DAFTAR UPAH KERJA HARIAN

KABUPATEN MALANG
2016

HARGA RATA-RATA
NO TENAGA KERJA (HARI) SATUAN
(Rp.)
1 2 3 5

1 Mandor orang/Hari 100,000.00


2 Kepala Tukang Gali Tanah orang/Hari 85,000.00
3 Kepala Tukang Batu orang/Hari 85,000.00
4 Kepala Tukang Kayu orang/Hari 85,000.00
5 Kepala Tukang Besi orang/Hari 85,000.00
6 Kepala Tukang Cat orang/Hari 85,000.00
7 Kepala Tukang Listrik orang/Hari 85,000.00
8 Kepala Tukang Pipa orang/Hari 85,000.00
9 Tukang Gali Tanah orang/Hari 82,500.00
10 Tukang Batu orang/Hari 82,500.00
11 Tukang Kayu orang/Hari 82,500.00
12 Tukang Besi orang/Hari 82,500.00
13 Tukang Cat orang/Hari 82,500.00
14 Tukang Aspal orang/Hari 82,500.00
15 Tukang Plitur orang/Hari 82,500.00
16 Tukang Pipa orang/Hari 82,500.00
17 Tukang Listrik orang/Hari 82,500.00
18 Pembantu Tukang Batu orang/Hari 65,000.00
19 Pembantu Tukang Kayu orang/Hari 65,000.00
20 Pembantu Tukang Besi orang/Hari 65,000.00
21 Pembantu Tukang Cat orang/Hari 65,000.00
22 Pembantu Tukang Listrik orang/Hari 65,000.00
23 Pembantu Tukang Pipa orang/Hari 65,000.00
24 Pekerja orang/Hari 60,000.00
25 Pekerja Semi Terampil orang/Hari 55,000.00
26 Pekerja Terampil orang/Hari 65,000.00
27 Juru Ukur orang/Hari 82,500.00
28 Pembantu Juru ukur orang/Hari 65,000.00
29 Operator orang/Hari 82,000.00
30 Operator Terampil orang/Hari 82,000.00
31 Operator Semi Terampil orang/Hari 65,000.00
32 Pembantu Operator orang/Hari 65,195.00
33 Mekanik orang/Hari 95,000.00
36 Pembantu Mekanik orang/Hari 85,000.00
37 Sopir orang/Hari 75,000.00
38 Pembantu Sopir orang/Hari 62,400.00
39 Penjaga Malam orang/Hari 65,000.00
STANDART SATUAN HARGA BAHAN
KABUPATEN MALANG
2016

HARGA
NO JENIS BAHAN SATUAN (Rp.)

1 2 3 4

Jenis Bahan Bangunan Penutup Atap dan Plafond


1 Asbes datar tebal. 4 mm ( 100 X 100 ) Lbr 64,500.00
2 Asbes datar tebal. 4 mm ( 120 X 240 ) Lbr 74,500.00
3 Asbes datar tebal. 5 mm ( 60 X 180 ) Lbr 60,800.00
4 Asbes datar tebal. 6 mm ( 40 X 80 ) Lbr 56,600.00
5 Asbes gelombang besar tebal. 5 mm (1.50 X 1.05) Lbr 110,700.00
6 Asbes gelombang besar tebal. 5 mm (1.80 X 1.05) Lbr 112,100.00
7 Asbes gelombang kecil tebal. 5 mm (2.10 X 1.05) Lbr 88,500.00
8 Asbes gelombang kecil tebal. 5 mm (2.40 X 1.05) Lbr 98,700.00
9 Asbes gelombang kecil tebal. 5 mm (3.00 X 1.05) Lbr 142,800.00
10 Asbes gelombang besar tebal. 4 mm (1.50 X 0.92) Lbr 97,200.00
11 Asbes gelombang besar tebal. 4 mm (1.80 X 0.92) Lbr 90,700.00
12 Asbes gelombang besar tebal. 4 mm (2.10 X 0.92) Lbr 99,800.00
13 Asbes gelombang besar tb. 5 mm (3. 05 X 1.05) Lbr 131,300.00
14 Asbes gelombang kecil tebal. 4 mm (2.40 X 0.92) Lbr 95,600.00
15 Asbes gelombang kecil tebal. 4 mm (3.00 X 0.92) Lbr 102,100.00
16 Asbes gelombang kecil tb. 4 mm (3.05 X 1.05) Lbr 103,100.00
17 Asbes wuwung gelombang besar tebal. 5 mm Lbr 69,100.00
18 Asbes wuwung gelombang kecil tebal. 4 mm Lbr 50,200.00
19 Atap aluminium Gelombang tebal 0,40 M2 70,400.00
20 Asbes Eternit 1 x 1 m Lbr 15,000.00
21 Gyfsum tebal 9 mm M2 84,000.00
22 Gyfsum tebal 12 mm M2 99,800.00
23 Fiber glass lebar (180X230) cm M2 78,700.00
24 Roolflight Twinlight M2 157,500.00
25 Atap Polli Carbonat + Rangka M2 680,000.00
26 Sisalation/Alumunium Foil M2 39,800.00
27 Genteng flam pres jawa / lokal BH 750.00
28 Genteng galvanum BH 59,000.00
29 Harplek Lbr 73,500.00
30 Genteng kaca BH 30,200.00
31 Genteng Glazur BH 10,700.00
32 Bubungan Genteng Glazur BH 28,900.00
33 Genteng wuwung galvalum BH 42,000.00
34 Genteng model Karang pilang Ex.Lokal BH 3,000.00
35 Genteng wuwung karang pilang Ex.Lokal BH 9,400.00
36 Genteng Kodok Ex. Bambe BH 7,500.00
37 Genteng Kodok Ex. Wisma BH 7,500.00
38 Genteng Palentong BH 4,900.00
39 Genteng Palentong Super BH 10,700.00
40 Genteng Nok Palentong BH 9,400.00
41 Genteng Bubung Kodok BH 6,200.00
42 Genteng Nok Kodok Glazzur BH 12,400.00
43 Genteng Beton BH 6,700.00
44 Genteng Sirap M2 162,600.00
45 Nok Genteng Pinggir BH 47,800.00
46 Nok Stel Gelombang Lbr 48,400.00
47 Seng gelombang BJLS 30 ukuran 1,8 x 0,9 Lbr 148,900.00
48 Seng gelombang BJLS 40 PJG 2,00 mtr Lbr 81,400.00
49 Seng Gelombang BJLS 30 (0,8x3,00) Lbr 161,400.00
50 Seng Gelombang BJLS 30 (0,8x1,50) Lbr 123,400.00
51 Seng Plat Dasar BJLS 30 (0,45x1,00) Lbr 30,200.00
52 Seng Plat Dasar BJLS 30 (0,60x1,00) Lbr 39,400.00
53 Seng Plat Dasar BJLS 30 (0,90x1,00) Lbr 59,400.00
54 Teakwood 122x244x4mm Lbr 144,900.00
55 Teakwood 110x210x4mm Lbr 100,800.00
56 Soft Board 4 x 8 x 4 mm Lbr 86,400.00
57 Gypsum Board 122 x 244 x 9 mm Lbr 100,000.00
58 Kalsi Board 120 x 240 x 4 mm Lbr 78,700.00
59 Triplek 122x244x4 mm Lbr 120,700.00
60 Triplek 122x244x6 mm Lbr 189,100.00
61 Triplek 122x244x9 mm Lbr 152,300.00
62 Triplek 120x244x12 mm Lbr 188,000.00
63 Sirap asbes 4 mm M2 74,500.00
64 Sirap asbes 5 mm M2 89,600.00
65 List Gypsum m' 22,800.00

Jenis Bahan Bangunan Menggunakan Kayu


1 Kayu gelam diameter 10 - 12 cm Bt 50,600.00
2 Kayu jati balok 8/12, 6/12 M 35,000,000.00
3 Kayu jati usuk 5/7, 4/6, 3/5 M 35,000,000.00
4 Kayu jati papan 2/20 x 2 m M 39,500,000.00
5 Kayu jati reng 2/3, 3/5 M 35,459,900.00
6 Kayu kamper (balok) M 14,059,500.00
7 Kayu kamper (papan) M 15,775,500.00
8 Kayu kamper (usuk) M 12,402,000.00
9 Kayu kamper (reng) M 12,402,000.00
10 Kayu meranti (balok) M 6,795,700.00
11 Kayu meranti (papan) M 7,151,600.00
12 Kayu meranti (usuk) M 6,747,000.00
13 Kayu meranti (begesting) M 4,200,000.00
14 Kayu bengkirai balok M 11,659,000.00
15 Kayu bengkirai papan M 12,831,000.00
16 Kayu bengkirai usuk M 11,659,000.00
17 Dolken ayu O 8-10 cm/400 cm Bt 82,600.00
18 Kayu Kruing (Balok) M 8,268,000.00
19 Kayu Kruing (Papan) M 8,672,600.00
20 Kayu Kruing (Usuk) M 8,268,000.00
21 List Kayu 2/4 Kamper Ljr 8,800.00
22 List Kayu Propil M' 37,000.00
23 Perancah Kayu M 4,368,000.00
24 Bambu bongkotan 10 - 12 cm pj. 3.00 mt Bt 3,753,000.00
25 Bambu ori 10 - 12 cm pj. 3.00 mt Bt 315,100.00
26 Bambu O 6 - 10/600 cm Bt 41,500.00
27 Bambu Wulung Bt 28,300.00
28 Bambu Petung Bt 44,000.00
29 Bambu Tali/apus Bt 25,200.00
30 Gedek guling Bt 47,000.00
31 Bilik Bambu Bt 157,500.00
32 Multipltks 0,9 mm 1.22 x 2.44 Lbr 185,900.00
33 HVL Lbr 908,200.00
34 Kayu Terentang m3 4,286,700.00
35 Kayu Balau m3 6,303,900.00
36 Gebalan Rumput m2 18,900.00
37 Karung Plastik Bh 4,300.00
38 Tusuk Bambu Bh 24,600.00
39 Ijuk Kg 214,500.00
40 Kayu acuan m3 3,412,500.00

Bahan Menggunakan Batu/Pasir & Semen


1 Bataco tebal 10 Cm Bh 6,200.00
2 Batu bata merah kelas I Bh 800.00
3 Batu bata merah kelas 2 Bh 700.00
4 Batu kali pecah (Pecah Mesin)15/20 M 235,000.00
5 Batu kali pecah (Pecah Mesin) 5/7 M 260,000.00
6 Batu kali pecah (Pecah Mesin)3/5 M 300,000.00
7 Batu gunung pecah 15/20 M 165,000.00
8 Batu pecah 5/7 M3 289,000.00
9 Batu Ppecah 2/3 M3 235,000.00
10 Batu pecah 1/2 M3 320,000.00
11 Batu ampyang Kg 35,000.00
12 Batu belah 15/20 cm Gunung M 260,000.00
13 Batu bobos uk. 10 x 20 x 1.5 cm Bh 11,200.00
14 Batu gilang (kasar acak) M2 69,400.00
15 Batu gilang (kasar bermodul) M2 145,600.00
16 Batu gilang jember (halus) M2 139,800.00
17 Batu kambang Kg 13,100.00
18 Batu / cor koral pecah (Pecah Mesin) 2/3 M 310,000.00
19 Batu / cor koral pecah (Pecah Mesin) 1/1 M 320,000.00
20 Batu / cor koral pecah (Pecah Mesin) 1/2 M 320,000.00
21 Batu / cor koral pecah (Pecah Mesin) 5/7 M 315,000.00
22 Batu / cor koral pecah (Pecah Mesin) 0,5/1 M 320,000.00
23 Batu / cor koral pecah (Pecah Mesin) 3/5-4/6 M 315,000.00
24 Batu krikil beton pecah mesin (jagungan) M 192,500.00
25 Batu belah/Kerakal M 210,100.00
26 Batu Tempel Hitam M2 86,700.00
27 Batu Apung Kg 12,500.00
28 Pasir cor/beton M 247,500.00
29 Pasir Halus m3 215,000.00
30 Pasir pasang M 215,000.00
31 Pasir urug M 195,000.00
32 Klingker Bh 66,000.00
33 Glass bead Bh 92,000.00
34 Glass block Bh 33,900.00
35 Semen berwarna yiyitan Kg 40,300.00
36 Semen merah M3 117,600.00
37 Semen PC (Portland Cemen)/semen gresik ( 40 kg ) Kg 1,800.00
38 Semen tiga roda (40 Kg) Kg 1,750.00
39 Semen putih Kg 3,600.00
40 Semen Nat Kg 17,400.00
41 Kapur pasang (10 Kg) Kg 30,300.00
42 Kapur gamping Ton 1,170,000.00
43 Kapur Padam Kg 8,000.00
44 Tanah uruk M3 183,800.00
45 Tanah katel M3 188,200.00
46 Tanah Sirtu M3 206,200.00
47 Tanah Liat M3 183,800.00
48 Ijuk Kg 34,100.00
49 Tali Ijuk Kg 52,300.00
50 Batacote Kg 6,000.00
51 Bahan Tanah Timbunan M3 17,100.00
52 Batu Kali M3 303,000.00

Bahan Menggunakan Besi / Logam


1 Besi begel / baut Kg 35,000.00
2 Besi beton polos Kg 15,000.00
3 Besi beton ulir Kg 15,000.00
4 Besi beton diameter 16 mm, 11- 12 m Lonjor 306,200.00
5 Besi beton diameter 12 mm, 11 - 12 m Lonjor 155,700.00
6 Besi beton diameter 10 mm, 11-12 m Lonjor 102,000.00
7 Besi beton diameter 8 mm, 11 - 12 m Lonjor 75,300.00
8 Besi beton diameter 6 mm, 11 - 12 m Lonjor 47,200.00
9 Besi beton diameter 4 mm, 11 - 12 m Lonjor 18,300.00
10 Besi beton diameter 14 mm, 11 - 12 m Lonjor 189,000.00
11 Besi pipa Lonjor 154,500.00
12 Buah 9,400.00
13 Besi pipa galvanish medium 1 1/2, 6m Lonjor 402,400.00
14 Besi pipa galvanish medium 1 1/4, 6m Lonjor 495,300.00
15 Besi pipa galvanish medium 1, 6m Lonjor 235,800.00
16 Besi pipa galvanish medium 1/2, 6m Lonjor 282,200.00
17 Besi pipa galvanish medium 3/4, 6m Lonjor 420,900.00
18 Besi pipa galvanish medium 2 1/2, 6m Lonjor 827,700.00
19 Besi pipa galvanish medium 2, 6m Lonjor 781,900.00
20 Besi pipa galvanish medium 3, 6m Lonjor 1,331,800.00
21 Besi pipa galvanish medium 4, 6m Lonjor 1,783,200.00
22 Besi pipa galvanish medium 5, 6m Lonjor 3,065,900.00
23 Besi pipa galvanish medium 6, 6m Lonjor 2,669,800.00
24 Besi pipa galvanish medium 3/4, 6m Lonjor 252,000.00
25 Besi angkur Kg 32,100.00
26 Besi trestang 10 mm Lonjor 122,800.00
27 Besi plat 4 x 8 tebal 2 mm Lbr 1,583,400.00
28 Besi plat alumunium tb. 2 mm M2 78,100.00
29 Besi plat bordes 4" x 8" tb. 3 mm Lbr 21,900.00
30 Besi plat strip 2.5" pj.8mm Lonjor 158,300.00
31 Besi profil WF <= 200 mm(256Kg/ljr) Kg 16,000.00
32 Besi profil WF >= 200 mm s/d 400 mm Kg 16,000.00
33 Besi profil WF >= 200 mm s/d 500 mm Kg 16,000.00
34 Besi siku L. 70 . 70 . 7 Kg 17,500.00
35 Besi siku L. 40 . 40 .4 Kg 17,500.00
36 Besi steinliss steel Kg 26,200.00
37 Besi Strip Kg 26,200.00
38 Canal C. Kg 17,500.00
39 Kawat baja hitam 10 mm Kg 38,100.00
40 Kawat harmonika M2 62,200.00
41 Kawat ikat beton Kg 25,300.00
42 Kawat nyamuk kasa alumunium M2 40,700.00
43 Kawat duri pagar Kg 33,600.00
44 Kawat nyamuk kasa plastik M2 23,500.00
45 Elektroda stainless Kg 370,800.00
46 Elektrode baja Kg 48,000.00
47 Tiang pagar BRC/PMG 2" tinggi 1.50 mt Bt 212,600.00
48 Pintu dorong BRC/PMG uk. 1.2 x 3. 00 m2 Unit 2,538,300.00
49 Pintu swing ganda BRC/PMG uk. 1.2 x 3. 00 m2 Unit 2,197,000.00
50 Pagar BRC/PMG A (uk. 1.2 x 2.4 mt) Unit 635,000.00
51 Pipa baja (SCH) 1" medium Lonjor 320,400.00
52 Pipa baja (SCH) 2" medium Lonjor 698,600.00
53 Pipa baja (SCH) 3" medium Lonjor 1,444,600.00
54 Pipa baja (SCH) 4" medium Lonjor 2,458,500.00
55 Pipa baja (SCH) 5" medium Lonjor 4,746,600.00
56 Pipa baja (SCH) 6" medium Lonjor 6,205,800.00
57 Pipa besi putih 1,2" medium Lonjor 148,700.00
58 Sunscreen Alumunium M2 234,400.00
59 Pipa Stanlisteel 1" Ljr 707,300.00
60 Pipa besi hollo2.5 m Ljr 351,600.00
61 Besi Galvalum M2 350,100.00
62 Kawat Seng Polos Kg 31,900.00
63 Kawat Loket M2 32,900.00
64 Kawat Burung M2 41,000.00
65 Pagar besi komplit dengan mainan M2 1,368,300.00
66 Pintu pagar besi komplit dengan mainan M2 1,476,800.00
67 Pintu rolling door (dan rangka kusen) M2 677,600.00
68 Pintu harmonika M2 1,413,700.00
69 Jendela Nako Bh 248,700.00
70 Kusen aluminium Coklat M' 148,800.00
71 Kusen aluminium Coklat M' 125,000.00
72 Pintu + Kusen PVC Unit 498,800.00
73 Jarum keras 8 mm Bh 59,800.00
74 Daun jendela Casmen non kaca M2 1,341,600.00
75 Hollow 10/10 M' 30,400.00
76 Kusen Aluminium Warna Silver 4/10 M' 94,500.00
77 Kusen Aluminium Warna Coklat 4/10 M' 99,800.00
78 Profil List Kaca bh 26,200.00
79 Tube Sealant tube 38,800.00
80 Besi Balok Kg 31,600.00
81 Besi bulat 42 Kg 14,100.00
82 Besi Bulat 60 Kg 14,100.00
83 Besi Siku Kg 1,104,600.00
84 Bronjong kawat pabrikasi diameter 2,7 mm Bh 292,500.00
85 Bronze Kg 78,000.00
86 Besi cor Kg 18,300.00
87 Baja cor Kg 24,300.00
88 Besi INP Kg 36,500.00
89 Drucklager besar Bh 312,000.00
90 Drucklager kecil Bh 238,800.00
91 Gembok Besar Bh 103,700.00
92 kawat bronjong M1 36,300.00
93 Kawat biasa galvanis Kg 92,400.00
94 Mur baut 1/2", 5/8", 7/8" Kg 35,800.00
95 Nipple Bh 15,700.00
96 Splite pen Bh 46,300.00
97 Rantai Kg 36,700.00
98 Seal Bh 43,000.00
99 Naf + ring besar Bh 536,200.00
100 Naf + ring kecil Bh 438,700.00
101 Baja Tulangan (polos) U24 Kg 13,300.00
102 Baja Tulangan (ulir) D32 Kg 14,900.00
103 Baja Bergelombang Kg 16,200.00
104 Baja Struktur Kg 16,000.00
105 Pipa Baja Kg 17,500.00
106 Baja Prategang Kg 12,700.00
107 Baja Tulangan (polos) U32 Kg 14,100.00
108 Baja Tulangan (ulir) D39 Kg 15,600.00
109 Baja Tulangan (ulir) D48 Kg 16,100.00
110 Rel Pengaman M1 493,300.00
111 Pelat Rambu (Eng. Grade) Bh 209,100.00
112 Pelat Rambu (High I. Grade) Bh 257,400.00
113 Kawat Beton Kg 25,300.00
114 Kawat Las Dos 40,300.00
115 Spie 17,000.00
116 Seal Karet 171,600.00
117 Galvalum 0.75 Ljr 86,400.00
118 Galvalum 0.45 Ljr 37,200.00
119 Besi hollow 4x4x1.2 m' 16,250.00
120 Besi hollow 2x4x1.2 m' 14,083.33

Bahan untuk lantai


1 Paving stone persegi abu-2 tb. 6 cm halus Bh 1,700.00
2 Paving stone persegi abu-2 tb. 6 cm kasar Bh 2,000.00
3 Paving stone 3 berlian abu-2 tb. 6 cm Bh 2,100.00
4 Paving stone segi 6 abu-2 tb. 6 cm Bh 2,100.00
5 Paving stone persegi merah abu-2 tb. 6 cm Bh 2,400.00
6 Paving stone 3 berlian merah abu-2 tb. 6 cm Bh 2,000.00
7 Paving stone segi 6 merah abu-2 tb. 6 cm Bh 2,100.00
8 Paving stone persegi abu-2 tb. 8 cm halus Bh 1,900.00
9 Paving stone persegi abu-2 tb. 8 cm kasar K300 Bh 1,800.00
10 Paving stone 3 berlian abu-2 tb. 8 cm Bh 2,100.00
11 Paving stone segi 6 merah tb. 8 cm Bh 2,300.00
12 Paving stone persegi merah tb. 8 cm Bh 2,400.00
13 Paving stone (BLOK) USKUP m' Rp 9,200.00
14 Paving stone 3 berlian merah tb. 8 cm Bh 2,100.00
15 Paving stone segi 6 merah tb. 8 cm Bh 2,100.00
16 Paving stone persegi abu-2 tb. 10 cm halus Bh 2,400.00
17 Paving stone persegi abu-2 tb. 10 cm kasar Bh 2,200.00
18 Paving stone 3 berlian abu-2 tb. 10 cm Bh 1,900.00
19 Tegel PC abu-abu 20 x 20 cm Bh 1,500.00
20 Tegel PC abu-abu 20 x 30 cm Bh 4,500.00
21 Tegel PC abu-abu 30 x 30 cm Bh 4,500.00
22 Tegel PC abu-abu 40 x 40 cm Bh 4,600.00
23 Kanstin 14 x 25 x 40 cm Bh 20,100.00
24 Ubin Warna 20x20 cm Bh 4,600.00
25 Ubin Warna 30x30 cm Bh 6,000.00
26 Ubin Warna 40x40 cm Bh 12,400.00
27 TOK 10 X 20 Bh 1,000.00
28 Tegel keramik 10 x20 Bh 6,100.00
29 Tegel keramik 15 x 15 Bh 2,200.00
30 Tegel keramik 15 x 20 Bh 2,600.00
31 Tegel keramik 20 x 20 Bh 3,500.00
32 Tegel keramik 25 x 25 Bh 4,000.00
33 Tegel keramik 30 x 30 motif Bh 6,500.00
34 Tegel putih polos ex mulia 30 x 30 Bh 6,000.00
35 Tegel trotoar Bh 4,100.00
36 Tegel keramik 40 x 40 (motif / warna) Bh 17,000.00
37 Tegel keramik 20 x 40 Bh 7,800.00
38 Tegel keramik 25 x 40 Bh 7,900.00
39 Tegel Keramik 50 x 50 Bh 22,300.00
40 Tegel list dinding Bh 32,200.00
41 Tegel keramik 20 x 25 (dinding) Bh 5,300.00
42 Tegel wafel 20 x 20 Bh 2,600.00
43 Plint Ubin PC Warna 10x20 cm Bh 2,700.00
44 Plint Ubin PC Warna 10x30 cm Bh 2,800.00
45 Plint Ubin PC Warna 10x40 cm Bh 3,300.00
46 Bahan Teraso Cor Bh 55,900.00
47 Marmer M2 463,100.00
48 Batu lempeng jember acak M2 73,700.00
49 Batu palimanan tebal 2 cm M2 157,500.00
50 Batu sisir M2 301,700.00
51 Batu ampyang M2 66,900.00
52 Nero Granito 60/60 cm (Setara) bh 176,100.00
53 Granit M2 1,263,600.00
54 Roster 20 x 40 M2 12,900.00
55 Batu Alur Cetak M2 63,000.00
56 List Keramik Dinding 5 / 25 bh 1,300.00
57 Kolplint Lantai 8 / 40 bh 5,200.00

Bahan untuk pengecatan


1 Cat besi emco Kg 80,000.00
2 Cat kayu emco Kg 80,000.00
3 Cat meni (besi/kayu) cap pedang Kg 40,300.00
4 Meni A Kg 43,000.00
5 Meni B Kg 26,800.00
6 Cat tembok (Catilax) Kg 45,000.00
7 Cat tembok (mowilex) Kg 92,000.00
8 Cerelak Kg 485,700.00
9 Politur Liter 90,700.00
10 Vernis Utk Kayu Liter 80,600.00
11 Dempul Kg 47,000.00
12 Minyak Cat/Afduner Liter 63,000.00
13 Teer Kg 30,200.00
14 Kolteer Kg 18,900.00
15 Kertas gosok Lbr 5,300.00
16 Plamur tembok Galon 105,000.00
17 Plamur kayu Kg 35,100.00
18 Plamur Besi Kg 47,000.00
19 Thermoplastic Kg 14,200.00
20 Spiritus Ltr 20,500.00
21 Lem Kg 16,500.00
22 Thinner B / minyak cat Ltr 27,000.00
23 Soda Api Kg 53,700.00
24 Sabun Kg 36,800.00
25 Teak Oil Ltr 29,400.00
26 Residu Ltr 21,200.00
27 Kuas Bh 47,000.00
28 Waterstop lb. 150 mm Lbr 1,700.00
29 Waterstop lb. 200 mm Lbr 2,400.00
30 Waterstop lb. 230 mm Lbr 3,000.00
31 Waterstop lb. 250 mm Lbr 3,100.00
32 Waterstop lb. 300 mm Lbr 4,700.00
33 Waterstop lb. 320 mm Lbr 5,500.00

Bahan Penggantung Dan Pengunci


1 Engsel H Stl 28,600.00
2 Engsel kuningan ARCH asli Stl 95,550.00
3 Engsel Jendela Stl 27,100.00
4 Hak Angin Stl 34,500.00
5 Engsel Pintu Stl 45,800.00
6 Grendel Bh 18,000.00
7 Grendel biasa (besar) Bh 27,500.00
8 Grendel biasa (kecil) Bh 13,700.00
9 Grendel kuningan / cromm (kecil) Bh 20,500.00
10 Grendel tanam Bh 113,000.00
11 Kunci gembok besar Bh 68,900.00
12 Kunci gembok sedang Bh 48,000.00
13 Kunci tanam -808 Bh 140,000.00
14 Kunci tanam besar kupu tarung Bh 161,500.00
15 Kunci tanam antik Bh 377,000.00
16 Kunci tanam kamar mandi Bh 83,500.00
17 Kunci silinder Bh 161,000.00
18 Kunci selot (Cap Kuda terbang 2 x putaran) Bh 194,000.00
19 Kunci lemari Bh 33,700.00
20 Hak angin Bj 33,000.00
21 Hak angin 4 mm (lurus) Bj 6,300.00
22 Hak angin (sikutan) Stl 23,000.00
23 Hak angin lurus (bisa disetel maju/mundur) Stl 99,000.00
24 Kait angin Bh 32,000.00
25 Dor closer Bh 424,400.00
26 Dor stop Bh 45,800.00
27 Rel pintu dorong Bh 481,600.00
28 pintu kaca tempert + acessories unit 51,725,000.00

Bahan untuk KM / WC / Urinoir


1 Pipa / slang spiral saluran kran Set 116,000.00
2 Closet duduk putih porselin komplit Bh 1,945,000.00
3 Closet jongkok porselin warna putih Bh 193,000.00
4 Closet jongkok teraso Bh 195,000.00
5 Closet jongkok INA Bh 239,000.00
6 Kran air Bh 132,100.00
7 Watermur Bh 61,400.00
8 Westafel besar warna Bh 619,000.00
9 Rol TBA Rol 10,300.00
10 Sifon wasser Set 178,400.00
11 Water drain + Assesoris Set 177,000.00
12 Bak fiberglass Bh 980,600.00
13 Bak cuci stainless steel Bh 986,200.00
14 Urinoir Bh 2,694,800.00
15 Floor drain Bh 36,500.00
16 Avour Stenlless Bh 46,300.00

Bahan Jenis Kaca


1 Kaca polos tb. 3 mm M2 139,400.00
2 Kaca polos tb. 5 mm M2 206,000.00
3 Kaca polos tb. 8 mm M2 241,000.00
4 Kaca rayband tb. 5 mm M2 255,000.00
5 Krepyak kaca nako + kerangka Lbr 215,400.00
6 Kaca cermin tebal 5 mm M2 413,700.00
7 Kaca cermin tebal 10 mm M2 369,800.00

Bahan Beton Cetakan


1 Bahan roster klingker warna merah Bh 9,500.00
2 Buis beton diameter 15 cm Bh 36,700.00
3 Buis beton diameter 20 cm Bh 40,300.00
4 Buis beton diameter 30 cm Bh 57,700.00
5 Buis beton diameter 40 cm Bh 73,900.00
6 Buis beton diameter 50 cm Bh 100,800.00
7 Buis beton diameter 60 cm Bh 100,500.00
8 Buis beton diameter 80 cm Bh 154,600.00
9 Buis Beton U 20 cm Bh 38,700.00
10 Buis Beton U 30 cm Bh 47,100.00
11 Buis Beton U 40 cm Bh 63,300.00
12 Tandon air feber Glas kapasitas 250 L Bh 736,500.00
13 Tandon air feber Glas kapasitas 300 L Bh 959,300.00
14 Tandon air feber Glas kapasitas 500 L Bh 1,013,800.00
15 Tandon air feber Glas kapasitas 700 L Bh 1,155,700.00
16 Tandon air feber Glas kapasitas 1000 L Bh 1,575,900.00
17 Roster/Krawang 12 x 11 x 24 cm Bh 7,300.00
18 Beton K-125 m3 945,300.00
19 Beton K-250 m3 1,350,300.00
20 Beton K-300 m3 1,343,400.00
21 Beton K-350 m3 1,359,900.00
22 Beton K-400 m3 1,379,000.00
23 Beton K-500 m3 1,527,800.00
24 Gorong-gorong Beton (K-500) diameter=0.80 m, tebal =10 cm m' 36,700.00
25 Tiang Pancang Beton Pratekan m3 598,200.00
26 Tiang Pancang Baja M1 682,900.00

Bahan plastik Pipa PVC


1 Keni PVC 2" Bh 15,800.00
2 Klem PVC Bh 9,400.00
3 Pipa paralon 5/8" Ljr 16,100.00
4 Pipa PVC 1/2" panjang 4.00 mt (maspion) M1 33,600.00
5 Pipa PVC 2" panjang 4.00 mt (maspion) M1 118,600.00
6 Pipa PVC 3" panjang 4.00 mt (maspion) M1 165,100.00
7 Pipa PVC 3/4" panjang 4.00 mt (maspion) M1 64,800.00
8 Pipa PVC 4" panjang 4.00 mt (maspion) M1 323,500.00
9 Pipa PVC 5" panjang 4.00 mt (maspion) M1 495,500.00
10 Pipa PVC 3" type D pj. 6.00 mt M1 325,400.00
11 Pipa PVC 4" type D pj. 6.00 mt M1 520,500.00
12 Pipa PVC 5" type D pj. 6.00 mt M1 619,500.00
13 Pipa SCH 40 JIS 4 "" M1 474,200.00
14 Pipa Galvanis Dia. 1.6" Btg 461,700.00
15 Pipa porus M1 414,300.00
16 Pipa HDPE 200 mm Ljr 395,000.00

Bahan Jenis Paku


1 Paku asbes Kg 28,600.00
2 Paku Segala Ukuran Kg 19,400.00
3 Paku seng payung Kg 33,600.00
4 Paku skrup 2'' Dos 50,400.00
5 Paku sumbat Bh 1,000.00
6 Paku triplek Kg 30,700.00
7 Paku usuk Kg 29,400.00
8 Sekerup Bh 600.00
9 Paku Pancing Bh 3,200.00
10 Paku Baja Dos 62,400.00
11 Paku Reng Kg 29,400.00
12 Paku Sekrup 3.5'' Dos 100,800.00
13 Paku Keling 3/4''.5/8''.7/8'' Kg 29,400.00

Bahan-Bahan Peralatan Listrik


1 Capasito Sx 135 W 20 MF/250 V Bh 160,200.00
2 Capasito Sx 90 W 10 MF/250 V Bh 75,400.00
3 Faiting Flapon Bh 29,600.00
4 T Doos PVC Bh 6,200.00
5 Isolator Bh 1,700.00
6 Stop Kontak (Broco) Bh 43,800.00
7 Skakelar tunggal (broco) Bh 52,900.00
8 Skakelar ganda (broco) Bh 53,600.00
9 Skakelar / Handel Bh 47,000.00
10 sekering Lengkap Bh 128,700.00
11 Sekering SPA 60 Amp Bh 187,600.00
12 Las Doof Bh 700.00
13 Panel Box Bh 413,000.00
14 Main Swith Bh 326,200.00
15 Sekering MCB thermix 10-16 Amp Bh 33,700.00
16 Sekering MCB thermix 10 Amp Bh 33,700.00
17 Stater lampu TL Bh 7,800.00
18 Lampu Pijar 25,10,75/220 V Bh 73,500.00
19 Lampu TL 20 W/220V Komplet balas Kaca (Philip) Bh 87,700.00
20 Lampu TL 40 W/220V Komplet balas Kaca (Philip) Bh 105,600.00
21 Down Light 11 Watt + armateur Bh 94,525.00
22 Lampu Mercury 1 x 250 watt Bh 643,500.00
23 1 unit Memasang Lampu Sorot 50 watt Bh 215,625.00
24 Kabel NYA 500 V 1x2,5 mm2 M' 21,000.00
25 Kabel NYA 1000 V 1x1,5 mm2 M' 18,900.00
26 Kabel NYA 1000 V 1x2,5 mm2 M' 21,000.00
27 Kabel NYA 1000 V 1x2 mm2 M' 21,000.00
28 Kabel NYFGBY 4 x 25 mm M' 309,800.00
29 Kabel NYFGBY 4 x 35 mm M' 391,100.00
30 Kabel NYFGBY 4 x 50 mm M' 491,800.00
31 Kabel NYFGBY 4 x 70 mm M' 639,700.00
32 Kabel NYM 500 V 2x1,5 mm M' 24,700.00
33 Kabel NYM 500 V 2x2,5 mm M' 26,100.00
34 Kabel NYM 500 V 2x4 mm M' 31,100.00
35 Kabel NYY 2x2,5 mm M' 42,400.00
36 Kabel NYY 3x2,5 mm M' 46,800.00
37 Kabel NYY 4x10 mm M' 103,400.00
38 Kabel NYY 4x16 mm M' 227,600.00
39 Kabel NYY 4x4 mm M2 65,900.00

BAHAN FURNISHING INTERIOR DECORATION


1 Karpet merk accord M2 228,100.00
2 Karpet merk setara M2 195,000.00
3 Karpet merk aloha M2 404,600.00
4 Karpet merk cellini M2 464,400.00
5 Fitrase erk corals & aquirlda M 2
341,200.00
6 Foom lapisan karpet M 2
365,600.00
7 Vertical blind merk shin ichi M 2
289,300.00
8 Vertical blind M 2
53,600.00
9 Wall paper merk Contrack paper Roll 243,700.00
10 Wall paper merk kansai M2 204,700.00
11 Wall paper merk neulin M2 100,400.00
12 Karpet merk KARINA M2
13 Feltex karpet Wool P - 21 M2
14 Karpet 80 % Wool 20% Nilon M2
15 Underlier Tebal 6 mm M2
16 Parquet Jati M2
17 Gym Floor BH
18 Vynil Karet 30 X 30 ( Kw 1 ) BH
19 Vynil Karet 30 X 30 ( Kw 2 ) BH
20 Vynil Asbes 30 X 30 cm BH
21 Vynil Motif kembang BH
22 Vynil Wall Covering BH
23 Floor Hardener Ferrovax KG
24 Floor Hardener Mastercron " S " KG
25 Wall Paper M2

KAWAT
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
1 bh 300,000.00
2x1x0,5 ; Mesh 8x10cm; Dia.2,70 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
2 bh 395,000.00
3x1x0,5 ; Mesh 8x10cm; Dia.2,70 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
3 bh 395,000.00
2x1x1 ; Mesh 8x10cm; Dia.2,70 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
4 bh 560,000.00
3x1x1 ; Mesh 8x10cm; Dia. 2,70 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
5 bh 300,000.00
2x1x0,5 ; Mesh 8x10cm; Dia. 3,00 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
6 bh 430,000.00
3x1x0,5 ; Mesh 8x10cm; Dia. 3,00 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
7 bh 430,000.00
2x1x1 ; Mesh 8x10cm; Dia. 3,00 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
8 bh 615,000.00
3x1x1 ; Mesh 8x10 cm; Dia. 3,00 mm
Bronjong kawat pabrikasi lapisan seng tebal ukuran (PxLxT)
9 bh 255,000.00
2x1x0,5 ; Mesh 10x12cm; Dia. 3,00 mm
Bronjong kawat ukuran (PxLxT) 2x1x0,5 ; Mesh 80x100mm;
10 bh 272,500.00
Dia. 2,70 mm
Bronjong kawat ukuran (PxLxT) 3x1x0,5 ; Mesh 80x100mm;
11 bh 384,800.00
Dia. 2,70 mm
Bronjong kawat ukuran (PxLxT) 4x1x0,5 ; Mesh 80x100mm;
12 bh 485,800.00
Dia. 2,70 mm
Bronjong kawat ukuran (PxLxT) 3x1,5x0,5 ; Mesh 80x100mm;
13 bh 511,800.00
Dia. 2,70 mm
Bronjong kawat ukuran (PxLxT) 2x1x1 ; Mesh 80x100mm; Dia.
14 bh 397,800.00
2,70 mm
Bronjong kawat ukuran (PxLxT) 3x1x1 ; Mesh 80x100mm; Dia.
15 bh 533,800.00
2,70 mm
Bronjong kawat ukuran (PxLxT) 4x1x1 ; Mesh 80x100mm; Dia.
16 bh 709,800.00
2,70 mm
Bronjong kawat ukuran (PxLxT) 2x1x0,5 ; Mesh 80x100mm;
17 bh 322,800.00
Dia. 2,70 mm
Bronjong kawat ukuran (PxLxT) 3x1x0,5 ; Mesh 80x100mm;
18 bh 460,800.00
Dia. 3,00 mm
Bronjong kawat ukuran (PxLxT) 4x1x0,5 ; Mesh 80x100mm;
19 bh 582,800.00
Dia. 3,00 mm
Bronjong kawat ukuran (PxLxT) 3x1,5x0,5 ; Mesh 80x100mm;
20 bh 614,500.00
Dia. 3,00 mm
Bronjong kawat ukuran (PxLxT) 2x1x1 ; Mesh 80x100mm; Dia.
21 bh 466,800.00
3,00 mm
Bronjong kawat ukuran (PxLxT) 3x1x1 ; Mesh 80x100mm; Dia.
22 bh 638,800.00
3,00 mm
Bronjong kawat ukuran (PxLxT) 4x1x1 ; Mesh 80x100mm; Dia.
23 bh 849,800.00
3,00 mm

BAHAN UNTUK PERTAMANAN


GRASSING ( RERUMPUTAN )
1 Rumput Gajah Tinggi M2 18,000.00
2 Rumput Gajah Pendek M2 17,500.00
3 Rumput Embun M2 18,500.00
4 Rumput Golf Kwalitas I M2 120,100.00
5 Rumput Golf Kwalitas II M2 87,400.00

GROUND COVER ( PERDU )


1 Arum Sengkelep Pot kecil 5,550.00
2 Blego Bandung Pot kecil 1,700.00
3 Heliconia Pot kecil 4,200.00
4 Kucai Pot kecil 1,100.00
5 Lely Paris Pot kecil 1,700.00
6 Lely Spider Pot kecil 1,700.00
7 Nanas Kodok Pot kecil 1,700.00
8 Pisang Bali Pot kecil 82,000.00
9 Pisang zebra Pot kecil 5,500.00
10 Sansivera Pot kecil 12,600.00
11 Sepatu Phylum Pot kecil 51,000.00
12 Song of India Pot kecil 17,000.00
13 Tricolor t = 1 - 1,5 mtr Pot kecil 109,400.00
14 Tricolor t = 50 cm Pot kecil 29,600.00

POHON PELINDUNG
1 Pakis Galar tg batang = 1 - 2 mtr Phn 206,000.00
2 Palem Phoenix t btg = 40 cm Phn 96,100.00
3 Palem Putri t btg = 1 mtr Phn 350,650.00
4 Palem Sadeng t btg = 2 mtr Phn 816,500.00
5 Pandan Bali t btg = 1 - 1,5 mtr Phn 191,100.00
6 Tabir Buya t btg 2,5 - 3 mtr Phn 482,500.00

PUPUK
1 Pupuk organik ( Kompos ) Zak 23,000.00
2 Pupuk anorganik ( Urea,Za ) Kg 6,700.00

SEWA ALAT - ALAT


1 Pesawat ukur unit/Hr 389,000.00
2 Molen unit/Hr 378,200.00
3 Vibrator unit/Hr 77,000.00
4 Motoran (50) Bh 220,000.00
5 Palu/ bodem Bh 105,700.00
6 Molen unit 378,200.00
7 Gergaji Bh 111,750.00
8 Tampar pemikul kayu Bh 18,975.00
9 Vibrator Roller unit/Hr 686,500.00
10 Dump truck 3.5 ( min. 5 jam ) Jam 373,800.00
11 Motor Grender 125 - 140 Pk ( min. 5 jam ) unit/Hr 271,000.00
12 Phenumatis Tire Roller ( min. 5 jam ) Jam 261,000.00
13 Truck Tangki air ( min. 5 jam ) Jam 31,500.00
14 Vibrator Roller ( min. 5 jam ) Jam 629,500.00
15 Escavator 80-140 HP Unit/hari 720,500.00
16 Concrete Mixer 0.50 M3 ( min. 3 jam ) Jam 269,600.00
17 Kompresor, blangsit pot, selang dan nozzle Bh/Hr 268,900.00
18 Pump Water ( min. 3 jam ) Jam 126,500.00
19 Kompresor Hr 292,400.00
20 Blasting Hr 292,400.00
21 Pot Hr 292,400.00
22 Selang Hr 292,400.00
23 Nozzle Hr 292,400.00
24 Ganco Bh 66,300.00
25 Keranjang Bh 22,500.00
26 Alat pelancip / Pisau Besar Bh 28,900.00
27 Kereta dorong unit 619,300.00
28 Jack hammer Bh/Hr 144,700.00
29 Timbris unit 50,050.00
30 Linggis Bh 82,800.00
31 Ember Bh 17,200.00
32 Cetok Bh 27,500.00
33 Kuas Bh 17,000.00
34 Kasut kayu Bh 74,500.00
35 Kotak adukan Bh 35,600.00
36 Tang pemotong kawat Bh 25,100.00
37 Tripot unit/Hr 495,000.00
38 Gunting pemotong baja Bh 97,100.00
39 Kunci pembengkok tulangan Bh 36,200.00
40 Gerobak Bh 602,800.00
41 Pompa air unit/Hr 830,000.00
42 Excavator 80-140 HP unit/Hr 785,000.00
43 Vibratory roller 6-8T unit/Hr 651,800.00
44 Sabit Bh 27,500.00
45 Sewa walles Jam 104,000.00

BAHAN PENUNJANG LAINNYA


BAHAN BBM
1 Bensin Non Subsidi liter 13,650.00
2 Solar Non Subsidi liter 11,600.00
3 Minyak Tanah liter 15,170.00
4 Aspal AC (AC 60 - 70 ) curah kg 12,976.70
5 Agregat Kasar M3 382,549.00
6 Agregat Halus M3 382,549.00
7 Filler kg 1,500.00
8 Gravel M3 161,641.00
9 Bahan Pilihan M3 37,400.00
10 Aspal AC (AC 60 - 70 ) curah kg 14,332.00
11 Aspal Curah kg 14,332.00
12 Sirtu M3 224,142.00
13 Cat Marka (Non thermoplas) kg 35,000.00
14 Cat Marka (thermoplastic) kg 43,104.00
15 Minyak pelumas/oli Liter 40,949.00
16 Plastik filter M2 22,000.00
17 Bahan Agr. Base kelas A M3 285,949.00
18 Bahan Agr. Base kelas B M3 288,471.00
19 Bahan Agr. Base kelas C M3 243,780.00
20 Bahan Agr. Base kelas C2 M3 193,969.00
21 Geotextile M2 53,880.00
22 Aspal Elmusi kg 17,640.00
23 Thinner Liter 55,163.00
24 Glass Bead Kg 88,950.00
25 Butonic Aspal ton 6,171,223.30
26 Glass Bead kg 39,380.00
27 Pelat Rambu ( Eng. Grade) Buah 235,950.00
28 Pelat Rambu (High I. Grade) Buah 290,400.00
29 Rel Pengaman m' 556,600.00
30 Chipping m3 290,953.00
31 Chipping (kg) Kg 539.00
32 Pemantul Cahaya Bh 26,940.00
33 Pemantul Cahaya (Reflector) Buah 18,150.00
34 Arbocell Kg 46,440.00
35 Minyak fluks Liter 9,483.00
36 Bunker Oil Liter 8,621.00
37 asbuton halus Ton 404,102.00
38 PCI Girder L=17 m Buah 114,180,000.00
39 PCI Girder L=21 m Buah 128,700,000.00
40 PCI Girder L=26 m Buah 164,340,000.00
41 PCI Girder L=32 m Buah 207,900,000.00
42 PCI Girder L=34 m Bh 222,420,000.00
43 PCI Girder L=36 m Buah 203,885,000.00
44 PCI Girder L=41 m Buah 254,100,000.00
45 Cerucuk m' 23,160.00
46 Elastomer Buah 484,922.00
47 Bahan Pengawet : kreosot Liter 7,920.00
48 Mata Kucing Buah 112,920.00
49 Anchorage Buah 871,200.00
50 Anti strpping agent Liter 39,600.00
51 Bahan modifikasi Kg 2,694.00
52 Ducting ( Kabel prestess) m' 224,400.00
53 Ducting (Syrand prestress) m' 79,200.00
54 Multiplek 12 mm Lembar 264,000.00
55 Elastomer jenis 1 Buah 567,600.00
56 Elastomer jenis 2 Buah 957,000.00
57 Elastomer jenis 3 Buah 1,293,125.00
58 Expansion Tipe Joint Asphaltic Plug m' 1,518,000.00
59 Expansion Join Tipe Rubber m' 1,782,000.00
60 Expansion Baja Siku m' 402,600.00
61 Marmer Buah 538,450.00
62 Kerb Type A Buah 66,000.00
63 Mini Timber Pile Buah 39,600.00
64 Expasion Joint Tipe Torma m' 1,749,000.00
65 Strip Bearing Buah 336,600.00
66 Joint Socket Pile 35x35 set 884,400.00
67 Joint Socket Pile 16x16x16 set 99,000.00
68 Mikro Pile 16x16x16 m' 82,280.00
69 matras Concrete Buah 594,000.00
70 Assetilline Botol 343,200.00
71 Oxygen Botol 171,600.00
72 Batu Bara Kg 1,078.00
73 Agregat Pecah Mesin 0-5 mm M3 382,549.00
74 Agregat Pecah Mesin 5-10 & 10-20 mm M3 382,549.00
75 Agregat Pecah Mesin 20-30 mm M3 382,549.00
76 Joint Sealent kg 80,820.00
77 Cat Anti Karet kg 64,656.00
78 Expansion Cap m2 10,776.00
79 Polytene 125 mikro kg 33,000.00
80 Curring Compound liter 59,400.00
81 Additive liter 80,820.00
82 Casing m2 21,552.00
82 Oli Mesin Liter 45,720.00
82 Minyak Rem Liter 71,340.00
82 Mikro Pile 16x16x16 M1 89,760.00
82 Pelat Rambu (Eng. Grade) Bh 257,400.00
82 Pelat Rambu (High I. Grade) Bh 316,800.00
82 Aspal AC ( AC 60 - 70 ) curah Drem 10,257.50
82 Bitumen ( asphalt ) KG 6,219,000.00
82 Bitumen ( asphalt - curah ) KG 4,020.00
82 Bitumen ( asbuton ) Ton 3,742,200.00
82 Kerosine Liter 2,940.00
82 Kayu Bakar M3 166,320.00
82 Alat-alat kerja % 7.70
82 Minyak Bekisting Liter 4,400.00

HARGA ALAT - ALAT


1 Asphalt Mixing Plant Bh 5,280,000,000.00
2 Asphalt Finisher Bh 1,584,000,000.00
3 Asphalt Sprayer Bh 114,840,000.00
4 Buldozer 100-150 Hp Bh 1,364,880,000.00
5 Compressor 4000-6500 L/M Bh 145,200,000.00
6 Concrete Mixer 0,3-0,6 M3 Bh 231,660,000.00
7 Crane 10-15 Ton Bh 1,964,160,000.00
8 Dump Truck 3-4 M3 Bh 158,400,000.00
9 Dump Truck Bh 396,000,000.00
10 Excavator 80-140 Hp Bh 1,516,970,255.00
11 Flat Bed Truck 3-4 M3 Bh 396,000,000.00
12 Generator Set Bh 198,000,000.00
13 Motor Grader > 100 Hp Bh 1,296,240,000.00
14 Track Loader 75-100 Hp Bh 982,000,000.00
15 Wheel Loader 1,0-1,6 M3 Bh 744,480,000.00
16 Thee Wheel Roller 6-8 T Bh 462,000,000.00
17 Tandem Roller 6-8 T Bh 462,000,000.00
18 Tire Roller 5-8 T Bh 947,232,000.00
19 Vibratory Roller 5-8 T Bh 1,212,799,500.00
20 Concrete Vibrator Bh 5,280,000.00
21 Stone Crusher Bh 1,320,000,000.00
22 Water Pump 70-100 mm Bh 6,600,000.00
23 Water Tanker 3000-4500 liter Bh 138,600,000.00
24 Pedestrian Roller Bh 198,000,000.00
25 Tamper Bh 22,440,000.00
26 Jack Hammer Bh 46,200,000.00
27 Fulvi Mixer Bh 1,188,000,000.00
28 Concrete Pump Bh 165,500,000.00
29 Trailer 20 Ton Bh 792,000,000.00
30 Pile Driver + Hammer Bh 1,155,000,000.00
31 Crane On Track 35 Ton Bh 1,122,000,000.00
32 Welding Set Bh 25,100,000.00
33 Bor Pile Machine Bh 2,970,000,000.00
34 Asphalt Liquid Mixer Bh 19,800,000.00
35 Trailer 15 Ton Bh 594,000,000.00
36 Rock Drill Breaker Bh 1,241,157,481.00
37 Cold Milling Bh 4,945,000,000.00
38 Cold Recycler Bh 6,922,080,000.00
39 Hot Recycler Bh 35,610,000,000.00
40 Aggregat (chi[p) Spreader Bh 521,400,000.00
41 Asphalt Distribition Bh 521,400,000.00
42 Split From Paver Bh 1,765,028,572.00
43 Concrete Pan Mixer Bh 1,323,901,313.00
44 Concrete Breaker Bh 1,188,000,000.00
45 Asphalt Tanker Bh 660,000,000.00
46 Cement Tanker Bh 660,000,000.00
47 Concrete Mixer (350) Bh 46,200,000.00
48 Vibrating Rammer Bh 26,400,000.00
49 Truck Mixer Bh 660,000,000.00
50 Bore Pile Machine Diameter 60 Bh 1,544,400,000.00
51 Cane On Track 75 - 100 Ton Bh 1,188,000,000.00
52 Blending Equipment Bh 660,000,000.00
53 Asphalt Liquid Mixer (Kapasitas 20000) Bh 1,080,000,000.00
55 Rubber Track Cat 304 CCR Bh 27,600,000.00
56 Bucket 304 CCR Bh 9,600,000.00
57 Filter Hidrotis 304 CCR Bh 3,000,000.00
58 Huusing Hidrotis 304 CCR Bh 840,000.00
59 Filter Oil Mesin 304 CCR Bh 2,400,000.00
60 Palu / bodem Bh 124,116.00
61 Gergaji Bh 121,500.00
62 Ganco Bh 72,100.00
63 Keranjang Bh 24,200.00
64 Alat Pelancip / pisau besar Bh 30,800.00
65 Linggis Bh 89,100.00
66 Ember Bh 17,900.00
67 Kunci pembengkok tulangan Bh 39,400.00
68 Gerobak Bh 656,600.00
Harga Satuan
KODE URAIAN
(Rp)
A PEKERJAAN PERSIAPAN

1. 1m2 PEMBERSIHAN LOKASI


Upah
0.05 Oh Mandor 100,000.00
0.10 Oh Pekerja 60,000.00
Sub Jumlah

2. 1 m1 PENGUKURAN dan PEMASANGAN BOUWPLANK


Bahan
0.01 m Kayu kasau meranti 6,795,700.00
0.00 m Papan meranti 7,151,600.00
0.02 kg Paku 29,400.00
Upah
0.01 Oh Mandor 100,000.00
0.01 Oh Kepala tukang kayu 85,000.00
0.10 Oh Tukang kayu 82,500.00
0.10 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
B PEKERJAAN TANAH

1. 1m3 GALIAN TANAH BIASA SEDALAM 1 M


Upah
0.04 Oh Mandor 100,000.00
0.40 Oh Pekerja 60,000.00
Sub Jumlah

3. 1m3 URUGAN TANAH KEMBALI


Upah
0.02 Oh Mandor 100,000.00
0.19 Oh Pekerja 60,000.00
Sub Jumlah

4. 1m3 URUGAN TANAH


Bahan
1.20 m Tanah urug 183,800.00
Upah
0.01 Oh Mandor 100,000.00
0.30 Oh Pekerja 60,000.00
Sub Jumlah
5. 1m3 URUGAN PASIR
Bahan
1.20 m Pasir urug 195,000.00
Upah
0.01 Oh Mandor 100,000.00
0.30 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
C PEKERJAAN PONDASI

1. 1m3 PASANGAN BATU KOSONG (ANSTAMPING)


Bahan
1.20 m Batu kali 235,000.00
0.30 m Pasir urug 195,000.00
Upah
0.04 Oh Mandor 100,000.00
0.04 Oh Kepala tukang batu 85,000.00
0.39 Oh Tukang batu 82,500.00
0.78 Oh Pekerja 60,000.00
Sub Jumlah

2. 1m3 PASANGAN BATU KALI 1PC : 5 PS


Bahan
1.10 m Batu kali pecah 15/20 235,000.00
136.00 kg Semen gresik/ PC (kg) 1,800.00
0.54 m Pasir pasang 215,000.00
Upah
0.08 Oh Mandor 100,000.00
0.06 Oh Kepala tukang batu 85,000.00
0.60 Oh Tukang batu 82,500.00
1.50 Oh Pekerja 60,000.00
Sub Jumlah
1m2 PASANGAN PONDASI ROLLAG
Bahan
70.00 bh Batu merah kelas 2 700.00
14.37 kg Semen gresik / PC (kg) 1,800.00
0.04 m Pasir pasang 215,000.00
Upah
0.02 Oh Mandor 100,000.00
0.01 Oh Kepala tukang batu 85,000.00
0.10 Oh Tukang batu 82,500.00
0.32 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
D PEKERJAAN DINDING

2. 1m2 PASANGAN BATU MERAH 1/2 BATA 1 PC : 6 PS


Bahan
70.00 bh Batu merah kelas 2 700.00
8.32 kg Semen gresik / PC (kg) 1,800.00
0.05 m Pasir pasang 215,000.00
Upah
0.02 Oh Mandor 100,000.00
0.01 Oh Kepala tukang batu 85,000.00
0.10 Oh Tukang batu 82,500.00
0.32 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
E PEKERJAAN PLESTERAN

2. 1m2 PLESTERAN 1 PC : 6 PS, t = 15 mm


Bahan
3.68 kg Semen / gresikPC (kg) 1,800.00
0.02 m Pasir pasang 148,800.00
Upah
0.01 Oh Mandor 82,000.00
0.02 Oh Kepala tukang batu 63,700.00
0.15 Oh Tukang batu 58,600.00
0.20 Oh Pekerja 45,300.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
F PEKERJAAN KAYU

1. 1m3 PASANG KUSEN PINTU & JENDELA KAYU JATI


Bahan
1.10 m Kayu jati 35,000,000.00
Upah
0.30 Oh Mandor 100,000.00
2.00 Oh Kepala tukang kayu 85,000.00
20.00 Oh Tukang kayu 58,600.00
6.00 Oh Pekerja 45,300.00
Sub Jumlah

3. 1m2 PASANG PINTU & JENDELA KACA KAYU JATI


Bahan
0.04 m Kayu jati papan 39,500,000.00
Upah
0.80 Oh Mandor 100,000.00
2.00 Oh Kepala tukang kayu 85,000.00
0.20 Oh Tukang kayu 82,500.00
0.04 Oh Pekerja 60,000.00
Sub Jumlah

4. 1m3 PASANG KONSTRUKSI KUDA KUDA KAYU JATI


Bahan
1.10 m Kayu Jati balok 35,000,000.00
15.00 kg Besi strip 26,200.00
0.80 kg Paku kayu segala ukuran 19,400.00
Upah
0.20 Oh Mandor 100,000.00
1.20 Oh Kepala tukang kayu 85,000.00
12.00 Oh Tukang kayu 82,500.00
4.00 Oh Pekerja biasa 60,000.00
Sub Jumlah

5. 1m2 PASANG KASO + RENG GENTENG KODOK KAYU JATI


Bahan
0.01 m Kayu Jati usuk / reng 35,000,000.00
0.15 kg Paku kayu segala ukuran 19,400.00
Upah
0.01 Oh Mandor 100,000.00
0.01 Oh Kepala tukang kayu 85,000.00
0.10 Oh Tukang kayu 82,500.00
0.10 Oh Pekerja biasa 60,000.00
Sub Jumlah

6. 1m2 PASANG RANGKA LANGIT - LANGIT


Bahan
0.02 m Kayu Jati usuk 12,402,000.00
0.15 kg Paku kayu segala ukuran 19,400.00
Upah
0.01 Oh Mandor 82,000.00
0.03 Oh Kepala tukang kayu 100,000.00
0.30 Oh Tukang kayu 85,000.00
0.20 Oh Pekerja 60,000.00
Sub Jumlah

7. 1m1 PASANG LISPLANG ( 2 x 30 ) cm, KAYU MERANTI


Bahan
0.01 m Kayu meranti (papan) 7,151,600.00
0.05 kg Paku kayu segala ukuran 19,400.00
Upah
0.01 Oh Mandor 100,000.00
0.02 Oh Kepala tukang kayu 85,000.00
0.22 Oh Tukang kayu 82,500.00
0.11 Oh Pekerja 60,000.00
Sub Jumlah

8. 1m1 PASANG LIST PLAFON KAYU PROFIL


Bahan
1.00 m' Kayu profil 37,000.00
Upah
0.00 Oh Mandor 100,000.00
0.00 Oh Kepala tukang kayu 85,000.00
0.02 Oh Tukang kayu 82,500.00
0.02 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
G PEKERJAAN BETON

1. 1m3 LANTAI KERJA BETON 1 PC : 3 PS : 5 KR


Bahan
10.00 kg Semen gresik / PC (kg) 1,800.00
0.03 m Pasir beton 247,500.00
0.04 m Batu pecah/koral (mesin) 310,000.00
Upah
0.01 Oh Mandor 100,000.00
0.00 Oh Kepala tukang batu 85,000.00
0.02 Oh Tukang batu 82,500.00
1.15 Oh Pekerja 60,000.00
Sub Jumlah

2. 1m3 BETON BERTULANG 1 PC : 2 PS : 4 KR


Bahan
280.00 kg Semen / PC (kg) 1,800.00
0.45 m Pasir beton 247,500.00
0.90 m Batu pecah/koral (mesin) 310,000.00
Upah
0.08 Oh Mandor 100,000.00
0.03 Oh Kepala tukang batu 85,000.00
0.25 Oh Tukang batu 85,000.00
1.65 Oh Pekerja 60,000.00
Sub Jumlah

3. kg PEMBESIAN ( POLOS )
Bahan
1.05 kg Besi beton 15,000.00
0.02 kg Kawat beton 25,300.00
Upah
0.00 Oh Mandor 100,000.00
0.00 Oh Kepala tukang besi 85,000.00
0.01 Oh Tukang besi 82,500.00
0.01 Oh Pekerja 60,000.00
Sub Jumlah

5. 1m2 PASANG BEKISTING SLOOF


Bahan
0.05 m Kayu papan meranti bekesting 4,200,000.00
0.30 kg Paku biasa 2" - 5" 29,400.00
0.10 ltr Minyak bekisting 4,400.00
Upah
0.01 Oh Mandor 100,000.00
0.03 Oh Kepala tukang kayu 85,000.00
0.26 Oh Tukang kayu 82,500.00
0.30 Oh Pekerja 60,000.00
Sub Jumlah

6. 1m2 PASANG BEKISTING KOLOM


Bahan
0.04 m Kayu papan meranti bekesting 7,151,600.00
0.40 kg Paku biasa 2" - 5" 29,400.00
0.20 ltr Minyak bekisting 4,400.00
0.02 m Kayu meranti ( balok) 6,795,700.00
0.35 lbr Plywood , t = 9mm 100,800.00
2.00 btg Dolken 8 - 10 / 4m 82,600.00
Upah
0.01 Oh Mandor 100,000.00
0.03 Oh Kepala tukang kayu 85,000.00
0.33 Oh Tukang kayu 82,500.00
0.30 Oh Pekerja 60,000.00
Sub Jumlah

7. 1m2 PASANG BEKISTING BALOK


Bahan
0.04 m Kayu papan meranti bekesting 7,151,600.00
0.40 kg Paku biasa 2" - 5" 29,400.00
0.20 ltr Minyak bekisting 4,400.00
0.02 m Kayu meranti ( balok) 6,795,700.00
0.35 lbr Plywood , t = 9mm 100,800.00
2.00 btg Dolken 8 - 10 / 4m 82,600.00
Upah
0.01 Oh Mandor 100,000.00
0.03 Oh Kepala tukang kayu 85,000.00
0.33 Oh Tukang kayu 82,500.00
0.32 Oh Pekerja 60,000.00
Sub Jumlah
Harga Satuan
KODE URAIAN
(Rp)
H PEKERJAAN ATAP

1. 1m2 PAS. ATAP GENTENG KODOK


Bahan
25.00 bh Genteng kodok glazuur 10,700.00
Upah
0.01 Oh Mandor 100,000.00
0.01 Oh Kepala tukang kayu 85,000.00
0.08 Oh Tukang kayu 82,500.00
0.15 Oh Pekerja 60,000.00
Sub Jumlah

2. 1m1 PAS. BUBUNG KODOK


Bahan
5.00 bh Bubung genteng kdk glazuur 28,900.00
8.00 kg Semen / PC gresik (kg) 1,800.00
0.03 m Pasir pasang 215,000.00
Upah
0.00 Oh Mandor 100,000.00
0.02 Oh Kepala tukang kayu 85,000.00
0.20 Oh Tukang kayu 85,000.00
0.40 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
I PEKERJAAN LANGIT-LANGIT

1. 1m2 PAS. LANGIT LANGIT GYPSUM BOARD


Bahan
0.35 lbr Gypsumboard 100,000.00
0.03 kg Paku segala ukuran 19,400.00
0.39 dos Paku skrup 50,400.00
Upah
0.00 Oh Mandor 100,000.00
0.01 Oh Kepala tukang kayu 85,000.00
0.10 Oh Tukang kayu 82,500.00
0.07 Oh Pekerja 60,000.00
Sub Jumlah

2. 1m1 PAS. LIST LANGIT - LANGIT GYPSUM


Bahan
1.10 m' List gypsum 22,800.00
0.05 kg Lem kayu 16,500.00
Upah
0.00 Oh Mandor 100,000.00
0.01 Oh Kepala tukang kayu 85,000.00
0.05 Oh Tukang kayu 82,500.00
0.05 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
J PEKERJAAN KERAMIK

1. 1m2 PASANG LANTAI KERAMIK 30 x 30 cm WARNA / MOTIF


Bahan
11.87 bh Ubin keramik 30 x 30 cm 4,500.00
11.38 kg Semen gresik / PC (kg) 1,800.00
0.04 m Pasir pasang 215,000.00
1.50 kg Semen warna 40,300.00
Upah
0.03 Oh Mandor 100,000.00
0.04 Oh Kepala tukang batu 85,000.00
0.35 Oh Tukang batu 85,000.00
0.62 Oh Pekerja 60,000.00
Sub Jumlah

3. ` PASANG BATU TEMPEL


Bahan
45.00 bh Tegel keramik MOTIF Batu 30x30 6,500.00
9.30 kg Semen gresik / PC (kg) 1,800.00
0.02 m Pasir pasang 215,000.00
1.50 kg Semen warna 40,300.00
Upah
0.03 Oh Mandor 100,000.00
0.05 Oh Kepala tukang batu 82,500.00
0.45 Oh Tukang batu 82,500.00
0.60 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
K PEKERJAAN KUNCI & KACA

3. 1 bh PASANG ENGSEL PINTU


Bahan
1.00 bh Engsel pintu 28,600.00
Upah
0.00 Oh Mandor 100,000.00
0.02 Oh Kepala tukang kayu 85,000.00
0.15 Oh Tukang kayu 82,500.00
0.02 Oh Pekerja 60,000.00
Sub Jumlah
5. 1 bh PASANG GRENDEL PINTU
Bahan
1.00 bh Grendel Pintu 18,000.00
Upah
0.00 Oh Mandor 100,000.00
0.02 Oh Kepala tukang kayu 85,000.00
0.15 Oh Tukang kayu 82,500.00
0.02 Oh Pekerja 60,000.00
Sub Jumlah

8. 1 bh PASANG KACA RAYBEN t = 5 mm


Bahan
1.10 m2 Kaca rayban tb. 5 mm 255,000.00
Upah
0.00 Oh Mandor 100,000.00
0.02 Oh Kepala tukang kayu 85,000.00
0.15 Oh Tukang kayu 82,500.00
0.02 Oh Pekerja 45,300.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
N PEKERJAAN FINISHING

2. 1 m2 MELABUR BIDANG KAYU DENGAN POLITUR


Bahan
0.88 ltr Politur jadi 90,700.00
3.00 lbr Kertas gosok 5,300.00
Upah
0.00 Oh Mandor 100,000.00
0.02 Oh Kepala tukang cat 85,000.00
0.06 Oh Tukang cat 82,500.00
- Oh Pekerja 45,300.00
Sub Jumlah

3. 1 m2 MENGECAT TEMBOK BARU : 1 lps PLAMIR,1 lps CAT DASAR, 2 lps CAT PENUTUP
Bahan
0.20 kg Plamir 105,000.00
0.23 kg Cat dasar 35,000.00
0.48 kg Cat penutup 2 kali 45,000.00
Upah
0.00 Oh Mandor 100,000.00
0.01 Oh Kepala tukang cat 85,000.00
0.06 Oh Tukang cat 82,500.00
0.02 Oh Pekerja 60,000.00
Sub Jumlah

Harga Satuan
KODE URAIAN
(Rp)
O PEKERJAAN INSTALASI LISTRIK

1. 1 ttk PASANG STOP KONTAK


Bahan
1.00 bh Stop kontak 43,800.00
15.00 m' Kabel NYA 2.5 mm 42,400.00
1.00 bh T dos PVC 6,200.00
0.65 ljr Pipa PVC 5/8" 16,100.00
Upah
0.05 Oh Mandor 100,000.00
0.05 Oh Kepala tukang listrik 85,000.00
0.50 Oh Tukang listrik 82,500.00
0.50 Oh Pekerja 60,000.00
Sub Jumlah

2. 1 ttk PASANG LAMPU PIJAR 5 - 40 Watt + SAKLAR


Bahan
1.00 bh Lampu pijar 5 - 40 Watt 73,500.00
20.00 m' Kabel NYA 2.5 mm 21,000.00
1.00 bh Saklar 52,900.00
15.00 m' Isolator 1,300.00
2.00 bh T dos PVC 6,200.00
1.00 ljr Pipa PVC 5/8" 16,100.00
1.00 bh Fitting plafon 29,600.00
6.00 bh Las dof 700.00
Upah
0.05 Oh Mandor 100,000.00
0.05 Oh Kepala tukang listrik 85,000.00
0.50 Oh Tukang listrik 82,500.00
0.50 Oh Pekerja 60,000.00
Sub Jumlah
Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

5,000.00
6,000.00
11,000.00 11,000.00
xfg

54,365.60
32,182.20
588.00

500.00
850.00
8,250.00
6,000.00
15,600.00 87,135.80 102,735.80

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

4,000.00
24,000.00
28,000.00 28,000.00

1,900.00
11,520.00
13,420.00 13,420.00

220,560.00

1,000.00
18,000.00
19,000.00 220,560.00 239,560.00
234,000.00

1,000.00
18,000.00
19,000.00 234,000.00 253,000.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

282,000.00
58,500.00

3,900.00
3,315.00
32,175.00
46,800.00
86,190.00 340,500.00 426,690.00

258,500.00
244,800.00
116,960.00

7,500.00
5,100.00
49,500.00
90,000.00
152,100.00 620,260.00 772,360.00

49,000.00
25,866.00
8,600.00

1,500.00
850.00
8,250.00
19,200.00
29,800.00 83,466.00 113,266.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)


49,000.00
14,976.00
10,535.00

1,500.00
850.00
8,250.00
19,200.00
29,800.00 74,511.00 104,311.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

6,624.00
3,422.40 3,422.40

820.00
955.50
8,790.00
9,060.00
19,625.50 10,046.40 29,671.90

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

38,500,000.00

30,000.00
170,000.00
1,172,000.00
271,800.00
1,643,800.00 38,500,000.00 40,143,800.00

1,382,500.00
80,000.00
170,000.00
16,500.00
2,400.00
268,900.00 1,382,500.00 1,651,400.00

38,500,000.00
393,000.00
15,520.00

20,000.00
102,000.00
990,000.00
240,000.00
1,352,000.00 38,908,520.00 40,260,520.00

420,000.00
2,910.00

500.00
850.00
8,250.00
6,000.00
15,600.00 422,910.00 438,510.00

285,246.00
2,910.00

820.00
3,000.00
25,500.00
12,000.00
41,320.00 288,156.00 329,476.00

78,667.60
970.00

500.00
1,870.00
18,150.00
6,600.00
27,120.00 79,637.60 106,757.60

37,000.00

100.00
170.00
1,732.50
1,260.00
3,262.50 37,000.00 40,262.50

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

18,000.00
6,435.00
13,640.00

600.00
170.00
1,650.00
69,000.00
71,420.00 38,075.00 109,495.00

504,000.00
111,375.00
279,000.00

8,000.00
2,125.00
21,250.00
99,000.00
130,375.00 894,375.00 1,024,750.00

15,750.00
379.50

30.00
59.50
577.50
420.00
1,087.00 16,129.50 17,216.50

189,000.00
8,820.00
440.00

500.00
2,210.00
21,450.00
18,000.00
42,160.00 198,260.00 240,420.00

286,064.00
11,760.00
880.00
101,935.50
35,280.00
165,200.00

600.00
2,805.00
27,225.00
18,000.00
48,630.00 601,119.50 649,749.50

286,064.00
11,760.00
880.00
122,322.60
35,280.00
165,200.00

600.00
2,805.00
27,225.00
19,200.00
49,830.00 621,506.60 671,336.60
Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

267,500.00

800.00
680.00
6,187.50
9,000.00
16,667.50 267,500.00 284,167.50

144,500.00
14,400.00
6,880.00

200.00
1,700.00
17,000.00
24,000.00
42,900.00 165,780.00 208,680.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

35,000.00
582.00
19,656.00

350.00
850.00
8,250.00
4,200.00
13,650.00 55,238.00 68,888.00

25,080.00
825.00

300.00
425.00
4,125.00
3,000.00
7,850.00 25,905.00 33,755.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

53,415.00
20,484.00
9,030.00
60,450.00

3,000.00
2,975.00
29,750.00
37,200.00
72,925.00 143,379.00 216,304.00

292,500.00
16,740.00
3,870.00
60,450.00

3,000.00
3,712.50
37,125.00
36,000.00
79,837.50 373,560.00 453,397.50

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

28,600.00

75.00
1,275.00
12,375.00
900.00
14,625.00 28,600.00 43,225.00
18,000.00

75.00
1,275.00
12,375.00
900.00
14,625.00 18,000.00 32,625.00

280,500.00

75.00
1,275.00
12,375.00
679.50
14,404.50 280,500.00 294,904.50

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

79,816.00
15,900.00

250.00
1,360.00
4,950.00
-
6,560.00 95,716.00 102,276.00

, 2 lps CAT PENUTUP

21,000.00
8,050.00
21,600.00

250.00
535.50
5,197.50
1,200.00
7,183.00 50,650.00 57,833.00

Upah (Rp) Bahan (Rp) Jumlah Harga (Rp)

43,800.00
636,000.00
6,200.00
10,465.00

5,000.00
4,250.00
41,250.00
30,000.00
80,500.00 696,465.00 776,965.00

73,500.00
420,000.00
52,900.00
19,500.00
12,400.00
16,100.00
29,600.00
4,200.00

5,000.00
4,250.00
41,250.00
30,000.00
80,500.00 628,200.00 708,700.00
No. Uraian Gambar Penampang

A DEVISI 1. PERSIAPAN

1 Pembersihan Lokasi plan

Pengukuran dan pemasangan


2
Bowplank

B DEVISI 2. PEKERJAAN TANAH

3 Galian tanah pondasi

4 Galian pondasi rollag

5 Urugan pasir bawah pondasi

6 Urugan tanah kembali bekas galian


7 Urugan pasir dibawah lantai lantai

8 Urugan tanah peninggian lantai

m3

C DEVISI 3. STRUKTUR BAWAH

9 Astampeng

10 Pasangan Batukali

11 Pasangan rollag bata

D DEVISI 4. BETON

11 Sloof

12 Kolom praktis

13 Balok pratis diatas kusen


14 Ring balok

15 tul. pokok sloof 4 10

4 10

25
SK 8-150
16 sengkang sloof 8 15

15 tul. pokok kolom praktis 4 10

4 10
15 SK 8-150
15
16 sengkang kolom 8

15 tul. pokok ring 4 10


4 10
15

SK 8-150
15
16 sengkang ring 8

tul. pokok balok praktis diatas kusen


15
4 10
4 10
15

SK 8-150

tul. pokok balok praktis diatas kusen 15


16
4 10

Pekisting sloof -
Pekisting kolom -

Pekisting balok -

E DEVISI 5. PEKERJAAN PINTU

15 Kusen Pintu Jendela

16 Daun pintu jendela

17 Kaca clear t=6mm

18 Engsel stainless 4" standart -

19 Handle -

E DEVISI 5. DINDING DAN PLASTER

18 Pas. Bata merah -


19 Plester dinding dalam -

20 Plester dinding luar

21 Pekerjaan acian -

G DEVISI 5. PEKERJAAN LANTAI

21 Rabat beton

22 Keramik granit tile 30 x 30 -

G DEVISI 5. ATAP
23 kuda-kuda galvalum UK 75-75 mm

24 Rangka atap galvalum UK 75-75 mm -

24 Penutup atap (genting kodokan)

25 Bubugan -

H DEVISI 6 PLAFON

Rangka plafon hollow

Plafon gibsum board 100 x 100

I PEKERJAAN FINSHING

25 Pengecatan dinding dalam -

26 Pengecatan dinding luar -

27 Pas. Batu tempel -


Pengecatan batu tempel -
Rumus
Perkiraan
lebar panjang tinggi Keterangan Volume
Kuantitas
X Y Z

6.1 6.1 - (lebar+2) x (panjang+2) 37.21 37.21

6.6 6.6 - keliling pos+keliling teras 26.40 26.40

lebar x tinggi x keliling


0.8 0.9 10 7.20 7.20
pos

lebar x tinggi x keliling


0.15 0.3 10 0.45 0.45
pos

panjang x lebar x
0.8 0.005 10 0.04 0.04
ketebalan

(lebar x tinggi kel) -


0.8 0.7 10 2.30 2.30
(volum pondasi)
2.5 0.1 2.5 luas lantai x ketebalan 0.63 0.63

2.5 0.15 2.5 luas lantai x ketebalan 0.94 0.94

m3

0.8 0.15 10 panjang x tinggi x keliling 1.20 1.20

luas penampang x keliling


0.55 0.6 10 = ((a+b)/2) x (tinggi)) x 3.30 3.30
( keliling)

lebar x tinggi x keliling


0.14 0.4 16.8 0.94 0.94
pos

lebar x tinggi x keliling


0.15 0.25 10 0.38 0.38
pos

lebar kuadrad x tinggi x


0.15 0.15 12 0.27 0.27
jumlah

0.15 0.15 2.66 lebar x tinggi x panjang 0.06 0.06


lebar x tinggi x keliling
0.15 0.15 10 0.23 0.23
pos

4 x ( panjang sloof +
2.5 2.5 - 6.24 24.94
panjang kait) x koefisien

panjang sloof / jarak antar


sengkang x (keliling
0.15 0.25 9.04 36.15
sengkang + kait) x
koefisie

4 x ( panjang kolom +
- - 3 7.39 29.58
panjang kait) x koefisie

panjang kolom/ jarak


antar sengkang x (keliling
- - 3 5.92 23.66
sengkang + kait) x
koefisie

4 x ( panjang ring +
2.5 2.5 - 6.24 24.94
panjang kait) x koefisie

panjang ring / jarak antar


sengkang x (keliling
0.125 0.125 - 5.96 23.83
sengkang + kait) x
koefisie

total keseluruhan panjang


3.43 - - 8.45 8.45
tulangan diatas kusen

panjang ring / jarak antar


sengkang x (keliling
- - - 7.05 7.05
sengkang + kait) x
koefisie

2 x tinggi sloof x panjang


- 2.5 0.25 1.25 5.00
sloof
4 x lebar kolom praktis x
- 0.15 3 1.80 7.20
tinggi kolom praktis

2 x tinggi balok x panjang


balok + (2 x tinggi balok
- - - 3.97 3.97
atas kusen * panjang
balok atas kusen)

(l. Penampang x kusen


0.06 0.15 15.61 hor) + 2 x (l. Penampang 0.14 0.14
x kus. Ver)

2(l. Penampang x kusen


0.03 0.1 5.3 hor) + 2(l. Penampang x 0.02 0.02
kus. Ver)

2(l. Penampang x kusen


- - - hor) + 2(l. Penampang x 2.39 2.39
kus. Ver)

- - - - - 3.00

- - - - - 1.00

(keliling pos x tinggi


2.5 2.5 3 dinding) - (lubang 26.17 26.17
dinding)
(keliling pos (dalam) x
2.35 2.35 3 tinggi dinding) - (lubang 24.37 24.37
dinding)

(keliling pos(luar) x tinggi


2.65 2.65 3 dinding) - (lubang 27.97 27.97
dinding)

=luas plester dinding


dalam + luas plester
- - - 0.00
dinding luar - luas batu
tempel

(luas pos + luas teras) x


3.3 3.3 0.05 0.54 0.54
ketebalan

3.3 3.3 - luas pos + luas teras 10.89 10.89


jumlah panjang
keseluruhan rangka kuda
kuda x jumlah kuda kuda

luas penutup atap x


koefisien

luas penutup atap =


(lebar x tinggi atap miring
4.1 - 2.3 x 1/2 ) x 4 4.72 18.86
(atap mring memakai
phitagoras )

panjang keseluruhan
bubungan
2.6 10.40 10.40
(memakai phitagoras)

= luas dinding dalam x


- - -
koefisien berat cat

= luas dinding luar - luas


- - - batu tempel x koefisien
berat cat

lebar x tinggi
= luas batu tempel x
koefisien berat cat
Satuan

m2

m1

m3

m3

m3

m3
m3

m3

m3

m3

m3

m3

m3

m3
m3

kg

kg

kg

kg

kg

kg

kg

kg

m2
m2

m2

m3

m3

m2

buah

buah

m2
m2

m2

m2

m3

m2
m2

m1
DAFTAR VOLUME PEKERJAAN PEMBANGUNAN POS SATPAM
NO URAIAN PEKERJAAN VOL SATUAN
I PEKERJAAN PERSIAPAN
pekerjaan pembersihan lahan 37.21 m2
pengukuran dan pemasangan bowplank 26.40 m1

II PEKERJAAN TANAH
galian tanah untuk pondasi 7.20 m2
urugan tanah kembali 2.30 m3
urugan tanah peninggian lantai 0.94 m3
urugan pasir urug 0.67 m3

III PEKERJAAN PONDASI


pasangan batu kosong (astampeng) 1.20 m3
pasangan pondasi batu kali 1:5 3.30 m3
pondasi rollag 0.94 m2

IV PEKERJAAN PASANGAN DAN PLESTERAN


pasangan bata merah 1/2 bata 1 PC : 6 Pasir 26.17 m3
plesteran 1 PC : 6 Pasir t=15mm 52.34 m2

V PEKERJAAN KAYU
pasang kusen pintu dan jendela kayu jat 0.14
pasang pintu dan jendela kaca kayu jat 0.02
pasangan kuda-kuda kayu jat
pasangan kaso + reng gentng kodok kayu jat
pasang rangka langit-langit
pasang listplank kayu merant (2x30)

VI PEKERJAAN BETON
lantai kerja beton ( rabat beton) 0.54 kg
beton bertulang 0.93 kg
pembesian polos 178.61 kg
pasang bekistng sloof 5.00 m2
pasang bekistng kolom 7.20 m2
pasang bekistng balok 3.97 m2

VII PEKERJAAN ATAP


pasangan atap gentng kodok 18.86 m2
pasangan bubungan kodok 10.40 m1

VIII PEKERJAAN LANGIT-LANGIT


pasangan langit2 gibsum board
pasangan list langit2

IX PEKERJAAN KERAMIK
pasangan lantai keramik 30 x 30
X PEKERJAAN KUNCI DAN DAN KACA
pasang engsel pintu
pasang grendel pintu
pasang kaca rayben t=5cm

XI PEKERAAN FINISHING
melabur bidang kayu dengan politur
mengecat tembok baru

XII PEKERJAAN INSTALASI LISTRIK


pasang stop kontak
pasang lampu pijar 40 wat
DAFTAR VOLUME PEKERJAAN PEMBANGUNAN POS SATPAM
NO URAIAN PEKERJAAN VOL SATUAN HARGA SATUAN
I PEKERJAAN PERSIAPAN
pekerjaan pembersihan lahan 37.21 m2 Rp 11,000.00
pengukuran dan pemasangan bowplank 26.40 m1 Rp 102,735.80
JUMLAH I
II PEKERJAAN TANAH
galian tanah untuk pondasi 7.20 m2 Rp 28,000.00
urugan tanah kembali 2.30 m3 Rp 13,420.00
urugan tanah peninggian lantai 0.94 m3 Rp 239,560.00
urugan pasir urug 0.67 m3 Rp 253,000.00
JUMLAH II
III PEKERJAAN PONDASI
pasangan batu kosong (astampeng) 1.20 m3 Rp 426,690.00
pasangan pondasi batu kali 1:5 3.30 m3 Rp 772,360.00
pasangan pondasi rollag 0.94 m2 Rp 113,266.00
JUMLAH III
IV PEKERJAAN PASANGAN DAN PLESTERAN
pasangan bata merah 1/2 bata 1 PC : 6 Pasir 26.17 m3 Rp 104,311.00
plesteran 1 PC : 6 Pasir t=15mm 52.34 m2 Rp 29,671.90
JUMLAH IV
V PEKERJAAN KAYU
pasang kusen pintu dan jendela kayu jat 0.14 m3 Rp 40,143,800.00
pasang pintu dan jendela kaca kayu jat 0.02 m3 Rp 1,651,400.00
pasangan kuda-kuda kayu jat m3 Rp 40,260,520.00
pasangan kaso + reng gentng kodok kayu jat m3 Rp 438,510.00
pasang rangka langit-langit m3 Rp 329,476.00
pasang listplank kayu merant (2x30) m3 Rp 106,757.60
JUMLAH V
VI PEKERJAAN BETON
lantai kerja beton ( rabat beton) 0.54 Rp 109,495.00
beton bertulang 0.93 m3 Rp 1,024,750.00
pembesian polos 178.61 kg Rp 17,216.50
pasang bekistng sloof 5.00 m2 Rp 240,420.00
pasang bekistng kolom 7.20 m2 Rp 649,749.50
pasang bekistng balok 3.97 m2 Rp 671,336.60
JUMLAH VI
VII PEKERJAAN ATAP
pasangan atap gentng kodok 18.86 Rp 284,167.50
pasangan bubungan kodok 10.40 Rp 208,680.00
JUMLAH VII
VIII PEKERJAAN LANGIT-LANGIT
pasangan langit2 gibsum board Rp 68,888.00
pasangan list langit2 Rp 33,755.00
JUMLAH VIII
IX PEKERJAAN KERAMIK
pasangan lantai keramik 30 x 30 Rp 216,304.00
JUMLAH IX
X PEKERJAAN KUNCI DAN DAN KACA
pasang engsel pintu Rp 43,225.00
pasang grendel pintu Rp 32,625.00
pasang kaca rayben t=5cm Rp 294,904.50
JUMLAH X
XI PEKERAAN FINISHING
melabur bidang kayu dengan politur Rp 102,276.00
mengecat tembok baru Rp 57,833.00
JUMLAH XI
XII PEKERJAAN INSTALASI LISTRIK
pasang stop kontak Rp 776,965.00
pasang lampu pijar 40 wat Rp 708,700.00
JUMLAH XII
SATPAM
JUMLAH HARGA

Rp 409,310.00
Rp 2,712,225.12
Rp 3,121,535.12

Rp 201,600.00
Rp 30,866.00
Rp 224,587.50
Rp 168,245.00
Rp 625,298.50

Rp 2,548,788.00

Rp 2,548,788.00

Rp 2,729,818.87
Rp 1,553,027.25
Rp 4,282,846.12

Rp 5,639,802.46
Rp 26,257.26
Rp -
Rp -
Rp -
Rp -
Rp 5,666,059.72

Rp 59,620.03
Rp 952,863.79
Rp 3,075,052.19
Rp 1,202,100.00
Rp 4,678,196.40
Rp 2,664,534.97
Rp 12,632,367.37

Rp 5,359,399.05
Rp 2,170,272.00
Rp 7,529,671.05

Rp -
Rp -
Rp -
Rp -
Rp -

Rp -
Rp -
Rp -
Rp -

Rp -
Rp -
Rp -

Rp -
Rp -
Rp -
NO URAIAN PEKERJAAN BIAYA
I PEKERJAAN PERSIAPAN Rp 3,121,535
II PEKERJAAN TANAH Rp 625,299
III PEKERJAAN PONDASI Rp 2,548,788
IV PEKERJAAN PASANGAN DAN PLESTERAN Rp 4,282,846
V PEKERJAAN KAYU Rp 5,666,060
VI PEKERJAAN BETON Rp 12,632,367
VII PEKERJAAN ATAP Rp 7,529,671
VIII PEKERJAAN LANGIT-LANGIT Rp -
IX PEKERJAAN KERAMIK Rp -
X PEKERJAAN KUNCI DAN DAN KACA Rp -
XI PEKERAAN FINISHING Rp -
XII PEKERJAAN INSTALASI LISTRIK Rp -
TOTAL Rp 33,285,031