REKAPITULASI

DAFTAR KUANTITAS DAN HARGA


ESTIMATE ENGINEERING

PEKERJAAN : PEMBANGUNAN 1 RUANG MADRASAH


LOKASI : SINGAPARNA, KABUPATEN TASIKMALAYA, JAWA BARAT
TAHUN : 2023

JUMLAH BIAYA
NO. URAIAN PEKERJAAN
(Rp.)
1 2 3

I PEKERJAAN PERSIAPAN 6.051.200,00


II PEKERJAAN GALIAN URUGAN 7.888.708,79
III PEKERJAAN PONDASI 31.883.808,00
IV PEKERJAAN BETON 368.400.145,24
V PEKERJAAN DINDING DAN PLESTERAN 131.274.140,00
VI PEKERJAAN KUSEN,PINTU,JENDELA ALUMUNIUM 76.161.984,00
VII PEKERJAAN PLAFOND 46.471.409,60
VIII PEKERJAAN ATAP 51.233.363,37
IX PEKERJAAN LANTAI 59.429.868,80
X PEKERJAAN ELEKTRIKAL 10.002.100,00
XI PEKERJAAN PENGECATAN 51.906.080,00
XII PEKERJAAN MEBELAIR 25.000.000,00

Jumlah Total 865.702.807,80


Dibulatkan 865.702.000,00
Terbilang :

DELAPAN RATUS ENAM PULUH LIMA JUTA TUJUH RATUS DUA RIBU RUPIAH

Tasikmalaya, 12 November 2023


Dibuat Oleh : Diperiksa Oleh :

Disetujui Oleh :
RINCIAN
DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : PEMBANGUNAN 1 RUANG MADRASAH


LOKASI : SINGAPARNA, KABUPATEN TASIKMALAYA, JAWA BARAT
TAHUN : 2023

JUMLAH
HARGA SATUAN
NO. URAIAN PEKERJAAN KODE ANALISA VOLUME SAT. SATUAN
(Rp.)
(Rp.)
1 2 3 4 5 6 7

I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank A.2.2.1.4 44,00 m' 82.800,00 3.643.200,00
2 Pembersihan dan perataan lapangan A.2.2.1.9 112,00 m2 21.500,00 2.408.000,00
6.051.200,00
II PEKERJAAN GALIAN URUGAN
1 Galian Tanah Pondasi Menerus A.2.3.1.1 48,30 m3 93.800,00 4.530.774,50
3
2 Urugan Tanah Kembali Bekas Galian Pondasi A.2.3.1.9 12,08 m 67.500,00 815.104,69
3
3 Urugan pasir Bawah Pondasi A.2.3.1.11 5,92 m 219.200,00 1.296.896,80
3
4 Urugan Pasir Bawah Lantai A.2.3.1.11 5,68 m 219.200,00 1.245.932,80
7.888.708,79
III PEKERJAAN PONDASI
3
1 Pas. Aanstamping batu kosong A.3.2.1.9 7,92 m 546.800,00 4.330.656,00
2 Pas. Pondasi batu belah 1:5 A.3.2.1.3 29,04 m3 948.800,00 27.553.152,00
31.883.808,00
IV PEKERJAAN BETON
1 Beton Pondasi foorplat 80x80x25
3
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 1,53 m 1.075.127,00 1.645.750,66
- Besi Beton (U-24) A.4.1.1.17 225,92 Kg 18.600,00 4.202.177,95
- Bekisting A.4.1.1.21 3,06 m2 264.600,00 810.072,90
2 Beton Sloof 17/30
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 5,61 m3 1.075.127,00 6.031.462,47
- Besi Beton (U-24) A.4.1.1.17 770,00 Kg 18.600,00 14.322.000,00
- Bekisting A.4.1.1.21 84,70 m2 264.600,00 22.411.620,00
3 Beton Kolom Praktis 12/12 ; Camp. 1Pc : 2Ps : 3Kr A.4.1.1.35 16,00 m' 115.000,00 1.840.000,00
4 Beton Kolom 35/35 ; Camp. 1Pc : 2Ps : 3Kr
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 10,58 m3 1.075.127,00 11.379.144,17
- Besi Beton (U-24) A.4.1.1.17 1.064,36 Kg 18.600,00 19.797.125,76
2
- Bekisting A.4.1.1.22 120,96 m 407.500,00 49.291.200,00
5 Beton Kolom 15/20 ; Camp. 1Pc : 2Ps : 3Kr
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 3,90 m3 1.075.127,00 4.192.995,30
- Besi Beton (U-24) A.4.1.1.17 677,82 Kg 18.600,00 12.607.452,00
2
- Bekisting A.4.1.1.22 91,00 m 407.500,00 37.082.500,00
6 Beton Balok Lintel 10/15 ; Camp. 1Pc : 2Ps : 3Kr A.4.1.1.36 56,00 m1 143.700,00 8.047.200,00
7 Ring Balok Beton 15/20
3
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 1,08 m 1.075.127,00 1.161.137,16
- Besi Beton (U-24) A.4.1.1.17 170,64 Kg 18.600,00 3.173.904,00
- Bekisting A.4.1.1.23 14,40 m2 457.200,00 6.583.680,00
8 Beton Balok 17/30
3
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 9,79 m 1.075.127,00 10.527.643,58
- Besi Beton (U-24) A.4.1.1.17 1.344,00 Kg 18.600,00 24.998.400,00
2
- Bekisting A.4.1.1.21 147,84 m 264.600,00 39.118.464,00
9 Beton Plat Lantai 12cm
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 19,20 m3 1.075.127,00 20.642.438,40
- Besi Beton (U-24) A.4.1.1.17 1.262,59 Kg 18.600,00 23.484.211,20
2
- Bekisting A.4.1.1.24 80,00 m 469.500,00 37.560.000,00
10 Beton Plat Tangga 10 cm
- Beton mutu f'c = 14.5 Mpa A.4.1.1.4 1,45 m3 1.075.127,00 1.558.504,10
- Besi Beton (U-24) A.4.1.1.17 274,06 Kg 18.600,00 5.097.541,59
2
- Bekisting A.4.1.1.35 7,25 m 115.000,00 833.520,00
368.400.145,24
JUMLAH
HARGA SATUAN
NO. URAIAN PEKERJAAN KODE ANALISA VOLUME SAT. SATUAN
(Rp.)
(Rp.)
1 2 3 4 5 6 7
V PEKERJAAN DINDING DAN PLESTERAN
1 Dinding Bata ad 1PC : 5Ps A.4.4.1.10 305,80 m2 146.500,00 44.799.700,00
2
2 Plesteran Dinding Bata ad 1PC : 5PS A.4.4.2.5 611,60 m 86.600,00 52.964.560,00
3 Pekerjaan Acian A.4.4.2.27 611,60 m2 54.300,00 33.209.880,00
4 Pas. Plakat, ukuran 20 x 30 cm U&B 1,00 ls 300.000,00 300.000,00
131.274.140,00
VI PEKERJAAN KUSEN,PINTU,JENDELA ALUMUNIUM
1 Type Pintu P1, Alumunium 4" Warna Dihitung 4,00 Unit 2.694.096,00 10.776.384,00
2 Type Jendela J2, Alumunium 4" Warna Dihitung 24,00 Unit 2.724.400,00 65.385.600,00
76.161.984,00
VII PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Kayu Kelas III A.4.6.1.20 231,60 m2 126.700,00 29.343.720,00
2
2 Pek. Plafond GRC A.4.5.1.13 231,60 m 59.756,00 13.839.489,60
3 List Profil Plafond Gypsum A.4.5.1.11 82,00 m' 40.100,00 3.288.200,00
46.471.409,60
VIII PEKERJAAN ATAP
2
1 Rangka Atap Baja Ringan U&B 134,94 m 180.000,00 24.289.156,63
2 Lisplank Wood Plank A.4.6.1.30 41,20 m' 70.600,00 2.908.720,00
3 Genteng Metal Pasir A.4.5.2.32 134,94 m2 162.900,00 21.981.686,75
4 Nok Genteng Metal Pasir A.4.5.2.37 14,00 m' 146.700,00 2.053.800,00
51.233.363,37
IX PEKERJAAN LANTAI
1 Lantai Keramik 40 x 40 Putih Polos A.4.4.3.74 242,99 m2 188.900,00 45.901.188,80
2 Rabat Beton Keliling Bangunan A.4.1.1.1 4,40 m3 974.700,00 4.288.680,00
3 Pas. Saluran Gravel A.5.1.1.34 44,00 m' 210.000,00 9.240.000,00
59.429.868,80
X PEKERJAAN ELEKTRIKAL
1 Penyambungan Listrik U&B 2,00 ls 350.000,00 700.000,00
2 MCB 10 A, 1 fasa U&B 1,00 bh 54.500,00 54.500,00
3 Instalasi Penerangan U&B 12,00 Ttk 233.000,00 2.796.000,00
4 Instalasi Saklar dan Stop Kontak U&B 12,00 Ttk 233.000,00 2.796.000,00
5 Stop Kontak, Sek. Broco U&B 4,00 bh 23.900,00 95.600,00
6 Saklar Tunggal Sek. Broco U&B 4,00 bh 18.200,00 72.800,00
7 Saklar Ganda, Sek. Broco U&B 4,00 bh 20.500,00 82.000,00
8 Lampu TL 1 x 40 watt + box U&B 8,00 bh 392.250,00 3.138.000,00
9 Lampu SL 18 Watt ex. Philips led U&B 4,00 bh 66.800,00 267.200,00
10.002.100,00
XI PEKERJAAN PENGECATAN
2
1 Pengecatan Dinding ex.Mowilex A.4.7.1.10. 611,60 m 62.300,00 38.102.680,00
2
2 Pengecatan Plafond Cat Tembok ex. Mowilex A.4.7.1.23. 231,60 m 55.900,00 12.946.440,00
3 Pengecatan Bidang Kayu ex. Avian A.4.7.1.4. 16,48 m2 52.000,00 856.960,00
51.906.080,00
XII PEKERJAAN MEBELAIR
1 Pekerjaan Mebelair dan Perabotannya U&B 1,00 set 25.000.000,00 25.000.000,00
25.000.000,00