JUMLAH 286,888,445.00
PPN 10% 28,688,844.50
JUMLAH TOTAL 315,577,289.50
JUMLAH TOTAL 315,577,000.00
Terbilang :
#NAME?
I. PEKERJAAN PERSIAPAN
1 Biaya Pembuatan Papan Proyek unit 1.00 300,000.00 300,000.00
2 Biaya Administrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00
3 Biaya Bongkaran ls 1.00 3,500,000.00 3,500,000.00
4 Biaya Pengadaan Alat Bantu / Prancah ls 1.00 1,500,000.00 1,500,000.00
5 Biaya Pengadaan Listrik dan Air Kerja ls 1.00 1,000,000.00 1,000,000.00
6 Biaya K3 ls 1.00 1,000,000.00 1,000,000.00
8,300,000.00
LANTAI BAWAH
II. PEKERJAAN PASANGAN
1 Plesteran 15 tebal 15 mm m2 25.99 78,900.00 2,050,611.00
2 Acian m2 25.99 46,600.00 1,211,134.00
3 Rabat Beton beton t= 5cm Mutu K-100 (135) m3 0.68 1,088,900.00 740,452.00
4 Saluran Air Hujan Bata Merah Besar lebar 20cm m1 47.90 150,400.00 7,204,160.00
11,206,357.00
III. PEKERJAAN KUSEN ALUMUNIUM
1 Pemasangan Daun Pintu Alumunium 0,8 x 2,10 m (Daun Pintu Panel Multyplek 9mm Lapis HPL) unit 3.00 999,700.00 2,999,100.00
2 Kusen Pintu Besi uk. 0,7x1,95m unit 4.00 1,600,000.00 6,400,000.00
9,399,100.00
IV. PEKERJAAN ATAP DAN PLAFOND
1 Kuda - Kuda Baja Ringan m2 36.75 170,000.00 6,247,500.00
2 Atap U-PVC tebal 12mm Merah Maroon m2 84.75 264,300.00 22,399,425.00
3 Listplank GRC tebal 9mm Tumpangsari m1 24.45 92,800.00 2,268,960.00
30,915,885.00
V. PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 Pengecatan Dinding Interior 2x Merk Vinillex m2 224.03 29,000.00 6,496,870.00
2 Pengecatan Dinding Exterior 2x Merk Vinillex m2 273.00 28,800.00 7,862,400.00
3 Pengecatan Dinding Exterior 3x Merk Vinillex m2 25.99 40,700.00 1,057,793.00
4 Pengecatan Kayu 3x Merk Seiv (pintu besi dan listplank ) m2 17.03 61,700.00 1,050,751.00
16,467,814.00
LANTAI ATAS
VI. PEKERJAAN PASANGAN
1 Lantai Keramik 30x30 Polos Merk Mulia ( Tambal Sulam ) m2 40.97 171,100.00 7,009,967.00
2 Bata Merah Besar 1/2 Bata 15 ( Diatas Folding gate ) m2 7.25 153,400.00 1,112,150.00
3 Plesteran 15 tebal 15 mm ( Perbaikan dinding retak ) m2 29.50 78,900.00 2,327,550.00
4 Acian m2 37.48 46,600.00 1,746,568.00
5 Balok Lintel 13x18 (210 kg Besi + Bekisting) K-175 m3 0.34 6,484,900.00 2,204,866.00
14,401,101.00
VII. PEKERJAAN KUSEN ALUMUNIUM
1 Pemasangan Daun Pintu Alumunium 0,8 x 2,10 m (Daun Pintu Panel Multyplek 9mm Lapis HPL) unit 4.00 999,700.00 3,998,800.00
2 Pemasangan Folding Gate m2 30.53 535,000.00 16,333,550.00
3 Pemasangan Slot jendela buah 2.00 47,000.00 94,000.00
20,426,350.00
VIII. PEKERJAAN ATAP DAN PLAFOND
1 Pemasangan Reng Baja Ringan Atap Onduline tile ( Penambahan ) m2 168.75 65,100.00 10,985,625.00
2 Atap Bitumen Onduline Tile Shaded Red uk. 1950 x 960 Monolayer 3mm m2 337.50 165,900.00 55,991,250.00
3 Nok Bitumen Selulosa Shaded Red m1 27.00 171,400.00 4,627,800.00
4 Nok Tepi Bitumen Selulosa Shaded Red m1 25.00 147,500.00 3,687,500.00
5 Listplank Capit Gunting GRC tebal 9 mm m1 4.80 92,800.00 445,440.00
6 Plafond PVC tebal 9mm Lebar 16cm + List Shunda Plafond Type MA 16050 + LS 302 m2 265.71 258,100.00 68,579,751.00
7 Rangka Plafond Hollow Galvalume 20x40 + 40x40 tb. 0,35mm ( Perkuatan Rangka Hollow Lama ) m2 106.28 62,900.00 6,685,012.00
151,002,378.00
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Titik Lampu Conduit Pipa PVC 5/8 titik 17.00 140,400.00 2,386,800.00
2 Instalasi Stop Kontak Conduit Pipa PVC 5/8 titik 1.00 130,600.00 130,600.00
3 Lampu LED Downlight 12 watt Type Eridani Philips buah 5.00 120,000.00 600,000.00
4 Lampu RMI In Bow 2 x 20 watt Philips buah 12.00 315,000.00 3,780,000.00
5 Stop Kontak Merk Brocco buah 1.00 29,100.00 29,100.00
6 Saklar Ganda Merk Brocco buah 1.00 32,400.00 32,400.00
6,958,900.00
X. PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 Pengecatan Dinding Interior 2x Merk Vinillex m2 235.79 29,000.00 6,837,910.00
2 Pengecatan Dinding Exterior 2x Merk Vinillex m2 188.80 28,800.00 5,437,440.00
3 Pengecatan Kayu 2x Merk Seiv ( listplank dan Railling ) m2 32.88 41,600.00 1,367,808.00
4 Pengecatan Kayu 3x Merk Seiv ( Folding gate) m2 61.06 61,700.00 3,767,402.00
5 Biaya Pembersihan Lokasi Setelah Pekerjaan Selesai ls 1.00 400,000.00 400,000.00
17,810,560.00
SPESIFIKASI TEKNIS MATERIAL
I. PEKERJAAN PERSIAPAN 2.893 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
MOBILISASI DAN DEMOBILISASI
K3 DAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
LANTAI BAWAH
II. PEKERJAAN PASANGAN 3.906 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
III. PEKERJAAN KUSEN ALUMUNIUM 3.276
IV. PEKERJAAN ATAP DAN PLAFOND 10.776 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27
V. PEKERJAAN PENGECATAN DAN PENYELESAIAN 5.740
LANTAI ATAS
VI. PEKERJAAN PASANGAN 5.020 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
VII. PEKERJAAN KUSEN ALUMUNIUM 7.120
VIII. PEKERJAAN ATAP DAN PLAFOND 52.635 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32 1.32
IX. PEKERJAAN INSTALASI LISTRIK 2.426
X. PEKERJAAN PENGECATAN DAN PENYELESAIAN 6.208
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
0.478
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
1.617
Fisik Rencana 100.000
0.478
0.957
1.435
1.914
2.392
2.871
3.349
3.828
4.306
4.784
5.263
5.741
6.220
6.698
7.177
7.655
8.134
11.19
12.80
14.42
16.04
17.66
19.27
20.89
22.51
24.13
25.74
27.36
28.98
30.60
32.21
33.83
35.45
37.06
38.68
40.30
41.92
43.53
45.15
46.77
48.39
50.00
51.62
53.24
54.86
56.47
58.09
59.71
61.33
62.94
64.56
66.18
8.61
9.09
9.57
Jumlah Fisik Rencana
Fisik Nyata
Deviasi
I. PEKERJAAN PERSIAPAN 2.893 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 2.893
MOBILISASI DAN DEMOBILISASI
K3 DAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
LANTAI BAWAH
II. PEKERJAAN PASANGAN 3.906 3.906
III. PEKERJAAN KUSEN ALUMUNIUM 3.276 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 3.276
IV. PEKERJAAN ATAP DAN PLAFOND 10.776 0.27 0.27 0.27 0.27 0.27 10.776
V. PEKERJAAN PENGECATAN DAN PENYELESAIAN 5.740 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 5.740
LANTAI ATAS
VI. PEKERJAAN PASANGAN 5.020 5.020
VII. PEKERJAAN KUSEN ALUMUNIUM 7.120 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 7.120
VIII. PEKERJAAN ATAP DAN PLAFOND 52.635 1.32 1.32 1.32 1.32 1.32 52.635
IX. PEKERJAAN INSTALASI LISTRIK 2.426 0.49 0.49 0.49 0.49 0.49 2.426
X. PEKERJAAN PENGECATAN DAN PENYELESAIAN 6.208 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41 6.208
2.103
2.103
2.103
2.103
2.103
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.725
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
0.829
Fisik Rencana 100.000 100.000
100.00
68.28
70.38
72.49
74.59
76.69
77.42
78.14
78.87
79.59
80.32
81.04
81.77
82.49
83.22
83.94
84.67
85.39
86.12
86.84
87.57
88.40
89.23
90.06
90.88
91.71
92.54
93.37
94.20
95.03
95.86
96.69
97.51
98.34
99.17
Jumlah Fisik Rencana
Deviasi
Nama Paket Pekerjaan : Rehabilitasi Ruang Kelas SDN Puspanegara 05 Kec. Citeureup
Lokasi Pekerjaan : Kecamatan Citeureup Kabupaten Bogor
Waktu Pelaksanaan : 90 (sembilan puluh) Hari Kalender
1, 2, 3 90
H
90 90
0 4, 8 20 6, 10 60 5, 9 75 7, 12 90
A B C D E
0 20 20 40 60 15 75 15 90
0 11
F
0 5
1 PEKERJAAN PERSIAPAN
2 MOBILISASI DAN DEMOBILISASI
3 K3 DAN PROTOKOL KESEHATAN PENCEGAHAN COVID-19
LANTAI BAWAH
4 PEKERJAAN PASANGAN
5 PEKERJAAN KUSEN ALUMUNIUM
6 PEKERJAAN ATAP DAN PLAFOND
7 PEKERJAAN PENGECATAN DAN PENYELESAIAN
LANTAI ATAS
8 PEKERJAAN PASANGAN
9 PEKERJAAN KUSEN ALUMUNIUM
10 PEKERJAAN ATAP DAN PLAFOND
11 PEKERJAAN INSTALASI LISTRIK
12 PEKERJAAN PENGECATAN DAN PENYELESAIAN
No Uraian Upah
1 Mandor 150,300.00
2 Kepala Tukang 141,300.00
3 Kepala Tukang Batu 141,300.00
4 Kepala Tukang Kayu 141,300.00
5 Kepala Tukang Besi 141,300.00
6 Kepala Tukang Cat 141,300.00
7 Kepala Tukang Listrik 141,300.00
8 Tukang 123,300.00
9 Tukang Batu 123,300.00
10 Tukang Kayu 123,300.00
11 Tukang besi 123,300.00
12 Tukang Alumunium 123,300.00
13 Tukang Cat 123,300.00
14 Tukang Listrik 123,300.00
15 Tukang Pipa 123,300.00
16 Tukang Plitur 123,300.00
17 Tukang Taman 123,300.00
18 Pekerja 114,300.00
19 Sopir 141,300.00
20 Operator 123,300.00
21 Mekanik 123,300.00
22 Pembantu Sopir 114,300.00
23 Pembantu Operator 114,300.00
24 Pembantu Mekanik 114,300.00
HARGA SATUAN BAHAN / MATERIAL
No Bahan / Material Spesifikasi Bahan Satuan Harga
-
BAHAN PENUTUP RANGKA PLAFOND -
1 GRC (120 x 240) cm, t = 4 mm lembar 72,000.00
2 Gypsum Board 120 x 240 x 9 mm lembar 75,000.00
3 List Gypsum Panjang 2m m1 15,000.00
4 Tepung Gypsum kg 12,000.00
5 Cotton Plester buah 24,000.00
6 Coumpound zak 88,000.00
7 Plafond PVC tb. 9mm Setara Shunda Plafond (16x0,9 cm) m1 29,000.00
8 List Sudut Plafond PVC Setara Shunda Plafond m1 20,750.00
9 List Sambungan Plafond PVC Setara Shunda Plafond m1 16,000.00
-
BAHAN KAYU LAPIS -
1 Multiplek 9 mm 120 x 240 lembar 150,000.00
2 HPL (High Preassure Laminate) 120 x 240 lembar 200,000.00
-
BAHAN LANTAI DAN PELAPIS DINDING -
1 Keramik 10 x 20 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 70,000.00
2 Keramik 20 x 20 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 65,000.00
3 Keramik 20 x 20 Polos setara Mulia KW 1 DN Putih polos dus 55,000.00
4 Keramik 20 x 25 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 76,000.00
5 Keramik 25 x 25 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 65,000.00
6 Keramik 25 x 40 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 77,000.00
7 Keramik 30 x 30 Polos setara Mulia KW 1 DN Putih polos dus 45,000.00
8 Keramik 30 x 30 Corak setara Mulia KW 1 Warna/Corak (Anti Slip) dus 55,000.00
9 Keramik 40 x 40 Polos setara Mulia KW 1 DN Putih polos dus 65,000.00
10 Keramik 40 x 40 Corak setara Mulia KW 1 Warna / Corak (Anti Slip) dus 76,000.00
11 Keramik 60 x 60 Polos setara Mulia KW 1 DN Putih polos dus 156,000.00
12 Keramik 60 x 60 Corak setara Mulia KW 1 Warna / Corak (Anti Slip) dus 169,000.00
13 Granite 60 x 60 Granite Polis m2 495,000.00
14 Granite 30 x 60 m2 200,000.00
15 Ornamen GRC 1,500,000.00
16 Logo Kabupaten Bogor Stainless t = 30 cm 1,000,000.00
17 Logo Kabupaten Bogor Stainless t = 40 cm 1,250,000.00
-
BAHAN SALURAN AIR KOTOR / BERSIH -
1 Buis Beton 1/2 dia 20 cm 20 cm (1 m') m1 68,000.00
2 Buis Beton dia 20 cm m1 110,000.00
-
BAHAN LOGAM DAN BAHAN JADINYA -
1 Besi Beton kg 13,000.00
2 Kawat Beton kg 25,000.00
3 Besi Hollow 20x40 Galvalum t=0.35 mm (20x40, P= 4 m) btg 18,000.00
4 Besi Hollow 40x40 Galvalum t=0.35 mm (40x40, P= 4 m) btg 22,000.00
5 Besi Siku L. 30x30x3 btg 116,000.00
6 Besi Plat Strip 3 x 30mm x 6 m btg 69,000.00
7 Seng Plat BJLS 30, lebar 90cm tebal 0,30mm, Lebar 90 cm m1 71,000.00
8 Kawat Las bh 1,500.00
9 Pagar BRC + Tiang 2" Galvanize 1,20 x 2,40 dia 8 lembar 575,000.00
10 Bondek / Floordeck Galvalume 6 x 1 x 0,75 lembar 600,000.00
-
KUSEN -
1 Kusen Alumunium Natural 4" YKK 1.3 mm t = 1,3 mm (4") m1 155,000.00
2 Kusen Alumunium Natural 4" Alexindo 1.3 mm t = 1,3 mm (4") m1 100,000.00
3 Profil Alumunium Natural 6 cm m1 45,000.00
4 Profil Alumunium Natural 8 cm m1 60,000.00
5 Jalusi Alumunium m1 55,000.00
6 Spandrel Alumunium lebar 8 cm, panjang 6 m batang 175,000.00
7 Handle Alumunium buah 160,000.00
8 Handle Jendela Alumunium buah 20,000.00
9 Pintu PVC buah 400,000.00
No Bahan / Material Spesifikasi Bahan Satuan Harga
SEWA ALAT -
No Bahan / Material Spesifikasi Bahan Satuan Harga
4 H.4. Lantai Keramik 20x20 Corak Anti Slip (Bahan dan Merk Sesuai RKS) 198,600.00
5 H.5. Dinding Keramik 20x25 Corak (Bahan dan Merk Sesuai RKS) 342,600.00
6 H.5.Hit-a Dinding Granite 30x60 Corak (Bahan dan Merk Sesuai RKS) 492,600.00
7 H.6. Dinding keramik 10cm x 20cm Corak setara Mulia 335,500.00
8 H.7. Dinding Batu Tempel Hitam 273,200.00
9 H.8. Paving Block Natural 8cm 330,700.00
10 H.9. Paving Block Warna 8cm 373,100.00
11 H.10. Paving Block Natural 6cm 300,500.00
12 H.11. Paving Block Warna 6cm 342,800.00
13 H.11.Hit-a Pemasangan Paving Block Existing 103,600.00
1 O.1. Kusen Partisi Alm 2,20x1,60 m, Daun Multiplek 9 mm + Rangka Alumunium 2,089,100.00
2 O.1.Hit-a Daun Partisi Multiplek 9 mm, Rangka Alumunium 1,211,300.00
3 O.2. Kusen Jendela Alumunium 0,70 x 1,60 m (1 lubang dgn 1 Daun Jendela) 1,198,600.00
4 O.3. Kusen Jendela Alumunium 1,35 x 1,60 m (2 lubang dgn 1 Daun Jendela) 1,698,900.00
5 O.3.Hit-a Kusen Jendela Sliding Alumunium 1,35 x 1,60 m (2 lubang 2 daun) 1,746,500.00
6 O.4. Kusen Jendela Alumunium 2,00 x 1,60 m (3 lubang dgn 2 Daun Jendela) 2,453,500.00
7 O.4.Hit-a Kusen Jendela Sliding Alumunium 2,00 x 1,60 m (3 lubang 2 Daun) 2,206,900.00
8 O.5. Kusen Jendela Alumunium 2,65 x 1,60 m (4 lubang dgn 2 Daun Jendela) 2,953,800.00
9 O.5.Hit-a Kusen Jendela Sliding Alumunium 2,65 x 1,60 m (4 lubang 2 Daun) 2,707,200.00
10 O.6. Kusen Bouvenligh Alumunium 0,70 x 0,70 m (1 lubang) 542,300.00
11 O.7. Kusen Bouvenligh Alumunium 1,35 x 0,70 m (2 lubang) 815,200.00
12 O.8. Kusen Bouvenligh Alumunium 2,00 x 0,70 m (3 lubang) 1,123,700.00
13 O.9. Kusen Bouvenligh Alumunium 2,65 x 0,70 m (4 lubang) 1,389,200.00
14 O.10. Kusen Alumunium Sopi - sopi 1,279,600.00
15 O.11. Kusen Pintu Alumunium 0,9 x 2,8 m (Daun Pintu Panel Multyplek 9mm) 2,024,800.00
16 O.11.Hit-a Kusen Pintu Alumunium 0,9 x 2,8 m (Daun Pintu Panel Spandrel Alumunium) 2,527,300.00
17 O.11.Hit-b Pemasangan Daun Pintu Alumunium (Daun Pintu Panel Multyplek 9mm) 999,700.00
18 O.11.Hit-c Kusen Pintu Alumunium 0,9 x 2,0 m (Daun Pintu Panel Multyplek 9mm) 1,680,300.00
19 O.12. Kusen Pintu Alumunium 1,7 x 2,8 m (Daun Pintu Panel Multyplek Lapis HPL) 3,842,700.00
20 O.12.Hit-a Kusen Pintu Alumunium 1,7 x 2,8 m (Daun Pintu Panel Multyplek) 3,481,900.00
21 O.12.Hit-b Kusen Pintu Alumunium 1,5 x 2,60 m (Daun Pintu Panel Multyplek Lapis HPL) 3,680,924.92
22 O.13. Kusen Pintu & Jendela Alm 1,55 x 2,80 m (1 lb. Pintu + 1 lb. Jendela Mati) 2,719,500.00
23 O.14. Kusen Pintu & Jendela Alm 2,20 x 2,80 m (1 lb. Pintu + 2 lb. 1 Daun Jendela) 3,475,400.00
24 O.14.Hit-a Kusen Pintu & Jendela Sliding Alm 2,20 x 2,80 m (1 lb. Pintu + 2 lb 2 Daun) 3,483,100.00
25 O.15. Kusen Pintu & Jendela Alm 2,85 x 2,80 m (1 lb. Pintu + 3 lb. 2 Daun Jendela) 4,301,100.00
26 O.15.Hit-a Kusen Pintu & Jendela Sliding Alm 2,85 x 2,80 m (1 lb. Pintu + 3 lb. 2 Daun) 4,054,500.00
27 O.16. Penambahan & Pemasangan Kembali Kusen Alumunium Existing 345,700.00
28 O.17. Pemasangan Kembali Kusen Alumunium Existing 206,100.00
Jumlah Alat
Jumlah Harga
C PERALATAN
Jumlah Alat
Jumlah Alat
Jumlah Harga
C PERALATAN
Jumlah Alat
Jumlah Harga
C PERALATAN
Jumlah Alat
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
Jumlah Bahan
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 64,665.00
E OVERHEAD & PROFIT 10% x D 6,466.50
F JUMLAH HARGA PEKERJAAN (D+E) 71,131.50
G PEMBULATAN 71,200.00
Jumlah Bahan
C PERALATAN
Stemper Jam 0.486 42,400.00 20,606.40
Jumlah Alat
D JUMLAH (A+B+C) 85,271.40
E OVERHEAD & PROFIT 10% x D 8,527.14
F JUMLAH HARGA PEKERJAAN (D+E) 93,798.54
G PEMBULATAN 93,800.00
Jenis Pekerjaan : Urugan Pasir
Satuan : 1 m3
Kode : B.10.
Jumlah Alat
D JUMLAH (A+B+C) 275,793.00
E OVERHEAD & PROFIT 10% x D 27,579.30
F JUMLAH HARGA PEKERJAAN (D+E) 303,372.30
G PEMBULATAN 303,400.00
Jumlah Alat
D JUMLAH (A+B+C) 160,399.50
E OVERHEAD & PROFIT 10% x D 16,039.95
F JUMLAH HARGA PEKERJAAN (D+E) 176,439.45
G PEMBULATAN 176,500.00
Jumlah Alat
D JUMLAH (A+B+C) 272,332.50
E OVERHEAD & PROFIT 10% x D 27,233.25
F JUMLAH HARGA PEKERJAAN (D+E) 299,565.75
G PEMBULATAN 299,600.00
Jumlah Alat
Jumlah Alat
D JUMLAH (A+B+C) 81,607.50
E OVERHEAD & PROFIT 10% x D 8,160.75
F JUMLAH HARGA PEKERJAAN (D+E) 89,768.25
G PEMBULATAN 89,800.00
Jumlah Alat
D JUMLAH (A+B+C) 37,747.20
E OVERHEAD & PROFIT 10% x D 3,774.72
F JUMLAH HARGA PEKERJAAN (D+E) 41,521.92
G PEMBULATAN 41,600.00
Jumlah Alat
Jumlah Alat
Jumlah Alat
D JUMLAH (A+B+C) 953,695.00
E OVERHEAD & PROFIT 10% x D 95,369.50
F JUMLAH HARGA PEKERJAAN (D+E) 1,049,064.50
G PEMBULATAN 1,049,100.00
Jumlah Alat
D JUMLAH (A+B+C) 925,795.00
E OVERHEAD & PROFIT 10% x D 92,579.50
F JUMLAH HARGA PEKERJAAN (D+E) 1,018,374.50
G PEMBULATAN 1,018,400.00
Jumlah Alat
JENIS PEKERJAAN : Pondasi Siklop 60% Beton 1:2:3 dan 40 % Batu Belah
SATUAN : 1 m3
KODE : C.5.
Jumlah Alat
Jumlah Alat
Jumlah Alat
D JUMLAH (A+B+C) 193,615.60
E OVERHEAD & PROFIT 10% x D 19,361.56
F JUMLAH HARGA PEKERJAAN (D+E) 212,977.16
G PEMBULATAN 213,000.00
Jumlah Alat
D JUMLAH (A+B+C) 204,115.60
E OVERHEAD & PROFIT 10% x D 20,411.56
F JUMLAH HARGA PEKERJAAN (D+E) 224,527.16
G PEMBULATAN 224,600.00
Jumlah Alat
D JUMLAH (A+B+C) 341,429.80
E OVERHEAD & PROFIT 10% x D 34,142.98
F JUMLAH HARGA PEKERJAAN (D+E) 375,572.78
G PEMBULATAN 375,600.00
Jumlah Alat
D JUMLAH (A+B+C) 347,729.80
E OVERHEAD & PROFIT 10% x D 34,772.98
F JUMLAH HARGA PEKERJAAN (D+E) 382,502.78
G PEMBULATAN 382,600.00
Jumlah Alat
D JUMLAH (A+B+C) 401,429.80
E OVERHEAD & PROFIT 10% x D 40,142.98
F JUMLAH HARGA PEKERJAAN (D+E) 441,572.78
G PEMBULATAN 441,600.00
Jumlah Alat
D JUMLAH (A+B+C) 345,929.80
E OVERHEAD & PROFIT 10% x D 34,592.98
F JUMLAH HARGA PEKERJAAN (D+E) 380,522.78
G PEMBULATAN 380,600.00
Jumlah Alat
D JUMLAH (A+B+C) 317,709.80
E OVERHEAD & PROFIT 10% x D 31,770.98
F JUMLAH HARGA PEKERJAAN (D+E) 349,480.78
G PEMBULATAN 349,500.00
E. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
Jumlah Alat -
D JUMLAH (A+B+C) 1,137.12
E OVERHEAD & PROFIT 10% x D 113.71
F JUMLAH HARGA PEKERJAAN (D+E) 1,250.83
G PEMBULATAN 1,300.00
Jumlah Alat -
D JUMLAH (A+B+C) 426,109.40
E OVERHEAD & PROFIT 10% x D 42,610.94
F JUMLAH HARGA PEKERJAAN (D+E) 468,720.34
G PEMBULATAN 468,800.00
Jumlah Alat -
D JUMLAH (A+B+C) 375,924.50
E OVERHEAD & PROFIT 10% x D 37,592.45
F JUMLAH HARGA PEKERJAAN (D+E) 413,516.95
G PEMBULATAN 413,600.00
JENIS PEKERJAAN : Pemasangan Kusen Alumunium
SATUAN : 1 Unit
KODE : E.4.
Jumlah Alat
D JUMLAH (A+B+C) 32,640.02
E OVERHEAD & PROFIT 10% x D 3,264.00
F JUMLAH HARGA PEKERJAAN (D+E) 35,904.02
G PEMBULATAN 36,000.00
Jumlah Alat
D JUMLAH (A+B+C) 118,919.45
E OVERHEAD & PROFIT 10% x D 11,891.95
F JUMLAH HARGA PEKERJAAN (D+E) 130,811.40
G PEMBULATAN 130,900.00
Jumlah Alat
D JUMLAH (A+B+C) 165,246.30
E OVERHEAD & PROFIT 10% x D 16,524.63
F JUMLAH HARGA PEKERJAAN (D+E) 181,770.93
G PEMBULATAN 181,800.00
D. HARGA SATUAN PEKERJAAN BETON
Jumlah Alat
D JUMLAH (A+B+C) 989,833.80
E OVERHEAD & PROFIT 10% x D 98,983.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,088,817.18
G PEMBULATAN 1,088,900.00
Jumlah Alat
D JUMLAH (A+B+C) 1,021,533.80
E OVERHEAD & PROFIT 10% x D 102,153.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,123,687.18
G PEMBULATAN 1,123,700.00
Jumlah Alat
D JUMLAH (A+B+C) 1,046,333.80
E OVERHEAD & PROFIT 10% x D 104,633.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,150,967.18
G PEMBULATAN 1,151,000.00
Jumlah Alat
D JUMLAH (A+B+C) 1,070,303.80
E OVERHEAD & PROFIT 10% x D 107,030.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,177,334.18
G PEMBULATAN 1,177,400.00
Jumlah Alat
D JUMLAH (A+B+C) 1,097,863.80
E OVERHEAD & PROFIT 10% x D 109,786.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,207,650.18
G PEMBULATAN 1,207,700.00
Jumlah Alat
D JUMLAH (A+B+C) 1,115,513.80
E OVERHEAD & PROFIT 10% x D 111,551.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,227,065.18
G PEMBULATAN 1,227,100.00
Jumlah Alat
D JUMLAH (A+B+C) 1,138,833.80
E OVERHEAD & PROFIT 10% x D 113,883.38
F JUMLAH HARGA PEKERJAAN (D+E) 1,252,717.18
G PEMBULATAN 1,252,800.00
Jumlah Alat
D JUMLAH (A+B+C) 912,364.00
E OVERHEAD & PROFIT 10% x D 91,236.40
F JUMLAH HARGA PEKERJAAN (D+E) 1,003,600.40
G PEMBULATAN 1,003,700.00
Jumlah Alat
D JUMLAH (A+B+C) 158,472.30
E OVERHEAD & PROFIT 10% x D 15,847.23
F JUMLAH HARGA PEKERJAAN (D+E) 174,319.53
G PEMBULATAN 174,400.00
Jumlah Alat
D JUMLAH (A+B+C) 15,847.23
E OVERHEAD & PROFIT 10% x D 1,584.72
F JUMLAH HARGA PEKERJAAN (D+E) 17,431.95
G PEMBULATAN 17,500.00
Jumlah Alat
D JUMLAH (A+B+C) 4,289,422.60
E OVERHEAD & PROFIT 10% x D 428,942.26
F JUMLAH HARGA PEKERJAAN (D+E) 4,718,364.86
G PEMBULATAN 4,718,400.00
Jumlah Alat
D JUMLAH (A+B+C) 4,334,632.60
E OVERHEAD & PROFIT 10% x D 433,463.26
F JUMLAH HARGA PEKERJAAN (D+E) 4,768,095.86
G PEMBULATAN 4,768,100.00
Jumlah Alat
D JUMLAH (A+B+C) 5,237,645.30
E OVERHEAD & PROFIT 10% x D 523,764.53
F JUMLAH HARGA PEKERJAAN (D+E) 5,761,409.83
G PEMBULATAN 5,761,500.00
Jumlah Alat
D JUMLAH (A+B+C) 5,273,008.40
E OVERHEAD & PROFIT 10% x D 527,300.84
F JUMLAH HARGA PEKERJAAN (D+E) 5,800,309.24
G PEMBULATAN 5,800,400.00
Jumlah Alat
D JUMLAH (A+B+C) 5,026,288.40
E OVERHEAD & PROFIT 10% x D 502,628.84
F JUMLAH HARGA PEKERJAAN (D+E) 5,528,917.24
G PEMBULATAN 5,529,000.00
Jumlah Alat
D JUMLAH (A+B+C) 5,874,008.40
E OVERHEAD & PROFIT 10% x D 587,400.84
F JUMLAH HARGA PEKERJAAN (D+E) 6,461,409.24
G PEMBULATAN 6,461,500.00
Jumlah Alat
D JUMLAH (A+B+C) 5,900,288.40
E OVERHEAD & PROFIT 10% x D 590,028.84
F JUMLAH HARGA PEKERJAAN (D+E) 6,490,317.24
G PEMBULATAN 6,490,400.00
Jumlah Alat
D JUMLAH (A+B+C) 6,383,048.20
E OVERHEAD & PROFIT 10% x D 638,304.82
F JUMLAH HARGA PEKERJAAN (D+E) 7,021,353.02
G PEMBULATAN 7,021,400.00
Jumlah Alat
D JUMLAH (A+B+C) 5,834,087.30
E OVERHEAD & PROFIT 10% x D 583,408.73
F JUMLAH HARGA PEKERJAAN (D+E) 6,417,496.03
G PEMBULATAN 6,417,500.00
Jumlah Alat
D JUMLAH (A+B+C) 5,430,920.50
E OVERHEAD & PROFIT 10% x D 543,092.05
F JUMLAH HARGA PEKERJAAN (D+E) 5,974,012.55
G PEMBULATAN 5,974,100.00
Jumlah Alat
D JUMLAH (A+B+C) 6,013,218.30
E OVERHEAD & PROFIT 10% x D 601,321.83
F JUMLAH HARGA PEKERJAAN (D+E) 6,614,540.13
G PEMBULATAN 6,614,600.00
Jumlah Alat
D JUMLAH (A+B+C) 6,026,498.30
E OVERHEAD & PROFIT 10% x D 602,649.83
F JUMLAH HARGA PEKERJAAN (D+E) 6,629,148.13
G PEMBULATAN 6,629,200.00
JENIS PEKERJAAN : Kolom 20x20 (140 kg Besi + Bekisting) K-175
SATUAN : 1 m3
KODE : D.19.
Jumlah Alat
D JUMLAH (A+B+C) 5,090,218.30
E OVERHEAD & PROFIT 10% x D 509,021.83
F JUMLAH HARGA PEKERJAAN (D+E) 5,599,240.13
G PEMBULATAN 5,599,300.00
Jumlah Alat
D JUMLAH (A+B+C) 5,340,009.80
E OVERHEAD & PROFIT 10% x D 534,000.98
F JUMLAH HARGA PEKERJAAN (D+E) 5,874,010.78
G PEMBULATAN 5,874,100.00
Jumlah Alat
D JUMLAH (A+B+C) 5,366,289.80
E OVERHEAD & PROFIT 10% x D 536,628.98
F JUMLAH HARGA PEKERJAAN (D+E) 5,902,918.78
G PEMBULATAN 5,903,000.00
JENIS PEKERJAAN : Balok Topi Beton 12x15 (215 kg Besi + Bekisting) K-175
SATUAN : 1 m3
KODE : D.22.
Jumlah Alat
D JUMLAH (A+B+C) 6,124,647.60
E OVERHEAD & PROFIT 10% x D 612,464.76
F JUMLAH HARGA PEKERJAAN (D+E) 6,737,112.36
G PEMBULATAN 6,737,200.00
Jumlah Alat
D JUMLAH (A+B+C) 5,777,776.30
E OVERHEAD & PROFIT 10% x D 577,777.63
F JUMLAH HARGA PEKERJAAN (D+E) 6,355,553.93
G PEMBULATAN 6,355,600.00
Jumlah Alat
D JUMLAH (A+B+C) 5,322,776.30
E OVERHEAD & PROFIT 10% x D 532,277.63
F JUMLAH HARGA PEKERJAAN (D+E) 5,855,053.93
G PEMBULATAN 5,855,100.00
Jumlah Alat
D JUMLAH (A+B+C) 5,895,276.30
E OVERHEAD & PROFIT 10% x D 589,527.63
F JUMLAH HARGA PEKERJAAN (D+E) 6,484,803.93
G PEMBULATAN 6,484,900.00
Jumlah Alat
D JUMLAH (A+B+C) 5,844,573.50
E OVERHEAD & PROFIT 10% x D 584,457.35
F JUMLAH HARGA PEKERJAAN (D+E) 6,429,030.85
G PEMBULATAN 6,429,100.00
Jumlah Alat
D JUMLAH (A+B+C) 5,799,363.50
E OVERHEAD & PROFIT 10% x D 579,936.35
F JUMLAH HARGA PEKERJAAN (D+E) 6,379,299.85
G PEMBULATAN 6,379,300.00
Jumlah Alat
D JUMLAH (A+B+C) 5,151,418.50
E OVERHEAD & PROFIT 10% x D 515,141.85
F JUMLAH HARGA PEKERJAAN (D+E) 5,666,560.35
G PEMBULATAN 5,666,600.00
JENIS PEKERJAAN : Plat Beton tb. 12cm (110 kg Besi + Bekisting) K-225
SATUAN : 1 m3
KODE : D.28.
Jumlah Alat
D JUMLAH (A+B+C) 4,441,932.50
E OVERHEAD & PROFIT 10% x D 444,193.25
F JUMLAH HARGA PEKERJAAN (D+E) 4,886,125.75
G PEMBULATAN 4,886,200.00
JENIS PEKERJAAN : Plat Beton tb. 12cm (110 kg Besi + Bekisting Bondek) K-225
SATUAN : 1 m3
KODE : D.28.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 4,537,032.50
E OVERHEAD & PROFIT 10% x D 453,703.25
F JUMLAH HARGA PEKERJAAN (D+E) 4,990,735.75
G PEMBULATAN 4,990,800.00
JENIS PEKERJAAN : Plat Beton tb. 12cm (110 kg Besi + Bekisting) K-175
SATUAN : 1 m3
KODE : D.28.Hit-b
Jumlah Alat
D JUMLAH (A+B+C) 4,378,252.50
E OVERHEAD & PROFIT 10% x D 437,825.25
F JUMLAH HARGA PEKERJAAN (D+E) 4,816,077.75
G PEMBULATAN 4,816,100.00
JENIS PEKERJAAN : Plat Beton tb. 8cm (50 kg besi + Bekisting) K-175
SATUAN : 1 m3
KODE : D.29.
Jumlah Alat
D JUMLAH (A+B+C) 3,115,501.50
E OVERHEAD & PROFIT 10% x D 311,550.15
F JUMLAH HARGA PEKERJAAN (D+E) 3,427,051.65
G PEMBULATAN 3,427,100.00
JENIS PEKERJAAN : Plat Beton tb. 8cm (50 kg besi + Bekisting) K-225
SATUAN : 1 m3
KODE : D.29.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 3,141,781.50
E OVERHEAD & PROFIT 10% x D 314,178.15
F JUMLAH HARGA PEKERJAAN (D+E) 3,455,959.65
G PEMBULATAN 3,456,000.00
Jumlah Alat
D JUMLAH (A+B+C) 5,075,752.60
E OVERHEAD & PROFIT 10% x D 507,575.26
F JUMLAH HARGA PEKERJAAN (D+E) 5,583,327.86
G PEMBULATAN 5,583,400.00
Jumlah Alat
D JUMLAH (A+B+C) 5,489,245.30
E OVERHEAD & PROFIT 10% x D 548,924.53
F JUMLAH HARGA PEKERJAAN (D+E) 6,038,169.83
G PEMBULATAN 6,038,200.00
F. HARGA SATUAN PEKERJAAN DINDING
Jumlah Alat
D JUMLAH (A+B+C) 296,710.00
E OVERHEAD & PROFIT 10% x D 29,671.00
F JUMLAH HARGA PEKERJAAN (D+E) 326,381.00
G PEMBULATAN 326,400.00
Jumlah Alat
D JUMLAH (A+B+C) 286,035.00
E OVERHEAD & PROFIT 10% x D 28,603.50
F JUMLAH HARGA PEKERJAAN (D+E) 314,638.50
G PEMBULATAN 314,700.00
Jumlah Alat
D JUMLAH (A+B+C) 143,968.50
E OVERHEAD & PROFIT 10% x D 14,396.85
F JUMLAH HARGA PEKERJAAN (D+E) 158,365.35
G PEMBULATAN 158,400.00
Jumlah Alat
D JUMLAH (A+B+C) 139,371.50
E OVERHEAD & PROFIT 10% x D 13,937.15
F JUMLAH HARGA PEKERJAAN (D+E) 153,308.65
G PEMBULATAN 153,400.00
JENIS PEKERJAAN : Dinding Partisi Double GRC 4mm + Rangka Baja Ringan
SATUAN : 1 m2
KODE : F.5.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang Batu L.02 OH 0.6000 123,300.00 73,980.00
Kepala Tukang L.03 OH 0.0600 141,300.00 8,478.00
Mandor L.04 OH 0.0100 150,300.00 1,503.00
Jumlah Tenaga 106,821.00
B BAHAN
Baja Ringan (Main Truss C 75 tb. 0,75 mm) m1 5.5000 12,500.00 68,750.00
GRC Lembar 0.8600 72,000.00 61,920.00
Screw GRC Kg 0.1500 75,000.00 11,250.00
Assesories 10% % 0.1000 130,670.00 13,067.00
Jumlah Bahan 154,987.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 261,808.00
E OVERHEAD & PROFIT 10% x D 26,180.80
F JUMLAH HARGA PEKERJAAN (D+E) 287,988.80
G PEMBULATAN 288,000.00
G. HARGA SATUAN PEKERJAAN PLESTERAN
Jumlah Alat
D JUMLAH (A+B+C) 74,167.80
E OVERHEAD & PROFIT 10% x D 7,416.78
F JUMLAH HARGA PEKERJAAN (D+E) 81,584.58
G PEMBULATAN 81,600.00
Jumlah Alat
D JUMLAH (A+B+C) 71,698.20
E OVERHEAD & PROFIT 10% x D 7,169.82
F JUMLAH HARGA PEKERJAAN (D+E) 78,868.02
G PEMBULATAN 78,900.00
Jumlah Alat
D JUMLAH (A+B+C) 81,936.30
E OVERHEAD & PROFIT 10% x D 8,193.63
F JUMLAH HARGA PEKERJAAN (D+E) 90,129.93
G PEMBULATAN 90,200.00
Jumlah Alat
D JUMLAH (A+B+C) 95,998.20
E OVERHEAD & PROFIT 10% x D 9,599.82
F JUMLAH HARGA PEKERJAAN (D+E) 105,598.02
G PEMBULATAN 105,600.00
Jumlah Alat
D JUMLAH (A+B+C) 69,267.20
E OVERHEAD & PROFIT 10% x D 6,926.72
F JUMLAH HARGA PEKERJAAN (D+E) 76,193.92
G PEMBULATAN 76,200.00
Jumlah Alat
Jumlah Alat
D JUMLAH (A+B+C) 69,001.00
E OVERHEAD & PROFIT 10% x D 6,900.10
F JUMLAH HARGA PEKERJAAN (D+E) 75,901.10
G PEMBULATAN 76,000.00
Jumlah Alat
D JUMLAH (A+B+C) 42,331.00
E OVERHEAD & PROFIT 10% x D 4,233.10
F JUMLAH HARGA PEKERJAAN (D+E) 46,564.10
G PEMBULATAN 46,600.00
H. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING
JENIS PEKERJAAN : Lantai Keramik 30x30 Polos (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.1.
Jumlah Alat
D JUMLAH (A+B+C) 155,537.80
E OVERHEAD & PROFIT 10% x D 15,553.78
F JUMLAH HARGA PEKERJAAN (D+E) 171,091.58
G PEMBULATAN 171,100.00
JENIS PEKERJAAN : Lantai Keramik 30x30 Corak Anti Slip (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.2.
Jumlah Alat
D JUMLAH (A+B+C) 166,537.80
E OVERHEAD & PROFIT 10% x D 16,653.78
F JUMLAH HARGA PEKERJAAN (D+E) 183,191.58
G PEMBULATAN 183,200.00
JENIS PEKERJAAN : Lantai Keramik 40x40 Polos (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.3.
Jumlah Alat
D JUMLAH (A+B+C) 171,518.30
E OVERHEAD & PROFIT 10% x D 17,151.83
F JUMLAH HARGA PEKERJAAN (D+E) 188,670.13
G PEMBULATAN 188,700.00
JENIS PEKERJAAN : Lantai Keramik 20x20 Corak Anti Slip (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.4.
Jumlah Alat
JENIS PEKERJAAN : Dinding Keramik 20x25 Corak (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.5.
Jumlah Alat
D JUMLAH (A+B+C) 311,367.00
E OVERHEAD & PROFIT 10% x D 31,136.70
F JUMLAH HARGA PEKERJAAN (D+E) 342,503.70
G PEMBULATAN 342,600.00
JENIS PEKERJAAN : Dinding Granite 30x60 Corak (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.5.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 447,767.00
E OVERHEAD & PROFIT 10% x D 44,776.70
F JUMLAH HARGA PEKERJAAN (D+E) 492,543.70
G PEMBULATAN 492,600.00
JENIS PEKERJAAN : Dinding Keramik 10x20 Corak (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : H.6.
Jumlah Alat
D JUMLAH (A+B+C) 304,977.00
E OVERHEAD & PROFIT 10% x D 30,497.70
F JUMLAH HARGA PEKERJAAN (D+E) 335,474.70
G PEMBULATAN 335,500.00
Jumlah Alat
D JUMLAH (A+B+C) 248,356.00
E OVERHEAD & PROFIT 10% x D 24,835.60
F JUMLAH HARGA PEKERJAAN (D+E) 273,191.60
G PEMBULATAN 273,200.00
Jumlah Alat
D JUMLAH (A+B+C) 300,633.25
E OVERHEAD & PROFIT 10% x D 30,063.33
F JUMLAH HARGA PEKERJAAN (D+E) 330,696.58
G PEMBULATAN 330,700.00
Jumlah Alat
D JUMLAH (A+B+C) 339,133.25
E OVERHEAD & PROFIT 10% x D 33,913.33
F JUMLAH HARGA PEKERJAAN (D+E) 373,046.58
G PEMBULATAN 373,100.00
Jumlah Alat
D JUMLAH (A+B+C) 273,133.25
E OVERHEAD & PROFIT 10% x D 27,313.33
F JUMLAH HARGA PEKERJAAN (D+E) 300,446.58
G PEMBULATAN 300,500.00
Jumlah Alat
D JUMLAH (A+B+C) 311,633.25
E OVERHEAD & PROFIT 10% x D 31,163.33
F JUMLAH HARGA PEKERJAAN (D+E) 342,796.58
G PEMBULATAN 342,800.00
JENIS PEKERJAAN : Plafond Gypsum (Bahan dan Merk Sesuai RKS)+ Rangka Kayu
SATUAN : 1 m2
KODE : I.1.
Jumlah Alat
D JUMLAH (A+B+C) 184,062.05
E OVERHEAD & PROFIT 10% x D 18,406.21
F JUMLAH HARGA PEKERJAAN (D+E) 202,468.26
G PEMBULATAN 202,500.00
JENIS PEKERJAAN : Plafond Gypsum (Bahan dan Merk Sesuai RKS) + Rangka Hollow
SATUAN : 1 m2
KODE : I.2.
Jumlah Alat
D JUMLAH (A+B+C) 99,161.00
E OVERHEAD & PROFIT 10% x D 9,916.10
F JUMLAH HARGA PEKERJAAN (D+E) 109,077.10
G PEMBULATAN 109,100.00
JENIS PEKERJAAN : Plafond GRC tebal 4mm (Bahan dan Merk Sesuai RKS) + Rangka Kayu
SATUAN : 1 m2
KODE : I.3.
Jumlah Alat
D JUMLAH (A+B+C) 195,440.05
E OVERHEAD & PROFIT 10% x D 19,544.01
F JUMLAH HARGA PEKERJAAN (D+E) 214,984.06
G PEMBULATAN 215,000.00
JENIS PEKERJAAN : Plafond GRC tebal 4mm (Bahan dan Merk Sesuai RKS) + Rangka Hollow
SATUAN : 1 m2
KODE : I.4.
Jumlah Alat
D JUMLAH (A+B+C) 98,069.00
E OVERHEAD & PROFIT 10% x D 9,806.90
F JUMLAH HARGA PEKERJAAN (D+E) 107,875.90
G PEMBULATAN 107,900.00
JENIS PEKERJAAN : Plafond PVC tebal 9mm + List (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : I.5.
Jumlah Alat
D JUMLAH (A+B+C) 57,158.50
E OVERHEAD & PROFIT 10% x D 5,715.85
F JUMLAH HARGA PEKERJAAN (D+E) 62,874.35
G PEMBULATAN 62,900.00
Jumlah Alat
D JUMLAH (A+B+C) 18,487.40
E OVERHEAD & PROFIT 10% x D 1,848.74
F JUMLAH HARGA PEKERJAAN (D+E) 20,336.14
G PEMBULATAN 20,400.00
Jumlah Alat
D JUMLAH (A+B+C) 39,457.40
E OVERHEAD & PROFIT 10% x D 3,945.74
F JUMLAH HARGA PEKERJAAN (D+E) 43,403.14
G PEMBULATAN 43,500.00
Jumlah Alat
D JUMLAH (A+B+C) 28,907.40
E OVERHEAD & PROFIT 10% x D 2,890.74
F JUMLAH HARGA PEKERJAAN (D+E) 31,798.14
G PEMBULATAN 31,800.00
Jumlah Alat
D JUMLAH (A+B+C) 84,359.10
E OVERHEAD & PROFIT 10% x D 8,435.91
F JUMLAH HARGA PEKERJAAN (D+E) 92,795.01
G PEMBULATAN 92,800.00
Jumlah Alat
D JUMLAH (A+B+C) 84,359.10
E OVERHEAD & PROFIT 10% x D 8,435.91
F JUMLAH HARGA PEKERJAAN (D+E) 92,795.01
G PEMBULATAN 92,800.00
J. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Tukang Kayu L.03 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.11 OH 0.0075 141,300.00 1,059.75
Mandor L.15 OH 0.0080 150,300.00 1,202.40
Jumlah Tenaga 28,654.65
B BAHAN
Genteng palentong Bh 25.0000 3,000.00 75,000.00
Jumlah Bahan 75,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 103,654.65
E OVERHEAD & PROFIT 10% x D 10,365.47
F JUMLAH HARGA PEKERJAAN (D+E) 114,020.12
G PEMBULATAN 114,100.00
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Tukang Kayu L.03 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.11 OH 0.0080 141,300.00 1,130.40
Mandor L.15 OH 0.0080 150,300.00 1,202.40
Jumlah Tenaga 28,725.30
B BAHAN
Genteng Murando Natural Bh 18.0000 5,000.00 90,000.00
Jumlah Bahan 90,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 118,725.30
E OVERHEAD & PROFIT 10% x D 11,872.53
F JUMLAH HARGA PEKERJAAN (D+E) 130,597.83
G PEMBULATAN 130,600.00
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Tukang Kayu L.03 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.11 OH 0.0080 141,300.00 1,130.40
Mandor L.15 OH 0.0080 150,300.00 1,202.40
Jumlah Tenaga 28,725.30
B BAHAN
Genteng Murando Glazur Bh 18.0000 6,000.00 108,000.00
Jumlah Bahan 108,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 136,725.30
E OVERHEAD & PROFIT 10% x D 13,672.53
F JUMLAH HARGA PEKERJAAN (D+E) 150,397.83
G PEMBULATAN 150,400.00
JENIS PEKERJAAN : Atap Metal Roof Berpasir (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.4.
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang Kayu L.03 OH 0.1000 123,300.00 12,330.00
Kepala tukang L.11 OH 0.0100 141,300.00 1,413.00
Mandor L.15 OH 0.0010 150,300.00 150.30
Jumlah Tenaga 36,753.30
B BAHAN
Genteng metal Berpasir lembar 1.3000 65,000.00 84,500.00
Sekrup 1 - 3 cm Kg 0.0250 75,000.00 1,875.00
Jumlah Bahan 86,375.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 123,128.30
E OVERHEAD & PROFIT 10% x D 12,312.83
F JUMLAH HARGA PEKERJAAN (D+E) 135,441.13
G PEMBULATAN 135,500.00
JENIS PEKERJAAN : Atap Bitumen Selulosa Shaded Red (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.5.
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang L.03 OH 0.1000 123,300.00 12,330.00
Jumlah Tenaga 35,190.00
B BAHAN
Genteng Bitumen Lembar 3.2380 56,500.00 182,947.00
Screw Atap Bitumen bh 16.1900 1,200.00 19,428.00
Jumlah Bahan 202,375.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 237,565.00
E OVERHEAD & PROFIT 10% x D 23,756.50
F JUMLAH HARGA PEKERJAAN (D+E) 261,321.50
G PEMBULATAN 261,400.00
JENIS PEKERJAAN : Atap Bitumen Bergelombang Memanjang Shaded Red (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.5.Hit-a
A TENAGA
Pekerja L.01 OH 0.1400 114,300.00 16,002.00
Tukang L.03 OH 0.0700 123,300.00 8,631.00
Jumlah Tenaga 24,633.00
B BAHAN
Genteng Bitumen Memanjang Lembar 0.7230 155,000.00 112,065.00
Screw Atap Bitumen bh 11.7650 1,200.00 14,118.00
Jumlah Bahan 126,183.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 150,816.00
E OVERHEAD & PROFIT 10% x D 15,081.60
F JUMLAH HARGA PEKERJAAN (D+E) 165,897.60
G PEMBULATAN 165,900.00
JENIS PEKERJAAN : Atap U-PVC tebal 12mm Merah Maroon (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.6.
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang L.03 OH 0.1000 123,300.00 12,330.00
Jumlah Tenaga 35,190.00
B BAHAN
Genteng U-PVC m2 m2 1.0000 180,000.00 180,000.00
Screw Atap U-PVC bh 10.0000 2,500.00 25,000.00
Jumlah Bahan 205,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 240,190.00
E OVERHEAD & PROFIT 10% x D 24,019.00
F JUMLAH HARGA PEKERJAAN (D+E) 264,209.00
G PEMBULATAN 264,300.00
A TENAGA
Pekerja L.01 OH 0.4000 114,300.00 45,720.00
Tukang Kayu L.03 OH 0.2000 123,300.00 24,660.00
Kepala tukang L.11 OH 0.0200 141,300.00 2,826.00
Mandor L.15 OH 0.0020 150,300.00 300.60
Jumlah Tenaga 73,506.60
B BAHAN
Bubungan genteng palentong Bh 5.0000 10,000.00 50,000.00
Semen Portland Kg 8.0000 1,300.00 10,400.00
Pasir pasang M3 0.0320 300,000.00 9,600.00
Jumlah Bahan 70,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 143,506.60
E OVERHEAD & PROFIT 10% x D 14,350.66
F JUMLAH HARGA PEKERJAAN (D+E) 157,857.26
G PEMBULATAN 157,900.00
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Tukang Kayu L.03 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.11 OH 0.0080 141,300.00 1,130.40
Mandor L.15 OH 0.0080 150,300.00 1,202.40
Jumlah Tenaga 28,725.30
B BAHAN
Bubungan Murando Natural Bh 5.0000 12,000.00 60,000.00
Semen Portland Kg 8.0000 1,300.00 10,400.00
Pasir pasang M3 0.0320 300,000.00 9,600.00
Jumlah Bahan 80,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 108,725.30
E OVERHEAD & PROFIT 10% x D 10,872.53
F JUMLAH HARGA PEKERJAAN (D+E) 119,597.83
G PEMBULATAN 119,600.00
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Tukang Kayu L.03 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.11 OH 0.0080 141,300.00 1,130.40
Mandor L.15 OH 0.0080 150,300.00 1,202.40
Jumlah Tenaga 28,725.30
B BAHAN
Bubungan Murando Glazur Bh 5.0000 12,000.00 60,000.00
Semen Portland Kg 8.0000 1,300.00 10,400.00
Pasir pasang M3 0.0320 300,000.00 9,600.00
Jumlah Bahan 80,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 108,725.30
E OVERHEAD & PROFIT 10% x D 10,872.53
F JUMLAH HARGA PEKERJAAN (D+E) 119,597.83
G PEMBULATAN 119,600.00
JENIS PEKERJAAN : Nok Metal Roof Berpasir (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m1
KODE : J.10.
A TENAGA
Pekerja L.01 OH 0.2500 114,300.00 28,575.00
Tukang Kayu L.03 OH 0.1500 123,300.00 18,495.00
Kepala tukang L.11 OH 0.0150 141,300.00 2,119.50
Mandor L.15 OH 0.0130 150,300.00 1,953.90
Jumlah Tenaga 51,143.40
B BAHAN
Genteng Nok Metal Berpasir Bh 1.0000 34,000.00 34,000.00
Sekrup 1 - 3 cm Kg 0.0500 75,000.00 3,750.00
Jumlah Bahan 37,750.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 88,893.40
E OVERHEAD & PROFIT 10% x D 8,889.34
F JUMLAH HARGA PEKERJAAN (D+E) 97,782.74
G PEMBULATAN 97,800.00
JENIS PEKERJAAN : Nok Bitumen Selulosa Shaded Red (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.11.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.0840 114,300.00 9,601.20
Tukang L.03 OH 0.1250 123,300.00 15,412.50
Jumlah Tenaga 25,013.70
B BAHAN
Genteng Nok Bitumen Lembar 1.2500 95,000.00 118,750.00
Screw Atap Bitumen bh 10.0000 1,200.00 12,000.00
Jumlah Bahan 130,750.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 155,763.70
E OVERHEAD & PROFIT 10% x D 15,576.37
F JUMLAH HARGA PEKERJAAN (D+E) 171,340.07
G PEMBULATAN 171,400.00
JENIS PEKERJAAN : Nok U-PVC tebal 12mm Merah Maroon (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.12.
A TENAGA
Pekerja L.01 OH 0.0840 114,300.00 9,601.20
Tukang L.03 OH 0.1250 123,300.00 15,412.50
Jumlah Tenaga 25,013.70
B BAHAN
Nok U-PVC Lembar 1.0000 99,000.00 99,000.00
Screw Atap U-PVC bh 6.0000 2,500.00 15,000.00
Jumlah Bahan 114,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 139,013.70
E OVERHEAD & PROFIT 10% x D 13,901.37
F JUMLAH HARGA PEKERJAAN (D+E) 152,915.07
G PEMBULATAN 153,000.00
A TENAGA
Pekerja L.01 OH 0.2500 114,300.00 28,575.00
Tukang Kayu L.03 OH 0.1500 123,300.00 18,495.00
Kepala tukang L.11 OH 0.0150 141,300.00 2,119.50
Mandor L.15 OH 0.0130 150,300.00 1,953.90
Jumlah Tenaga 51,143.40
B BAHAN
Genteng Nok Pinggir Morando Bh 5.0000 10,000.00 50,000.00
Paku 8 - 15 cm Kg 0.0500 17,000.00 850.00
Jumlah Bahan 50,850.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 101,993.40
E OVERHEAD & PROFIT 10% x D 10,199.34
F JUMLAH HARGA PEKERJAAN (D+E) 112,192.74
G PEMBULATAN 112,200.00
JENIS PEKERJAAN : Nok Tepi Bitumen Selulosa Shaded Red (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : J.14.
A TENAGA
Pekerja L.01 OH 0.0840 114,300.00 9,601.20
Tukang L.03 OH 0.1250 123,300.00 15,412.50
Jumlah Tenaga 25,013.70
B BAHAN
Genteng Nok Bitumen Lembar 1.0420 95,000.00 98,990.00
Screw Atap Bitumen bh 8.3360 1,200.00 10,003.20
Jumlah Bahan 108,993.20
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 134,006.90
E OVERHEAD & PROFIT 10% x D 13,400.69
F JUMLAH HARGA PEKERJAAN (D+E) 147,407.59
G PEMBULATAN 147,500.00
JENIS PEKERJAAN : Kuda-Kuda Baja Ringan (Lolos Verifikasi PUPR sesuai RKS)
SATUAN : 1 m2
KODE : J.15.
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang L.03 OH 0.1000 123,300.00 12,330.00
Jumlah Tenaga 35,190.00
B BAHAN
Baja Ringan (Main Truss C 75 tb. 0,75 mm) m1 2.8000 12,500.00 35,000.00
Reng R-35 tb. 0,45 mm m1 5.1000 5,800.00 29,580.00
Sekrup Baja Ringan bh 20.0000 1,500.00 30,000.00
Sekrup Reng bh 10.0000 1,200.00 12,000.00
Dinabolt bh 1.0000 5,000.00 5,000.00
Jumlah Bahan 111,580.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 146,770.00
E OVERHEAD & PROFIT 10% x D 14,677.00
F JUMLAH HARGA PEKERJAAN (D+E) 161,447.00
G PEMBULATAN 161,500.00
A TENAGA
Pekerja L.01 OH 0.1000 114,300.00 11,430.00
Tukang L.03 OH 0.0500 123,300.00 6,165.00
Jumlah Tenaga 17,595.00
B BAHAN
Reng R-35 tb. 0,45 mm m1 5.1000 5,800.00 29,580.00
Sekrup Reng bh 10.0000 1,200.00 12,000.00
Jumlah Bahan 41,580.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 59,175.00
E OVERHEAD & PROFIT 10% x D 5,917.50
F JUMLAH HARGA PEKERJAAN (D+E) 65,092.50
G PEMBULATAN 65,100.00
K. HARGA SATUAN PEKERJAAN KAYU
JENIS PEKERJAAN : Daun Pintu Panel Multyplek tb 9mm, Rangka kayu kelas II
SATUAN : 1 m2
KODE : K.1.
A TENAGA
Pekerja L.01 OH 0.6000 114,300.00 68,580.00
Tukang kayu L.03 OH 2.0000 123,300.00 246,600.00
Kepala tukang L.03 OH 0.2000 141,300.00 28,260.00
Mandor L.04 OH 0.0500 150,300.00 7,515.00
Jumlah Tenaga 350,955.00
B BAHAN
Kayu papan kelas II m3 0.0230 2,500,000.00 57,500.00
Paku 1 - 3 cm kg 0.3000 20,000.00 6,000.00
Lem kayu kg 0.1500 25,000.00 3,750.00
Multiplek 9 mm Lembar 0.2300 150,000.00 34,500.00
Jumlah Bahan 101,750.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 452,705.00
E OVERHEAD & PROFIT 10% x D 45,270.50
F JUMLAH HARGA PEKERJAAN (D+E) 497,975.50
G PEMBULATAN 498,000.00
A TENAGA
Pekerja L.01 OH 0.7500 114,300.00 85,725.00
Tukang Alumunium L.03 OH 0.3125 123,300.00 38,531.25
Kepala tukang L.03 OH 0.0313 141,300.00 4,422.69
Mandor L.04 OH 0.0750 150,300.00 11,272.50
Jumlah Tenaga 139,951.44
B BAHAN
Profil Alumunium Natural 8 cm m1 7.4000 60,000.00 444,000.00
Multiplek 9 mm Lembar 0.6000 150,000.00 90,000.00
Asesories 5% % 1.0000 26,700.00 26,700.00
Jumlah Bahan 560,700.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 700,651.44
E OVERHEAD & PROFIT 10% x D 70,065.14
F JUMLAH HARGA PEKERJAAN (D+E) 770,716.58
G PEMBULATAN 770,800.00
A TENAGA
Pekerja L.01 OH 0.7500 114,300.00 85,725.00
Tukang Alumunium L.03 OH 0.3125 123,300.00 38,531.25
Kepala tukang L.03 OH 0.0313 141,300.00 4,422.69
Mandor L.04 OH 0.0750 150,300.00 11,272.50
Jumlah Tenaga 139,951.44
B BAHAN
Profil Alumunium Natural 8 cm m1 7.4000 60,000.00 444,000.00
Spandrel Alumunium batang 3.0000 175,000.00 525,000.00
Asesories 5% kg 1.0000 48,450.00 48,450.00
Jumlah Bahan 1,017,450.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 1,157,401.44
E OVERHEAD & PROFIT 10% x D 115,740.14
F JUMLAH HARGA PEKERJAAN (D+E) 1,273,141.58
G PEMBULATAN 1,273,200.00
JENIS PEKERJAAN : Daun Pintu Panel Multyplek 9mm Lapis HPL, Rangka Alumunium
SATUAN : 1 Unit
KODE : K.4.
A TENAGA
Pekerja L.01 OH 0.7500 114,300.00 85,725.00
Tukang Alumunium L.03 OH 0.3125 123,300.00 38,531.25
Kepala tukang L.03 OH 0.0313 141,300.00 4,422.69
Mandor L.04 OH 0.0750 150,300.00 11,272.50
Jumlah Tenaga 139,951.44
B BAHAN
Profil Alumunium Natural 8 cm m1 7.4000 60,000.00 444,000.00
Multiplek 9 mm Lembar 0.6000 150,000.00 90,000.00
HPL (High Preassure Laminate) Lembar 0.8200 200,000.00 164,000.00
Asesories 5% kg 1.0000 26,700.00 26,700.00
Jumlah Bahan 724,700.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 864,651.44
E OVERHEAD & PROFIT 10% x D 86,465.14
F JUMLAH HARGA PEKERJAAN (D+E) 951,116.58
G PEMBULATAN 951,200.00
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang kayu L.03 OH 0.3000 123,300.00 36,990.00
Kepala tukang L.03 OH 0.0300 141,300.00 4,239.00
Mandor L.04 OH 0.0100 150,300.00 1,503.00
Jumlah Tenaga 65,592.00
B BAHAN
Kayu Balok Kelas II m3 0.0163 2,500,000.00 40,750.00
Paku 8 - 15 cm kg 0.2500 17,000.00 4,250.00
Jumlah Bahan 45,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 110,592.00
E OVERHEAD & PROFIT 10% x D 11,059.20
F JUMLAH HARGA PEKERJAAN (D+E) 121,651.20
G PEMBULATAN 121,700.00
L. HARGA SATUAN PEKERJAAN PENGECATAN
A TENAGA
Pekerja L.01 OH 0.1500 114,300.00 17,145.00
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 17,595.90
B BAHAN
Soda api Kg 0.0500 27,000.00 1,350.00
Jumlah Bahan 1,350.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 18,945.90
E OVERHEAD & PROFIT 10 % x D 1,894.59
F JUMLAH HARGA PEKERJAAN (D+E) 20,840.49
G PEMBULATAN 20,900.00
A TENAGA
Pekerja L.01 OH 0.0700 114,300.00 8,001.00
Tukang L.02 OH 0.0090 123,300.00 1,109.70
Kepala Tukang L.03 OH 0.0060 141,300.00 847.80
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 10,409.40
B BAHAN
Meni besi/kayu Kg 0.2000 30,000.00 6,000.00
Cat Kayu Kg 0.2600 75,000.00 19,500.00
Kuas Bh 0.0100 20,500.00 205.00
Minyak cat / Afdunner Kg 0.0300 11,000.00 330.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Jumlah Bahan 27,335.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 37,744.40
E OVERHEAD & PROFIT 10 % x D 3,774.44
F JUMLAH HARGA PEKERJAAN (D+E) 41,518.84
G PEMBULATAN 41,600.00
A TENAGA
Pekerja L.01 OH 0.0700 114,300.00 8,001.00
Tukang L.02 OH 0.1050 123,300.00 12,946.50
Kepala Tukang L.03 OH 0.0040 141,300.00 565.20
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 21,963.60
B BAHAN
Meni besi/kayu Kg 0.2000 30,000.00 6,000.00
Cat Kayu Kg 0.3500 75,000.00 26,250.00
Kuas Bh 0.0100 20,500.00 205.00
Minyak cat / Afdunner Kg 0.0300 11,000.00 330.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Jumlah Bahan 34,085.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 56,048.60
E OVERHEAD & PROFIT 10 % x D 5,604.86
F JUMLAH HARGA PEKERJAAN (D+E) 61,653.46
G PEMBULATAN 61,700.00
JENIS PEKERJAAN : Pengecatan Dinding Interior 2x (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : L.4.
A TENAGA
Pekerja L.01 OH 0.0200 114,300.00 2,286.00
Tukang L.02 OH 0.0630 123,300.00 7,767.90
Kepala Tukang L.03 OH 0.0063 141,300.00 890.19
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 11,394.99
B BAHAN
Plamir Kg 0.1000 25,000.00 2,500.00
Cat Dasar Kg 0.1000 25,000.00 2,500.00
Cat Tembok Interior Kg 0.2600 31,000.00 8,060.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Rol Cat Bh 0.0100 35,000.00 350.00
Jumlah Bahan 14,915.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 26,309.99
E OVERHEAD & PROFIT 10 % x D 2,631.00
F JUMLAH HARGA PEKERJAAN (D+E) 28,940.99
G PEMBULATAN 29,000.00
JENIS PEKERJAAN : Pengecatan Dinding Interior 3x (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : L.5.
A TENAGA
Pekerja L.01 OH 0.0300 114,300.00 3,429.00
Tukang L.02 OH 0.0945 123,300.00 11,651.85
Kepala Tukang L.03 OH 0.0095 141,300.00 1,342.35
Mandor L.04 OH 0.0038 150,300.00 571.14
Jumlah Tenaga 16,994.34
B BAHAN
Plamir Kg 0.1000 25,000.00 2,500.00
Cat Dasar Kg 0.1000 25,000.00 2,500.00
Cat Tembok Interior Kg 0.3900 31,000.00 12,090.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Rol Cat Bh 0.0100 35,000.00 350.00
Jumlah Bahan 18,945.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 35,939.34
E OVERHEAD & PROFIT 10 % x D 3,593.93
F JUMLAH HARGA PEKERJAAN (D+E) 39,533.27
G PEMBULATAN 39,600.00
JENIS PEKERJAAN : Pengecatan Dinding Exterior 2x (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : L.6.
A TENAGA
Pekerja L.01 OH 0.0200 114,300.00 2,286.00
Tukang L.02 OH 0.0630 123,300.00 7,767.90
Kepala Tukang L.03 OH 0.0063 141,300.00 890.19
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 11,394.99
B BAHAN
Cat Dasar Kg 0.1000 25,000.00 2,500.00
Cat Tembok Exterior Kg 0.2600 40,000.00 10,400.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Rol Cat Bh 0.0100 35,000.00 350.00
Jumlah Bahan 14,755.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 26,149.99
E OVERHEAD & PROFIT 10 % x D 2,615.00
F JUMLAH HARGA PEKERJAAN (D+E) 28,764.99
G PEMBULATAN 28,800.00
JENIS PEKERJAAN : Pengecatan Dinding Exterior 3x (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : L.7.
A TENAGA
Pekerja L.01 OH 0.0300 114,300.00 3,429.00
Tukang L.02 OH 0.0945 123,300.00 11,651.85
Kepala Tukang L.03 OH 0.0095 141,300.00 1,342.35
Mandor L.04 OH 0.0038 150,300.00 571.14
Jumlah Tenaga 16,994.34
B BAHAN
Cat Dasar Kg 0.1000 25,000.00 2,500.00
Cat Tembok Exterior Kg 0.3900 40,000.00 15,600.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Rol Cat Bh 0.0100 35,000.00 350.00
Jumlah Bahan 19,955.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 36,949.34
E OVERHEAD & PROFIT 10 % x D 3,694.93
F JUMLAH HARGA PEKERJAAN (D+E) 40,644.27
G PEMBULATAN 40,700.00
JENIS PEKERJAAN : Pengecatan Dinding Lama 2x (Bahan dan Merk Sesuai RKS)
SATUAN : 1 m2
KODE : L.8.
A TENAGA
Pekerja L.01 OH 0.0280 114,300.00 3,200.40
Tukang L.02 OH 0.0420 123,300.00 5,178.60
Kepala Tukang L.03 OH 0.0042 141,300.00 593.46
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 9,423.36
B BAHAN
Cat Dasar Kg 0.1200 25,000.00 3,000.00
Cat Tembok Exterior Kg 0.1800 40,000.00 7,200.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Rol Cat Bh 0.0100 35,000.00 350.00
Jumlah Bahan 12,055.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 21,478.36
E OVERHEAD & PROFIT 10 % x D 2,147.84
F JUMLAH HARGA PEKERJAAN (D+E) 23,626.20
G PEMBULATAN 23,700.00
A TENAGA
Pekerja L.01 OH 0.1333 114,300.00 15,236.19
Tukang L.02 OH 0.2000 123,300.00 24,660.00
Kepala Tukang L.03 OH 0.0200 141,300.00 2,826.00
Mandor L.04 OH 0.0067 150,300.00 1,007.01
Jumlah Tenaga 43,729.20
B BAHAN
Plamir Kg 0.1000 25,000.00 2,500.00
Cat Tembok Interior Kg 0.1067 31,000.00 3,307.70
Rol Cat Bh 0.0067 35,000.00 234.50
Alat bantu / steger Ls 0.6667 2,000.00 1,333.40
Jumlah Bahan 7,375.60
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 51,104.80
E OVERHEAD & PROFIT 10 % x D 5,110.48
F JUMLAH HARGA PEKERJAAN (D+E) 56,215.28
G PEMBULATAN 56,300.00
A TENAGA
Pekerja L.01 OH 0.2000 114,300.00 22,860.00
Tukang L.02 OH 0.3000 123,300.00 36,990.00
Kepala Tukang L.03 OH 0.0300 141,300.00 4,239.00
Mandor L.04 OH 0.0100 150,300.00 1,503.00
Jumlah Tenaga 65,592.00
B BAHAN
Plamir Kg 0.1600 25,000.00 4,000.00
Cat Tembok Interior Kg 0.1500 31,000.00 4,650.00
Rol Cat Bh 0.0100 35,000.00 350.00
Alat bantu / steger Ls 1.0000 2,000.00 2,000.00
Jumlah Bahan 11,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 76,592.00
E OVERHEAD & PROFIT 10 % x D 7,659.20
F JUMLAH HARGA PEKERJAAN (D+E) 84,251.20
G PEMBULATAN 84,300.00
A TENAGA
Pekerja L.01 OH 0.1600 114,300.00 18,288.00
Tukang L.02 OH 0.1600 123,300.00 19,728.00
Kepala Tukang L.03 OH 0.0160 141,300.00 2,260.80
Mandor L.04 OH 0.0030 150,300.00 450.90
Jumlah Tenaga 40,727.70
B BAHAN
Vernis liter 0.1500 52,000.00 7,800.00
Ampelas Lbr 0.2000 6,500.00 1,300.00
Kuas Bh 0.0100 20,500.00 205.00
Jumlah Bahan 9,305.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 50,032.70
E OVERHEAD & PROFIT 10 % x D 5,003.27
F JUMLAH HARGA PEKERJAAN (D+E) 55,035.97
G PEMBULATAN 55,100.00
M. HARGA SATUAN PEKERJAAN SANITAIR
JENIS PEKERJAAN : Pemasangan Closet Duduk (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.1.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.3300 114,300.00 37,719.00
Tukang L.02 OH 0.1600 123,300.00 19,728.00
Kepala Tukang L.03 OH 0.0110 141,300.00 1,554.30
Mandor L.04 OH 0.0110 150,300.00 1,653.30
Jumlah Tenaga 60,654.60
B BAHAN
Closet duduk Unit 1.0000 1,500,000.00 1,500,000.00
Perlengkapan 6% Ls 1.0000 90,000.00 90,000.00
Jumlah Bahan 1,590,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 1,650,654.60
E OVERHEAD & PROFIT 10% x D 165,065.46
F JUMLAH HARGA PEKERJAAN (D+E) 1,815,720.06
G PEMBULATAN 1,815,800.00
JENIS PEKERJAAN : Pemasangan Closet Jongkok (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.2.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.1000 114,300.00 11,430.00
Tukang L.02 OH 0.1500 123,300.00 18,495.00
Kepala tukang L.03 OH 0.0150 141,300.00 2,119.50
Mandor L.04 OH 0.0160 150,300.00 2,404.80
Jumlah Tenaga 34,449.30
B BAHAN
Closet Jongkok Poslin Warna Unit 1.0000 350,000.00 350,000.00
Semen Portland Kg 6.0000 1,300.00 7,800.00
Pasir pasang M3 0.0100 300,000.00 3,000.00
Jumlah Bahan 360,800.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 395,249.30
E OVERHEAD & PROFIT 10% x D 39,524.93
F JUMLAH HARGA PEKERJAAN (D+E) 434,774.23
G PEMBULATAN 434,800.00
Jumlah Alat
D JUMLAH (A+B+C) 1,465,024.50
E OVERHEAD & PROFIT 10% x D 146,502.45
F JUMLAH HARGA PEKERJAAN (D+E) 1,611,526.95
G PEMBULATAN 1,611,600.00
JENIS PEKERJAAN : Pemasangan Partisi / Sekat Urinoir (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.3.Hit-a
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.1000 114,300.00 11,430.00
Tukang L.02 OH 0.1000 123,300.00 12,330.00
Kepala tukang L.03 OH 0.0100 141,300.00 1,413.00
Mandor L.04 OH 0.0050 150,300.00 751.50
Jumlah Tenaga 25,924.50
B BAHAN
Partisi / Sekat Urinoir Unit 1.0000 1,200,000.00 1,200,000.00
Perlengkapan 6% % 1.0000 72,000.00 72,000.00
Jumlah Bahan 1,272,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 1,297,924.50
E OVERHEAD & PROFIT 10% x D 129,792.45
F JUMLAH HARGA PEKERJAAN (D+E) 1,427,716.95
G PEMBULATAN 1,427,800.00
Jumlah Alat
D JUMLAH (A+B+C) 511,615.80
E OVERHEAD & PROFIT 10% x D 51,161.58
F JUMLAH HARGA PEKERJAAN (D+E) 562,777.38
G PEMBULATAN 562,800.00
JENIS PEKERJAAN : Pemasangan Bak Fiberglass (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.5.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.1000 114,300.00 11,430.00
Tukang L.02 OH 0.0750 123,300.00 9,247.50
Kepala tukang L.03 OH 0.0075 141,300.00 1,059.75
Mandor L.04 OH 0.0010 150,300.00 150.30
Jumlah Tenaga 21,887.55
B BAHAN
Bak Fiberglass Unit 1.0000 350,000.00 350,000.00
Perlengkapan 6 % % 1.0000 21,000.00 21,000.00
Jumlah Bahan 371,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 392,887.55
E OVERHEAD & PROFIT 10% x D 39,288.76
F JUMLAH HARGA PEKERJAAN (D+E) 432,176.31
G PEMBULATAN 432,200.00
JENIS PEKERJAAN : Pemasangan Floor drain (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.6.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.0100 114,300.00 1,143.00
Tukang L.02 OH 0.1000 123,300.00 12,330.00
Kepala tukang L.03 OH 0.0100 141,300.00 1,413.00
Mandor L.04 OH 0.0050 150,300.00 751.50
Jumlah Tenaga 15,637.50
B BAHAN
Floor Drain Stainless Unit 1.0000 43,000.00 43,000.00
Jumlah Bahan 43,000.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 58,637.50
E OVERHEAD & PROFIT 10% x D 5,863.75
F JUMLAH HARGA PEKERJAAN (D+E) 64,501.25
G PEMBULATAN 64,600.00
JENIS PEKERJAAN : Pemasangan Kran 1/2 " (Bahan dan Merk Sesuai RKS)
SATUAN : 1 bh
KODE : M.7.
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.0100 114,300.00 1,143.00
Tukang L.02 OH 0.1000 123,300.00 12,330.00
Kepala tukang L.03 OH 0.0100 141,300.00 1,413.00
Mandor L.04 OH 0.0050 150,300.00 751.50
Jumlah Tenaga 15,637.50
B BAHAN
Kran 1/2" Stainless Bh 1.0000 35,000.00 35,000.00
Seal Tape Bh 0.0250 6,000.00 150.00
Jumlah Bahan 35,150.00
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 50,787.50
E OVERHEAD & PROFIT 10% x D 5,078.75
F JUMLAH HARGA PEKERJAAN (D+E) 55,866.25
G PEMBULATAN 55,900.00
Jumlah Alat
D JUMLAH (A+B+C) 25,418.70
E OVERHEAD & PROFIT 10% x D 2,541.87
F JUMLAH HARGA PEKERJAAN (D+E) 27,960.57
G PEMBULATAN 28,000.00
Jumlah Alat
D JUMLAH (A+B+C) 29,995.20
E OVERHEAD & PROFIT 10% x D 2,999.52
F JUMLAH HARGA PEKERJAAN (D+E) 32,994.72
G PEMBULATAN 33,000.00
Jumlah Alat
D JUMLAH (A+B+C) 28,955.70
E OVERHEAD & PROFIT 10% x D 2,895.57
F JUMLAH HARGA PEKERJAAN (D+E) 31,851.27
G PEMBULATAN 31,900.00
Jumlah Alat
D JUMLAH (A+B+C) 59,653.80
E OVERHEAD & PROFIT 10% x D 5,965.38
F JUMLAH HARGA PEKERJAAN (D+E) 65,619.18
G PEMBULATAN 65,700.00
Jumlah Alat
D JUMLAH (A+B+C) 71,034.30
E OVERHEAD & PROFIT 10% x D 7,103.43
F JUMLAH HARGA PEKERJAAN (D+E) 78,137.73
G PEMBULATAN 78,200.00
Jumlah Alat
D JUMLAH (A+B+C) 135,292.05
E OVERHEAD & PROFIT 10% x D 13,529.21
F JUMLAH HARGA PEKERJAAN (D+E) 148,821.26
G PEMBULATAN 148,900.00
Jumlah Alat
D JUMLAH (A+B+C) 205,519.05
E OVERHEAD & PROFIT 10% x D 20,551.91
F JUMLAH HARGA PEKERJAAN (D+E) 226,070.96
G PEMBULATAN 226,100.00
Jumlah Alat
D JUMLAH (A+B+C) 187,213.40
E OVERHEAD & PROFIT 10% x D 18,721.34
F JUMLAH HARGA PEKERJAAN (D+E) 205,934.74
G PEMBULATAN 206,000.00
Jumlah Alat
D JUMLAH (A+B+C) 233,413.40
E OVERHEAD & PROFIT 10% x D 23,341.34
F JUMLAH HARGA PEKERJAAN (D+E) 256,754.74
G PEMBULATAN 256,800.00
Jumlah Alat
D JUMLAH (A+B+C) 136,663.25
E OVERHEAD & PROFIT 10% x D 13,666.33
F JUMLAH HARGA PEKERJAAN (D+E) 150,329.58
G PEMBULATAN 150,400.00
Jumlah Tenaga -
B BAHAN
Galian Tanah Biasa Dalam 2 m B.2. m3 2.2500 120,600.00 271,350.00
Pasir urug m3 0.1070 200,000.00 21,400.00
Lantai Kerja Beton Mutu K-100 D.8. m3 1.1250 1,003,700.00 1,129,162.50
Bata Merah 1/2 Bata 1:3 F.3. m2 7.5000 158,400.00 1,188,000.00
Plat Beton tb. 12cm (110 kg Besi + Bekisting) K-175 D.28.Hit-b m3 0.1500 4,816,100.00 722,415.00
Plesteran 1:3 tebal 15mm G.1. m2 7.5000 81,600.00 612,000.00
Pipa PVC AW 4" m1 4.0000 109,325.00 437,300.00
Pipa PVC AW 1 1/2" m1 2.5000 16,733.33 41,833.33
Galian Tanah Biasa Dalam 1 m (Rembesan) B.1. m3 1.6880 98,500.00 166,268.00
Ijuk kg 2.7000 23,500.00 63,450.00
Kerikil / Seplit m3 0.5250 300,000.00 157,500.00
Pipa PVC AW 4" Berlobang m1 4.0000 109,325.00 437,300.00
Urugan Kembali Galian Tanah B.8. m3 0.5630 71,200.00 40,085.60
Jumlah Bahan 5,288,064.43
C PERALATAN
Jumlah Alat
D JUMLAH (A+B+C) 5,288,064.43
E OVERHEAD & PROFIT 10% x D 528,806.44
F JUMLAH HARGA PEKERJAAN (D+E) 5,816,870.88
G PEMBULATAN 5,816,900.00
Jumlah Alat
D JUMLAH (A+B+C) 165,003.30
E OVERHEAD & PROFIT 10% x D 16,500.33
F JUMLAH HARGA PEKERJAAN (D+E) 181,503.63
G PEMBULATAN 181,600.00
Jumlah Alat
D JUMLAH (A+B+C) 212,725.89
E OVERHEAD & PROFIT 10% x D 21,272.59
F JUMLAH HARGA PEKERJAAN (D+E) 233,998.48
G PEMBULATAN 234,000.00
Jumlah Alat
D JUMLAH (A+B+C) 212,725.89
E OVERHEAD & PROFIT 10% x D 21,272.59
F JUMLAH HARGA PEKERJAAN (D+E) 233,998.48
G PEMBULATAN 234,000.00
Jumlah Alat
D JUMLAH (A+B+C) 439,469.50
E OVERHEAD & PROFIT 10% x D 43,946.95
F JUMLAH HARGA PEKERJAAN (D+E) 483,416.45
G PEMBULATAN 483,500.00
Q. HARGA SATUAN PEKERJAAN ELEKTRIKAL
Jumlah Alat
D JUMLAH (A+B+C) 127,620.00
E OVERHEAD & PROFIT 10% x D 12,762.00
F JUMLAH HARGA PEKERJAAN (D+E) 140,382.00
G PEMBULATAN 140,400.00
Jumlah Alat
D JUMLAH (A+B+C) 118,720.00
E OVERHEAD & PROFIT 10% x D 11,872.00
F JUMLAH HARGA PEKERJAAN (D+E) 130,592.00
G PEMBULATAN 130,600.00
Jumlah Alat
D JUMLAH (A+B+C) 63,930.00
E OVERHEAD & PROFIT 10% x D 6,393.00
F JUMLAH HARGA PEKERJAAN (D+E) 70,323.00
G PEMBULATAN 70,400.00
Jumlah Alat
D JUMLAH (A+B+C) 97,730.00
E OVERHEAD & PROFIT 10% x D 9,773.00
F JUMLAH HARGA PEKERJAAN (D+E) 107,503.00
G PEMBULATAN 107,600.00
Jumlah Alat
D JUMLAH (A+B+C) 26,430.00
E OVERHEAD & PROFIT 10% x D 2,643.00
F JUMLAH HARGA PEKERJAAN (D+E) 29,073.00
G PEMBULATAN 29,100.00
Jumlah Alat
D JUMLAH (A+B+C) 26,430.00
E OVERHEAD & PROFIT 10% x D 2,643.00
F JUMLAH HARGA PEKERJAAN (D+E) 29,073.00
G PEMBULATAN 29,100.00
Jumlah Alat
D JUMLAH (A+B+C) 29,430.00
E OVERHEAD & PROFIT 10% x D 2,943.00
F JUMLAH HARGA PEKERJAAN (D+E) 32,373.00
G PEMBULATAN 32,400.00
Jumlah Alat
D JUMLAH (A+B+C) 126,430.00
E OVERHEAD & PROFIT 10% x D 12,643.00
F JUMLAH HARGA PEKERJAAN (D+E) 139,073.00
G PEMBULATAN 139,100.00
N. HARGA SATUAN PEKERJAAN KUNCI DAN KACA
Jumlah Alat
D JUMLAH (A+B+C) 160,609.50
E OVERHEAD & PROFIT 10% x D 16,060.95
F JUMLAH HARGA PEKERJAAN (D+E) 176,670.45
G PEMBULATAN 176,700.00
Jumlah Alat
D JUMLAH (A+B+C) 72,531.40
E OVERHEAD & PROFIT 10% x D 7,253.14
F JUMLAH HARGA PEKERJAAN (D+E) 79,784.54
G PEMBULATAN 79,800.00
Jumlah Alat
D JUMLAH (A+B+C) 58,637.50
E OVERHEAD & PROFIT 10% x D 5,863.75
F JUMLAH HARGA PEKERJAAN (D+E) 64,501.25
G PEMBULATAN 64,600.00
Jumlah Alat
D JUMLAH (A+B+C) 42,637.50
E OVERHEAD & PROFIT 10% x D 4,263.75
F JUMLAH HARGA PEKERJAAN (D+E) 46,901.25
G PEMBULATAN 47,000.00
Jumlah Alat
D JUMLAH (A+B+C) 50,531.40
E OVERHEAD & PROFIT 10% x D 5,053.14
F JUMLAH HARGA PEKERJAAN (D+E) 55,584.54
G PEMBULATAN 55,600.00
Jumlah Alat
D JUMLAH (A+B+C) 249,880.90
E OVERHEAD & PROFIT 10% x D 24,988.09
F JUMLAH HARGA PEKERJAAN (D+E) 274,868.99
G PEMBULATAN 274,900.00
Jumlah Alat
D JUMLAH (A+B+C) 50,637.50
E OVERHEAD & PROFIT 10% x D 5,063.75
F JUMLAH HARGA PEKERJAAN (D+E) 55,701.25
G PEMBULATAN 55,800.00
Jumlah Alat
D JUMLAH (A+B+C) 150,649.24
E OVERHEAD & PROFIT 10 % x D 15,064.92
F JUMLAH HARGA PEKERJAAN (D+E) 165,714.16
G PEMBULATAN 165,800.00
O. HARGA SATUAN PEKERJAAN KUSEN ALUMUNIUM
JENIS PEKERJAAN : Kusen Partisi Alm 2,20x1,60 m, Daun Multiplek 9 mm + Rangka Alumunium
SATUAN : 1 Unit
KODE : O.1.
Jumlah Alat
D JUMLAH (A+B+C) 1,899,126.50
E OVERHEAD & PROFIT 10% x D 189,912.65
F JUMLAH HARGA PEKERJAAN (D+E) 2,089,039.15
G PEMBULATAN 2,089,100.00
Jumlah Alat
D JUMLAH (A+B+C) 1,101,126.50
E OVERHEAD & PROFIT 10% x D 110,112.65
F JUMLAH HARGA PEKERJAAN (D+E) 1,211,239.15
G PEMBULATAN 1,211,300.00
JENIS PEKERJAAN : Kusen Jendela Alumunium 0,70 x 1,60 m (1 lubang dgn 1 Daun Jendela)
SATUAN : 1 Unit
KODE : O.2.
Jumlah Alat
D JUMLAH (A+B+C) 1,089,612.50
E OVERHEAD & PROFIT 10% x D 108,961.25
F JUMLAH HARGA PEKERJAAN (D+E) 1,198,573.75
G PEMBULATAN 1,198,600.00
JENIS PEKERJAAN : Kusen Jendela Alumunium 1,35 x 1,60 m (2 lubang dgn 1 Daun Jendela)
SATUAN : 1 Unit
KODE : O.3.
Jumlah Alat
D JUMLAH (A+B+C) 1,544,420.00
E OVERHEAD & PROFIT 10% x D 154,442.00
F JUMLAH HARGA PEKERJAAN (D+E) 1,698,862.00
G PEMBULATAN 1,698,900.00
JENIS PEKERJAAN : Kusen Jendela Sliding Alumunium 1,35 x 1,60 m (2 lubang 2 daun)
SATUAN : 1 Unit
KODE : O.3.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 1,587,675.00
E OVERHEAD & PROFIT 10% x D 158,767.50
F JUMLAH HARGA PEKERJAAN (D+E) 1,746,442.50
G PEMBULATAN 1,746,500.00
JENIS PEKERJAAN : Kusen Jendela Alumunium 2,00 x 1,60 m (3 lubang dgn 2 Daun Jendela)
SATUAN : 1 Unit
KODE : O.4.
Jumlah Alat
D JUMLAH (A+B+C) 2,230,397.50
E OVERHEAD & PROFIT 10% x D 223,039.75
F JUMLAH HARGA PEKERJAAN (D+E) 2,453,437.25
G PEMBULATAN 2,453,500.00
JENIS PEKERJAAN : Kusen Jendela Sliding Alumunium 2,00 x 1,60 m (3 lubang 2 Daun)
SATUAN : 1 Unit
KODE : O.4.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 2,006,257.50
E OVERHEAD & PROFIT 10% x D 200,625.75
F JUMLAH HARGA PEKERJAAN (D+E) 2,206,883.25
G PEMBULATAN 2,206,900.00
JENIS PEKERJAAN : Kusen Jendela Alumunium 2,65 x 1,60 m (4 lubang dgn 2 Daun Jendela)
SATUAN : 1 Unit
KODE : O.5.
Jumlah Alat
D JUMLAH (A+B+C) 2,685,205.00
E OVERHEAD & PROFIT 10% x D 268,520.50
F JUMLAH HARGA PEKERJAAN (D+E) 2,953,725.50
G PEMBULATAN 2,953,800.00
JENIS PEKERJAAN : Kusen Jendela Sliding Alumunium 2,65 x 1,60 m (4 lubang 2 Daun)
SATUAN : 1 Unit
KODE : O.5.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 2,461,065.00
E OVERHEAD & PROFIT 10% x D 246,106.50
F JUMLAH HARGA PEKERJAAN (D+E) 2,707,171.50
G PEMBULATAN 2,707,200.00
Jumlah Alat
D JUMLAH (A+B+C) 492,987.69
E OVERHEAD & PROFIT 10% x D 49,298.77
F JUMLAH HARGA PEKERJAAN (D+E) 542,286.46
G PEMBULATAN 542,300.00
Jumlah Alat
D JUMLAH (A+B+C) 741,023.94
E OVERHEAD & PROFIT 10% x D 74,102.39
F JUMLAH HARGA PEKERJAAN (D+E) 815,126.33
G PEMBULATAN 815,200.00
Jumlah Alat
D JUMLAH (A+B+C) 1,021,462.50
E OVERHEAD & PROFIT 10% x D 102,146.25
F JUMLAH HARGA PEKERJAAN (D+E) 1,123,608.75
G PEMBULATAN 1,123,700.00
JENIS PEKERJAAN : Kusen Bouvenligh Alumunium 2,65 x 0,70 m (4 lubang)
SATUAN : 1 Unit
KODE : O.9.
Jumlah Alat
D JUMLAH (A+B+C) 1,262,857.50
E OVERHEAD & PROFIT 10% x D 126,285.75
F JUMLAH HARGA PEKERJAAN (D+E) 1,389,143.25
G PEMBULATAN 1,389,200.00
Jumlah Alat
D JUMLAH (A+B+C) 1,163,212.50
E OVERHEAD & PROFIT 10% x D 116,321.25
F JUMLAH HARGA PEKERJAAN (D+E) 1,279,533.75
G PEMBULATAN 1,279,600.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 0,9 x 2,8 m (Daun Pintu Panel Multyplek 9mm)
SATUAN : 1 Unit
KODE : O.11.
Jumlah Alat
D JUMLAH (A+B+C) 1,840,721.44
E OVERHEAD & PROFIT 10% x D 184,072.14
F JUMLAH HARGA PEKERJAAN (D+E) 2,024,793.58
G PEMBULATAN 2,024,800.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 0,9 x 2,8 m (Daun Pintu Panel Spandrel Alumunium)
SATUAN : 1 Unit
KODE : O.11.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 2,297,471.44
E OVERHEAD & PROFIT 10% x D 229,747.14
F JUMLAH HARGA PEKERJAAN (D+E) 2,527,218.58
G PEMBULATAN 2,527,300.00
JENIS PEKERJAAN : Pemasangan Daun Pintu Alumunium (Daun Pintu Panel Multyplek 9mm)
SATUAN : 1 Unit
KODE : O.11.Hit-b
Jumlah Alat
D JUMLAH (A+B+C) 908,755.44
E OVERHEAD & PROFIT 10% x D 90,875.54
F JUMLAH HARGA PEKERJAAN (D+E) 999,630.98
G PEMBULATAN 999,700.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 0,9 x 2,0 m (Daun Pintu Panel Multyplek 9mm)
SATUAN : 1 Unit
KODE : O.11.Hit-c
Jumlah Alat
D JUMLAH (A+B+C) 1,527,506.44
E OVERHEAD & PROFIT 10% x D 152,750.64
F JUMLAH HARGA PEKERJAAN (D+E) 1,680,257.08
G PEMBULATAN 1,680,300.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 1,7 x 2,8 m (Daun Pintu Panel Multyplek Lapis HPL)
SATUAN : 1 Unit
KODE : O.12.
Jumlah Alat
D JUMLAH (A+B+C) 3,493,295.38
E OVERHEAD & PROFIT 10% x D 349,329.54
F JUMLAH HARGA PEKERJAAN (D+E) 3,842,624.92
G PEMBULATAN 3,842,700.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 1,7 x 2,8 m (Daun Pintu Panel Multyplek)
SATUAN : 1 Unit
KODE : O.12.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 3,165,295.38
E OVERHEAD & PROFIT 10% x D 316,529.54
F JUMLAH HARGA PEKERJAAN (D+E) 3,481,824.92
G PEMBULATAN 3,481,900.00
JENIS PEKERJAAN : Kusen Pintu Alumunium 1,5 x 2,60 m (Daun Pintu Panel Multyplek Lapis HPL)
SATUAN : 1 Unit
KODE : O.12.Hit-b
Jumlah Alat
D JUMLAH (A+B+C) 3,346,295.38
E OVERHEAD & PROFIT 10% x D 334,629.54
F JUMLAH HARGA PEKERJAAN (D+E) 3,680,924.92
JENIS PEKERJAAN : Kusen Pintu & Jendela Alm 1,55 x 2,80 m (1 lb. Pintu + 1 lb. Jendela Mati)
SATUAN : 1 Unit
KODE : O.13.
Jumlah Alat
D JUMLAH (A+B+C) 2,472,183.94
E OVERHEAD & PROFIT 10% x D 247,218.39
F JUMLAH HARGA PEKERJAAN (D+E) 2,719,402.33
G PEMBULATAN 2,719,500.00
JENIS PEKERJAAN : Kusen Pintu & Jendela Alm 2,20 x 2,80 m (1 lb. Pintu + 2 lb. 1 Daun Jendela)
SATUAN : 1 Unit
KODE : O.14.
Jumlah Alat
D JUMLAH (A+B+C) 3,159,368.94
E OVERHEAD & PROFIT 10% x D 315,936.89
F JUMLAH HARGA PEKERJAAN (D+E) 3,475,305.83
G PEMBULATAN 3,475,400.00
JENIS PEKERJAAN : Kusen Pintu & Jendela Sliding Alm 2,20 x 2,80 m (1 lb. Pintu + 2 lb 2 Daun)
SATUAN : 1 Unit
KODE : O.14.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 3,166,398.94
E OVERHEAD & PROFIT 10% x D 316,639.89
F JUMLAH HARGA PEKERJAAN (D+E) 3,483,038.83
G PEMBULATAN 3,483,100.00
JENIS PEKERJAAN : Kusen Pintu & Jendela Alm 2,85 x 2,80 m (1 lb. Pintu + 3 lb. 2 Daun Jendela)
SATUAN : 1 Unit
KODE : O.15.
Jumlah Alat
D JUMLAH (A+B+C) 3,910,011.44
E OVERHEAD & PROFIT 10% x D 391,001.14
F JUMLAH HARGA PEKERJAAN (D+E) 4,301,012.58
G PEMBULATAN 4,301,100.00
JENIS PEKERJAAN : Kusen Pintu & Jendela Sliding Alm 2,85 x 2,80 m (1 lb. Pintu + 3 lb. 2 Daun)
SATUAN : 1 Unit
KODE : O.15.Hit-a
Jumlah Alat
D JUMLAH (A+B+C) 3,685,871.44
E OVERHEAD & PROFIT 10% x D 368,587.14
F JUMLAH HARGA PEKERJAAN (D+E) 4,054,458.58
G PEMBULATAN 4,054,500.00
Jumlah Alat
D JUMLAH (A+B+C) 314,205.00
E OVERHEAD & PROFIT 10% x D 31,420.50
F JUMLAH HARGA PEKERJAAN (D+E) 345,625.50
G PEMBULATAN 345,700.00