E PEKERJAAN K3 12,328,400.00
TERBILANG : Tiga Milyar Tujuh ratus Lima Puluh Empat Juta Dua ratus Satu Ribu Tujuh ratus Rupiah
RENCANA ANGGARAN BIAYA (RAB)
ENGGINERING ESTIMATE (EE)
1 2 3 4 6 7 = 3*6
I. PEKERJAAN PERSIAPAN
1 Uitzet / Pengukuran & Pas. Bowplank 160.00 m1 46,954.90 7,512,784.00
2 Papan nama kegiatan 1.00 bh 400,000.00 400,000.00
- Papan Banner
- Rangka Papan Nama Usuk 5/7
3 Pembuatan direksi keet 15.00 m2 1,186,149.45 17,792,241.80
4 Pembuatan Pagar Sementara dari seng bekas 132.00 m2 348,253.56 45,969,469.26
5 Pembersihan lokasi 1,485.00 m2 8,393.10 12,463,753.50
6 Uji Tes Beton K-250 18.00 bh 150,000.00 2,700,000.00
7 IMB 1.00 m2 1,095,305.07 1,095,305.07
1 2 3 4 6 7 = 3*6
IV. PEKERJAAN STRUKTUR/BETON
1 Kolom Struktur 30/30 Mutu Beton K.250
- Begisting 317.52 m2 209,248.77 66,440,669.45
- Pembesian 2,936.62 Kg 13,081.42 38,415,156.66
- Cor Beton 79.38 m3 924,021.32 73,348,812.48
10 Balok Beton 12/12 Mutu Beton K.175 (Pengunci Pasangan atap Dak Beton)
- Begisting 0.96 m2 143,115.99 137,391.35
- Pembesian 14.61 Kg 13,081.42 191,119.53
- Cor Beton 0.06 m3 720,302.66 43,218.16
1 2 3 4 6 7 = 3*6
V. PEKERJAAN PASANGAN
1 Pas. Batu merah 1 bata 1 pc : 4 ps (rollag) 116.12 m2 215,570.61 25,032,059.52
2 Pas. Batu merah 1/2 bata 1 pc : 3 ps (trassram) 111.60 m2 107,825.33 12,033,306.55
3 Plesteran, 1 Pc : 3 Ps, tebal 15 mm (trassram) 223.20 m2 64,911.89 14,488,334.29
4 Pas. Batu bata merah 1/2 bata 1 pc : 6 ps 1,576.62 m2 102,847.29 162,151,094.36
5 Plesteran, 1 Pc : 6 Ps, tebal 15 mm 3,396.02 m2 61,970.77 210,453,981.13
6 Acian 3,396.02 m2 15,850.69 53,829,251.76
7 Benangan sudut 2,082.04 m1 10,807.00 22,500,606.28
8 Roster Beton 15/30 cm 8.00 Bh 35,000.00 280,000.00
1 2 3 4 6 7 = 3*6
VII. PEKERJAAN KERAMIK
1 Pas. Keramik lantai Kamar Mandi 25x25 10.80 m2 234,120.53 2,528,501.67
2 Pas. Keramik Dinding Kamar Mandi 25x40 33.28 m2 234,120.53 7,791,531.07
278,741,774.02
225,566,532.00
X. PEKERJAAN PENGECATAN
1 Cat dinding 3,919.30 m2 19,329.89 75,759,618.28
2 Cat Besi 1,005.20 m2 25,575.22 25,708,211.14
3 Cat Kayu 260.00 m2 49,867.74 12,965,612.40
1 2 3 4 6 7 = 3*6
58,774,065.20
5 Aksesoris Penyambungan
- Seal Tape 12.00 Bh 3,000.00 36,000.00
- Klem Pipa 1 Inch 16.00 Bh 2,000.00 32,000.00
- Lem Penyambungan PVC (Kaleng) 1.00 Kg 43,000.00 43,000.00
- Tuns Clap 1 Inch 1.00 Bh 20,000.00 20,000.00
- Sttop Kran 1 Inch 2.00 Bh 80,000.00 160,000.00
- Knne 1 Inch 20.00 Bh 3,500.00 70,000.00
- Knne Drat Dalam Kuningan 3/4 Inch 4.00 Bh 30,000.00 120,000.00
- Shoc Drat Luar 1 Inch 2.00 Bh 15,000.00 30,000.00
- Water Mur 1 Inch 4.00 Bh 45,000.00 180,000.00
- Perlup T 1 X 3/4 Inch 4.00 Bh 10,000.00 40,000.00
10,032,801.81
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)
1 2 3 4 6 7 = 3*6
XIII. PEKERJAAN SANITASI AIR KOTOR
1 Pas. Pipa PVC Ø 3" D - maspion 10.00 m' 88,233.30 882,332.97
2 Aksesoris Penyambungan
- Knne 3 Inch 3.00 Bh 8,000.00 24,000.00
- T PVC 3 Inch 3.00 Bh 25,000.00 75,000.00
- Lem Penyambungan PVC (Kaleng) 0.10 Kg 43,000.00 4,300.00
6,384,604.13
4 Septictank
- Pas. Batu merah 1/2 bata 1 pc : 3 ps (trassram) 17.60 m2 107,825.33 1,897,725.76
- Plesteran, 1 Pc : 3 Ps, tebal 15 mm (trassram) 17.60 m2 64,911.89 1,142,449.30
- Penutup Plat Beton t = 10 cm
- Bekisting 3.12 m2 209,248.77 652,856.16
- Pembesihan 25.65 Kg 13,081.42 335,538.40
- Cor Beton 0.31 m3 720,302.66 223,293.83
5 Resapan
- Pas. Batu Kali 1 : 5 Ps 0.75 m3 785,426.50 589,069.88
- Pas. Bata Kosong 1.76 m2 170,306.20 299,738.91
- Pas. Trassram 1 bata 0.82 m2 215,570.61 176,767.90
- Urugan Krikil 0.12 m3 252,000.00 30,240.00
- Ijuk 3.00 Kg 30,000.00 90,000.00
- Penutup Plat Beton t = 10 cm
- Bekisting 2.40 m2 209,248.77 502,197.05
- Pembesihan 21.68 Kg 13,081.42 283,605.16
- Beton 0.24 m3 720,302.66 172,872.64
12,054,649.93
Harga Sat Pekerjaan
No Uraian Pekerjaan Volume Sat Sub Total (Rp)
(Rp)
1 2 3 4 6 7 = 3*6
1 2 3 4 6 7 = 3*6
II PEKERJAAN PAVINGISASI
1 Paving tebal 6cm K.300 579.86 m2 90,780.82 52,640,166.29
2 Kanstin Pengunci 10x20x40 K.300 123.95 m' 60,352.55 7,480,698.57