Anda di halaman 1dari 9

REKAPITULASI ANGGARAN BIAYA

PEKERJAAN PEMBANGUNAN MASJID JOESOEF BAKRI

NO Uraian Pekerjaan Jumlah Harga


( Rp )
A. PEKERJAAN MESJID JOESOEF BAKRI
I PEKERJAAN PENDAHULUAN 7,256,647.200
II PEKERJAAN TANAH DAN PASIR 12,376,883.777
III PEKERJAAN PASANGAN DAN PLESTERAN 301,392,133.161
IV PEKERJAAN STRUKTUR BETON BERTULANG 803,485,235.028
V PEKERJAAN PINTU & JENDELA 48,456,363.349
VI PEKERJAAN ATAP 770,158,000.569
VII PEKERJAAN PLAFOND 88,840,800.000
VIII PEKERJAAN LANTAI 221,208,378.131
IX PEKERJAAN FINISHING 50,758,965.895
X PEKERJAAN LAIN - LAIN 1,268,232.000

B. PEKERJAAN RUMAH WUDHU


I PEKERJAAN PENDAHULUAN 3,628,323.600
II PEKERJAAN TANAH DAN PASIR 9,934,700.655
III PEKERJAAN PASANGAN DAN PLESTERAN 93,491,093.044
IV PEKERJAAN STRUKTUR BETON BERTULANG 82,705,305.267
V PEKERJAAN PINTU & JENDELA 4,050,621.963
VI PEKERJAAN ATAP 19,964,099.309
VII PEKERJAAN PLAFOND 25,017,457.500
VIII PEKERJAAN LANTAI 23,750,337.895
IX PEKERJAAN INSTALASI LISTRIK 3,477,800.000
X PEKERJAAN BESI, KUNCI, KACA DAN PENGGANTUNGAN 8,225,560.000
XI PEKERJAAN SANITAIR 30,579,757.730
XII PEKERJAAN FINISHING 73,862,091.060

C. PEKERJAAN RUMAH MARBOT


I PEKERJAAN PENDAHULUAN 12,591,452.000
II PEKERJAAN TANAH DAN PASIR 6,406,719.645
III PEKERJAAN PASANGAN DAN PLESTERAN 59,162,131.148
IV PEKERJAAN STRUKTUR BETON BERTULANG 51,196,183.000
V PEKERJAAN PINTU & JENDELA 25,912,098.060
VI PEKERJAAN ATAP 12,328,671.221
VII PEKERJAAN PLAFOND 15,449,332.500
VIII PEKERJAAN LANTAI 20,997,118.195
IX PEKERJAAN INSTALASI LISTRIK 2,836,900.000
X PEKERJAAN BESI, KUNCI, KACA DAN PENGGANTUNGAN 5,667,307.000
XI PEKERJAAN SANITAIR 13,650,892.460
XII PEKERJAAN FINISHING 41,146,948.262

D. PEKERJAAN LANDSCAPE
I PEKERJAAN TANAH 386,673,664.114
II PEKERJAAN TAMAN 137,342,500.000
III PEKERJAAN JEMBATAN 22,244,831.648
IV PEKERJAAN SALURAN 55,119,586.302

E. PEKERJAAN PAGAR DEPAN


I PEKERJAAN TANAH 1,868,326.574
II PEKERJAAN PASANGAN DAN PLESTERAN 17,759,170.735
III PEKERJAAN STRUKTUR BETON BERTULANG 20,651,555.197
IV PEKERJAAN PASANGAN DAN PLESTERAN 20,409,441.052
IV PEKERJAAN FINISHING 14,066,985.920

Page 1 of 2
F. PEKERJAAN PAGAR BELAKANG DAN SAMPING
I PEKERJAAN TANAH 5,857,278.570
II PEKERJAAN PASANGAN DAN PLESTERAN 22,514,005.744
III PEKERJAAN STRUKTUR BETON BERTULANG 27,845,642.453
IV PEKERJAAN PASANGAN DAN PLESTERAN 39,590,875.950
IV PEKERJAAN FINISHING 25,606,127.100

Jumlah Total 3,748,784,531.983


Dibulatkan 3,748,784,000.00

Terbilang : Tiga Milyar Tujuh Ratus Empat Puluh Delapan Juta Tujuh Ratus Delapan Puluh Empat
Ribu Rupiah

Page 2 of 2
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN PEMBANGUNAN MASJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan
Jumlah Harga
( Rp ) ( Rp )
I PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran dan Pemasangan Bouplank 92.00 m' 78,876.60 7,256,647.20
Sub Jumlah 7,256,647.20
II PEKERJAAN TANAH DAN PASIR
1 Pek. Galian tanah Pondasi 99.65 m³ 83,140.20 8,284,920.93
2 Pek. Urugan Tanah Kembali 49.83 m³ 44,625.68 2,223,474.51
3 Pek. Urugan pasir bawah pondasi 4.98 m³ 291,914.48 1,454,463.90
4 Pek. Urugan tanah Peninggi Lantai 2.49 m³ 137,000.00 341,301.25
5 Pek. Urugan pasir bawah lantai 0.25 m³ 291,914.48 72,723.19
Sub Jumlah 12,376,883.78
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Batu kosong 11.96 m³ 1,405,442.45 16,806,280.76
2 Pek. Pas. Pondasi Menerus/ Batu Belah Ad. 1:3 79.60 m³ 1,405,442.45 111,866,191.41
3 Pek. Pasangan tembok trasraam camp 1pc:3psr 2.10 m2 299,440.00 628,824.00
4 Pek. Pasangan tembok Bataco camp 1pc:5psr 438.46 m2 206,169.93 90,397,267.95
5 Pek. Pas. Plesteran Ad 1 : 4 876.92 m2 93,159.66 81,693,569.05
Sub Jumlah 301,392,133.16
IV PEKERJAAN STRUKTUR BETON BERTULANG
1 Pek. Beton lantai kerja tebal 5cm 4.98 m³ 8,040.00 40,059.30
2 Pek. Beton fondasi footplat(F2) 0,8x0,8 63.78 m³ 6,090,033.86 388,397,999.58
3 Pek. Beton sloof SL1-(20x30) 6.98 m³ 8,719,837.46 60,825,226.17
4 Pek. Beton sloof SL2-(20x40) 8.97 m³ 8,719,837.46 78,203,862.22
5 Pek. Beton sloof SL3-(15x25) 3.74 m³ 8,719,837.46 32,584,942.59
6 Pek. Beton kolom type KU1- 30/30 4.95 m³ 10,016,100.51 49,579,697.53
7 Pek. Beton kolom type KU2- 25/25 3.44 m³ 10,016,100.51 34,430,345.51
8 Pek. Beton kolom type KU3- 15/30 2.48 m³ 10,016,100.51 24,789,848.77
9 Pek. Ring Balok- 15/15 89.00 m' 135,660.65 12,073,797.49
10 Pek. Beton balok (20/45) 8.97 m³ 9,646,268.28 86,512,557.07
11 Pek. Beton balok (15/25) 3.74 m³ 9,646,268.28 36,046,898.78
Sub Jumlah 803,485,235.03
V PEKERJAAN PINTU & JENDELA
1 Pek. Pasangan Kusen Pintu dan Jendela Kayu 1.39 m³ 10,479,000.00 14,566,933.35
2 Pek. Pasangan daun pintu dan jendela Kayu 2.17 m³ 10,479,000.00 22,739,430.00
3 Pek. pasangan kunci tanam 20.00 bh 350,000.00 7,000,000.00
4 Pek. Pasangan engsel tanam 10.00 bh 165,000.00 1,650,000.00
5 Pek. Pasangan grendel tanam 10.00 bh 250,000.00 2,500,000.00
Sub Jumlah 48,456,363.35
VI PEKERJAAN ATAP
1 Pek.Atap dak beton (Kubah dan Menara Utama) + Ornamen GRC 76.89 m³ 10,016,100.51 770,158,000.57
Sub Jumlah 770,158,000.57
VII PEKERJAAN PLAFOND
1 Pek.Rangka Plafond Hollo 40x40 dan 20x40 365.60 m2 148,000.00 54,108,800.00
2 Pek.Penutup Plafond Gipsum board 9mm 365.60 m2 95,000.00 34,732,000.00
Sub Jumlah 88,840,800.00
VIII PEKERJAAN LANTAI
1 Pek.Lantai HT 60x60 Polished 425.00 m2 382,005.61 162,352,385.53
2 Pek.Lantai Batu alam 113.43 m2 518,897.89 58,855,992.61
Sub Jumlah 221,208,378.13
IX PEKERJAAN FINISHING
1 Pek. Cat Tembok 876.92 m2 56,835.92 49,840,554.79
2 Pek. Cat Minyak kayu 18.29 m2 50,213.84 918,411.10
Sub Jumlah 50,758,965.90
X PEKERJAAN LAIN - LAIN
1 Pemipaan
- Sparing pipa air kotor PVC AW Ø 4" 8.40 m' 137,393.09 628,572.00
- Sparing air bekas Pipa PVC Ø 3" AW 14.00 m' 74,374.24 639,660.00

Sub Jumlah 1,268,232.00


Sub Jumlah Total 2,305,201,639.11

Page 1 of 7
RENCANA ANGGARAN BIAYA (RAB)
BANGUNAN RUMAH WUDHU
MESJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
( Rp ) ( Rp )
I PEKERJAAN PENDAHULUAN

1 Pek. Pengukuran dan Pemasangan Bouplank 46.00 m' 78,876.60 3,628,323.60


Sub Jumlah 3,628,323.60
II PEKERJAAN TANAH DAN PASIR

1 Pek. Galian pondasi setempat 0.65 m³ 83,140.20 53,874.85


2 Pek.Galian pondasi menerus 39.60 m³ 83,140.20 3,292,701.11
3 Pek.Urugan pasir bawah pondasi setempat 0.22 m³ 291,914.48 63,053.53
4 Pek.Urugan pasir bawah pondasi menerus 2.32 m³ 291,914.48 678,000.57
5 Pek.Urugan tanah pondasi 10.14 m³ 44,625.68 452,491.01
6 Pek.Urugan pasir bawah lantai 18.48 m³ 291,914.48 5,394,579.59
Sub Jumlah 9,934,700.66
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Batu kosong 9.29 m³ 1,405,442.45 13,057,122.49
2 Pek. Pas. Pondasi Menerus/ Batu Belah Ad. 1:3 17.42 m³ 1,405,442.45 24,482,104.67
3 Pek. Pasangan tembok trasraam camp 1pc:3psr 14.40 m³ 299,440.00 4,311,936.00
4 Pek. Pasangan tembok Bataco camp 1pc:5psr 37.08 m³ 206,169.93 7,644,162.53
5 Pek. Pas. Plesteran Ad 1 : 4 472.26 m2 93,159.66 43,995,767.35
Sub Jumlah 93,491,093.04
IV PEKERJAAN STRUKTUR BETON BERTULANG
1 Pek.Beton fondasi footplat(F2) 0,8x0,8 0.86 m³ 6,090,033.86 5,261,789.26
2 Pek.Beton sloof SL1-(20x35) 4.65 m³ 8,719,837.46 40,505,388.95
3 Pek.Pek Dak Beton Lantai 2.23 m³ 8,719,837.46 19,464,944.36
4 Pek.Beton kolom type KU1- 30/30 0.82 m³ 10,016,100.51 8,248,258.77
5 Pek.Beton ring balok (15/25) 68.00 m' 135,660.65 9,224,923.93
Sub Jumlah 82,705,305.27
V PEKERJAAN PINTU & JENDELA
1 Pek.Pasangan Kusen (almunium) 0.19 m2 441,504.31 81,929.07
2 Pek.Pasangan daun pintu lapis almunium 0.15 m2 1,689,857.11 248,692.89
3 Pek.pasangan kunci tanam 4.00 bh 350,000.00 1,400,000.00
4 Pek.Pasangan engsel tanam 8.00 bh 165,000.00 1,320,000.00
5 Pek.Pasangan grendel tanam 4.00 bh 250,000.00 1,000,000.00
Sub Jumlah 4,050,621.96
VI PEKERJAAN ATAP
1 Pek.Pas Atap Genteng Metal Bebatuan 51.48 m2 239,045.84 12,305,183.42
2 Pek.Pas Konstruksi kuda-kuda Rangka baja ringan 51.48 m2 148,785.43 7,658,915.89
Sub Jumlah 19,964,099.31
VII PEKERJAAN PLAFOND
1 Pek.Rangka Plafond Hollo 4 mm 102.95 m2 148,000.00 15,236,970.00
2 Pek.Penutup Plafond Gipsum board 9mm 102.95 m2 95,000.00 9,780,487.50
Sub Jumlah 25,017,457.50
VIII PEKERJAAN LANTAI
1 Pek.Pelapis Lantai HT. 60x60 Polished 73.92 m2 135,660.00 10,027,987.20
1 Pek Dinding Keramik 10.24 m2 313,889.79 3,214,231.40
2 Pek.Rabat Keliling Bangunan 41.56 m2 252,842.14 10,508,119.30
Sub Jumlah 23,750,337.90
IX PEKERJAAN INSTALASI LISTRIK
1 Pek. Pas. Instalasi listrik 16.00 Ttk 25,300.00 404,800.00
2 Pek. Pas. Stop kontak 8.00 Bh 55,000.00 440,000.00
3 Pek. Pas. Saklar
a. Saklar tunggal 4.00 Bh 25,000.00 100,000.00
b. Saklar ganda 10.00 Bh 30,000.00 300,000.00
4 Pek. Pas. Lampu
a. TL 10.00 Bh 150,000.00 1,500,000.00
b. Lampu Down Light 10 Watt + Box Tanam 13.00 Bh 25,000.00 325,000.00
c. Lampu taman 2.00 Bh 150,000.00 300,000.00
5 Pek. Pas. MCB 1.00 Ls 108,000.00 108,000.00
Sub Jumlah 3,477,800.00
X PEKERJAAN BESI, KUNCI, KACA DAN PENGGANTUNGAN
1 Pek. Pas. Kunci tanam silinder 5.00 Bh 216,535.00 1,082,675.00
2 Pek. Pas. Kunci tanam kamar mandi 5.00 Bh 156,035.00 780,175.00
3 Pek. Pas. Handel pintu 10.00 Bh 19,992.00 199,920.00
4 Pek. Pas. Engsel 10.00 Bh 45,199.00 451,990.00
Sub Jumlah 8,225,560.00

Page 2 of 7
XI PEKERJAAN SANITAIR
1 Pek. Pas. Bak mandi 5.00 Bh 1,649,175.00 8,245,875.00
2 Pek. Pas. Bak Urinoir 5.00 Bh 1,971,125.00 9,855,625.00
3 Pek. Pas. Closet duduk 5.00 Bh 2,319,515.00 11,597,575.00
4 Pek. Pas. Instalasi air bersih 23.88 m¹ 73,382.00 1,751,995.25
5 Pek. Pas. Kran Air 23.00 Bh 22,962.00 528,126.00
6 Pek. Pas. Floor drain 5.00 Bh 19,992.00 99,960.00
7 Pek. Pas. Instalasi air kotor 31.34 m¹ 58,487.00 1,832,982.58
8 Pek. Sumur resapan 1.00 Bh 2,000,000.00 2,000,000.00
9 Pek. Septik tank 1.00 LS 2,700,000.00 2,700,000.00
10 Pek. Saluran air hujan 6.10 m¹ 34,999.00 213,493.90
Sub Jumlah 30,579,757.73
XII PEKERJAAN FINISHING
1 Pek. Cat Tembok 546.08 m2 135,259.48 73,862,091.06
Sub Jumlah 73,862,091.06
Sub Jumlah Total 378,687,148.02

Page 3 of 7
RENCANA ANGGARAN BIAYA (RAB)
BANGUNAN RUMAH MARBOT
MESJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
( Rp ) ( Rp )
I PEKERJAAN PENDAHULUAN

1 Pek. Pengukuran dan Pemasangan Bouplank 42.05 m' 299,440.00 12,591,452.00


Sub Jumlah 12,591,452.00
II PEKERJAAN TANAH DAN PASIR

1 Pek. Galian pondasi setempat 0.65 m³ 83,140.20 53,874.85


2 Pek.Galian pondasi menerus 21.35 m³ 83,140.20 1,774,939.34
3 Pek.Urugan pasir bawah pondasi setempat 0.22 m³ 291,914.48 63,053.53
4 Pek.Urugan pasir bawah pondasi menerus 1.25 m³ 291,914.48 364,528.21
5 Pek.Urugan tanah pondasi 5.31 m³ 44,625.68 236,845.22
6 Pek.Urugan pasir bawah lantai 13.41 m³ 291,914.48 3,913,478.50
Sub Jumlah 6,406,719.64
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Batu kosong 5.00 m³ 1,405,442.45 7,020,185.01
2 Pek. Pas. Pondasi Menerus/ Batu Belah Ad. 1:3 9.37 m³ 1,405,442.45 13,162,846.90
3 Pek. Pasangan tembok trasraam camp 1pc:3psr 37.08 m³ 299,440.00 11,102,336.88
4 Pek. Pasangan tembok Bataco camp 1pc:5psr 20.48 m³ 206,169.93 4,222,360.19
5 Pek. Pas. Plesteran Ad 1 : 4 253.91 m2 93,159.66 23,654,402.17
Sub Jumlah 59,162,131.15
IV PEKERJAAN STRUKTUR BETON BERTULANG
1 Pek.Beton fondasi footplat(F2) 0,8x0,8 0.86 m³ 6,090,033.86 5,261,789.26
2 Pek.Beton sloof SL1-(20x35) 2.50 m³ 8,719,837.46 21,777,794.05
3 Pek.Pek Dak Beton Lantai 1.25 m³ 8,719,837.46 10,888,897.02
4 Pek.Beton kolom type KU1- 30/30 0.82 m³ 10,016,100.51 8,248,258.77
5 Pek.Beton ring balok (15/25) 37.00 m' 135,660.65 5,019,443.90
Sub Jumlah 51,196,183.00
V PEKERJAAN PINTU & JENDELA
1 Pek.Pasangan Kusen (almunium) 16.20 m2 441,504.31 7,152,369.78
2 Pek.Pasangan daun pintu lapis almunium 8.90 m2 1,689,857.11 15,039,728.28
3 Pek.pasangan kunci tanam 4.00 Bh 350,000.00 1,400,000.00
4 Pek.Pasangan engsel tanam 8.00 Bh 165,000.00 1,320,000.00
5 Pek.Pasangan grendel tanam 4.00 Bh 250,000.00 1,000,000.00
Sub Jumlah 25,912,098.06
VI PEKERJAAN ATAP
1 Pek.Pas Atap Genteng Metal Bebatuan 31.79 m2 239,045.84 7,598,968.45
2 Pek.Pas Konstruksi kuda-kuda Rangka baja ringan 31.79 m2 148,785.43 4,729,702.77
Sub Jumlah 12,328,671.22
VII PEKERJAAN PLAFOND
1 Pek.Rangka Plafond Hollo 4 mm 63.58 m2 148,000.00 9,409,470.00
2 Pek.Penutup Plafond Gipsum board 9mm 63.58 m2 95,000.00 6,039,862.50
Sub Jumlah 15,449,332.50
VIII PEKERJAAN LANTAI
1 Pek.Lantai Granit 60x60 53.63 m2 135,660.00 7,274,767.50
1 Pek Dinding Keramik 10.24 m2 313,889.79 3,214,231.40
2 Pek.Rabat Keliling Bangunan 41.56 m2 252,842.14 10,508,119.30
Sub Jumlah 20,997,118.20
IX PEKERJAAN INSTALASI LISTRIK
1 Pek. Pas. Instalasi listrik 13.00 Ttk 25,300.00 328,900.00
2 Pek. Pas. Stop kontak 10.00 Bh 55,000.00 550,000.00
3 Pek. Pas. Saklar
a. Saklar tunggal 4.00 Bh 25,000.00 100,000.00
b. Saklar ganda 10.00 Bh 30,000.00 300,000.00
4 Pek. Pas. Lampu
a. TL 7.00 Bh 150,000.00 1,050,000.00
b. Lampu Down Light 10 Watt + Box Tanam 4.00 Bh 25,000.00 100,000.00
c. Lampu taman 2.00 Bh 150,000.00 300,000.00
5 Pek. Pas. MCB 1.00 Ls 108,000.00 108,000.00
Sub Jumlah 2,836,900.00
X PEKERJAAN BESI, KUNCI, KACA DAN PENGGANTUNGAN
1 Pek. Pas. Kunci tanam silinder 3.00 Bh Rp 216,535.00 649,605.00
2 Pek. Pas. Kunci tanam kamar mandi 1.00 Bh Rp 156,035.00 156,035.00
3 Pek. Pas. Handel pintu 3.00 Bh Rp 19,992.00 59,976.00
4 Pek. Pas. Engsel 9.00 Bh Rp 45,199.00 406,791.00
Sub Jumlah 5,667,307.00

Page 4 of 7
XI PEKERJAAN SANITAIR
1 Pek. Pas. Bak mandi 1.00 Bh Rp 1,649,175.00 1,649,175.00
2 Pek. Pas. Bak Urinoir 1.00 Bh Rp 1,971,125.00 1,971,125.00
3 Pek. Pas. Closet duduk 1.00 Bh Rp 2,319,515.00 2,319,515.00
4 Pek. Pas. Instalasi air bersih 36.84 m¹ Rp 73,382.00 2,703,392.88
5 Pek. Pas. Kran Air 3.00 Bh Rp 22,962.00 68,886.00
6 Pek. Pas. Floor drain 1.00 Bh Rp 19,992.00 19,992.00
7 Pek. Pas. Instalasi air kotor 31.34 m¹ Rp 58,487.00 1,832,982.58
8 Pek. Sumur resapan 1.00 Bh Rp 2,000,000.00 2,000,000.00
9 Pek. Septik tank 1.00 LS Rp 2,700,000.00 2,700,000.00
10 Pek. Saluran air hujan 1.00 m¹ Rp 34,999.00 34,999.00
Sub Jumlah 13,650,892.46
XII PEKERJAAN FINISHING
1 Pek. Cat Tembok dan Plafond 304.21 m2 135,259.48 41,146,948.26
Sub Jumlah 41,146,948.26
Sub Jumlah Total 267,345,753.49

Page 5 of 7
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN LANDSCAPE
MESJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
( Rp ) ( Rp )
A. PEKERJAAN LANDSCAPE
I PEKERJAAN TANAH
1 Timbunan Tanah 1,825.00 m³ 25,000.00 45,625,000.00
2 Pemadatan 2,500.00 m2 10,000.00 25,000,000.00
3 Lapisan Batu Pecah/ Splite 158.00 m³ 250,000.00 39,500,000.00
4 Abu Batu 43.00 m³ 120,000.00 5,160,000.00
5 Pemasangan Paving Block 1,053.00 m2 54,000.00 56,862,000.00
6 Pemasangan Kansten 326.00 m' 85,000.00 27,710,000.00
7 Pekerjaan Pagar Seng Gelombang Pengaman Keliling Area Bangunan 240.00 m' 176,000.00 42,240,000.00
8 Pek. Pembersihan dan Perataan Lahan dengan Alat 2,805.00 m2 51,542.48 144,576,664.11
Sub Jumlah 386,673,664.11
II PEKERJAAN TAMAN
1 Timbunan Tanah Merah Subur 128.70 m³ 25,000.00 3,217,500.00
2 Pemasangan Rumput 1,073.00 m2 125,000.00 134,125,000.00
Sub Jumlah 137,342,500.00
III PEKERJAAN JEMBATAN
1 Pembuatan Pondasi Batu Kali (0.5X0.75x8.5)X2 6.40 m³ 1,405,442.45 8,994,831.65
2 Pengecoran Jembatan Beton (8.5x2.5x0.25) 5.30 m³ 2,500,000.00 13,250,000.00
Sub Jumlah 22,244,831.65
IV PEKERJAAN SALURAN
1 Pembuatan Saluran Beton (60x7.5x10 cm) 60.00 m' 252,842.14 15,170,528.34
2 Pemasangan Buis Beton (30cm) 158.00 m' 252,842.14 39,949,057.96
Sub Jumlah 55,119,586.30
Sub Jumlah Total 601,380,582.06

Page 6 of 7
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN PAGAR DEPAN
MESJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
( Rp ) ( Rp )
A. PEKERJAAN PAGAR DEPAN
I PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 4.21 m³ 83,140.20 350,186.52
2 Pek.Galian pondasi menerus 18.26 m³ 83,140.20 1,518,140.05
Sub Jumlah 1,868,326.57
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Batu kosong 4.21 m2 1,405,442.45 5,919,723.58
2 Pek. Pas. Pondasi Menerus/ Batu Belah Ad. 1:3 8.42 m2 1,405,442.45 11,839,447.16
Sub Jumlah 17,759,170.74
III PEKERJAAN STRUKTUR BETON BERTULANG
1 Pek.Beton fondasi footplat(F2) 0,8x0,8 0.84 m³ 6,090,033.86 5,130,244.53
2 Pek. Beton Sloof (15X20) 1.78 m³ 8,719,837.46 15,521,310.67
Sub Jumlah 20,651,555.20
IV PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan tembok Bataco camp 1pc:5psr 52.00 M2 206,169.93 10,720,836.41
2 Pek Pelesteran dan Profil Kolom Beton Pagar 104.00 M2 93,159.66 9,688,604.64
Sub Jumlah 20,409,441.05
IV PEKERJAAN FINISHING
1 Pek Cat Tembok Dinding Pagar 104.00 M2 135,259.48 14,066,985.92
Sub Jumlah 14,066,985.92
Sub Jumlah Total 74,755,479.48

RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN PAGAR SAMPING KANAN -KIRI & BELAKANG
MESJID JOESOEF BAKRI

Harga
No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
( Rp ) ( Rp )
A. PEKERJAAN PAGAR BELAKANG DAN SAMPING
I PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 27.80 m³ 99,742.50 2,773,040.99
2 Pek.Galian pondasi menerus 30.92 m³ 99,742.50 3,084,237.59
Sub Jumlah 5,857,278.57
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Batu kosong 5.56 m³ 1,686,095.81 9,375,367.16
2 Pek. Pas. Pondasi Menerus/ Batu Belah Ad. 1:3 7.79 m³ 1,686,095.81 13,138,638.59
Sub Jumlah 22,514,005.74
III PEKERJAAN STRUKTUR BETON BERTULANG
1 Pek.Beton fondasi footplat(F2) 0,8x0,8 3.56 m³ 7,306,155.18 26,000,092.95
2 Pek.Beton sloof SL1-(20x35) 0.23 m³ 7,894,712.65 1,845,549.50
Sub Jumlah 27,845,642.45
IV PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan tembok biasa camp 1pc:5psr 78.90 M2 278,260.00 21,954,714.00
2 Pek. Pas. Plesteran Ad 1 : 4 157.80 M2 111,762.75 17,636,161.95
Sub Jumlah 39,590,875.95
IV PEKERJAAN FINISHING
1 Pek. Cat Tembok dan Plafond 157.80 M2 162,269.50 25,606,127.10
Sub Jumlah 25,606,127.10
Sub Jumlah Total 121,413,929.82