REKAPITULASI

RENCANA ANGGARAN BIAYA ARSITEKTUR


HOTEL MADINA TASIKMALAYA
TAHUN 2019

NO. URAIAN KERJA JUMLAH HARGA TOTAL HARGA

1 2 3 4
B PEKERJAAN ARSITEKTUR
LANTAI BASMENT
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 101.076.854,02
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 205.720.660,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 175.704.255,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 100.050.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 105.960.960,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 34.371.000,00
SUB JUMLAH Rp 722.883.729,02
LANTAI DASAR
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 269.608.198,05
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 339.295.238,40
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 138.346.200,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 522.270.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 82.870.349,10
VI PEKERJAAN TANGGA (STAIR CASE) Rp 27.496.800,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 66.079.400,00
SUB JUMLAH Rp 1.445.966.185,55
LANTAI 2
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 545.977.631,14
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 253.125.732,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 128.417.646,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 756.140.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 77.203.392,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 13.748.400,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 82.545.600,00
SUB JUMLAH Rp 1.857.158.401,14
LANTAI 3
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 467.582.428,66
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 208.324.932,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 94.976.346,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 581.900.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 97.779.632,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 13.748.400,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 72.227.400,00
SUB JUMLAH Rp 1.536.539.138,66
LANTAI 4
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 467.582.428,66
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 208.324.932,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 94.976.346,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 581.900.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 97.779.632,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 13.748.400,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 72.227.400,00
SUB JUMLAH Rp 1.536.539.138,66
LANTAI 5
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 467.582.428,66
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 208.324.932,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 94.976.346,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 581.900.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 97.779.632,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 13.748.400,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 72.227.400,00
SUB JUMLAH Rp 1.536.539.138,66
LANTAI 6
REKAPITULASI
RENCANA ANGGARAN BIAYA ARSITEKTUR
HOTEL MADINA TASIKMALAYA
TAHUN 2019

NO. URAIAN KERJA JUMLAH HARGA TOTAL HARGA

1 2 3 4
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 467.582.428,66
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 208.324.932,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 94.976.346,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 581.900.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 97.779.632,00
VI PEKERJAAN TANGGA (STAIR CASE) Rp 13.748.400,00
VII PEKERJAAN TOILET ( SANITAIR TOTO) Rp 72.227.400,00
SUB JUMLAH Rp 1.536.539.138,66
LANTAI ATAP/RUANG MESIN
I PEKERJAAN DINDING ( OCUPATION WORK) Rp 61.918.288,96
II PEKERJAAN LANTAI ( FLOOR TILE) Rp 200.909.200,00
III PEKERJAAN PLAFOND (EMPLOYMENT CEILING ) Rp 12.826.800,00
IV PEKERJAAN PINTU DAN JENDELA (DOOR WINDOW) Rp 18.000.000,00
V PEKERJAAN PENGECATAN (PAINTING) Rp 15.249.600,00
SUB JUMLAH Rp 308.903.888,96
KONSTRUKSI ATAP DAN FASAD
I PEKERJAAN ATAP TYPE 1 Rp 125.572.474,00
III PEKERJAAN FASAD Rp 415.600.000,00
SUB JUMLAH Rp 541.172.474,00
Jumlah Rp 11.022.241.233,28
Dibulatkan Rp 11.022.000.000,00