No TOTAL
JUMLAH 799,973,816.09
PPN 11% 87,997,119.77
JUMLAH 887,970,935.86
DIBULATKAN 887,970,000.00
Taufiq
Direktur.
RENCANA ANGGARAN BIAYA (RAB)
I. PEKERJAAN PERSIAPAN
Biaya Pembuatan Papan Proyek 1.00 Unit 250,000.00 250,000.00
Biaya Administrasi dan Dokumentasi 1.00 ls 1,500,000.00 1,500,000.00
Biaya Pengadaan Alat Bantu / Prancah 1.00 ls 2,000,000.00 2,000,000.00
Biaya Pengadaan Listrik dan Air Kerja 1.00 ls 600,000.00 600,000.00
Biaya Mobilisasi & Demobilisasi 1.00 ls 2,500,000.00 2,500,000.00
Biaya K3 1.00 Ls 5,000,000.00 5,000,000.00
Sub Jumlah Rp 11,850,000.00
II. PEKERJAAN GALIAN DAN URUGAN
Urugan Pasir dibawah Lantai tebal 5 cm 11.90 m3 295,665.44 3,518,418.77
Sub Jumlah 3,518,418.77
III. PEKERJAAN BETON STRUKTUR
Kolom 12x12 K-225 (KP)
Bekisting Kolom 2x Pemakaian 6.43 m2 171,838.03 1,104,918.53
Bekisting Hanya Upah 3.22 m2 53,904.39 173,572.14
Pembesian Besi Polos 149.11 kg 17,716.34 2,641,682.81
Beton Mutu K-225 (Fc 19,3 Mpa) 0.39 m3 1,202,873.56 469,120.69
Kolom 20x20 K-225 (K)
Bekisting Kolom 2x Pemakaian 25.95 m2 171,838.03 4,459,196.85
Bekisting Hanya Upah 25.95 m2 53,904.39 1,398,818.92
Pembesian Besi Polos 189.78 kg 17,716.34 3,362,206.18
Pembesian Besi Ulir 406.34 kg 17,716.34 7,198,855.83
Beton Mutu K-225 (Fc 19,3 Mpa) 3.90 m3 1,202,873.56 4,691,206.89
Balok 11x11 K-225 (BL) -
Bekisting Balok 2x Pemakaian 9.31 m2 175,421.39 1,633,173.13
Bekisting Hanya Upah 9.31 m2 53,904.39 501,849.87
Pembesian Besi Polos 312.94 kg 17,716.34 5,544,150.08
Beton Mutu K-225 (Fc 19,3 Mpa) 1.02 m3 1,202,873.56 1,226,931.03
Balok 15x25 K-225 (RB) -
Bekisting Balok 2x Pemakaian 29.30 m2 175,421.39 5,139,846.70
Bekisting Hanya Upah 29.30 m2 53,904.39 1,579,398.63
Pembesian Besi Polos 239.71 kg 17,716.34 4,246,782.82
Pembesian Besi Ulir 641.54 kg 17,716.34 11,365,737.97
Beton Mutu K-225 (Fc 19,3 Mpa) 4.40 m3 1,202,873.56 5,292,643.67
Balok Portal 13x18 K-225 (RB)1 -
Bekisting Balok 2x Pemakaian 1.85 m2 175,421.39 324,529.57
Pembesian Besi Polos 13.48 kg 17,716.34 238,816.20
Pembesian Besi Ulir 38.13 kg 17,716.34 675,523.88
Beton Mutu K-225 (Fc 19,3 Mpa) 0.12 m3 1,202,873.56 144,344.83
Balok Portal 13x18 K-225 (PR) -
Bekisting Balok 2x Pemakaian 2.31 m2 175,421.39 405,223.41
Bekisting Hanya Upah 2.31 m2 53,904.39 124,519.14
Pembesian Besi Polos 18.56 kg 17,716.34 328,815.19
Pembesian Besi Ulir 51.97 kg 17,716.34 920,717.96
Beton Mutu K-225 (Fc 19,3 Mpa) 0.29 m3 1,202,873.56 348,833.33
Balok Sopi-Sopi 13x18 K-225 (BS) -
Bekisting Balok 2x Pemakaian 15.85 m2 175,421.39 2,780,429.02
Bekisting Hanya Upah 15.85 m2 53,904.39 854,384.58
Pembesian Besi Polos 129.92 kg 17,716.34 2,301,706.33
Pembesian Besi Ulir 367.06 kg 17,716.34 6,502,958.16
Beton Mutu K-225 (Fc 19,3 Mpa) 2.06 m3 1,202,873.56 2,477,919.54