JUMLAH
No. URAIAN DAN JENIS PEKERJAAN
HARGA
I. PERSIAPAN LAPANGAN/ SITEWORK 6.012.972,33
II. PENERAPAN SMKK 7.945.000,00
III. PEKERJAAN TANAH 244.618.347,36
IV. PEKERJAAN PONDASI 224.396.436,77
V. PEKERJAAN BETON 161.875.467,00
VI. PEKERJAAN PASANGAN DINDING 70.539.361,57
VII. PEKERJAAN PLESTERAN 52.608.938,77
VIII. PEKERJAAN PARTISI 32.187.993,06
IX. PEKERJAAN PENUTUP LANTAI 62.921.466,05
X. PEKERJAAN LANGIT-LANGIT (PLAFON) 74.102.621,89
XI. PEKERJAAN KUSEN PINTU DAN JENDELA 106.909.963,80
XII. PEKERJAAN PENUTUP ATAP 143.273.313,59
XIII. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 23.289.240,00
XIV. PEKERJAAN SANITAIR 48.619.879,42
XV. PEKERJAAN ARSITEKTUR ORNAMEN DINDING DAN FINISHING 72.993.206,21
XVI. PEKERJAAN AKHIR 19.571.000,00
A REAL COST 1.351.865.207,81
B. PPN (11% X A) 148.705.172,86
C. TOTAL COST ( A + B + C) 1.500.570.380,67
DIBULATKAN 1.500.570.000,00
Terbilang : Satu Milyar Lima Ratus Juta Lima Ratus Tujuh Puluh Ribu Rupiah