I. UPAH PEKERJA
HARGA
NO. JENIS PEKERJA KODE SATUA
Rp
N
1 Pekerja L. 01 Hr 75,000.00
2 Mandor L. 02 Hr 100,000.00
3 Tukang listrik L. 03 Hr 87,500.00
4 Tukang kayu L. 04 Hr 87,500.00
5 Kep. tk. kayu L. 05 Hr 93,750.00
6 Tukang batu L. 06 Hr 87,500.00
7 Kep. tk. batu L. 07 Hr 93,750.00
8 Tukang besi L. 08 Hr 87,500.00
9 Kep. tk. besi L. 09 Hr 93,750.00
10 Tukang cat L. 10 Hr 87,500.00
11 Kep. tk. cat L. 11 Hr 93,750.00
12 Tukang plitur L. 12 Hr 87,500.00
13 Tukang jalan L. 13 Hr 87,500.00
14 Tukang gali L. 14 Hr 87,500.00
15 Tukang masak aspal L. 15 Hr 87,500.00
16 Tk. leideng L. 16 Hr 87,500.00
17 Operator M a s i n i s L. 17 Hr 87,500.00
18 Pemb. Masinis L. 18 Hr 81,250.00
19 Penjaga api L. 19 Hr 80,000.00
20 Penjaga malam L. 20 Hr 65,000.00
21 Sopir L. 21 Hr 81,250.00
22 Pembantu Sopir L. 22 Hr 75,000.00
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
: I (SATU)
II BAHAN
I BAHAN DASAR
1 BATU KALI Bulat Belah m3 278,100.00
Pecah 10/15 m3 309,320.00
Pecah 5/7 m3 314,820.00
Pecah 3/5 m3 323,070.00
2 KERIKIL Timbunan Pilihan/sirtu m3 75,800.00
Sawur / Koral m3 261,250.00
Beton 0,5/1 m3 230,000.00
Beton 1/2 m3 230,000.00
Beton 2/3 m3 230,000.00
3 BATU BATA bh 838.00
4 PASIR Urug m3 187,500.00
Pasang m3 294,250.00
Beton m3 313,500.00
5 TANAH Padas m3 60,700.00
6 KAPUR Pasang m3 288,700.00
7 PORTLAND CEMENT
Portland Cement kg 1,750.00
Portland Cement 40 kg kg 70,000.00
Semen warna kg 1,900.00
II BAHAN PENUTUP ATAP
1 GENTENG BETON
Kerpus Beton Warna Standard bh 8,500.00
Genteng press beton polos tipe nusantara bh 8,500.00
5 PLY WOOD
Teak wood
. 120 X 240 X 3 mm lbr 85,000.00
. 90 X 210 X 4 mm lbr 77,500.00
Tripleks
. 120 X 240 X 3 mm lbr 52,800.00
. 120 X 240 X 4 mm lbr 62,800.00
Multipleks
. 120 X 240 X 9 mm lbr 109,000.00
. 120 X 240 X 12 mm lbr 150,000.00
Formika ukuran pintu lbr 75,000.00
Eternit m2 18,500.00
GRC (1,2 x 2,4 m2 tb 4 mm) lbr 60,000.00
Plywood tebal 4 mm uk.90x220cm lbr 52,800.00
Plywood tebal 4 mm uk.120x240cm lbr 80,000.00
IX BAHAN FINISHING
1 KAYU
Menie kg 29,000.00
Dempul plamur kg 25,000.00
Ambril/amplas lbr 5,700.00
Cat dasar kg 62,800.00
- Koas bh 9,000.00
. Plitur jadi ltr 51,000.00
. Vernis ltr 42,100.00
2 TEMBOK
Plamur kg 15,000.00
Cat tembok kg 21,000.00
3 BESI
Menie kg 45,000.00
Cat kg 55,000.00
Minyak cat ltr 17,000.00
Residu (teer/aspal) drum 296,000.00
Lem Aica Aibon kg 35,000.00
X BAHAN KACA
1 POLOS 3 mm m2 70,000.00
5 mm m2 95,000.00
2 RAY BAND 5 mm m2 108,000.00
XV LAIN -LAIN
1 Naco rayban 5 mm per Daun bh 82,000.00
2 Naco bening 5 mm per Daun bh 91,000.00
3 Rolling door Besi m2 285,000.00
4 Rolling door Almunium m2 443,000.00
5 Kusen Almunium 4" Putih m' 72,000.00
6 Kusen Almunium 4" Coklat m' 78,000.00
7 Besi Holo rangka gypsum m1 6,250.00
8 Minyak Beton & bekisting ltr 17,000.00
9 Pintu Lipat Besi 0.8 mm m2 660,000.00
10 Soda api kg 27,200.00
11 Air m3 72,500.00
12 Solar (Industri) ltr 8,700.00
13 Premium (Industri) ltr 6,950.00
14 Pelumas ltr 33,000.00
15 MCB /Box m' 250,000.00
16 Fiting unit 15,000.00
17 Dudukan Fitting unit 5,000.00
18 Kabel m' 5,000.00
19 Lampu 20 watt unit 40,000.00
20 Lampu 10 watt unit 20,000.00
21 Saklar tunggal unit 27,000.00
22 Saklar ganda unit 35,000.00
23 Stop kontak unit 18,000.00
24 Kabel NYM /50m 8,500.00
XVI ORNAMEN
1 Pohon Palem unit 200,000.00
2 Rumput Gajah mini unit 25,000.00
3 Pohon Mangga unit 250,000.00
4 Bunga Bogenvile unit 35,000.00
5 Batu coral putih kg 5,000.00
6 Lampu taman unit 5,000.00
7 u-ditch unit 442,000.00
8 Pohon dollar unit 30,000.00
9 aluminium penutup unit 550,000.00
10 Aluminium komposit panel unit 550,000.00
I PEKERJAAN PERSIAPAN
A. 2.2.1.9 Pembersihan 1 m2 lapangan dan perataan
Harga
Jumlah
No Uraian Kode Satuan Koefisien Satuan
(Rp) Harga
A TENAGA
Pekerja L. 01 OH 0.750 75,000.00 56,250.00
Mandor L. 02 OH 0.025 100,000.00 2,500.00
JUMLAH TENAGA
58,750.00
KERJA
B Jumlah (A) 58,750.00
C Overhead & Profit ( 10 %) 10% x B 5,875.00
D Harga Satuan Pekerjaan (B+C) 64,625.00
A.2.3.1.9. Pengurukan kembali 1 m3 galian tanah
Harga
Jumlah
Satuan
No Uraian Kode Satuan Koefisien
(Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.500 75,000.00 37,500.00
Mandor L. 02 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA
42,500.00
KERJA
JUMLAH HARGA
42,500.00
BAHAN
B Jumlah (A) 42,500.00
C Overhead & Profit ( 10 %) 10% x B 4,250.00
D Harga Satuan Pekerjaan (B+C) 46,750.00
A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug
Harga
Jumlah
Satuan
No Uraian Kode Satuan Koefisien
(Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.300 75,000.00 22,500.00
Mandor L. 02 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA
23,500.00
KERJA
B BAHAN
Pasir urug m3 1.200 187,500.00 225,000.00
JUMLAH HARGA
225,000.00
BAHAN
C Jumlah (A+B) 248,500.00
D Overhead & Profit (10 %) 10% x C 24,850.00
E Harga Satuan Pekerjaan (C+D) 273,350.00
A.2.3.1.10. Pemadatan Tanah (per 20 cm)
Harga
Jumlah
Satuan
No Uraian Kode Satuan Koefisien
(Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.500 75,000.00 37,500.00
Mandor L. 02 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA
42,500.00
KERJA
JUMLAH HARGA
42,500.00
BAHAN
C Jumlah (A) 42,500.00
D Overhead & Profit (10 %) 10% x C 4,250.00
E Harga Satuan Pekerjaan (C+D) 46,750.00
A.2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 m
Harga
Jumlah
Satuan
No Uraian Kode Satuan Koefisien
(Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.9 75,000.00 67,500.00
Mandor L. 02 OH 0.045 100,000.00 4,500.00
JUMLAH TENAGA
72,000.00
KERJA
B Jumlah (A) 72,000.00
C Overhead & Profit ( 10 %) 10% x B 7,200.00
D Harga Satuan Pekerjaan (B+C) 79,200.00
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
IV PEKERJAAN BETON
A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 1.650 75,000.00 123,750.00
Tukang Batu L. 06 OH 0.275 87,500.00 24,062.50
Kepala Tukang Batu L. 07 OH 0.028 93,750.00 2,625.00
Mandor L. 02 OH 0.083 100,000.00 8,300.00
JUMLAH TENAGA KERJA 158,737.50
B BAHAN
Semen Portland kg 247 1,750.00 432,250.00
Pasir Beton m3 869 313,500.00 272,431,500.00
Kerikil 2/3 m3 999 230,000.00 229,770,000.00
JUMLAH HARGA BAHAN 502,633,750.00
Jumlah (A+B) 502,792,487.50
C Overhead & Profit (10 %) 10% x C 50,279,248.75
D Harga Satuan Pekerjaan (C+D) 553,071,736.25
E
A.4.1.1.5 Harga Satuan Jumlah
Uraian Kode Satuan Koefisien (Rp) Harga
No (Rp)
TENAGA
A Pekerja L. 01 OH 1.650 75,000.00 123,750.00
Tukang Batu L. 06 OH 0.275 87,500.00 24,062.50
Kepala Tukang Batu L. 07 OH 0.028 93,750.00 2,625.00
Mandor L. 02 OH 0.083 100,000.00 8,300.00
JUMLAH TENAGA KERJA 158,737.50
BAHAN
B Semen Portland kg 326 1,750.00 570,500.00
Pasir Beton kg 760 313,500.00 238,260,000.00
Kerikil 2/3 kg 1029 230,000.00 236,670,000.00
JUMLAH HARGA BAHAN 475,500,500.00
Jumlah (A+B) 475,659,237.50
Overhead & Profit (10 %) 10% x C 47,565,923.75
C Harga Satuan Pekerjaan (C+D) 523,225,161.25
D
E
A.4.1.1.17 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.070 75,000.00 5,250.00
A Tukang Besi L. 08 OH 0.070 87,500.00 6,125.00
Kepala Tukang Besi L. 07 OH 0.007 93,750.00 656.25
Mandor L. 02 OH 0.004 100,000.00 400.00
JUMLAH TENAGA KERJA 12,431.25
BAHAN
Besi beton (polos / ulir) kg 10.500 10,000.00 105,000.00
B Kawat beton kg 0.150 19,000.00 2,850.00
JUMLAH HARGA BAHAN 107,850.00
Jumlah (A+B) 120,281.25
Overhead & Profit (Contoh 10 %) 10% x C 12,028.13
C Harga Satuan Pekerjaan (C+D) 13,230.94
D
E
A.4.1.1.2 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.520 75,000.00 39,000.00
A Tukang Kayu L. 06 OH 0.260 87,500.00 22,750.00
Kepala Tukang Kayu L. 07 OH 0.026 93,750.00 2,437.50
Mandor L. 02 OH 0.026 100,000.00 2,600.00
JUMLAH TENAGA KERJA 66,787.50
BAHAN
Kayu sengon m3 0.045 3,475,000.00 156,375.00
B Paku 5 cm – 10 cm kg 0.300 13,000.00 3,900.00
Minyak bekisting Liter 0.100 33,000.00 3,300.00
JUMLAH HARGA BAHAN 163,575.00
Jumlah (A+B) 230,362.50
Overhead & Profit (10 %) 10% x C 23,036.25
C Harga Satuan Pekerjaan (C+D) 253,398.75
D
E Pemasangan 1 m2 bekisting untuk kolom
A.4.1.1.22 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.660 75,000.00 49,500.00
A Tukang Kayu L. 06 OH 0.330 87,500.00 28,875.00
Kepala Tukang Kayu L. 07 OH 0.033 93,750.00 3,093.75
Mandor L. 02 OH 0.033 100,000.00 3,300.00
JUMLAH TENAGA KERJA 84,768.75
BAHAN
Kayu Sengon m3 0.040 3,475,000.00 139,000.00
B Paku 5 cm – 12 cm kg 0.400 13,000.00 5,200.00
Minyak bekisting Liter 0.200 33,000.00 6,600.00
Balok kayu Meranti m3 0.015 7,850,000.00 117,750.00
Plywood tebal 9 mm Lbr 0.350 109,000.00 38,150.00
Bambu m 2.000 17,500.00 35,000.00
JUMLAH HARGA BAHAN 341,700.00
Jumlah (A+B) 426,468.75
Overhead & Profit (10 %) 10% x C 42,646.88
C Harga Satuan Pekerjaan (C+D) 469,115.63
D Pemasangan 1 m2 bekisting untuk balok
E
A.4.1.1.23
Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.660 75,000.00 49,500.00
A Tukang Kayu L. 06 OH 0.330 87,500.00 28,875.00
Kepala Tukang Kayu L. 07 OH 0.033 93,750.00 3,093.75
Mandor L. 02 OH 0.033 100,000.00 3,300.00
JUMLAH TENAGA KERJA 84,768.75
BAHAN
Kayu Sengon m3 0.040 3,475,000.00 139,000.00
B Paku 5 cm – 12 cm kg 0.400 13,000.00 5,200.00
Minyak bekisting Liter 0.200 33,000.00 6,600.00
Balok kayu Meranti m3 0.018 7,850,000.00 141,300.00
Plywood tebal 9 mm Lbr 0.350 109,000.00 38,150.00
Bambu Batang 2.000 17,500.00 35,000.00
JUMLAH HARGA BAHAN 365,250.00
Jumlah (A+B) 450,018.75
Overhead & Profit (Contoh 10 %) 10% x C 45,001.88
C Harga Satuan Pekerjaan (C+D) 495,020.63
D
E Pemasangan 1 m2 bekisting untuk lantai
A.4.1.1.24 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.660 75,000.00 49,500.00
A Tukang Kayu L. 06 OH 0.330 87,500.00 28,875.00
Kepala Tukang Kayu L. 07 OH 0.033 93,750.00 3,093.75
Mandor L. 02 OH 0.033 100,000.00 3,300.00
JUMLAH TENAGA KERJA 84,768.75
BAHAN
Kayu Sengon m3 0.040 3,475,000.00 139,000.00
B Paku 5 cm – 12 cm kg 0.400 13,000.00 5,200.00
Minyak bekisting Liter 0.200 33,000.00 6,600.00
Balok kayu Meranti m3 0.015 7,850,000.00 117,750.00
Plywood tebal 9 mm Lbr 0.350 109,000.00 38,150.00
Bambu Batang 6.000 17,500.00 105,000.00
JUMLAH HARGA BAHAN 411,700.00
Jumlah (A+B) 496,468.75
Overhead & Profit (Contoh 10 %) 10% x C 49,646.88
C Harga Satuan Pekerjaan (C+D) 546,115.63
D
E
A.4.1.1.27 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.150 75,000.00 11,250.00
A Tukang Kayu L. 06 OH 0.050 87,500.00 4,375.00
Kepala Tukang kayu L. 07 OH 0.005 93,750.00 468.75
Mandor L. 02 OH 0.008 100,000.00 800.00
JUMLAH TENAGA KERJA 16,893.75
BAHAN
Kayu Terentang m3 0.026 2,000,000.00 52,800.00
B Paku 2" – 5" kg 0.600 13,000.00 7,800.00
Dolken Kayu Galam m3 0.500 18,000.00 9,000.00
JUMLAH HARGA BAHAN 69,600.00
Jumlah (A+B) 86,493.75
Overhead & Profit (Contoh 10 %) 10% x C 8,649.38
C Harga Satuan Pekerjaan (C+D) 95,143.13
D
E
A.4.1.1.8 Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 1.650 75,000.00 123,750.00
A Tukang Batu L. 06 OH 0.275 87,500.00 24,062.50
Kepala Tukang Batu L. 07 OH 0.028 93,750.00 2,625.00
Mandor L. 02 OH 0.083 100,000.00 8,300.00
JUMLAH TENAGA KERJA 158,737.50
BAHAN
Semen Portland kg 384 1,700.00 652,800.00
B Pasir Beton kg 692 313,500.00 216,942,000.00
Kerikil 2/3 kg 1,039 230,000.00 238,970,000.00
Air Liter 215 #REF! #REF!
JUMLAH HARGA BAHAN #REF!
Jumlah (A+B) #REF!
Overhead & Profit (10 %) 10% x C #REF!
C Harga Satuan Pekerjaan (C+D) #REF!
D
E
A.4.1.1.20
Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.52 75,000.00 39,000.00
A Tukang Kayu L. 06 OH 0.26 87,500.00 22,750.00
Kepala Tukang L. 07 OH 0.026 93,750.00 2,437.50
Mandor L. 02 OH 0.026 100,000.00 2,600.00
JUMLAH TENAGA KERJA 66,787.50
BAHAN
Kayu Klas III (Terentang) m3 0.04 2,000,000.00 80,000.00
B Paku Biasa 2" - 5" kg 0.3 13,000.00 3,900.00
Minyak Bekisting Liter 0.1 33,000.00 3,300.00
JUMLAH HARGA BAHAN 87,200.00
Jumlah (A+B) 153,987.50
Overhead & Profit (Contoh 10 %) 10% x C 15,398.75
C Harga Satuan Pekerjaan (C+D) 169,386.25
D
E
A.4.1.1.26
Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
No TENAGA
Pekerja L. 01 OH 0.66 75,000.00 49,500.00
A Tukang Kayu L. 06 OH 0.33 87,500.00 28,875.00
Kepala Tukang L. 07 OH 0.033 93,750.00 3,093.75
Mandor L. 02 OH 0.033 100,000.00 3,300.00
JUMLAH TENAGA KERJA 84,768.75
BAHAN
Kayu Klas III (Terentang) m3 0.03 2,000,000.00 60,000.00
B Paku Biasa 2" - 5" kg 0.4 13,000.00 5,200.00
Minyak Bekisting Liter 0.15 33,000.00 4,950.00
JUMLAH HARGA BAHAN 70,150.00
Jumlah (A+B) 154,918.75
Overhead & Profit (Contoh 10 %) 10% x C 15,491.88
C Harga Satuan Pekerjaan (C+D) 170,410.63
D
E
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II dan III (Kamfer)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 6.000 75,000.00 450,000.00
Tukang kayu L. 04 OH 18.000 87,500.00 1,575,000.00
Kepala Tukang Kayu L. 05 OH 1.800 93,750.00 168,750.00
Mandor L. 02 OH 0.300 100,000.00 30,000.00
JUMLAH TENAGA KERJA 2,223,750.00
B BAHAN
Balok kayu Kamfer m3 1.200 8,855,000.00 10,626,000.00
Paku 10 cm Kg 1.250 13,000.00 16,250.00
Lem kayu bh 1.000 19,000.00 19,000.00
JUMLAH HARGA BAHAN 10,661,250.00
C Jumlah (A+B) 12,885,000.00
D Overhead & Profit (Contoh 10 %) 10% x C 1,288,500.00
E Harga Satuan Pekerjaan (C+D) 14,173,500.00
A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu Kelas II (Kamfer)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.350 75,000.00 26,250.00
Tukang kayu L. 04 OH 1.050 87,500.00 91,875.00
Kepala Tukang Kayu L. 05 OH 0.105 93,750.00 9,843.75
Mandor L. 02 OH 0.018 100,000.00 1,800.00
JUMLAH TENAGA KERJA 129,768.75
B BAHAN
Papan kayu Kamfer m3 0.040 9,150,000.00 366,000.00
Paku 5 – 7 cm Kg 0.050 35,000.00 1,750.00
JUMLAH HARGA BAHAN 367,750.00
C Jumlah (A+B) 497,518.75
D Overhead & Profit (0 %) 10% x C 49,751.88
E Harga Satuan Pekerjaan (C+D) 547,270.63
Pembuatan dan pemasangan 1
A.4.6.1.6. m2 pintu dan jendela kaca, kayu
kelas II (Jati)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.800 75,000.00 60,000.00
Tukang kayu L. 04 OH 2.400 87,500.00 210,000.00
Kepala Tukang Kayu L. 05 OH 0.240 93,750.00 22,500.00
Mandor L. 02 OH 0.040 100,000.00 4,000.00
JUMLAH TENAGA KERJA 296,500.00
B BAHAN
Papan kayu Jati m3 0.024 27,150,000.00 651,600.00
Lem kayu Kg 0.300 19,000.00 5,700.00
JUMLAH HARGA BAHAN 657,300.00
C Jumlah (A+B+C) 953,800.00
D Overhead & Profit (10 %) 10% x C 95,380.00
E Harga Satuan Pekerjaan (C+D) 1,049,180.00
A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.015 75,000.00 1,125.00
Tukang kayu L. 04 OH 0.15 87,500.00 13,125.00
Kepala Tukang Kayu L. 05 OH 0.015 93,750.00 1,406.25
Mandor L. 02 OH 0.0008 100,000.00 80.00
JUMLAH TENAGA KERJA 15,736.25
B BAHAN
Kaca tebal 5 mm m2 1.10 95,000.00 104,500.00
Sealant Kg 0.05 60,000.00 3,000.00
JUMLAH HARGA BAHAN 107,500.00
C Jumlah (A+B) 123,236.25
D Overhead & Profit (Contoh 10 %) 10% x C 12,323.63
E Harga Satuan Pekerjaan (C+D) 135,559.88
A.4.6.2.5. Pemasangan 1 buah engsel pintu
8 Hitung D-04 1 unit Pek. Pasang Pintu Fiber Kamar Mandi 132,550.00
A Tenaga 132,100.00
0.84 OH Pekerja 75,000.00 50,400.00
0.84 OH Tukang 87,500.00 73,500.00
0.08 OH Kepala Tukang 93,750.00 7,500.00
0.01 OH Mandor 70,000.00 700.00
B Bahan
C PERALATAN
D Jumlah A + B + C 132,100.00
E Overhead & Profit 10% 13,210.00
F Harga Satuan Pekerjaan (D+E) 145,310.00
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
Rp 27,616.33
Rp 8,893.75
Rp 3,750.00
Rp 4,375.00
Rp 468.75
Rp 300.00
Rp 16,212.00
Rp 15,120.00
Rp 1,092.00
Rp 25,105.75
Rp 2,510.58
Rp 27,616.33
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
IX PEKERJAAN PENGECATAN
A.4.7.1.10.Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.02 75,000.00 1,500.00
Tukang cat L. 10 OH 0.063 87,500.00 5,512.50
Kepala tukang cat L. 11 OH 0.0063 93,750.00 590.63
Mandor L. 02 OH 0.003 100,000.00 300.00
JUMLAH TENAGA KERJA 7,903.13
B BAHAN
Plamur Kg 0.10 25,000 2,500.00
Cat dasar Kg 0.10 62,800 6,280.00
Cat penutup Kg 0.26 21,000 5,460.00
JUMLAH HARGA BAHAN 14,240.00
C Jumlah (A+B) 22,143.13
D Overhead & Profit (10 %) 10% x C 2,214.31
E Harga Satuan Pekerjaan (C+D) 24,357.44
A.4.7.1.10.Pengecatan 1 m2 Atap
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.02 75,000.00 1,500.00
Tukang cat L. 10 OH 0.063 87,500.00 5,512.50
Kepala tukang cat L. 11 OH 0.0063 93,750.00 590.63
Mandor L. 02 OH 0.003 100,000.00 300.00
JUMLAH TENAGA KERJA 7,903.13
B BAHAN
Cat penutup Kg 0.26 21,000 5,460.00
JUMLAH HARGA BAHAN 5,460.00
C Jumlah (A+B) 13,363.13
D Overhead & Profit (Contoh 10 %) 10% x C 1,336.31
E Harga Satuan Pekerjaan (C+D) 14,699.44
A.4.7.1.4. Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L. 01 OH 0.07 75,000.00 5,250.00
Tukang cat L. 10 OH 0.009 87,500.00 787.50
Kepala tukang cat L. 11 OH 0.006 93,750.00 562.50
Mandor L. 02 OH 0.003 100,000.00 300.00
JUMLAH TENAGA KERJA 6,900.00
B BAHAN
Cat menie Kg 0.20 29,000.00 5,800.00
Plamur Kg 0.15 25,000.00 3,750.00
Cat dasar Kg 0.17 62,800.00 10,676.00
Cat penutup Kg 0.26 21,000.00 5,460.00
Kuas Bh 0.01 9,000.00 90.00
Vernis ltr 0.03 42,100.00 1,263.00
Ampelas Lbr 0.2 5,700.00 1,140.00
JUMLAH HARGA BAHAN 28,179
C Jumlah (A+B) 35,079.00
D Overhead & Profit (10 %) 10% x C 3,507.90
E Harga Satuan Pekerjaan (C+D) 38,586.90
BAB V
PERHITUNGAN VOLUME DAN RAB
TUGAS MANAJEMEN KONSTRUKSI
PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH SURAKARTA
X PEKERJAAN SANITASI
XI PEKERJAAN ELEKTIKAL