Anda di halaman 1dari 30

REKAPITULASI ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

NO ITEM PEKERJAAN JUMLAH HARGA

A BANGUNAN BARU BELAKANG 64,047,764.10


I PEKERJAAN PENDAHULUAN 656,250.00
II PEKERJAAN PONDASI 3,441,748.97
III PEKERJAAN BETON BERTULANG 16,031,905.88
IV PEKERJAAN DINDING 28,837,300.00
V PEKERJAAN PLAFOND 2,831,500.00
VI PEKERJAAN ATAP 1,072,000.00
VII PEKERJAAN LANTAI 2,888,065.00
VIII PEKERJAAN KAMAR MANDI / WC 2,221,806.25
IX PEKERJAAN PENGECATAN 3,298,438.00
X PEKERJAAN MEKANIKAL & ELEKTRIKAL 2,768,750.00

B REHAB BANGUNAN EXISTING 23,714,906.57


I PEKERJAAN PENDAHULUAN 1,813,750.00
II PEKERJAAN PONDASI 246,725.00
III PEKERJAAN BETON BERTULANG 946,989.07
IV PEKERJAAN DINDING 4,588,500.00
V PEKERJAAN PLAFOND 2,677,500.00
VI PEKERJAAN ATAP 2,472,000.00
VII PEKERJAAN LANTAI 2,360,750.00
VIII PEKERJAAN KAMAR MANDI / WC 3,610,812.50
IX PEKERJAAN PENGECATAN 3,332,880.00
X PEKERJAAN MEKANIKAL & ELEKTRIKAL 1,665,000.00

JUMLAH TOTAL 87,762,670.66


DIBULATKAN 87,700,000.00

Terbilang : Delapan Puluh Tujuh Juta Tujuh Ratus Ribu Rupiah

Padang, September 2021


Dibuat / Dihitung Oleh :

SONY KRISTIANTO, ST
Estimator
Catatan :
1. Perhitungan Volume masing2 Item Pekerjaan bisa di check dalam lembar AKTUAL CHECK.
NO ITEM PEKERJAAN JUMLAH HARGA

2. Analisa Harga Satuan Pekerjaan menggunakan Standar SNI - Dinas Pekerjaan Umum.
3. Urut-urutan Olah Data sbb : Aktual Check, Upah/ Bahan ---> Analisa SNI PU ---> RAB ---> Rekap
4. Semua Data Perhitungan & Harga bisa kami pertanggungjawabkan secara ke-Ilmuan Teknik Sipil.
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMBANGUNAN RUMAH TINGGAL
PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

NO ITEM PEKERJAAN SAT VOL HARGA SAT JMLH HARGA

A BANGUNAN BARU BELAKANG 64,047,764.10

I PEKERJAAN PENDAHULUAN 656,250.00


1 Pengukuran dan Pemasangan Bowplang M' 25.00 26,250.00 656,250.00

II PEKERJAAN PONDASI 3,441,748.97


A BATU KALI
1 Galian Pondasi M3 5.34 78,750.00 420,131.25
2 Pas. Pondasi Batu Kali M3 4.67 254,250.00 1,186,870.78
3 Urugan Tanah Bekas Galian M3 1.17 28,750.00 33,552.15

B PLAT SETEMPAT
1 Galian Pondasi M3 3.84 78,750.00 302,400.00
2 Lantai Kerja Pondasi Beton 1:3:5 M3 0.13 215,750.00 27,616.00
3 Beton Pondasi Plat uk. 80x80x40 M3 1.02 1,409,744.91 1,443,578.79
4 Urugan Tanah Bekas Galian M3 0.96 28,750.00 27,600.00

III PEKERJAAN BETON BERTULANG 16,031,905.88


1 Sloof 15/35 M3 0.95 1,478,594.48 1,397,271.79
2 Sloof Praktis 13/15 M3 0.19 1,468,805.84 277,108.58
3 Kolom Praktis 13/13 M3 0.55 1,776,435.55 984,713.75
4 Kolom Struktur 15/40 M3 1.66 1,780,620.19 2,948,707.03
5 Kolom Mezanine 15/40 M3 0.37 1,780,620.19 651,706.99
6 Balok Latei 13/15 M3 0.30 1,734,801.94 514,195.29
7 Balok Latei 13/15 Talang Beton M3 0.09 1,734,801.94 152,228.87
8 Balok Mezanine 15/35 M3 0.45 1,811,160.92 808,230.56
9 Ring Balok 13/15 (Dapur) M3 0.13 1,734,801.94 226,651.87
10 Ring Balok 15/35 (Renc Balok Lt.2) M3 0.95 1,811,160.92 1,711,547.07
11 Plat Beton Mezanine T.12 M3 1.08 1,691,354.96 1,826,663.36
12 Dak Beton T.12 (Renc Plat Lt.2) M3 2.43 1,691,354.96 4,109,992.55
13 Talang Beton M3 0.27 1,566,252.48 422,888.17

IV PEKERJAAN DINDING 28,837,300.00


1 Dinding Batu Bata M2 135.85 47,750.00 6,486,837.50
2 Plesteran Dinding M2 271.70 44,750.00 12,158,575.00
3 Acian M2 271.70 32,000.00 8,694,400.00
4 Afwerking Dak Beton (Plat Lt.2) M2 20.25 58,950.00 1,193,737.50
5 Waterproofing Dak Beton (Plat Lt.2) & Talang Beton M2 20.25 15,000.00 303,750.00
NO ITEM PEKERJAAN SAT VOL HARGA SAT JMLH HARGA

V PEKERJAAN PLAFOND 2,831,500.00


1 Plafond Gypsum + Rangka Hollow, Lantai Mezanine M2 9.00 70,000.00 630,000.00
2 Plafond Gypsum + Rangka Hollow, Bawah Dak/ Plat Lt.2 M2 20.25 70,000.00 1,417,500.00
3 Plafond Gypsum + Rangka Hollow , Dapur M2 11.20 70,000.00 784,000.00

VI PEKERJAAN ATAP 1,072,000.00


1 Kuda-kuda Baja Ringan + Genteng Metal, Dapur M2 16.80 60,000.00 1,008,000.00
2 Listplank GRC M' 3.20 20,000.00 64,000.00

VII PEKERJAAN LANTAI 2,888,065.00


1 Tanah Timbunan untuk peninggian level lantai M3 14.40 31,500.00 453,600.00
2 Cor Beton Lantai 1:3:5 M3 1.80 215,750.00 388,350.00
3 Lantai Granit uk. 60x60 M2 29.25 57,500.00 1,681,875.00
4 Plin Lantai Lebar 10x60 cm M' 31.40 11,600.00 364,240.00

VIII PEKERJAAN KAMAR MANDI / WC 2,221,806.25


1 Dinding Keramik KM uk. 30x60, tinggi 2.5 m M2 14.88 120,750.00 1,796,156.25
2 Lantai Keramik KM uk. 60x60 Unpolish M2 2.20 120,750.00 265,650.00
3 Closet Duduk Unit 1.00 150,000.00 150,000.00
4 Kran Air Bh 1.00 5,000.00 5,000.00
5 Floor Drain Bh 1.00 5,000.00 5,000.00

X PEKERJAAN PENGECATAN 3,298,438.00


1 Cat Tembok dg Cat Air Interior M2 135.85 12,140.00 1,649,219.00
2 Cat Tembok dg Cat Air Exterior M2 135.85 12,140.00 1,649,219.00

XII PEKERJAAN MEKANIKAL & ELEKTRIKAL 2,768,750.00


A MEKANIKAL
1 Pipa PVC D 4 Inch Air Kotor & Septictank M' 34.38 10,000.00 343,750.00
2 Pipa PVC D.4" dr Talang Air Beton & Dak Beton M' 16.00 10,000.00 160,000.00
3 Pipa PVC AW 3/4" Air Bersih M' 24.00 10,000.00 240,000.00

B ELEKTRIKAL (Pekerjaan Listrik Diluar Bola Lampu)


1 Instalasi Titik Lampu Titik 5.00 225,000.00 1,125,000.00
2 Instalasi Stop Kontak Titik 3.00 225,000.00 675,000.00
3 Instalasi Stop Kontak AC Titik 1.00 225,000.00 225,000.00

B REHAB BANGUNAN EXISTING 23,714,906.57

I PEKERJAAN PENDAHULUAN 1,813,750.00


1 Bongkaran Dinding Bata M2 38.00 21,500.00 817,000.00
2 Bongkaran Lantai M2 48.00 11,500.00 552,000.00
3 Bongkaran Plafond M2 48.00 3,500.00 168,000.00
4 Bongkaran Atap Teras M2 18.00 15,375.00 276,750.00

II PEKERJAAN PONDASI 246,725.00


A BATU KALI
1 Galian Pondasi M3 0.80 78,750.00 63,000.00
NO ITEM PEKERJAAN SAT VOL HARGA SAT JMLH HARGA

2 Pas. Pondasi Batu Kali M3 0.70 254,250.00 177,975.00


3 Urugan Tanah Bekas Galian M3 0.20 28,750.00 5,750.00

III PEKERJAAN BETON BERTULANG 946,989.07


1 Sloof 13/15 M3 0.12 1,468,805.84 171,850.28
2 Kolom Praktis 13/13 M3 0.20 1,776,435.55 360,261.13
3 Balok Latei 13/15 M3 0.12 1,734,801.94 202,971.83
4 Ring Balok 13/15 M3 0.12 1,811,160.92 211,905.83

IV PEKERJAAN DINDING 4,588,500.00


1 Dinding Batu Bata M2 22.80 47,750.00 1,088,700.00
2 Plesteran Dinding M2 45.60 44,750.00 2,040,600.00
3 Acian M2 45.60 32,000.00 1,459,200.00

V PEKERJAAN PLAFOND 2,677,500.00


1 Plafond Gypsum + Rangka Hollow M2 38.25 70,000.00 2,677,500.00

VI PEKERJAAN ATAP 2,472,000.00


1 Kuda-kuda Baja Ringan + Genteng Metal M2 38.70 60,000.00 2,322,000.00
2 Listplank GRC M' 7.50 20,000.00 150,000.00

VII PEKERJAAN LANTAI 2,360,750.00


1 Lantai Granit uk. 60x60 M2 34.50 57,500.00 1,983,750.00
2 Plin Lantai Lebar 10x60 cm M' 32.50 11,600.00 377,000.00

VIII PEKERJAAN KAMAR MANDI / WC 3,610,812.50


1 Dinding Keramik KM uk. 30x60, tinggi 3 m M2 24.00 120,750.00 2,898,000.00
2 Lantai Keramik KM uk. 60x60 Unpolish M2 3.75 120,750.00 452,812.50
3 Closet Duduk Unit 1.00 150,000.00 150,000.00
4 Shower Unit 1.00 100,000.00 100,000.00
5 Kran Air Bh 1.00 5,000.00 5,000.00
6 Floor Drain Bh 1.00 5,000.00 5,000.00

IX PEKERJAAN PENGECATAN 3,332,880.00


1 Cat Tembok dg Cat Air Interior M2 231.00 12,140.00 2,804,340.00
2 Cat Tembok dg Cat Air Exterior M2 21.00 12,140.00 254,940.00
3 Cat Kusen, Daun Pintu / Jendela dg Cat Minyak M2 14.40 19,000.00 273,600.00

X PEKERJAAN MEKANIKAL & ELEKTRIKAL 1,665,000.00


ELEKTRIKAL (Rehab Ulang)
1 Instalasi Titik Lampu Titik 7.00 120,000.00 840,000.00
2 Instalasi Stop Kontak Titik 3.00 120,000.00 360,000.00
3 Instalasi Stop Kontak AC Titik 1.00 120,000.00 120,000.00
4 Instalasi Stop Kontak TV Titik 1.00 225,000.00 225,000.00
5 Instalasi MCB Titik 1.00 120,000.00 120,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
STD - SNI DINAS PEKERJAAN UMUM
KEGIATAN : PEMBANGUNAN RUMAH TINGGAL
PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

1 1 M' Pemasangan Bowplank


Bahan
0.0120 M3 Balok kayu Kelas III (5x7) - -
0.0200 Kg Paku - -
0.0070 M3 Papan Bekisting - -
Tenaga
0.1000 Oh Pekerja 100,000.00 10,000.00
0.1000 Oh Tukang Kayu 140,000.00 14,000.00
0.0100 Oh Kepala Tukang 150,000.00 1,500.00
0.0050 Oh Mandor 150,000.00 750.00
Jumlah 26,250.00

2 1 M2 Membersihkan Lapangan
Tenaga
0.1000 Oh Pekerja 100,000.00 10,000.00
0.0500 Oh Mandor 150,000.00 7,500.00
Jumlah 17,500.00

3 1 M2 Bongkaran Dinding Bata


Tenaga
0.2000 Oh Pekerja 100,000.00 20,000.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 21,500.00

4 1 M2 Bongkaran Lantai Beton


Tenaga
0.1000 Oh Pekerja 100,000.00 10,000.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 11,500.00

5 1 M2 Bongkaran Plafond
Tenaga
0.0200 Oh Pekerja 100,000.00 2,000.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 3,500.00

6 1 M2 Bongkaran Kap Atap


Tenaga
0.1000 Oh Pekerja 100,000.00 10,000.00
0.0250 Oh Tukang 140,000.00 3,500.00
0.0025 Oh Kepala Tukang 150,000.00 375.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 15,375.00

7 1 M3 Menggali Tanah Biasa Sedalam 1 Meter


NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

Tenaga
0.7500 Oh Pekerja 100,000.00 75,000.00
0.0250 Oh Mandor 150,000.00 3,750.00
Jumlah 78,750.00

8 1 M3 Mengurug Kembali Tanah Galian


Tenaga
0.2500 Oh Pekerja 100,000.00 25,000.00
0.0250 Oh Mandor 150,000.00 3,750.00
Jumlah 28,750.00

9 1 M3 Mengurug Tanah Timbunan Untuk Peninggian + Pemadatan


Bahan
1.2000 M3 Tanah Timbunan - -
Tenaga
0.3000 Oh Pekerja 100,000.00 30,000.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 31,500.00

10 1 M3 Pasangan Pondasi Kosong (Aanstampang)


Bahan
1.2000 M3 Batu Kali - -
0.4320 M3 Pasir Urug - -
Tenaga
0.7800 Oh Pekerja 100,000.00 78,000.00
0.3900 Oh Tukang Batu 140,000.00 54,600.00
0.0390 Oh Kepala Tukang 150,000.00 5,850.00
0.0390 Oh Mandor 150,000.00 5,850.00
Jumlah 144,300.00

11 1 M3 Pasangan Pondasi Batu Kali 1 Pc : 4 Ps


Bahan
1.2000 M3 Batu Kali - -
163.0000 Kg Semen Portland (50 Kg) - -
0.5200 M3 Pasir Pasang - -
Tenaga
1.5000 Oh Pekerja 100,000.00 150,000.00
0.6000 Oh Tukang Batu 140,000.00 84,000.00
0.0600 Oh Kepala Tukang 150,000.00 9,000.00
0.0750 Oh Mandor 150,000.00 11,250.00
Jumlah 254,250.00

12 1 M3 Beton 1:2:3
Bahan
336.0000 Kg Semen Portland (50 Kg) - -
0.5400 M3 Pasir Beton - -
0.8100 M3 Kerikil Cor - -
Tenaga
1.6500 Oh Pekerja 100,000.00 165,000.00
0.2750 Oh Tukang Batu 140,000.00 38,500.00
0.0280 Oh Kepala Tukang 150,000.00 4,200.00
0.0830 Oh Mandor 150,000.00 12,450.00
Jumlah 220,150.00

13 1 M3 Beton Tumbuk 1:3:5


Bahan
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

218.0000 Kg Semen Portland (50 Kg) - -


0.5200 M3 Pasir Beton - -
0.8700 M3 Kerikil Cor - -
Tenaga
1.6500 Oh Pekerja 100,000.00 165,000.00
0.2500 Oh Tukang Batu 140,000.00 35,000.00
0.0250 Oh Kepala Tukang 150,000.00 3,750.00
0.0800 Oh Mandor 150,000.00 12,000.00
Jumlah 215,750.00

14 1 M3 Beton Mutu K 175


Bahan
326.0000 Kg Semen Portland (50 Kg) - -
760.0000 Kg Pasir Beton - -
1.0000 M3 Split - -
Tenaga
1.6500 Oh Pekerja 100,000.00 165,000.00
0.2750 Oh Tukang Batu 140,000.00 38,500.00
0.0280 Oh Kepala Tukang 150,000.00 4,200.00
0.0830 Oh Mandor 150,000.00 12,450.00
Jumlah 220,150.00

15 1 M3 Beton Mutu K 250


Bahan
384.0000 Kg Semen Portland (50 Kg) - -
692.0000 Kg Pasir Beton - -
1.0000 M3 Split - -
Tenaga
1.6500 Oh Pekerja 100,000.00 165,000.00
0.2750 Oh Tukang Batu 140,000.00 38,500.00
0.0280 Oh Kepala Tukang 150,000.00 4,200.00
0.0830 Oh Mandor 150,000.00 12,450.00
Jumlah 220,150.00

16 1 M2 Cetakan Beton Pondasi


Bahan
0.3000 Kg Paku 5 cm - 10 cm - -
0.1000 Ltr Minyak Begisting - -
0.0400 M3 Kayu Kelas IV - -
Tenaga
0.5200 Oh Pekerja 100,000.00 52,000.00
0.2600 Oh Tukang Kayu 140,000.00 36,400.00
0.0260 Oh Kepala Tukang 150,000.00 3,900.00
0.0260 Oh Mandor 150,000.00 3,900.00
Jumlah 96,200.00

17 1 M2 Cetakan Beton Sloof


Bahan
0.3000 Kg Paku 5 cm - 10 cm - -
0.1000 Ltr Minyak Begisting - -
0.0450 M3 Kayu Kelas III - -
Tenaga
0.5200 Oh Pekerja 100,000.00 52,000.00
0.2600 Oh Tukang Kayu 140,000.00 36,400.00
0.0260 Oh Kepala Tukang 150,000.00 3,900.00
0.0260 Oh Mandor 150,000.00 3,900.00
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

Jumlah 96,200.00

18 1 M2 Pasang bekisting untuk Kolom


Bahan
0.4000 Kg Paku 5 cm - 10 cm - -
0.2000 Lt Minyak bekisting - -
0.0400 M3 Kayu Kelas III - -
0.0150 M3 Balok kayu Kelas III - -
Tenaga
0.6600 Oh Pekerja 100,000.00 66,000.00
0.3300 Oh Tukang kayu 140,000.00 46,200.00
0.0330 Oh Kepala tukang 150,000.00 4,950.00
0.0330 Oh Mandor 150,000.00 4,950.00
Jumlah 122,100.00

19 1 M2 Pasang bekisting untuk Balok


Bahan
0.4000 Kg Paku 5 cm - 10 cm - -
0.2000 Lt Minyak bekisting - -
0.0400 M3 Kayu Kelas III - -
0.0180 M3 Balok kayu Kelas III - -
Tenaga
0.6600 Oh Pekerja 100,000.00 66,000.00
0.3300 Oh Tukang kayu 140,000.00 46,200.00
0.0330 Oh Kepala tukang 150,000.00 4,950.00
0.0330 Oh Mandor 150,000.00 4,950.00
Jumlah 122,100.00

20 1 M2 Cetakan Beton Plat Lantai


Bahan
0.4000 Kg Paku 5 cm - 10 cm - -
0.2000 Ltr Minyak Begisting - -
0.0400 M3 Kayu Kelas III - -
0.0150 M3 Balok Kayu Kelas III - -
6.0000 Btng Kayu kelas III uk 4/6 Cm - -
0.3500 Lbr Triplek T.9 mm - -
Tenaga
0.6600 Oh Pekerja 100,000.00 66,000.00
0.3300 Oh Tukang Kayu 140,000.00 46,200.00
0.0330 Oh Kepala Tukang 150,000.00 4,950.00
0.0330 Oh Mandor 150,000.00 4,950.00
Jumlah 122,100.00

21 1 Kg Pembesian dengan Besi Polos atau Besi Ulir


Bahan
1.0500 Kg Besi Beton - -
0.0150 Kg Kawat Beton - -
Tenaga
0.0070 Oh Pekerja 100,000.00 700.00
0.0070 Oh Tukang Besi 140,000.00 980.00
0.0007 Oh Kepala Tukang 150,000.00 105.00
0.0004 Oh Mandor 150,000.00 60.00
Jumlah 1,845.00

22 1 M3 Membuat beton bertulang Poer Pondasi 80x80x40 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

123.3577 Kg Pembesian 1,845.00 227,594.91


10.0000 M2 Bekisting Pondasi 96,200.00 962,000.00
Jumlah 1,409,744.91

23 1 M3 Membuat beton bertulang Sloof Praktis 13 x 15 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
155.3690 Kg Pembesian 1,845.00 286,655.84
10.0000 M2 Bekisting Sloof 96,200.00 962,000.00
Jumlah 1,468,805.84

24 1 M3 Membuat beton bertulang Sloof Struktur 15 x 35 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
160.6745 Kg Pembesian 1,845.00 296,444.48
10.0000 M2 Bekisting Sloof 96,200.00 962,000.00
Jumlah 1,478,594.48

25 1 M3 Membuat beton bertulang Kolom Praktis 13 x 13 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
181.7266 Kg Pembesian 1,845.00 335,285.55
10.0000 M2 Bekisting Kolom 122,100.00 1,221,000.00
Jumlah 1,776,435.55

26 1 M3 Membuat beton bertulang Kolom Struktur 15 x 40 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
183.9947 Kg Pembesian 1,845.00 339,470.19
10.0000 M2 Bekisting Kolom Praktis 122,100.00 1,221,000.00
Jumlah 1,780,620.19

27 1 M3 Membuat beton bertulang Balok Latei 13 x 15 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
159.1609 Kg Pembesian 1,845.00 293,651.94
10.0000 M2 Bekisting Balok 122,100.00 1,221,000.00
Jumlah 1,734,801.94

28 1 M3 Membuat beton bertulang Balok Struktur 15 x 35 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
200.5479 Kg Pembesian 1,845.00 370,010.92
10.0000 M2 Bekisting Balok 122,100.00 1,221,000.00
Jumlah 1,811,160.92

29 1 M3 Membuat beton bertulang Ring Balok Praktis 13 x 15 cm


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
159.1609 Kg Pembesian 1,845.00 293,651.94
10.0000 M2 Bekisting Balok Praktis 122,100.00 1,221,000.00
Jumlah 1,734,801.94

30 1 M3 Membuat beton bertulang Plat Lantai


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
135.6124 Kg Pembesian 1,845.00 250,204.96
10.0000 M2 Bekisting Plat Lantai 122,100.00 1,221,000.00
Jumlah 1,691,354.96

31 1 M3 Membuat beton bertulang Talang Beton


1.0000 M3 Beton 1:2:3 220,150.00 220,150.00
67.8062 Kg Pembesian 1,845.00 125,102.48
10.0000 M2 Bekisting Plat Lantai 122,100.00 1,221,000.00
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

Jumlah 1,566,252.48

32 1 M2 Pasangan batu bata tebal 1/2 bata, 1 Pc : 2 Ps


Bahan
70.0000 Bh Batu Bata - -
0.3790 Zak Semen portland ( 50 Kg) - -
0.0380 M3 Pasir pasang - -
Tenaga
0.3000 Oh Pekerja 100,000.00 30,000.00
0.1000 Oh Tukang batu 140,000.00 14,000.00
0.0100 Oh Kepala tukang 150,000.00 1,500.00
0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 47,750.00

33 1 M2 Pasangan batu bata tebal 1/2 bata, 1 Pc : 4 Ps


Bahan
70.0000 Bh Batu Bata - -
0.2300 Zak Semen portland ( 50 Kg) - -
0.0430 M3 Pasir pasang - -
Tenaga
0.3000 Oh Pekerja 100,000.00 30,000.00
0.1000 Oh Tukang batu 140,000.00 14,000.00
0.0100 Oh Kepala tukang 150,000.00 1,500.00
0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 47,750.00

34 1 M2 Pasangan batu bata tebal 1 bata, 1 Pc : 4 Ps


Bahan
140.0000 Bh Batu Bata - -
0.5310 Zak Semen portland ( 50 Kg) - -
0.0930 M3 Pasir pasang - -
Tenaga
0.6000 Oh Pekerja 100,000.00 60,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
0.0200 Oh Kepala tukang 150,000.00 3,000.00
0.0300 Oh Mandor 150,000.00 4,500.00
Jumlah 95,500.00

35 1 M2 Plesteran 1 Pc : 2 Ps, tebal 15 mm


Bahan
0.2045 Zak Semen portland ( 50 Kg) - -
0.0200 M3 Pasir pasang - -
Tenaga
0.2000 Oh Pekerja 100,000.00 20,000.00
0.1500 Oh Tukang batu 140,000.00 21,000.00
0.0150 Oh Kepala tukang 150,000.00 2,250.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 44,750.00

36 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm


Bahan
0.1248 Zak Semen portland ( 50 Kg) - -
0.0240 M3 Pasir pasang - -
Tenaga
0.2000 Oh Pekerja 100,000.00 20,000.00
0.1500 Oh Tukang batu 140,000.00 21,000.00
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

0.0150 Oh Kepala tukang 150,000.00 2,250.00


0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 44,750.00

37 1 M2 Pekerjaan Afwerking Beton


Bahan
0.1940 Zak Semen portland ( 50 Kg) - -
0.0220 M3 Pasir pasang - -
Tenaga
0.2600 Oh Pekerja 100,000.00 26,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
0.0200 Oh Kepala tukang 150,000.00 3,000.00
0.0130 Oh Mandor 150,000.00 1,950.00
Jumlah 58,950.00

38 1 M2 Pekerjaan Acian
Bahan
3.2500 Kg Semen portland ( 50 Kg) - -
Tenaga
0.1500 Oh Pekerja 100,000.00 15,000.00
0.1000 Oh Tukang batu 140,000.00 14,000.00
0.0100 Oh Kepala tukang 150,000.00 1,500.00
0.0100 Oh Mandor 150,000.00 1,500.00
Jumlah 32,000.00

39 1 M2 Pasang Keramik Lantai WC Anti Slip uk 60x60 cm Unpolish


Bahan
1.0000 M2 Keramik 60x60 - -
0.2080 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.6200 Kg Tepung AFA - -
Tenaga
0.6200 Oh Pekerja 100,000.00 62,000.00
0.3500 Oh Tukang batu 140,000.00 49,000.00
0.0350 Oh Kepala tukang 150,000.00 5,250.00
0.0300 Oh Mandor 150,000.00 4,500.00
Jumlah 120,750.00

40 1 M Pasang Keramik Dinding uk 25x40 cm


Bahan
1.0000 M2 Keramik 25x40 - -
0.2080 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.6200 Kg Tepung AFA - -
Tenaga
0.6200 Oh Pekerja 100,000.00 62,000.00
0.3500 Oh Tukang batu 140,000.00 49,000.00
0.0350 Oh Kepala tukang 150,000.00 5,250.00
0.0300 Oh Mandor 150,000.00 4,500.00
Jumlah 120,750.00

41 1 M Pasang Keramik Dinding uk 30x60 cm


Bahan
1.0000 M2 Keramik 30x60 - -
0.2080 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

1.6200 Kg Tepung AFA - -


Tenaga
0.6200 Oh Pekerja 100,000.00 62,000.00
0.3500 Oh Tukang batu 140,000.00 49,000.00
0.0350 Oh Kepala tukang 150,000.00 5,250.00
0.0300 Oh Mandor 150,000.00 4,500.00
Jumlah 120,750.00

42 1 M2 Pasang Lantai Keramik uk 40x40 cm


Bahan
1.0000 M2 Keramik 40x40 - -
0.2000 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.5000 Kg Tepung AFA - -
Tenaga
0.2500 Oh Pekerja 100,000.00 25,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
0.0150 Oh Kepala tukang 150,000.00 2,250.00
0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 57,500.00

43 1 M2 Pasang Lantai Keramik Anti Slip uk 40x40 cm


Bahan
1.0000 M2 Keramik Anti Slip uk 40x40 - -
0.2000 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.5000 Kg Tepung AFA - -
Tenaga
0.2500 Oh Pekerja 100,000.00 25,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
0.0150 Oh Kepala tukang 150,000.00 2,250.00
0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 57,500.00

44 1 M2 Pasang Lantai Granit uk 60x60 cm


Bahan
1.0000 M2 Granit 60x60 - -
0.2000 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.5000 Kg Tepung AFA - -
Tenaga
0.2500 Oh Pekerja 100,000.00 25,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
0.0150 Oh Kepala tukang 150,000.00 2,250.00
0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 57,500.00

45 1 M2 Pasang Lantai Granit Anti Slip uk 60x60 cm


Bahan
1.0000 M2 Granit Anti Slip 60x60 - -
0.2000 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.5000 Kg Tepung AFA - -
Tenaga
0.2500 Oh Pekerja 100,000.00 25,000.00
0.2000 Oh Tukang batu 140,000.00 28,000.00
NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

0.0150 Oh Kepala tukang 150,000.00 2,250.00


0.0150 Oh Mandor 150,000.00 2,250.00
Jumlah 57,500.00

46 1 M' Pasang Plin Granit Anti Slip uk 10x60 cm


Bahan
0.8333 M2 Plin Granit 10x60 - -
0.0083 Zak Semen portland ( 50 Kg) - -
0.0019 M3 Pasir pasang - -
0.0625 Kg Tepung AFA - -
Tenaga
0.0625 Oh Pekerja 100,000.00 6,250.00
0.0313 Oh Tukang batu 140,000.00 4,375.00
0.0033 Oh Kepala tukang 150,000.00 487.50
0.0033 Oh Mandor 150,000.00 487.50
Jumlah 11,600.00 11,600.00

47 1 M Pasang Pasang Batu Alam


Bahan
1.0000 M2 Batu Alam - -
0.2000 Zak Semen portland ( 50 Kg) - -
0.0450 M3 Pasir pasang - -
1.5000 Kg Tepung AFA - -
Tenaga
0.5000 Oh Pekerja 100,000.00 50,000.00
0.5000 Oh Tukang batu 140,000.00 70,000.00
0.0500 Oh Kepala tukang 150,000.00 7,500.00
0.0500 Oh Mandor 150,000.00 7,500.00
Jumlah 135,000.00

48 1 M2 Mencat Kayu Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Bahan
0.2000 Kg Cat Menie - -
0.1500 Kg Plamir - -
0.1700 Kg Cat Dasar - -
0.2600 Kg Cat Minyak Ex Dulux - -
Tenaga
0.0700 Oh Pekerja 100,000.00 7,000.00
0.0750 Oh Tukang Cat 140,000.00 10,500.00
0.0075 Oh Kepala tukang 150,000.00 1,125.00
0.0025 Oh Mandor 150,000.00 375.00
Jumlah 19,000.00

49 1 M2 Mencat Tembok Baru Interior


Bahan
0.1000 Kg Alkali - -
0.1000 Kg Cat Dasar - -
0.2600 Kg Cat Air Ex Jotun Interior - -
Tenaga
0.0200 Oh Pekerja 100,000.00 2,000.00
0.0630 Oh Tukang Cat 140,000.00 8,820.00
0.0063 Oh Kepala tukang 150,000.00 945.00
0.0025 Oh Mandor 150,000.00 375.00
Jumlah 12,140.00

50 1 M2 Mencat Tembok Baru Exterior


NO URAIAN PEKERJAAN HARGA SAT JUMLAH JUML TOTAL

Bahan
0.1000 Kg Alkali - -
0.1000 Kg Cat Dasar - -
0.2600 Kg Cat Air Ex Jotun Exterior - -
Tenaga
0.0200 Oh Pekerja 100,000.00 2,000.00
0.0630 Oh Tukang Cat 140,000.00 8,820.00
0.0063 Oh Kepala tukang 150,000.00 945.00
0.0025 Oh Mandor 150,000.00 375.00
Jumlah 12,140.00
DAFTAR HARGA SATUAN UPAH & BAHAN
KEGIATAN : PEMBANGUNAN RUMAH TINGGAL
PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021
NO URAIAN UPAH / BAHAN SAT HARGA SAT KETERANGAN
UPAH
1 Pekerja Oh 100,000.00
2 Tukang Oh 140,000.00
3 Kepala Tukang Oh 150,000.00
4 Mandor Oh 150,000.00
BAHAN
1 Batu Bulat Utuh/ Batu Belah M3 - 1 Truk -
2 Batu Pecah / Split 1/2 - 1 cm M3 - 1 Ton -
3 Kerikil Beton/ Kerikil Cor M3 - 1 Truk -
4 Pasir Pasang M3 - 1 Truk -
5 Pasir Beton M3 - 1 Truk -
6 Pasir Urug M3 - 1 Truk -
7 Tanah Timbunan Biasa M3 - 1 Truk -
8 Batu Bata Buah -
9 Semen Portland ( 50 Kg) Zak - 1 Kg -
10 Semen Putih ( 40 kg) Zak - 1 Kg -
11 Semen Abu-abu Kg -
12 Kayu Banio ( Papan) Klas I M3 -
13 Kayu Banio (Balok) Klas I M3 -
14 Kayu Marsawa (Papan) Klas II M3 -
15 Kayu Marsawa ( Balok) Klas II M3 -
16 Kayu Merantih ( Papan) Klas III M3 -
17 Kayu Merantih (Balok) Klas III M3 -
18 Kayu Bekesting ( Papan) Klas IV M3 -
19 Kayu Bekesting ( Balok) Klas IV M3 -
20 Kayu Perancah (Balok) Klas IV M3 -
21 Kayu Kelas III uk 4/6 Batang -
22 Triplek T.4 Lembar -
23 Triplek T.6 Lembar -
24 Triplek T.9 Lembar -
25 Lem Kayu Kg -
26 Kawat Beton Kg -
27 Besi Beton Kg -
28 Paku Kg - 1 KTK -
29 Granit Lantai 60x60 cm M2 -
30 Granit Lantai Anti Slip 60x60 cm M2 -
31 Granit Dinding 30x60 cm M2 -
32 Keramik Lantai 40x40 cm M2 -
33 Keramik Anti Slip 40x40 cm M2 -
34 Keramik Dinding 25x40 cm M2 -
35 Keramik Lantai Anti Slip 25 x 25 cm M2 -
36 Plint Keramik 10x60 cm M' -
37 Batu Alam M2 -
38 Plamir Kayu - Wa Kg -
39 Meni Kayu - Wa Kg -
40 Meni Besi - Wa Kg -
41 Cat Dasar Alkali Kg -
42 Cat Tembok Ex Catylac Kg - 1 PILE -
43 Cat Tembok Ex Jotun (Interior) Kg - 1 PILE -
44 Cat Tembok Ex Jotun (Exterior) Kg - 1 PILE -
45 Cat Tembok Ex Dulux (Interior) Kg - 1 PILE -
46 Cat Tembok Ex Dulux (Exterior) Kg - 1 PILE -
47 Cat Minyak Ex Dulux Kg -
NO URAIAN UPAH / BAHAN SAT HARGA SAT KETERANGAN
48 Minyak bekesting Liter -
ACTUAL CHECK
KEGIATAN : PEMBANGUNAN RUMAH TINGGAL
PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

NO ITEM PEKERJAAN VOL SAT

A BANGUNAN BARU BELAKANG

I PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemasangan Bowplang P 8.00 25.00 M'
L 4.50

II PEKERJAAN PONDASI
A BATU KALI
1 Galian Pondasi P 26.68 5.34 M3
L 0.40
H 0.50

2 Pas. Pondasi Batu Kali P 26.68 4.67 M3


La 0.30
Lb 0.40
H 0.50

3 Urugan Tanah Bekas Galian 1.17 M3

B PLAT SETEMPAT
1 Galian Pondasi P 0.80 3.84 M3
L 0.80
H 1.50
Jumlah 4.00

2 Lantai Kerja Pondasi Beton 1:3:5 P 0.80 0.13 M3


L 0.80
H 0.05
Jumlah 4.00

3 Beton Pondasi Plat uk. 80x80x40 P 0.80 1.02 M3


L 0.80
H 0.40
Jumlah 4.00

4 Urugan Tanah Bekas Galian 0.96 M3

III PEKERJAAN BETON BERTULANG


1 Sloof 15/35 B 0.15 0.95 M3
NO ITEM PEKERJAAN VOL SAT

H 0.35
P 18.00

2 Sloof Praktis 13/15 B 0.13 0.19 M3


H 0.15
P 9.68

3 Kolom Praktis 13/13 B 0.13 0.55 M3


H 0.13
T 2.70
Jumlah 4.00 0.18

B 0.13
H 0.13
T 5.50
Jumlah 4.00 0.37

4 Kolom Struktur 15/40 B 0.15 1.66 M3


H 0.40
T 6.90
Jumlah 4.00

5 Kolom Mezanine 15/40 B 0.15 0.37 M3


H 0.40
T 3.05
Jumlah 2.00

6 Balok Latei 13/15 B 0.13 0.30 M3


H 0.15
P 15.20

7 Balok Latei 13/15 Talang Beton B 0.13 0.09 M3


H 0.15
P 4.50

8 Balok Mezanine 15/35 B 0.15 0.45 M3


H 0.35
P 8.50

9 Ring Balok 13/15 (Dapur) B 0.13 0.13 M3


H 0.15
P 6.70

10 Ring Balok 15/35 (Renc Balok Lt.2) B 0.15 0.95 M3


H 0.35
P 18.00
NO ITEM PEKERJAAN VOL SAT

11 Plat Beton Mezanine T.12 P 4.50 1.08 M3


L 2.00
H 0.12

12 Dak Beton T.12 (Renc Plat Lt.2) P 4.50 2.43 M3


L 4.50
H 0.12

13 Talang Beton P 4.50 0.27 M3


L 0.60
H 0.10

IV PEKERJAAN DINDING
1 Dinding Batu Bata P 24.70 135.85 M2
T 5.50

2 Plesteran Dinding 271.70 M2


3 Acian 271.70 M2
4 Afwerking Dak Beton (Plat Lt.2) P 4.50 20.25 M2
L 4.50

5 Waterproofing Dak Beton (Plat Lt.2) & Talang Beton 20.25 M2

V PEKERJAAN PLAFOND
1 Plafond Gypsum + Rangka Hollow, Lantai Mezanine P 4.50 9.00 M2
L 2.00

2 Plafond Gypsum + Rangka Hollow, Bawah Dak/ Plat Lt.2 P 4.50 20.25 M2
L 4.50

3 Plafond Gypsum + Rangka Hollow , Dapur P 3.50 11.20 M2


L 3.20

VI PEKERJAAN ATAP
1 Kuda-kuda Baja Ringan + Genteng Metal, Dapur P 3.50 16.80 M2
L 4.00
Idx 1.20

2 Listplank GRC P 3.20 3.20 M'

VII PEKERJAAN LANTAI


1 Tanah Timbunan untuk peninggian level lantai P 8.00 14.40 M3
L 4.50
H 0.40

2 Cor Beton Lantai 1:3:5 P 8.00 1.80 M3


L 4.50
H 0.05
NO ITEM PEKERJAAN VOL SAT

3 Lantai Granit uk. 60x60 P 4.50 29.25 M2


L 4.50 18.05

P 3.50
L 3.20 11.20

4 Plin Lantai Lebar 10x60 cm P 31.40 31.40 M'

VIII PEKERJAAN KAMAR MANDI / WC


1 Dinding Keramik KM uk. 30x60, tinggi 2.5 m P 5.95 14.88 M2
T 2.50

2 Lantai Keramik KM uk. 60x60 Unpolish P 1.60 2.20 M2


L 1.38

3 Closet Duduk 1.00 Unit


4 Kran Air 1.00 Bh
5 Floor Drain 1.00 Bh

X PEKERJAAN PENGECATAN
1 Cat Tembok dg Cat Air Interior 135.85 M2
2 Cat Tembok dg Cat Air Exterior 135.85 M2

XII PEKERJAAN MEKANIKAL & ELEKTRIKAL


A MEKANIKAL
1 Pipa PVC D 4 Inch Air Kotor & Septictank P Sptc 9.38 34.38 M
P AK 25.00

2 Pipa PVC D.4" dr Talang Air Beton & Dak Beton P 16.00 16.00 M
3 Pipa PVC AW 3/4" Air Bersih P 24.00 24.00 M

B ELEKTRIKAL (Pekerjaan Listrik Diluar Bola Lampu)


1 Instalasi Titik Lampu 5.00 Titik
2 Instalasi Stop Kontak 3.00 Titik
3 Instalasi Stop Kontak AC 1.00 Titik

B REHAB BANGUNAN EXISTING

I PEKERJAAN PENDAHULUAN
1 Bongkaran Dinding Bata P 10.00 38.00 M2
T 3.80

2 Bongkaran Lantai P 6.00 48.00 M2


L 8.00

3 Bongkaran Plafond P 6.00 48.00 M2


NO ITEM PEKERJAAN VOL SAT

L 8.00

4 Bongkaran Atap Teras P 3.00 18.00 M2


L 6.00

II PEKERJAAN PONDASI
A BATU KALI
1 Galian Pondasi B 0.40 0.80 M3
H 0.50
P 4.00

2 Pas. Pondasi Batu Kali P 4.00 0.70 M3


La 0.30
Lb 0.40
H 0.50
3 Urugan Tanah Bekas Galian 0.20 M3

III PEKERJAAN BETON BERTULANG


1 Sloof 13/15 B 0.13 0.12 M3
H 0.15
P 6.00

2 Kolom Praktis 13/13 B 0.13 0.20 M3


H 0.13
T 4.00
Jumlah 3.00

3 Balok Latei 13/15 B 0.13 0.12 M3


H 0.15
P 6.00

4 Ring Balok 13/15 B 0.13 0.12 M3


H 0.15
P 6.00

IV PEKERJAAN DINDING
1 Dinding Batu Bata P 6.00 22.80 M2
T 3.80

2 Plesteran Dinding 45.60 M2


3 Acian 45.60 M2

V PEKERJAAN PLAFOND
1 Plafond Gypsum + Rangka Hollow P 5.50 38.25 M2
L 6.00 33.00
P 1.50
L 3.50 5.25
NO ITEM PEKERJAAN VOL SAT

VI PEKERJAAN ATAP
1 Kuda-kuda Baja Ringan + Genteng Metal P 5.00 38.70 M2
L 4.30
Idx 1.80

2 Listplank GRC P 7.50 7.50 M'

VII PEKERJAAN LANTAI


1 Lantai Granit uk. 60x60 P 5.50 34.50 M2
L 6.00 33.00
P 1.50
L 3.50 5.25

2 Plin Lantai Lebar 10x60 cm P 32.50 32.50 M'

VIII PEKERJAAN KAMAR MANDI / WC


1 Dinding Keramik KM uk. 30x60, tinggi 3 m P 8.00 24.00 M2
T 3.00

2 Lantai Keramik KM uk. 60x60 Unpolish P 2.50 3.75 M2


L 1.50

3 Closet Duduk 1.00 Unit


4 Shower 1.00 Unit
5 Kran Air 1.00 Bh
6 Floor Drain 1.00 Bh

X PEKERJAAN PENGECATAN
1 Cat Tembok dg Cat Air Interior P 33.00 231.00 M2
T 3.50
Jumlah 2.00

2 Cat Tembok dg Cat Air Exterior P 6.00 21.00 M2


T 3.50

3 Cat Kusen, Daun Pintu / Jendela dg Cat Minyak P 6.00 14.40 M2


T 2.40

XII PEKERJAAN MEKANIKAL & ELEKTRIKAL


ELEKTRIKAL (Pekerjaan Listrik Diluar Bola Lampu)
1 Instalasi Titik Lampu 7.00 Titik
2 Instalasi Stop Kontak 3.00 Titik
3 Instalasi Stop Kontak AC 1.00 Titik
4 Instalasi Stop Kontak TV 1.00 Titik
5 Instalasi MCB 1.00 Titik
REKAPITULASI ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

PELAKSANA :
SONY KRISTIANTO, ST
Jl. Adinegoro Komplek Singgalang Blok B3 No.18 Tabing - Padang
08126768313
RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

PELAKSANA :
SONY KRISTIANTO, ST
Jl. Adinegoro Komplek Singgalang Blok B3 No.18 Tabing - Padang
08126768313
DAFTAR ANALISA PEKERJAAN STD - SNI
DINAS PEKERJAAN UMUM

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

PELAKSANA :
SONY KRISTIANTO, ST
Jl. Adinegoro Komplek Singgalang Blok B3 No.18 Tabing - Padang
08126768313
DAFTAR HARGA SATUAN UPAH & BAHAN

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

PELAKSANA :
SONY KRISTIANTO, ST
Jl. Adinegoro Komplek Singgalang Blok B3 No.18 Tabing - Padang
08126768313

ACTUAL CHECK

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


PEKERJAAN : REHABILITASI RUMAH IBU PATRIYENI
LOKASI : GRIYA ELOK, ARAI PINANG - PADANG
TAHUN : 2021

PELAKSANA :
SONY KRISTIANTO, ST
Jl. Adinegoro Komplek Singgalang Blok B3 No.18 Tabing - Padang
08126768313
RAB 1

Rp 87,700,000.00
Terbilang : Delapan Puluh Tujuh Juta Tujuh Ratus Ribu Rupiah

Milyar 0
ratusan 87 0
Juta 87 80 7
puluhan DELAPAN PULUH
satuan TUJUH
JUTA
ratusan 700 7 TUJUH RATUS
Ribu 0 0 0
puluhan
satuan
RIBU
ratusan 0 0
Satu 0 0 0
puluhan
satuan

Anda mungkin juga menyukai