4. Papan mal =
=
Pjg balok untuk 1 m3 beton x luas permukaan papan
13.33 m2 -------> 50%
1 2 3
20 Ø 10 - 150 Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2
3 Ø 12 = 61.96 kg
1 2 3
35 Ø8 - 150 = 31.90 kg
25
25
1 2 3
Ø8 - 150
= 57.66 kg
13
2Ø 10
4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan
= 8.88 m2 -------> 50%
11
11
1 2 3
1 2 3
25 2Ø 12 = 39.6533 kg
Ø 8 - 150 4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan
20
20
1 2 3
- = Pjg*Jb*Jl*0.006162*d*d
= 21.370 Kg
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
JUMLAH HARGA
No. URAIAN PEKERJAAN (Rp.)
LANTAI I
A PEKERJAAN PERSIAPAN 24,097,251.15
B PEKERJAAN TANAH GALIAN URUGAN DAN TIMBUNAN #NAME?
C PEKERJAAN BETON BERTULANG #NAME?
D PEKERJAAN TANGGA 15,882,964.99
E PEKERJAAN DINDING DAN PLASTERAN 71,759,446.49
F PEKERJAAN LANTAI 44,028,125.22
G PEKERJAAN PLAFOND 16,983,794.78
H PEKERJAAN PINTU DAN JENDELA 29,055,974.31
I PEKERJAAN ELEKTRIKAL 806,000.00
J PEKERJAAN PENGECATAN 13,860,165.72
K PEKERJAAN LAIN-LAIN 4,700,000.00
LANTAI II
A PEKERJAAN BETON BERTULANG 416,571,170.79
B PEKERJAAN DINDING DAN PLASTERAN 82,060,847.55
C PEKERJAAN LANTAI 29,719,198.31
D PEKERJAAN PLAFOND 49,396,057.23
E PEKERJAAN PINTU DAN JENDELA 29,055,974.31
F PEKERJAAN ATAP 106,878,986.46
G PEKERJAAN ELEKTRIKAL 721,000.00
H PEKERJAAN PENGECATAN 18,477,095.73
I PEKERJAAN LAIN-LAIN 3,000,000.00
TOTAL HARGA #NAME?
PPN 10% #NAME?
TOTA AKHIR #NAME?
DIBULATKAN 1,173,696,000.00
Terbilang : Satu Milyar Seratus Tujuh Puluh Tiga Juta Enam Ratus Sembilan Puluh Enam Ribu Rupiah
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME Analisa SATUAN HARGA
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan M2 322.65 AHSP PU A.2.2.1.9 25,850.00 8,340,373.25
2 Administrasi dan Dokumentasi ls 1.00 Taksir 700,000.00 700,000.00
3 Papan Nama Proyek ls 1.00 Taksir 500,000.00 500,000.00
4 Listrik Kerja ls 1.00 Taksir 3,500,000.00 3,500,000.00
5 Pengukuran dan Pemasangan Bowplank M1 63.90 AHSP PU A.2.2.1.4 118,261.00 7,556,877.90
6 Pengurusan Izin Mendirikan Bangunan (IMB) ls 1.00 Taksir 3,500,000.00 3,500,000.00
Sub Total 24,097,251.15
II PEKERJAAN TANAH, GALIAN, URUGAN DAN TIMBUNAN
A Pondasi Tapak A
1 Galian Tanah Sedalam 2 m (Pondasi Tapak) M3 47.52 AHSP PU A.2.3.1.8a 96,626.20 4,591,677.02
2 Urugan Tanah Kembali (Bekas Galian Pondasi) M3 35.64 AHSP PU A.2.3.1.9 56,827.10 2,025,317.84
3 Pasir Alas M3 3.17 AHSP PU A.2.3.1.11 249,370.00 790,004.16
4 Aanstamping M3 15.84 AHSP PU A.3.2.1.9 615,565.50 9,750,557.52
B Pondasi Tapak B
1 Galian Tanah Sedalam 2 m (Pondasi Tapak) M3 #NAME? AHSP PU A.2.3.1.8a 96,626.20 #NAME?
2 Urugan Tanah Kembali (Bekas Galian Pondasi) M3 #NAME? AHSP PU A.2.3.1.9 56,827.10 #NAME?
3 Pasir Alas M3 #NAME? AHSP PU A.2.3.1.11 249,370.00 #NAME?
4 Aanstamping M3 #NAME? AHSP PU A.3.2.1.9 615,565.50 #NAME?
C Pondasi Menerus
1 Galian Tanah Pondasi M3 50.85 AHSP PU A.2.3.1.8a 96,626.20 4,913,249.02
2 Urugan Tanah Kembali (Bekas Galian Pondasi) M3 12.71 AHSP PU A.2.3.1.9 56,827.10 722,386.10
3 Pasir Alas M3 3.63 AHSP PU A.2.3.1.11 249,370.00 905,711.84
4 Aanstamping M3 7.26 AHSP PU A.3.2.1.9 615,565.50 4,471,467.79
5 Pondasi Batu Gunung M3 7.26 AHSP PU A.3.2.1.2 1,097,305.00 7,970,823.52
Sub Total #NAME?
III PEKERJAAN BETON BERTULANG
LANTAI I
1 Pekerjaan Pondasi Tapak 1 (Uk. 120 cm x 120 cm)
###
Beton K-225 M3 9.50 AHSP PU A.4.1.1.7 1,241,493.15 11,799,150.91
Besi Tulangan Pokok Ø14 - 150 Kg 918.28 AHSP PU A.4.1.1.17 23,355.75 21,447,071.41
Bekisting + Perawatan Beton M2 38.02 AHSP PU A.4.1.1.20 320,947.00 12,201,121.15
2 Plat Tangga
Beton K-225 M3 0.79 AHSP PU A.4.1.1.7 1,241,493.15 976,111.58
Besi Polos ∅-10 Kg 53.83 AHSP PU A.4.1.1.17 23,355.75 1,257,268.80
Bekisting M2 6.55 AHSP PU A.4.1.1.26 620,713.50 4,066,914.85
4 Plat Bordes
Beton K-225 M3 0.31 AHSP PU A.4.1.1.7 1,241,493.15 387,345.86
Besi Polos ∅-10 Kg 16.02 AHSP PU A.4.1.1.17 23,355.75 374,187.14
Bekisting M2 2.60 AHSP PU A.4.1.1.26 620,713.50 1,613,855.10
5 Keramik
Keramik Bordes 40x40 M2 3.73 AHSP PU A.4.4.3.34.a 314,776.00 1,172,855.38
Keramik Anak Tangga 40x40 M2 2.60 AHSP PU A.4.4.3.34.a 314,776.00 818,417.60
6 Pemasangan Railling Tangga
Railling Tangga Besi M1 7.28 Taksir 520,000.00 3,785,600.00
Sub Total 15,882,964.99
V PEKERJAAN DINDING DAN PLASTERAN
LANTAI I
1 Pas. Dinding Bata Trassram 1 : 2 M2 20.00 AHSP PU A.4.4.1.1 380,517.50 7,610,350.00
2 Plesteran 1 : 2 M2 40.00 AHSP PU A.4.4.2.2 102,061.30 4,082,452.00
3 Pas. Dinding Bata 1 : 4 M2 153.98 AHSP PU A.4.4.1.7 185,983.88 28,636,867.15
4 Plesteran 1 : 4 M2 307.95 AHSP PU A.4.4.2.2 102,061.30 31,429,777.34
Sub Total 71,759,446.49
LANTAI II
1 Pas. Dinding Bata 1 : 4 M2 210.36 AHSP PU A.4.4.1.7 185,983.88 39,122,638.03
2 Plesteran 1 : 4 M2 420.71 AHSP PU A.4.4.2.2 102,061.30 42,938,209.52
Sub Total 82,060,847.55
VI PEKERJAAN LANTAI
A LANTAI I
1 Urugan Tanah Bawah Lantai M3 41.44 AHSP PU A.2.3.1.11a 150,370.00 6,231,272.65
2 Urugan Pasir M3 17.37 AHSP PU A.2.3.1.11 249,370.00 4,332,679.07
3 Beton Cor Bawah Lantai M3 3.47 AHSP PU A.4.4.1.8 179,474.63 623,656.37
5 Keramik 40x40 M2 104.33 AHSP PU A.4.4.3.34.a 314,776.00 32,840,517.12
Sub Total 44,028,125.22
B LANTAI II
1 Keramik 40x40 M2 94.41 AHSP PU A.4.4.3.34.a 314,776.00 29,719,198.31
Sub Total 29,719,198.31
VII PEKERJAAN PLAFOND
A LANTAI I
Plafond Multyplek 4 mm M2 131.78 AHSP PU A.4.5.1.7 59,801.50 7,880,880.88
Rangka Plafond M2 131.78 AHSP PU A.4.5.1.5 69,074.50 9,102,913.91
Sub Total 16,983,794.78
B LANTAI II
Plafond Multyplek 4 mm M2 383.28 AHSP PU A.4.5.1.7 59,801.50 22,920,934.21
Rangka Plafond M2 383.28 AHSP PU A.4.5.1.5 69,074.50 26,475,123.03
Sub Total 49,396,057.23
VIII PEKERJAAN PINTU DAN JENDELA
A LANTAI I
1 Pintu (P1)
Kusen Pintu M2 0.13 AHSP PU A.4.2.1.11 115,042.95 15,323.72
Daun Pintu M2 3.78 AHSP PU A.4.6.1.5 997,700.00 3,771,306.00
Engsel Bh 6.00 AHSP PU A.4.6.2.5 65,737.10 394,422.60
Kunci Tanam Bh 2.00 AHSP PU A.4.6.2.4 266,761.00 533,522.00
Papan Ventilasi M2 0.96 AHSP PU A.4.6.1.10 940,665.00 903,038.40
2 Jendela (J1)
Kusen Jendela M2 0.15 AHSP PU A.4.2.1.11 115,042.95 17,394.49
Daun Jendela M2 4.00 AHSP PU A.4.6.1.5 997,700.00 3,990,800.00
Kaca 5 mm M2 2.48 AHSP PU A.4.6.2.17 178,789.60 442,826.08
Engsel Bh 8.00 AHSP PU A.4.6.2.5 65,737.10 525,896.80
Pacok Jendela Bh 4.00 AHSP PU A.4.6.2.10 40,987.10 163,948.40
Hak Angin Bh 4.00 AHSP PU A.4.6.2.9 52,537.10 210,148.40
Tarikan Jendela Bh 4.00 Taksir 12,000.00 48,000.00
Papan Ventilasi M2 0.72 AHSP PU A.4.6.1.10 940,665.00 677,278.80
3 Jendela (J2)
Kusen Jendela M2 0.63 AHSP PU A.4.2.1.11 115,042.95 72,684.14
Daun Jendela M2 9.00 AHSP PU A.4.6.1.5 997,700.00 8,979,300.00
Kaca 5 mm M2 5.57 AHSP PU A.4.6.2.17 178,789.60 996,358.68
Engsel Bh 36.00 AHSP PU A.4.6.2.5 65,737.10 2,366,535.60
Pacok Jendela Bh 18.00 AHSP PU A.4.6.2.10 40,987.10 737,767.80
Hak Angin Bh 18.00 AHSP PU A.4.6.2.9 52,537.10 945,667.80
Tarikan Jendela Bh 18.00 Taksir 12,000.00 216,000.00
Papan Ventilasi M2 3.24 AHSP PU A.4.6.1.10 940,665.00 3,047,754.60
Sub Total 29,055,974.31
B LANTAI II
1 Pintu (P1)
Kusen Pintu M2 0.13 AHSP PU A.4.2.1.11 115,042.95 15,323.72
Daun Pintu M2 3.78 AHSP PU A.4.6.1.5 997,700.00 3,771,306.00
Engsel Bh 6.00 AHSP PU A.4.6.2.5 65,737.10 394,422.60
Kunci Tanam Bh 2.00 AHSP PU A.4.6.2.4 266,761.00 533,522.00
Papan Ventilasi M2 0.96 AHSP PU A.4.6.1.10 940,665.00 903,038.40
2 Jendela (J1)
Kusen Jendela M2 0.15 AHSP PU A.4.2.1.11 115,042.95 17,394.49
Daun Jendela M2 4.00 AHSP PU A.4.6.1.5 997,700.00 3,990,800.00
Kaca 5 mm M2 2.48 AHSP PU A.4.6.2.17 178,789.60 442,826.08
Engsel Bh 8.00 AHSP PU A.4.6.2.5 65,737.10 525,896.80
Pacok Jendela Bh 4.00 AHSP PU A.4.6.2.10 40,987.10 163,948.40
Hak Angin Bh 4.00 AHSP PU A.4.6.2.9 52,537.10 210,148.40
Tarikan Jendela Bh 4.00 Taksir 12,000.00 48,000.00
Papan Ventilasi M2 0.72 AHSP PU A.4.6.1.10 940,665.00 677,278.80
3 Jendela (J2)
Kusen Jendela M2 0.63 AHSP PU A.4.2.1.11 115,042.95 72,684.14
Daun Jendela M2 9.00 AHSP PU A.4.6.1.5 997,700.00 8,979,300.00
Kaca 5 mm M2 5.57 AHSP PU A.4.6.2.17 178,789.60 996,358.68
Engsel Bh 36.00 AHSP PU A.4.6.2.5 65,737.10 2,366,535.60
Pacok Jendela Bh 18.00 AHSP PU A.4.6.2.10 40,987.10 737,767.80
Hak Angin Bh 18.00 AHSP PU A.4.6.2.9 52,537.10 945,667.80
Tarikan Jendela Bh 18.00 Taksir 12,000.00 216,000.00
Papan Ventilasi M2 3.24 AHSP PU A.4.6.1.10 940,665.00 3,047,754.60
Sub Total 29,055,974.31
IX PEKERJAAN ATAP
1 Rangka Atap Baja Ringan M2 192.73 Taksir 350,000.00 67,453,750.00
2 Penutup Atap Seng M2 192.73 AHSP PU A.4.5.1.32 152,537.00 29,397,693.33
3 Listplank GRC polos L = 0,20 M1 61.02 AHSP PU A.4.6.1.21 116,589.00 7,114,260.78
4 Rabung Atap Seng M1 32.30 AHSP PU A.4.5.1.39.a 90,194.50 2,913,282.35
Sub Total 106,878,986.46
X PEKERJAAN ELEKTRIKAL
A LANTAI I
1 Bola Lampu Pijar 40 Watt Bh 3.00 Taksir 55,000.00 165,000.00
2 Bola Lampu TL 20 Watt 220V Bh 4.00 Taksir 45,000.00 180,000.00
3 Sakelar Ganda Bh 1.00 Taksir 20,000.00 20,000.00
4 Sakelar Tunggal Bh 3.00 Taksir 12,000.00 36,000.00
5 Stop Kontak Bh 2.00 Taksir 75,000.00 150,000.00
6 Kabel Instalasi 2,5 mm Ls 2.00 Taksir 85,000.00 170,000.00
7 Bak Zekering Bh 1.00 Taksir 85,000.00 85,000.00
Sub Total 806,000.00
B LANTAI II
1 Bola Lampu Pijar 40 Watt Bh 3.00 Taksir 55,000.00 165,000.00
2 Bola Lampu TL 20 Watt 220V Bh 4.00 Taksir 45,000.00 180,000.00
3 Sakelar Ganda Bh 1.00 Taksir 20,000.00 20,000.00
4 Sakelar Tunggal Bh 3.00 Taksir 12,000.00 36,000.00
5 Stop Kontak Bh 2.00 Taksir 75,000.00 150,000.00
6 Kabel Instalasi 2,5 mm Ls 2.00 Taksir 85,000.00 170,000.00
Sub Total 721,000.00
XI PEKERJAAN PENGECATAN
A LANTAI I
1 Pengecatan Dinding Lantai I M2 307.95 AHSP PU A.4.7.1.10 40,944.75 12,608,935.76
2 Pengecatan Kusen Dan Jendela M2 22.62 AHSP PU A.4.7.1.4 55,324.50 1,251,229.96
Sub Total 13,860,165.72
B LANTAI II
1 Pengecatan Dinding Lantai 2 M2 420.71 AHSP PU A.4.7.1.10 40,944.75 17,225,865.77
2 Pengecatan Kusen Dan Jendela M2 22.62 AHSP PU A.4.7.1.4 55,324.50 1,251,229.96
Sub Total 18,477,095.73
XII PEKERJAAN LAIN- LAIN
A LANTAI I
1 Pembuatan Tangga Teras ls 2.00 Taksir 2,350,000.00 4,700,000.00
Sub Total 4,700,000.00
B LANTAI II
2 Finising Pada Tombak Layar (2 sisi) ls 1.00 Taksir 3,000,000.00 3,000,000.00
Sub Total 3,000,000.00