REKAPITULASI

KEGIATAN : PEMBANGUNAN PASTORI


PEKERJAAN : PEMBANGUNAN PASTORI
LOKASI : ALO KEC. RAINIS
TAHUN ANGGARAN : 2023

JUMLAH
NO URAIAN JENIS PEKERJAAN / KEGIATAN HARGA
(Rp)
1 2 3

I PEKERJAAN PERSIAPAN 1.758.872,21

II PEKERJAAN TANAH 5.397.541,16

III PEKERJAAN PONDASI 32.329.869,29

IV PEKERJAAN METZEL/ BETON 108.001.462,72

V PEKERJAAN STRUKTUR BETON BERTULANG 62.105.655,83

VI PEKERJAAN PENUTUP LANTAI DAN DINDING 39.743.058,99

VII PEKERJAAN KUSEN PINTU, JENDELA 24.235.934,18

VIII PEKERJAAN KUNCI DAN PENGGANTUNG 7.706.175,00

IX PEKERJAAN ATAP 85.269.469,71

X PEKERJAAN PLAFOND 28.674.593,04

XI PEKERJAAN INSTALASI LISTRIK 8.800.242,89

XII PEKERJAAN SANITASI/ PLUMBING 23.364.148,89

XIII PEKERJAAN PENGECATAN 23.436.669,56

(A) JUMLAH BIAYA KONSTRUKSI 450.823.693,48


(B) PAJAK ( 10% x A )
(C) JUMLAH TOTAL (A+B ) 450.823.693,48
(B) DIBULATKAN 450.000.000,00

Terbilang : EMPAT RATUS LIMA PULUH JUTA RUPIAH