Anda di halaman 1dari 9

REKAPITULASI RENCANA ANGGARAN BIAYA

PROGRAM : PENINGKATAN SARANA DISTRIBUSI PERDAGANGAN


KEGIATAN : PEMBANGUNAN DAN PENGELOLAAN SARANA DISTRIBUSI PERDAGANGAN
SUB KEGIATAN : PENYEDIAAN SARANA DISTRIBUSI PERDAGANGAN
PEKERJAAN : PEMBANGUNAN PASAR TUNGGORONO
LOKASI : PASAR TUNGGORONO KAB. JOMBANG
SUMBER DANA : BANTUAN KEUANGAN PROVINSI JAWA TIMUR TAHUN ANGGARAN 2022

No Item Pekerjaan Sub Total (Rp)


1 2 3
A PEKERJAAN FISIK PEMBANGUNAN PASAR TUNGGORONO
I. PEKERJAAN PERSIAPAN 87,933,553.63
II. PEKERJAAN TANAH 112,613,160.89
III. PEKERJAAN PONDASI 165,527,632.81
IV. PEKERJAAN STRUKTUR/BETON 616,702,595.00
V. PEKERJAAN PASANGAN 500,768,633.90
VI. PEKERJAAN ATAP 810,723,378.48
VII. PEKERJAAN KERAMIK 10,320,032.74
VIII. PEKERJAAN PINTU & JENDELA 278,741,774.02
IX. PEKERJAAN PENGAMAN 225,566,532.00
X. PEKERJAAN PENGECATAN 114,433,441.82
XI. PEKERJAAN MEKANIKAL ELEKTRIKAL 58,774,065.20
XII. PEKERJAAN SANITASI AIR BERSIH 10,032,801.81
XIII. PEKERJAAN SANITASI AIR KOTOR 6,384,604.13
XIV. PEKERJAAN KOTORAN 12,054,649.93
XV. PEKERJAAN ORNAMEN 34,500,000.00

B PEKERJAAN FISIK PEMBUATAN LAPAK SEMENTARA


I PEKERJAAN GALIAN TANAH 5,091,446.39
II PEKERJAAN PONDASI & PARTISI 76,991,436.29
III. PEKERJAAN ATAP 27,023,616.14
IV. PEKERJAAN PINTU 18,219,060.05

C PEKERJAAN PAVINGISASI HALAMAN DEPAN


I PEKERJAAN GALIAN TANAH 16,466,629.35
II PEKERJAAN PAVINGISASI 60,120,864.86

D RAHAB BEDAK YANG KOSONG 120,845,428.71

E PEKERJAAN K3 12,328,400.00

I JUMLAH BKF 3,382,163,738.14


II PPN 11 % 372,038,011.20
III JUMLAH 3,754,201,749.34
IV DIBULATKAN 3,754,201,700.00

TERBILANG : Tiga Milyar Tujuh ratus Lima Puluh Empat Juta Dua ratus Satu Ribu Tujuh ratus Rupiah
RENCANA ANGGARAN BIAYA (RAB)
ENGGINERING ESTIMATE (EE)

PROGRAM : PENINGKATAN SARANA DISTRIBUSI PERDAGANGAN


KEGIATAN : PEMBANGUNAN DAN PENGELOLAAN SARANA DISTRIBUSI PERDAGANGAN
SUB KEGIATAN : PENYEDIAAN SARANA DISTRIBUSI PERDAGANGAN
PEKERJAAN : PEMBANGUNAN PASAR TUNGGORONO
LOKASI : PASAR TUNGGORONO KAB. JOMBANG
SUMBER DANA : BANTUAN KEUANGAN PROVINSI JAWA TIMUR TAHUN ANGGARAN 2022

Harga Sat Pekerjaan


No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6

A PEKERJAAN FISIK PEMBANGUNAN PASAR TUNGGORONO

I. PEKERJAAN PERSIAPAN
1 Uitzet / Pengukuran & Pas. Bowplank 160.00 m1 46,954.90 7,512,784.00
2 Papan nama kegiatan 1.00 bh 400,000.00 400,000.00
- Papan Banner
- Rangka Papan Nama Usuk 5/7
3 Pembuatan direksi keet 15.00 m2 1,186,149.45 17,792,241.80
4 Pembuatan Pagar Sementara dari seng bekas 132.00 m2 348,253.56 45,969,469.26
5 Pembersihan lokasi 1,485.00 m2 8,393.10 12,463,753.50
6 Uji Tes Beton K-250 18.00 bh 150,000.00 2,700,000.00
7 IMB 1.00 m2 1,095,305.07 1,095,305.07

sub total 87,933,553.63

II. PEKERJAAN TANAH


1 Pekerjaan Galian Pondasi Tanah Biasa Sedalam 2 Meter 308.02 m3 101,989.80 31,414,898.20
2 Pekerjaan Urug Tanah Kembali 91.20 m3 59,691.00 5,443,819.20
3 Pekerjaan Tanah Urug Peninggian Lantai 492.25 m3 126,805.50 62,420,007.38
4 Pekerjaan Pasir Urug 86.63 m3 153,924.00 13,334,436.12

sub total 112,613,160.89

III. PEKERJAAN PONDASI


1 Lantai Kerja Pondasi Tebal 5cm Mutu Beton K-175
- Cor Beton 2.10 m3 720,302.66 1,512,635.59

2 Footplate Pondasi gedung 100.100.30cm Mutu Beton K-250


- Pembesian 1,439.37 Kg 13,081.42 18,829,002.07
- Cor Beton 12.60 m3 924,021.32 11,642,668.65

3 Aanstamping 70.09 m3 446,182.65 31,272,941.94


4 Pas. Batu kali 1pc : 4pp 130.21 m3 785,426.50 102,270,384.57

sub total 165,527,632.81


Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6
IV. PEKERJAAN STRUKTUR/BETON
1 Kolom Struktur 30/30 Mutu Beton K.250
- Begisting 317.52 m2 209,248.77 66,440,669.45
- Pembesian 2,936.62 Kg 13,081.42 38,415,156.66
- Cor Beton 79.38 m3 924,021.32 73,348,812.48

2 Balok Sloof 15/25 Mutu Beton K-250


- Begisting 339.00 m2 143,115.99 48,516,320.61
- Pembesian 3,757.25 Kg 13,081.42 49,150,161.54
- Cor Beton 25.42 m3 924,021.32 23,488,621.98

3 Rabat lantai Bedak tebal 10cm Mutu Beton K.250


- Cor Beton 145.64 m3 924,021.32 134,574,465.22

4 Kolom Praktis 12/12 Mutu Beton K-175


- Begisting 3X Pakai 111.36 m2 69,749.59 7,767,314.34
- Pembesian 2,204.77 Kg 13,081.42 28,841,520.17
- Cor Beton 6.68 m3 720,302.66 4,811,621.78

5 Kolom 12/25 Mutu Beton K-175


- Begisting 9.60 m2 69,749.59 669,596.06
- Pembesian 63.34 Kg 13,081.42 828,577.08
- Cor Beton 0.36 m3 720,302.66 259,308.96

6 Balok Latay 12/25 Mutu Beton K-175


- Begisting 100.27 m2 143,115.99 14,350,240.32
- Pembesian 1,132.69 Kg 13,081.42 14,817,192.49
- Cor Beton 8.13 m3 720,302.66 5,856,060.64

7 Ring Balok 12/25 Mutu Beton K-175


- Begisting 322.65 m2 47,705.33 15,392,124.72
- Pembesian 3,440.09 Kg 13,081.42 45,001,258.69
- Cor Beton 19.36 m3 720,302.66 13,945,059.53

8 Balok Beton B1 15/40 Mutu Beton K.175


- Begisting 26.60 m2 213,793.77 5,686,914.28
- Pembesian 221.32 Kg 13,081.42 2,895,179.65
- Cor Beton 1.68 m3 720,302.66 1,210,108.47

9 Balok Beton B2 15/30 Mutu Beton K.175


- Begisting 15.15 m2 213,793.77 3,238,975.62
- Pembesian 169.69 Kg 13,081.42 2,219,785.99
- Cor Beton 1.03 m3 720,302.66 741,911.74

10 Balok Beton 12/12 Mutu Beton K.175 (Pengunci Pasangan atap Dak Beton)
- Begisting 0.96 m2 143,115.99 137,391.35
- Pembesian 14.61 Kg 13,081.42 191,119.53
- Cor Beton 0.06 m3 720,302.66 43,218.16

11 Balok Konsol BK 15/60 Mutu Beton K.175


- Begisting 4.05 m2 213,793.77 865,864.77
- Pembesian 37.57 Kg 13,081.42 491,468.91
- Cor Beton 0.27 m3 720,302.66 194,481.72
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6

12 Canopi Beton Tebal 10Cm Mutu Beton K.175


- Begisting 9.00 m2 209,248.77 1,883,238.93
- Pembesian 74.04 Kg 13,081.42 968,548.26
- Cor Beton 0.90 m3 720,302.66 648,272.40

13 Plat Atap Dek Beton Tebal 10Cm Mutu Beton K.175


- Begisting 22.65 m2 209,248.77 4,739,484.64
- Pembesian 186.33 Kg 13,081.42 2,437,460.80
- Cor Beton 2.27 m3 720,302.66 1,635,087.04

sub total 616,702,595.00

V. PEKERJAAN PASANGAN
1 Pas. Batu merah 1 bata 1 pc : 4 ps (rollag) 116.12 m2 215,570.61 25,032,059.52
2 Pas. Batu merah 1/2 bata 1 pc : 3 ps (trassram) 111.60 m2 107,825.33 12,033,306.55
3 Plesteran, 1 Pc : 3 Ps, tebal 15 mm (trassram) 223.20 m2 64,911.89 14,488,334.29
4 Pas. Batu bata merah 1/2 bata 1 pc : 6 ps 1,576.62 m2 102,847.29 162,151,094.36
5 Plesteran, 1 Pc : 6 Ps, tebal 15 mm 3,396.02 m2 61,970.77 210,453,981.13
6 Acian 3,396.02 m2 15,850.69 53,829,251.76
7 Benangan sudut 2,082.04 m1 10,807.00 22,500,606.28
8 Roster Beton 15/30 cm 8.00 Bh 35,000.00 280,000.00

sub total 500,768,633.90

VI. PEKERJAAN ATAP


1 Kolom WF 200.100.5,5.8 mm 1,962.67 kg 22,242.22 43,654,137.93
2 Kuda-kuda Rafter WF 200.100.5,5.8 mm 5,269.33 kg 22,242.22 117,201,597.11
3 Kuda-kuda Rangka CNP 150,50,20.2.3 139.56 kg 22,242.22 3,104,124.22
4 Konsolan/TritisanWF 200.100.5,5.8 mm 1,977.60 kg 22,242.22 43,986,214.27
5 Potongan/Voute WF 200.100.32 (Join antara kuda-kuda dan kolom) 234.72 kg 22,242.22 5,220,693.88
6 Anchor (bolt nut) ASTM 307 @ 6xdia.19 mm L=600 mm 240.00 Bh 85,000.00 20,400,000.00
7 Bout Mur HTB Ø16 mm (Join Antar WF) 640.00 Bh 7,500.00 4,800,000.00
8 Bout Mur HTB Ø12x20 mm (Baut Gording CNP) 1,562.00 Bh 5,500.00 8,591,000.00
9 Plat Plandes Tebal=10 mm 283.46 kg 22,242.22 6,304,779.68
10 Plat Besi Join Antar Kaki Kuda-Kuda WF Tebal8 mm 425.20 kg 22,242.22 9,457,391.94
11 Plat Besi Pengaku/Stifenerr Kuda-Kuda WF, Tebal= 8 mm 131.45 kg 22,242.22 2,923,739.82
12 Plat Besi Penyaga Gording Tebal 8mm 1,195.84 kg 22,242.22 26,598,136.36
13 Gording CNP 150,50,20.2.3 7,500.76 kg 22,242.22 166,833,554.09
14 Besi Ikatan Gording Trektang Dia 10mm 1,216.77 kg 22,242.22 27,063,666.03
15 Besi Ikatan Angin Besi Beton Dia 10mm 303.17 kg 22,242.22 6,743,173.84
16 Jarum Keras 60.00 Bh 20,000.00 1,200,000.00
17 Pas. Atap Zincalume KR-5 t=0.30 mm 1,771.22 m2 70,094.00 124,151,894.68
18 Pas. Bubungan Zinkcalume 53.00 m' 73,542.14 3,897,733.42
19 Penutup Dinding Zincalume + Rangka CNP 125,50,20.2.3 80.00 m2 293,950.40 23,516,032.00
20 Penutup Dinding Woodplank 3000.300.8mm + Rangka CNP 125,50,20.2.3 260.00 m2 378,563.15 98,426,419.00
21 Pas Lisplank Zincalume Tinggi 60Cm 418.30 m' 70,114.20 29,328,769.86
22 Pas. Cremona Rangka CNP 150.50.20.2,3 975.45 kg 22,242.22 21,696,173.50
23 Pas. Regel Cremona besi ø12 mm 189.03 kg 22,242.22 4,204,446.85
24 Penyambungan Las Listrik 1.00 Ls 11,419,700.00 11,419,700.00

sub total 810,723,378.48


Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6
VII. PEKERJAAN KERAMIK
1 Pas. Keramik lantai Kamar Mandi 25x25 10.80 m2 234,120.53 2,528,501.67
2 Pas. Keramik Dinding Kamar Mandi 25x40 33.28 m2 234,120.53 7,791,531.07

sub total 10,320,032.74

VIII. PEKERJAAN PINTU & JENDELA


1 Pintu Rolling Door Aluminium tebal 1mm 622.55 m2 436,118.00 271,505,260.90
2 Kusen Allumunium 4'' + Kaca Mati Tebal 5mm (Teras) 1.00 Bh 2,036,513.12 2,036,513.12
3 Pintu Aluminium 4'' (KM/WC) 4.00 Bh 1,300,000.00 5,200,000.00

278,741,774.02

IX. PEKERJAAN PENGAMAN


1 Pas. Kerangkeng Pengaman Rangka Besi Hollow 40/40 810.00 m2 278,477.20 225,566,532.00

225,566,532.00

X. PEKERJAAN PENGECATAN
1 Cat dinding 3,919.30 m2 19,329.89 75,759,618.28
2 Cat Besi 1,005.20 m2 25,575.22 25,708,211.14
3 Cat Kayu 260.00 m2 49,867.74 12,965,612.40

sub total 114,433,441.82

XI. PEKERJAAN MEKANIKAL ELEKTRIKAL


1 Pas. Instalasi Titik Lampu 25.00 Titik 140,652.60 3,516,315.00
2 Pas. Instalasi Titik Stop Kontak 77.00 Titik 120,452.60 9,274,850.20
3 Lampu Mercury 250 Waat + Trafo & Cap Lampu 21.00 Bh 608,000.00 12,768,000.00
4 Lampu LED bulp 8 Waat 4.00 Bh 55,000.00 220,000.00
5 Handle 25 Amper 0.1 3.00 Bh 320,000.00 960,000.00
7 Stop Kontak 76.00 Bh 25,000.00 1,900,000.00
8 Kabel Nym 2x1,5 mm Panjang 100 Meter 2.00 Roll 1,400,000.00 2,800,000.00
9 Kabel Nym 3x2,5 mm Panjang 100 Meter 2.00 Roll 1,800,000.00 3,600,000.00

10 Pasang Panel MDP Lantai 1


- Pemasangan KWH Meter 3 Phase 23KVA Baru+Kabel Instalasi 1.00 Ls 5,000,000.00 5,000,000.00
- Box Panel Lantai 1 Uk. 60x80x20 1.00 Bh 1,100,000.00 1,100,000.00
- MCB 25A 1 phase 3.00 Bh 110,000.00 330,000.00
- MCB 16A 1 phase 2.00 Bh 100,000.00 200,000.00
- MCB 10A 1 phase 5.00 Bh 80,000.00 400,000.00
- MCB 4A 1 phase 2.00 Bh 65,000.00 130,000.00
- CT (Current Transformator) 1.00 Bh 65,000.00 65,000.00
- Volt Amper 1.00 Bh 65,000.00 65,000.00
- HZ 1.00 Bh 65,000.00 65,000.00
- Amper Meter 1.00 Bh 65,000.00 65,000.00
- Breaker 3 Phase 150 Amper 1.00 Bh 1,200,000.00 1,200,000.00
- Fuse Kubur 3.00 Bh 20,000.00 60,000.00
- Lampu Indikator 3.00 Bh 20,000.00 60,000.00
- Selector Swit 3.00 Bh 45,000.00 135,000.00
- Base Bar 3P 1.00 Bh 250,000.00 250,000.00
- Rill MCB 3.00 Bh 30,000.00 90,000.00
- Plat Sisir 3 Phase 1.00 Bh 120,000.00 120,000.00
- BC 10 mm 3.00 m' 150,000.00 450,000.00
- Kabel 0.75mm 3.00 m' 2,300.00 6,900.00
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6

11 Pas. Penangkal Petir (ARDE)


- Pemasangan Penangkal Petir (ARDE) 1.00 Ls 500,000.00 500,000.00
- Kuku Macam Kuningan Pengikat Antar Kabel BC 4.00 Bh 20,000.00 80,000.00
- Bleksem 1'' Atas 2.00 Bh 250,000.00 500,000.00
- Bleksem 1'' Bawah 1.00 Bh 250,000.00 250,000.00
- Pipa Besi Stik Bleksem 1'' BSA 2.80 m' 112,500.00 315,000.00
- Tima Budeng 6.00 Bh 70,000.00 420,000.00
- Kabel Tembaga BC 50mm 56.00 m' 130,000.00 7,280,000.00
- Klem/Pengikat BC Jarak 40 Cm 140.00 Bh 7,000.00 980,000.00
- Pipa PVC 3/4'' AW Pelindung BC 56.00 m' 9,250.00 518,000.00
- Pengeboran Titik Penangkal Bawah+Pipa 5.00 m' 120,000.00 600,000.00
- pengukuran Kabel Grounding untuk Penangkal petir/Pemeegeran 1.00 Ls 2,500,000.00 2,500,000.00

58,774,065.20

XII. PEKERJAAN SANITASI AIR BERSIH


1 Pengeboran Sanitasi Air Bersih 3 Inch 25.00 m' 120,000.00 3,000,000.00
2 Pas. Pompa Air Bersih Shimizu Type 135 1.00 Bh 1,500,000.00 1,500,000.00
3 Pas. Kran air 3/4'' 4.00 Bh 91,265.62 365,062.48
4 Pas. Pipa PVC Ø1 In 47.20 m' 24,798.73 1,170,500.15

5 Aksesoris Penyambungan
- Seal Tape 12.00 Bh 3,000.00 36,000.00
- Klem Pipa 1 Inch 16.00 Bh 2,000.00 32,000.00
- Lem Penyambungan PVC (Kaleng) 1.00 Kg 43,000.00 43,000.00
- Tuns Clap 1 Inch 1.00 Bh 20,000.00 20,000.00
- Sttop Kran 1 Inch 2.00 Bh 80,000.00 160,000.00
- Knne 1 Inch 20.00 Bh 3,500.00 70,000.00
- Knne Drat Dalam Kuningan 3/4 Inch 4.00 Bh 30,000.00 120,000.00
- Shoc Drat Luar 1 Inch 2.00 Bh 15,000.00 30,000.00
- Water Mur 1 Inch 4.00 Bh 45,000.00 180,000.00
- Perlup T 1 X 3/4 Inch 4.00 Bh 10,000.00 40,000.00

6 Bak Mandi 4.00 Bh 600,000.00 2,400,000.00


7 Rumah Pompa
- Galian Tanah 0.14 m3 101,989.80 14,278.57
- Rabat Lantai Tebal 5Cm 0.02 m3 720,302.66 14,406.05
- Pas. 1/2 Bata Trasram Camp 1Pc:3Ps 2.40 m2 107,825.33 258,780.79
- Plesteran Trasram Camp 1Pc:3Ps 4.80 m2 64,911.89 311,577.08
- Acian 4.80 m2 15,850.69 76,083.30
- Plat Besi Penutup Tebal 2mm 5.67 Kg 22,242.22 126,113.39
- Kunci Gembok 1.00 Bh 50,000.00 50,000.00
- Oval Pall Kunci Gembok 1.00 Bh 15,000.00 15,000.00

10,032,801.81
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6
XIII. PEKERJAAN SANITASI AIR KOTOR
1 Pas. Pipa PVC Ø 3" D - maspion 10.00 m' 88,233.30 882,332.97
2 Aksesoris Penyambungan
- Knne 3 Inch 3.00 Bh 8,000.00 24,000.00
- T PVC 3 Inch 3.00 Bh 25,000.00 75,000.00
- Lem Penyambungan PVC (Kaleng) 0.10 Kg 43,000.00 4,300.00

3 Floor drain Stainlles 4.00 Bh 99,800.12 399,200.48


4 Galian tanah Biasa 7.46 m3 101,989.80 760,843.91
5 Urug tanah kembali 2.75 m3 59,691.00 164,150.25
6 Pas. Buis Beton Diameter 40 Cm 22.00 m1 100,000.00 2,200,000.00

7 Pekerjaan Bak Kontrol Saluran 60x60x70 Cm


- Pas. 1/2 Bata Merah Camp 1Pc: 3Ps 6.72 m2 107,825.33 724,586.20
- Plesteran Dinding Bak Kontrol Camp 1Pc: 3Ps 6.72 m2 64,911.89 436,207.91
- Acian Dinding Bak Kontrol 6.72 m2 15,850.69 106,516.62
- Rabat Beton Bak Kontrol Tebal 5 Cm 0.07 m3 720,302.66 50,421.19
- Penutup Beton Bak Kontrol Tebal 10 Cm 0.14 m3 720,302.66 100,842.37
- Pembesian Beton Bak Kontrol 11.84 kg 13,081.42 154,884.00
- Bekisting Beton Bak Kontrol 1.44 m2 209,248.77 301,318.23

6,384,604.13

XIV. PEKERJAAN KOTORAN


1 Pas. Clossed jongkok 4.00 Bh 670,741.00 2,682,964.00
2 Pas. Pipa PVC Ø 4" D - maspion 20.00 m' 126,941.55 2,538,830.94
3 Aksesoris Penyambungan
- Knne 4 Inch 8.00 Bh 15,000.00 120,000.00
- T PVC 4 Inch 3.00 Bh 45,000.00 135,000.00
- Clean Out 4Inch 4.00 Bh 40,000.00 160,000.00
- Lem Penyambungan PVC (Kaleng) 0.50 Kg 43,000.00 21,500.00

4 Septictank
- Pas. Batu merah 1/2 bata 1 pc : 3 ps (trassram) 17.60 m2 107,825.33 1,897,725.76
- Plesteran, 1 Pc : 3 Ps, tebal 15 mm (trassram) 17.60 m2 64,911.89 1,142,449.30
- Penutup Plat Beton t = 10 cm
- Bekisting 3.12 m2 209,248.77 652,856.16
- Pembesihan 25.65 Kg 13,081.42 335,538.40
- Cor Beton 0.31 m3 720,302.66 223,293.83

5 Resapan
- Pas. Batu Kali 1 : 5 Ps 0.75 m3 785,426.50 589,069.88
- Pas. Bata Kosong 1.76 m2 170,306.20 299,738.91
- Pas. Trassram 1 bata 0.82 m2 215,570.61 176,767.90
- Urugan Krikil 0.12 m3 252,000.00 30,240.00
- Ijuk 3.00 Kg 30,000.00 90,000.00
- Penutup Plat Beton t = 10 cm
- Bekisting 2.40 m2 209,248.77 502,197.05
- Pembesihan 21.68 Kg 13,081.42 283,605.16
- Beton 0.24 m3 720,302.66 172,872.64

12,054,649.93
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6

XV. PEKERJAAN ORNAMEN


1 Pas. Sunccren kisi-kisi hollow 40/60 Tebal 1.20mm 10.00 m2 350,000.00 3,500,000.00
2 Pas. Kisi-Kisi Rangka Hollow 100.50.1,20mm, 20.40.1,20mm 2.00 Bh 4,000,000.00 8,000,000.00
3 Penyambungan Las Listrik 1.00 Ls 500,000.00 500,000.00
4 Pas. Tulisan Bahan Stainles Tinggi 60Cm (PASAR TUNGGORONO) 15.00 Bh 1,000,000.00 15,000,000.00
5 Turbin Ventilator roof C 75 dual Fan T=1.5mm 5.00 Bh 1,500,000.00 7,500,000.00

sub total 34,500,000.00

B PEKERJAAN FISIK PEMBUATAN LAPAK SEMENTARA

I PEKERJAAN GALIAN TANAH


1 Pekerjaan Galian Tanah Biasa 1.73 m3 82,900.00 143,417.00
2 Urug tanah dipadatkan 22.50 m3 126,805.50 2,853,123.75
3 Urug pasir 13.61 m3 153,924.00 2,094,905.64

sub total 5,091,446.39

II PEKERJAAN PONDASI & PARTISI


1 Pondasi Beton 20/20/60 Camp 1pc:2Ps:Krl
- Cor Beton 1.73 m3 720,302.66 1,246,123.61
2 Rabat lantai Bedak tebal 5cm 11.25 m3 720,302.66 8,103,404.95
- Cor Beton

3 Pas. Batu merah 1 bata 1 pc : 4 ps (rollag) 56.70 m2 215,570.61 12,222,853.73


4 Pas. Dinding Partisi Rangka Kayu 3/5 Triplek Tebal 3mm 559.55 m2 93,624.98 52,387,857.56
5 Pas. Pilar Kayu 5/7mm 0.67 m3 4,524,173.80 3,031,196.45

sub total 76,991,436.29

III. PEKERJAAN ATAP


1 Pas. Penutup Atap asbes Gelombang Kecil Tebal 4mm Uk. 2.40cmx1.05cm 322.82 m2 58,962.79 19,034,367.87
3 Kuda-kuda Rangka Atap Balok Kayu 5/7 0.69 m3 5,284,118.00 3,646,041.42
4 Gording Rangka Atap Balok Kayu 5/7 0.96 m3 4,524,173.80 4,343,206.85

sub total 27,023,616.14

IV. PEKERJAAN PINTU


1 Pas. Pintu Geser Penutup Triplek Tebal 3mm Rangka Kayu 3/5 122.50 m2 93,624.98 11,469,060.05
2 Pas. Engsel Pintu Lipat 240.00 bh 20,000.00 4,800,000.00
3 Oval Pall Kunci Gembok 30.00 bh 15,000.00 450,000.00
4 Kunci Gembok 50mm 30.00 bh 50,000.00 1,500,000.00

sub total 18,219,060.05

C PEKERJAAN PAVINGISASI HALAMAN DEPAN

I PEKERJAAN GALIAN TANAH


1 Galian tanah Kanstin 0.99 m3 82,900.00 82,071.00
2 Tanah Urug 86.98 m3 126,805.50 11,029,542.39
3 Urug pasir 34.79 m3 153,924.00 5,355,015.96

sub total 16,466,629.35


Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)

1 2 3 4 6 7 = 3*6
II PEKERJAAN PAVINGISASI
1 Paving tebal 6cm K.300 579.86 m2 90,780.82 52,640,166.29
2 Kanstin Pengunci 10x20x40 K.300 123.95 m' 60,352.55 7,480,698.57

sub total 60,120,864.86

D RAHAB BEDAK YANG KOSONG

1 Pemindahan Barang & Pembersihan 48.00 Bedak/Bh 150,000.00 7,200,000.00


2 Pas. Pintu Geser Penutup Triplek Tebal 3mm Rangka Kayu 3/5 240.00 m2 93,624.98 22,469,995.20
3 Pas. Engsel Pintu Lipat 384.00 Bh 20,000.00 7,680,000.00
4 Oval Pall Kunci Gembok 48.00 Bh 15,000.00 720,000.00
5 Kunci Gembok 50mm 48.00 Bh 50,000.00 2,400,000.00
6 Pas. Dinding Partisi Rangka Kayu 3/5 Triplek Tebal 3mm 720.00 m2 93,624.98 67,409,985.60
7 Rabat lantai Bedak tebal 5cm
- Cor Beton 18.00 m3 720,302.66 12,965,447.91

sub total 120,845,428.71