TUGAS 8
PERENCANAAN PONDASI TIANG PANCANG GROUP PILE
DATA TANAH CONE PENETRATION TEST (CPT)
Oleh:
Nama: Nabilah Fasya
Nim: 160523610921
Off: D
Data :
N = 1000 ton
ML = 80 ton.m
MB = 60 ton.m
MT s/d TK = 5,60 m
Dw = 1,20 m
Lpile = 4m
T = 1/10 Lpile cap
= 1/10 10,23
= 1,02 m
D pile = 40 cm x 40 cm
beban penutup lantai keramik = 24 kg/m2 (PMI 1970)
beban berguna pada bangunan tempat ibadah = 400 kg/m2 (PMI 1970)
= 1,40 ton/m3
= 1,80 ton/m3
1
= 1,00 ton/m3
= 2,40 ton/m3
= 1,80 ton/m3
3. Penyelesaian :
3.1 Konversikan CPT menjadi Data Triaxial Test (C dan )
3.1.1 Menentukan Nilai Kohesi (C)
Kedalaman 8D + 4D = 12D = 12 (0,4 m) = 4,8 m
Perhitungan qc dimulai dari kedalaman = (MT s/d TK) – (8D + 4D)
= 5,60 m – 4,8 m
= 0,8 m
C = antara dan
2
3.1.2 Menentukan Sudut Geser ( ) memakai Rumus Mejerhoft
3.2 Dicoba dengan Tiang Pancang sebanyak 24 Pile seperti dibawah ini:
3
Kontrol
1600 cm2 =
D =
= 45 cm
= 0,45 m
Sehingga diperoleh Dekivalen = 0,45 m
S = 4 D ekivalen
= 4 0,45
= 1,81 m
Lg = ΣS + D riil
= (5 1,81) + 0,4 m
= 9,43 m
Bg = ΣS + D riil
= (3 1,81) + 0,4 m
= 5,82 m
4
Ukuran poer : Lx = Lg + 2D
= 9,43 + 2(0,4)
= 10,23 m
Ukuran poer : By = Bg + 2D
= 5,82 + 2(0,4)
= 6,62 m
Uraian perhitungan ΣV
1) Berat Pile Cap
V = B L T ; Berat = V
= 6,62 10,23 1,02 = 69,246 2,4
3
= 69,246 m = 166,190 ton
5
2) Berat 24 Pile
V = jumlah pile
= 24
= 15,360 m3
Berat = V
= 15,360 2,4
= 36,864 ton
Arah X
= 0,5 S
= 0,5 1,806
= 0,903 m (8 tiang)
= S
= 0,903 + 1,806 m
= 2,709 m (8 tiang)
= +S
= 2,709 + 1,806
= 4,515 m (8 tiang)
Arah Y
= 0,5 S
= 0,5 1,806
= 0,903 m (12 tiang)
= +S
= 0,903 + 1,806
= 2,709 m (12 tiang)
7
= 12 (0,903 m)2 = 9,783 m2
= 12 (2,709 m)2 = 88,051 m2
+
2
= 97,834 m
8
Bg = 5,82 m
Lg = 9,43 m
9
68,670 ton > Qmaks = 55,074 ton (AMAN)
m=4
n =6
Qall = Qis Eg n
= 68,670 0,861 24
= 1420,145 ton > ΣV = 1243,94 ton (AMAN)
10
3.10 Menghitung Penurunan ( )
Keterangan gambar :
2/3 Lpile = 2/3 4 = 2,667 m
h = [(MT s/d TK) – (2/3Lpile)]
= [(5,6 m) – (2,667 m)]
= 2,933 m
h1 =
= 1,467 m
h2 =
= 1,467 m
Z1 =
= 0,733 m
Z2 = h1
= 1,467 m
= 2,2 m
11
3.10.1 Menghitung Tegangan Efektif Tanah (Po’)
= (
= (1,4 1,2) [( 1,8 – 1) (2,667 – 1,2)] + [(1,8 – 1) 0,773)]
= 3,440 ton/m2
=
= 3,440 [(1,8 – 1) (2,2 – 0,733)]
2
= 4,613 ton/m
12
13
Penurunan total ( ) =
= 0,02568 + 0,00672
= 0,03240 cm
14
Lampiran 1. Perencanaan Pondasi Dangkal Tiang Pancang Group Pile Data Tanah CPT
15
16
Lampiran 2. Berat Sendiri Bahan Bangunan dan Konstruksi
17
18
Lampiran 3. Muatan Hidup Lantai Bangunan
19
Lampiran 4. Faktor Aman yang disarankan (Reese & O’neill, 1989)
20
Lampiran 5. Menentukan Angka Kohesi C
21
Lampiran 6. Grafik Hubungan Vb’ dan
22
Lampiran 7. Grafik Variation of with Undrained Cohesion of Clay
23
Lampiran 8. Faktor – Faktor Daya Dukung (Vesic, 1973)
24
Lampiran 9. Data Sondir CPT S2 Masjid SMA Sholahudin Malang
25