DAFTAR HARGA SATUAN BAHAN BANGUNAN

NO Jenis Barang Satuan Harga


A. UPAH
1 Mandor Orang 150,000.00
2 Kepala Tukang Orang 165,000.00
3 Tukang Orang 135,000.00
4 Pekerja Orang 125,000.00

B. HARGA BAHAN
1 Air Liter 120.00
T Ampelas Lembar 3,500.00
T Besi Strip Tebal 5 mm Kg 150,000.00
T Balok Kayu Kelas II M3 3,900,000.00
2 Batu Bata Buah 950.00
3 Batu Kali/ Batu Belah (Sungai/Gunung) M3 200,000.00
4 Batu Belah 5-7 Cm M3 195,000.00
5 Batu Pecah 2-3 Cm M3 320,000.00
T Besi Baja Profil Kg 150,000.00
6 Besi Beton Polos Kg 16,000.00
7 Besi Beton Ulir Kg 19,000.00
8 Bubungan Genteng M1 50,000.00
9 Bubungan Seng M1 40,000.00
10 Cat Dasar Tembok/Sealer Setara Vinilex Kg 35,000.00
11 Cat Kayu Dasar Kg 50,000.00
12 Cat Kayu Mengkilat Kg 65,000.00
13 Cat Menie Besi Kg 35,000.00
14 Cat Tembok Setara Vinilex Kg 55,000.00
15 Dempul Kayu Kg 18,000.00
16 Dolken Kayu Ф8-10/400 Cm Batang 75,000.00
17 Door Holden Pasang 135,000.00
18 Engsel Jendela Pasang 25,000.00
19 Engsel Pintu Pasang 25,000.00
20 Floor Drain Buah 27,000.00
21 Gypsum Board Tebal 9 mm Lembar 125,000.00
22 Jaring Kawat Baja Kg 36,000.00
23 Hak Nagin Pasang 17,000.00
24 Kaca Bening Uk.2 mm M2 75,000.00
25 Kaca Bening Uk.3 mm M2 85,000.00
26 Kaca Bening Uk. 5 mm M2 120,000.00
27 Kaca Rayband Uk. 3 mm M2 130,000.00
28 kacca Rayband Uk. 5 mm M2 153,000.00
29 Kaso-Kaso (5x7) Cm M3 3,500,000.00
30 Kawat Beton Kg 20,000.00
31 Kawat Duri Kg 50,000.00
32 Kawat Harmonika M2 60,000.00
33 Kawat Nyamuk/Kasa Logam M2 40,000.00
34 Kawat Nyamuk/Kasa Plastik M2 30,000.00
T Kerawang/Rooster Bh 700,000.00
T Kayu Kaso 5 x 7 cm M3 325,000.00
T Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 70,000.00
35 Kayu Bakar M3 750,000.00
36 Kayu Bakau 10 Cm Batang 60,000.00
37 Kayu Kelas I (Seumantok/Ulim/dll) M3 5,500,000.00
38 Kayu Kelas II (Kamper/Kruing/dll) M3 4,800,000.00
39 Kayu Kelas III (Borneo/dll) M3 3,900,000.00
40 Kayu Kelas IV (Semgon/dll) M3 3,750,000.00
41 Keramik Non Pholised 20 x 20 Cm Setara Ikat Bh 3,000.00
42 Keramik Uk. 20 x 20 Cm Bh 3,500.00
43 Keramik Uk. 40 x40 Cm Bh 12,000.00
44 Keramik Uk. 20 x 25 Cm Bh 3,500.00
45 Keramik Uk. 30 x 30 Cm Bh 6,200.00
46 Kertas Amplas Lembar 3,000.00
47 Kloset Duduk Keramik Setara Toto+Tabung Buah 1,500,000.00
48 Kloset Jongkok Keramik Setara Toto Buah 350,000.00
49 Kran Air 3/4" Buah 10,000.00
50 Kuas Cat Buah 15,000.00
51 Kunci Pintu (Standar) Buah 150,000.00
52 Kunci Pintu Biasa Buah 100,000.00
53 Lampu Hemat Energi 11 Watt Setara Hannochs Buah 35,000.00
54 Lampu Hemat Energi 18 Watt Setara Hannochs Buah 40,000.00
55 Lampu Hemat Energi 20 Watt Setara Hannochs Buah 45,000.00
56 Lem Kayu Kg 18,000.00
57 List Eternit Kayu M1 8,000.00
58 Marmer M2 50,000.00
59 Minyak Cat Liter 25,000.00
60 Minyak Bekisting Liter 5,000.00
61 Multypleks 3 mm Lembar 70,000.00
62 Multypleks 4 mm Lembar 75,000.00
63 Multypleks 6 mm Lembar 125,000.00
64 Multypleks 9 mm Lembar 155,000.00
65 Pacok Jendela Dan Ventilasi Pasang 7,500.00
66 Paku Asbes Kg 20,000.00
67 Paku Beton 8 Inchi Kotak 19,000.00
68 Paku Kait Buah 1,000.00
69 Paku Kayu Kg 18,000.00
70 Paku Tripleks Kg 19,000.00
71 Paku semg Kg 20,000.00
72 Paku Sumbat Buah 1,200.00
73 Paku Skrup Kg 23,000.00
74 Pasir Batu (Sirtu) Material Jalan M3 300,000.00
75 Pasir Beton Atau Kerikil M3 200,000.00
76 Pasir Pasang M3 190,000.00
77 Pasir Urug M3 150,000.00
78 Pelumas/Oli Liter 40,000.00
79 Pipa Leading Ф 1" Glavanis Tebal 3,2 mm Batang 75,000.00
80 Pipa Leading Ф 2" Glavanis Tebal 3,2 mm Batang 85,000.00
81 Pipa Leading Ф 3" Glavanis Tebal 3,2 mm Batang 90,000.00
82 Pipa PVC Ф 1" Batang 40,000.00
83 Pipa PVC Ф 2" Batang 50,000.00
84 Pipa PVC Ф 3" Batang 60,000.00
T Plamir Kayu Kg 18,000.00
85 Plamir Tembok Kg 30,000.00
86 Plin Kramik Buah 5,000.00
87 Plywood Tebal 9 mm Lembar 150,000.00
T Profil Aluminium M 80,000.00
T Penjaga Jarak Bekisting / Spacer Bh 30,000.00
T Rabung Seng Genteng M 130,000.00
88 Pemasangan Atap Baja Ringan M2 350,000.00
89 Residu Kg 10,000.00
90 Reservoir Air 500 Liter Buah 1,500,000.00
91 Reservoir Air 1000 Liter Buah 2,500,000.00
92 Reservoir Air 500 Liter Stainless steel Buah 2,000,000.00
93 Schakelar Buah 12,500.00
94 Semen @ 40 Kg Zak 55,000.00
95 Semen @ 40 Kg Kg 1,375.00
96 Semen Putih @ 50 Kg Zak 220,000.00
97 Semen Putih @ 50 Kg Kg 4,400.00
98 Semen Warna Kg 7,500.00
99 Seng Genteng Metal M2 75,000.00
100 Seng BJLS 0,20 Cat Pabrik M2 70,000.00
101 Seng Gelombang BJLS 30 M2 50,000.00
102 Seng Gelombang BJLS 30 Cat Pabrik M2 55,000.00
103 Seng Plat BJLS 20 M2 60,000.00
104 Seng Plat BJLS 30 M2 65,000.00
104 Solar (Industri) Liter 12,500.00
106 Sekrup Fixer Buah 500.00
107 Sealant Kg 15,500.00
108 Sumur+Pompa Tangan Terpasang Unit 2,000,000.00
109 Tanah Timbun M3 75,000.00
110 Tiang Pancang m' 300,000.00
111 Teralis Besi M2 380,000.00
112 Titik Lampu/Instalasi Titik 150,000.00
113 Urinoir Keramik Unit 2,500,000.00
114 Vinyl M2 25,000.00
115 WireMesh (Ulir) Kg 175,000.00
116 Zakering (Kast Lokal 1 Zekering) Unit 350,000.00

C. ALAT
1 Stamper Hari-Sewa 40,000.00
2 Dump Truck Jam 200,000.00
3 Molen Jam 50,000.00
Catatan : Bila Bahan Tidak Tercantum Di tabel ini boleh di Tambah
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pembersihan Lapangan
Satuan / Unit : M2
Analisa : AHSP PU A.2.2.1.9
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.1000 125,000.00 12,500.00
2 Mandor OH 0.0500 150,000.00 7,500.00
Jumlah Tenaga Kerja 20,000.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 20,000.00
E Overhead & Profit 10% X D 2,000.00
F Harga Satuan Pekerjaan ( D + E ) 22,000.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pengukuran Dan Pemasangan Bowplank
Satuan / Unit : M'
Analisa : AHSP PU A.2.2.1.4
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.1000 125,000 12,500
2 Tukang OH 0.1000 135,000 13,500
3 Kepala Tukang OH 0.0100 165,000 1,650
4 Mandor OH 0.0050 150,000 750
Jumlah Tenaga Kerja 28,400
B. BAHAN
1 Kayu Kelas III M³ 0.0120 3,900,000 46,800
2 Paku Kayu Kg 0.0200 18,000 360
3 Papan Kayu Kelas IV M³ 0.0070 3,750,000 26,250
Jumlah Bahan 73,410
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 101,810
E Overhead & Profit 10% X D 10,181
F Harga Satuan Pekerjaan ( D + E ) 111,991
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1-2 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.8a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.5260 125,000.00 65,750.00
2 Mandor OH 0.0526 150,000.00 7,890.00
Jumlah Tenaga Kerja 73,640.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 73,640.0
E. Overhead & Profit 10% X D 7,364.00
F. Harga Satuan Pekerjaan ( D + E ) 81,004.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Galian Tanah Biasa Sedalam 2-3 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.8b
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.7350 125000 91,875.00
2 Mandor OH 0.0735 150,000.00 11,025.00
Jumlah Tenaga Kerja 102,900.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 102,900.00
E. Overhead & Profit 10% X D 10,290.00
F. Harga Satuan Pekerjaan ( D + E ) 113,190.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.7500 125,000.0 93,750.00
2 Mandor OH 0.0250 150,000.0 3,750.00
Jumlah Tenaga Kerja 97,500.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 97,500.00
E. Overhead & Profit 10% X D 9,750.00
F. Harga Satuan Pekerjaan ( D + E ) 107,250.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Mengurug Kembali Galian
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.9
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.2500 125,000.00 31,250.00
2 Mandor OH 0.0833 150,000.00 12,495.00
Jumlah Tenaga Kerja 43,745.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 43,745.00
E. Overhead & Profit 10% X D 4,374.50
F. Harga Satuan Pekerjaan ( D + E ) 48,119.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memadatkan Tanah ( per 20ncm )
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.10
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.5000 125,000.00 62,500.00
2 Mandor OH 0.0500 150,000.00 7,500.00
Jumlah Tenaga Kerja 70,000.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 140,000.00
E. Overhead & Profit 10% X D 14,000.00
F. Harga Satuan Pekerjaan ( D + E ) 154,000.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : p
Satuan / Unit : M3
Analisa : AHSP PU - T.14 E
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.5000 125,000.00 62,500.00
2 Mandor OH 0.0500 150,000.00 7,500.00
Jumlah Tenaga Kerja 70,000.00
B. BAHAN
1 Tanah Timbun M3 1.200 75000 90,000.00
Jumlah Bahan 90,000.00
C. PERALATAN
1 Pemadat Timbuanan (Stamper) Sewa-Hari 0.05 40000 2,000.00
Jumlah Peralatan 2,000.00
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 254,000.00
E. Overhead & Profit 10% X D 25,400.00
F. Harga Satuan Pekerjaan ( D + E ) 279,400.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Urugan Pasir
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.11
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.3000 125,000.00 37,500.00
2 Mandor OH 0.0100 150,000.00 1,500.00
Jumlah Tenaga Kerja 39,000.00
B. BAHAN
1 Pasir Urug M3 1.200 150,000.00 180,000.00
Jumlah Bahan
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 219,000.00
E. Overhead & Profit 10% X D 21,900.00
F. Harga Satuan Pekerjaan ( D + E ) 240,900.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Timbunan Tanah
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.11.a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja Galian Tanah OH 0.3000 125,000.00 37,500.00
2 Mandor OH 0.0100 150,000.00 1,500.00
Jumlah Tenaga Kerja 39,000.00
B. BAHAN
1 Tanah Timbun M3 1.200 75,000.00 90,000.00
Jumlah Bahan
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 129,000.00
E. Overhead & Profit 10% X D 12,900.00
F. Harga Satuan Pekerjaan ( D + E ) 141,900.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pondasi Batu Belah / Kali Campuran 1 : 4
Satuan / Unit : M3
Analisa : AHSP PU A.3.2.1.2
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.5000 125,000.00 187,500.00
2 Tukang OH 0.7500 135,000.00 101,250.00
3 Kepala tukang OH 0.0750 165,000.00 12,375.00
4 Mandor OH 0.0750 150,000.00 11,250.00
Jumlah Tenaga Kerja 312,375.00
B. BAHAN
1 Batu Gunung / Batu Kali M3 1.200 200,000.00 240,000.00
2 Semen Portland Kg 163.000 1,375.00 224,125.00
3 Pasir Pasang M3 0.520 190,000.00 98,800.00
Jumlah Bahan 562,925.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 875,300.00
E. Overhead & Profit 10% X D 87,530.00
F. Harga Satuan Pekerjaan ( D + E ) 962,830.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Batu Kosong ( Aanstamping )
Satuan / Unit : M3
Analisa : AHSP PU A.3.2.1.9
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.7800 125,000.00 97,500.00
2 Tukang OH 0.3900 135,000.00 52,650.00
3 Kepala tukang OH 0.0390 165,000.00 6,435.00
4 Mandor OH 0.0390 150,000.00 5,850.00
Jumlah Tenaga Kerja 162,435.00
B. BAHAN
1 Batu Gunung / Batu Kali M3 1.2000 200,000.00 240,000.00
2 Pasir Urug M3 0.4320 150,000.00 64,800.00
Jumlah Bahan 304,800.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 467,235.00
E. Overhead & Profit 10% X D 46,723.50
F. Harga Satuan Pekerjaan ( D + E ) 513,958.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Beton Mutu F'c = 7,4 Mpa (K 100),
Slump (12 ± 2) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.1
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 247.00 1,375.00 339,625.00
2 Pasir Beton Kg 869.00 142.86 124,142.86
3 Kerikil Kg 999.00 148.15 148,000.00
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 637,567.86
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 898,012.86
E. Overhead & Profit 10% X D 89,801.29
F. Harga Satuan Pekerjaan ( D + E ) 987,814.14
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Beton Mutu F'c = 9,8 Mpa (K 125),
Slump (12 ± 2) cm, W/c = 0,78
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.2
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 247.00 1,375.00 339,625.00
2 Pasir Beton Kg 869.00 142.86 124,142.86
3 Kerikil Kg 999.00 148.15 148,000.00
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 637,567.86
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 898,012.86
E. Overhead & Profit 10% X D 89,801.29
F. Harga Satuan Pekerjaan ( D + E ) 987,814.14
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Beton Mutu F'c = 14,5 Mpa (K 175),
Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 326.00 1,375.00 448,250.00
2 Pasir Beton Kg 760.00 142.86 108,571.43
3 Kerikil Kg 1,029.00 148.15 152,444.44
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 735,065.87
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 995,510.87
E. Overhead & Profit 10% X D 99,551.09
F. Harga Satuan Pekerjaan ( D + E ) 1,095,061.96
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Beton Mutu F'c = 16,9 Mpa (K 200),
Slump (12 ± 2) cm, W/c = 0,61
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.6
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 326.00 1,375.00 448,250.00
2 Pasir Beton Kg 760.00 142.86 108,571.43
3 Kerikil Kg 1,029.00 148.15 152,444.44
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 735,065.87
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 995,510.87
E. Overhead & Profit 10% X D 99,551.09
F. Harga Satuan Pekerjaan ( D + E ) 1,095,061.96
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Beton Mutu F'c = 19,3 Mpa (K 225),
Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 371.00 1,375.00 510,125.00
2 Pasir Beton Kg 698.00 142.86 99,714.29
3 Kerikil Kg 1,047.00 148.15 155,111.11
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 790,750.40
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,051,195.40
E. Overhead & Profit 10% X D 105,119.54
F. Harga Satuan Pekerjaan ( D + E ) 1,156,314.94
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Beton Mutu F'c = 19,3 Mpa (K 250),
Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 384.00 1,375.00 528,000.00
2 Pasir Beton Kg 692.00 142.86 98,857.14
3 Kerikil Kg 1,039.00 148.15 153,925.93
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 806,583.07
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,067,028.07
E. Overhead & Profit 10% X D 106,702.81
F. Harga Satuan Pekerjaan ( D + E ) 1,173,730.88
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Beton Mutu F'c = 24,0 Mpa (K 275),
Slump (12 ± 2) cm, W/c = 0,53
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 406.00 1,375.00 558,250.00
2 Pasir Beton Kg 684.00 142.86 97,714.29
3 Kerikil Kg 1,026.00 148.15 152,000.00
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 833,764.29
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,094,209.29
E. Overhead & Profit 10% X D 109,420.93
F. Harga Satuan Pekerjaan ( D + E ) 1,203,630.21
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Beton Mutu F'c = 26,4 Mpa (K 300),
Slump (12 ± 2) cm, W/c = 0,52
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 125,000.00 206,250.00
2 Tukang OH 0.2750 135,000.00 37,125.00
3 Kepala tukang OH 0.0280 165,000.00 4,620.00
4 Mandor OH 0.0830 150,000.00 12,450.00
Jumlah Tenaga Kerja 260,445.00
B. BAHAN
1 Semen Portland Kg 413.00 1,375.00 567,875.00
2 Pasir Beton Kg 681.00 142.86 97,285.71
3 Kerikil Kg 1,021.00 148.15 151,259.26
4 Air Liter 215.00 120.00 25,800.00
Jumlah Bahan 842,219.97
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,102,664.97
E. Overhead & Profit 10% X D 110,266.50
F. Harga Satuan Pekerjaan ( D + E ) 1,212,931.47
Wc Faktor ; Pasir ; 1.400 Kg, dan Kerikil = 1.350 Kg
1400 1350
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pembesian 1 Kg Dengan Besi Polos
Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.17
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0700 125,000.00 8,750.00
2 Tukang OH 0.0700 135,000.00 9,450.00
3 Kepala tukang OH 0.0070 165,000.00 1,155.00
4 Mandor OH 0.0400 150,000.00 6,000.00
Jumlah Tenaga Kerja 25,355.00
B. BAHAN
1 Besi Beton Polos Kg 10.500 16,000.00 168,000.00
2 Kawat Beton Kg 0.150 20,000.00 3,000.00
Jumlah Bahan 171,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 196,355.00
E. Per Kg Pembesian = D/10 19,635.50
F. Overhead & Profit 10% X E 1,963.55
G. Harga Satuan Pekerjaan ( E + F ) 21,599.05

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pembesian 1 Kg Dengan Besi Ulir
Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.17.a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0700 125,000.00 8,750.00
2 Tukang OH 0.0700 135,000.00 9,450.00
3 Kepala tukang OH 0.0070 165,000.00 1,155.00
4 Mandor OH 0.0400 150,000.00 6,000.00
Jumlah Tenaga Kerja 25,355.00
B. BAHAN
1 Besi Beton Ulir Kg 10.500 19,000.00 199,500.00
2 Kawat Beton Kg 0.150 20,000.00 3,000.00
Jumlah Bahan 202,500.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 227,855.00
E. Per Kg Pembesian = D/10 22,785.50
F. Overhead & Profit 10% X E 2,278.55
G. Harga Satuan Pekerjaan ( E + F ) 25,064.05
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 Kg Jaring Kawat Baja/Wire Mesh
Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.19
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0250 125,000.000 3,125.000
2 Tukang OH 0.0250 135,000.000 3,375.000
3 Kepala tukang OH 0.0020 165,000.000 330.000
4 Mandor OH 0.0010 150,000.000 150.000
Jumlah Tenaga Kerja 6,980.000
B. BAHAN
1 Jaring Kawat Baja Di Las Kg 1.020 36,000.000 36,720.000
2 Kawat Beton Kg 0.050 20,000.000 1,000.000
Jumlah Bahan 37,720.000
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 44,700.000
E. Overhead & Profit 10% X D 4,470.000
F. Harga Satuan Pekerjaan ( D + E ) 49,170.000

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Bekisting Untuk Pondasi
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.20
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.5200 125,000.00 65,000.00
2 Tukang OH 0.2600 135,000.00 35,100.00
3 Kepala tukang OH 0.0260 165,000.00 4,290.00
4 Mandor OH 0.0260 150,000.00 3,900.00
Jumlah Tenaga Kerja 108,290.00
B. BAHAN
1 Kayu Kelas III M³ 0.040 3,900,000.00 156,000.00
2 Paku 5 Cm - 10 Cm Kg 0.300 18,000.00 5,400.00
3 Minyak Bekisting Liter 0.100 5,000.00 500.00
Jumlah Bahan 161,900.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 270,190.00
E. Overhead & Profit 10% X D 27,019.00
F. Harga Satuan Pekerjaan ( D+E ) 297,209.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Sloof
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.21
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.5200 125,000.00 65,000.00
2 Tukang OH 0.2600 135,000.00 35,100.00
3 Kepala tukang OH 0.0260 165,000.00 4,290.00
4 Mandor OH 0.0260 150,000.00 3,900.00
Jumlah Tenaga Kerja 108,290.00
B. BAHAN
1 Kayu Kelas III M³ 0.040 3,900,000.00 156,000.00
2 Paku 5 Cm - 10 Cm Kg 0.300 18,000.00 5,400.00
3 Minyak Bekisting Liter 0.100 5,000.00 500.00
Jumlah Bahan 161,900.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 270,190.00
E. Overhead & Profit 10% X D 27,019.00
F. Harga Satuan Pekerjaan ( D+E ) 297,209.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Bekisting Untuk Kolom
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.22
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6600 125,000.00 82,500.00
2 Tukang OH 0.3300 135,000.00 44,550.00
3 Kepala tukang OH 0.0330 165,000.00 5,445.00
4 Mandor OH 0.0330 150,000.00 4,950.00
Jumlah Tenaga Kerja 137,445.00
B. BAHAN
1 Kayu Kelas III M³ 0.0400 3,900,000.00 156,000.00
2 Paku 5 Cm - 10 Cm Kg 0.4000 19,000.00 7,600.00
3 Minyak Bekisting Liter 0.2000 5,000.00 1,000.00
4 Balok Kayu Kelas II M³ 0.0150 3,900,000.00 58,500.00
5 Plywood Tebal 9 mm Lbr 0.3500 150,000.00 52,500.00
6 Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 2.0000 70,000.00 140,000.00
Jumlah Bahan 415,600.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 553,045.00
E. Overhead & Profit 10% X D 55,304.50
F. Harga Satuan Pekerjaan ( D+E ) 608,349.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Balok
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.23
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6600 125,000.00 82,500.00
2 Tukang OH 0.3300 135,000.00 44,550.00
3 Kepala tukang OH 0.0330 165,000.00 5,445.00
4 Mandor OH 0.0330 150,000.00 4,950.00
Jumlah Tenaga Kerja 137,445.00
B. BAHAN
1 Kayu Kelas III M³ 0.0400 3,900,000.00 156,000.00
2 Paku 5 Cm - 10 Cm Kg 0.4000 18,000.00 7,200.00
3 Minyak Bekisting Liter 0.2000 5,000.00 1,000.00
4 Balok Kayu Kelas II M³ 0.0180 3,900,000.00 70,200.00
5 Plywood Tebal 9 mm Lbr 0.3500 150,000.00 52,500.00
6 Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 2.0000 70,000.00 140,000.00
Jumlah Bahan 426,900.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 564,345.00
E. Overhead & Profit 10% X D 56,434.50
F. Harga Satuan Pekerjaan ( D+E ) 620,779.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Bekisting Untuk Plat Lantai
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.24
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6600 125,000.00 82,500.00
2 Tukang OH 0.3300 135,000.00 44,550.00
3 Kepala tukang OH 0.0330 165,000.00 5,445.00
4 Mandor OH 0.0330 150,000.00 4,950.00
Jumlah Tenaga Kerja 137,445.00
B. BAHAN
1 Kayu Kelas III M³ 0.0400 3,900,000.00 156,000.00
2 Paku 5 Cm - 10 Cm Kg 0.4000 18,000.00 7,200.00
3 Minyak Bekisting Liter 0.2000 5,000.00 1,000.00
4 Balok Kayu Kelas II M³ 0.0150 3,900,000.00 58,500.00
5 Plywood Tebal 9 mm Lbr 0.3500 150,000.00 52,500.00
6 Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 6.0000 70,000.00 420,000.00
Jumlah Bahan 695,200.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 832,645.00
E. Overhead & Profit 10% X D 83,264.50
F. Harga Satuan Pekerjaan ( D+E ) 915,909.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Dinding
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.25
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6600 125,000.00 82,500.00
2 Tukang OH 0.3300 135,000.00 44,550.00
3 Kepala tukang OH 0.0330 165,000.00 5,445.00
4 Mandor OH 0.0330 150,000.00 4,950.00
Jumlah Tenaga Kerja 137,445.00
B. BAHAN
1 Kayu Kelas III M³ 0.030 3,900,000.00 117,000.00
2 Paku 5 Cm - 10 Cm Kg 0.400 18,000.00 7,200.00
3 Minyak Bekisting Liter 0.200 5,000.00 1,000.00
4 Balok Kayu Kelas II M³ 0.020 3,900,000.00 78,000.00
5 Plywood Tebal 9 mm Lbr 0.350 150,000.00 52,500.00
6 Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 3.000 70,000.00 210,000.00
7 Penjaga Jarak Bekisting / Spacer Bh 4.000 30,000.00 120,000.00
Jumlah Bahan 585,700.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 723,145.00
E. Overhead & Profit 10% X D 72,314.50
F. Harga Satuan Pekerjaan ( D+E ) 795,459.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Bekisting Untuk Tangga
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.26
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6600 125,000.00 82,500.00
2 Tukang OH 0.3300 135,000.00 44,550.00
3 Kepala tukang OH 0.0330 165,000.00 5,445.00
4 Mandor OH 0.0330 150,000.00 4,950.00
Jumlah Tenaga Kerja 137,445.00
B. BAHAN
1 Kayu Kelas III M³ 0.030 3,900,000.00 117,000.00
2 Paku 5 Cm - 10 Cm Kg 0.400 18,000.00 7,200.00
3 Minyak Bekisting Liter 0.150 5,000.00 750.00
4 Balok Kayu Kelas II M³ 0.015 3,900,000.00 58,500.00
5 Plywood Tebal 9 mm Lbr 0.350 150,000.00 52,500.00
6 Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 2.000 70000 140,000.00
Jumlah Bahan 375,950.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 513,395.00
E. Overhead & Profit 10% X D 51,339.50
F. Harga Satuan Pekerjaan ( D+E ) 564,734.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Baja Profil
Satuan / Unit : Kg
Analisa : AHSP PU A.4.2.1.1
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0600 125,000.00 7,500.00
2 Tukang OH 0.0600 135,000.00 8,100.00
3 Kepala tukang OH 0.0060 165,000.00 990.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 17,040.00
B. BAHAN
1 Besi Baja Profil Kg 1.150 150,000.00 172,500.00
Jumlah Bahan 172,500.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 189,540.00
E. Overhead & Profit 10% X D 18,954.00
F. Harga Satuan Pekerjaan ( D+E ) 208,494.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pemasangan rangka Kuda-Kuda Baja Profil IWF
Satuan / Unit : Kg
Analisa : Taksir
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0600 125,000.00 7,500.0000
2 Tukang OH 0.0600 135,000.00 8,100.00
3 Kepala tukang OH 0.0060 165,000.00 990.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 17,040.00
B. BAHAN
1 Besi Baja Profil IWF Kg 1.150 150,000.00 172,500.00
Jumlah Bahan 172,500.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 189,540.00
E. Overhead & Profit 10% X D 18,954.00
F. Harga Satuan Pekerjaan ( D + E ) 208,494.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Kusen Pintu Alluminium
Satuan / Unit : M
Analisa : AHSP PU A.4.2.1.11
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0430 125,000.00 5,375.00
2 Tukang OH 0.0430 135,000.00 5,805.00
3 Kepala tukang OH 0.0430 165,000.00 7,095.00
4 Mandor OH 0.0021 150,000.00 315.00
Jumlah Tenaga Kerja 18,590.00
B. BAHAN
1 Profil Aluminium M 1.100 80,000.00 88,000.00
2 Sekrup Fixer Buah 2.000 500.00 1,000.00
3 Sealant Tube 0.060 15,500.00 930.00
Jumlah Bahan 89,930.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 108,520.00
E. Overhead & Profit 10% X D 10,852.00
F. Harga Satuan Pekerjaan ( D + E ) 119,372.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 2 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.1
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6000 125,000.00 75,000.00
2 Tukang OH 0.2000 135,000.00 27,000.00
3 Kepala tukang OH 0.0200 165,000.00 3,300.00
4 Mandor OH 0.0300 150,000.00 4,500.00
Jumlah Tenaga Kerja 109,800.00
B. BAHAN
1 Batu Bata Bh 140.000 950.00 133,000.00
2 Semen Portland Kg 43.500 1,375.00 59,812.50
3 Pasir Pasang M3 0.080 190,000.00 15,200.00
Jumlah Bahan 208,012.50
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 317,812.50
E. Overhead & Profit 10% X D 31,781.25
F. Harga Satuan Pekerjaan ( D + E ) 349,593.75
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 3 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.2
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6000 125,000.00 75,000.00
2 Tukang OH 0.2000 135,000.00 27,000.00
3 Kepala tukang OH 0.0200 165,000.00 3,300.00
4 Mandor OH 0.0300 150,000.00 4,500.00
Jumlah Tenaga Kerja 109,800.00
B. BAHAN
1 Batu Bata Bh 140.000 950.00 133,000.00
2 Semen Portland Kg 32.950 1,375.00 45,306.25
3 Pasir Pasang M3 0.091 190,000.00 17,290.00
Jumlah Bahan 195,596.25
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 305,396.25
E. Overhead & Profit 10% X D 30,539.63
F. Harga Satuan Pekerjaan ( D + E ) 335,935.88

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.3
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6000 125,000.00 75,000.00
2 Tukang OH 0.2000 135,000.00 27,000.00
3 Kepala tukang OH 0.0200 165,000.00 3,300.00
4 Mandor OH 0.0300 150,000.00 4,500.00
Jumlah Tenaga Kerja 109,800.00
B. BAHAN
1 Batu Bata Bh 140.000 950.00 133,000.00
2 Semen Portland Kg 26.550 1,375.00 36,506.25
3 Pasir Pasang M3 0.093 190,000.00 17,670.00
Jumlah Bahan 187,176.25
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 296,976.25
E. Overhead & Profit 10% X D 29,697.63
F. Harga Satuan Pekerjaan ( D + E ) 326,673.88
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 5 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.4
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6000 125,000.00 75,000.00
2 Tukang OH 0.2000 135,000.00 27,000.00
3 Kepala tukang OH 0.0200 165,000.00 3,300.00
4 Mandor OH 0.0300 150,000.00 4,500.00
Jumlah Tenaga Kerja 109,800.00
B. BAHAN
1 Batu Bata Bh 140.000 950.00 133,000.00
2 Semen Portland Kg 22.200 1,375.00 30,525.00
3 Pasir Pasang M3 0.102 190,000.00 19,380.00
Jumlah Bahan 182,905.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 292,705.00
E. Overhead & Profit 10% X D 29,270.50
F. Harga Satuan Pekerjaan ( D + E ) 321,975.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 2 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.7
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Batu Bata Bh 70.000 950.00 66,500.00
2 Semen Portland Kg 18.950 1,375.00 26,056.25
3 Pasir Pasang M3 0.038 190,000.00 7,220.00
Jumlah Bahan 99,776.25
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 154,676.25
E. Overhead & Profit 10% X D 15,467.63
F. Harga Satuan Pekerjaan ( D + E ) 170,143.88
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Batu Bata Bh 70.000 950.00 66,500.00
2 Semen Portland Kg 14.370 1,375.00 19,758.75
3 Pasir Pasang M3 0.040 190,000.00 7,600.00
Jumlah Bahan 93,858.75
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 148,758.75
E. Overhead & Profit 10% X D 14,875.88
F. Harga Satuan Pekerjaan ( D + E ) 163,634.63

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Batu Bata Bh 70.000 950.00 66,500.00
2 Semen Portland Kg 11.500 1,375.00 15,812.50
3 Pasir Pasang M3 0.043 190,000.00 8,170.00
Jumlah Bahan 90,482.50
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 145,382.50
E. Overhead & Profit 10% X D 14,538.25
F. Harga Satuan Pekerjaan ( D + E ) 159,920.75
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.10
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Batu Bata Bh 70.000 950.00 66,500.00
2 Semen Portland Kg 9.680 1,375.00 13,310.00
3 Pasir Pasang M3 0.045 190,000.00 8,550.00
Jumlah Bahan 88,360.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 143,260.00
E. Overhead & Profit 10% X D 14,326.00
F. Harga Satuan Pekerjaan ( D + E ) 157,586.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Kerawang (Roster) Camp. 1Pc : 3 pp
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.22
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Kerawang/Roster Bh 30.000 950.00 28,500.00
2 Semen Portland Kg 11.000 1,375.00 15,125.00
3 Pasir Pasang M3 0.035 190,000.00 6,650.00
Jumlah Bahan 50,275.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 105,175.00
E. Overhead & Profit 10% X D 10,517.50
F. Harga Satuan Pekerjaan ( D + E ) 115,692.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Kerawang (Roster) Camp. 1Pc : 4 pp
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.23
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 54,900.00
B. BAHAN
1 Kerawang/Roster Bh 30.000 700,000.00 21,000,000.00
2 Semen Portland Kg 11.000 1,375.00 15,125.00
3 Pasir Pasang M3 0.035 190,000.00 6,650.00
Jumlah Bahan 21,021,775.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 21,076,675.00
E. Overhead & Profit 10% X D 2,107,667.50
F. Harga Satuan Pekerjaan ( D + E ) 23,184,342.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Plasteran 1 Pc : 1 pp Tebal 15 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.1
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 62,475.00
B. BAHAN
1 Semen Portland Kg 15.504 1,375.00 21,318.00
2 Pasir Pasang M3 0.016 190,000.00 3,040.00
Jumlah Bahan 24,358.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 86,833.00
E. Overhead & Profit 10% X D 8,683.30
F. Harga Satuan Pekerjaan ( D + E ) 95,516.30
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Plasteran 1 Pc : 2 pp Tebal 15 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.2
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 62,475.00
B. BAHAN
1 Semen Portland Kg 10.224 1,375.00 14,058.00
2 Pasir Pasang M3 0.020 190,000.00 3,800.00
Jumlah Bahan 17,858.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 80,333.00
E. Overhead & Profit 10% X D 8,033.30
F. Harga Satuan Pekerjaan ( D + E ) 88,366.30

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Plasteran 1 Pc : 3 pp Tebal 15 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.3
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 62,475.00
B. BAHAN
1 Semen Portland Kg 6.240 1,375.00 8,580.00
2 Pasir Pasang M3 0.023 190,000.00 4,370.00
Jumlah Bahan 12,950.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,425.00
E. Overhead & Profit 10% X D 7,542.50
F. Harga Satuan Pekerjaan ( D + E ) 82,967.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Plasteran 1 Pc :4 pp Tebal 15 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.4
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 62,475.00
B. BAHAN
1 Semen Portland Kg 6.240 1,375.00 8,580.00
2 Pasir Pasang M3 0.024 190,000.00 4,560.00
Jumlah Bahan 13,140.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,615.00
E. Overhead & Profit 10% X D 7,561.50
F. Harga Satuan Pekerjaan ( D + E ) 83,176.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Plasteran 1 Pc : 5 pp Tebal 15 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.3000 125,000.00 37,500.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0150 150,000.00 2,250.00
Jumlah Tenaga Kerja 62,475.00
B. BAHAN
1 Semen Portland Kg 15.504 1,375.00 21,318.00
2 Pasir Pasang M3 0.016 190,000.00 3,040.00
Jumlah Bahan 24,358.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 86,833.00
E. Overhead & Profit 10% X D 8,683.30
F. Harga Satuan Pekerjaan ( D + E ) 95,516.30
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Acian
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.27
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.2000 125,000.00 25,000.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0100 150,000.00 1,500.00
Jumlah Tenaga Kerja 41,650.00
B. BAHAN
1 Semen Portland Kg 3.250 1,375.00 4,468.75
Jumlah Bahan 4,468.75
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 46,118.75
E. Overhead & Profit 10% X D 4,611.88
F. Harga Satuan Pekerjaan ( D + E ) 50,730.63

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Keramik Lantai Uk. 40 x 40 Cm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.34.a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.7000 125,000.00 87,500.00
2 Tukang OH 0.3500 135,000.00 47,250.00
3 Kepala tukang OH 0.0350 165,000.00 5,775.00
4 Mandor OH 0.0350 150,000.00 5,250.00
Jumlah Tenaga Kerja 145,775.00
B. BAHAN
1 Keramik Lantai Uk. 40 x 40 Cm Bh 6.630 12,000.00 79,560.00
2 Semen Portland Kg 9.800 1,375.00 13,475.00
3 Semen Warna Kg 1.300 7,500.00 9,750.00
4 Pasir Pasang M3 0.045 190,000.00 8,550.00
Jumlah Bahan 111,335.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 257,110.00
E. Overhead & Profit 10% X D 25,711.00
F. Harga Satuan Pekerjaan ( D + E ) 282,821.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Keramik Uk. 30 x 30 Cm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.35
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.7000 125,000.00 87,500.00
2 Tukang OH 0.3500 135,000.00 47,250.00
3 Kepala tukang OH 0.0350 165,000.00 5,775.00
4 Mandor OH 0.0350 150,000.00 5,250.00
Jumlah Tenaga Kerja 145,775.00
B. BAHAN
1 Keramik Lantai Uk. 30 x 30 Cm Bh 11.870 6,200.00 73,594.00
2 Semen Portland Kg 10.000 1,375.00 13,750.00
3 Semen Warna Kg 1.500 7,500.00 11,250.00
4 Pasir Pasang M3 0.045 190,000.00 8,550.00
Jumlah Bahan 107,144.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 252,919.00
E. Overhead & Profit 10% X D 25,291.90
F. Harga Satuan Pekerjaan ( D + E ) 278,210.90

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Keramik Lantai Uk. 20 x 20 Cm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.36
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.7000 125,000.00 87,500.00
2 Tukang OH 0.3500 135,000.00 47,250.00
3 Kepala tukang OH 0.0350 165,000.00 5,775.00
4 Mandor OH 0.0350 150,000.00 5,250.00
Jumlah Tenaga Kerja 145,775.00
B. BAHAN
1 Keramik Lantai Uk. 20 x 20 Cm Bh 26.500 3,500.00 92,750.00
2 Semen Portland Kg 10.400 1,375.00 14,300.00
3 Semen Warna Kg 1.620 7,500.00 12,150.00
4 Pasir Pasang M3 0.045 190,000.00 8,550.00
Jumlah Bahan 127,750.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 273,525.00
E. Overhead & Profit 10% X D 27,352.50
F. Harga Satuan Pekerjaan ( D + E ) 300,877.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Keramik Lantai Uk. 10 x 10 Cm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.34.a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0900 125,000.00 11,250.00
2 Tukang OH 0.0900 135,000.00 12,150.00
3 Kepala tukang OH 0.0350 165,000.00 5,775.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 29,925.00
B. BAHAN
1 Piint Keramik Uk.10 x 10 Cm Bh 10.600 5,000.00 53,000.00
2 Semen Portland Kg 1.140 1,375.00 1,567.50
3 Semen Warna Kg 0.050 7,500.00 375.00
4 Pasir Pasang M3 0.003 190,000.00 570.00
Jumlah Bahan 55,512.50
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 85,437.50
E. Overhead & Profit 10% X D 8,543.75
F. Harga Satuan Pekerjaan ( D + E ) 93,981.25

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pasangan Dinding Keramik Uk. 20 x 25 Cm
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.54
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.9000 125,000.00 112,500.00
2 Tukang OH 0.4500 135,000.00 60,750.00
3 Kepala tukang OH 0.0450 165,000.00 7,425.00
4 Mandor OH 0.0450 150,000.00 6,750.00
Jumlah Tenaga Kerja 187,425.00
B. BAHAN
1 Keramik Dinding Uk. 20 x 25 Cm Bh 20.000 3,500.00 70,000.00
2 Semen Portland Kg 9.300 1,375.00 12,787.50
3 Semen Warna Kg 1.940 7,500.00 14,550.00
4 Pasir Pasang M3 0.018 190,000.00 3,420.00
Jumlah Bahan 100,757.50
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 288,182.50
E. Overhead & Profit 10% X D 28,818.25
F. Harga Satuan Pekerjaan ( D + E ) 317,000.75
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Langit-Langit Tripleks Ukuran (120x240) cm,
tebal 4 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.1000 125,000.00 12,500.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 28,400.00
B. BAHAN
1 Keramik Dinding Uk. 20 x 25 Cm Bh 0.375 3,500.00 1,312.50
2 Semen Portland Kg 0.030 1,375.00 41.25
Jumlah Bahan 1,353.75
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 29,753.75
E. Overhead & Profit 10% X D 2,975.38
F. Harga Satuan Pekerjaan ( D+E ) 32,729.13

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Langit-Langit Multyplek Ukuran 4 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.1000 125,000.00 12,500.00
2 Tukang OH 0.0500 135,000.00 6,750.00
3 Kepala tukang OH 0.0050 165,000.00 825.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 20,825.00
B. BAHAN
1 Multyplek 4 mm Bh 0.3640 75,000.00 27,300.00
2 Semen Portland Kg 0.1100 1,375.00 151.25
Jumlah Bahan 27,451.25
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 48,276.25
E. Overhead & Profit 10% X D 4,827.63
F. Harga Satuan Pekerjaan ( D+E ) 53,103.8750
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang List Profil kayu
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.9
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0500 125,000.00 6,250.00
2 Tukang OH 0.0500 135,000.00 6,750.00
3 Kepala tukang OH 0.0050 165,000.00 825.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 14,275.00
B. BAHAN
1 List Profil M 1.0500 8,000.00 8,400.00
2 Paku Kayu Kg 0.0100 18,000.00 180.00
Jumlah Bahan 8,580.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 22,855.00
E. Overhead & Profit 10% X D 2,285.50
F. Harga Satuan Pekerjaan ( D+E ) 25,140.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Atap Seng Genteng
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.2.32
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.2000 125,000.00 25,000.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0010 150,000.00 150.00
Jumlah Tenaga Kerja 40,300.00
B. BAHAN
1 Atap Seng Genteng Lbr 1.1500 75,000.00 86,250.00
2 Paku Seng Kg 0.2000 20,000.00 4,000.00
Jumlah Bahan 90,250.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 130,550.00
E. Overhead & Profit 10% X D 13,055.00
F. Harga Satuan Pekerjaan ( D+E ) 143,605.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Rabung Seng Atap
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.2.39.a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.1500 125,000.00 18,750.00
2 Tukang OH 0.0700 135,000.00 9,450.00
3 Kepala tukang OH 0.0070 165,000.00 1,155.00
4 Mandor OH 0.0200 150,000.00 3,000.00
Jumlah Tenaga Kerja 32,355.00
B. BAHAN
1 Rabung Seng Genteng M 0.3000 130,000.00 39,000.00
2 Paku Seng Kg 0.2160 20,000.00 4,320.00
Jumlah Bahan 43,320.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,675.00
E. Overhead & Profit 10% X D 7,567.50
F. Harga Satuan Pekerjaan ( D+E ) 83,242.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Dan Memasang Kusen Pintu Dan
Kusen Jendela, Kayu Kelas 1
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.1
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.7000 125,000.00 87,500.00
2 Tukang OH 21.0000 135,000.00 2,835,000.00
3 Kepala tukang OH 2.1000 165,000.00 346,500.00
4 Mandor OH 0.3500 150,000.00 52,500.00
Jumlah Tenaga Kerja 3,321,500.00
B. BAHAN
1 Balok Kayu Kelas 1 M3 1.1000 5,500,000.00 6,050,000.00
2 Paku Kayu Kg 1.2500 18,000.00 22,500.00
3 Lem Kayu Kg 1.0000 18,000.00 18,000.00
Jumlah Bahan 6,090,500.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,412,000.00
E. Overhead & Profit 10% X D 941,200.00
F. Harga Satuan Pekerjaan ( D+E ) 10,353,200.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Membuat Dan Memasang Daun Pintu Panel, Kayu Kls II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.0000 125,000.00 125,000.00
2 Tukang OH 3.0000 135,000.00 405,000.00
3 Kepala tukang OH 0.3000 165,000.00 49,500.00
4 Mandor OH 0.0500 150,000.00 7,500.00
Jumlah Tenaga Kerja 587,000.00
B. BAHAN
1 Papan Kayu Kelas II M3 0.0400 4,800,000.00 192,000.00
2 Lem Kayu Kg 0.5000 18,000.00 9,000.00
Jumlah Bahan 201,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 788,000.00
E. Overhead & Profit 10% X D 78,800.00
F. Harga Satuan Pekerjaan ( D+E ) 866,800.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Membuat Dan Memasang Daun Jendela Kayu Kelas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.6
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.8000 125,000.00 100,000.00
2 Tukang OH 2.4000 135,000.00 324,000.00
3 Kepala tukang OH 0.2400 165,000.00 39,600.00
4 Mandor OH 0.0400 150,000.00 6,000.00
Jumlah Tenaga Kerja 469,600.00
B. BAHAN
1 Papan Kayu Kelas II M3 0.0240 4,800,000.00 115,200.00
2 Lem Kayu Kg 0.3000 18,000.00 5,400.00
Jumlah Bahan 120,600.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 590,200.00
E. Overhead & Profit 10% X D 59,020.00
F. Harga Satuan Pekerjaan ( D+E ) 649,220.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Jalusi Kusen, Kayu Kelas I
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.10
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.6700 125,000.00 83,750.00
2 Tukang OH 2.0000 135,000.00 270,000.00
3 Kepala tukang OH 0.2000 165,000.00 33,000.00
4 Mandor OH 0.3350 150,000.00 50,250.00
Jumlah Tenaga Kerja 437,000.00
B. BAHAN
1 Papan Kayu Kelas I M3 0.0600 5,500,000.00 330,000.00
2 Paku Kayu Kg 0.1500 18,000.00 2,700.00
Jumlah Bahan 332,700.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 769,700.00
E. Overhead & Profit 10% X D 76,970.00
F. Harga Satuan Pekerjaan ( D+E ) 846,670.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Konstruksi Kuda-Kuda, Kayu Kelas I
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.14
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 6.7000 125,000.00 837,500.00
2 Tukang OH 10.1000 135,000.00 1,363,500.00
3 Kepala tukang OH 2.0100 165,000.00 331,650.00
4 Mandor OH 0.3350 150,000.00 50,250.00
Jumlah Tenaga Kerja 2,582,900.00
B. BAHAN
1 Balok Kayu Kelas I M3 1.2000 5,500,000.00 6,600,000.00
2 Besi Strip Tebal 5 mm Kg 15.0000 150,000.00 2,250,000.00
3 Paku Kayu Kg 5.6000 18,000.00 100,800.00
Jumlah Bahan 8,950,800.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 11,533,700.00
E. Overhead & Profit 10% X D 1,153,370.00
F. Harga Satuan Pekerjaan ( D+E ) 12,687,070.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Konstruksi Gordeng, Kayu Kelas II
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.15
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 2.4000 125,000.00 300,000.00
2 Tukang OH 7.2000 135,000.00 972,000.00
3 Kepala tukang OH 0.7200 165,000.00 118,800.00
4 Mandor OH 0.1200 150,000.00 18,000.00
Jumlah Tenaga Kerja 1,408,800.00
B. BAHAN
1 Balok Kayu Kelas I M3 1.1000 5,500,000.00 6,050,000.00
2 Besi Strip Tebal 5 mm Kg 15.0000 150,000.00 2,250,000.00
3 Paku Kayu Kg 3.0000 18,000.00 54,000.00
Jumlah Bahan 8,354,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,762,800.00
E. Overhead & Profit 10% X D 976,280.00
F. Harga Satuan Pekerjaan ( D+E ) 10,739,080.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Rangka Langit-Langit Kayu Kelas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.20
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.2000 125,000.00 25,000.00
2 Tukang OH 0.3000 135,000.00 40,500.00
3 Kepala tukang OH 0.0300 165,000.00 4,950.00
4 Mandor OH 0.0100 150,000.00 1,500.00
Jumlah Tenaga Kerja 71,950.00
B. BAHAN
1 Kayu Kaso 5 x 7 cm M3 0.0163 325,000.00 5,297.50
2 Paku Kayu Kg 0.2500 18,000.00 4,500.00
Jumlah Bahan 9,797.50
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 81,747.50
E. Overhead & Profit 10% X D 8,174.75
F. Harga Satuan Pekerjaan ( D+E ) 89,922.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Listplank Uk. 2,5x20 Cm Kayu Kelas I
Atau Kelas II
Satuan / Unit : M'
Analisa : AHSP PU A.4.6.1.21
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.1000 125,000.00 12,500.00
2 Tukang OH 0.2000 135,000.00 27,000.00
3 Kepala tukang OH 0.0200 165,000.00 3,300.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 43,550.00
B. BAHAN
1 Kayu Kelas II M3 0.0108 4,800,000.00 51,840.00
2 Paku Kg 0.1000 18,000.00 1,800.00
Jumlah Bahan 53,640.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 97,190.00
E. Overhead & Profit 10% X D 9,719.00
F. Harga Satuan Pekerjaan ( D+E ) 106,909.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Kunci Silinder
Satuan / Unit : Buah
Analisa : AHSP PU A.4.6.2.4
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0050 125,000.00 625.00
2 Tukang OH 0.5000 135,000.00 67,500.00
3 Kepala tukang OH 0.0500 165,000.00 8,250.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 76,825.00
B. BAHAN
1 Kunci Pintu Standar Bh 1.0000 150,000.00 150,000.00
Jumlah Bahan 150,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 226,825.00
E. Overhead & Profit 10% X D 22,682.50
F. Harga Satuan Pekerjaan ( D+E ) 249,507.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Engsel Pintu
Satuan / Unit : Buah
Analisa : AHSP PU A.4.6.2.5
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0150 125,000.00 1,875.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 1.0008 150,000.00 150,120.00
Jumlah Tenaga Kerja 174,720.00
B. BAHAN
1 Engsel Pintu Bh 1.0000 25,000.00 25,000.00
Jumlah Bahan 25,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 199,720.00
E. Overhead & Profit 10% X D 19,972.00
F. Harga Satuan Pekerjaan ( D+E ) 219,692.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Engsel Jendela Kupu-Kupu
Satuan / Unit : Buah
Analisa : AHSP PU A.4.6.2.6
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0150 125,000.00 1,875.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 1.0008 150,000.00 150,120.00
Jumlah Tenaga Kerja 174,720.00
B. BAHAN
1 Engsel Jendela Bh 1.0000 25,000.00 25,000.00
Jumlah Bahan 25,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 199,720.00
E. Overhead & Profit 10% X D 19,972.00
F. Harga Satuan Pekerjaan ( D+E ) 219,692.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Hak / Kait Angin Jendela
Satuan / Unit : Buah
Analisa : AHSP PU A.4.6.2.9
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0150 125,000.00 1,875.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0008 150,000.00 120.00
Jumlah Tenaga Kerja 24,720.00
B. BAHAN
1 Hak Angin Jendela Bh 1.0000 17,000.00 17,000.00
Jumlah Bahan 17,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 41,720.00
E. Overhead & Profit 10% X D 4,172.00
F. Harga Satuan Pekerjaan ( D+E ) 45,892.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Pacok Jendela
Satuan / Unit : Buah
Analisa : AHSP PU A.4.6.2.10
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0150 125,000.00 1,875.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0008 150,000.00 120.00
Jumlah Tenaga Kerja 24,720.00
B. BAHAN
1 Pacok Jendela Bh 1.0000 7,500.00 7,500.00
Jumlah Bahan 7,500.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,220.00
E. Overhead & Profit 10% X D 3,222.00
F. Harga Satuan Pekerjaan ( D+E ) 35,442.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Kloset Jongkok Porselen
Satuan / Unit : Buah
Analisa : AHSP PU A.5.1.1.2
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.0000 125,000.00 125,000.00
2 Tukang OH 1.5000 135,000.00 202,500.00
3 Kepala tukang OH 1.5000 165,000.00 247,500.00
4 Mandor OH 0.1600 150,000.00 24,000.00
Jumlah Tenaga Kerja 599,000.00
B. BAHAN
1 Kloset Jongkok Porselen Bh 1.0000 350,000.00 350,000.00
2 Semen Portland Kg 6.0000 1,375.00 8,250.00
3 Pasir Pasang M3 0.0100 190,000.00 1,900.00
Jumlah Bahan 360,150.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 959,150.00
E. Overhead & Profit 10% X D 95,915.00
F. Harga Satuan Pekerjaan ( D+E ) 1,055,065.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang 1 Buah Urinoir
Satuan / Unit : Buah
Analisa : AHSP PU A.5.1.1.4
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.0000 125,000.00 125,000.00
2 Tukang OH 1.0000 135,000.00 135,000.00
3 Kepala tukang OH 0.1000 165,000.00 16,500.00
4 Mandor OH 0.0500 150,000.00 7,500.00
Jumlah Tenaga Kerja 284,000.00
B. BAHAN
1 Urinoir Bh 1.0000 2,500,000.00 2,500,000.00
2 Semen Portland Kg 6.0000 1,375.00 8,250.00
3 Pasir Pasang M3 0.0100 190,000.00 1,900.00
4 Perlengkapan % 30.0000 -
Jumlah Bahan 2,510,150.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 2,794,150.00
E. Overhead & Profit 10% X D 279,415.00
F. Harga Satuan Pekerjaan ( D+E ) 3,073,565.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Floor Drain
Satuan / Unit : Buah
Analisa : AHSP PU A.4.5.1.14
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0100 125,000.00 1,250.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 17,150.00
B. BAHAN
1 Floor Drain Bh 1.0000 27,000.00 27,000.00
Jumlah Bahan 27,000.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 44,150.00
E. Overhead & Profit 10% X D 4,415.00
F. Harga Satuan Pekerjaan ( D+E ) 48,565.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang Kran Air dia. 1/2" atau 3/4
Satuan / Unit : Buah
Analisa : AHSP PU A.4.5.1.19
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0100 125,000.00 1,250.00
2 Tukang OH 0.1000 135,000.00 13,500.00
3 Kepala tukang OH 0.0100 165,000.00 1,650.00
4 Mandor OH 0.0050 150,000.00 750.00
Jumlah Tenaga Kerja 17,150.00 BK1
B. BAHAN BK2
1 Floor Drain Bh 1.0000 27,000.00 27,000.00
Jumlah Bahan 27,000.00
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 44,150.00
E. Overhead & Profit 10% X D 4,415.00
F. Harga Satuan Pekerjaan ( D+E ) 48,565.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 m2 kaca tebal 5 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.2.17
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0150 125,000.00 1,875.00
2 Tukang OH 0.1500 135,000.00 20,250.00
3 Kepala tukang OH 0.0150 165,000.00 2,475.00
4 Mandor OH 0.0008 150,000.00 120.00
Jumlah Tenaga Kerja 24,720.00
B. BAHAN
1 Kaca Tebal 5 mm M2 1.1000 120,000.00 132,000.00
2 Sealant Tube 0.0500 15,500.00 775.00
Jumlah Bahan 132,775.00
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 157,495.00
E. Overhead & Profit 10% X D 15,749.50
F. Harga Satuan Pekerjaan ( D+E ) 173,244.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pengecatan Bidang kayu Lama
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4a
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0700 125,000.00 8,750.00
2 Tukang OH 0.0090 135,000.00 1,215.00
3 Kepala tukang OH 0.0060 165,000.00 990.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 11,405.00
B. BAHAN
1 Pengencer/Minyak Cat Liter 0.0300 25,000.00 750.00
2 Cat Kayu Penutup Kg 0.1700 65,000.00 11,050.00
Jumlah Bahan 11,800.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 23,205.00
E. Overhead & Profit 10% X D 2,320.50
F. Harga Satuan Pekerjaan ( D+E ) 25,525.50
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengecatan Bidang kayu Baru (1 x plamir, 1 x cat dasar,
2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0700 125,000.00 8,750.00
2 Tukang OH 0.0090 135,000.00 1,215.00
3 Kepala tukang OH 0.0060 165,000.00 990.00
4 Mandor OH 0.0030 150,000.00 450.00
Jumlah Tenaga Kerja 11,405.00
B. BAHAN
1 Cat Menie Kg 0.2000 35,000.00 7,000.00
2 Plamir Kayu Kg 0.1500 18,000.00 2,700.00
3 Cat Dasar Kayu Kg 0.1700 50,000.00 8,500.00
4 Cat Kayu Penutup Kg 0.2600 65,000.00 16,900.00
5 Kuas Bh 0.0100 15,000.00 150.00
6 Pengencer Liter 0.0300 40,000.00 1,200.00
7 Ampelas Lembar 0.2000 3,500.00 700.00
Jumlah Bahan 37,150.00
C. PERALATAN
Jumlah Peralatan -
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 48,555.00
E. Overhead & Profit 10% X D 4,855.50
F. Harga Satuan Pekerjaan ( D+E ) 53,410.50

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pengecetan Tembok Baru (1 x plamir, 1 x cat dasar,
2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0200 125,000.00 2,500.00
2 Tukang OH 0.0630 135,000.00 8,505.00
3 Kepala tukang OH 0.0063 165,000.00 1,039.50
4 Mandor OH 0.0025 150,000.00 375.00
Jumlah Tenaga Kerja 12,419.50
B. BAHAN
1 Plamir Kg 0.1000 18,000.00 1,800.00
2 Cat Dasar Tembok Kg 0.1000 35,000.00 3,500.00
3 Cat Tembok / Penutup 2x Kg 0.2600 55,000.00 14,300.00
Jumlah Bahan 19,600.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,019.50
E. Overhead & Profit 10% X D 3,201.95
F. Harga Satuan Pekerjaan ( D+E ) 35,221.45
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengecetan Tembok Lama (1 x Cat Dasar,
2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.11
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 0.0280 125,000.00 3,500.00
2 Tukang OH 0.0420 135,000.00 5,670.00
3 Kepala tukang OH 0.0042 165,000.00 693.00
4 Mandor OH 0.0025 150,000.00 375.00
Jumlah Tenaga Kerja 10,238.00
B. BAHAN
1 Cat Dasar Tembok Kg 0.1200 35,000.00 4,200.00
2 Cat Tembok/Penutup 2x Kg 0.1800 55,000.00 9,900.00
Jumlah Bahan 14,100.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 24,338.00
E. Overhead & Profit 10% X D 2,433.80
F. Harga Satuan Pekerjaan ( D+E ) 26,771.80
PEKERJAAN LANTAI I
No Item Pekerjaan Volume Satuan Analisa Harga Satuan (Rp) Jumlah (Rp)
1 2 3 4 5 6 7
I. Pekerjaan Persiapan
1 Pembersihan Lapangan 405.00 M2 AHSP PU A.2.2.1.9 Rp 22,000.00 Rp 8,910,000.00
2 Pasang Bawplank/Pengukuran 79.00 M' AHSP PU A.2.2.1.4 Rp 111,991.00 Rp 8,847,289.00
3 Papan Nama Proyek 1.00 Bh Taksir Rp 1,000,000.00 Rp 1,000,000.00
4 Gudang Kerja 1.00 Unit Taksir Rp 20,000,000.00 Rp 2,000,000.00
5 Dokumentasi dan Administrasi 1.00 Ls Taksir Rp 2,000,000.00 Rp 2,000,000.00
SubTotal Rp 22,757,289.00

II. Pekerjaan Tanah dan Pondasi


1. Perkerjaan Pondasi Tapak 150/200
a. Galian Tanah 65.82 M3 AHSP PU A.2.3.1.8b Rp 113,190.00 Rp 7,450,618.56
b. Aanstamping 2.99 M3 AHSP PU A.3.2.1.9 Rp 513,958.50 Rp 1,537,763.83
c. Urungan Tanah Kembali 49.37 M3 AHSP PU A.2.3.1.9 Rp 48,119.50 Rp 2,375,563.48
d. Urugan Pasir 2.99 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 720,772.80

2. Perkerjaan Pondasi Tapak 125/125


a. Galian Tanah 69.38 M3 AHSP PU A.2.3.1.8b Rp 113,190.00 Rp 7,853,405.18
b. Aanstamping 3.15 M3 AHSP PU A.3.2.1.9 Rp 513,958.50 Rp 1,620,896.62
c. Urungan Tanah Kembali 52.04 M3 AHSP PU A.2.3.1.9 Rp 48,119.50 Rp 2,503,988.41
d. Urugan Pasir 3.15 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 759,738.38

3. Perkerjaan Pondasi Tapak 100/100


a. Galian Tanah 38.02 M3 AHSP PU A.2.3.1.8b Rp 113,190.00 Rp 4,303,031.04
b. Aanstamping 1.73 M3 AHSP PU A.3.2.1.9 Rp 513,958.50 Rp 888,120.29
c. Urungan Tanah Kembali 28.51 M3 AHSP PU A.2.3.1.9 Rp 48,119.50 Rp 1,371,983.18
d. Urugan Pasir 1.73 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 416,275.20

4. Perkerjaan Pondasi Menerus


a. Galian Tanah 92.13 M3 AHSP PU A.2.3.1.8a Rp 81,004.00 Rp 7,462,898.52
b. Aanstamping 11.40 M3 AHSP PU A.3.2.1.9 Rp 513,958.50 Rp 5,859,126.90
c. Urungan Tanah Kembali 23.03 M3 AHSP PU A.2.3.1.9 Rp 48,119.50 Rp 1,108,312.38
d. Urugan Pasir 5.70 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 1,373,130.00
e Pas. Batu Gunung 38.48 M3 AHSP PU A.3.2.1.2 Rp 962,830.00 Rp 37,044,884.25

5. Timbunan Tanah Bawah Lantai


a. Timbunan Tanah Bawah Lantai 92.42 M3 AHSP PU A.2.3.1.11.a Rp 141,900.00 Rp 13,114,308.60
SubTotal Rp 97,764,817.61

III. Pekerjaan Beton Bertulang


1. Pondasi Tapak 150/200
a Beton K-250 15.12 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 17,746,810.84
b Besi Tulangan ø 16-150 mm 1192.57 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 25,758,353.83
c Bekisting + Perawatan Beton 37.80 M2 AHSP PU A.4.1.1.20 Rp 297,209.00 Rp 11,234,500.20

2. Pondasi Tapak 125/125


a Beton K-250 15.95 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 18,717,339.56
b Besi Tulangan ø 16-150 mm 1257.79 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 27,167,013.81
c Bekisting + Perawatan Beton 39.87 M2 AHSP PU A.4.1.1.20 Rp 297,209.00 Rp 11,848,886.93

3. Pondasi Tapak 100/100


a Beton K-250 9.72 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 11,408,664.11
b Besi Tulangan ø 16-150 mm 78.87 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 1,703,594.83
c Bekisting + Perawatan Beton 2.50 M2 AHSP PU A.4.1.1.20 Rp 297,209.00 Rp 743,022.50
1 2 3 4 5 6 7
4. Sloof Beton 30/55
a Beton K-250 5.28 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 6,197,299.02
b Besi Tulanagan Pokok D16 404.03 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 10,126,614.09
c Besi Tulanagan Pinggang D16 113.63 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 2,848,110.21
d Besi Tulanagan Sengkang ∅ 10-150 mm 206.86 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 4,468,041.60
e Bekiting + Perawatan Beton 17.60 M2 AHSP PU A.4.1.1.21 Rp 297,209.00 Rp 5,230,878.40
f Pasir Urug 0.80 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 192,720.00
g Aantamping 1.60 M3 AHSP PU A.3.2.1.9 Rp 513,958.50 Rp 822,333.60

5. Sloof Beton 25/40


a Beton K-250 14.25 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 16,725,664.98
b Besi Tulanagan Pinggang D 16 506.02 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 12,682,990.79
c Besi Tulanagan Pokok D 16 632.53 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 15,853,738.48
d Besi Tulanagan Sengkang ∅ 10-150 mm 21.44 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 463,070.76
e Bekiting + Perawatan Beton 4.00 M2 AHSP PU A.4.1.1.21 Rp 297,209.00 Rp 1,188,836.00

6. Kolom 40/60
a Beton K-250 7.20 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 8,666,137.54
b Besi Tulanagan Pokok D16 801.20 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 20,081,402.08
c Besi Tulanagan Pinggang D16 400.60 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 10,040,701.04
d Besi Tulanagan Sengkang ∅ 10-100 mm 344.89 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 7,449,399.17
e Bekiting + Perawatan Beton 30.00 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 18,250,485.00

7. Kolom 40/40
a Beton K-250 14.40 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 17,332,275.09
b Besi Tulanagan Pokok D16 1420.42 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 35,601,377.64
c Besi Tulanagan Pinggang D16 568.17 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 14,240,551.06
d Besi Tulanagan Sengkang ∅ 10-100 mm 810.97 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 17,516,154.80
e Bekiting + Perawatan Beton 72.00 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 43,801,164.00

8. Kolom Praktis 13/13


a Beton K-250 0.76 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 914,006.69
b Besi Tulanagan Pokok ∅14 217.18 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 5,443,396.66
c Besi Tulanagan Sengkang ∅ 10-100 mm 102.54 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 2,214,866.00
d Bekiting + Perawatan Beton 11.68 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 7,107,160.02

9. Balok Lantai 25/60


a Beton K-250 4.80 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 5,633,908.20
b Besi Tulanagan Pokok D16 505.04 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 12,658,267.61
c Besi Tulanagan Pinggang D14 77.33 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 1,938,297.23
d Besi Tulanagan Sengkang ∅ 10-85 mm 36.69 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 792,557.27
e Bekiting + Perawatan Beton 19.36 M2 AHSP PU A.4.1.1.23 Rp 620,779.50 Rp 12,018,291.12

10. Balok Lantai 25/40


a Beton K-250 15.80 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 18,544,947.84
b Besi Tulanagan Pokok D16 1496.17 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 37,500,117.79
c Besi Tulanagan Pinggang D14 381.84 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 9,570,342.56
d Besi Tulanagan Sengkang ∅ 10-85 mm 750.52 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 16,210,539.20
e Bekiting + Perawatan Beton 63.99 M2 AHSP PU A.4.1.1.23 Rp 620,779.50 Rp 39,723,680.21

11. Balok Bordes 20/30


a Beton K-250 0.18 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 211,271.56
b Besi Tulanagan Pokok D12 13.32 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 333,762.92
c Besi Tulanagan Pinggang D12 5.33 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 133,505.17
d Besi Tulanagan Sengkang ∅ 10-100 mm 15.75 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 340,232.37
e Bekiting + Perawatan Beton 0.84 M2 AHSP PU A.4.1.1.23 Rp 620,779.50 Rp 521,454.78
1 2 3 4 5 6 7
12. Plat Bordes
a Beton K-250 0.50 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 586,137.72
b Besi Tulanagan Sengkang ∅ 10-100 mm 25.64 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 553,867.96
c Bekiting + Perawatan Beton 4.16 M2 AHSP PU A.4.1.1.24 Rp 915,909.50 Rp 3,811,557.38

13. Plat Tangga


a Beton K-250 1.01 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 1,190,163.11
b Besi Tulanagan Sengkang ∅ 10-100 mm 52.07 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 1,124,638.77
c Bekiting + Perawatan Beton 8.45 M2 AHSP PU A.4.1.1.26 Rp 564,734.50 Rp 4,772,006.53

14. Sloof Tangga 25/40


a Beton K-250 0.13 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 152,585.01
b Besi Tulanagan Pokok D12 5.77 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 144,630.60
c Besi Tulanagan Pinggang D12 4.62 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 115,704.48
d Besi Tulanagan Sengkang ∅ 10-100 mm 2.79 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 60,199.20
e Bekiting + Perawatan Beton 4.00 M2 AHSP PU A.4.1.1.21 Rp 297,209.00 Rp 1,188,836.00
SubTotal Rp 71,174,779.96

IV. Pekerjaan Dinding Dan Plasteran


a Pasangan Dinding Bata Adukan 1:4 162.84 M2 AHSP PU A.4.4.1.9 Rp 159,920.75 Rp 26,041,494.93
b Pasangan Dinding Bata Adukan 1:2 123.07 M2 AHSP PU A.4.4.1.7 Rp 170,143.88 Rp 20,940,287.27
c Plasteran Dinding Bata Adukan 1:4 325.68 M2 AHSP PU A.4.4.2.4 Rp 83,176.50 Rp 27,088,922.52
d Plasteran Dinding Bata Adukan 1:2 246.15 M2 AHSP PU A.4.4.2.2 Rp 88,366.30 Rp 21,751,188.01
e SubTotal Rp 95,821,892.73

V. Pekerjaan Lantai
a Urugan Tanah di Bawah Lantai 92.42 M3 AHSP PU A.2.3.1.9 Rp 48,119.50 Rp 4,447,173.87
b Pasir Urug 38.95 M3 AHSP PU A.2.3.1.11 Rp 240,900.00 Rp 9,382,123.92
c Beton Cor K-100 18.17 M3 AHSP PU A.4.1.1.1 Rp 987,814.14 Rp 17,953,386.72
d Lantai Keramik 40 x40 Cm 207.00 M2 AHSP PU A.4.4.3.34.a Rp 282,821.00 Rp 58,544,173.26
e Lantai Keramik 20 x20 Cm 14.78 M2 AHSP PU A.4.4.3.36 Rp 300,877.50 Rp 4,447,751.73
SubTotal Rp 212,347,690.25

VI. Pekerjaan Pintu, Jendela dan Ventilasi


a Kusen Pintu 1 Kayu Kelas I 0.09 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 927,066.94
b Kusen Pintu 2 Kayu Kelas I 0.15 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 1,602,178.41
c Kusen Jendela 1 Kayu Kelas I 0.52 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 5,345,978.35
d Kusen Ventilasi 1 Kayu Kelas I 0.51 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 5,232,921.41
e Daun Pintu 1 Kayu Kelas II 6.72 M2 AHSP PU A.4.6.1.5 Rp 866,800.00 Rp 5,824,896.00
f Daun Pintu 2 Kayu Kelas II 6.72 M2 AHSP PU A.4.6.1.5 Rp 866,800.00 Rp 5,824,896.00
g Daun Ambang Jendela Kayu Kelas II 2.64 M2 AHSP PU A.4.6.1.6 Rp 649,220.00 Rp 1,713,940.80
h Kaca Jendela Tebal 5 mm 4.83 M2 AHSP PU A.4.6.2.17 Rp 173,244.50 Rp 836,770.94
i Kaca Ventilasi Tebal 5 mm 2.84 M2 AHSP PU A.4.6.2.17 Rp 173,244.50 Rp 491,408.02
SubTotal Rp 27,800,056.87

VII. Pekerjaan Pengecatan


a Pengecatan Dinding Luar dan Dalam 325.68 M2 AHSP PU A.4.7.1.10 Rp 35,221.45 Rp 11,470,921.84
b Pengecatan Kusen 30.78 M2 AHSP PU A.4.7.1.4 Rp 53,410.50 Rp 1,644,178.15
SubTotal Rp 13,115,099.99
1 2 3 4 5 6 7
VIII. Pekerjaan Instalasi Listrik
a Box Sekering 1.00 Bh Taksir Rp 6,000,000.00 Rp 6,000,000.00
b Stop Kontak Tunggal 2.00 Bh Taksir Rp 15,000.00 Rp 30,000.00
c Saklar Tunggal 4.00 Bh Taksir Rp 15,000.00 Rp 60,000.00
d Saklar Double 2.00 Bh Taksir Rp 25,000.00 Rp 50,000.00
e Bola Lampu Philip 18 Watt 6.00 Bh Taksir Rp 30,000.00 Rp 180,000.00
f Bola Lampu TL 40 Watt 220 V. 13.00 Bh Taksir Rp 250,000.00 Rp 3,250,000.00
g Lampu barel 1.00 Bh Taksir Rp 200,000.00 Rp 200,000.00
h Kabel Instalasi ∅ 2.5 mm 1.00 Ls Taksir Rp 15,000.00 Rp 15,000.00
SubTotal Rp 9,785,000.00

IX. Pekerjaan Pengunci


a Kunci Tanam 2 Kali Putar 6.00 Bh Taksir Rp 45,000.00 Rp 270,000.00
b Engsel Pintu 24.00 Bh AHSP PU A.4.6.2.5 Rp 219,692.00 Rp 5,272,608.00
c Engsel Jendela 30.00 Bh AHSP PU A.4.6.2.6 Rp 219,692.00 Rp 6,590,760.00
d Hak Angin Jendela/Kait Angin 20.00 Bh AHSP PU A.4.6.2.9 Rp 45,892.00 Rp 917,840.00
e Tarikan Jendela/Pegangan 10.00 Bh Taksir Rp 10,000.00 Rp 100,000.00
f Grendel/Pacok Jendela 20.00 Bh AHSP PU A.4.6.2.10 Rp 35,442.00 Rp 708,840.00
g Grendel/Pacok Pintu 4.00 Bh Taksir Rp 40,000.00 Rp 160,000.00
SubTotal Rp 14,020,048.00

X. Sanitasi
a Pipa PVC ∅ 4" 1.00 Ls Taksir Rp 200,000.00 Rp 200,000.00
b Pipa PVC ∅ 3" 1.00 Ls Taksir Rp 150,000.00 Rp 150,000.00
c Pipa PVC ∅ 3/4" 1.00 Ls Taksir Rp 50,000.00 Rp 50,000.00
d Urinoir 3.00 Bh AHSP PU A.5.1.1.4 Rp 3,073,565.00 Rp 9,220,695.00
e Kloset Jongkok 3.00 Bh AHSP PU A.5.1.1.2 Rp 1,055,065.00 Rp 3,165,195.00
f Kran Air 6.00 Bh AHSP PU A.4.5.1.19 Rp 48,565.00 Rp 291,390.00
g Floor Drain 3.00 Bh AHSP PU A.4.5.1.14 Rp 48,565.00 Rp 145,695.00
h Rumah Pompa Sanyo Elektrik 1.00 Bh Taksir Rp 700,000.00 Rp 700,000.00
i Septictank 1.00 Bh Taksir Rp 12,000,000.00 Rp 12,000,000.00
j Resapan 1.00 Bh Taksir Rp 3,500,000.00 Rp 3,500,000.00
k Bak Kontrol 3.00 Bh Taksir Rp 1,000,000.00 Rp 3,000,000.00
SubTotal Rp 32,422,975.00
PEKERJAAN LANTAI II
No Item Pekerjaan Volume Satuan Analisa Harga Satuan (Rp) Jumlah (Rp)
1 2 3 4 5 6 7
I. Pekerjaan Beton Bertulang
1. Kolom 40/60
a Beton K-250 6.05 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 7,279,555.54
b Besi Tulanagan Pokok D16 111.28 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 2,789,083.62
c Besi Tulanagan Pinggang D16 55.64 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 1,394,541.81
d Besi Tulanagan Sengkang ∅ 10-100 mm 47.90 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 1,034,638.77
e Bekiting + Perawatan Beton 4.17 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 2,534,789.58

2. Kolom 40/40
a Beton K-250 12.10 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 14,559,111.07
b Besi Tulanagan Pokok D16 98.64 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 2,472,317.89
c Besi Tulanagan Pinggang D16 39.46 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 988,927.16
d Besi Tulanagan Sengkang ∅ 10-100 mm 56.32 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 1,216,399.64
e Bekiting + Perawatan Beton 5.00 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 3,041,747.50

3. Kolom Praktis 13/13


a Beton K-250 0.48 M3 AHSP PU A.4.1.1.8 Rp 1,203,630.21 Rp 576,677.29
b Besi Tulanagan Pokok D16 286.00 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 7,168,258.98
c Besi Tulanagan Sengkang ∅ 10-100 mm 135.04 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 2,916,695.97
d Bekiting + Perawatan Beton 15.38 M2 AHSP PU A.4.1.1.22 Rp 608,349.50 Rp 9,359,223.08

4 Plat Lantai
a Beton K-250 24.25 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 28,462,504.24
b Besi Tulangan sengkang ø 10-200 mm 1245.22 Kg AHSP PU A.4.1.17 Rp 21,599.05 Rp 26,895,503.38
c Bekiting + Perawatan Beton 202.08 M2 AHSP PU A.4.1.1.24 Rp 915,909.50 Rp 185,086,991.76

5 Ring Balok 25/35


a Beton K-250 13.20 M3 AHSP PU A.4.1.1.8 Rp 1,173,730.88 Rp 15,493,247.56
b Besi Tulanagan Pokok D16 90.19 Kg AHSP PU A.4.1.1.17.a Rp 25,064.05 Rp 2,260,404.93
c Besi Tulanagan Sengkang ∅ 10-100 mm 74.44 Kg AHSP PU A.4.1.1.17 Rp 21,599.05 Rp 1,607,884.58
d Bekiting + Perawatan Beton 4.06 M2 AHSP PU A.4.1.1.23 Rp 620,779.50 Rp 2,518,591.11
SubTotal Rp 319,657,095.46

II. Pekerjaan Pintu, Jendela dan Ventilasi


a Kusen Pintu 1 Kayu Kelas I 0.09 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 927,066.94
b Kusen Pintu 2 Kayu Kelas I 0.15 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 1,602,178.41
c Kusen Jendela 1 Kayu Kelas I 0.52 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 5,345,978.35
d Kusen Ventilasi 1 Kayu Kelas I 0.51 M2 AHSP PU A.4.6.1.1 Rp 10,353,200.00 Rp 5,232,921.41
e Daun Pintu 1 Kayu Kelas II 6.72 M2 AHSP PU A.4.6.1.5 Rp 866,800.00 Rp 5,824,896.00
f Daun Pintu 2 Kayu Kelas II 6.72 M2 AHSP PU A.4.6.1.5 Rp 866,800.00 Rp 5,824,896.00
g Daun Ambang Jendela Kayu Kelas II 2.64 M2 AHSP PU A.4.6.1.6 Rp 649,220.00 Rp 1,713,940.80
h Kaca Jendela Tebal 5 mm 4.83 M2 AHSP PU A.4.6.2.17 Rp 173,244.50 Rp 836,770.94
i Kaca Ventilasi Tebal 5 mm 2.84 M2 AHSP PU A.4.6.2.17 Rp 173,244.50 Rp 491,408.02
SubTotal Rp 27,800,056.87

III. Pekerjaan Dinding Dan Plasteran


1 Pasangan Dinding Bata Adukan 1:4 288.02 M2 AHSP PU A.4.4.1.9 Rp 159,920.75 Rp 46,059,894.65
2 Pasangan Dinding Bata Adukan 1:2 34.20 M2 AHSP PU A.4.4.1.7 Rp 170,143.88 Rp 5,818,920.53
3 Plasteran Dinding Bata Adukan 1:4 576.03 M2 AHSP PU A.4.4.2.4 Rp 83,176.50 Rp 47,912,492.00
4 Plasteran Dinding Bata Adukan 1:2 68.40 M2 AHSP PU A.4.4.2.2 Rp 88,366.30 Rp 6,044,254.92
SubTotal Rp 105,835,562.10

IV. Pekerjaan Lantai


1 Lantai Keramik 40 x40 Cm 192.87 M2 AHSP PU A.4.4.3.34.a Rp 282,821.00 Rp 54,546,569.13
2 Lantai Keramik 20 x20 Cm 14.78 M2 AHSP PU A.4.4.3.36 Rp 300,877.50 Rp 4,447,751.73
SubTotal Rp 58,994,320.86
1 2 3 4 5 6 7
V. Pekerjaan Pengecatan
1 Pengecatan Dinding 576.03 M2 AHSP PU A.4.7.1.11 Rp 26,771.80 Rp 15,421,467.04
2 Pengecatan Kusen 30.78 M2 AHSP PU A.4.7.1.4 Rp 53,410.50 Rp 1,644,178.15
SubTotal Rp 17,065,645.19

VI Pekerjaan Instalasi Listrik


a Box Sekering 1.00 Bh Taksir Rp 6,000,000.00 Rp 6,000,000.00
b Stop Kontak Tunggal 2.00 Bh Taksir Rp 15,000.00 Rp 30,000.00
c Saklar Tunggal 4.00 Bh Taksir Rp 15,000.00 Rp 60,000.00
d Saklar Double 2.00 Bh Taksir Rp 25,000.00 Rp 50,000.00
e Bola Lampu Philip 18 Watt 6.00 Bh Taksir Rp 30,000.00 Rp 180,000.00
f Bola Lampu TL 40 Watt 220 V. 14.00 Bh Taksir Rp 250,000.00 Rp 3,500,000.00
g Lampu barel 1.00 Bh Taksir Rp 350,000.00 Rp 350,000.00
h Kabel Instalasi ∅ 2.5 mm 1.00 Ls Taksir Rp 15,000.00 Rp 15,000.00
SubTotal Rp 10,185,000.00

VII. Pekerjaan Pengunci


a Kunci Tanam 2 Kali Putar 6.00 Bh Taksir Rp 45,000.00 Rp 270,000.00
b Engsel Pintu 24.00 Bh AHSP PU A.4.6.2.5 Rp 219,692.00 Rp 5,272,608.00
c Engsel Jendela 30.00 Bh AHSP PU A.4.6.2.6 Rp 219,692.00 Rp 6,590,760.00
d Hak Angin Jendela/Kait Angin 20.00 Bh AHSP PU A.4.6.2.9 Rp 45,892.00 Rp 917,840.00
e Tarikan Jendela/Pegangan 10.00 Bh Taksir Rp 10,000.00 Rp 100,000.00
f Grendel/Pacok Jendela 20.00 Bh AHSP PU A.4.6.2.10 Rp 35,442.00 Rp 708,840.00
g Grendel/Pacok Pintu 4.00 Bh Taksir Rp 40,000.00 Rp 160,000.00
SubTotal Rp 14,020,048.00

VIII. Sanitasi
a Pipa PVC ∅ 4" 1.00 Ls Taksir Rp 200,000.00 Rp 200,000.00
b Pipa PVC ∅ 3" 1.00 Ls Taksir Rp 150,000.00 Rp 150,000.00
c Pipa PVC ∅ 3/4" 1.00 Ls Taksir Rp 50,000.00 Rp 50,000.00
d Urinoir 3.00 Bh AHSP PU A.5.1.1.4 Rp 3,073,565.00 Rp 9,220,695.00
e Kloset Jongkok 3.00 Bh AHSP PU A.5.1.1.2 Rp 1,055,065.00 Rp 3,165,195.00
f Kran Air 6.00 Bh AHSP PU A.4.5.1.19 Rp 48,565.00 Rp 291,390.00
g Floor Drain 3.00 Bh AHSP PU A.4.5.1.14 Rp 48,565.00 Rp 145,695.00
h Rumah Pompa Sanyo Elektrik 1.00 Bh Taksir Rp 700,000.00 Rp 700,000.00
SubTotal Rp 13,922,975.00

IX. Pekerjaan Atap


1 Pek. Rangka Atap Baja Ringan 293.28 M2 Taksir Rp 350,000.00 Rp 102,648,000.00
2 Pek. Penutup Atap Seng Spandek 293.28 M2 AHSP PU A.4.5.2.32 Rp 143,605.00 Rp 42,116,474.40
3 Pek. Rabung Seng Spandek 28.20 M AHSP PU A.4.5.2.39.a Rp 83,242.50 Rp 2,347,438.50
4 Papan Lisplank 2,5/20 56.40 M AHSP PU A.4.6.1.21 Rp 106,909.00 Rp 6,029,667.60
SubTotal Rp 153,141,580.50
JUMLAH
No. URAIAN PEKERJAAN SATUAN
BANYAK BAHAN

1 Kayu Klas III 22.908 M3


2 Paku Kayu 4.745 Kg
3 Papan Kayu Klas. IV 0.553 M3
4 Urugan Pasir 17.249 M3
5 Semen Portland 86126.179 Kg
6 Pasir Urug 55.753 M3
7 Pasir Beton 82058.802 Kg
8 Kerikil 155444.760 Kg
9 Air 32276.390 Liter
10 Batu Gunung / Batu Kali 71.219 M3
11 Pasir Pasang 72.740 M3
12 Tanah Timbun 110.903 M3
13 Besi Beton Polos 54868.586 kg
14 Kawat Beton 1987.752 kg
15 Paku 5 Cm - 10 Cm 208.819 Kg
16 Minyak Bekisting 99.018 Liter
17 Besi Beton Ulir 87277.022 kg
18 Plywood Tebal 9 mm 129.210 Lbr
19 Kayu Dolken dia. 8 - 10 Cm, L = 4 M 1741.111 Batang
20 Balok Kayu Kelas II 5.802 M³
21 Batu Bata 42569.170 Bh
22 Keramik Lantai Uk. 40 x 40 Cm 2651.117 Bh
23 Keramik Lantai Uk. 20 x 20 Cm 783.478 Kg
24 Semen Warna 567.723 Kg
25 Atap Seng Genteng 337.272 Lbr
26 Paku Seng 58.656 Kg
27 Rabung Seng Genteng 8.460 M
28 Paku 5.640 kg
29 Balok Kayu Kelas 1 2.785 M3
30 Lem Kayu 14.196 Kg
31 Papan Kayu Kelas II 1.202 M3
32 Sealant 0.767 Tube
33 Kaca Tebal 5 mm 16.866 M2
34 Plamir 90.171 Kg
35 Cat Dasar Tembok 90.171 Kg
36 Cat Tembok / Penutup 2x 234.446 Kg
37 Cat Menie 12.314 Kg
38 Plamir Kayu 9.235 Kg
39 Cat Dasar Kayu 10.466 Kg
40 Cat Kayu Penutup 16.008 Kg
41 Kuas 0.616 Bh
42 Pengencer 1.847 Liter
43 Ampelas 12.314 Lembar
44 Kloset Jongkok Porselen 6.000 Bh
45 Urinoir 6.000 Bh
46 Engsel Pintu 48.000 Bh
47 Kunci Pintu Standar 12.000 Bh
48 Engsel Jendela 60.000 Bh
49 Pacok Jendela 40.000 Bh
50 Hak Angin Jendela 40.000 Bh
PERHITUNGAN JUMLAH BAHAN / MATERIAL

PEKERJAAN :
LOKASI :

NO URAIAN PEKERJAN VOL. SAT URAIAN BAHAN KOEF. JLH. BAHAN

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan 405.000 M²
B Pengukuran/Pemasangan Bowplank 79.000 M¹ Kayu Klas III 0.012 M3 0.948 M3
Paku Kayu 0.020 Kg 1.580 Kg
Papan Kayu Klas. IV 0.007 M3 0.553 M3

II PEKERJAAN TANAH DAN PONDASI `


A Pondasi Tapak
Galian Tanah Pondasi Tapak 173.223 M³
Urugan Kembali Pondasi Tapak 129.917 M³
Lapisan Pasir 7.874 M³ Urugan Pasir 1.200 M3 9.449 M3
Aanstamping 7.874 M³ Batu Gunung / Batu Kali 1.20 Kg 9.449 Kg
Pasir Urug 0.43 Kg 3.401 Kg

B Pondasi Menerus
Galian Pondasi Menerus 92.130 M³
Urugan Kembali Pondasi Menerus 23.033 M³
Alas Pasir Pondasi Menerus 5.700 M³ Urugan Pasir 1.200 M3 6.840 M3
Aanstamping 11.400 M³ Batu Gunung / Batu Kali 1.200 M3 13.680 M3
Pasir Urug 0.432 M3 4.925 M3
Pasangan Batu Gunung 38.475 M³ Batu Gunung / Batu Kali 1.200 M3 46.170 M3
Semen Portland 163.000 Kg 6,271.425 Kg
Pasir Pasang 0.520 M3 20.007 M3

C Timbunan Tanah Bawah Lantai


Timbunan Tanah Bawah Lantai 92.419 M³ Tanah Timbun 1.200 M3 110.903 M3
Urugan Pasir Bawah Lantai 38.946 M³ Pasir Urug 1.200 M3 46.735 M3

III PEKERJAAN BETON BERTULANG


A PONDASI
1 Pondasi Tapak 150/200
Beton K-250 15.120 M³ Semen Portland 384.00 Kg 5,806.080 Kg
Pasir Beton 692.00 Kg 10,463.040 Kg
Kerikil 1039.00 Kg 15,709.680 Kg
Air 215.00 Liter 3,250.800 Liter
Besi Tulangan pinggang ø 10-100 mm 1,192.569 Kg Besi Beton Polos 10.500 Kg 12,521.973 Kg
Kawat Beton 0.150 Kg 178.885 Kg
Bekisting + Perawatan Beton 39.867 M² Kayu Kelas III 0.040 M³ 1.595 M³
Paku 5 Cm - 10 Cm 0.300 Kg 11.960 Kg
Minyak Bekisting 0.100 Liter 3.987 Liter

2 Pondasi Tapak 125/125


Beton K-250 15.947 M³ Semen Portland 384.00 Kg 6,123.600 Kg
Pasir Beton 692.00 Kg 11,035.238 Kg
Kerikil 1039.00 Kg 16,568.803 Kg
Air 215.00 Liter 3,428.578 Liter
Besi Tulangan ø 16-150 mm 1,257.787 Kg Besi Beton Polos 10.500 Kg 13,206.768 Kg
Kawat Beton 0.150 Kg 188.668 Kg
Bekisting + Perawatan Beton 39.867 M² Kayu Kelas III 0.040 M³ 1.595 M³
Paku 5 Cm - 10 Cm 0.300 Kg 11.960 Kg
Minyak Bekisting 0.100 Liter 3.987 Liter

3 Pondasi Tapak 100/100


Beton K-250 9.720 M³ Semen Portland 384.00 Kg 3,732.480 Kg
Pasir Beton 692.00 Kg 6,726.240 Kg
Kerikil 1039.00 Kg 10,099.080 Kg
Air 215.00 Liter 2,089.800 Liter
Besi Tulangan ø 16-150 mm 78.874 Kg Besi Beton Polos 10.500 Kg 828.173 Kg
Kawat Beton 0.150 Kg 11.831 Kg
Bekisting + Perawatan Beton 2.500 M² Kayu Kelas III 0.040 M³ 0.100 M³
Paku 5 Cm - 10 Cm 0.300 Kg 0.750 Kg
Minyak Bekisting 0.100 Liter 0.250 Liter

B SLOFF
1 Sloof Beton 30/55
Beton K-250 5.280 M³ Semen Portland 384.000 Kg 2,027.520 Kg
Pasir Beton 692.000 Kg 3,653.760 Kg
Kerikil 1039.000 Kg 5,485.920 Kg
Air 215.000 Liter 1,135.200 Liter
Besi Tulanagan Pokok D16 404.029 Kg Besi Beton Ulir 10.500 Kg 4,242.309 kg
Kawat Beton 0.150 Kg 60.604 kg
Besi Tulanagan Pinggang D16 113.633 Kg Besi Beton Ulir 10.500 Kg 1,193.149 kg
Kawat Beton 0.150 Kg 17.045 kg
Besi Tulanagan Sengkang ∅ 10-150 mm 206.863 Kg Besi Beton Polos 10.500 Kg 2,172.060 kg
Kawat Beton 0.150 Kg 31.029 kg
Bekiting + Perawatan Beton 17.600 M² Kayu Kelas III 0.040 M³ 0.704 M³
Paku 5 Cm - 10 Cm 0.300 Kg 5.280 Kg
Minyak Bekisting 0.100 Liter 1.760 Liter
Lapisan Pasir 0.800 M³ Urugan Pasir 1.200 M3 0.960 M3
Aanstamping 1.600 M³ Batu Gunung / Batu Kali 1.200 Kg 1.920 Kg
Pasir Urug 0.432 Kg 0.691 Kg
2 Sloof Beton 25/40
Beton K-250 14.250 M³ Semen Portland 384.000 Kg 5,472.000 Kg
Pasir Beton 692.000 Kg 9,861.000 Kg
Kerikil 1039.000 Kg 14,805.750 Kg
Air 215.000 Liter 3,063.750 Liter
Besi Tulanagan Pinggang D 16 506.023 Kg Besi Beton Ulir 10.500 Kg 5,313.244 kg
Kawat Beton 0.150 Kg 75.903 kg
Besi Tulanagan Pokok D 16 632.529 Kg Besi Beton Ulir 10.500 Kg 6,641.555 kg
Kawat Beton 0.150 Kg 94.879 kg
Besi Tulanagan Sengkang ∅ 10-150 mm 21.439 Kg Besi Beton Polos 10.500 Kg 225.114 kg
Kawat Beton 0.150 Kg 3.216 kg
Bekiting + Perawatan Beton 4.000 M² Kayu Kelas III 0.040 M³ 0.160 M³
Paku 5 Cm - 10 Cm 0.300 Kg 1.200 Kg
Minyak Bekisting 0.100 Liter 0.400 Liter

LANTAI 1
1 KOLOM
Kolom 40/60
Beton K-250 7.200 M³ Semen Portland 406.000 Kg 2,923.200 Kg
Pasir Beton 684.000 Kg 4,924.800 Kg
Kerikil 1026.000 Kg 7,387.200 Kg
Air 215.000 Liter 1,548.000 Liter
Besi Tulanagan Pokok D16 801.203 Kg Besi Beton Ulir 10.500 Kg 8,412.636 Kg
Kawat Beton 0.150 Kg 120.181 Kg
Besi Tulanagan Pinggang D16 400.602 Kg Besi Beton Ulir 10.500 Kg 4,206.318 Kg
Kawat Beton 0.150 Kg 60.090 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 344.895 Kg Besi Beton Polos 10.500 Kg 3,621.395 Kg
Kawat Beton 0.150 Kg 51.734 Kg
Bekiting + Perawatan Beton 30.000 M² Kayu Kelas III 0.040 M³ 1.200 M³
Paku 5 Cm - 10 Cm 0.400 Kg 12.000 Kg
Minyak Bekisting 0.200 Liter 6.000 Liter
Balok Kayu Kelas II 0.015 M³ 0.450 M³
Plywood Tebal 9 mm 0.350 Lbr 10.500 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 60.000 Batang
Kolom 40/40
Beton K-250 14.400 M³ Semen Portland 406.000 Kg 5,846.400 Kg
Pasir Beton 684.000 Kg 9,849.600 Kg
Kerikil 1026.000 Kg 14,774.400 Kg
Air 215.000 Liter 3,096.000 Liter
Besi Tulanagan Pokok D16 1,420.416 Kg Besi Beton Ulir 10.500 Kg 14,914.368 Kg
Kawat Beton 0.150 Kg 213.062 Kg
Besi Tulanagan Pinggang D16 568.166 Kg Besi Beton Ulir 10.500 Kg 5,965.747 Kg
Kawat Beton 0.150 Kg 85.225 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 810.969 Kg Besi Beton Polos 10.500 Kg 8,515.172 Kg
Kawat Beton 0.150 Kg 121.645 Kg
Bekiting + Perawatan Beton 72.000 M² Kayu Kelas III 0.040 M³ 2.880 M³
Paku 5 Cm - 10 Cm 0.400 Kg 28.800 Kg
Minyak Bekisting 0.200 Liter 14.400 Liter
Balok Kayu Kelas II 0.015 M³ 1.080 M³
Plywood Tebal 9 mm 0.350 Lbr 25.200 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 144.000 Batang

Kolom KP 13/13
Beton K-250 0.759 M³ Semen Portland 406.000 Kg 308.306 Kg
Pasir Beton 684.000 Kg 519.413 Kg
Kerikil 1026.000 Kg 779.119 Kg
Air 215.000 Liter 163.266 Liter
Besi Tulanagan Pokok ∅14 217.179 Kg Besi Beton Ulir 10.500 Kg 2,280.384 Kg
Kawat Beton 0.150 Kg 32.577 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 102.545 Kg Besi Beton Polos 10.500 Kg 1,076.718 Kg
Kawat Beton 0.150 Kg 15.382 Kg
Bekiting + Perawatan Beton 11.683 M² Kayu Kelas III 0.040 M³ 0.467 M³
Paku 5 Cm - 10 Cm 0.400 Kg 4.673 Kg
Minyak Bekisting 0.200 Liter 2.337 Liter
Balok Kayu Kelas II 0.015 M³ 0.175 M³
Plywood Tebal 9 mm 0.350 Lbr 4.089 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 23.365 Batang

2 BALOK LANTAI
Balok Lantai 25/60
Beton K-250 4.800 Semen Portland 384.000 Kg 1,843.200 Kg
Pasir Beton 692.000 Kg 3,321.600 Kg
Kerikil 1039.000 Kg 4,987.200 Kg
Air 215.000 Liter 1,032.000 Liter
Besi Tulanagan Pokok D16 505.037 Besi Beton Ulir 10.500 Kg 5,302.886 Kg
Kawat Beton 0.150 Kg 75.756 Kg
Besi Tulanagan Pinggang D14 77.334 Besi Beton Ulir 10.500 Kg 812.004 Kg
Kawat Beton 0.150 Kg 11.600 Kg
Besi Tulanagan Sengkang ∅ 10-85 mm 36.694 Besi Beton Polos 10.500 Kg 385.288 Kg
Kawat Beton 0.150 Kg 5.504 Kg
Bekiting + Perawatan Beton 19.360 M² Kayu Kelas III 0.040 M³ 0.774 M³
Paku 5 Cm - 10 Cm 0.400 Kg 7.744 Kg
Minyak Bekisting 0.200 Liter 3.872 Liter
Balok Kayu Kelas II 0.018 M³ 0.348 M³
Plywood Tebal 9 mm 0.350 Lbr 6.776 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 38.720 Batang

Balok Lantai 25/40


Beton K-250 15.800 Semen Portland 384.000 Kg 6,067.200 Kg
Pasir Beton 692.000 Kg 10,933.600 Kg
Kerikil 1039.000 Kg 16,416.200 Kg
Air 215.000 Liter 3,397.000 Liter
Besi Tulanagan Pokok D16 1,496.172 Besi Beton Ulir 10.500 Kg 15,709.801 Kg
Kawat Beton 0.150 Kg 224.426 Kg
Besi Tulanagan Pinggang D14 381.835 Besi Beton Ulir 10.500 Kg 4,009.272 Kg
Kawat Beton 0.150 Kg 57.275 Kg
Besi Tulanagan Sengkang ∅ 10-85 mm 750.521 Besi Beton Polos 10.500 Kg 7,880.470 Kg
Kawat Beton 0.150 Kg 112.578 Kg
Bekiting + Perawatan Beton 63.990 M² Kayu Kelas III 0.040 M³ 2.560 M³
Paku 5 Cm - 10 Cm 0.400 Kg 25.596 Kg
Minyak Bekisting 0.200 Liter 12.798 Liter
Balok Kayu Kelas II 0.018 M³ 1.152 M³
Plywood Tebal 9 mm 0.350 Lbr 22.397 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 127.980 Batang

3 TANGGA
Balok Bordes 20/30
Beton K-250 0.180 Semen Portland 384.000 Kg 69.120 Kg
Pasir Beton 692.000 Kg 124.560 Kg
Kerikil 1039.000 Kg 187.020 Kg
Air 215.000 Liter 38.700 Liter
Besi Tulanagan Pokok D12 13.316 Besi Beton Ulir 10.500 Kg 139.822 Kg
Kawat Beton 0.150 Kg 1.997 Kg
Besi Tulanagan Pinggang D12 5.327 Besi Beton Ulir 10.500 Kg 55.929 Kg
Kawat Beton 0.150 Kg 0.799 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 15.752 Besi Beton Polos 10.500 Kg 165.398 Kg
Kawat Beton 0.150 Kg 2.363 Kg
Bekiting + Perawatan Beton 0.840 M² Kayu Kelas III 0.040 M³ 0.034 M³
Paku 5 Cm - 10 Cm 0.400 Kg 0.336 Kg
Minyak Bekisting 0.200 Liter 0.168 Liter
Balok Kayu Kelas II 0.018 M³ 0.015 M³
Plywood Tebal 9 mm 0.350 Lbr 0.294 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 1.680 Batang

Plat Bordes
Beton K-250 0.499 Semen Portland 384.000 Kg 191.762 Kg
Pasir Beton 692.000 Kg 345.571 Kg
Kerikil 1039.000 Kg 518.856 Kg
Air 215.000 Liter 107.367 Liter
Besi Tulanagan Sengkang ∅ 10-100 mm 25.643 Besi Beton Ulir 10.500 Kg 269.253 Kg
Kawat Beton 0.150 Kg 3.846 Kg
Bekiting + Perawatan Beton 4.162 M² Kayu Kelas III 0.040 M³ 0.166 M³
Paku 5 Cm - 10 Cm 0.400 Kg 1.665 Kg
Minyak Bekisting 0.200 Liter 0.832 Liter
Balok Kayu Kelas II 0.015 M³ 0.062 M³
Plywood Tebal 9 mm 0.350 Lbr 1.457 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 6.000 Batang 24.969 Batang
Plat Tangga
Beton K-250 1.014 Semen Portland 384.000 Kg 389.376 Kg
Pasir Beton 692.000 Kg 701.688 Kg
Kerikil 1039.000 Kg 1,053.546 Kg
Air 215.000 Liter 218.010 Liter
Besi Tulanagan Sengkang ∅ 10-100 mm 52.069 Besi Beton Ulir 10.500 Kg 546.723 Kg
Kawat Beton 0.150 Kg 7.810 Kg
Bekiting + Perawatan Beton 8.450 M² Kayu Kelas III 0.040 M³ 0.338 M³
Paku 5 Cm - 10 Cm 0.400 Kg 3.380 Kg
Minyak Bekisting 0.200 Liter 1.690 Liter
Balok Kayu Kelas II 0.015 M³ 0.127 M³
Plywood Tebal 9 mm 0.350 Lbr 2.958 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 6.000 Batang 50.700 Batang

Sloof Tangga 25/40


Beton K-250 0.130 Semen Portland 384.000 Kg 49.920 Kg
Pasir Beton 692.000 Kg 89.960 Kg
Kerikil 1039.000 Kg 135.070 Kg
Air 215.000 Liter 27.950 Liter
Besi Tulanagan Pokok D12 5.770 Besi Beton Ulir 10.500 Kg 60.590 Kg
Kawat Beton 0.150 Kg 0.866 Kg
Besi Tulanagan Pinggang D12 4.616 Besi Beton Ulir 10.500 Kg 48.472 Kg
Kawat Beton 0.150 Kg 0.692 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 2.787 Besi Beton Polos 10.500 Kg 29.265 Kg
Kawat Beton 0.150 Kg 0.418 Kg
Bekiting + Perawatan Beton 4.000 M² Kayu Kelas III 0.040 M³ 0.160 M³
Paku 5 Cm - 10 Cm 0.300 Kg 1.200 Kg
Minyak Bekisting 0.100 Liter 0.400 Liter

LANTAI 2
1 KOLOM
Kolom 40/60
Beton K-275 6.048 Semen Portland 406.000 Kg 2,455.488 Kg
Pasir Beton 684.000 Kg 4,136.832 Kg
Kerikil 1026.000 Kg 6,205.248 Kg
Air 215.000 Liter 1,300.320 Liter
Besi Tulangan Pokok ø 16 111.278 Besi Beton Ulir 10.500 Kg 1,168.422 Kg
Kawat Beton 0.150 Kg 16.692 Kg
Besi Tulangan pinggang ø 12 55.639 Besi Beton Ulir 10.500 Kg 584.211 Kg
Kawat Beton 0.150 Kg 8.346 Kg
Besi Tulangan sengkang ø 10-200 mm 47.902 Besi Beton Polos 10.500 Kg 502.972 Kg
Kawat Beton 0.150 Kg 7.185 Kg
Bekiting + Perawatan Beton 4.167 M² Kayu Kelas III 0.040 M³ 0.167 M³
Paku 5 Cm - 10 Cm 0.400 Kg 1.667 Kg
Minyak Bekisting 0.200 Liter 0.833 Liter
Balok Kayu Kelas II 0.015 M³ 0.063 M³
Plywood Tebal 9 mm 0.350 Lbr 1.458 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 8.333 Batang

Kolom 40/40
Beton K-250 12.096 Semen Portland 406.000 Kg 4,910.976 Kg
Pasir Beton 684.000 Kg 8,273.664 Kg
Kerikil 1026.000 Kg 12,410.496 Kg
Air 215.000 Liter 2,600.640 Liter
Besi Tulanagan Pokok D16 98.640 Besi Beton Ulir 10.500 Kg 1,035.720 Kg
Kawat Beton 0.150 Kg 14.796 Kg
Besi Tulanagan Pinggang D16 39.456 Besi Beton Ulir 10.500 Kg 414.288 Kg
Kawat Beton 0.150 Kg 5.918 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 56.317 Besi Beton Polos 10.500 Kg 591.331 Kg
Kawat Beton 0.150 Kg 8.448 Kg
Bekiting + Perawatan Beton 5.000 M² Kayu Kelas III 0.040 M³ 0.200 M³
Paku 5 Cm - 10 Cm 0.400 Kg 2.000 Kg
Minyak Bekisting 0.200 Liter 1.000 Liter
Balok Kayu Kelas II 0.015 M³ 0.075 M³
Plywood Tebal 9 mm 0.350 Lbr 1.750 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 10.000 Batang

Kolom Praktis 13/13


Beton K-250 0.479 Semen Portland 406.000 Kg 194.521 Kg
Pasir Beton 684.000 Kg 327.715 Kg
Kerikil 1026.000 Kg 491.572 Kg
Air 215.000 Liter 103.010 Liter
Besi Tulanagan Pokok D16 285.998 Besi Beton Ulir 10.500 Kg 3,002.975 Kg
Kawat Beton 0.150 Kg 42.900 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 135.038 Besi Beton Polos 10.500 Kg 1,417.901 Kg
Kawat Beton 0.150 Kg 20.256 Kg
Bekiting + Perawatan Beton 15.385 M² Kayu Kelas III 0.040 M³ 0.615 M³
Paku 5 Cm - 10 Cm 0.400 Kg 6.154 Kg
Minyak Bekisting 0.200 Liter 3.077 Liter
Balok Kayu Kelas II 0.015 M³ 0.231 M³
Plywood Tebal 9 mm 0.350 Lbr 5.385 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 30.769 Batang
4 PLAT LANTAI
Beton K-250 13.200 Semen Portland 384.000 Kg 5,068.800 Kg
Pasir Beton 692.000 Kg 9,134.400 Kg
Kerikil 1039.000 Kg 13,714.800 Kg
Air 215.000 Liter 2,838.000 Liter
Besi Tulangan sengkang ø 10-200 mm 90.185 Besi Beton Polos 10.500 Kg 946.944 Kg
Kawat Beton 0.150 Kg 13.528 Kg
Bekiting + Perawatan Beton 202.080 M² Kayu Kelas III 0.040 M³ 8.083 M³
Paku 5 Cm - 10 Cm 0.400 Kg 80.832 Kg
Minyak Bekisting 0.200 Liter 40.416 Liter
Balok Kayu Kelas II 0.015 M³ 3.031 M³
Plywood Tebal 9 mm 0.350 Lbr 70.728 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 6.000 Batang 1,212.480 Batang

5 RING BALOK
Ring Balok 25/35
Beton K-250 13.200 Semen Portland 384.000 Kg 5,068.800 Kg
Pasir Beton 692.000 Kg 9,134.400 Kg
Kerikil 1039.000 Kg 13,714.800 Kg
Air 215.000 Liter 2,838.000 Liter
Besi Tulanagan Pokok D16 90.185 Besi Beton Ulir 10.500 Kg 946.944 Kg
Kawat Beton 0.150 Kg 13.528 Kg
Besi Tulanagan Sengkang ∅ 10-100 mm 74.442 Besi Beton Polos 10.500 Kg 781.645 Kg
Kawat Beton 0.150 Kg 11.166 Kg
Bekiting + Perawatan Beton 4.057 M² Kayu Kelas III 0.040 M³ 0.162 M³
Paku 5 Cm - 10 Cm 0.400 Kg 1.623 Kg
Minyak Bekisting 0.200 Liter 0.811 Liter
Balok Kayu Kelas II 0.018 M³ 0.073 M³
Plywood Tebal 9 mm 0.350 Lbr 1.420 Lbr
Kayu Dolken dia. 8 - 10 Cm, L = 4 M 2.000 Batang 8.114 Batang

V PEKERJAAN PASANGAN DAN PLASTERAN


LANTAI 1
1 PASANGAN DINDING
Pasangan Dinding Bata Adukan 1:2 123.07 M² Batu Bata 70.000 Bh 8,615.180 Bh
Semen Portland 18.950 Kg 2,332.252 Kg
Pasir Pasang 0.038 M3 4.677 M3
Pasangan Dinding Bata Adukan 1:4 162.84 M² Batu Bata 70.000 Bh 11,398.800 Bh
Semen Portland 11.500 Kg 1,872.660 Kg
Pasir Pasang 0.043 M3 7.002 M3
2 PLESTERAN
Plasteran Dinding Bata Adukan 1:4 325.68 M² Semen Portland 6.240 Kg 2,032.243 Kg
Pasir Pasang 0.024 M3 7.816 M3
Plasteran Dinding Bata Adukan 1:2 246.15 M² Semen Portland 10.224 Kg 2,516.617 Kg
Pasir Pasang 0.020 M3 4.923 M3

LANTAI 2
1 PASANGAN DINDING
Pasangan Dinding Bata Adukan 1:4 288.02 M² Batu Bata 70.000 Bh 20,161.190 Bh
Semen Portland 11.500 Kg 3,312.196 Kg
Pasir Pasang 0.043 M3 12.385 M3
Pasangan Dinding Bata Adukan 1:2 34.20 M² Batu Bata 70.000 Bh 2,394.000 Bh
Semen Portland 18.950 Kg 648.090 Kg
Pasir Pasang 0.038 M3 1.300 M3
2 PLESTERAN
Plasteran Dinding Bata Adukan 1:4 576.03 M² Semen Portland 6.240 Kg 3,594.452 Kg
Pasir Pasang 0.024 M3 13.825 M3
Plasteran Dinding Bata Adukan 1:2 68.40 M² Semen Portland 10.224 Kg 699.322 Kg
Pasir Pasang 0.020 M3 1.368 M3

VI PEKERJAAN GRANIT DAN KERAMIK


LANTAI I
1 Lantai Keramik 40 x40 Cm 207.00 M² Keramik Lantai Uk. 40 x 40 Cm 6.630 Bh 1,372.415 Bh
Semen Portland 9.800 Kg 2,028.608 Kg
Semen Warna 1.300 Kg 269.101 Kg
Pasir Pasang 0.045 M3 9.315 M3
2 Lantai Keramik 20 x20 Cm 14.78 M² Keramik Lantai Uk. 20 x 20 Cm 26.500 Bh 391.739 Bh
Semen Portland 10.400 Kg 153.739 Kg
Semen Warna 1.620 Kg 23.948 Kg
Pasir Pasang 0.045 M3 0.665 M3

LANTAI II
1 Lantai Keramik 40 x40 Cm 192.87 M² Keramik Lantai Uk. 40 x 40 Cm 6.630 Bh 1,278.702 Bh
Semen Portland 9.800 Kg 1,890.087 Kg
Semen Warna 1.300 Kg 250.726 Kg
Pasir Pasang 0.045 M3 8.679 M3
2 Lantai Keramik 20 x20 Cm 14.78 M² Keramik Lantai Uk. 20 x 20 Cm 26.500 Bh 391.739 Bh
Semen Portland 10.400 Kg 153.739 Kg
Semen Warna 1.620 Kg 23.948 Kg
Pasir Pasang 0.045 M3 0.665 M3

VII PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC


LANTAI I
1 Reilling Tangga 40*40 7.70 M (Taksir)

2 PEMASANGAN PINTU
Kusen Pintu 1 Kayu Kelas I 0.09 M3 Balok Kayu Kelas 1 1.100 M3 0.098 M3
Paku Kayu 1.250 Kg 0.112 Kg
Lem Kayu 1.000 Kg 0.090 Kg
Kusen Pintu 2 Kayu Kelas I 0.15 M3 Balok Kayu Kelas 1 1.100 M3 0.170 M3
Paku Kayu 1.250 Kg 0.193 Kg
Lem Kayu 1.000 Kg 0.155 Kg
Daun Pintu 1 Kayu Kelas II 6.72 M² Papan Kayu Kelas II 0.040 M3 0.269 M3
Lem Kayu 0.500 Kg 3.360 Kg
Daun Pintu 2 Kayu Kelas II 6.72 M² Papan Kayu Kelas II 0.040 M3 0.269 M3
Lem Kayu 0.500 Kg 3.360 Kg

3 PEMASANGAN JENDELA
Kusen Jendela 1 Kayu Kelas I 0.52 M3 Balok Kayu Kelas 1 1.100 M3 0.568 M3
Paku Kayu 1.250 Kg 0.645 Kg
Lem Kayu 1.000 Kg 0.516 Kg
Daun Ambang Jendela Kayu Kelas II 2.64 M² Papan Kayu Kelas II 0.024 M3 0.063 M3
Lem Kayu 0.300 Kg 0.792 Kg
Kaca Jendela Tebal 5 mm 4.83 M² Kaca Tebal 5 mm 1.100 M2 5.313 M2
Sealant 0.050 Tube 0.242 Tube

4 PEMASANGAN VENTILASI
Kusen Ventilasi 1 Kayu Kelas I 0.51 M3 Balok Kayu Kelas 1 1.100 M3 0.556 M3
Paku Kayu 1.250 Kg 0.632 Kg
Lem Kayu 1.000 Kg 0.505 Kg
Kaca Ventilasi Tebal 5 mm 2.84 M² Kaca Tebal 5 mm 1.100 M2 3.120 M2
Sealant 0.050 Tube 0.142 Tube

LANTAI II
1 PEMASANGAN PINTU
Kusen Pintu 1 Kayu Kelas I 0.09 M3 Balok Kayu Kelas 1 1.100 M3 0.098 M3
Paku Kayu 1.250 Kg 0.112 Kg
Lem Kayu 1.000 Kg 0.090 Kg
Kusen Pintu 2 Kayu Kelas I 0.15 M3 Balok Kayu Kelas 1 1.100 M3 0.170 M3
Paku Kayu 1.250 Kg 0.193 Kg
Lem Kayu 1.000 Kg 0.155 Kg
Daun Pintu 1 Kayu Kelas II 6.72 M² Papan Kayu Kelas II 0.040 M3 0.269 M3
Lem Kayu 0.500 Kg 3.360 Kg
Daun Pintu 2 Kayu Kelas II 6.72 M² Papan Kayu Kelas II 0.040 M3 0.269 M3
Lem Kayu 0.500 Kg 3.360 Kg

2 PEMASANGAN JENDELA
Kusen Jendela 1 Kayu Kelas I 0.52 M3 Balok Kayu Kelas 1 1.100 M3 0.568 M3
Paku Kayu 1.250 Kg 0.645 Kg
Lem Kayu 1.000 Kg 0.516 Kg
Daun Ambang Jendela Kayu Kelas II 2.64 M² Papan Kayu Kelas II 0.024 M3 0.063 M3
Lem Kayu 0.300 Kg 0.792 Kg
Kaca Jendela Tebal 5 mm 4.83 M² Kaca Tebal 5 mm 1.100 M2 5.313 M2
Sealant 0.050 Tube 0.242 Tube

3 PEMASANGAN VENTILASI
Kusen Ventilasi 1 Kayu Kelas I 0.51 M3 Balok Kayu Kelas 1 1.100 M3 0.556 M3
Paku Kayu 1.250 Kg 0.632 Kg
Lem Kayu 1.000 Kg 0.505 Kg
Kaca Ventilasi Tebal 5 mm 2.84 M² Kaca Tebal 5 mm 1.100 M2 3.120 M2
Sealant 0.050 Tube 0.142 Tube

VIII PEKERJAAN ATAP


1 Rangka Baja Ringan C75-75 293.28 M² Taksir
2 Penutup Atap Seng Spandek 293.28 M² Atap Seng Genteng 1.15 Lbr 337.272 Lbr
Paku Seng 0.2 Kg 58.656 Kg
3 Rabung Seng Spandek 28.20 M Rabung Seng Genteng 0.3 M 8.460 M
Paku Seng 0.216 Kg 6.091 Kg
4 List Plank 56.40 M Kayu Kelas II 0.0108 M3 0.609 M3
Paku 0.1 Kg 5.640 Kg

IX PEKERJAAN PENGECATAN
LANTAI 1
1 Pengecatan Dinding 325.68 M² Plamir 0.100 Kg 32.568 Kg 90.171
Cat Dasar Tembok 0.100 Kg 32.568 Kg 90.171
Cat Tembok / Penutup 2x 0.260 Kg 84.677 Kg 234.446
2 Pengecatan Kusen 30.78 M² Cat Menie 0.200 Kg 6.157 Kg 12.314
Plamir Kayu 0.150 Kg 4.618 Kg 9.235
Cat Dasar Kayu 0.170 Kg 5.233 Kg 10.466
Cat Kayu Penutup 0.260 Kg 8.004 Kg 16.008
Kuas 0.010 Bh 0.308 Bh 0.616
Pengencer 0.030 Liter 0.924 Liter 1.847
Ampelas 0.200 Lembar 6.157 Lembar 12.314

LANTAI 2
1 Pengecatan Dinding 576.03 M² Plamir 0.100 Kg 57.603 Kg
Cat Dasar Tembok 0.100 Kg 57.603 Kg
Cat Tembok / Penutup 2x 0.260 Kg 149.769 Kg
2 Pengecatan Kusen 30.78 M² Cat Menie 0.200 Kg 6.157 Kg
Plamir Kayu 0.150 Kg 4.618 Kg
Cat Dasar Kayu 0.170 Kg 5.233 Kg
Cat Kayu Penutup 0.260 Kg 8.004 Kg
Kuas 0.010 Bh 0.308 Bh
Pengencer 0.030 Liter 0.924 Liter
Ampelas 0.200 Lembar 6.157 Lembar

X PEKERJAAN ELEKTRIKAL
LANTAI 1
1 Box Sekering 1 Bh (Taksir) 1.000 Bh 1 Bh
2 Stop Kontak Tunggal 2 Bh (Taksir) 1.000 Bh 2 Bh
3 Saklar Tunggal 4 Bh (Taksir) 1.000 Bh 4 Bh
4 Saklar Double 2 Bh (Taksir) 1.000 Bh 2 Bh
5 Bola Lampu Philip 18 Watt 6 Bh (Taksir) 1.000 Bh 6 Bh
6 Bola Lampu TL 40 Watt 220 V. 13 Bh (Taksir) 1.000 Bh 13 Bh
7 Lampu barel 1 Bh (Taksir) 1.000 Bh 1 Bh
8 Kabel Instalasi ∅ 2.5 mm 1 Bh (Taksir) 1.000 Bh 1 Bh
LANTAI 2
1 Box Sekering 1 Bh (Taksir) 1.000 Bh 1 Bh
2 Stop Kontak Tunggal 2 Bh (Taksir) 1.000 Bh 2 Bh
3 Saklar Tunggal 4 Bh (Taksir) 1.000 Bh 4 Bh
4 Saklar Double 2 Bh (Taksir) 1.000 Bh 2 Bh
5 Bola Lampu Philip 18 Watt 6 Bh (Taksir) 1.000 Bh 6 Bh
6 Bola Lampu TL 40 Watt 220 V. 14 Bh (Taksir) 1.000 Bh 14 Bh
7 Lampu barel 1 Bh (Taksir) 1.000 Bh 1 Bh
8 Kabel Instalasi ∅ 2.5 mm 1 Bh (Taksir) 1.000 Bh 1 Bh

XI PEKERJAAN SANITASI
1 Urinoir 6 Bh Urinoir 1 Bh 6 Bh
Semen Portland 6 Kg 36 Kg
Pasir Pasang 0.01 M3 0.060 M3
Perlengkapan 30 % 2 %
2 Kloset Jongkok 6 Bh Kloset Jongkok Porselen 1 Bh 6 Bh
Semen Portland 6 Kg 36 Kg
Pasir Pasang 0.01 M3 0.060 M3
3 Kran Air 12 Bh Kran Air 1 Bh 12 Bh
4 Floor Drain 6 Bh Floor Drain 1 Bh 6 Bh
5 Rumah Pompa Sanyo Elektrik 2 Bh (Taksir) 1.000 Bh 2 Bh
6 Septictank 1 Bh (Taksir) 1.000 Bh 1 Bh
7 Resapan 1 Bh (Taksir) 1.000 Bh 1 Bh
8 Bak Kontrol 3 Bh (Taksir) 1.000 Bh 3 Bh
9 Pipa PVC ∅ 4" 2 Ls (Taksir) 1.000 Bh 2 Bh
10 Pipa PVC ∅ 3" 2 Ls (Taksir) 1.000 Bh 2 Bh
11 Pipa PVC ∅ 3/4" 2 Ls (Taksir) 1.000 Bh 2 Bh

XII PEKERJAAN KUNCI DAN PENGGANTUNG


1 Engsel Pintu 48 Bh Engsel Pintu 1.000 Bh 48 Bh
2 Engsel Jendela 60 Bh Engsel Jendela 1.000 Bh 60 Bh
3 Hak Angin Jendela/Kait Angin 40 Bh Hak Angin Jendela 1.000 Bh 40 Bh
4 Grendel/Pacok Jendela 40 Bh Pacok Jendela 1.000 Bh 40 Bh
5 Kunci Tanam 2 Kali Putar 12 Bh Kunci Pintu Standar 1.000 Bh 12 Bh
6 Tarikan Jendela/Pegangan 20 Bh (Taksir) 1.000 Bh 20 Bh
7 Grendel/Pacok Pintu 8 Bh (Taksir) 1.000 Bh 8 Bh
REKAPITULASI ANALISA TEKNIS

NO URAIAN PEKERJAAN VOLUME SATUAN HARI


I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 405.000 m2 3
2 Pengukuran dan pemasangan bouwplank 79.000 m 2
Total Hari Pekerjaan 5
II PEKERJAAN TANAH DAN PONDASI
A Pondasi Tapak
1 Galian Tanah 173.22 m3 5
2 Aanstamping 7.87 m 3
1
3 Urungan Tanah Kembali 129.92 m 3
4
4 Urugan Pasir 7.87 m 3
1

B Pondasi Menerus
1 Galian Pondasi Menerus 92.13 m3 4
2 Urugan Kembali Pondasi Menerus 23.03 m3 1
3 Alas Pasir Pondasi Menerus 5.700 m3 1
4 Aanstamping 11.400 m3 2
5 Pasangan Batu Gunung 38.475 m 3
6

C. Timbunan Tanah Bawah Lantai


1 Timbunan Tanah Bawah Lantai 92.419 m3 4
2 Urugan Pasir Bawah Lantai 38.946 m 3
2
Total Hari Pekerjaan 31

III PEKERJAAN BETON BERTULANG


LANTAI 1
1 Pondasi Tapak 150/200
a Beton K-250 15.120 m3 3
b Besi Tulangan pinggang ø 10-100 mm 1192.569 kg 7
c Bekisting + Perawatan Beton 37.800 m2 3
2 Pondasi Tapak 125/125
a Beton K-250 15.947 m3 3
b Besi Tulangan ø 16-150 mm 1257.787 kg 9
c Bekisting + Perawatan Beton 39.867 m2 2
3 Pondasi Tapak 100/100
a Beton K-250 9.720 m3 2
b Besi Tulangan ø 16-150 mm 78.874 kg 1
c Bekisting + Perawatan Beton 2.500 m2 1
4 Sloof Beton 30/55
a Beton K-250 5.280 m3 1
b Besi Tulanagan Pokok D16 404.029 kg 6
c Besi Tulanagan Pinggang D16 113.633 kg 3
d Besi Tulanagan Sengkang ∅ 10-150 mm 206.863 kg 5
e Bekiting + Perawatan Beton 17.600 m2 2
f Pasir Urug 0.800 kg 0
g Aantamping 1.600 kg 1
5 Sloof Beton 25/40
a Beton K-250 14.250 m3 3
b Besi Tulanagan Pinggang D 16 506.023 kg 3
c Besi Tulanagan Pokok D 16 632.529 kg 4
d Besi Tulanagan Sengkang ∅ 10-150 mm 21.439 kg 1
e Bekiting + Perawatan Beton 4.000 m2 1
6 Kolom 40/60
a Beton K-250 7.200 m3 0
b Besi Tulanagan Pokok D16 801.203 kg 4
c Besi Tulanagan Pinggang D16 400.602 kg 2
d Besi Tulanagan Sengkang ∅ 10-100 mm 344.895 kg 2
e Bekiting + Perawatan Beton 30.000 m2 1
7 Kolom 40/40
a Beton K-250 14.400 m3 1
b Besi Tulanagan Pokok D16 1420.416 kg 7
c Besi Tulanagan Pinggang D16 568.166 kg 3
d Besi Tulanagan Sengkang ∅ 10-100 mm 810.969 kg 5
e Bekiting + Perawatan Beton 72.000 m2 3
8 Kolom Praktis 13/13
a Beton K-250 0.759 m3 0
b Besi Tulanagan Pokok ∅14 217.179 kg 2
c Besi Tulanagan Sengkang ∅ 10-100 mm 102.545 kg 2
d Bekiting + Perawatan Beton 11.683 kg 1
9 Balok Lantai 25/60
a Beton K-250 4.800 m3 1
b Besi Tulanagan Pokok D16 505.037 kg 3
c Besi Tulanagan Pinggang D14 77.334 kg 1
d Besi Tulanagan Sengkang ∅ 10-85 mm 36.694 kg 1
e Bekiting + Perawatan Beton 19.360 m2 1
10 Balok Lantai 25/40
a Beton K-250 15.800 m3 1
b Besi Tulanagan Pokok D16 1496.172 kg 5
c Besi Tulanagan Pinggang D14 381.835 kg 4
d Besi Tulanagan Sengkang ∅ 10-85 mm 750.521 kg 4
e Bekiting + Perawatan Beton 63.990 m2 2
11 Balok Bordes 20/30
a Beton K-250 0.180 m3 0
b Besi Tulanagan Pokok D12 13.316 kg 1
c Besi Tulanagan Pinggang D12 5.327 kg 0
d Besi Tulanagan Sengkang ∅ 10-100 mm 15.752 kg 1
e Bekiting + Perawatan Beton 0.840 m2 0
12 Plat Bordes
a Beton K-250 0.499 m3 1
b Besi Tulanagan Sengkang ∅ 10-100 mm 25.643 kg 1
c Bekiting + Perawatan Beton 4.162 m2 1
13 Plat Tangga
a Beton K-250 1.014 m3 1
b Besi Tulanagan Sengkang ∅ 10-100 mm 52.069 kg 1
c Bekiting + Perawatan Beton 8.450 m2 1
14 Sloof Tangga 25/40
a Beton K-250 0.130 m3 0
b Besi Tulanagan Pokok D12 5.770 kg 1
c Besi Tulanagan Pinggang D12 4.616 kg 0
d Besi Tulanagan Sengkang ∅ 10-100 mm 2.787 kg 0
e Bekiting + Perawatan Beton 4.000 m2 1
LANTAI 2
1 Kolom 40/60
a Beton K-250 6.048 m3 1
b Besi Tulanagan Pokok D16 111.278 kg 1
c Besi Tulanagan Pinggang D16 55.639 kg 1
d Besi Tulanagan Sengkang ∅ 10-100 mm 47.902 kg 1
e Bekiting + Perawatan Beton 4.167 m2 1
2 Kolom 40/40
a Beton K-250 12.096 m3 2
b Besi Tulanagan Pokok D16 98.640 kg 1
c Besi Tulanagan Pinggang D16 39.456 kg 1
d Besi Tulanagan Sengkang ∅ 10-100 mm 56.317 kg 1
e Bekiting + Perawatan Beton 5.000 m2 1
3 Kolom Praktis 13/13
a Beton K-250 0.479 m3 0
b Besi Tulanagan Pokok D16 285.998 kg 4
c Besi Tulanagan Sengkang ∅ 10-100 mm 135.038 kg 3
d Bekiting + Perawatan Beton 15.385 m2 2
4 Plat Lantai
a Beton K-250 24.250 m3 5
b Besi Tulangan sengkang ø 10-200 mm 1245.217 kg 8
c Bekiting + Perawatan Beton 202.080 m2 7
5 Ring Balok 25/35
a Beton K-250 13.200 m3 3
b Besi Tulanagan Pokok D16 90.185 kg 2
c Besi Tulanagan Sengkang ∅ 10-100 mm 74.442 kg 1
d Bekiting + Perawatan Beton 4.057 m2 1
Total Hari Pekerjaan 177

IV PEKERJAAN PASANGAN DAN PLASTERAN


LANTAI 1
1 Pasangan Dinding Bata Adukan 1:2 123.074 m2 5
2 Pasangan Dinding Bata Adukan 1:4 162.840 m2 7
3 Plasteran Dinding Bata Adukan 1:2 246.148 m2 8
4 Plasteran Dinding Bata Adukan 1:4 325.680 m2 10
LANTAI 2
1 Pasangan Dinding Bata Adukan 1:2 34.200 m2 1
2 Pasangan Dinding Bata Adukan 1:4 288.017 m2 6
3 Plasteran Dinding Bata Adukan 1:2 68.400 m 2
2
4 Plasteran Dinding Bata Adukan 1:4 576.034 m2 14
Total Hari Pekerjaan 54

V PEKERJAAN LANTAI
LANTAI 1
1 Lantai Keramik 40 x40 Cm 207.001 m 2
6
2 Lantai Keramik 20 x20 Cm 14.783 m2 1
LANTAI 2
1 Lantai Keramik 40 x40 Cm 192.866 m2 5
2 Lantai Keramik 20 x20 Cm 14.783 m 2
1
Total Hari Pekerjaan 13

VI PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan 293.280 m2 6
2 Pek. Penutup Atap Seng Spandek 293.280 m2 3
3 Pek. Rabung Seng Spandek 28.200 m 1
4 Papan Lisplank 2,5/20 56.400 m 2
Total Hari Pekerjaan 12

VII PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC


LANTAI 1
1 Reilling Tangga 40*40 7.700 m 1
2 Kusen Pintu 1 Kayu Kelas I 0.090 m3 1
3 Daun Pintu 1 Kayu Kelas II 6.720 m2 5
4 Kusen Pintu 2 Kayu Kelas I 0.155 m 1
5 Daun Pintu 2 Kayu Kelas II 6.720 Bh 5
6 Kusen Jendela 1 Kayu Kelas I 0.516 m2 2
7 Daun Ambang Jendela Kayu Kelas II 2.640 m 2
2
8 Kaca Jendela Tebal 5 mm 4.830 m2 1
9 Kusen Ventilasi 1 Kayu Kelas I 0.505 m2 2
10 Kaca Ventilasi Tebal 5 mm 2.837 m 2
1
LANTAI 2
1 Kusen Pintu 1 Kayu Kelas I 0.090 m2 1
2 Daun Pintu 1 Kayu Kelas II 6.720 m2 5
3 Kusen Pintu 2 Kayu Kelas I 0.155 m 1
4 Daun Pintu 2 Kayu Kelas II 6.720 m2 5
5 Kusen Jendela 1 Kayu Kelas I 0.516 m 2
2
6 Daun Ambang Jendela Kayu Kelas II 2.640 m2 2
7 Kaca Jendela Tebal 5 mm 4.830 m 2
1
8 Kusen Ventilasi 1 Kayu Kelas I 0.505 m 2
9 Kaca Ventilasi Tebal 5 mm 2.837 m2 1
Total Hari Pekerjaan 40

VIII PEKERJAAN PENGECATAN


LANTAI 1
1 Pengecatan Dinding Luar dan Dalam 325.680 m2 4
2 Pengecatan Kusen 30.784 m 2
1
LANTAI 2
1 Pengecatan Dinding 576.034 m2 7
2 Pengecatan Kusen 30.784 m2 1
Total Hari Pekerjaan 13

X PEKERJAAN ELEKTRIKAL
LANTAI 1
1 Box Sekering 1.000 Bh 1
2 Stop Kontak Tunggal 2.000 Bh 1
3 Saklar Tunggal 4.000 Bh 1
4 Saklar Double 2.000 Bh 1
5 Bola Lampu Philip 18 Watt 6.000 Bh 1
6 Bola Lampu TL 40 Watt 220 V. 13.000 Bh 1
7 Lampu barel 1.000 Bh 1
8 Kabel Instalasi ∅ 2.5 mm 1.000 Ls 3
LANTAI 2
1 Box Sekering 1.000 Bh 1
2 Stop Kontak Tunggal 2.000 Bh 1
3 Saklar Tunggal 4.000 Bh 1
4 Saklar Double 2.000 Bh 1
5 Bola Lampu Philip 18 Watt 6.000 Bh 1
6 Bola Lampu TL 40 Watt 220 V. 14.000 Bh 1
7 Lampu barel 1.000 Bh 1
8 Kabel Instalasi ∅ 2.5 mm 1.000 Ls 3

Total Hari Pekerjaan 20

XI PEKERJAAN SANITASI
1 Urinoir 6.000 Bh 3
2 Kloset Jongkok 6.000 Bh 5
3 Kran Air 12.000 Bh 2
4 Floor Drain 6.000 Bh 1
5 Rumah Pompa Sanyo Elektrik 2.000 Bh 2
6 Septictank 1.000 Bh 3
7 Resapan 1.000 Bh 2
8 Bak Kontrol 3.000 Bh 2
9 Pipa PVC ∅ 4" 2.000 Bh 4
10 Pipa PVC ∅ 3" 2.000 Bh 2
11 Pipa PVC ∅ 3/4" 2.000 Bh 2
Total Hari Pekerjaan 27

XII PEKERJAAN KUNCI DAN PENGGANTUNG


1 Engsel Pintu 48.000 Bh 9
2 Engsel Jendela 60.000 Bh 9
3 Hak Angin Jendela/Kait Angin 40.000 Bh 2
4 Grendel/Pacok Jendela 40.000 Bh 2
5 Kunci Tanam 2 Kali Putar 12.000 Bh 2
6 Tarikan Jendela/Pegangan 20.000 Bh 2
7 Grendel/Pacok Pintu 8.000 Bh 2
Total Hari Pekerjaan 29

JADI TOTAL KESELURUHAN HARI PEKERJAAN 422


ANALISA TEKNIS

PEKERJAAN BANGUNAN LANTAI I


I PEKERJAAN PERSIAPAN

A. Pembersihan Lapangan
Volume (V) : 405.00 M³
Indeks Tenaga Kerja (N) : 0.15 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 6.667 m/org/hari
N 0.15
Durasi Pelaksanaan (D) : V 405.00
= = 3.038 = 3 Hari
nxP 20 x 6.667

B. Pemasangan Bouwplank
Volume (V) : 79.00 M
Indeks Tenaga Kerja (N) : 0.215 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 4.651 m/org/hari
N 0.215
Durasi Pelaksanaan (D) : V 79.00
= = 2.123 = 2 Hari
nxP 8 x 4.651

TOTAL HARI KERJA = 5 hari

II PEKERJAAN TANAH DAN PONDASI

A. Pondasi Tapak
1. Galian Tanah Pondasi Tapak
Volume (V) : 173.22 M³
Indeks Tenaga Kerja (N) : 0.5786 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 1.728 m/org/hari
N 0.5786
Durasi Pelaksanaan (D) : V 173.22
= = 5.011 = 5 Hari
nxP 20 x 1.728

2. Urugan Kembali Pondasi Tapak


Volume (V) : 129.92 M³
Indeks Tenaga Kerja (N) : 0.3333 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 3.000 m/org/hari
N 0.3333
Durasi Pelaksanaan (D) : V 129.92
= = 4.330 = 4 Hari
nxP 10 x 3.000

3. Lapisan Pasir
Volume (V) : 7.87 M³
Indeks Tenaga Kerja (N) : 0.310 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 3.226 m/org/hari
N 0.310
Durasi Pelaksanaan (D) : V 7.87
= = 1.220 = 1 Hari
nxP 2 x 3.226

4. Aanstamping
Volume (V) : 7.87 M³
Indeks Tenaga Kerja (N) : 1.248 Oh
Jumlah Tenaga Kerja (n) : 7 org
Produktifitas : 1 1
= = 0.801 m/org/hari
N 1.248
Durasi Pelaksanaan (D) : V 7.87
= = 1.404 = 1 Hari
nxP 7 x 0.801

TOTAL HARI KERJA = 12 hari

B. Pondasi Menerus
1. Galian Tanah Pondasi Menerus
Volume (V) : 92.13 M³
Indeks Tenaga Kerja (N) : 0.775 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 1.290 m/org/hari
N 0.775
Durasi Pelaksanaan (D) : V 92.13
= = 3.570 = 4 Hari
nxP 20 x 1.290
2. Urugan Kembali Pondasi Menerus
Volume (V) : 23.03 M³
Indeks Tenaga Kerja (N) : 0.333 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 3.000 m/org/hari
N 0.333
Durasi Pelaksanaan (D) : V 23.03
= = 0.960 = 1 Hari
nxP 8 x 3.000

3. Lapisan Pasir
Volume (V) : 5.70 M²
Indeks Tenaga Kerja (N) : 0.310 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 3.226 m/org/hari
N 0.310
Durasi Pelaksanaan (D) : V 5.70
= = 0.884 = 1 Hari
nxP 2 x 3.226

4. Aanstamping
Volume (V) : 11.40 M³
Indeks Tenaga Kerja (N) : 1.248 Oh
Jumlah Tenaga Kerja (n) : 7 org
Produktifitas : 1 1
= = 0.801 m/org/hari
N 1.248
Durasi Pelaksanaan (D) : V 11.40
= = 2.032 = 2 Hari
nxP 7 x 0.801

5. Pasangan Batu Gunung


Volume (V) : 92.13 M³
Indeks Tenaga Kerja (N) : 2.400 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 0.417 m/org/hari
N 2.400
Durasi Pelaksanaan (D) : V 92.13
= = 5.528 = 6 Hari
nxP 40 x 0.417

TOTAL HARI KERJA = 13 hari

III Timbunan Tanah Bawah Lantai

1. Timbunan Tanah Bawah Lantai


Volume (V) : 92.42 M³
Indeks Tenaga Kerja (N) : 0.310 Oh
Jumlah Tenaga Kerja (n) : 7 org
Produktifitas : 1 1
= = 3.226 m/org/hari
N 0.310
Durasi Pelaksanaan (D) : V 92.42
= = 4.093 = 4 Hari
nxP 7 x 3.226

2. Urugan Pasir Bawah Lantai


Volume (V) : 38.95 M³
Indeks Tenaga Kerja (N) : 0.310 Oh
Jumlah Tenaga Kerja (n) : 7 org
Produktifitas : 1 1
= = 3.226 m/org/hari
N 0.310
Durasi Pelaksanaan (D) : V 38.95
= = 1.725 = 2 Hari
nxP 7 x 3.226

TOTAL HARI KERJA = 6 hari

IV PEKERJAAN BETON BERTULANG


LANTAI 1
A. PONDASI TAPAK

Pondasi Tapak 150/200


1. Beton K-250
Volume (V) : 15.12 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 15.12
= = 3.078 = 3 Hari
nxP 10 x 0.491
2. Besi Tulangan ø 16-150 mm
Volume (V) : 1,192.57 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 1,192.57
= = 7.434 = 7 Hari
nxP 30 x 5.348

3. Bekisting + Perawatan Beton


Volume (V) : 37.80 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 1.202 kg/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 37.80
= = 3.145 = 3 Hari
nxP 10 x 1.202

Pondasi Tapak 125/125


1. Beton K-250
Volume (V) : 15.95 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 15.95
= = 3.247 = 3 Hari
nxP 10 x 0.491
2. Besi Tulangan ø 16-150 mm
Volume (V) : 1,257.79 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 25 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 1,257.79
= = 9.408 = 9 Hari
nxP 25 x 5.348

3. Bekisting + Perawatan Beton


Volume (V) : 39.87 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 1.202 kg/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 39.87
= = 1.658 = 2 Hari
nxP 20 x 1.202

Pondasi Tapak 100/100


1. Beton K-250
Volume (V) : 9.72 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 9.72
= = 1.979 = 2 Hari
nxP 10 x 0.491
2. Besi Tulanagan Sengkang ∅ 10-85 mm
Volume (V) : 78.87 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 78.87
= = 1.475 = 1 Hari
nxP 10 x 5.348

3. Bekisting + Perawatan Beton


Volume (V) : 2.50 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 1.202 kg/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 2.50
= = 1.040 = 1 Hari
nxP 2 x 1.202

B. SLOOF BETON

Sloof Beton 30/55


1. Beton K-250
Volume (V) : 5.28 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 5.28
= = 0.538 = 1 Hari
nxP 20 x 0.491
2. Besi Tulanagan Pokok D16
Volume (V) : 891.71 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 891.71
= = 5.558 = 6 Hari
nxP 30 x 5.348

3. Besi Tulanagan Pinggang D16


Volume (V) : 401.27 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
n 0.187
Durasi Pelaksanaan (D) : V 401.27
= = 2.501 = 3 Hari
nxP 30 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-150 mm


Volume (V) : 809.15 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 809.15
= = 5.044 = 5 Hari
nxP 30 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 45.20 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 1.202 m/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 45.20
= = 1.880 = 2 Hari
nxP 20 x 1.202

6. Pasir Urug
Volume (V) : 0.80 M³
Indeks Tenaga Kerja (N) : 0.310 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 3.226 m/org/hari
N 0.310
Durasi Pelaksanaan (D) : V 0.80
= = 0.248 = 0 Hari
nxP 1 x 3.226

7. Aanstamping
Volume (V) : 1.60 M³
Indeks Tenaga Kerja (N) : 1.248 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.801 m/org/hari
N 1.248
Durasi Pelaksanaan (D) : V 1.60
= = 0.998 = 1 Hari
nxP 2 x 0.801

Sloof Beton 25/40


1. Beton K-250
Volume (V) : 14.25 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 14.25
= = 2.901 = 3 Hari
nxP 10 x 0.491
2. Besi Tulanagan Pinggang D 16
Volume (V) : 506.02 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 506.02
= = 3.154 = 3 Hari
nxP 30 x 5.348

3. Besi Tulanagan Pokok D 16


Volume (V) : 632.53 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 632.53
= = 3.943 = 4 Hari
nxP 30 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-150 mm


Volume (V) : 21.44 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 5.348 kg/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 21.44
= = 0.802 = 1 Hari
nxP 5 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 4.00 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 1.202 m/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 4.00
= = 0.666 = 1 Hari
nxP 5 x 1.202

C. KOLOM

Kolom 40/60
1. Beton K-250
Volume (V) : 7.20 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 7.20
= = 0.489 = 0 Hari
nxP 30 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 801.20 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 35 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 801.20
= = 4.281 = 4 Hari
nxP 35 x 5.348

3. Besi Tulanagan Pinggang D16


Volume (V) : 400.60 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 m/org/hari
n 0.187
Durasi Pelaksanaan (D) : V 400.60
= = 2.497 = 2 Hari
nxP 30 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 344.89 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 m/org/hari
n 0.187
Durasi Pelaksanaan (D) : V 344.89
= = 2.150 = 2 Hari
nxP 30 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 30.00 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 25 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 30.00
= = 1.267 = 1 Hari
nxP 25 x 0.947

Kolom 40/40
1. Beton K-250
Volume (V) : 14.40 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 14.40
= = 0.977 = 1 Hari
nxP 30 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 1,420.42 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 1,420.42
= = 6.640 = 7 Hari
nxP 40 x 5.348

3. Besi Tulanagan Pinggang D16


Volume (V) : 568.17 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 35 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 568.17
= = 3.036 = 3 Hari
nxP 35 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 810.97 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 810.97
= = 5.055 = 5 Hari
nxP 30 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 72.00 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 72.00
= = 2.534 = 3 Hari
nxP 30 x 0.947

Kolom KP 13/13
1. Beton K-250
Volume (V) : 0.76 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 0.76
= = 0.309 = 0 Hari
nxP 5 x 0.491

2. Besi Tulanagan Pokok ∅14


Volume (V) : 217.18 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 217.18
= = 2.031 = 2 Hari
nxP 20 x 5.348

3. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 102.54 M³
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 102.54
= = 1.918 = 2 Hari
nxP 10 x 5.348

4. Bekiting + Perawatan Beton


Volume (V) : 11.68 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.947 0
N 1.056
Durasi Pelaksanaan (D) : V 11.68
= = 1.234 = 1 Hari
nxP 10 x 0.947

D. BALOK LANTAI

Balok Lantai 25/60


1. Beton K-250
Volume (V) : 4.80 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 4.80
= = 0.652 = 1 Hari
nxP 15 x 0.491
2. Besi Tulanagan Pokok D16
Volume (V) : 505.04 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 505.04
= = 3.148 = 3 Hari
nxP 30 x 5.348

3. Besi Tulanagan Pinggang D14


Volume (V) : 77.33 M³
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 77.33
= = 1.446 = 1 Hari
nxP 10 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-85 mm


Volume (V) : 36.69 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 36.69
= = 0.686 = 1 Hari
nxP 10 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 19.36 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 0.947 0
N 1.056
Durasi Pelaksanaan (D) : V 19.36
= = 1.363 = 1 Hari
n xP 15 x 0.947

Balok Lantai 25/40


1. Beton K-250
Volume (V) : 15.80 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 15.80
= = 1.072 = 1 Hari
nxP 30 x 0.491
2. Besi Tulanagan Pokok D16
Volume (V) : 1,496.17 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 1,496.17
= = 6.995 = 5 Hari
nxP 40 x 5.348

3. Besi Tulanagan Pinggang D14


Volume (V) : 381.84 M³
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 381.84
= = 1.785 = 4 Hari
nxP 40 x 5.348

4. Besi Tulangan sengkang ø 10-200 mm


Volume (V) : 750.52 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 750.52
= = 3.509 = 4 Hari
nxP 40 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 63.99 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 63.99
= = 2.252 = 2 Hari
nxP 30 x 0.947

E. TANGGA

Balok Bordes 20/30


1. Beton K-250
Volume (V) : 0.18 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 0.18
= = 0.183 = 0 Hari
nxP 2 x 0.491

2. Besi Tulanagan Pokok D12


Volume (V) : 13.32 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 13.32
= = 1.245 = 1 Hari
nxP 2 x 5.348

3. Besi Tulanagan Pinggang D12


Volume (V) : 5.33 M³
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 5.33
= = 0.498 = 0 Hari
nxP 2 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 15.75 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 15.75
= = 1.473 = 1 Hari
nxP 2 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 0.84 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 0.84
= = 0.444 = 0 Hari
nxP 2 x 0.947

Plat Bordes
1. Beton K-250
Volume (V) : 0.50 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 0.50
= = 0.508 = 1 Hari
nxP 2 x 0.491

2. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 25.64 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 25.64
= = 1.199 = 1 Hari
nxP 4 x 5.348

3. Bekiting + Perawatan Beton


Volume (V) : 8.45 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 8.45
= = 1.487 = 1 Hari
nxP 6 x 0.947

Plat Tangga
1. Beton K-250
Volume (V) : 1.01 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 1.01
= = 1.032 = 1 Hari
nxP 2 x 0.491
2. Besi Tulanagan Sengkang ∅ 10-100 mm
Volume (V) : 52.07 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 52.07
= = 1.217 = 1 Hari
nxP 8 x 5.348

3. Bekiting + Perawatan Beton


Volume (V) : 8.45 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 8.45
= = 1.115 = 1 Hari
nxP 8 x 0.947

Sloof Tangga 25/40


1. Beton K-250
Volume (V) : 0.13 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 0.13
= = 0.132 = 0 Hari
nxP 2 x 0.491

2. Besi Tulanagan Pokok D12


Volume (V) : 5.77 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 5.77
= = 0.540 = 1 Hari
nxP 2 x 5.348

3. Besi Tulanagan Pinggang D12


Volume (V) : 4.62 M³
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 4.62
= = 0.432 = 0 Hari
nxP 2 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 2.79 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 2.79
= = 0.261 = 0 Hari
nxP 2 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 4.00 M2
Indeks Tenaga Kerja (N) : 0.832 Oh
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : 1 1
= = 1.202 m/org/hari
N 0.832
Durasi Pelaksanaan (D) : V 4.00
= = 0.832 = 1 Hari
nxP 4 x 1.202

TOTAL HARI KERJA = 131 hari

LANTAI 2
A. KOLOM

Kolom 40/60
1. Beton K-250
Volume (V) : 6.05 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 6.05
= = 1.231 = 1 Hari
nxP 10 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 111.28 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 111.28
= = 1.387 = 1 Hari
nxP 15 x 5.348

3. Besi Tulanagan Pinggang D16


Volume (V) : 55.64 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 55.64
= = 1.040 = 1 Hari
nxP 10 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 47.90 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 47.90
= = 0.896 = 1 Hari
nxP 10 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 4.17 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 4.17
= = 0.880 = 1 Hari
nxP 5 x 0.947

Kolom 40/40
1. Beton K-250
Volume (V) : 12.10 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 12.10
= = 2.463 = 2 Hari
nxP 10 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 98.64 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 98.64
= = 1.230 = 1 Hari
nxP 15 x 5.348

3. Besi Tulanagan Pinggang D16


Volume (V) : 39.46 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 39.46
= = 0.738 = 1 Hari
nxP 10 x 5.348

4. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 56.32 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 56.32
= = 1.053 = 1 Hari
nxP 10 x 5.348

5. Bekiting + Perawatan Beton


Volume (V) : 5.00 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 5.00
= = 0.528 = 1 Hari
nxP 10 x 0.947

Kolom Praktis 13/13


1. Beton K-250
Volume (V) : 0.48 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 2 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 0.48
= = 0.195 = 0 Hari
= = 0.195 = 0 Hari
nxP 5 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 286.00 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 286.00
= = 3.565 = 4 Hari
nxP 15 x 5.348

3. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 135.04 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 135.04
= = 2.525 = 3 Hari
nxP 10 x 5.348

4. Bekiting + Perawatan Beton


Volume (V) : 15.38 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 15.38
= = 1.625 = 2 Hari
nxP 10 x 0.947

B. PLAT LANTAI

1. Beton K-250
Volume (V) : 24.25 M³
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 24.25
= = 4.937 = 5 Hari
nxP 10 x 0.491

2. Besi Tulangan sengkang ø 10-200 mm


Volume (V) : 1,245.22 M2
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 1,245.22
= = 7.762 = 8 Hari
nxP 30 x 5.348

3. Bekiting + Perawatan Beton


Volume (V) : 202.08 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 202.08
= = 7.113 = 7 Hari
nxP 30 x 0.947

C. RING BALOK

Ring Balok 25/35


1. Beton K-250
Volume (V) : 13.20 Kg
Indeks Tenaga Kerja (N) : 2.036 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 0.491 m/org/hari
N 2.036
Durasi Pelaksanaan (D) : V 13.20
= = 2.688 = 3 Hari
nxP 10 x 0.491

2. Besi Tulanagan Pokok D16


Volume (V) : 90.19 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 90.19
= = 1.686 = 2 Hari
nxP 10 x 5.348

3. Besi Tulanagan Sengkang ∅ 10-100 mm


Volume (V) : 74.44 Kg
Indeks Tenaga Kerja (N) : 0.187 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 5.348 m/org/hari
N 0.187
Durasi Pelaksanaan (D) : V 74.44
= = 1.392 = 1 Hari
nxP 10 x 5.348

4. Bekiting + Perawatan Beton


Volume (V) : 4.06 M2
Indeks Tenaga Kerja (N) : 1.056 Oh
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : 1 1
= = 0.947 m/org/hari
N 1.056
Durasi Pelaksanaan (D) : V 4.06
= = 1.071 = 1 Hari
n xP 4 x 0.947

TOTAL HARI KERJA = 46 hari

V PEKERJAAN PASANGAN DAN PLASTERAN


LANTAI 1

A. DINDING
1. Pasangan Dinding Bata Adukan 1:2
Volume (V) : 123.07 M²
Indeks Tenaga Kerja (N) : 0.425 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 2.353 m/org/hari
N 0.425
Durasi Pelaksanaan (D) : V 123.07
= = 5.231 = 5 Hari
nxP 10 x 2.353

2. Plasteran Dinding Bata Adukan 1:2


Volume (V) : 246.15 M²
Indeks Tenaga Kerja (N) : 0.480 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 2.083 m/org/hari
N 0.480
Durasi Pelaksanaan (D) : V 246.15
= = 7.877 = 8 Hari
nxP 15 x 2.083

3. Pasangan Dinding Bata 1:4


Volume (V) : 162.84 M²
Indeks Tenaga Kerja (N) : 0.425 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 2.353 m/org/hari
N 0.425
Durasi Pelaksanaan (D) : V 162.84
= = 6.921 = 7 Hari
nxP 10 x 2.353

4 Plasteran Dinding Bata 1:4


Volume (V) : 325.68 M²
Indeks Tenaga Kerja (N) : 0.480 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 2.083 m/org/hari
N 0.480
Durasi Pelaksanaan (D) : V 325.68
= = 10.422 = 10 Hari
nxP 15 x 2.083

TOTAL HARI KERJA = 30 hari

LANTAI 2

A. DINDING
1. Pasangan Dinding Bata Adukan 1:2
Volume (V) : 34.20 M²
Indeks Tenaga Kerja (N) : 0.425 Oh
Jumlah Tenaga Kerja (n) : 10 org
Produktifitas : 1 1
= = 2.353 m/org/hari
N 0.425
Durasi Pelaksanaan (D) : V 34.20
= = 1.454 = 1 Hari
nxP 10 x 2.353

2. Plasteran Dinding Bata Adukan 1:2


Volume (V) : 68.40 M²
Indeks Tenaga Kerja (N) : 0.480 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 2.083 m/org/hari
N 0.480
Durasi Pelaksanaan (D) : V 68.40
= = 2.189 = 2 Hari
nxP 15 x 2.083

3. Pasangan Dinding Bata 1:4


Volume (V) : 288.02 M²
Indeks Tenaga Kerja (N) : 0.425 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 2.353 m/org/hari
N 0.425
Durasi Pelaksanaan (D) : V 288.02
= = 6.120 = 6 Hari
n xP 20 x 2.353

4. Plasteran Dinding Bata 1:4


Volume (V) : 576.03 M²
Indeks Tenaga Kerja (N) : 0.480 Oh
Jumlah Tenaga Kerja (n) : 20 org
Produktifitas : 1 1
= = 2.083 m/org/hari
N 0.480
Durasi Pelaksanaan (D) : V 576.03
= = 13.825 = 14 Hari
nxP 20 x 2.083

TOTAL HARI KERJA = 24 hari

VI PEKERJAAN KERAMIK
LANTAI 1

A LANTAI KERAMIK
1. Lantai Keramik 40 x40 Cm
Volume (V) : 207.00 M³
Indeks Tenaga Kerja (N) : 1.120 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 0.893 m/org/hari
N 1.120
Durasi Pelaksanaan (D) : V 207.00
= = 5.796 = 6 Hari
nxP 40 x 0.893

2. Lantai Keramik 20 x20 Cm


Volume (V) : 14.78 M³
Indeks Tenaga Kerja (N) : 1.120 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 0.893 m/org/hari
N 1.120
Durasi Pelaksanaan (D) : V 14.78
= = 1.104 = 1 Hari
nxP 15 x 0.893

TOTAL HARI KERJA = 7 hari

LANTAI 2

A LANTAI KERAMIK
1. Lantai Keramik 40 x40 Cm
Volume (V) : 192.87 M²
Indeks Tenaga Kerja (N) : 1.120 Oh
Jumlah Tenaga Kerja (n) : 40 org
Produktifitas : 1 1
= = 0.893 m/org/hari
N 1.120
Durasi Pelaksanaan (D) : V 192.87
= = 5.400 = 5 Hari
nxP 40 x 0.893

2. Lantai Keramik 20 x20 Cm


Volume (V) : 14.78 M²
Indeks Tenaga Kerja (N) : 1.120 Oh
Jumlah Tenaga Kerja (n) : 15 org
Produktifitas : 1 1
= = 0.893 m/org/hari
N 1.120
Durasi Pelaksanaan (D) : V 14.78
= = 1.104 = 1 Hari
= = 1.104 = 1 Hari
nxP 15 x 0.893

TOTAL HARI KERJA = 7 hari

VII PEKERJAAN ATAP

1. Rangka Baja Ringan C75-75


Volume (V) : 293.28 M²
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 18 org
Produktifitas : -
Durasi Pelaksanaan (D) : 6 Hari 6 Hari

2. Penutup Atap Seng Spandek


Volume (V) : 293.28 M²
Indeks Tenaga Kerja (N) : 0.311 Oh
Jumlah Tenaga Kerja (n) : 30 org
Produktifitas : 1 1
= = 3.215 m/org/hari
N 0.311
Durasi Pelaksanaan (D) : V 293.28
= = 3.040 = 3 Hari
nxP 30 x 3.215

3. Rabung Seng Spandek


Volume (V) : 28.20 M
Indeks Tenaga Kerja (N) : 0.247 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 4.049 m/org/hari
= = 4.049 m/org/hari
N 0.247
Durasi Pelaksanaan (D) : V 28.20
= = 1.161 = 1 Hari
nxP 6 x 4.049

4. List Plank
Volume (V) : 56.40 M
Indeks Tenaga Kerja (N) : 0.325 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 3.077 m/org/hari
N 0.325
Durasi Pelaksanaan (D) : V 56.40
= = 2.291 = 2 Hari
nxP 8 x 3.077

TOTAL HARI KERJA = 12 hari

VIII PEKERJAAN PEMASANGAN PINTU, JENDELA DAN VENTILASI DAN LAINNYA


LANTAI 1

1. Reilling Tangga 40*40


Volume (V) : 7.70 M²
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 Hari 1 Hari

PINTU
1. Kusen Pintu 1 Kayu Kelas I
Volume (V) : 0.09 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.09
= = 1.081 = 1 Hari
nxP 2 x 0.041

2. Daun Pintu 1 Kayu Kelas II


Volume (V) : 6.72 M²
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 6.72
= = 4.872 = 5 Hari
nxP 6 x 0.230

3. Kusen Pintu 2 Kayu Kelas I


Volume (V) : 0.15 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.15
= = 1.246 = 1 Hari
nxP 3 x 0.041

4. Daun Pintu 2 Kayu Kelas II


Volume (V) : 6.72 M²
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 6.72
= = 4.872 = 5 Hari
nxP 6 x 0.230

JENDELA
1. Kusen Jendela 1 Kayu Kelas I
Volume (V) : 0.52 M³
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.041 m/org/hari
n 24.150
Durasi Pelaksanaan (D) : V 0.52
= = 2.078 = 2 Hari
nxP 6 x 0.041

2. Daun Ambang Jendela Kayu Kelas II


Volume (V) : 2.64 M³
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 2.64
= = 1.914 = 2 Hari
nxP 6 x 0.230

3. Kaca Jendela Tebal 5 mm


Volume (V) : 4.83 M³
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 4.83
= = 0.873 = 1 Hari
= = 0.873 = 1 Hari
nxP 1 x 5.531

VENTILASI
1. Kusen Ventilasi 1 Kayu Kelas I
Volume (V) : 0.51 org
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.51
= = 2.034 = 2 Hari
nxP 6 x 0.041

2. Kaca Ventilasi Tebal 5 mm


Volume (V) : 2.84 M¹
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 5.531 m/org/hari
N 0.181
Durasi Pelaksanaan (D) : V 2.84
= = 0.513 = 1 Hari
nxP 1 x 5.531

TOTAL HARI KERJA = 20 hari

LANTAI 2

PINTU
1. Kusen Pintu 1 Kayu Kelas I
Volume (V) : 0.09 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.09
= = 1.081 = 1 Hari
nxP 2 x 0.041

2. Daun Pintu 1 Kayu Kelas II


Volume (V) : 6.72 M²
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 6.72
= = 4.872 = 5 Hari
nxP 6 x 0.230

3. Kusen Pintu 2 Kayu Kelas I


Volume (V) : 0.15 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.15
= = 1.246 = 1 Hari
nxP 3 x 0.041

4. Daun Pintu 2 Kayu Kelas II


Volume (V) : 6.72 M²
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 6.72
= = 4.872 = 5 Hari
nxP 6 x 0.230

JENDELA
1. Kusen Jendela 1 Kayu Kelas I
Volume (V) : 0.52 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.041 m/org/hari
n 24.150
Durasi Pelaksanaan (D) : V 0.52
= = 2.078 = 2 Hari
n xP 6 x 0.041

2. Daun Ambang Jendela Kayu Kelas II


Volume (V) : 2.64 M²
Indeks Tenaga Kerja (N) : 4.350 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.230 m/org/hari
n 4.350
Durasi Pelaksanaan (D) : V 2.64
= = 1.914 = 2 Hari
nxP 6 x 0.230

3. Kaca Jendela Tebal 5 mm


Volume (V) : 4.83 M²
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 4.83
= = 0.873 = 1 Hari
nxP 1 x 5.531

VENTILASI
1. Kusen Ventilasi 1 Kayu Kelas I
Volume (V) : 0.51 M²
Indeks Tenaga Kerja (N) : 24.150 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1
= = 0.041 Kg/org/hari
= = 0.041 Kg/org/hari
N 24.150
Durasi Pelaksanaan (D) : V 0.51
= = 2.034 = 2 Hari
nxP 6 x 0.041

2. Kaca Ventilasi Tebal 5 mm


Volume (V) : 2.84 M²
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 5.531 m/org/hari
N 0.181
Durasi Pelaksanaan (D) : V 2.84
= = 0.513 = 1 Hari
nxP 1 x 5.531

TOTAL HARI KERJA = 19 hari

XI PEKERJAAN PENGECATAN
LANTAI 1

1. Pengecatan Dinding Luar dan Dalam


Volume (V) : 325.68 M²
Indeks Tenaga Kerja (N) : 0.092 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 10.893 m/org/hari
N 0.092
Durasi Pelaksanaan (D) : V 325.68
= = 3.737 = 4 Hari
nxP 8 x 10.893

2. Pengecatan Kusen
Volume (V) : 30.78 M²
Indeks Tenaga Kerja (N) : 0.088 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 11.364 m/org/hari
n 0.088
Durasi Pelaksanaan (D) : V 30.78
= = 1.354 = 1 Hari
nxP 2 x 11.364

TOTAL HARI KERJA = 5 hari

LANTAI 2

1. Pengecatan Dinding
Volume (V) : 576.03 M²
Indeks Tenaga Kerja (N) : 0.092 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1
= = 10.893 m/org/hari
N 0.092
Durasi Pelaksanaan (D) : V 576.03
= = 6.610 = 7 Hari
nxP 8 x 10.893

2. Pengecatan Kusen
Volume (V) : 30.78 M²
Indeks Tenaga Kerja (N) : 0.088 Oh
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : 1 1
= = 11.364 m/org/hari
n 0.088
Durasi Pelaksanaan (D) : V 30.78
= = 1.354 = 1 Hari
nxP 2 x 11.364

TOTAL HARI KERJA = 8 hari

X PEKERJAAN ELEKTRIKAL
LANTAI 1

1. Box Sekering
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

2. Stop Kontak Tunggal


Volume (V) : 2.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

3. Saklar Tunggal
Volume (V) : 4.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

4. Saklar Double
Volume (V) : 2.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

5. Bola Lampu Philip 18 Watt


Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Bola Lampu TL 40 Watt 220 V.


Volume (V) : 13.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

7. Lampu barel
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

8. Kabel Instalasi ∅ 2.5 mm


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 3 = 3 Hari

TOTAL HARI KERJA = 10 hari

LANTAI 2

1. Box Sekering
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

2. Stop Kontak Tunggal


Volume (V) : 2.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

3. Saklar Tunggal
Volume (V) : 4.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

4. Saklar Double
Volume (V) : 2.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

5. Bola Lampu Philip 18 Watt


Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Bola Lampu TL 40 Watt 220 V.


Volume (V) : 14.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

7. Lampu barel
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 2 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

8. Kabel Instalasi ∅ 2.5 mm


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 3 = 3 Hari

TOTAL HARI KERJA = 10 hari

XI PEKERJAAN SANITASI
LANTAI 1

1. Urinoir
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 2.150 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.465 m/org/hari
N 2.150
Durasi Pelaksanaan (D) : V 3.00
= = 1.290 = 1 Hari
nxP 5 x 0.465

2. Kloset Jongkok
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 4.160 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.240 m/org/hari
N 4.160
Durasi Pelaksanaan (D) : V 3.00
= = 2.496 = 2 Hari
nxP 5 x 0.240

3. Kran Air
Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : 0.125 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 8.000 m/org/hari
N 0.125
Durasi Pelaksanaan (D) : V 6.00
= = 0.750 = 1 Hari
nxP 1 x 8.000

4. Floor Drain
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 0.125 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 8.000 m/org/hari
N 0.125
Durasi Pelaksanaan (D) : V 3.00
= = 0.375 = 0 Hari
nxP 1 x 8.000

5. Rumah Pompa Sanyo Elektrik


Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Septictank
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 3 = 3 Hari

7. Resapan
Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 2 = 2 Hari

8. Bak Kontrol
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 4 org
Produktifitas : -
Durasi Pelaksanaan (D) : 2 = 2 Hari

9. Pipa PVC ∅ 4"


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 2 = 2 Hari

10. Pipa PVC ∅ 3"


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari
11. Pipa PVC ∅ 3/4"
Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

TOTAL HARI KERJA = 17 hari


LANTAI 2

1. Urinoir
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 2.150 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.465 m/org/hari
N 2.150
Durasi Pelaksanaan (D) : V 3.00
= = 1.290 = 1 Hari
nxP 5 x 0.465

2. Kloset Jongkok
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 4.160 Oh
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : 1 1
= = 0.240 m/org/hari
N 4.160
Durasi Pelaksanaan (D) : V 3.00
= = 2.496 = 2 Hari
nxP 5 x 0.240

3. Kran Air
Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : 0.125 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 8.000 m/org/hari
N 0.125
Durasi Pelaksanaan (D) : V 6.00
= = 0.750 = 1 Hari
nxP 1 x 8.000

4. Floor Drain
Volume (V) : 3.00 Bh
Indeks Tenaga Kerja (N) : 0.125 Oh
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : 1 1
= = 8.000 m/org/hari
N 0.125
Durasi Pelaksanaan (D) : V 3.00
= = 0.375 = 0 Hari
nxP 1 x 8.000

5. Rumah Pompa Sanyo Elektrik


Volume (V) : 1.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Pipa PVC ∅ 4"


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 2 = 2 Hari

7. Pipa PVC ∅ 3"


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

8. Pipa PVC ∅ 3/4"


Volume (V) : 1.00 Ls
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 5 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

TOTAL HARI KERJA = 10 hari

XII PEKERJAAN KUNCI DAN PENGGANTUNG


LANTAI 1

1. Engsel Pintu
Volume (V) : 24.00 Bh
Indeks Tenaga Kerja (N) : 1.181 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1 0.847
= = m/org/hari
n 1.181
Durasi Pelaksanaan (D) : V 24.00
= = 4.723 = 5 Hari
nxP 6 x 0.847

2. Engsel Jendela
Volume (V) : 30.00 Bh
Indeks Tenaga Kerja (N) : 1.181 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1 0.847
= = m/org/hari
n 1.181
Durasi Pelaksanaan (D) : V 30.00
= = 4.428 = 4 Hari
nxP 8 x 0.847
3. Hak Angin Jendela/Kait Angin
Volume (V) : 20.00 Bh
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 20.00
= = 1.205 = 1 Hari
nxP 3 x 5.531

4. Grendel/Pacok Jendela
Volume (V) : 20.00 Bh
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 20.00
= = 1.205 = 1 Hari
nxP 3 x 5.531

5. Kunci Tanam 2 Kali Putar


Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Tarikan Jendela/Pegangan
Volume (V) : 10.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

7. Grendel/Pacok Pintu
Volume (V) : 4.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

TOTAL HARI KERJA = 15 hari

LANTAI 1

1. Engsel Pintu
Volume (V) : 24.00 Bh
Indeks Tenaga Kerja (N) : 1.181 Oh
Jumlah Tenaga Kerja (n) : 6 org
Produktifitas : 1 1 0.847
= = m/org/hari
n 1.181
Durasi Pelaksanaan (D) : V 24.00
= = 4.723 = 5 Hari
nxP 6 x 0.847

2. Engsel Jendela
Volume (V) : 30.00 Bh
Indeks Tenaga Kerja (N) : 1.181 Oh
Jumlah Tenaga Kerja (n) : 8 org
Produktifitas : 1 1 0.847
= = m/org/hari
n 1.181
Durasi Pelaksanaan (D) : V 30.00
= = 4.428 = 4 Hari
nxP 8 x 0.847

3. Hak Angin Jendela/Kait Angin


Volume (V) : 20.00 Bh
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 20.00
= = 1.205 = 1 Hari
nxP 3 x 5.531

4. Grendel/Pacok Jendela
Volume (V) : 20.00 Bh
Indeks Tenaga Kerja (N) : 0.181 Oh
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : 1 1
= = 5.531 m/org/hari
n 0.181
Durasi Pelaksanaan (D) : V 20.00
= = 1.205 = 1 Hari
nxP 3 x 5.531

5. Kunci Tanam 2 Kali Putar


Volume (V) : 6.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 1 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

6. Tarikan Jendela/Pegangan
Volume (V) : 10.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

7. Grendel/Pacok Pintu
Volume (V) : 4.00 Bh
Indeks Tenaga Kerja (N) : Taksir
Jumlah Tenaga Kerja (n) : 3 org
Produktifitas : -
Durasi Pelaksanaan (D) : 1 = 1 Hari

TOTAL HARI KERJA = 15 hari


NAMA PEKERJAAN :
JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp.)
1 PEKERJAAN PERSIAPAN Rp 22,757,289
2 PEKERJAAN TANAH DAN PONDASI Rp 97,764,818
3 PEKERJAAN BETON BERTULANG Rp 390,831,875
4 PEKERJAAN PASANGAN DAN PLASTERAN Rp 201,657,455
5 PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC Rp 55,600,114
6 PEKERJAAN ELEKTRIKAL Rp 19,970,000
7 PEKERJAAN KUNCI DAN PENGGANTUNG Rp 28,040,096
8 PEKERJAAN SANITASI Rp 46,345,950
9 PEKERJAAN LANTAI Rp 271,342,011
10 PEKERJAAN ATAP Rp 153,141,581
11 PEKERJAAN PENGECATAN Rp 30,180,745
JUMLAH Rp 1,317,631,933
RENC. KEMAJUAN PEK. MINGGUAN
RENC. KEMAJUAN PEK. KUMULATIF
RENCANA KEMAJUAN BULANAN
BOBOT REALISASI
NAMA PEKERJAAN :
No. URAIAN PEKERJAAN
JUMLAH HARGA
(Rp.)
1 PEKERJAAN PERSIAPAN Rp 22,757,289
2 PEKERJAAN TANAH DAN PONDASI Rp 97,344,226
3 PEKERJAAN BETON BERTULANG Rp 390,831,875
4 PEKERJAAN PASANGAN DAN PLASTERAN Rp 201,657,455
5 PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC Rp 55,600,114
6 PEKERJAAN ELEKTRIKAL Rp 19,970,000
7 PEKERJAAN KUNCI DAN PENGGANTUNG Rp 28,040,096
8 PEKERJAAN SANITASI Rp 46,345,950
9 PEKERJAAN LANTAI Rp 271,199,385
10 PEKERJAAN ATAP Rp 153,141,581
11 PEKERJAAN PENGECATAN Rp 30,180,745
JUMLAH Rp 1,317,068,716
RENC. KEMAJUAN PEK. MINGGUAN
RENC. KEMAJUAN PEK. KUMULATIF
RENCANA KEMAJUAN BULANAN
BOBOT REALISASI
120
JUMLAH BULAN I BULAN II BULAN III BULAN IV
BOBOT
(%)
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1.73 1.73
7.42 1.85 1.85 1.85 1.85
29.66
80 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19
15.30
4.22
60
1.52
2.13
3.52
40

20.59
11.62
20
2.29
100.00
00 1.72 1.93 1.94 1.95 3.06 1.27 1.28 1.2 9 1.210 1.2 11 1.2 12 1.2 13 1.2 14 1.2 15 1.2 16
1 17
1.7 3.6 5.4 7.3 10.3 11.5 12.7 13.9 15.1 16.3 17.5 18.6 19.8 21.0 22.2
7.3 13.9 18.6 23.4
JADWAL PELAKSANAAN PEKERJAAN
JUMLAH
BOBOT BULAN I BULAN II BULAN III BULAN IV
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1.73 1.73
7.39 7.39
29.67 4.95 4.95 4.95
15.31
4.22
1.52
2.13
3.52
20.59
11.63
2.29
100.00
1.7 12.3 4.9 4.9
1.7 14.1 19.0 24.0
JADWAL PELAKSANAAN PEKERJAAN
BULAN IV BULAN V
Chart Title BULAN VI BULAN VII BULAN VIII

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19 1.19
2.55 2.55 2.55 2.55 2.55
0.84 0.84 0.84 0.84 0.84

10.3
5.81 5.81

4 15 16 1.2 171.2 181.2 191.2 201.2 211.2 221.2 1.2


23 1.2
24 1.2
25 1.2
4.6
26
29 1.2
9.2
27
30 4.6
9.2
31 13.7
28 32 33 34
23.4 24.6 25.8 26.9 28.1 29.3 30.5 31.7 32.9 34.1 35.2 36.4 41.0 45.6 54.8 64.0 77.7
23.4 28.1 32.9 41.0 77.7
BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII
16

4.95 4.95 4.95 4.95


7.66
2.11

11.63

4.9 4.9 4.9 4.9 21.4


24.0 28.9 33.8 38.8 60.2
KET
BULAN IX BULAN X
%
33 34 35 36 37 38 39 40 41
100

75
2.55

0.51 0.51 0.51


50
0.53 0.53 0.53 0.53
0.88 0.88 0.88 0.88
10.3
25
1.15 1.15
0
31 32 14.2
33 1.4
34 1.4
35 0.9
36 1.1
37 1.738 0.5
39 0.5
40 0.5
41
91.9 93.3 94.7 95.6 96.7 98.4 98.9 99.5 100
95.6 99.5 100
BULAN IX BULAN X BULAN XI BULAN XII KET
%
100

7.66
2.11
1.52 50
2.13
3.52
20.59

2.29 0

9.8 1.5 24.1 4.4


70.0 71.5 95.6 100.0
0 180
1 7 30
2 7 30
3 7 30
4 7 30
7 30
7 30
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
Pekerjaan
Lokasi
Tahun Anggaran

Jumlah JAD
No Uraian Bahan Banyaknya Satuan BULAN I BULAN II BULAN III
Bahan 1 2 3 4 1 2 3 4 1
1 Kayu Klas III 24.94 M3
2 Paku Kayu 5.08 Kg
3 Papan Kayu Klas. IV 0.55 M3
4 Urugan Pasir 17.25 M3
5 Semen Portland 90,350.18 Kg
6 Pasir Urug 55.75 M3
7 Pasir Beton 89,670.80 Kg
8 Kerikil 166,873.76 Kg
9 Air 34,641.39 Liter
10 Batu Gunung / Batu Kali 71.22 M3
11 Pasir Pasang 72.74 M3
12 Tanah Timbun 107.35 M3
13 Besi Beton Polos 58,799.65 kg
14 Kawat Beton 2,238.26 kg
15 Paku 5 Cm - 10 Cm 228.56 Kg
16 Minyak Bekisting 108.57 Liter
17 Besi Beton Ulir 100,881.20 kg
18 Plywood Tebal 9 mm 144.83 Lbr
19 Kayu Dolken dia. 8 - 10 Cm, L = 4 M 1,830.37 Batang
20 Balok Kayu Kelas II 6.61 M³
21 Batu Bata 42,569.17 Bh
22 Keramik Lantai Uk. 40 x 40 Cm 2,651.12 Bh
23 Keramik Lantai Uk. 20 x 20 Cm 783.48 Kg
24 Semen Warna 567.72 Kg
25 Atap Seng Genteng 332.34 Lbr
26 Paku Seng 57.80 Kg
27 Rabung Seng Genteng 7.65 M
28 Paku 1.97 kg
29 Balok Kayu Kelas 1 3.08 M3
30 Lem Kayu 11.75 Kg
31 Papan Kayu Kelas II 2.90 M3
32 Sealant 0.77 Tube
33 Kaca Tebal 5 mm 16.87 M2
34 Plamir 90.17 Kg
35 Cat Dasar Tembok 90.17 Kg
36 Cat Tembok / Penutup 2x 234.45 Kg
37 Cat Menie 12.31 Kg
38 Plamir Kayu 9.24 Kg
39 Cat Dasar Kayu 10.47 Kg
40 Cat Kayu Penutup 16.01 Kg
41 Kuas 0.62 Bh
42 Pengencer 1.85 Liter
43 Ampelas 12.31 Lbr
44 Kloset Jongkok Porselen 6.00 Bh
45 Urinoir 6.00 Bh
46 Engsel Pintu 48.00 Bh
47 Kunci Pintu Standar 12.00 Bh
48 Engsel Jendela 60.00 Bh
49 Pacok Jendela 40.00 Bh
50 Hak Angin Jendela 40.00 Bh
JADWAL PELAKSANAAN PEKARJAAN
BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII BULAN IX
2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
URAIAN PERALATAN UNIT SAT. BULAN I BULAN II BULAN III
1 2 3 4 1 2 3 4 1 2 3

TRUCK 4 Unit
DUMP TRUCK 4 Unit
MOBIL TANGKI AIR 2 Unit
MOBIL PICK UP 2 Unit
SEPEDA MOTOR 4 Unit
MOLEN 3 Unit
READY MIX 1 Unit
STAMPER 2 Unit
VIBRATOR 1 Unit
GENSET 2 Unit
MESIN POMPA AIR 2 Unit
THODELIT 1 Unit
WATER PASS 1 Unit
KERETA SORONG 6 Unit
SKABILDING/PERANCAH 20 Psg P
METERAN 50 M 1 Unit
MESIN POTONG BESI 4 Unit
KOMPUTER 1 Unit
PRINTER 1 Unit
ALAT-ALAT TUKANG 3 Set
METERAN 5 M 1 Unit
EXCAVATOR 1 Unit
CRANE 1 Unit
JADWAL PENGGUNAAN PERALATAN
BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII BULAN IX
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3
BULAN IX BULAN X BULAN XI
4 1 2 3 4 1 2 3 4
DIAGRAM KEBUTUHAN TENAGA KERJA PERMINGGU

70

60 59 59
55
50
50
45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45

40

33 33 33
30 29 29
26
23
20
20
16 16

10 9 9 9 9 9 9

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

DIAGRAM KEBUTUHAN TENAGA KERJA PERBULAN


250

204
200
185
180 180 180 180

150 140
125

100

47 50
50

0
BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII BULAN IX BULAN X

DIAGRAM KEBUTUHAN TENAGA KERJA KOMULATIF


1600
1480
1471
1462
1453
1437
1421
1412
1403
1394
1374
1351
1322

1400
1293
1234
1175
1120

1200
1075
1030
985
940

1000
895
850
805
760

800
715
670
625
580
535

600
490
445
400
355

400
310
265
220
175

200
125
92
59
26

0
1 2 3 4 5 6 7 8 9 10 11 12 13 1 4 1 5 1 6 1 7 18 1 9 20 21 22 23 24 2 5 2 6 2 7 2 8 2 9 30 31 32 33 34 3 5 3 6 3 7 38 39 40 41
NO URAIAN PEKERJAAN
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH DAN PONDASI
II.A. Pondasi Tapak
II.B. Pondasi Menerus
II.C. Timbunan Tanah Bawah Lantai
III PEKERJAAN BETON BERTULANG
III.A. Pondasi Tapak 150 x 200 Cm
III.B. Pondasi Tapak 125 x 125 Cm
III.C. Pondasi Tapak 100 x 100 Cm
III.D. Sloof Beton 30/55
III.E. Sloof Beton 25/40
III.F. Kolom 40/60
III.G. Kolom 40/40
III.H. Kolom KP 13/13
III.I. Balok Lantai 25/60
III.J. Balok Lantai 25/40
III.K. Balok Bordes 20/20
III.L. Plat Bordes
III.M. Plat Tangga
III.N. Sloof Tangga 25/40
III.O. Kolom K1 40/60
III.P. Kolom K1 40/40
III.Q. Kolom Praktis 13/13
III.R. Plat Lantai
III.S. Balok RB 25/30
IV PEKERJAAN PASANGAN DAN PLASTERAN
IV.A. Pasangan Dinding Bata 1:2(Trasram)
IV.B. Plasteran Dinding Bata 1:2(Trasram)
IV.C. Pasangan Dinding Bata 1:4
IV.D. Plasteran Dinding Bata 1:4
IV.E. Pasangan Dinding Bata 1:2(Trasram)
IV.F. Plasteran Dinding Bata 1:2(Trasram)
IV.G. Pasangan Dinding Bata 1:4
IV.H. Plasteran Dinding Bata 1:4
V PEKERJAAN GRANIT DAN KERAMIK
V.A. Lantai Keramik 40 x 40 Cm
V.B. Lantai Keramik 20 x 20 Cm
V.C. Lantai Keramik 40 x 40 Cm
V.D. Lantai Keramik 20 x 20 Cm
VI PEKERJAAN ATAP
VI.A. Atap
VII PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC
VIII.A. Pemasangan Pintu, Jendela, Ventilasi dan lainnya
VIII.B. Pemasangan Pintu, Jendela, Ventilasi dan lainnya
VIII PEKERJAAN PENGECATAN
VIII.A. Pengecatan
VIII.B. Pengecatan
IX PEKERJAAN ELEKTRIKAL
IX.A. Elektrikal
IX.B. Elektrikal
X PEKERJAAN SANITASI
X.A. Sanitasi
X.B. Sanitasi
XI PEKERJAAN KUNCI DAN PENGGANTUNG
XI.A. Kunci dan Penggantung
XI.B. Kunci dan Penggantung
PEKERJAAN LANTAI DURASI
LANTAI I 5 HARI

LANTAI I 12 HARI
LANTAI I 13 HARI
LANTAI I 6 HARI 31

LANTAI I 14 HARI
LANTAI I 14 HARI
LANTAI I 4 HARI
LANTAI I 17 HARI
LANTAI I 11 HARI
LANTAI I 11 HARI
LANTAI I 18 HARI
LANTAI I 5 HARI
LANTAI I 7 HARI
LANTAI I 16 HARI
LANTAI I 4 HARI
LANTAI I 3 HARI
LANTAI I 3 HARI
LANTAI I 2 HARI
LANTAI II 5 HARI
LANTAI II 6 HARI
LANTAI II 8 HARI
LANTAI II 20 HARI
LANTAI II 7 HARI 177

LANTAI I 5 HARI
LANTAI I 8 HARI
LANTAI I 7 HARI
LANTAI I 10 HARI
LANTAI II 1 HARI
LANTAI II 2 HARI
LANTAI II 6 HARI
LANTAI II 14 HARI 54

LANTAI I 6 HARI
LANTAI I 1 HARI
LANTAI II 5 HARI
LANTAI II 1 HARI 13

LANTAI II 12 HARI 12

LANTAI I 20 HARI
LANTAI II 19 HARI 40
LANTAI I 5 HARI
LANTAI II 8 HARI 13

LANTAI I 10 HARI
LANTAI II 10 HARI 20

LANTAI I 17 HARI
LANTAI II 10 HARI 27

LANTAI I 15 HARI
LANTAI II 15 HARI 29
NO URAIAN PEKERJAAN
V PEKERJAAN GRANIT DAN KERAMIK
V.A.
V.B.
V.C.
V.D.
VI PEKERJAAN ATAP
VI.A.
VII PEKERJAAN PEMASANGAN PINTU,JEND
VIII.A.
VIII.B.
VIII PEKERJAAN PENGECATAN
VIII.A.
VIII.B.
IX PEKERJAAN ELEKTRIKAL
IX.A.
IX.B.
X PEKERJAAN SANITASI
X.A.
X.B.
XI PEKERJAAN KUNCI DAN PENGGANTUN
XI.A.
XI.B.
URAIAN PEKERJAAN PEKERJAAN LANTAI DURASI
PEKERJAAN GRANIT DAN KERAMIK
Lantai Keramik 40 x 40 Cm LANTAI I 6
Lantai Keramik 20 x 20 Cm LANTAI I 1
Lantai Keramik 40 x 40 Cm LANTAI II 5
Lantai Keramik 20 x 20 Cm LANTAI II 1
PEKERJAAN ATAP
Atap LANTAI II 12
PEKERJAAN PEMASANGAN PINTU,JENDELA,ETC
Pemasangan Pintu, Jendela, Ventilasi dan lainnya LANTAI I 20
Pemasangan Pintu, Jendela, Ventilasi dan lainnya LANTAI II 19
PEKERJAAN PENGECATAN 0
Pengecatan LANTAI I 5
Pengecatan LANTAI II 8
PEKERJAAN ELEKTRIKAL
Elektrikal LANTAI I 10
Elektrikal LANTAI II 10
PEKERJAAN SANITASI
Sanitasi LANTAI I 17
Sanitasi LANTAI II 10
PEKERJAAN KUNCI DAN PENGGANTUNG
Kunci dan Penggantung LANTAI I 15
Kunci dan Penggantung LANTAI II 15
DURASI

HARI
HARI
HARI
HARI

HARI

HARI
HARI
HARI
HARI

HARI
HARI

HARI
HARI

HARI
HARI
NO LANTAI 1
I. PEKERJAAN PERSIAPAN
1. Pembersihan Lahan
GAMBAR :

PERHITUNGAN VOL SAT


Panjang = 30
Lebar = 13.5
Luas (PxL) = 15*32,5 405 M2

2. Pasang Bawplank/Pengukuran
GAMBAR :

PERHITUNGAN VOL SAT


Panjang = 11.5
Lebar = 28
Keliling = (P+L)*2 79 M'
II. PEKERJAAN TANAH PONDASI TAPAK
NO PERHITUNGAN VOL SAT GAMBAR
1 Pekerjaan Pondasi Tapak 150/200
a. Galian Tanah
Tinggi = 2.2 M
Lebar = 1.7 M
Panjang = 2.2 M
Unit = 8 Unit
Volume = (PxLxT)xUnit 65.824 M3

b. Aanstamping
Tinggi = 0.1 M
Lebar = 1.7 M
Panjang = 2.2 M
Unit = 8 Unit
Volume = ( P x L x T ) x Unit 2.992 M3

c. Urungan Tanah Kembali


Volume = 3/4 x Volume Galian
Volume Galian Tanah = 65.824
49.368 M3
d. Pasir Alas
Tinggi = 0.1 M
Lebar = 1.7 M
Panjang = 2.2 M
Unit = 8 Unit
Volume = ( P x L x T ) x Unit 2.992 M3

e. Pondasi Tapak Berulang 1:2:3


Pias I
Tinggi = 0.4 M
Lebar = 1.5 M
Panjang = 2 M
Unit = 8 Unit
Volume = ( P x L x T ) x Unit 9.60 M3

Pias II
Tinggi = 0.1 M
Lebar = 1.5 M
Panjang = 2 M
Unit = 8 Unit
Volume = (( P x L x (1/2*T) ) x Unit 1.20 M3

Pias III
Tinggi = 2.25 M
Lebar = 0.4 M
Panjang = 0.6 M
Unit = 8 Unit
Volume = ( P x L x T ) x Unit 4.32 M3

Volume Total = 9,6+1,2+4,32 15.12 M3


NO PERHITUNGAN VOL SAT GAMBAR
2 Pekerjaan Pondasi Tapak 125/125
a Galian Tanah
Tinggi = 2.2 M
Lebar = 1.45 M
Panjang = 1.45 M
Unit = 15 Unit
Volume = (PxLxT)xUnit 69.3825 M3

b. Aanstamping
Tinggi = 0.1 M
Lebar = 1.45 M
Panjang = 1.45 M
Unit = 15 Unit
Volume = ( P x L x T ) x Unit 3.15375 M3

c. Urungan Tanah Kembali


Volume = 3/4 x Volume Galian
Volume Galian Tanah = 69.3825
52.0369 M3
d. Pasir Alas
Tinggi = 0.1 M
Lebar = 1.45 M
Panjang = 1.45 M
Unit = 15 Unit
Volume = ( P x L x T ) x Unit 3.15375 M3

e. Pondasi Tapak Berulang 1:2:3


Pias I
Tinggi = 0.4 M
Lebar = 1.25 M
Panjang = 1.25 M
Unit = 15 Unit
Volume = ( P x L x T ) x Unit 9.38 M3

Pias II
Tinggi = 0.1 M
Lebar = 1.25 M
Panjang = 1.25 M
Unit = 15 Unit
Volume = (( P x L x (1/2*T) ) x Unit 1.17 M3

Pias III
Tinggi = 2.25 M
Lebar = 0.4 M
Panjang = 0.4 M
Unit = 15 Unit
Volume = ( P x L x T ) x Unit 5.4 M3

Volume Total = 9,38+1,17+5,4 15.9469 M3


NO PERHITUNGAN VOL SAT GAMBAR
3 Pekerjaan Pondasi Tapak 100/100
a. Galian Tanah
Tinggi = 2.2 M
Lebar = 1.2 M
Panjang = 1.2 M
Unit = 12 Unit
Volume = (PxLxT)xUnit 38.016 M3

b. Aanstamping
Tinggi = 0.1 M
Lebar = 1.2 M
Panjang = 1.2 M
Unit = 12 Unit
Volume = ( P x L x T ) x Unit 1.728 M3

c. Urungan Tanah Kembali


Volume = 3/4 x Volume Galian
Volume Galian Tanah = 38.016 M3
28.512 M3
d. Pasir Alas
Tinggi = 0.1 M
Lebar = 1.2 M
Panjang = 1.2 M
Unit = 12 Unit
Volume = ( P x L x T ) x Unit 1.728 M3

e. Pondasi Tapak Berulang 1:2:3


Pias I
Tinggi = 0.4 M
Lebar = 1 M
Panjang = 1 M
Unit = 12 Unit
Volume = ( P x L x T ) x Unit 4.80 M3

Pias II
Tinggi = 0.1 M
Lebar = 1 M
Panjang = 1 M
Unit = 12 Unit
Volume = (( P x L x (1/2*T) ) x Unit 0.60 M3

Pias III
Tinggi = 2.25 M
Lebar = 0.4 M
Panjang = 0.4 M
Unit = 12 Unit
Volume = ( P x L x T ) x Unit 4.32 M3

Volume Total = 4,8+0,6+4,32 9.72 M3


III PEKERJAAN TANAH PONDASI MENERUS
GAMBAR :

NO PERHITUNGAN VOL SAT GAMBAR


a. GalianPondasi Menerus
Panjang Horizontal = 55.98 M
Panjang Vertikal = 34.6 M
Total Panjang = 90.58 M
Tinggi = 0.75 M
Lebar = 0.80 M
Volume = (P*L*T)
90,58+0,80+0,75 92.13 M3

b Urugan Kembali Pondasi Menerus


Volume = 1/4*Vol. Galian pond. Menerus
= 1/4*(92,13) 23.03 M3

c Pasir Alas Pondasi Menerus


Tinggi = 0.05 M
Lebar = 0.8 M
Panjang = 142.5 M
Volume = (P*L*T) 5.7 M3

d Aanstamping Pondasi Menerus


Tinggi = 0.1 M
Lebar = 0.8 M
Panjang = 142.5 M
Volume = (P*L*T) 11.4 M3
142,5x0,8x0,1

e Pas. Batu Gunung


Tinggi = 0.6 M
Lebar a = 0.3 M
Lebar b = 0.6 M
Panjang = 142.5 M
Volume = (( a + b )/2 x P x T )) 38.475 M3
((0,3+0,6)/2)x142,5x0,6
f Sloof 25/40
Tinggi = 0.4 M
Lebar = 0.25 M
Panjang = 142.5 M
Volume = (P*L*T) 14.25 M3
142,5x0,25x0,4

g Sloof 30/55
Tinggi = 0.55 M
Lebar = 0.3 M
Panjang = 32 M
Volume = (P*L*T) 5.28 M3
= 32x0,3x0,55

Pasir Alas Sloof


Tinggi = 0.05 M
Lebar = 0.5 M
Panjang = 32 M
Volume = (P*L*T) 0.80 M3
= 32x0,05x0,55

Anstamping Sloof
Tinggi = 0.1 M
Lebar = 0.5 M
Panjang = 32 M
Volume = (P*L*T) 1.6 M3
= 32+0,5+0,1
V PEKERJAAN LANTAI
GAMBAR :

NO PERHITUNGAN VOL SAT GAMBAR


1 Urugan Tanah Bawah lantai
a Tangga Elv. -0.25 (Bagian 1)
Tinggi = 0.36 M
Lebar = 0.4 M
Panjang = 26.0 M
Volume = (PxLxT)
= 26x0,3x0,1 3.744 M3

b Selasar Elv. -0.05 (Bagian 1)


Tinggi = 0.3 M
Lebar = 1.5 M
Panjang = 25.93 M
L.kolom dalam = 1.44 M2
Volume = (((P x L)-L.Kol) x T)
= (25,3x1,44)-1,44)x0,3 11.23 M3

c. Lantai Bawah Tangga ±0.00


Tinggi = 0.35 M
Lebar = 4.93 M
Panjang = 5.74 M
L.kolom dalam = 4.28 M2
Volume = (((P x L)-L.Kol) x T)
= ((5,74x4,93)-4,28)x0,35 19.79 M3

d Ruang Belajar ±0.00


Tinggi = 0.35 M
Lebar = 7.87 M
Panjang = 9.87 M
L.kolom dalam = 4.69 M2
Volume = (((P x L)-L.Kol) x T)*2 M2
54.37 M3
e Kamar Mandi
Kamar Mandi -0.15 (Bagian 1)
Tinggi = 0.15 M
Lebar = 2.74 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = (((P x L)-L.Kol) x T)
((1,87x2,74)-0,27)x0,15 0.77 M3

Kamar Mandi -0.15 (Bagian 2)


Tinggi = 0.15 M
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = (((P x L)-L.Kol) x T)
= ((1,87x2,87)-0,27)x0,15 1.61 M3

f Urinoir -0.15
Tinggi = 0.15 M
Lebar = 2 M
Panjang = 3 M
L.kolom dalam = 0.27 M2
Volume = (((P x L)-L.Kol) x T)
= ((3x2)-0,27)x0,15 0.90 M3

Volume Total = 0,78+11,23+19,79+54,37+ 92.42 M3


0,77+1,61+0,9
NO PERHITUNGAN VOL SAT GAMBAR
2 Pasir Urug Bawah lantai
a Selasar
Tinggi = 0.15 M
Lebar = 1.5 M
Panjang = 25.925 M
L.kolom dalam = 1.44 M2
Volume = ((P x L)-L.Kol) x T
= ((25,925x1,5))-1,44)x0,15 11.23 M3

b Ruang Belajar 1 dan Ruang Belajar 2


Tinggi = 0.15 M
Lebar = 7.87 M
Panjang = 9.87 M
L.kolom dalam = 4.69 M2
Volume = (((P x L)-L.Kol) x T)*2
= ((9,87x7,87))-4,69)x0,15 21.90 M3

c Lantai dibawah tangga


Tinggi = 0.15 M
Lebar = 4.925 M
Panjang = 5.74 M
L.kolom dalam = 4.28 M2
Volume = ((P x L)-L.Kolom) x T
= ((5,74x4,925))-4,28)x0,15 3.60 M3

d WC 1
Tinggi = 0.15 M
Lebar = 2.74 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = ((P x L)-L.Kolom) x T
= ((5,74x4,925))-4,28)x0,15 0.73 M3

e WC 2
Tinggi = 0.15 M
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = ((P x L)-L.Kolom) x T
= ((5,74x4,925))-4,28)x0,15 0.76 M3

f Urinoir
Tinggi = 0.15 M
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.535 M2
Volume = ((P x L)-L.Kolom) x T
= ((1,87x2,87))-0,535)x0,15 0.72 M3

V.Total = 11,23+21,90+3,60+0,73+ 38.95


0,76+0,72
3 Beton Cor Bawah Lantai
a Selasar
Tinggi = 0.07 M
Lebar = 1.5 M
Panjang = 25.925 M
L.kolom dalam = 1.44 M2
Volume = (((P x L)-L.Kol) x T)*2
= ((25,925x1,5))-1,44)x0,07 5.24 M3

b Ruang Belajar 1 dan Ruang Belajar 2


Tinggi = 0.07 M
Lebar = 7.87 M
Panjang = 9.87 M
L.kolom dalam = 4.69 M2
Volume = (((P x L)-L.Kol) x T)*2
= ((9,975x7,87))-4,69)x0,07x2 10.22 M3

c Lantai dibawah tangga


Tinggi = 0.07 M
Lebar = 4.925 M
Panjang = 5.74 M
L.kolom dalam = 4.28 M2
Volume = ((P x L)-L.Kolom) x T
= ((5,745x4,925))-4,28)x0,07 1.68 M3

d WC 1
Tinggi = 0.07 M
Lebar = 2.74 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = ((P x L)-L.Kolom) x T
= ((1,875x2,74))-0,27)x0,07 0.34 M3

e WC 2
Tinggi = 0.07 M
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Volume = ((P x L)-L.Kolom) x T
= ((1,87x1,87))-0,27)x0,07 0.36 M3

f Urinoir
Tinggi = 0.07 M
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.535 M2
Volume = ((P x L)-L.Kolom) x T
((1,875x2,87))-0,535)x0,07 0.34 M3

V.Total = 5,24+10,221,68+0,34+0,36+ 18.17 M3


0.34
4 Keramik
a Keramik 40x40
Selasar
Lebar = 1.5 M
Panjang = 25.925 M
L.kolom dalam = 1.44 M2
Luas = ( P x L )-L.Kolom
= 25,925x1,5)-1,44 37.4 M2

Ruang Belajar 1 dan Ruang Belajar 2


Lebar = 7.87 M
Panjang = 9.87 M
L.kolom dalam = 4.69 M2
Luas = ( P x L )-L.Kolom*2
= (9,87x7,87)-4,69x2 146.0 M2

Lantai dibawah tangga


Lebar = 4.925 M
Panjang = 5.74 M
L.kolom dalam = 4.69 M2
Luas = ( P x L )-L.Kolom
= (5,74x4,925)-4,69 23.6 M2

Total Keramik 40x40 = 37,40x146x23,60 207.0 M2

b Keramik 20x20
WC 1
Lebar = 2.74 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,74)-0,27 4.9 M2

WC 2
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,87)-0,27 5.1 M2

Urinoir
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.535 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,87])-0,535 4.8 M2

L.Total Keramik 20x20 = 4,90x5,10x4,80 14.8 M2


VI PEKERJAAN TANGGA
GAMBAR :

a Anak Tangga
Lebar = 1.3 M
Panjang = 3.25 M
Tinggi = 0.09 M
Luas = PxLxTx2(Jlh.anak tangga sama)
= 1,3x1,3x18 0.4 M2

b Plat Tangga
Lebar = 1.30 M
Panjang = 3.25 M
Tinggi = 0.12 M
Volume = PxLxTx2
= 3,25x1,30x0,12x2 1.01 M3

c Plat Bordes
Lebar = 1.45 M
Panjang = 2.87 M
Tinggi = 0.12 M
Volume = PxLxT
= 2,87x1,45x0,12 0.50 M3

d Balok Bordes 20/30


Lebar = 0.2 M
Panjang = 3 M
Tinggi = 0.3 M
Volume = PxLxT
= 3x0,2x0,3 0.18 M3

e Sloof 25/40
Lebar = 0.25 M
Panjang = 1.3 M
Tinggi = 0.40 M
Volume = PxLxT
= 1,3x0,25x0,40 0.13 M3

f Keramik
Anak Tangga
Panjang = 0.3
Lebar = 0.18
Jumlah = 18
Luas = PxLxJumlah
= 0,3x0,18x18 1.0 M3

Bordes
Panjang = 2.87
Lebar = 1.45
Luas = PxL
= 2,87x1,45 4.2 M3

g Relling Tangga
Panjang = Px2
= 3,55x2 7.1 M
VI PEKERJAAN BETON BERTULANG
GAMBAR :

3. PEKERJAAN BETON BERTULANG


a Kolom Praktis 13/13
Tinggi = 3.75 M
Lebar = 0.15 M
Panjang = 0.15 M
Unit =9 Unit
Volume = (PxLxT)xUnit
0,15x0,15x3,75x9 0.76 M3

b Kolom K1 40/60
Tinggi = 3.75 M
Lebar = 0.4 M
Panjang = 0.6 M
Unit = 8 Unit
Volume = (PxLxT)xUnit
0,5x0,15x3,75x9 7.20 M3

c Kolom K2 40/40
Tinggi = 3.75 M
Lebar = 0.4 M
Panjang = 0.4 M
Unit = 24 Unit
Volume = (PxLxT)xUnit
0,4x0,4x3,75x24 14.40 M3
VII PEKERJAAN KUSEN
GAMBAR :

NO PERHITUNGAN VOL SAT GAMBAR


3. Perhitungan Volume Kusen
a Kusen
Kusen Pintu P1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 5.74 M
Unit =2 Unit
Volume = (PxLxT)xUnit
5.74x0,06x0,13x2 0.09 M3

Kusen Pintu P2
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 4.96 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
= 4,96x0,06x0,13x4 0.15 M3

Kusen Jendela J1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 6.62 M
Unit = 10 Unit
Volume = (PxLxT)xUnit
= 6,62+0,06+0,13x10 0.52 M3

Kusen Ventilasi V1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 4.32 M
Unit = 15 Unit
Volume = (PxLxT)xUnit
= 4,32x0,06x0,13x15 0.51 M3
Total = 0,09+0,15+0,52+0,51 1.27 M3
b Daun Pintu dan Jendela
Daun Pintu P1
Lebar = 2.1 M
Panjang = 1.6 M
Unit = 2 Unit
Volume = (PxLx)xUnit
1,6x2,1x2 6.72 M2

Daun Pintu P2
Lebar = 2.1 M
Panjang = 0.8 M
Unit = 4 Unit
Volume = (PxL)xUnit
0,8x2,1x4 6.72 M2
c Ambang Daun Jendela
Daun Jendela J1
Lebar = 0.08 M
Panjang = 3.30 M
Unit = 10 Unit
Volume = (PxLx)xUnit
3,30x0.08x10 2.64 M2

d Kaca
Kaca Jendela J2
Lebar = 1.05 M
Panjang = 0.46 M
Unit = 10 Unit
Volume = (PxLx)xUnit
1,22x0.08x10 4.83 M2

Kaca Ventilasi
Lebar = 0.31 M
Panjang = 0.61 M
Unit = 15 Unit
Volume = (PxLx)xUnit
1,22x0.08x15 2.84 M2

Pengecatan Kusen
P1 = (0,13+0,06)x5,74x2 2.18 M2
P2 = (0,13+0,06)x4,96x4 3.77 M2
J1 = (0,13+0,06)x6,62x10 12.58 M2
J1 = (0,13+0,06)x4,32x15 12.26 M2
Total = 2,18+3,77+12,58+12,26 30.78 M2
NO PERHITUNGAN VOL SAT GAMBAR
4 PEKERJAAN DINDING
a Mengitung Dinding Bata Transram 1 : 2
Dinding Bata Trasram 1 : 2 ( A : Tangga )
Tinggi = 0.25 M
Panjang = 26.3 M
Lebar Kusen =0 M2
Luas = (P -L.Kusen)xT
= (26,3-0)x0,25 6.58 M2

Dinding Bata Trasram 1 : 2 ( B : Selasar )


Tinggi = 0.45 M
Panjang = 27.5 M
Lebar Kusen =0 M2
Luas = (P -L.Kusen)xT
= (27,5-0)x0,45 12.38 M2

Dinding Bata Trasram 1 : 2 ( C : Ruang Belajar dan Ruang bawah tangga )


Tinggi = 0.9 M
Panjang = 71 M
Lebar Kusen = 3.44 M 2

Luas = (P -L.Kusen)xT
= (71-3,44)x0,9 60.80 M2

Dinding Bata 1 : 4 ( D : Wc dan Urinoir )


Tinggi = 1.9 M
Panjang = 26 M
Lebar Kusen = 3.2 M2
Luas = (P -L.Kusen)xT
= (26-3,2)x1,9 43.32 M2
Luas Total = 6,58+12,38+60,80+43,32 123.07 M2

Luas Kusen Pintu =

Plesteran = (L.dinding1:2)x2
= (123,07)x2 246.15 M2

b Mengitung Dinding Bata 1 : 4


Dinding Ruang belajar dan Dinding di Bawah Tangga
Tinggi = 2.85 M
Panjang = 71 M
Luas Kusen = 43.81 M2
Luas = (PxT)-Luas Kusen
= 97x3,10-43,81 158.55 M2

Wc dan Urinoir
Tinggi = 1.85 M
Panjang = 26 M
Luas Kusen = 43.81 M2
Luas = (PxT)-Luas Kusen
= 97x3,10-43,81 4.30 M2
Luas Total = 158,55+4,30 162.84 M2

Luas Plesteran = (L.dinding1:4)x2


= (162,84)x2 325.68 M2
Pengecetan 162,84*2 325.68 M2
NO LANTAI 2
I. DENAH LANTAI II
GAMBAR :

II. DENAH BALOK LANTAI

NO PERHITUNGAN VOL SAT GAMBAR


1 PLAT LANTAI
a Pias I
Tinggi = 0.12 M
Panjang = 3.13 M
Lebar = 1.30 M
Banyak Pias I (U) = 6
Volume = (PxLxT)xU
= 3,13x1,30x0,12x6 2.93 M3

b Pias II
Tinggi = 0.12 M
Panjang = 2.85 M
Lebar = 1.30 M
Banyak Pias I (U) = 2
Volume = (PxLxT)xU
= 2,85x1,30x0,12x2 0.89 M3

c Pias III
Tinggi = 0.12 M
Panjang = 3.13 M
Lebar = 3.80 M
Banyak Pias I (U) = 12
Volume = (PxLxT)xU
= 3,13x3,80x0,12x12 17.13 M3
d Pias IV
Tinggi = 0.12 M
Panjang = 2.8 M
Lebar = 3.76 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= 2,80x3,76x0,12x1 1.26 M3

e Pias V
Tinggi = 0.12 M
Panjang = 2.80 M
Lebar = 0.80 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= 2,80x0,80x0,12x1 0.27 M3

f Pias VI
Tinggi = 0.12 M
Panjang = 1.80 M
Lebar = 1.30 M
Banyak Pias I (U) = 2
Volume = (PxLxT)xU
= 1,80x1,30x0,12x1 0.56 M3

g Pias VII
Tinggi = 0.12 M
Panjang = 1.80 M
Lebar = 2.80 M
Banyak Pias I (U) = 2
Volume = (PxLxT)xU
= 1,80x2,80x0,12x2 1.21 M3

V.Total = 24.25

2 BALOK LANTAI
a Balok Lantai 25/40
Tinggi = 0.4 M
Panjang = 158 M
Lebar = 0.25 M
Volume = (PxLxT)xU
= 135x0,25x0,4 15.80 M3

b Balok Lantai 25/60


Tinggi = 0.6 M
Panjang = 32 M
Lebar = 0.25 M
Volume = (PxLxT)xU
= 32x0,25x0,6 4.80 M3

Volume Total B.Lantai = 13,50+4,80 20.60 M3


NO PERHITUNGAN VOL SAT GAMBAR
4 Keramik
a Keramik 40x40
Selasar
Lebar = 1.5 M
Panjang = 25.925 M
L.kolom dalam = 1.44 M2
Luas = ( P x L )-L.Kolom
= 25,925x1,5)-1,44 37.4 M2

Ruang Belajar 1 dan Ruang Belajar 2


Lebar = 7.87 M
Panjang = 9.87 M
L.kolom dalam = 4.69 M2
Luas = ( P x L )-L.Kolom*2
= (9,87x7,87)-4,69x2 146.0 M2

Lantai Bagian Tengah


Lebar = 4.925 M
Panjang = 2.87 M
L.kolom dalam = 4.69 M2
Luas = ( P x L )-L.Kolom
= (5,74x2,87)-4,69 9.4 M2

Total Keramik 40x40 = 37,40x146x23,60 192.9 M2

b Keramik 20x20
WC 1
Lebar = 2.74 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,74)-0,27 4.9 M2

WC 2
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.27 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,87)-0,27 5.1 M2

Urinoir
Lebar = 2.87 M
Panjang = 1.87 M
L.kolom dalam = 0.535 M2
Luas = ( P x L )-L.Kolom
= (1,87x2,87])-0,535 4.8 M2

L.Total Keramik 20x20 = 4,90x5,10x4,80 14.8 M2


III. DENAH KOLOM LANTAI 2
GAMBAR :

3. PEKERJAAN BETON BERTULANG


a Kolom Praktis 13/13
Tinggi = 3.15 M
Lebar = 0.13 M
Panjang = 0.13 M
Unit =9 Unit
Volume = (PxLxT)xUnit
0,15x0,15x3,75x9 0.48 M3

b Kolom K1 40/60
Tinggi = 3.15 M
Lebar = 0.4 M
Panjang = 0.6 M
Unit = 8 Unit
Volume = (PxLxT)xUnit
0,5x0,15x3,75x9 6.05 M3

c Kolom K2 40/40
Tinggi = 3.15 M
Lebar = 0.4 M
Panjang = 0.4 M
Unit = 24 Unit
Volume = (PxLxT)xUnit 12.10 M3
0,4x0,4x3,75x24
IV. PEKERJAAN KUSEN
GAMBAR :

NO PERHITUNGAN VOL SAT GAMBAR


3. Perhitungan Volume Kusen
a Kusen
Kusen Pintu P1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 5.74 M
Unit =2 Unit
Volume = (PxLxT)xUnit
5.74x0,06x0,13x2 0.09 M3

Kusen Pintu P2
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 4.96 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
= 4,96x0,06x0,13x4 0.15 M3

Kusen Jendela J1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 6.62 M
Unit = 10 Unit
Volume = (PxLxT)xUnit
= 6,62+0,06+0,13x10 0.52 M3

Kusen Ventilasi V1
Tinggi = 0.13 M
Lebar = 0.06 M
Panjang = 4.32 M
Unit = 15 Unit
Volume = (PxLxT)xUnit
= 4,32x0,06x0,13x15 0.51 M3
Total = 0,09+0,15+0,52+0,51 1.27 M3
b Daun Pintu dan Jendela
Daun Pintu P1
Lebar = 2.1 M
Panjang = 1.6 M
Unit = 2 Unit
Volume = (PxLx)xUnit
1,6x2,1x2 6.72 M2

Daun Pintu P2
Lebar = 2.1 M
Panjang = 0.8 M
Unit = 4 Unit
Volume = (PxL)xUnit
0,8x2,1x4 6.72 M2
c Ambang Daun Jendela
Daun Jendela J1
Lebar = 0.08 M
Panjang = 3.30 M
Unit = 10 Unit
Volume = (PxLx)xUnit
3,30x0.08x10 2.64 M2

d Kaca
Kaca Jendela J2
Lebar = 1.05 M
Panjang = 0.46 M
Unit = 10 Unit
Volume = (PxLx)xUnit
1,22x0.08x10 4.83 M2

Kaca Ventilasi
Lebar = 0.31 M
Panjang = 0.61 M
Unit = 15 Unit
Volume = (PxLx)xUnit
1,22x0.08x15 2.84 M2

V. PEKERJAAN DINDING
NO PERHITUNGAN VOL SAT GAMBAR
1. Menghitung dinding Bata 1 : 2
Mengitung Dinding Bata 1 : 2 (Bagian 1)
Tinggi = 3.15 M
Panjang = 97 M
L.Kusen = 43.63 M2
Luas = (PxT)-Luas Kusen
= 102x43,63-43,63 261.92 M2

Mengitung Dinding Bata 1 : 4 (Bagian 2)


Tinggi = 0.9 M
Panjang = 29 M
Lebar Kusen =0 M2
Luas = (PxT)-Luas Kusen
= 29x0,9-0 26.10 M2
Luas Total = 261,92+26,10 288.02 M2

Plesteran = L.Dindingx2
288,02x2 576.03 M2
Pengecetan 162,84*2 576.03 M2
2 Menghitung Dinding Transram
Dinding Bata 1 : 4 ( Wc dan Urinoir )
Tinggi = 1.5 M
Panjang = 26 M
Lebar Kusen = 3.2 M2
Luas = (P -Lebar Kusen)xT
= (26-3,2)x1,5 34.20 M2

Plesteran = L.Dindingx2
= 34,20x2 68.4 M2
V. RING BALOK

NO PERHITUNGAN VOL SAT GAMBAR


1. Menghitung Ring Balok
Balok Lantai 25/35
Tinggi = 0.4 M
Panjang = 132 M
Lebar = 0.25 M
Volume = (PxLxT)xU
= 132x0,25x0,4 13.20 M3

V. PEKERJAAN ATAP
GAMBAR :

1. Pekerjaan Atap
Rangka Baja Ringan
Panjang = 28.2 M
Lebar = 10.4 M
Luas = PxL
= 28,2x10,4 293.28 M2

Penutup Atap
Seng Spandek = Luas 293.28 M2

Rabung
Seng Spandek = P 28.2 M

Lisplank
Panjang = 28.2
= Px2
= 28,2x2 56.4 M
PERHITUNGAN BESI DAN BEKISTING

Pekerjaan Bangunan Gedung Akper Cut Nyak Dien


Lokasi Banda Aceh

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


1 Sloof SL 1 ( 0.30 x 0.55 ) M = 1/( b x h)
= 6.061 m'
Jumlah Tul. Pokok = 8.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 4.00 Batang Berat besi Ø 16, = 76.52 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.150 M Berat besi Ø 12, = 21.52 kg
Luas Permukaan Papan = 1.10 M2
3. Tulangan Begel Besi Ø 10,
Panjang begel = 1.550 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 40.40 ± -------> 40.00 Btg
41 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 39.18 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L. permukaan papan


= 6.667 m2 -------> 50%

Total Berat Besi = 137.22 Kg/M3


Papan mal 2 x Pakai = 3.333 M2/M3

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


2 Sloof SL2 ( 0.25 x 0.40 ) M = 1/( b x h)
= 10.00 m'
Jumlah Tul. Pokok = 5.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 4.00 Batang Berat besi Ø 12, = 44.39 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.12 M Berat besi Ø 12, = 35.51 kg
Luas Permukaan Papan = 0.80 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 1.150 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 83.33 ± -------> 83.00 Btg
84 btg

Berat besi Ø 6, = Byk begel x Pjg begel x 0.006165 x dia.2


= 21.44 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L. permukaan papan


= 8.000 m2 -------> 50%

Total Berat Besi = 101.34 Kg/M3


Papan mal 2 x Pakai = 4.00 M2/M3
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


3 Kolom K1 ( 0.40 x 0.60 ) M = 1/( b x h)
= 4.17 m'
Jumlah Tul. Pokok = 12.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 19.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 6.00 Batang Berat besi Ø 19, = 111.28 kg
Ø Tul. Pinggang = 19.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 19, = 55.64 kg
Luas Permukaan Papan = 2.00 M2
3. Tulangan Begel Besi Ø 10,
Panjang begel = 1.850 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 41.67 ± -------> 41.00 Btg
42 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 47.90 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L.permukaan papan


= 8.33 m2 -------> 50%

Total Berat Besi = 214.82 Kg


Papan mal 2 x Pakai = 4.167 M2

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


4 Kolom K2 ( 0.40 x 0.40 ) M = 1/( b x h)
= 6.25 m'
Jumlah Tul. Pokok = 10.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 4.00 Batang Berat besi Ø 16, = 98.64 kg
Ø Tul. Pinggang = 16.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 16, = 39.46 kg
Luas Permukaan Papan = 1.60 M2
3. Tulangan Begel Besi Ø 10,
Panjang begel = 1.450 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 62.50 ± -------> 62.00 Btg
63 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 56.32 kg

4. Papan mal = Pjg balok untuk 1 m3 beton xL.permukaan papan


= 10.00 m2 -------> 50%

Total Berat Besi = 194.41 Kg


Papan mal 2 x Pakai = 5.000 M2
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


6 Kolom KP ( 0.13 x 0.13 ) M = 1/( b x h)
= 59.17 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 14.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 14, = 286.00 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 0.52 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 0.370 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 591.72 ± -------> 591.00 Btg
592 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 135.04 kg

4. Papan mal = Pjg balok untuk 1 m3 beton xL. permukaan papan


= 30.77 m2 -------> 50%

Total Berat Besi = 421.04 Kg


Papan mal 2 x Pakai = 15.38 M2

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


7 Balok BL1 25 ( 0.25 x 0.60 ) M = 1/( b x h)
= 6.67 m'
Jumlah Tul. Pokok = 10.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 16, = 105.22 kg
Ø Tul. Pinggang = 14.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.850 M Berat besi Ø 14, = 16.11 kg
Luas Permukaan Papan = 1.21 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.550 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 7.84 ± -------> 8.00 Btg
8 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 7.6446 kg

4. Papan mal = Pjg balok untuk 1 m3 beton xL. permukaan papan


= 8.07 m2 -------> 50%

Total Berat Besi = 128.97 Kg


Papan mal 2 x Pakai = 4.033 M2
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


8 Balok BL2 ( 0.25 x 0.40 ) M = 1/( b x h)
= 10.00 m'
Jumlah Tul. Pokok = 6.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 16, = 94.69 kg
Ø Tul. Pinggang = 14.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.150 M Berat besi Ø 14, = 24.17 kg
Luas Permukaan Papan = 0.81 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.150 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 66.67 ± -------> 67.00 Btg
67 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 47.50 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L. permukaan papan


= 8.10 m2 -------> 50%

Total Berat Besi = 166.36 Kg


Papan mal 2 x Pakai = 4.050 M2

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3
Balok RB 25/35
PERHITUNGAN Panjang balok untuk 1 m3
10 ( 0.25 x 0.35 ) M = 1/( b x h)
= 11.43 m'
Jumlah Tul. Pokok = 5.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 16, = 90.19 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 0.71 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.050 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 114.29 ± -------> 115.00 Btg
115 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 74.4424 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L. permukaan papan


= 8.11 m2 -------> 50%

Total Berat Besi = 164.63 Kg


Papan mal 2 x Pakai = 4.057 M2
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3
Balok Bordes 20/30
PERHITUNGAN Panjang balok untuk 1 m3
11 ( 0.20 x 0.30 ) M = 1/( b x h)
= 16.67 m'
Jumlah Tul. Pokok = 5.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 12, = 73.98 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 10.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 12, = 29.59 kg
Luas Permukaan Papan = 0.56 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 0.850 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 166.67 ± -------> 167.00 Btg
167 btg

Berat besi Ø 10, = Byk begel x Pjg begel x 0.006165 x dia.2


= 87.5122 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x L. permukaan papan


= 9.33 m2 -------> 50%

Total Berat Besi = 191.08 Kg


Papan mal 2 x Pakai = 4.667 M2

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 25,50 Meter


12 Plat Bordes = 12 cm Panjang Besi (Pjb) = 1.45 M
Jumlah Baris Besi (Jb) = 14.35 M
Bidang X = 2.87 M Jumlah Lapis (Jl) = 1.00 Lapis
Bidang Y = 1.45 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.20 M = 12.82 Kg

2. Untuk Bidang 22,50 Meter


Panjang Besi (Pjb) = 2.87 M
Jumlah Baris Besi (Jb) = 7.25 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 12.82 Kg

Total Berat Besi = 25.64 Kg

Berat Besi Untuk 1 m3 Beton = 51.35 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton


NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 25,50 Meter


13 Plat Tangga = 12 cm Panjang Besi (Pjb) = 3.25 M
Jumlah Baris Besi (Jb) = 7.35 M
Bidang X = 1.47 M Jumlah Lapis (Jl) = 1.00 Lapis
Bidang Y = 3.25 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.20 M = 14.72 Kg

2. Untuk Bidang 22,50 Meter


Panjang Besi (Pjb) = 1.47 M
Jumlah Baris Besi (Jb) = 16.25 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 14.72 Kg

Total Berat Besi = 29.44 Kg

Berat Besi Untuk 1 m3 Beton = 51.35 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.33 M2 / M3 Beton

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 25,50 Meter


14 Plat Lantai = 12 cm Panjang Besi (Pjb) = 19.00 M
Jumlah Baris Besi (Jb) = 260.00 M
Bidang X = 52.00 M Jumlah Lapis (Jl) = 1.00 Lapis
Bidang Y = 19.00 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.20 M = 3044.03 Kg

2. Untuk Bidang 22,50 Meter


Panjang Besi (Pjb) = 52.00 M
Jumlah Baris Besi (Jb) = 95.00 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 3044.03 Kg

Total Berat Besi = 6,088.06 Kg

Berat Besi Untuk 1 m3 Beton = 51.35 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton


NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 1.00 Meter


15 Pondasi Tapak 150/200 = 150 cm Panjang Besi (Pjb) = 2.00 M
Jumlah Baris Besi (Jb) = 10.00 M
Bidang X = 1.50 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 2.00 M Diameter Besi (d) = 16.00 mm
Tebal Pengecoran = 0.40 M
Diameter Besi = 16.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.150 M = 63.099 Kg

2. Untuk Bidang 1.00 Meter


Panjang Besi (Pjb) = 1.50 M
Jumlah Baris Besi (Jb) = 13.33 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 16.00 mm

Berat besi Ø 16, = Pjg*Jb*Jl*0.006162*d*d


= 31.549 Kg

Total Berat Besi = 94.65 Kg

Berat Besi Untuk 1 m3 Beton = 78.87 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 2.500 M2 / M3 Beton

NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 1.00 Meter


15 Pondasi Tapak 125/125 = 125 cm Panjang Besi (Pjb) = 1.25 M
Jumlah Baris Besi (Jb) = 8.33 M
Bidang X = 1.25 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 1.25 M Diameter Besi (d) = 16.00 mm
Tebal Pengecoran = 0.40 M
Diameter Besi = 16.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.150 M = 32.864 Kg

2. Untuk Bidang 1.00 Meter


Panjang Besi (Pjb) = 1.25 M
Jumlah Baris Besi (Jb) = 8.33 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 16.00 mm

Berat besi Ø 16, = Pjg*Jb*Jl*0.006162*d*d


= 16.432 Kg

Total Berat Besi = 49.30 Kg

Berat Besi Untuk 1 m3 Beton = 78.87 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 2.500 M2 / M3 Beton


NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN 1. Untuk Bidang 1.00 Meter


15 Pondasi Tapak 100/100 = 100 cm Panjang Besi (Pjb) = 1.00 M
Jumlah Baris Besi (Jb) = 6.67 M
Bidang X = 1.00 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 1.00 M Diameter Besi (d) = 16.00 mm
Tebal Pengecoran = 0.40 M
Diameter Besi = 16.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.150 M = 21.033 Kg

2. Untuk Bidang 1.00 Meter


Panjang Besi (Pjb) = 1.00 M
Jumlah Baris Besi (Jb) = 6.67 M
Jumlah Lapis (Jl) = 1.00 Lapis
Diameter Besi (d) = 16.00 mm

Berat besi Ø 16, = Pjg*Jb*Jl*0.006162*d*d


= 10.516 Kg

Total Berat Besi = 31.55 Kg

Berat Besi Untuk 1 m3 Beton = 78.87 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 2.500 M2 / M3 Beton


REKAPTULASI
RENCANA ANGGARAN BIAYA

Pekerjaan : Pembangunan Gedung Akper Cut Nyak Dhien


Lokasi : Banda Aceh
Tahun Anggaran : 2019

NO URAIAN PEKERJAAN JUMLAH HARGA

LANTAI I
1 Pekerjaan Persiapan Rp 22,757,289
2 Pekerjaan Tanah dan Pondasi Rp 97,764,818
3 Pekerjaan Beton Bertulang Rp 71,174,780
4 Pekerjaan Dinding Dan Plasteran Rp 95,821,893
5 Pekerjaan Lantai Rp 212,347,690
6 Pekerjaan Pintu, Jendela dan Ventilasi Rp 27,800,057
7 Pekerjaan Pengecatan Rp 13,115,100
8 Pekerjaan Instalasi Listrik Rp 9,785,000
9 Pekerjaan Pengunci Rp 14,020,048
10 Sanitasi Rp 32,422,975

LANTAI II
1 Pekrjaan Beton Bertulang Rp 319,657,095
2 Pekerjaan Pintu, Jendela dan Ventilasi Rp 27,800,057
3 Pekerjaan Dinding Dan Plasteran Rp 105,835,562
4 Pekerjaan Lantai Rp 58,994,321
5 Pekerjaan Pengecatan Rp 17,065,645
6 Pekerjaan Instalasi Listrik Rp 10,185,000
7 Pekerjaan Pengunci Rp 14,020,048
8 Sanitasi Rp 13,922,975
9 Pekerjaan Atap Rp 153,141,581

Jumlah Harga Pekerjaan Rp 1,317,631,933


Dibulatkan Rp 1,317,100,000
Terbilang : Satu Miliar Tujuh Puluh Enam Juta Enam Ratus Dua Puluh Tiga Ribu Rupiah